Upload
richard-yip
View
60
Download
1
Embed Size (px)
Citation preview
SAFF Sustainable Aquaponics @ Farmer Frog
Joshua Hurley, Justin Kneip, Richard Yip
Completed for UW Bothell Mechanical Engineering Senior Design Project 2016
with Dr. Pierre D. Mourad – Capstone Advisor
ii
SAFF - Sustainable Aquaponics at Farmer Frog
2016 Capstone Team:
Justin Kneip - Project Manager
Joshua Hurley - Communications Director / Lead Mechanical Engineer
Richard Yip - Lead Electrical Engineer
Additional Contributors:
Kelsi Martin - Junior Electrical Engineer
Donald Tran - Data Technician
Additional Researchers:
Trevin Jorgenson – Electrical Engineering
Johnny da Silva – Electrical Engineering
Special thanks to:
Joel Unruh and MT Solar
Tim Bailey and BlueFrog Solar
Jason Budgeon, Mike Dalton, Jen Olson, Wendy Wenrick and A&R Solar
John Harley and Brimma Solar
Amy Lucas at Snohomish County Parks
Cameron Whalen at University of Washington Bothell
iii
Table of Contents
DESIGN STRATEGY ................................................................................................................. 1
USER INSIGHTS & RESEARCH .............................................................................................................. 2
PROBLEM UNDERSTANDING & FRAMING .............................................................................................. 5
VISION EXPLORATION ........................................................................................................................ 7
TECHNOLOGY MAPPING .................................................................................................................. 11
PRODUCT PLANNING ....................................................................................................................... 13
HUMAN INTERFACE DESIGN .............................................................................................................. 14
CONCEPT DEVELOPMENT .................................................................................................... 17
CONCEPT RISK IDENTIFICATION AND MITIGATION ................................................................................. 18
REQUIREMENT DOCUMENTATION ...................................................................................................... 22
SYSTEM DESIGN & BUILD ..................................................................................................... 28
SYSTEM OVERVIEW ......................................................................................................................... 29
BUILD SCHEDULE ............................................................................................................................ 34
BUDGET ........................................................................................................................................ 35
APPENDIX A: COMPONENT SPECIFICATIONS ........................................................................ 37
APPENDIX B: COMPONENT USER MANUALS ........................................................................ 43
APPENDIX C: REQUIRED DOCUMENTATION SUBMISSION ..................................................... 81
APPENDIX D: OTHER DOCUMENTATION............................................................................... 88
1
Design Strategy
User Insights & Research 2
Problem Understanding and Framing 5
Vision Exploration 7
Technology Mapping 11
Product Planning 13
Human Interface Design 14
2
Figure 1: Idealized Sustainable Energy
Shows an idealized sustainable farm.
User Insights & Research
Consumer Journey Map
Zsofia Pasztor receives an emailed PDF construction
plan for the sustainable energy system at her farm. Our
team schedules solar panels to be delivered to her
farm, and has them installed at a suitable location.
Systems are connected as required by an electrical
contractor. We notify Zsofia of safety concerns and
components prone to damage during the setup,
storage and operations phases. Zsofia does not have
to worry about the function of her equipment while she
is at the farm or away from the farm as it is completely
autonomous. She merely performs periodic cleaning
and maintenance of the solar panels.
Stakeholder Framing
Stakeholders for this project include UWB and Farmer Frog as well as partnered solar
companies contributing supplies and experienced professionals. UWB has an interest in
promoting their campus’ support for sustainability and showing themselves as a leader in the
community. Dr. Pierre D. Mourad and the Community Based Learning (CBL) program of UWB
has facilitated integrating Farmer Frog with the ME capstone projects. Farmer Frog is providing
the majority of funding for this project. The client has multiple plans to improve their farm to
serve as an educational center for the community.
User Insight Report
The client is seeking a demonstration tool to show a potential method of supplying energy to an
aquaponics system pump on a somewhat remote farm. While traditional energy options could
be used such as electrical grid or gasoline generators, these options involve an output of CO2
emissions, and have a high operational cost when there is a lack of electrical grid access. The
client prefers to use technology that leaves less of an environmental impact. Current sustainable
energy technologies like solar power, or wind farms are making advances in megawatt level
generation, but less research is involved in small scale systems. Also, these energy systems
are rarely designed for portability (unlike a gasoline generator), rather they are designed for a
specific site for long term use. The lack of portability available for clean energy systems is an
opportunity for advancement in small scale power systems.
3
Figure 2: Farmer Frog Barn
This shows the ~30’ tall barn nearby.
Online Data Gathering
Our research included pumps, available wind resource, available yearly sunlight, structures,
transportation, battery and power conversion set up, and turbines for the aquaponics system.
Research into the the battery and power conversion setup showed that for both a wind or solar
system, batteries will require a charge controller to reject any back flow current as well as to
acknowledge when the battery is fully charged, and an inverter, to convert power from DC to
AC. Our investigation into turbine technology included: flying helium turbines, kite turbines, and
specially designed urban turbines. The two standardized types of turbines currently in use are
Horizontal Axis Wind Turbines (HAWT) and Vertical Axis Wind Turbines (VAWT). Research into
wind resource available at Farmer Frog showed a minimal amount of wind at 50m, and from
local data at near 30’, almost no regular wind speeds recorded. The average hours of sunlight
per year in Seattle are measured as 1.6 hours a day (winter) at lowest levels.
User Scenarios
Our client will be operating on the Farmer
Frog grounds, which is a protected Heritage
Historical Farm site owned by the county.
Possible mounting locations include the roof
of a nearby barn (appx 30’ tall) as well as
ample space on the ground near
farmhouse, and on the farmhouse’s roof.
The power system must be capable of
being disassembled in the event that
Farmer Frog is forced to move to another
location. In keeping with sustainable design,
Zsofia requests designing this system for as
long life as possible (30+ years).
4
Figure 3: Zsofia Pasztor
Personas
Zsofia Pasztor: This user is a small-scale farmer which owns a
sustainable aquaponics system. She is a 1st world
organic/sustainable farmer interested in supporting clean
energy and educating others on the subject. This 1st world
farmer has a limited budget, but has access to other support
and resources (UWB). This week she has invited a group of
college students to her farm in order to teach them about
integrating sustainable energy with sustainable farming.
