27
PCAPP Update 28 May 2014

PCAPP Update 28 May 2014

Embed Size (px)

Citation preview

Page 1: PCAPP Update 28 May 2014

PCAPP Update

28 May 2014

Page 2: PCAPP Update 28 May 2014

Safety

As of April 30, 2014

PCAPP staff has accomplished:

734 Safe Work Days

4,082,176 Safe Work Hours

VPP Application Submitted

2

Page 3: PCAPP Update 28 May 2014

Staffing – 1,018 employees

3

Bechtel Pueblo Team non-manual: 938

Pueblo

–241 Pueblo County hires

– 58 Colorado hires

–639 From Other Locations

Construction Workers:80

–Bechtel direct-hire – 50

–Subcontractor personnel – 30

Page 4: PCAPP Update 28 May 2014

Staffing Update

Upcoming Recruiting

Events:

May 22 -

Veterans Job Fair –

Colorado Springs,

Colorado

July 8-

Resume Writing

Workshop—Pueblo

Workforce Center

Hires v. Vacancies Pueblo County Applicants v. Hires

PCAPP Staffing Actuals

0

200

400

600

800

1000

1200

Jul-1

3

Aug-1

3

Sep-1

3

Oct-

13

No

v-1

3

De

c-1

3

Jan-1

4

Feb

-14

Ma

r-1

4

Apr-

14

Ma

y-1

4

Jun-1

4

Jul-1

4

Aug-1

4

Sep-1

4

Oct-

14

No

v-1

4

De

c-1

4

Jan-1

5

Feb

-15

Ma

r-1

5

Apr-

15

Ma

y-1

5

Jun-1

5

Jul-1

5

Aug-1

5

Sep-1

5

Sta

rt O

ps

Medical

Maintenance

Ops Support

Operations

Laboratory

Other

Actuals

1086

0

5

10

15

20

25

30

35

40

45

50

Filled Positions

Filled Positionscontaining PuebloCounty Applicants

Pueblo County NewHires

0

10

20

30

40

50New Hires PuebloCounty

New Hires fromColorado

New Hires fromOther (IncludesTransfers)

Positions Filled

4

Page 5: PCAPP Update 28 May 2014

Recruiting Efforts

5

Pueblo Community College Technical Career Fair on May 16 (above) and

May’s classified ad featuring local hire Jenny Owens

Page 6: PCAPP Update 28 May 2014

SYSTEMIZATION - 55% COMPLETE

APB 67%

ERB 66%

BTA 59%

As of May 2014

System Complete

UTILITIES 86%

HVAC 82%

FACILITIES 82%

6

Page 7: PCAPP Update 28 May 2014

Mar May Jul Sep Nov Jan 2015 Mar May Jul Sep

7

- Baseline

2014 Mar May Jul Sep NovJan

2015

Mar May Jul Sep 2015

120 daysHVAC Test &

Balance24 March 2014 - 21 July 2014

56 days

ERB Provisional Ops 30 September 2014 - 24 November 2014

28 days

Yard Provisional Ops 17 July 2014 - 13 August 2014

56 days

APB Provisional Ops 25 November 2014 - 19 January 2015

21 days

Integrated SYS Testing 20 January 2015 - 9 February 2015

30 days

Final HVAC 10 February 2015 - 11 March 2015

105 days

Optimization 12 March 2015 - 24 June 2015

56 days

BTA Provisional Ops 19 November 2014 - 13 January 2015

14 days

IOD 25 June 2015 - 8 July 2015

14 days

Fix Cat 1 Findings 9 July 2015 - 22 July 2015

60 daysEndorsement 23 July 2015 –

20 September 2015

START 21 September 2015

Systemization Schedule Overview

Page 8: PCAPP Update 28 May 2014

BTA Risk Reduction

What we are doing

• Identified BTA risks

• Defined mitigation actions

• Provided preliminary estimates of costs and benefits associated with BTA risk reduction implementation

• Optimizing BTA Systemization activities (biotreatment [ICB], bioreactor off-gas treatment, BRS, & WRS)

• Integrate proposed execution and implementation plan into IMS working file to indicate viability and benefits

• Accelerate BTA Provisional Ops

• Provide multiple opportunities for early BTA hands-on operator access and training for normal and off-normal Ops

8

Page 9: PCAPP Update 28 May 2014

BTA Risk Reduction

Four Key Mitigation Actions

• Perform enhanced water testing (2 parts: temp and ph control)

• Perform respirometry study (performed in laboratory)

• Perform BRS saltwater test

• Perform BTS/BRS surrogate hydrolysate test

Brine Reduction

System

9

Page 10: PCAPP Update 28 May 2014

BTA Risk Reduction

Benefits• Establish baseline operating temps

for ICBs

• Identify the optimal seed for BTS startup

• Evaluate dewatering performance and salt cake waste

• Demonstrate BRS effluent meets the water quality standards for recycle to the process water tanks

• Provide the forum for early training and hands-on operator access and use of BTA equipment and SOPs

• Demonstrate early TDG removal capability and provide a BTS module of full-rate processing at the start of Pilot Testing

10

Page 11: PCAPP Update 28 May 2014

2014May Jul Sep Nov

Jan

2015Mar May Jul Sep 2015

Today

Start of Agent Operations

Systemization Complete

BTA Provisional Ops

B14 System Demo Complete

B04 System Demo Complete

BT03 & BT04 System Complete

TDG #3(Optional

)TDG #2TDG #1TDG P.O.

