3
Building the Future Current Activities this Week : Mass Excavation : Mass Excavation Activities are ongoing in Area 3. Clarkson is continuing with backfilling On-Grade Seating Walls, Rock Excavation, and getting to grade. Site Utilities : Installation of the new electrical ductbank will continue this week. Installation of North Sanitary Manhole is ongoing. Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations : Area 2 Field Level – Footing installation on North Stage Footing has started. Area 1 Mezzanine Level – Installation of Elevator Pit Floor At Elevators 3/4 has started. Area 2 Concourse Level – Installation of 30” Drilled Piers at South East Restroom are complete. Soil Nail Wall : Area 2 – Shotcrete installation on final lift is ongoing. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 4/28/2010 Re: Wizards Stadium Project Update – Week of 4/26/2010 Mezzanine Level Area 1 – Backfill at D-Line Wall nearly complete at VIP Entrance. Concourse Level Area 2 – Drilled Pier at south restroom are complete (Column Lines 13.5 17). Mezzanine Level Area 1 – Sanitary Manhole installation is ongoing along Village West Parkway.

Construction Update 4-28-2010

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Construction Update 4-28-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Mass Excavation Activities are ongoing in Area 3.

Clarkson is continuing with backfilling On-Grade Seating

Walls, Rock Excavation, and getting to grade.

Site Utilities:

Installation of the new electrical ductbank will continue

this week.

Installation of North Sanitary Manhole is ongoing.

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Foundations:

Area 2 Field Level – Footing installation on North Stage

Footing has started.

Area 1 Mezzanine Level – Installation of Elevator Pit Floor

At Elevators 3/4 has started.

Area 2 Concourse Level – Installation of 30” Drilled Piers

at South East Restroom are complete.

Soil Nail Wall:

Area 2 – Shotcrete installation on final lift is ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 4/28/2010

Re: Wizards Stadium Project

Update – Week of

4/26/2010

Mezzanine Level Area 1 – Backfill at D-Line

Wall nearly complete at VIP Entrance.

Concourse Level Area 2 – Drilled Pier at

south restroom are complete (Column Lines

13.5 – 17).

Mezzanine Level Area 1 – Sanitary Manhole

installation is ongoing along Village West

Parkway.

Page 2: Construction Update 4-28-2010

Building the Future

Structural Steel Erection:

Field Bowl – Structural Steel Erection is ongoing between

Column Lines 28 – 31 and between Column Lines D – C.

Deep Underground Plumbing:

Sanitary piping is complete to Column Line 20.

Underground Electrical:

Secondary service ducts is complete from Electrical Room

01.34.04 south past Column Line 27.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling on-grade seating walls will continue is Area 1

and Grading will continue in Area 3.

Site Utilities:

Installation of Sanitary Manhole at the north end will

continue.

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue.

Deep Underground Plumbing:

Sanitary in Area 2 will continue.

Foundations:

Area 2 Field Level – Placement of foundations at stage

Area will continue.

Area 2 Concourse Level – Foundation installation will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-1 will continue.

Field Level Area 1 – Structural Steel Erection

at West Building continues.

Field Level Area 1 – Shot looking north from

Concourse Level.

Field Level Area 1 – North Field Walls and

Players Bench Area.

Page 3: Construction Update 4-28-2010

Building the Future

Additional Photos:

Mezzanine Level Area 1 – Reinforcing

installed for Elevator 3/4 pit floor.

Area 2 – Shotcrete installation has started

on final lift at South East Corner.

Concourse Level Area 1 – Shot looking north

across Field Club Entrance.

Field Level Area 1 – Gang forms being set at

South West Vomitory.

Area 1 – Shot looking South West showing

West Building Structural Steel. Notice

precast tub seat connections.

Field Level Area 2 – Reinforcing being

installed for stage footings (Column Lines

18.5 – 15).