10
84 http://ssrn.com/abstract=2201957 N N E E T T W W O O R R K K A A N N A A L L Y Y S S I I S S Part 6 - MINIMUM COST AND ASSOCIATED DURATION Samithamby Senthilnathan PhD (Business), M.Sc (Management), B.Sc (Business Administration) Department of Management, FCM Eastern University, Sri Lanka Abstract Part 6 of network analysis illustrates the determination of efficient (optimal) minimum cost as the primary objective and its associated duration in relation to completion of a project in consideration of the crashed durations and cost slopes of activities, and the time based fixed cost, of a project. This part is organized with Prioritised Minimum Cost, and Techniques and Estimation of Prioritised Minimum Cost. Key words: Minimum cost, critical path, associated duration JEL code: C00, O22 Note: This paper is intended to provide a basic explanation about the network analysis in relation to managing duration and cost of a project. Further extension of this paper depends on the support from readers who are expected to provide me your valuable comments and suggestions to continue this task. Please send your comments to [email protected] .

Network Analysis: Part 6 - Minimum Cost and Associated Duration

Embed Size (px)

Citation preview

84

http://ssrn.com/abstract=2201957

NNEETTWWOORRKK AANNAALLYYSSIISS PPaarrtt 66 -- MMIINNIIMMUUMM CCOOSSTT AANNDD AASSSSOOCCIIAATTEEDD DDUURRAATTIIOONN

SSaammiitthhaammbbyy SSeenntthhiillnnaatthhaann PPhhDD ((BBuussiinneessss)),, MM..SScc ((MMaannaaggeemmeenntt)),, BB..SScc ((BBuussiinneessss AAddmmiinniissttrraattiioonn))

DDeeppaarrttmmeenntt ooff MMaannaaggeemmeenntt,, FFCCMM

EEaasstteerrnn UUnniivveerrssiittyy,, SSrrii LLaannkkaa

Abstract

Part 6 of network analysis illustrates the determination of efficient (optimal)

minimum cost as the primary objective and its associated duration in relation

to completion of a project in consideration of the crashed durations and cost

slopes of activities, and the time based fixed cost, of a project.

This part is organized with Prioritised Minimum Cost, and Techniques and

Estimation of Prioritised Minimum Cost.

Key words: Minimum cost, critical path, associated duration

JEL code: C00, O22

Note: This paper is intended to provide a basic explanation about the network analysis in relation to managing duration and cost of a project. Further extension of this paper depends on the support from readers who are expected to provide me your valuable comments and suggestions to continue this task. Please send your comments to [email protected].

85

http://ssrn.com/abstract=2201957

6.1 PRIORITISED MINIMUM COST

In the previous Chapters 4 and 5, illustrations are given to determine in relation to

normal duration and normal (associated) cost, and minimum prioritised duration and

its associated optimal cost of a project, respectively. In the same context, there is a

possibility to explore the project minimum cost and its associated optimal duration. In

completing a project, it is possible to incur certain amount of fixed cost as per its unit

duration. Based on this possibility only, the minimum cost of a project is prioritized in

this chapter in association with the project completion duration.

The fixed cost based on unit duration plays a significant role in determining the

minimum cost of a project. Therefore, the leading role of fixed cost to prioritise and

estimate the minimum cost of a project can be explored in its comparison with the

savable durations and cost slopes of respective project critical activities. Either (a)

when the cost slopes of critical activities are more than the fixed cost or (b) when

critical activities with lowest cost slopes to the fixed cost have no room to save unit

duration, the minimum cost of the project would be equal to its normal cost.

6.2 TECHNIQUES AND ESTIMATION OF PRIORITISED MINIMUM COST

To understand the prioritized minimum cost of a project, consider the same example in

Chapter 5 with the additional information of fixed cost per unit of duration. In this

context, the example is reproduced below for convenience and easy understanding.

Example 6.1

The information on a project to be completed by ABC Company is given in Table 6.1. In

addition, consider that there is per day fixed cost of Rs. 100.00 to complete the project.

You can determine the minimum cost and associated optimal duration of the project by

using the information given.

Table 6.1: Project information

Activity Preceding

activity

Normal

duration

(days)

Crashed

duration

(days)

Normal

cost

(Rs.)

