16
By Jay Adams CEG CORRESPONDENT They didn’t have to find Nemo. Nemo found them. Hundreds, if not thou- sands, of contractors were temporarily hired by state DOTs and municipalities as private vendors in the states of Connecticut, Rhode Island and Massachusetts, among other New England states, to dig out from the worst single snowstorm to hit the area in 40 years. During the 30 or so hours that the storm raged over Feb. 8 and 9, pay loaders, dump trucks, front loaders and other snow-clearing vehicles were comman- deered by the hardest-hit cities and states on tempo- rary contracts to remove the snow that in some areas came in record-breaking amounts. Governors imposed driv- ing bans for two days and the only vehicles allowed on roads were those sporting plows. Commuter traffic was ordered stalled in order that the plows and other heavy iron could drive snow off highways to clear paths for emergency vehicles, police, fire, ambulance and especially power companies to restore energy to hundreds of thousands of New Englanders who lost it; some — like in Marion, Mass. and the Cape — for up to six days. DOTS and state governments were lauded, for the most part, for their plowing plans which worked quickly, due in large part to the hard work of the private vendors who were regular guys with plows. 40-Plus Inches of Snow While thousands of New England towns and cities were buried, Hamden, Conn., was one of the hard- est hit in the blizzard of 2013, seeing an astonishing 40-plus inches of snow. Hamden also is the town Sweeney Excavation Inc. has been headquartered for 26-plus years. Sweeney was ready. “Immediately following the storm, we placed four pay loaders with the town of Hamden and soon after dis- patched two tri-axle dump trucks to assist with moving the snow from the streets to the parks throughout the town where we piled the snow,” said Bob Sweeney, owner of Sweeney Excavation. “These loca- tions became known as snow farms.” Hamden collectively hired 30 to 40 pay loaders from private contractors and received additional assis- tance from the National Guard. “The first task after the storm was to simply open all roads in town to allow two-way traffic. Once done, the roads were then opened up from curb to curb, which exposed drainage structures and allowed melting snow to run off into drainage systems,” added Sweeney. “Where snow needed to be removed to accomplish this, it was loaded onto dump trucks and taken to the snow farms. “Our loaders and trucks worked 24-hour cycles starting on Feb. 11 and ending at noon on Feb. 17. Collectively, we State DOTs Hire Influx of Contractors to Dig States Out of Snowstorm Nemo THE NEW ENGLAND EDITION A Supplement to: Your New England States Connection • Kent Hogeboom 1-800-988-1203 “The Nation’s Best Read Construction Newspaper… Founded in 1957.” 1 1 1 11 2 16 201 3 9 1 95 95 495 95 9 16 3 26 2 202 89 93 93 95 2 7 4 7 2 89 89 91 91 3 7 2 2 6 90 90 495 95 93 195 95 6 95 7 6 395 95 84 91 91 84 95 E q u I P M E N T g u I D E FormErly March 27 2013 Vol. XlIX • No. 7 ® Hamden collectively hired 30 to 40 pay loaders from private contractors and received additional assis- tance from the National Guard. see NEMO page 4 Other Screeners Available ArguS INDuSTrIAl CO. www.ez-screen.com 866-745-5828 6’x5’ Screenbox Works with 1/2 to 1 3/4 Yd. Loaders, 25 H.P. Kohler Diesel Engine, 24” Conveyor Dumps Screened Product 9’ High $39,500 plus freight. 2013 EZ-Screen 1200XL New Option Separate 3 Products Kraft Power Corporation Perkins Master Service Dealer NJ, MA & NY Engines, Parts & Service 800-969-6121 www.kraftpower.com Authorized Deutz Distributor Kraft Power Corporation Engines, Parts & Service 800-969-6121 Woburn, MA & Syracuse, NY Auctioneering & Liquidation ITL Auctioneering www.itlauctions.us Justin Lyerla (508) 824-3262 WANTS YOUR HAMMER REPAIR CALL 888-81-GORILLA (46745) WE STOCK RUBBER TRACKS for Over 2,500 Models! Some Used Tracks Available. GUARANTEED TO FIT HIGH QUALITY FAST SHIPPING 888-888-1248 BEST PRICES! WANTED 603-595-2090 CATERPILLAR EQUIPMENT Call Lou Giza www.foleyengines.com