Student Visiting Farm: Jill Jackson is a student from University
of Washington in her junior year of college. She is there to
enhance her learning, as part of a class she is taking at
school. Jill will learn about how an aquaponics system can be
powered by renewable resources and about the challenges of
doing so. She will also learn about the potential problems of
scaling up or down a windmill aquaponics system, difficulties
in implementing solar power systems, and the natural limitations of a small farm. This user will
come away with an understanding of the physical and electrical factors involved with powering
an aquaponics system with renewable resources and basic operational understanding of an
aquaponics system.
5
Figure 4: Farm in the Forest. This photo shows the tall trees surrounding the
farm.
Problem Understanding & Framing
Product Assumptions Outline
Farmer frog is in need of a sustainable solution to
power their aquaponics system. The farm has
restrictions on ability to construct on the property
due to its status as preserved farmland owned by
the county. The low wind and tall trees nearby
makes a wind powered system highly unlikely
below 50m, nearby rivers are not powerful enough
to generate enough practical hydropower. There is
moderate to heavy cloud cover during winter,
limiting solar potential. In addition, this system will
also be used as a demonstration tool for educating
observers on the benefits of sustainably powered
aquaponics systems, and may also be used to
acquire additional funding to support an improved
system to power Farmer Frog’s entire power
needs, or to install a system on another farm.
Functional Assumptions Outline
An off grid solution will require a method of operation, activation, deactivation and energy
storage. A grid tied solution will require the same except for energy storage. For energy storage,
we anticipate a need for battery that will need to last up to 3 days without charging to power the
LEDS, and 6 days without charging if powering the pump. For a demonstration piece, the
system will need to be visible and intuitive to allow the audience to see and understand how the
system works on a basic level. Additionally, the system will need to power, at the very least, a
series of LED lights and/or a pump for the aquaponics system. We assume the pump to require
around 30W and know the LEDs require 14W.
Experience Assumptions Outline
This product will require a user manual, professional installation & maintenance, and a
demonstration of operation. It will also need to be easily disassembled should Farmer Frog
decide to not renew its lease with the county. The manual should include setup, deconstruction,
important safety notes, and basic maintenance/replacement procedures for the battery, solar
panel, and water pumps while the demonstration should include the bulk of the safety
information, detailing precise procedures to ensure safety while working with the equipment. For
simplicity and ease-of-use there should be labels on all parts.
6
Figure 5: Discovery Hall This photo shows Discovery Hall at UW
Bothell
Figure 6: Goat Goats on the farm are potential hazards to
the solar panels.
Business Needs Documentation
The next iteration of this project will begin their
work from the results of this project. We assume
that the budget for next year may be no less than
half of our current budget (~$1500). We also
assume that a selected battery will not require
replacement within a year, but poor structural
components may need refurbishing. Our initial
prototype will demonstrate the ability/feasibility of
providing power to the farm with a pair of solar
panels. It will also provide insight into scalability
and into potential improvements for future
iterations of this system. What improvements
made may be specific to a program, for example,
if the team taking over is in the Electrical Engineering program they might make improvements
to the electrical components of the system perhaps by advancing monitoring systems.
User Needs Documentation
We are assuming that students in high school and beyond are the main audience of this system,
as well as potential investors and other farmers.
Additionally, the system should be portable and
buildable with limited construction resources and
volunteer construction crew. To this end, we aim
to make individual pieces weigh no more than
80lbs and ensure minimal specialized machinery
is necessary in order to install or deconstruct the
system. We also assume that the system will
require some sort of shielding to prevent
inquisitive persons and farm animals from injury
and electrocution.
7
Vision Exploration
Interaction Wireframing
Figure 7: General Wireframe
This highlights the solar panels reliance on grid or battery backup to accommodate the load
requirements at low or no light times.
Visual Illustrations
Figures 8 and 9: Wind Designs.
Figure 8 (left) shows a grid tied battery backup wind design.
Figure 9 (right) shows an off grid battery wind design.
8
Figures 10 and 11: Wind Design and Solar Design.
Figure 10 (left) shows a grid tied wind design.
Figure 11 (right) shows a grid tied solar design.
Figures 12 and 13: Solar Designs.
Figure 12 (left) shows a grid tied solar design with a battery backup.
Figure 13 (right) shows an off grid solar design.
9
The concepts we are exploring incorporate variations of functional solar and wind powered
systems. They show the basic required equipment to create the systems as well as how they
will be connected to each other. All concepts allow for some sort of power to be provided during
a lack of sustainable energy production.
Figures 14: Wind + Solar Design.
This shows the potential for a grid tied system including both solar and wind power systems
in the design.
10
Figure 16: High Level Architecture This shows in general terms components and connections for the proposed system.
Architecture Exploration
Solar panel system hooked up to an on-grid inverter with a battery backup. If we had time to
construct 3D models we would generate a scale model of the farm; this scale model would allow
us to visualize both solar panel placement, as well as wind turbine placement. This model would
also represent the grid access points, and allow for placement experimentation.
11
Table 1: Interaction Table This shows in general terms how changes in the first column may affect the items in the first row.
Technology Mapping
System Planning and Thinking & Risk Analysis
The main risk of the design is the wear of the solar panels. From a user perspective, this means
the panels have to be located clear of trees and other debris that might damage them. The
electrical storage box also needs to have a container that is water resistant, easily accessible,
and is simple so that replacing the battery and components are easy for the user. Battery
leakage can cause serious damage to the container as well as the environment. Proper hazard
equipment must be worn when replacing damaged batteries. Wiring to the system also needs to
be intuitive and insulated so as to reduce damage to wires as well as prevent accidental shocks
to the user if they are trying to repair something.