Crashed

cost

(Rs.)

Cost

slope

(Rs.)

A - 4 3 360 420 60

B - 8 5 300 510 70

C A 5 3 170 270 50

D A 9 7 220 300 40

E B,C 5 3 200 600 200

Total 1250 2100 ---

86

http://ssrn.com/abstract=2201957

According to the project information in this example, it is important to initiate with

network diagram (Figure 6.1) and estimating associated (normal) cost of the project.

Figure 6.1: Project network for normal duration

Figure 6.1 shows project duration of 14 days and its associated cost is determined as:

Normal cost of activities = Rs. 1,250.00 (as in Table 6.1)

Fixed cost (for 14 days) = Rs. 1,400.00 (= 14 x Rs. 100)

Total normal cost for project duration = Rs. 2,650.00 and

The critical path of the project is A, C, and E.

Together with the above determined information, the bases 1, 2 and 3 organized for

Approach 2 in Chapter 5 are important, as given below, to determine the project

minimum cost and its associated duration.

Base 1: Related to activity, cost slope and duration to saved

Activity Cost slope

(Rs.)

Duration to

save (days)

A 60.00 1

B 70.00 3

C 50.00 2

D 40.00 2

E 200.00 2

Base 2: Identifying paths in the project

P1 A, D = 13 days

P2 A, C, E = 14 days

P3 B, E = 13 days

4

C 5 E

5

D 9

A

4

B 8

1

2

0

4 55

0

4

3

9 9

45

7

14 14

4

87

http://ssrn.com/abstract=2201957

Base 3: Setting the least cost schedule for the normal duration and cost of the project

Table 6.2: Least cost schedule

Activity Paths Critical

Path(s)

Cost

Adjustment

Adjusted Total

Cost (Rs.) P1 P2 P3

Normal Duration 13 14 13 P2 --- 2650.00

It is specifically mentionable that in Chapter 5, the minimum duration of a project is

prioritised and its optimal associated cost is determined and the cost is not given

preference over the duration of a project.

In contrast, in this chapter (6), the minimum cost is prioritised and estimated, and its

associated duration is determined. The preferential option is given to estimate project

minimum cost and its associated duration is determined accordingly. Indicatively,

almost the same steps that are applied for adjusting the least cost schedule in Approach

2 of Chapter 5 need to be employed to determine project minimum cost and its

associated duration.

Step 1: To determine the minimum cost of the project, the critical activities

should be in consideration to make adjustment in the least cost schedule.

The determination of minimum cost is also devised through adjustment of

crashed duration.

In this step, the critical activities A, C and E are considered for adjustment.

Step 2: Deciding the critical activity/activity combination for the adjustment

towards minimum cost, based on its savable duration and the fixed cost.

In this context, the adjustment towards the minimum cost should be made with

the activity or combination of activities that has the lower cost slope than per

unit fixed cost and the savable duration.

In Base 1 of this example, critical activity C has the lowest cost slope (Rs. 50.00)

and this cost slope needs to be compared with the fixed cost (Rs. 100.00). If the

(minimum) cost-slope of activity C is more than the fixed cost as the result of

reduction in project duration, the normal cost is the minimum cost of the

project. In contrast, in this example, the cost-slope of activity C (Rs. 50.00) is

less than the fixed cost of unit duration (Rs. 100.00).

88

http://ssrn.com/abstract=2201957

Further, Base 1 shows that activity C has savable duration of 2 days. In this

context, it is important to ensure whether this savable duration (2 days) of

activity C can be adjusted towards minimum cost. For this purpose, consider

the critical path duration (14 days), the highest duration of non-critical path

(13 of P1 and P3 in Base 2), and compare the difference between them (1 day =

14 – 13) with the savable duration (2 days) of activity C. The lowest of them (1

day or 2 days) is the amount of duration (1 day) that can be adjustable with

activity C for minimum cost.

Step 3: Adjusting least cost schedule. In accordance with Step 2 above, the least cost

schedule in Base 3 should be adjusted as follows.

Table 6.3: Adjusted least cost schedule

Activity Paths Critical

path(s) Cost adjustment

Adjusted

cost (Rs.) P1 P2 P3

Normal duration 13 14 13 P2 --- 2650.00

C(1) 13 13 13 All +50(1) – 100(1) 2600.00

As per the adjustments made in the least cost schedule (Table 6.3), Bases 1 and

2 are also modified as improved as given below.

