Upload
kansas-city-wizards
View
582
Download
1
Tags:
Embed Size (px)
Citation preview
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive. Storm Sewer installation
(Line 1000) has started at Village West Parkway.
Sanitary Sewer Line E installation is ongoing on east
side of France Family Dive.
Foundations:
Area 3 Field Level – Isolated footing installation is
Ongoing and is currently to Column Line 8.
Area 4 Mezzanine Level – Excavation for D-Line footing
Is ongoing and is currently to Column Line 37.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete, Press Level slab on deck is complete.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 6.23.2010
Re: Wizards Stadium Project
Update – Week of
6.21.2010
Field Level Area 3 – Secondary electrical
distribution is ongoing behind A-Line Wall.
Area 1 – Precast concrete treads and riser
installation is ongoing between column lines
32-30.
Press Level Area 1 – Concrete placed for
Exterior walkway outside of the Upper Suite
Lounge. Note the Ceremonial 1st
Column in
place.
Building the Future
Structural Steel Erection:
Area 1 –Steel Erection in sequence 1-3 is ongoing.
Area 1 – Roof deck installation has started in Sequence 1-4
Underground MEP:
Deep Underground Plumbing installation is ongoing in
Area 3.
Electrical Secondary Distribution is ongoing in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Field Level slab on
grade is ongoing in Area 3.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 1000
will continue. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue.
Area 1 – Shot of the West Building from the
southeast. Notice the precast risers at the
north end.
Field Level Area 2 – Gang forms being
installed for concrete placement at
southeast corner.
Area 1 – 142’ long Canopy Trusses are
starting to be delivered and staged in the
field.
Building the Future
Concrete Flatwork:
Area 1 Press Level – Concrete placement will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
continue. Roof decking installation on Sequence 1-4 will
continue.
Delivery of Roof Trusses for sequence 1-7 will continue
throughout the week.
Structural Precast:
Erection of the precast risers in Area 1 will continue.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue.
Field Level Area 2 – Shot looking south (from
Press Level Column Line 32) of Area 2.
Field Level Area 3 – Isolated footing
installation is ongoing.
Building the Future
Additional Photos:
Field Level Area 3 – Shot looking south of A-
Line foundation wall. Note openings in wall
for Supporters Section entrance.
Rigging being installed on Canopy truss.
France Family Drive – Storm inlet structure
installed at the west side of France Family
drive.
Area 1 – Shot looking north of the West
Building. Note the curve of the building.
Field Level Area 1 – Shotcrete wall weeps tie
in to storm sewer is ongoing.
Press Level Area 1 – Roof Deck installation
has started in Sequence 1-4.