12
Feasibility Planning
The first hurdle is to have our proposals approved by our client. She must approve of either a
solar/battery system or a solar/grid system. Once one of our proposals is approved the next
step is having a certified solar professional to approve our design and make sure it will operate
efficiently. The panel installation is the next factor to be addressed. To be able to install the
solar panels we must first find an installer and request a quote from them. We have contacted
several installers but were not able to receive a quote for our power system. This led to Justin
contacting a professor from Shoreline Community College, who also is a electrician, to price out
a cost of installation. He gave us a quote of around $1000 for installing the system. This lead
into the topic of budgeting. As of right now a system that meets all of our client’s needs is not
possible. The proposed solar/grid system is priced at $3410 (including labor) which is out of the
budget range of $3000 that is provided so additional funding is required. This system will be
able to power one LED light bulb. However, this system is scalable to eventually power all of our
client’s needs with more funds.
Competitive Analysis
There are many competitors, Solterra for example does much of the same services that we
provide. They provide designs of solar systems as well as install the systems. Their services
however are more expensive than ours. This is true for all other competitors.
Component Technology Research
Solar panels, charge controllers, inverters and batteries are all well proven technologies. Our
team’s experience using these technologies is very limited and may require an experienced
professional to evaluate selected components prior to commitment.
13
Product Planning
Product Roadmap
The first complete system will be a minimal system powering a selection of LEDs, with a plan for
scaling up in the future. The second iteration of this system will be upgraded to power more of
the LEDs for the aquaponics system. The third iteration of this system will power all the LEDs
for the aquaponics system. The fourth iteration of this system will power both the pump and
LEDs, and if grid connected, will add battery backup to the system. For the grid connected
system, iterations 2 and 3 may be combined depending on budget available.
Product Schedule & Budget
Acquiring the solar panels will take the longest amount of time. We must order the panels and
mount as soon possible. Once these main components are ordered then the supporting
products will be ordered. The total costs of a grid tied system (including labor) is estimated to be
$3300. Mounting the solar panels will be the first objective that will be done. Protecting the back
of the panels will be done with a short fence, and any batteries will be stored in battery storage
containers. The next step is connecting the wiring which will need help from an electrician.
Figure 17: Schedule Flow
This shows a generalized flow of scheduling from design to design review to scheduling
construction to ordering equipment to building product.
Work Breakdown
The first objective that had to be scheduled is meeting with our client Zsofia. This discussion will
be about the budget, product use, and site location of the product. After visiting the location, the
next step is to gather information of the constraints that were given to us. This included research
in wind turbines, blade orientation, local wind data, and power requirements. Rough design
brainstorming follows adequate research. The design will then go through calculations to see
the feasibility of the design and will progress through multiple iterations, evaluating many
alternatives. When the calculations are done and we determine the design is possible, we will
evaluate specific components merits and budget requirements. After selecting a set of
components we will present the design to the client and upon confirmation, will await delivery.
Construction of the design will follow in a logical order starting with grounds work and finishing
with electrical connections.
Ergonomics Studies
To improve access for maintenance and analysis electrical components such as the charge
controller and inverter will be raised off the ground to reduce stress from maintenance activities.
Additionally, battery banks would be raised off the ground to reduce lifting heights. Fencing
placed around the panels to protect from hazards will be removable to ease panel maintenance.
14
Figure 18: Area Map This map shows designated areas throughout the farm and
planned improvements.
Human Interface Design
User Work Flows
The user will not interact with our system directly very often. Once the system is setup, it will be
operating autonomously. Maintenance checks will be the main interaction between user and the
system. This will require the user to check the solar panels for any cracks or other forms of
damage as well as making sure they are clean for efficient sunlight collection. Next will be the
batteries. The batteries need to be checked for any leakage and if there are any damage to the
storage container. The ground mounting is to be inspected for any cracks and erosion. If any
flaws of the system is to be found contacting a professional solar panel installer is
recommended.
Environment Analysis
Farmer Frog is located in
Western Washington State in an
area that experiences very low
amounts of wind and low
sunlight capable of being
converted into energy. For
physical construction of the
system, regulatory bodies such
as Snohomish County Planning
and Development Services must
be consulted to ensure minimal
environmental impact.
Connection of the system to the
electrical grid, would require
certification and validation from
the Public Utility District (PUD). As connection to the local electrical grid is highly recommended
if available, our proposal involves a staged integration in which net metering can occur as early
as possible.
The target environment for the far future is that of the developing world: particularly poor nations
in Africa, Asia, South America, and elsewhere. Many of these regions have widely varying
availability of renewable energy. For this reason, our product could potentially benefit from
implementing the wind turbine device in other areas of the world where faster wind speeds are
available at much lower altitudes. The possible combination of wind and solar energy collectors,
and their associated scalabilities, allow this product to be implemented in many regions across
the globe--but at varying costs. Systems implemented in areas without local electrical grid
access will require redundancy built into the system in the form of additional panels/turbines
and/or additional batteries, all for additional costs.
15
Cultural Factors Mapping
The energy-collecting device lacks any sort of direct human interaction with the user apart from
installation and maintenance; rather the device allows the user to utilize other devices that
require electrical power. For installation, or in the event the device requires maintenance, the
device should be clearly marked as containing electrical components and that risk of electric
shock exists. Furthermore, this warning should also indicate the risk associated with electronic
equipment near water. As the client intends to use the system as an educational tool, this
prototype version of the device should be clearly marked with warning signs instructing children
to not play around the electrical equipment.
Information Architecture and Hierarchy
The extent of inputs required by the user for the device should be largely nonexistent; if the
device functions properly, it should only need to be “turned on” but will likely be in an “always
on” status. Rather, the only input our device receives is in the form of solar radiation energy, its
output is electricity. If there is no sunlight for the system to collect, there will be neither an input
nor output for the photovoltaic panels; instead, the grow lights and/or water pump will draw their
required energy from the electrical grid. During periods of sunlight the generated electricity will
be directed from the direct-current photovoltaic panels to the current inverter unit, allowing the
alternating-current grow lights to operate. The initial system will likely not include batteries and
will use the electrical grid as a backup energy source. Should batteries be required for true “off-
grid power” in the future, the collected energy would instead be directed to the charge
controller/batteries for temporary storage before reaching the inverter unit.
Analog Interface Design
Interfacing electrical components including the charge controller and inverters will be raised off
the ground by 3’ to 4’ to allow technician easier access for connections and maintenance.
Battery bank storage will also be raised off the ground by at least 6” and not more than 4”.