Base 1: Activity, cost slope and duration to be saved

Activity Cost slope

(Rs.)

Duration

saved (days)

A 60.00 1 1

B 70.00 3 3

C 50.00 2 1

D 40.00 2 2

E 200.00 2 2

Base 2: Identifying paths in network of the project

P1 A, D = 13 days

P2 A, C, E = 14 days, 13 days

P3 B, E = 13 days

Step 4: If there are two or more critical paths, their critical activities need to be

considered individually or in combination as required for adjustment

towards minimum cost, based on their cost slopes.

89

http://ssrn.com/abstract=2201957

At this point, due to the adjustments made in Bases 1, 2 and 3, all paths (P1, P2

and P3) are identifiable as the critical paths of the project. Therefore, to have

further improvement towards minimum cost of the project, the critical

activities on these paths should be considered individually or in combination to

reduce the project duration efficiently, based on their cost slopes and fixed cost.

As all paths are critical, not a single activity is found on all these paths.

Therefore, considering an activity individually to reduce project duration for

minimum cost becomes impossible. In this situation, it is only possible to

consider the combinations of activities, their cost slopes and fixed cost for

estimating efficient minimum cost.

In this example, the latest adjustment shows various combination of critical

activities on all three (P1, P2 and P3) critical paths as (A,B), (A,E), (A,D,B),

(A,C,B), (A,C,E), (A,D,E), (D,C,B) and (D,E). Comparatively, the combinations

(A,D,B), (A,C,B), (A,C,E) and (A,D,E) have higher cost slopes than other

combined cost slopes. Therefore, these combinations are not useful to improve

project cost and duration. In this context, the activity combinations (A,B), (A,E),

(D,C,B) and (D,E), and their respective cost slopes in Table 6.4 can only be

considered to determine the minimum cost efficiently and its associated

duration for the project.

Table 6.4: Cost slope of activity combination

Combination of activities

(per day)

Cost slope per unit of duration

(Rs.)

A(1), B(1) 60.00 + 70.00 = 130.00

A(1), E(1) 60.00 + 200.00 = 260.00

D(1), C(1), B(1) 40.00 + 50.00 + 70.00 = 160.00

D(1), E(1) 40.00 + 200.00 = 240.00

Table 6.4 shows that combination (A,B) has the lowest cost slope (Rs. 130.00)

to reduce a day on the critical paths. Therefore, the adjustment on duration for

further minimized cost improvement should be devised with the same

combination (A,B). However, while improving (minimizing) project duration

with the expense of Rs. 130.00 per day of combination (A,B), there is only one

(1) day saving of fixed cost Rs. 100.00.

90

http://ssrn.com/abstract=2201957

Comparatively, Rs. 130.00, the cost slope of combination (A,B), is more than Rs.

100.00 (the fixed cost of unit duration). Explicitly, it is clear that further

reduction in duration cannot improve the cost towards a minimum. Hence, the

minimum cost of the project is, as shown in Table 6.3, Rs. 2,600.00 and its

associated project duration is 13 days.

Note: In case, there are more than one critical paths with normal duration and cost

in completing a project, it is possible to continuously employ Step 4 to estimate

project minimum cost and its associated duration. However, it is important to have

a track on implementing this step, where the cost slopes of activity combinations

should not exceed the fixed cost in the adjustment process and should ultimately

reduce the total project cost beyond those cost slopes for crashing.

SELF REVIEW QUESTIONS

1. What do you understand about the minimum cost in relation to completing a

project?

2. What is the objective of prioritizing minimum cost in completing a project?

3. Indicate and explain the steps in determining the project minimum cost and its

associated duration.

4. Briefly explain how determination of project minimum cost and its associated

duration differ from estimating project normal duration and cost.

5. Explain in brief how determination of project minimum cost and its associated

duration differ from estimating project minimum duration and its associated

cost.

