Fp_0100-UNDERPASS AT INTERCHANGE TARČIN EARTH WORK Excavation of the foundations protected by steel sheet piling and cofferdam including disposal of surplus excavated material to approved disposal area and supporting of construction pit and water drawing. Item includes sheet piles and cofferdams made from steel battens for support and protection of construction pit (cca 365 m 2 ). at 3 rd and 4 th category (46 m) Abutments m 3 1.245,70 0,00 Filling in foundations of piers and whole structure till the level of highway m 3 4.325,86 0,00 TOTAL EARTH WORKS 0,00 CONCRETE WORKS Items includes supply of concrete, all transport and handling, fabrication, assembly and disassembly of formwork and scaffold (formwork for visible surfaces must be smooth), concrete placing and cure, and all other required work and material. Levelling layers under foundations of abutments and piers made of concrete MB-20 m 3 24,91 0,00 Protection of waterproofing made of fine grain concrete thickness d= 10 cm m 3 50,81 0,00 Foundation, pad and slab foundations, MB-35. m 3 249,15 0,00 Piers as supports to the plane spanning structures of various systems and as supports to the over-arch structure of arch bridges Abutments, concrete class 35, M100 m 3 510,01 0,00 Main structure of underpass made of concrete class MB35, M-150 m 3 406,46 0,00 Cantilever walls next to abutments made of concrete class 35 m 3 94,26 0,00 TOTAL CONCRETE WORKS 0,00

Pothodnik Radovi

Embed Size (px)

DESCRIPTION

Pothodnik

Citation preview

Page 1: Pothodnik Radovi

Fp_0100-UNDERPASS AT INTERCHANGE TARČIN                 EARTH WORK        Excavation of the foundations protected by steel sheet piling and cofferdam including disposal of surplus excavated material to approved disposal area and supporting of construction pit and water drawing. Item includes sheet piles and cofferdams made from steel battens for support and protection of construction pit (cca 365 m2).

        at 3rd and 4th category (46 m)        Abutments m3 1.245,70   0,00Filling in foundations of piers and whole structure till the level of highway m3 4.325,86   0,00TOTAL EARTH WORKS       0,00         CONCRETE WORKS        

Items includes supply of concrete, all transport and handling, fabrication, assembly and disassembly of formwork and scaffold (formwork for visible surfaces must be smooth), concrete placing and cure, and all other required work and material.        Levelling layers under foundations of abutments and piers made of concrete MB-20 m3 24,91   0,00

Protection of waterproofing made of fine grain concrete thickness d= 10 cm m3 50,81   0,00Foundation, pad and slab foundations, MB-35. m3 249,15   0,00Piers as supports to the plane spanning structures of various systems and as supports to the over-arch structure of arch bridges        Abutments, concrete class 35, M100 m3 510,01   0,00Main structure of underpass made of concrete class MB35, M-150 m3 406,46   0,00Cantilever walls next to abutments made of concrete class 35 m3 94,26   0,00TOTAL CONCRETE WORKS       0,00         METAL WORKS        Supply, preparation and installation reinforcing steel RA 400/5002:        Abutment No. 1 44400.70 kg        Abutment No. 2 43316.50 kg        RC edge beam 963.32 kg        Cantilever walls next to abutment No. 1 4020.9 kg        Cantilever walls next to abutment No. 2 4349.8 kg 97.051,22   0,00

Page 2: Pothodnik Radovi

kgSupply, preparation and installation reinforcing steel Bst 500/520:        Main structure kg 93.684,75   0,00Galvanised railings on bridges according to the desig. Drawing 3.4.1. (total weight of railing 691,86 kg) m1 28,00   0,00TOTAL OF METAL WORKS       0,00         FINISHING AND OTHER WORKS        Waterproofing of the upper deck surface        Epoxy resin base coat 300-500 g/m2 cover with a quartz sand granulation of 0,5/1 mm. Minimum rough of the area with the base coat and quartz sand is 0,3 mm        Hot coat for fixing the stripes        Insulation tapes 5 mm thick with polyester inserts m2 500,78   0,00Execussion of mission G31 pcs 1,00   0,00Execussion of mission G32 pcs 1,00   0,00TOTAL FINISHING AND OTHER WORKS       0,00

 

 

 

 

  

Fp_0100 SUMMARY                 EARTH WORKS       0,00         CONCRETE WORKS       0,00         METAL WORKS       0,00         FINISHING AND OTHER WORKS       0,00         

TOTAL UNDERPASS AT INTERCHANGE TARČIN       0,00