Electrical cabling will be laid in trenches to protect against damage.
Graphic User Interface Design
The selected inverter and/or charge controller will have a standard GUI.
Best Use Practices Report
The points of failure of our solar system will be in the wiring of the product. If the system is not
wired properly there could be a lack of efficiency or failure of the entire system. Other points of
failure include natural phenomena which cannot be planned for. For example a strong gust
16
blowing the panels down or the power grid is out and the solar panels cannot provide sufficient
power. If the system is properly used and unreasonable weather conditions are avoided the
system should be operate smoothly. A regular maintenance plan should be followed to ensure
the successful operation of the solar system. This includes cleaning of the panels, inspections of
wiring and other electrical components, as well as an overall all inspection of the mounting.
Usability Requirements Documentation
The original power system was to design a wind powered system for our client, Zsofia. This
system had to be discarded due to research of local wind data. A new system that included
using solar energy was then developed to help the client’s need of electrical power. With the
new system, Zsofia will be able to demonstrate renewable energy and aquaponics systems.
For the ground mount of the solar panels we decided to go with designing our own. This will
allow us to reduce the cost of the overall system as well as give us more funds for other parts of
the project. The ground mounts will consist of 4x4 pressure treated wood posts and galvanized
L brackets. The benefits of having pressure wood is that they are durable in outdoor conditions,
this is true for the galvanized brackets as well. However a disadvantage of using wood as a
mount is that it increases the weight of the mount, making it harder to relocate.
17
Concept Development
Concept Risk Identification and Mitigation 18
Requirement Documentation 22
18
Figure 19: Circuit Model This shows a basic series of connections for our proposed system.
Concept Risk Identification and Mitigation
EE / Circuit Models
19
Figure 20: Panel Mount Model This is a 3D rendering of a proposed ground mount system for our solar panels.
Mechanical Models
Firmware Models
No deviation from manufacturer designed firmware for selected components.
Human Interaction Models
If possible we would model attempting to optimize the system for portability and user access,
however since this system only requires a minimal level of portability and access(must be able
to move elsewhere, minimal maintenance). Then we feel this is a low risk area to avoid concern
with, also this type of model would be time intensive.
20
Figure 21: System Integration Map This map shows designated areas throughout the farm and proposed locations for individual units.
System Interface Modeling, Testing, Risk Analysis
Estimation of Costs of Goods
Any system involving a functioning wind turbine has been determined to be infeasible within our
allotted budget for the given geographic location. It has been determined that approximately
$2000 of our budget would need to be spent to obtain a structure capable of reaching 60 feet--
less than half the altitude for which the National Renewable Energy Laboratory has data. Even a
Local Engagement donation of a 40-foot utility pole from Frontier would not offset our costs
enough to make wind energy more attractive for this region. Without reliable wind available, it is
our recommendation that solar energy be pursued for the current application.
Cost analysis for solar-collecting systems is hampered by a similarly high fixed-initial-cost.
Where the wind system required a $2000+ mounting structure, the solar system requires a
sizeable investment (~$1200) in a reliable electrical inverter unit. A cheap electrical AC/DC
inverter could be implemented, but it would not be able to safely support the expansion of the
energy-collecting system. This route would also require an inverter that is capable of connecting
to the active electrical grid. Following is a table outlining our estimated cost of components of
our system.
21
Table 2: Estimated Cost of Components This table outlines estimated costs incurred in the construction of our solar-collecting system.
Estimated Cost of Components
Component Cost
Inverter $1200
Solar Panel (each) $190-350
Mounting Structure $800
Electrical Installation* $0
Batteries (each) $100
Battery Storage* $0
Charge Controller $200
Solar/Battery System (1 panel, 1 battery, w/ grid access)
~$2800
Solar/Grid System (1 panel w/ grid access) ~$2500
Installation costs are not to be factored into our estimations due to availability of volunteer labor,
also, as a portion of the house could be appropriated for battery storage, this cost has been
eliminated.
22
Requirement Documentation
Design Decisions and Rationale
0.0 Our client desires an environmentally-friendly method of generating electricity in an effort to
reduce carbon footprint and educate visitors. The final product delivered to our client will be a
solar energy collecting system consisting of up to five photovoltaic solar panels mounted to a
support structure. The system will be capable of supplying a variable wattage, dependant on the
time of year which we will report an estimate to the client in terms of yearly wattage produced
and number of LEDs power offset per year. The system will be designed with scalability in mind,
should the client decide to upgrade/expand the system. Although the provided system will likely
not completely meet the client’s requirements in its first iteration, it will allow for electrical grid
backup and net metering of electricity usage from the local utility company; this in turn allows
the client to sell energy back to the utility company during periods of net positive energy
generation (summer months).
1.0 Tier 1 Schematics
1.1 Capturing sun energy rather than wind or hydro was selected for this system to reduce cost
and maximize energy capture while remaining a somewhat portable system. This system may
or may not be grid connected which is represented in the above schematic. If grid connected,
this system may or may not have a battery backup depending on what stage of development the
project is in.
23
2.0/2.1 Tier 2 Schematics
The SolarWorld SW325 XL Silver Mono Solar
Panel was chosen for high Wattage per dollar. To
provide enough power for the entire aquaponics
system we need roughly 5 panels.
Watts (W) Amps Volts (DC) Weight (lbs) Size (in) Cost ($)
325 9.48 37 47.6 78.46 × 39.4 × 1.3 300
The UPG UB12500 AGM battery are used to back up the
pump in case the panels do not provide enough power.
The absorbed glass mat (AGM) is a technology that
provides safe reliable power. They do not produces any
fumes, shock and vibration resistance, and is resistant to
freezing temperatures. A charge controller will be needed
to regulate the current to prevent damage of the batteries.
Volts Amp-Hours Cost ($) Type
12 50 103 AGM
The mounting system for the solar panels will be custom made using pressure treated wood and
galvanized brackets. We will be using 4x4x10 pressure treated wood and galvanized L brackets
and plates. The mount itself will be roughly 2 feet tall and 22 feet long. This mount will allow 3
panels to be attached to it. For design illustrations please check appendix. If the system is to be
mounted onto the roof of the barn, the mounting will have to be bought commercially as a kit
and installed by a professional contractor. Ideally the roof mounting will be made of aluminum to
ensure that it will be light enough for the rooftop.