TERMINOLOGY

Adjusted Minimum Cost Schedule Cost slop of Combined Activities

Calculation of Minimum Cost Minimum Cost and Associated Duration

Combination of Activities Minimum Cost

Cost Combination

91

http://ssrn.com/abstract=2201957

Exercise

Lanka Company has a project to complete with the information given below. Using this

information, you are required to determine:

1. Critical path(s), normal cost and associated duration (in days) of the project.

2. Project minimum cost, its associated duration and the network that represents

the minimum cost.

Information I: Contract regulation

If the project is completed with more than 25 days, the additional days taken for

completion are charged with per day penalty cost of Rs. 400.00. The fixed cost per

day for the project is Rs. 700.00.

Information II: Activities

Activity Preceding

activity

Normal duration

in days

Normal cost

in Rs.

A --- 6 6600

B A 10 12200

C B, F, I, H 4 4500

D C 10 11000

E --- 6 7000

F A 8 8000

G H 8 8000

H --- 10 10000

I E 5 5000

Information III: Crashing

Except the activities C and I, any other activity can be crashed to save 2 days in

duration. The additional cost for saving a day of the activity is 10% of its normal

cost.

Answer

It is possible to draw two networks for this example.

Type 1:

F

8

C

4 0 0

16 16

16 16

A

6

B

10

H

10

I

5

G

8

D

10

6 6

20 20

30 30

E

6

10

00 16

6 11

92

http://ssrn.com/abstract=2201957

Type 2:

Normal Duration = 30 days

Critical Path:

Normal Cost = 72,300.00 + 5(400.00) + 30(700.00)

= 72,300.00 + 2000.00 + 21,000.00

= Rs. 95,300.00

Adjusted least cost schedule

Activity Paths Critical

path

Cost

adjustment

Adjusted

Cost (Rs.) P1 P2 P3 P4 P5

Normal

duration 28 30 25 24 18 P2 --- 95,300.00

A(2) 26 28 25 24 18 P2 +660(2) – 700(2)

–400(2) = –880 94,420.00

D(2) 24 26 23 22 18 P2 +(1100 –700)(2)

–400(2) = 0 94,420.00

Network diagram representing minimum cost

A B C D

6 + 10 + 4 + 10 = 30 days

F

8

C

4 0 0

16 16

A

6

B

10

H

10

I

5

G

8

D

10

6 6

20 20

30 30

E

6

10

00 16

6 11

16 16

F

8

C

4 0 0

14 14

A

4

B

10

H

10

I

5

G

8

D

8

4 4

18

0

18

0

26

0

26

0

E

6

10

00 14

6 9

14 14

93

http://ssrn.com/abstract=2201957

Bibliography

Anderson, D.R., Sweeney, D.J., and William, T.A. (2006), Quantitative Methods for

Business, 10th ed., India: Thomson South Western.

Gupta, P.K., and Hira, D.S. (2007), Operations Research, 20th ed., India: S.Chand &

Company Ltd.

Hillier, F.S., and Hillier, M.S. (2005). Introduction to Management Science – A

modeling and Case Studies Approach with Spreadsheets, 2nd ed., New

Delhi: Tata McGraw-Hill Publishing Company Limited.

Hillier, F.S., and Lieberman, G.J. (1994). Operations Research, 2nd ed., New Delhi:

CBS Publishers and Distributors.

Kalavathy, S. (2002). Operations Research, 2nd ed., Delhi: Vikas Publishing House

Pvt Ltd.

Karunaratna. K. R. M. T. (2005). Quantitative Methods for Management, 3rd ed.,

Sri Lanka.

Lawrence, J.A., and Pasternack, B.A. (2002). Applied Management Science, 2nd

ed., India: John Wiley & Sons, Ins, India

Lucey T. (1988). Quantitative Techniques – An Instructional Manual, 3rd ed.,

London: English Language Book Society/DP Publication.

Pinney, W.E., and McWilliams, D.B. (1987). Management Science: An

Introduction to Quantitative, Analysis for Management, 2nd ed., New

York: Harper and Row, Publishers.

Taha, H.A. (2004).Operations Research: An Introduction, 7th ed., New Delhi:

Prentice-Hall of India Private Ltd.

Tulsian, P.C., and Pandey, V. (2002). Quantitative Techniques – Theory and

Problem, Delhi: Pearson Education (Singapore) Pte.

Wagner, H.M. (2008). Principles of Operations Research, 2nd ed., New Delhi: PHI

Learning Pvt Ltd.