17
Monthly Status Monthly Status Briefing Briefing September 2009

PCAPP Monthly Status Briefing September09.ppt

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PCAPP Monthly Status Briefing September09.ppt

Monthly Status Monthly Status BriefingBriefingSeptember 2009

Page 2: PCAPP Monthly Status Briefing September09.ppt

Project Background

The Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) will safely destroy 2,611 tons of mustard agent in mortar rounds and artillery projectiles stored at the U.S. Army Pueblo Chemical Depot.y p j y p

Neutralization followed by biotreatment is the technology selected by the Department of Defense to destroy the Pueblo chemical weapons stockpile.p p

The Program Manager, Assembled Chemical Weapons Alternatives (ACWA), headquartered at Aberdeen Proving Ground, Maryland is responsible for managing all aspects of the safe and g genvironmentally sound destruction of the chemical weapons stockpiles in both Colorado and Kentucky.

The Bechtel Pueblo Team, a partnership of Bechtel National, Inc.; Washington Demilitarization Company/URS; Parsons; and Battelle Memorial Institute, is the systems contractor selected to design, build, systemize, pilot test, operate and close PCAPP.

OPSEC Complete 09 September 2009

2

Page 3: PCAPP Monthly Status Briefing September09.ppt

Staffing

• Pueblo – 290 (92 local hires)Bechtel Pueblo Team non-manual: 298

• Other locations – 8

Construction Workers:Construction Workers:

• Bechtel direct hire – 223

• Subcontractor personnel – 29

OPSEC Complete 09 September 2009

3

Page 4: PCAPP Monthly Status Briefing September09.ppt

Subcontract Awards Inception to date, as of August 31p , g

OPSEC Complete 09 September 2009

4

Page 5: PCAPP Monthly Status Briefing September09.ppt

Acquisition Awards Status

Subcontracts Materials

FY 2009 Upcoming Request for Proposals

• Piping Equipment and Heat Tracing

• General Painting

• Misc. Construction & Architectural Materials

• Gypsum Drywall• General Painting

• Modular Medical Facility

• Control Support Building

• Gypsum Drywall

• Belt Conveyers

• Pumpspp gArchitectural & Plumbing finish work

• Pipe Supports

OPSEC Complete 09 September 2009

5

Page 6: PCAPP Monthly Status Briefing September09.ppt

Destruction Technology

OPSEC Complete 09 September 2009

6

Page 7: PCAPP Monthly Status Briefing September09.ppt

Construction Status - Complete

Multipurpose building

Energetics service magazine g gcorridor foundation

Underground infrastructure (utilities)

Switch gear foundation pads

Utility building structure

Agent filtration area, filtration stack and pipe rack foundations

Automated guided vehicle corridor –foundation, curbs/piers, structural steel

Tank foundations

OPSEC Complete 09 September 2009

7

Tank foundations

Page 8: PCAPP Monthly Status Briefing September09.ppt

Construction Status – In Progress

Agent Processing Building – misc. platform erection, siding, roofing, HVAC, cable tray, fire protection, process piping, electrical and mechanical equipment, interior masonry walls

Enhanced Reconfiguration Building – structural, misc. steel, explosion containment room wall elevated slab rebar and formwork, munitions & energetic service magazine corridor structural steel

U ili b ildi /b il h bl HVAC Utility building/boiler houses – cable tray, HVAC, electrical equipment, piping and structural steel, stacks

Biotreatment electrical building – excavation, underground conduit and rebar; foundation formwork underground conduit and rebar; foundation formwork

Control Support Building/Entry Control Facility -excavation, rebar, formwork, and underground utilities

Field erected tanks tank erections coatings and insulation Field erected tanks – tank erections, coatings and insulation

Pipe rack – vertical construction, pipe and cable tray

Biotreatment area – pipe rack and brine tank containment

OPSEC Complete 09 September 2009

walls, electrical building

88

Page 9: PCAPP Monthly Status Briefing September09.ppt

PCAPP Site Overview

4

2

3

4

1

Northwestern Corner ‐ Observation Point

1

2

3

Enhanced Reconfiguration Building

Automated Guided Vehicle Corridor

Agent Processing Building

OPSEC Complete 09 September 2009

9

4 Biotreatment Area

Page 10: PCAPP Monthly Status Briefing September09.ppt

Agent Processing Building

Mustard agent will be destroyed in the recently

OPSEC Complete 09 September 2009

Mustard agent will be destroyed in the recently enclosed neutralization bay.

1010

Page 11: PCAPP Monthly Status Briefing September09.ppt

Agent Processing Building

The munitions body storage room (tan building)

OPSEC Complete 09 September 2009

11

y g ( g)is currently under construction.

Page 12: PCAPP Monthly Status Briefing September09.ppt

Enhanced Reconfiguration Building

The munitions service magazine corridor leads the

OPSEC Complete 09 September 2009

12

gway to the Enhanced Reconfiguration Building.

Page 13: PCAPP Monthly Status Briefing September09.ppt

Explosion Containment Rooms

OPSEC Complete 09 September 2009

Over 400 cubic yards of self-consolidating concrete has been placed for the walls of the explosion containment rooms.

13

Page 14: PCAPP Monthly Status Briefing September09.ppt

Automated Guided Vehicle Corridor

Munitions will travel from the Enhanced Reconfiguration

OPSEC Complete 09 September 2009

14

Munitions will travel from the Enhanced Reconfiguration Building to the Agent Processing Building via this corridor.

Page 15: PCAPP Monthly Status Briefing September09.ppt

Biotreatment Area

Work progresses on the utility building switchgear

OPSEC Complete 09 September 2009

15

Work progresses on the utility building switchgear area, shown here in the foreground.

Page 16: PCAPP Monthly Status Briefing September09.ppt

Pueblo Chemical Agent-Destruction Pilot Plant

PCAPP Site Plan

OPSEC Complete 09 September 2009

1616

PCAPP Site Plan

Page 17: PCAPP Monthly Status Briefing September09.ppt

Contact Information

Pueblo Chemical Stockpile Outreach Office

U.S. Army Pueblo Chemical Depot

104 West B Street719-546-0400

Tom Schultz

45825 Highway 96 East719-549-4135

Chuck SpragueTom SchultzPCAPP

Public Affairs Officer

Chuck SpraguePublic Affairs Officer

Ken RoqueBob Kennemer

Community Outreach Manager

qPublic Affairs Specialist

Sandy RomeroBechtel Communications

Manager

OPSEC Complete 09 September 2009

17

g