24
Schneider C60 12/24V Charge Controller is used to
regulate current from our solar panels. This specific
component was chosen because it will fit in with the 12
Volt DC system. The controller is silent, durable, and
has automatic overload protection.
Battery Bank Voltage (DC) Max Current Output (Amp) Cost ($)
12/24 60 199
The inverter will allow us to convert the DC power
produced from our batteries to AC power which will allow
the pump to be plugged into the power system. The pump
is going to be a AC power pump so it can be backed up by
the grid system as well.
Watts (W) Input Voltage (VDC)
Output Voltage (VAC)
Type Cost ($)
2000 12 120 Pure Sine Wave 1,844
25
3.0 Tier 3 Schematics
Simulation of solar panels, charge controller and inverter
Simulation of inverter
Simulation of a solar panel
26
3.1
Off Grid
Solar panels will be connected to a charge controller. The charge controller controls electric
back flow to the solar panel. The connection also prevents batteries from overcharging. The
charge controller is then hooked to a battery as to have a backup of energy incase the solar
panels cannot provide enough electricity. Batteries are then hooked to an DC to AC inverter.
The power generated by the solar panels is DC so inorder to run basic household appliances
you need to convert your energy to AC. Thus you have a fully functional off grid system.
On grid
The solar panels will be connected to an on grid inverter. Which will prevent backflow of energy
as well as convert the energy being produced from DC to AC. The inverter is then hooked to a
metering system which measures the amount of energy that your system is producing. This
reduces your electricity bill. The inverter also has the capability to store backup energy by
attaching batteries and a charge controller to the inverter.
27
Draft Schedule
28
System Design & Build
System Overview 29
Build Schedule 32
Budget 33
Operations & Maintenance 35
29
System Overview
Key Components
SolarWorld Sunmodule Plus SW280 Mono Black Panels
These panels were selected for low cost per watt, made in USA,
availability online, lack of minimum panel order, and manufacturer’s
reliable history. Two panels were purchased and shipped to UW
Bothell.
APSystems YC500a Microinverter
A microinverter was selected for its scalability, and designed operation with a small number of
panels. This model can support two modules per inverter, and up to 7 inverters can be tied
together in a single string. We were also able to source this item locally from BlueFrog solar at a
discount and have it shipped to UW Bothell.
MT Solar 4-TOP4 Racking
This racking system is designed to accommodate 2-4
solar panels, and has a unique hoisting system for ease
of installation. Our team was able to source this item for
free from MT Solar and drove out to meet a company
representative in Moses Lake to pick up the equipment.
14’ Stainless Steel Pipe (4.5” OD)
A pole mount was ultimately selected by Farmer Frog as ideal for their needs. This pipe was
specified by MT Solar as required for our height needs (to avoid goat hazards) and by their
racking design. Least expensive and most convenient purchase was from OnlineMetals.com,
shipping out of Seattle took nearly 3 weeks as it was a custom size and unusual shipment
location, but shipment arrived at Farmer Frog without difficulty.
30
Completed System
31
32
33
Future Work
Our team suggests initial improvements to the system will upgrade from a 2 module solar pole
mount system to a 4 module pole mount system of two rows, two columns. This will require the
purchase of 2 additional solar panels (recommend Sunmodule Plus SW280 Mono Black panels)
and another APSystems YC500a microinverter (required if connecting to existing line,
recommended if used for a new mounting location). Racking and rails for additional 2 modules
were included in MT Solar 4-TOP4 racking donation.
An interesting analysis of our designed solar system would be achievable with the purchase of
BlueFrog Solar’s ECM monitoring system (farm internet connection required). This monitoring
system would record detailed production data from individual inverters and solar panels’ input &
output. This may be a potential computer science/mechanical engineering/electrical engineering
analysis and optimization research project.
34
Build Schedule
SAFF: Basic Project with G
antt & Dependencies
Exported on M
ay 24, 2016 7:53:45 PM PD
T
35
Budget
Category $$$ Comments
Solar Panels $1012 2x Sunmodule Plus SW280 Mono (includes freight)
Inverter $257 APSystems YC500a microinverter, trunc cable, end cap
Pole Racking $0 MT Solar 4Top4 Donation includes rails and end clamps
Hoist $66 1 ton hand chain hoist (for raising pole mounting)
Pole Foundation $190 Concrete, wood supports, stakes, gravel
Wiring $443 150’ 10ga THHN wire (R,W,Blk), PVC conduit, fasteners, etc
Permit $98 L&I permit
Total Budget $3000 $2000 from FarmerFrog, $1000 from UW Bothell
Remaining Funds
$322 10% buffer budget
36
Operations & Maintenance
1) Operations
a) System will function automatically as long as breakers and disconnect switches are in
the on position.
b) Panels are designed to handle expected snow loads.
2) Maintenance
a) Maintenance should be performed by a licensed electrician or solar installer.
b) Ensure breaker and disconnects are switched off prior to work.
c) Cover modules with a small tarp or blanket if possible to ensure they are not supplying
current to the connections.
d) Racking system may be lowered with provided 1-ton chain hoist for ease of access at
ground level.
e) Prior to lowering racking system, disconnect microinverter from junction boxes, and
remove junction boxes from U-bolt assemblies on pole.
f) At designed angle (40∘) cleaning will occur naturally by rain, if necessary, spray only top
of solar panels lightly with a hose.
g) If excessive snow (+10”) builds up on modules, brush lightly with a clean, soft bristled
broom.
37
Appendix A: Component Specifications
Microinverter Specifications 38
Solar Module Specifications 40
Pole and Racking Specifications 42
Microinverter Specifications
38
Microinverter Specifications
39
Solar Module Specifications
40
Solar Module Specifications
41
Pole and Racking Specifications 42
43
Appendix B: Component User Manuals
MT Solar 4-TOP4 Installation Manual 44
SolarWorld SW280 Mono Manual 54
APSystems YC500a Microinverter Manual 57
MT Solar 4-TOP4 Installation Manual
44
4” Series Top of Pole Mount
Installation Manual
2016 V2.5
www.mtsolar.us
844-MT-SOLAR (687-6527)
MT Solar 4-TOP4 Installation Manual
45
2
Thank you for choosing MT Solar Pole Mounts.