NewEngland #7,2013

Embed Size (px)

DESCRIPTION

NewEngland #7,2013

Citation preview

Page 1: NewEngland #7,2013

By Jay AdamsCEG CORRESPONDENT

They didn’t have to findNemo. Nemo found them.Hundreds, if not thou-

sands, of contractors weretemporarily hired by stateDOTs and municipalities asprivate vendors in the statesof Connecticut, RhodeIsland and Massachusetts,among other New Englandstates, to dig out from theworst single snowstorm tohit the area in 40 years.During the 30 or so hours

that the storm raged overFeb. 8 and 9, pay loaders,dump trucks, front loadersand other snow-clearingvehicles were comman-deered by the hardest-hitcities and states on tempo-rary contracts to remove thesnow that in some areascame in record-breakingamounts.Governors imposed driv-

ing bans for two days and theonly vehicles allowed onroads were those sportingplows. Commuter trafficwas ordered stalled in orderthat the plows and otherheavy iron could drive snowoff highways to clear paths for emergency vehicles, police,fire, ambulance and especially power companies to restoreenergy to hundreds of thousands of New Englanders wholost it; some — like in Marion, Mass. and the Cape — for upto six days.DOTS and state governments were lauded, for the most

part, for their plowing plans which worked quickly, due inlarge part to the hard work of the private vendors who wereregular guys with plows.

40-Plus Inches of Snow

While thousands of NewEngland towns and citieswere buried, Hamden,Conn., was one of the hard-est hit in the blizzard of2013, seeing an astonishing40-plus inches of snow.Hamden also is the townSweeney Excavation Inc.has been headquartered for26-plus years. Sweeney wasready.“Immediately following

the storm, we placed fourpay loaders with the town ofHamden and soon after dis-patched two tri-axle dumptrucks to assist with movingthe snow from the streets tothe parks throughout thetown where we piled thesnow,” said Bob Sweeney,owner of SweeneyExcavation. “These loca-tions became known assnow farms.” Hamden collectively

hired 30 to 40 pay loadersfrom private contractors andreceived additional assis-tance from the NationalGuard. “The first task after the

storm was to simply open allroads in town to allow two-way traffic. Once done, the roadswere then opened up from curb to curb, which exposeddrainage structures and allowed melting snow to run off intodrainage systems,” added Sweeney. “Where snow needed tobe removed to accomplish this, it was loaded onto dumptrucks and taken to the snow farms. “Our loaders and trucks worked 24-hour cycles starting on

Feb. 11 and ending at noon on Feb. 17. Collectively, we

State DOTs Hire Influx of Contractorsto Dig States Out of Snowstorm Nemo

THE NEW ENGLAND EDITION A Supplement to:

Your New England States Connection •  Kent Hogeboom 1-800-988-1203

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

1

1

1

11

2

16

201

3

9

1

95

95

495

95

9

16

3

26

2

202

89

93

93 95

2

7

4

7

2

89

89

91

91

37

22

6

90

90

495

9593

195

95

6

95

7

6395

95

8491

91

84

95

E q u I P M E N T g u I D E

F o r m E r l y

March 272013

Vol. XlIX • No.7

®

Hamden collectively hired 30 to 40 pay loaders fromprivate contractors and received additional assis-tance from the National Guard.

see NEMO page 4

Other Screeners AvailableArguS INDuSTrIAl CO.www.ez-screen.com866-745-5828

6’x5’ ScreenboxWorks with 1/2 to 1 3/4Yd. Loaders, 25 H.P.

Kohler Diesel Engine, 24”Conveyor Dumps

Screened Product 9’ High$39,500 plus freight.

