Building the Future
Current Activities this Week:
Mass Excavation:
Mass Excavation Activities are ongoing in Area 3.
Clarkson is continuing with backfilling On-Grade Seating
Walls, Rock Excavation, and getting to grade.
Site Utilities:
Installation of the new electrical ductbank will continue
this week.
Installation of North Sanitary Manhole is ongoing.
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Foundations:
Area 2 Field Level – Footing installation on North Stage
Footing has started.
Area 1 Mezzanine Level – Installation of Elevator Pit Floor
At Elevators 3/4 has started.
Area 2 Concourse Level – Installation of 30” Drilled Piers
at South East Restroom are complete.
Soil Nail Wall:
Area 2 – Shotcrete installation on final lift is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 4/28/2010
Re: Wizards Stadium Project
Update – Week of
4/26/2010
Mezzanine Level Area 1 – Backfill at D-Line
Wall nearly complete at VIP Entrance.
Concourse Level Area 2 – Drilled Pier at
south restroom are complete (Column Lines
13.5 – 17).
Mezzanine Level Area 1 – Sanitary Manhole
installation is ongoing along Village West
Parkway.
Building the Future
Structural Steel Erection:
Field Bowl – Structural Steel Erection is ongoing between
Column Lines 28 – 31 and between Column Lines D – C.
Deep Underground Plumbing:
Sanitary piping is complete to Column Line 20.
Underground Electrical:
Secondary service ducts is complete from Electrical Room
01.34.04 south past Column Line 27.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling on-grade seating walls will continue is Area 1
and Grading will continue in Area 3.
Site Utilities:
Installation of Sanitary Manhole at the north end will
continue.
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue.
Deep Underground Plumbing:
Sanitary in Area 2 will continue.
Foundations:
Area 2 Field Level – Placement of foundations at stage
Area will continue.
Area 2 Concourse Level – Foundation installation will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-1 will continue.
Field Level Area 1 – Structural Steel Erection
at West Building continues.
Field Level Area 1 – Shot looking north from
Concourse Level.
Field Level Area 1 – North Field Walls and
Players Bench Area.
Building the Future
Additional Photos:
Mezzanine Level Area 1 – Reinforcing
installed for Elevator 3/4 pit floor.
Area 2 – Shotcrete installation has started
on final lift at South East Corner.
Concourse Level Area 1 – Shot looking north
across Field Club Entrance.
Field Level Area 1 – Gang forms being set at
South West Vomitory.
Area 1 – Shot looking South West showing
West Building Structural Steel. Notice
precast tub seat connections.
Field Level Area 2 – Reinforcing being
installed for stage footings (Column Lines
18.5 – 15).