  1. 1. Contract for MaterialMaterial provided under separate Contract and delivered to Bihac Water Utility.WU has received material in total value of 741.000EUR:- Service Line Pipe material (PE80, PN10, OD25-50) 14.100m;- City Network Pipe material (PE100, PN16, OD63-250) -13.212m;-Transmission Main DI DN300, PN16 Pipe material 1.222m- In addition all Pipe fittings, 830nr Service valves, 330nr Gate valves, 30 Hydrants, 3.000nr Water Meters, 100nr Bulk Water Meters were provided by the Project
  2. 2. STEEL FLANGED TEESWATER METERS 3.000NR
  3. 3. VARIOUS MATERIALDI DN300 PAM UNIVERSAL PIPES (PN16) 1.222M
  4. 4. SERVICE LINES PE80, PN10 PIPE MATERIAL (OD25-50, L=14.100M)PIPE MAIN PE100, PN16 PIPE MATERIAL (OD63-250, L= 13.212M)
  5. 5. Projects Sign Board
  6. 6. Project Scope of Works:o Project Zone 1: Replacement of existing pipes by construction of new PE-HD pipes, OD 63 with total length 1151m, OD 90 with a total length 195m, OD 180 with a total length 721m, OD 250 with total length 97m. Construction of approx. 470 new house connections along and to the already new installed line PE DN200/PE DN100/PE DN50 (=OD250/OD 125/OD63); including disconnection of old lines and house connections.o Project Zone 4: Replacement of existing pipes by construction of new PE-HD pipes, OD 63 with total length 707m, OD 90 with total length 476m, OD 125 with total length 364m, OD 180 with total length 1814m. Construction of approx. 270 new house connections along and to the already new installed line PE DN200/PE DN100/PE DN50 (=OD250/OD 125/OD63); including disconnection of old lines and house connections.o Project Zone 5: Replacement of existing pipes by construction of new PE-HD pipes, OD 63 with total length 532m, OD 125 with total length 970m, OD 250 with total length 3.774m. Construction of approx. 231 new house connections along and to the already new installed line PE DN200/PE DN100/PE DN50 (=OD250/OD 125/OD63); including disconnection of old lines and house connections.o Project Zone 10: Replacement of existing pipes by construction of new PE-HD pipes, OD 63 with total length 140m, OD 125 with a total length 931m, Construction of approx. 150 new house connections along and to the already new installed line PE DN200/PE DN100/PE DN50 (=OD250/OD 125/OD63); including disconnection of old lines and house connections.
  7. 7. Zones 1, 4, 5 & 10 City NetworkIn Total installed:City Network Pipelines (PE100, PN16):OD63 2.371m;OD90 1.229m;OD125 1.069m;OD180 2.331m;OD225 437m;OD250 1.241mTotally installed 8.678m of main pipelines with 670 associated House Connections
  8. 8. PIPE WELDING
  9. 9. HOUSE CONNECTIONS DIAMETERS OD25-50, 670NR IN ~10.000M LENGTH
  10. 10. PIPE SADDLE HOUSE CONNECTIONSBRANCH GATE VALVE
  11. 11. PRESSURE TESTING (EN805)HYDRANT INSTALLATION (IN TOTAL 20 UNDERGROUND HYDRANTS INSTALLED)
  12. 12. HOUSE CONNECTION (SERVICE LINE) WITH PIPE SADDLE AND VALVEABOVE-GROUND HYDRANTS (3NR INSTALLED)
  13. 13. UNDERGROUND HYDRANTSUNDERGROUND HYDRANTS
  14. 14. PIPE TRENCH BACKFILLING COMPACTION (PLATE LOAD TEST PER DIN18134)PIPE MARKING TAPE
  15. 15. HOUSE CONNECTIONS TO WATER METER LOCATION (3.000NR WATER METERS AND ASSOCIATED FITTINGS PROVIDED FOR WATER UTILITY)HOUSE CONNECTIONS TO WATER METER LOCATION
  16. 16. TRENCH COMPACTIONPLATE LOAD TEST ON TRENCH AREAS(AS PER DIN 18134 / NORM B4417)
  17. 17. Zone 8 New WS RC Tank Debeljaca (700m3)The new RC water reservoir constructed app. 100 m north of the old reservoir. The maximum operating water level is at a height of 293,00masl, the minimum water level is at a height of 288,50masl.In the first stage only one chamber of the reservoir with a volume of 700m will be constructed. The walls and the piping built in a manner that an extension in the future with further 700m is possible without any changing.
  18. 18. ELECTRO MAGNETIC FLOW METER PROMAG 50W
  19. 19. ELECTRIC ACTUATOR
  20. 20. SCADA CONTROL CABINETAUTOMATIC AIR VALVE
  21. 21. Zone 8 Feeder Line DI DN300, L=332mGravity feed Feeder Line DI DN300 from new RC Tank Debeljaca to Flow Control Chamber
  22. 22. CONNECTION TO RC TANK DEBELJACACONNECTION TO FLOW METER CHAMBER
  23. 23. Zone 8 Flow Control ShaftThe flow control shaft constructed 250m north of the New Debeljaca Reservoir at the feeder line to the distribution network.
  24. 24. BASE SLAB REINFORCING WORKSDI PIPE PENETRATION THROUGH THE WALL
  25. 25. WALL REINFORCEMENT WORKSROOF SLAB REINFORCEMENT WORKS
  26. 26. HYDRO-INSULATIONFLOW EL.CONTROL VALVE BERMARD MODEL 718-03
  27. 27. Zone 9 Transmission Main Ductile Iron PipelineThe Project Zone 9 is presenting the transmission main from Privlica Pumping Station to the New Debeljaca Reservoir.The connection realized with a pressure DI pipe with a diameter of DN300mm. In parallel a data cable connection from Privlica Pumping Station to Debeljaca Reservoir shall be laid.DI DN300; PN16, L=826m
  28. 28. PIPE MATERIAL:PAM UNIVERSAL DI DN300, PN16TITANIUM SIT - JOINTS
  29. 29. CONNECTION OF DI PIPESTITANIUM SIT - JOINTS
  30. 30. PRESSURE TESTING ANCHORING THE PIPE-ENDSANALOG & DIGITAL PRESSURE GAUGES, TESTING AS PER EN805 STANDARD
  31. 31. Zone 9 Transmission Main Drain Valve
  32. 32. SUPPLY AND INSTALL AN OIL-IMMERSED TRANSFORMER10 KV/ 0.4 KV, RATED 1,000 KVA, INCLUDING ALL AUXILIARIES AND PROTECTION EQUIPMENT.TYPE: KBTS-1-VP 10(20)/0,4KV, 1X1000KVA (EN61330)
  33. 33. EL. MAG. FLOW METER ENDRESS+HAUSER PROMAG 50 WDN350, PN16
  34. 34. ELECTRO MAGNETIC FLOW METER ENDRESS+HAUSER PROMAG 50 W, DN250, PN16
  35. 35. Remaining BudgetOut of the remaining Budget the following items have been provided for WU:- Vehicle VW Van 2,5 TDI;- Leak Detection Equipment:Woltex Water Meters (3nr DN100, 200, 300)Geofon Guterman (2nr)Measuring Wheel M10 (2nr)SEWAD 30-s digital pressure logger (2nr)Kit for SEWAD 30-s (1nr)GPS/GIS Magellan Mobile Mapper 6 (1nr)FUJI Metal Locator F-90M (2nr)In total:Contract for Material 741.085,28Contract for Works 1,258,872.74Total Value: 1,999,958.02Total Project Budget: 2,000,000.00