It is the installer’s responsibility to determine foundation parameters based on local site conditions, such as wind speed, snow load, soil type, exposure category, etc. Installations also must comply with local building regulations and requirements.
We recommend consulting an engineer for a recommendation on foundation dimensions and pipe size and thickness. MT Solar can also provide a stamped drawing engineered for site-specific requirements for an additional fee. Please contact us to find out more.
Tips for Conventional Pipe Installation:
Dig hole according to recommended depth and diameter.
Set pipe in hole and use a level to ensure it is plumb and vertical to the ground.
If installing multiple poles, use a string to line up pipes.
Brace pipe to prevent it from moving while pouring concrete.
Proper compaction of backfill around sonotube or form is recommended, unless pouring so that con-crete is in direct contact with the soil.
Allow concrete to cure for recommended length of time.
Tools Required:
3/4” Socket
9/16” Socket
Crescent Wrench
Torque Wrench
Tape Measure
Angle Finder
Compass
Ladder
MT Solar 4-TOP4 Installation Manual
46
3
103 104 A
Installation Guide
102 B 102 A
104 B
The 4” Series Top of Pole Mount does not come standard with the lifting bracket and chain hoist. If you choose to add this option, follow steps 101 to 104 to install the lifting assembly.
101: With the 4" Sch 40 or Sch 80 steel pipe installed in the ground, slide the pole cap over the pipe.
102: Place the lifting insert into the top of the pipe until it sits flush. Place the lifting bracket into the lifting insert with the eye facing south.
103: Hang a 1 ton or greater chain fall hoist from the lifting eye.
104: Hang the U-Bracket Assembly on the Chain Hoist.
101
105: If you do not have a chain fall hoist, install pole cap at the top of the pole, in-sert the 5/8” x 7” bolt, two 5/8” fla
t washers and 5/8”nut
and four 1/2” x 1” set screws. Tighten all. Proceed with in-stallation of all components at the top of the pole.
107
106: Attach the Tilt Adjuster Handle to the tab on the Back Plate with the 1/2” x 1 1/2” Bolt, two 1/2” flat washers and 1/2” Nylock Nut.
105 106
MT Solar 4-TOP4 Installation Manual
47
4
107 109
108
110: Ensure that the MT Solar lette
r
i ng is upright, and atta
c
h one of the 2x3” rectangular tubes to the 2” pipes using the 1/2” x 3 1/2” bolts with 1/2” flat washers and split washers.
111: Install the remaining 2x3” rectangular tube. Snug up all 4 bolts, but leave loose enough to allow for some play when installing Angle pieces. Adjusting the Tilt Adjuster as necessary, level the array in prepa-ration for the installation of the 2” x 3” angle.
110
107: Slide one of the 2” pipes through the tilt adjuster and the other 2" pipe through the U Bracket Assembly sleeve.
108: Center pipes in sleeves. There should be equal length of pipe on either side of the sleeve.
109: Slide collars on 2” pivot pipe and tighten with 1/2” x 1” square head set bolts. Hold collar firm against the sleeve when tightening.
111
MT Solar 4-TOP4 Installation Manual
48
5
112 A 113
112 B
112: Install the first two 3x2 Angle sections to the 2x3 Tube using the 1/2" x 1 1/2” bolts, flat washers and split washers. Use the 1/2” x 1 1/4” bolts and 1/2” flan ge nuts to splice the two angle sections together.
113: Install the second two 3x2 Angle sections but DO NOT TIGHTEN at this step.
4 Module Installation
For 4 Module installations, follow steps 112 thru 117 below. For 2 or 3 Module installations, skip to step 118.
114 A 114 B
114: Standing on the North Side of the array with the Tube to Angle bolts started but not tightened, sight the Angle pieces to ensure they are parallel. If not, twist the array until they are then tighten the bolts between the Rectangular Tubes and the Angle.
MT Solar 4-TOP4 Installation Manual
49
6
115 B
115 A
115 C
115: Plan the layout of your rails according to your module width. Install the Beam Clamps on the I-beam using the 3/8” x 1 1/4” carriage bolts and 3/8” flange nuts.
Remember to leave a 5” gap in the center to allow for the 4” diameter pipe to protrude through, if you wish to put all the modules on at ground level.
117
116: Install the Mounting Rail into the beam clamps slot as per Mounting Rail instructions. Use 3/8” x 1” stainless steel bolts and 3/8” serrated flange nuts. Tighten beam clamps once the rails are in position for modules.
117: Center rails over Angle pieces, keeping equal length of rail off the end of each angle.
116
MT Solar 4-TOP4 Installation Manual
50
7
2 & 3 Module Installation
For 2 & 3 Module installations, follow the steps 118 thru 119 below. For 4 Module installations, see steps 112 through 117 above.
118 A
118 B
118: Install the Rail Attachment brackets to the ends of the 2x3 rectangular tube using the 1/2” x 1 1/2” bolts.
119 B 119 C
119: Install the Aluminum Rails to the Atta
c
hment brackets using the 3/8” x 1” stainless bolts and 3/8” fla
nge nuts.
119 A
MT Solar 4-TOP4 Installation Manual
51
8
120: Install Solar Modules as per Mounting Rail and module manufacturer instructions using top clamps. See last page of manual for Iron Ridge Rail and Clamp instructions.
120 A 120 B
121 A 121 B
122
121: For the TOP-2 and TOP-4, if you are installing modules at ground level, leave a 5” gap to allow for the 4” pipe to protrude through the array. If you are installing at the top of the pole, you do not need to provide this gap.
122: For the TOP-3, if installing at ground level, leave the middle module out until array is hoisted to the top. It is ok to temporarily install the outer two modules with just 2 end clamps each.
MT Solar 4-TOP4 Installation Manual
52
9
123 124
123: Once module installation is complete, raise and or tilt the array to facilitate module wiring and wire management as needed. When wiring is completed, raise the array to the top of the pole.
