14
Monthly Status Briefing May 2009

PCAPP Monthly Status Briefing May09

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PCAPP Monthly Status Briefing May09

Monthly Status BriefingMay 2009

Page 2: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Project Background

The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in mortar rounds and artillery projectiles stored at the U.S. Army Pueblo Chemical Depot.

Neutralization followed by biotreatment is the technology selected by the Department of Defense to destroy the Pueblo chemical weapons stockpile.

The Program Manager, Assembled Chemical Weapons Alternatives (ACWA), headquartered at Aberdeen Proving Ground, Maryland is responsible for managing all aspects of the safe and environmentally sound destruction of the chemical weapons stockpiles in both Colorado and Kentucky.

The Bechtel Pueblo Team, a partnership of Bechtel National, Inc.; Washington Demilitarization Company/URS; Parsons; and Battelle Memorial Institute, is the systems contractor selected to design, build, systemize, pilot test, operate and close PCAPP.

2

Page 3: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Staffing

3

Bechtel Pueblo Team non-manual: 265• Pueblo – 258 (85 local hires)• Other locations – 7

Construction Workers:• Bechtel direct hire – 196

• Subcontractor personnel – 37

Page 4: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Subcontract Awards

4

Inception to date, as of April 30

Page 5: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Acquisition Awards Status

5

FY 2009 Upcoming Awards:

Subcontracts• Piping Equipment and Heat Tracing• General Painting• Modular Medical Trailers

Materials• Misc. Construction Materials• Gypsum Drywall• Belt Conveyers

• Pumps• Pipe Supports

Page 6: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Construction Status - Complete

6

Multipurpose Building - foundation, shell, siding, and roof

Underground infrastructure (utilities)

Switch Gear Foundation Pads

Agent Filtration Area, Filtration Stack and pipe rack foundations

Automated Guided Vehicle Corridor –foundation, curbs/piers, structural steel

Tank foundations, all eight complete

Page 7: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Construction Status – In Progress

Agent Processing Building – misc. platform erection; siding and roofing, HVAC, cable tray, fire protection & process siding

Enhanced Reconfiguration Building – explosive containment room foundation, rebar placement and structural steel

Pipe Rack – vertical construction, pipe and cable tray

Biotreatment Area pipe rack

Excavation, formwork, rebar for Control Support Building, Munitions Service Magazine and Energetic Service Magazine corridors

Field erection – process water, sanitary and firewater tanks

Utility Building – siding & roofing, cable tray

77

Page 8: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

PCAPP Site Overview

8

1 2

3

4

1

2

3

4

Pipe Rack

Agent Processing Building

Automated Guided Vehicle Corridor

Enhanced Reconfiguration Building

Northwestern Corner ‐ Observation Point

1 2

3

4

Page 9: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Agent Processing Building

The agent water separator tanks (right) and the Munitions Wash Station wash water collection tanks are now in place in the Agent Processing Building.

99

Page 10: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Construction Site Tours

10

Members of the Colorado Chemical Demilitarization Citizen’s Advisory Commission toured the PCAPP site in April. John Thatcher (red jacket) and Irene Kornelly ask questions of Gary Anderson, PCAPP site project manager (right), and Mark Hunter, Bechtel lead field civil engineer (far left).

Page 11: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Enhanced Reconfiguration Building

Workers install rebar for three explosive containment rooms. Explosive components will be removed here.

1111

Page 12: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Construction Team of the Year

12

Steve Thieme, PCAPP site superintendent and Ed Snatchko, Bechtel construction manager (second and third from left), accept the Bechtel “2008 Construction Team of the Year Award” in the “Large Projects” category from Walker Kimball, President, Bechtel Construction Operations, Inc. (left) and Bill Dudley, President and Chief Operating Officer, Bechtel Group, Inc. (right). The award was given at the Bechtel Site Manager’s Conference in Chantilly, Virginia, April 13-17, 2009.

Page 13: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Voluntary Protection Program

13

On February 18, the PCAPP project was recognized by the U.S. Dept. of Labor Occupational Safety and Health Administration for receiving Star Status—the highest level of safety recognition—in their Voluntary Protection Program.

Page 14: PCAPP Monthly Status Briefing May09

OPSEC Complete 12 May 2009

Pueblo Chemical Agent-Destruction Pilot Plant

1414

PCAPP Final Design