4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Storm Sewer installation (Line 1000) has started at Village West Parkway. Sanitary Sewer Line E installation is ongoing on east side of France Family Dive. Foundations : Area 3 Field Level – Isolated footing installation is Ongoing and is currently to Column Line 8. Area 4 Mezzanine Level – Excavation for D-Line footing Is ongoing and is currently to Column Line 37. Concrete Flatwork : Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete, Press Level slab on deck is complete. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.23.2010 Re: Wizards Stadium Project Update – Week of 6.21.2010 Field Level Area 3 – Secondary electrical distribution is ongoing behind A-Line Wall. Area 1 – Precast concrete treads and riser installation is ongoing between column lines 32-30. Press Level Area 1 – Concrete placed for Exterior walkway outside of the Upper Suite Lounge. Note the Ceremonial 1 st Column in place.

Construction Update 6-28-2010

Embed Size (px)

Citation preview

Page 1: Construction Update 6-28-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive. Storm Sewer installation

(Line 1000) has started at Village West Parkway.

Sanitary Sewer Line E installation is ongoing on east

side of France Family Dive.

Foundations:

Area 3 Field Level – Isolated footing installation is

Ongoing and is currently to Column Line 8.

Area 4 Mezzanine Level – Excavation for D-Line footing

Is ongoing and is currently to Column Line 37.

Concrete Flatwork:

Area 1 – Mezzanine slab-on deck is complete, Main

Concourse structural slab is complete, Suite Level slab

on deck is complete, Press Level slab on deck is complete.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 6.23.2010

Re: Wizards Stadium Project

Update – Week of

6.21.2010

Field Level Area 3 – Secondary electrical

distribution is ongoing behind A-Line Wall.

Area 1 – Precast concrete treads and riser

installation is ongoing between column lines

32-30.

Press Level Area 1 – Concrete placed for

Exterior walkway outside of the Upper Suite

Lounge. Note the Ceremonial 1st

Column in

place.

Page 2: Construction Update 6-28-2010

Building the Future

Structural Steel Erection:

Area 1 –Steel Erection in sequence 1-3 is ongoing.

Area 1 – Roof deck installation has started in Sequence 1-4

Underground MEP:

Deep Underground Plumbing installation is ongoing in

Area 3.

Electrical Secondary Distribution is ongoing in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Field Level slab on

grade is ongoing in Area 3.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 1000

will continue. Installation of Sanitary Line E will continue.

Deep Underground Plumbing:

Deep Sanitary installation in Area 3 will continue.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Area 4 Mezzanine Level – Foundation Wall installation will

continue.

Area 1 – Shot of the West Building from the

southeast. Notice the precast risers at the

north end.

Field Level Area 2 – Gang forms being

installed for concrete placement at

southeast corner.

Area 1 – 142’ long Canopy Trusses are

starting to be delivered and staged in the

field.

Page 3: Construction Update 6-28-2010

Building the Future

Concrete Flatwork:

Area 1 Press Level – Concrete placement will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-3 will

continue. Roof decking installation on Sequence 1-4 will

continue.

Delivery of Roof Trusses for sequence 1-7 will continue

throughout the week.

Structural Precast:

Erection of the precast risers in Area 1 will continue.

Underground MEP:

Deep Sanitary installation will continue in Area 3.

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 1 Field Level slab

on grade will continue.

Field Level Area 2 – Shot looking south (from

Press Level Column Line 32) of Area 2.

Field Level Area 3 – Isolated footing

installation is ongoing.

Page 4: Construction Update 6-28-2010

Building the Future

Additional Photos:

Field Level Area 3 – Shot looking south of A-

Line foundation wall. Note openings in wall

for Supporters Section entrance.

Rigging being installed on Canopy truss.

France Family Drive – Storm inlet structure

installed at the west side of France Family

drive.

Area 1 – Shot looking north of the West

Building. Note the curve of the building.

Field Level Area 1 – Shotcrete wall weeps tie

in to storm sewer is ongoing.

Press Level Area 1 – Roof Deck installation

has started in Sequence 1-4.