124: If necessary, installing remaining module.
125
126
125: Insert the 5/8" x 7” bolt over the top of the pole with the 5/8” fla
t
washers and 5/8” nut. Securely tighten the 4 tension bolts in the back of the pole cap to 200 ft-lb.
126: Remove the chain hoist and lifting bracket and place the 1 3/8” diameter round cap in place.
Using an angle finder, adjust array to proper tilt.
Installation is complete.
MT Solar 4-TOP4 Installation Manual
53
10
SolarWorld Sunmodule SW280 Mono Manual
54
SolarWorld Sunmodule SW280 Mono Manual
55
SolarWorld Sunmodule SW280 Mono Manual
56
APSystems YC500a User Manual
57
APSystems YC500a User Manual
58
APSystems YC500a User Manual
59
APSystems YC500a User Manual
60
APSystems YC500a User Manual
61
APSystems YC500a User Manual
62
APSystems YC500a User Manual
63
APSystems YC500a User Manual
64
APSystems YC500a User Manual
65
APSystems YC500a User Manual
66
APsystems YC50 0 -A Installat ion/ User Manual 8
YC50 0 number per branch
2 3 4 5 6 7* 8 9
EXTERNAL W IRE
SIZE (AW G) MAXIMUM EXTERNAL CABLE LENGTH (f t )
12 370 .7 237.1 167.9 124.3 93.6 70 .2 51.4 35.7
10 593.1 379.4 268.6 198.9 149.7 112.3 82.3 57.1
8 926.8 592.9 419.6 310 .7 233.9 175.5 128.6 89.3
6 1482.8 948.6 671.4 497.1 374.3 280 .8 20 5.7 142.9
*7 is the maximum number / branch w ith a 20 amp br eaker
Step 2 – Attaching the APsystems microinverters to the
racking or the PV module frame
A. Mark the location of the microinverter on the rack, keeping in
mind the PV module junction box or any other obstructions.
B. Mount one microinverter at each of these locations using
hardware recommended by your module racking vendor.
C. GROUNDING WASHER: If using the appropriate grounding
washer (check with a licensed electrician), attach the grounding
washer between the PV racking frame and the microinverter.
WARNING: Prior to installing any of the microinverters, verify that
the utility voltage at the point of common connection matches the
voltage rating on the microinverter label.
Figure 5
AB
APSystems YC500a User Manual
67
APsystems YC50 0 -A Installat ion/ User Manual 9
WARNING: Do not mount the microinverter in a location that allows
exposure to direct sunlight. Allow a minimum of 3/4” (1.5 cm.) between
the roof and the bottom of the microinverter to allow proper air flo
w
.
NOTE: Connecting cables (steps 3-5) can be done in any order but DO
NOT energize the utility power grid until all the steps are completed.
Step 3 – Connecting APsystems microinverters to the PV module
Connect the DC cables from the PV modules to the microinverter per the
diagram below:
Note: When plugging in the DC cables, the microinverter should
immediately blink red then green three times. This will happen as
soon as the cables are plugged in and will show that the microinverter
is functioning correctly. This entire check function will start and end
within 5 seconds of plugging in the unit, so pay careful attention to
these lights when connecting the DC cables. This only occurs when DC
voltage is fir
s
t appl ied. The LED wi ll not flas
h
whe n t he second panel
is connected.
9
Figure 6
Photovoltaic panels
and microinverter DC
input cable connection
MC4 Connectors
AB
APSystems YC500a User Manual
68
APsystems YC50 0 -A Installat ion/ User Manual 10
WARNING: Ensure that all AC and DC wiring is correct. Check that
none of the AC and DC wires are pinched or damaged. Be sure that
all junction boxes are properly closed.
Step 4 - Ground the system
NOTE: If you already used grounding washers (WEEB) to ground the
microinverter chassis to the PV module racking as described in Step
2C, skip this step.
Each APsystems microinverter comes with a ground clamp that can
accommodate a single #6 awg strand and #4 awg solid conductor.
Check your local electrical code for grounding conductor sizing
requirements. Connect the grounding electrode conductor to the
microinverter ground clamp.
NOTE: The AC output neutral is not bonded to ground inside the
microinverter.
Figure 7
APSystems YC500a User Manual
69
APsystems YC50 0 -A Installat ion/ User Manual 11
Step 5 - Connecting the APsystems microinverter to the PV module
A. Check the microinverter datasheet for the maximum allowable
number of microinverters on one AC branch circuit.
B. Plug the AC female connector of the fir
s
t mi croi nverter int o the
male connector of the next microinverter, and so on, to form a
continuous AC branch circuit.
C. Install a protective end cap on the open AC connector of the last
microinverter in the AC branch circuit.
WARNING: Do NOT exceed the maximum number of microinverters
in an AC branch circuit, as displayed on the unit label.
Figure 9
A B
FigureFigure 8
APSystems YC500a User Manual
70
APsystems YC50 0 -A Installat ion/ User Manual 12
M icro inve rte rse ria l n u m b e rs
AB AB AB
1 0 11 2 34 5 80 4 4 1 01 12 3 45 8 04 5 1 01 1 23 4 58 0 54 ……
Step 6 - Completing the APsystems installation map
Fill in the APsystems registration cards, which provide system
information and the installation map. Feel free to provide your own
layout if a larger or more intricate installation map is required. The
layout map provided is designed to accommodate labels in vertical or
horizontal orientation to meet all fie
l
d PV conf igu
r
ati ons.
1. Each APsystems microinverter has a removable serial number
label. Peel each label off, and affix
it to the respective locat ion
on the APsystems installation map.
2. Fill out the warranty cards. The warranty card and installation
map are needed to register the site in the EMA.
3. Complete the EMA Installer Account Registration form found
on the APsystems website. APsystems will create the EMA
account and email you the account information. Then you can
use the EMA website to view detailed performance data for the
PV system.