Surrogate Test Material Procurement

Temp Mod Material

Procurement

Transition to Agent OpsSurrogate Testing

Field Work

Temp Mod

Design

Data Sheets

Salt Water TestField WorkTemp Mod DesignData

Sheets

Temp Mod Material

Procurement

Salt Water Test Material Procurement

Salt

Water

Testing

Surrogat

e Testing

Review &Add

Test Procedure Development

Test Plan

DevelopmentTest Plans

&

Procedure

sEWT Test 1B

EWT Test 1A*

Enhanced

Water Testing

BTA Risk Reduction Schedule

11

Page 12: PCAPP Update 28 May 2014

System Turnover

12

Significant progress was made when two systems—the natural gas system and the sanitary waste system—were turned over to the Operations team.

Page 13: PCAPP Update 28 May 2014

Agent Filtration Area

13

The last two of 10 plenums in the AFA have completed systemization testing, rendering them ready to receive cascading air flow. The plenums contain 180 pre-filters, 340 HEPA filters and 2,960 charcoal adsorber cells, weighing more than 123 tons.

Page 14: PCAPP Update 28 May 2014

Rep. Tipton Staffer Tour

14

PCAPP Project Manager Rick Holmes (second from left) and Operations Manager Kim Jackson give Regional Director Brian McCain, Constituent Services Representative (left) Doug Fitzgerald and Caseworker Robert Galena (right) from Rep. Scott Tipton’s office a tour of the facility on May 8.

Page 15: PCAPP Update 28 May 2014

Hazard School Board

15

PCAPP Employees learned a valuable lesson about the hazards associated with texting while driving as part of Safety’s Hazard School Board last month.

Page 16: PCAPP Update 28 May 2014

College Partnership

16

Pueblo Community College (PCC) Mechanical Systems Instructor Troy Bodle (right) assists PCAPP welder PetaKrajewski during a welding class. PCAPP has enlisted PCC to train eight PCAPP welders in titanium welding.

Page 17: PCAPP Update 28 May 2014

17

May 2014 Construction Update

Page 18: PCAPP Update 28 May 2014

18

May 2014 Construction Update

Page 19: PCAPP Update 28 May 2014

19

May 2014 Construction Update

Page 20: PCAPP Update 28 May 2014

Change House

Environmental

Enclosure #1

Environmental

Enclosure #3

Laboratory

PCAPP EDS Site Overview

20

Page 21: PCAPP Update 28 May 2014

PCAPP EDS Safety

As of April 30, the PCAPP EDS project staff has accomplished:

20 Safe Work Days

2,497 Safe Work Hours

21

Workers smooth concrete on May 8 after the first concrete slab pour for Environmental Enclosure #1.

Page 22: PCAPP Update 28 May 2014

PCAPP EDS ConstructionStaffing –26 employees

Construction

Workers: 6

–Subcontractor personnel – 20

A worker sets screws for the forms in preparation for the concrete slab pour for Environmental Enclosure #2

22

Page 23: PCAPP Update 28 May 2014

NOT STARTED

IN PROGRESS (POTENTIAL ISSUES)

IN PROGRESS (NO ISSUES)

COMPLETE

Key Milestone

DESIGN START (DEC 2013)

SITE DESIGN COMPLETE (MAR 2014)

CONSTRUCTION STARTS (27 MAR 2014)

CONSTRUCTION COMPLETE (OCT 2014)

E-DAY – EDS START OF

AGENT OPERATIONS (OCT 2014)

CONSTRUCTION CONTRACT AWARD (NOV 2013)

PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)

PCAPP EDS Schedule(JPME-P Working Schedule)

CONCRETE POURS BEGIN (17 APR 2014)

MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)

BEGIN TO ARRIVE (MAY 2014)

MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL

ENCLOSURES ARRIVE (JUN 2014)

ARRIVAL OF FIRST EDS UNIT (AUGUST 2014)

23

Page 24: PCAPP Update 28 May 2014

PCAPP EDS Permitting Progress

NOT STARTED

IN PROGRESS (POTENTIAL ISSUES)

IN PROGRESS (NO ISSUES)

COMPLETE

Key Milestone

CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)

STATE APPROVAL OF TEMPORARY AUTHORIZATION

FOR CONSTRUCTION (7 MAR 2014)

SITE CONSTRUCTION START (27MAR 2014)

APPROVAL OF CLASS III MODIFICATION

FOR OPERATIONS (SEP 2014)

E-DAY – EDS START OF AGENT

OPERATIONS (OCT 2014)

PCD RCRA PERMIT RENEWED (JAN 2014)

SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)

PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)

APPROVAL OF CD FOR OPERATIONS

(OCT 2014)

COUNTY APPROVAL OF TEMPORARY AUTHORIZATION

FOR CONSTRUCTION (26 MAR 2014)

RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)

24

Page 25: PCAPP Update 28 May 2014

Site Progress

25

Processing dirt, the job of mixing the fill with water under the weight of heavy equipment, makes for better compaction when it’s later moved into the enclosures as a base for the slabs that will be poured.

Page 26: PCAPP Update 28 May 2014

Site Progress

26

Measure twice, dig once. A worker confirms the depth of the trench being carved out. This for the pipes that will be part of the fire line that will serve the EDS site when complete.

Page 27: PCAPP Update 28 May 2014

Questions?

27

Acting Principal Deputy Assistant Secretary of Defense Dr. A. Tom Hopkins (third from left), Program Executive Officer ACWA Conrad Whyne (second from left) and PCAPP Project Manager Rick Holmes, listen to Jake Torres explain the munition process in the Vapor Containment Room.