2013 EZ-Screen1200XL

New OptionSeparate 3Products

Kraft Power Corporation

Perkins Master Service DealerNJ, MA & NY

Engines, Parts & Service

800-969-6121www.kraftpower.com

AuthorizedDeutz

Distributor

Kraft Power Corporation

Engines, Parts & Service

800-969-6121Woburn, MA & Syracuse, NY

Auctioneering & LiquidationITL Auctioneeringwww.itlauctions.usJustin Lyerla (508) 824-3262

WANTSYOUR

HAMMERREPAIR

CALL888-81-GORILLA

(46745)

WE STOCK RUBBER TRACKS

for Over 2,500 Models!Some Used Tracks Available.

• GUARANTEEDTO FIT

• HIGH QUALITY• FAST SHIPPING

888-888-1248

BEST PRICES!

WANTED

603-595-2090

CATERPILLAREQUIPMENT

Call Lou Giza

www.foleyengines.com

w

Page 2: NewEngland #7,2013

Page 2 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

THE W.I. CLARK COMPANYBrookfield, CT • Wallingford, CT • Plainfield, CT

Call Mark Doty @ 203-823-2316

WHEEL LOADERS2011 DEERE 244J, C/AIR, R/C 3 VALVE HYDS, 1 YD BUCKET WITHHYD CPLR, EXCELLENT CONDITION, STK# 22179 ..............$72,500

2008 DEERE 344J, A/C, RC, 3RD VALVE HYDS, HYD COUPLER, 920HRS, STK#20274 ..................................................................$98,500

2004 DEERE 544J, C/AIR, RC, RADIALS, 3RD VALVE HYDS., JRBCOUPLER, 2.5 YD BUCKET, STK#20904 ............................$121,000

2007 DEERE 544J, C/HEAT, HI-LIFT, 2 FUNCTION HYDS.,STK#21419 ........................................................................$102,000

INTERNATIONAL 530, EX-MUNICIPAL LOADER, 3 YD BUCKET, NEWENGINE AND TRANS APPROX 4 YEARS AGO ......................$17,500

COMPRESSORSIR P185WJD, DEERE POWERED, 90% RUBBER, 2 TO CHOOSEFROM ..............................................................STARTING AT $6,000

DOZER – CRAWLER

1984 DEERE 450D, 6 WAY BLADE, GOOD CONDITION, STK# 21370

..............................................................................................$13,500

2007 DEERE 1050J, A/C, 24" PADS, 159" SEMI-U BLADE, MS RIP-

PER, NEW PAINT, STK#20688 ............................................$315,000

EXCAVATOR – CRAWLER

2004 KOBELCO SK115SRDZ, 9’8” ARM, HYD THUMB, 32” BKT,

BLADE, 24” PADS, LOW HOURS, STK# 21428 ....................$66,500

MOTOR GRADER

1988 DEERE 570B, C/HEAT, 12’ BLADE, FRONT SCARIFIER, 80%

REAR RUBBER, 833 ORIGINAL HOURS, FULLY SERVICED, STK#

21413....................................................................................$65,000