Figure 10
APSystems YC500a User Manual
71
APSystems YC500a User Manual
72
APSystems YC500a User Manual
73
APSystems YC500a User Manual
74
APSystems YC500a User Manual
75
APSystems YC500a User Manual
76
APSystems YC500a User Manual
77
APSystems YC500a User Manual
78
APSystems YC500a User Manual
79
APsystems YC50 0 -A Installat ion/ User Manual 21
Figure 11
Sample W iring Diagrams
Sample W iring Diagram - 120 V/ 240 V Split Phase
Sample Wiring Diagram - 120V/ 240V Split Phase
AC
JUN
CT
ION
BO
X
EN
ER
GY
CO
MM
UN
ICA
TIO
N U
NIT
ET
HE
RN
ET C
ON
NEC
TIO
NT
O B
RO
AD
BA
ND
RO
UT
ER
12
0 VA
C P
OW
ER C
AB
LE
AC
BR
AN
CH
EN
D C
AB
LE
RE
D - L1
BLA
CK
- L2
WH
ITE - N
ME
TE
R
BR
AN
CH
EN
D C
AP
INS
TA
LLE
D O
N T
HE
OP
EN A
C C
ON
NE
CT
OR
UP
TO 7
YC5
00 P
ER
BR
AN
CH
CIR
CU
IT
Ap
system
s Y
C5
00
-NA
20
AM
P C
IRC
UIT
BR
EA
KE
R PE
RB
RA
NC
H C
IRC
UIT
TO
ME
TE
RO
R A
CD
ISTR
IBU
TIO
NPA
NE
L
NEU
TR
AL
GR
OU
ND
DIS
TR
IBU
TION
PAN
EL
120
V/2
40
V S
PLIT PH
ASE
SOLA
RPA
NEL
EC
U
APSystems YC500a User Manual
80
APsystems YC50 0 -A Installat ion/ User Manual 22
Sample Wiring Diagram - 120V/ 208V Three Phase
AC JU
NC
TIO
N B
OX
AC
BR
AN
CH
EN
D C
AB
LE
RE
D - L1
BLA
CK
- L2W
HIT
E - N
ME
TER
BR
AN
CH
END
CA
PIN
STA
LLED
ON
TH
EO
PE
N A
C C
ON
NE
CT
OR
UP T
O 6
YC5
00
PE
RB
RA
NC
H C
IRC
UIT
20
AM
P CIR
CU
ITB
RE
AK
ER
PE
RB
RA
NC
H C
IRC
UIT
TO M
ETE
RO
R A
CD
IST
RIB
UT
ION
PAN
EL
NE
UT
RA
LG
RO
UN
D
DIS
TR
IBU
TIO
N PA
NE
L1
20
V/ 2
08
V T
HR
EE P
HA
SE
SO
LAR
PAN
EL
ET
HER
NE
T CO
NN
EC
TIO
NTO
BR
OA
DB
AN
D R
OU
TE
R
Ap
system
sY
C5
00
-NA
12
0 VA
C P
OW
ER
CA
BLE
EN
ER
GY
CO
MM
UN
ICAT
ION
UN
IT
EC
U
NOTE: The ECU should function properly when connected to L1, L2
or L3.
Sample wiring diagram - 120 V/ 20 8V Three Phase
Figure 12
81
Appendix C: Required Documentation Submission
PUD Site Diagram 82
Initial Wiring Diagram 83
As-Built Wiring Diagram 84
Grounds Preparation Diagram 85
Warranty Information 86
PUD Site Diagram
82
Solar arrays on pole mount Modules 40”x65”
Micro inverters under modules
PUD meter & solar meter grouped on side of home panel in electrical room
Job: Farmer Frog 23210 Paradise Lake Rd Woodinville, WA 98077
Initial Wiring Diagram
83
560 W SOLAR PHOTOVOLTAIC SYSTEM
GENERATOR
Solar PV Array Module: SolarWorld 280 Mono Power Output: 280 W DC Quantity: 2 Modules Total Max Output: 560 W DC Location: Pole mount
INVERTERS
Qty 1: APS YC – 500A Max Power Output: 500 W AC Output Voltage: 240 V AC Max Amps Out: 2.08 A AC Location: Co-located with modules
MAIN SERVICE PANEL
Rating: 200 A / 240 V AC Main Breaker: 200A SERVICE METER
1 String of 1 panel 2 conductors #10 in 3/4“ PVC
1 String of 1 panel 2 conductors #10 in 3/4“ PVC
2 conductors #10 in 3/4“ PVC
#10 EGC
Total System Voltage Drop: 0.11%
Customer: Address: Designer:
Zsofia Pasztor 23210 Paradise Lake Rd Woodinville, WA 98077 S.A.F.F
As-Built Wiring Diagram
84
560 W SOLAR PHOTOVOLTAIC SYSTEM
GENERATOR
Solar PV Array Module: SolarWorld 280 Mono Power Output: 280 W DC Quantity: 2 Modules Total Max Output: 560 W DC Location: Pole mount
INVERTER
Qty 1: APS YC – 500A Max Power Output: 500 W AC Output Voltage: 240 V AC Max Amps Out: 2.08 A AC Location: Co-located with modules
MAIN SERVICE PANEL
Rating: 200 A / 240 V AC Main Breaker: 200A
SERVICE METER
1 String of 1 panel 2 conductors
1 String of 1 panel 2 conductors
3 conductors #10 in 3/4“ PVC
Total System Voltage Drop: 0.11%
Customer: Address: Designer:
Zsofia Pasztor 23210 Paradise Lake Rd Woodinville, WA 98077 S.A.F.F
#6 GEC
15 A
Grounds Preparation Diagram
85
30’onhouse 50’underground
2’dia
Sch40PVC&10gaTHHN
Sch80PVC&10gaTHHN
Warranty Information
86
87
88
Appendix D: Other Documentation
Contact Information 89
Initial PUD Interconnect Application
Net Metering Agreement
Contact Information
89
Company Topic Representative Email
BlueFrog Solar APSystems YC500a
Microinverter Tim Bailey [email protected]
MT Solar MT 4-TOP4 Joel Unruh [email protected]
SolarWorld SW 280 Mono Customer Support [email protected]
Technical Support [email protected]
A&R Solar Marketing Jen Olson [email protected]
Project Administrator Wendy Wenrick [email protected]
Electrician Mike Dalton [email protected]
Electrician Jason Budgeon [email protected]