See Our Complete Inventory at www.wiclark.com

1998 Deere 410E

stk# 21372 ..........................$47,500

c/heat, 4x4, stdhoe, 2000 original hours

2007 Deere 50D

stk# 20936 ..........................$42,500

ROPS, 890 hours,hydraulic thumb

IR P185WJD

Starting at 6,000

Deere powered,90% rubber, 3 tochoose from

Deere 450D

stk# 21370 ............................$13,500

ROPS, 6 wayblade, 2240 original hours

2006 Deere 544J

stk# 21348 ........................$127,500

A/C, RC, 3rdvalve hyds, JRBhyd cplr and 3yd bucket

2008 Deere 524K

stk# 20889 ........................$110,500

c/air, hi lift, hi- vis hyd coupler w/2.75yd bucket, radials

2004 Hitachi ZX270LC

stk#21442 ..........................$126,000

c/air, 10' 8" arm,42" pin on bucket

1988 Deere 570B

stk# 21413 ..........................$65,000

c/heat, 12’ blade,front scarifier,80% rubber, 833 originalhours

2006 Deere 250D

stk# 20949 ........................$146,500

25 ton haul truck,c, air, 80% radials, tailgate,great condition

2009 Carlson CP-90

stk# 20713 ........................$110,500

Cat engine, 8-15’electric screed,416 demo hours,excellent condition

2011 Deere 270DLC

stk# 20958 ........................$189,000

c/air, 10' 6" arm,54" bucket

2003 New Holland LS180

stk# 21417 ............................$24,000

c/heat, gp buck-et, 80% rubber,great snowmachine

Page 3: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 3

Volvo Construction Equipment

MASSACHUSETTS

251 Shaker Road, East Meadow, MA 01028

Direct: 413-525-6351

Toll Free: 800-292-6351

Parts Direct: 877-255-6351

www.tylerequipment.com

CONNECTICUT

1980 Berlin Turnpike, Berlin, CT 06037

Direct: 860-356-0840

Toll Free: 800-352-4473

Parts Direct: 860-356-0848

www.tylerequipment.com

2005 VOLVO EC240B LC, Stk #: 12231, S/N: 11777,3900 Hrs, This unit is in our East Longmeadowoffice. Call 1-800-352-4473 ........................$97,500

2006 INGERSOLL-RAND DD90HF, Stk #: 8650,S/N: 190361X, 1250 Hours, 66” Drum, WorkLights, Cummins Diesel ..............................$57,000

2002 VOLVO EC35, S/N: 28314849, 3475 Hrs, 2002VOLVO MINI-EXCAVATOR, Call 1-800-352-4473 formore information! ......................................$25,000

2007 INGERSOLL RAND DD90HF, Stk #: 8333,1200 Hrs, 66” Drums, Cummins Diesel Eng., WorkLights, ROPS Lights and Strobe ................$57,000

2010 VOLVO HB1100, Hyd. 2300 ft/lb hammer,w/S6 Manufacturer Plate, New Hoses Chisel Point.6 Month Mgf. Warranty ..............................$33,500

2006 VOLVO EC460B LC, S/N: 80090, 7420 Hrs,Many New Parts; Track Chains, Sprockets, etc.READY TO WORK! ....................................$156,000

2008 MSD250R Shear, S/N: 626034, Full Rebuilt by Genesis in 2012, 0 Cycles, BracketFits Most Brands w/a Bushing & Pin Kit, FOB Superior, WI ..............................$136,500

2005 SENNEBOGEN 850M, S/N: 850.0.149, 0 Hrs on Brand New Boom! ........$295,000

ATTACHMENTS

EXCAVATORS

1992 MORBARK 290, S/N: 8061, 2194 hours ......................................................$6,000

1990 OLATHE 986, #11957, 2309 Hrs, 12” Brush Chipper has Ford Diesel Engine andall the Parts and Service Manuals, Call Tom Tyler, VP at 203-509-0967................$6,000

CHIPPERS

Page 4: NewEngland #7,2013

Page 4 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

worked approximately 1,000-man hoursin that time span not including the hoursworked by managers, fuelers and mechan-ics,” said Sweeney.

The largest challenges vendors likeSweeney faced included getting operatorsplugged into shifts to allow for 24-hour,round-the-clock service to which privatevendors are not accustomed.

“We kept the loaders out moving on theroads. Each new crew of operators report-ed to our shop, we drove those operatorsto the pay loaders to swap out with theprevious shift and then drove that off-dutycrew back to our shop. We had staff tocycle to every loader to deliver fuel andgrease every eight hours,” he said. “Eachloader had three eight-hour shifts; there-fore, we had 12 operators for four payloaders. Tri-axles worked two 12-hourshifts, so we had four drivers for twodump trucks. We had one supervisor and one mechanic/fuel-er on every eight-hour shift. Therefore, it took 22 people tocomplete one 24-hour day,” he added.

Other Blizzard ChallengesCommunication also was a challenge. Officials in towns

like Hamden were trying to direct this large workforce to allsections of their communities, but they were not able to eas-

ily speak with the 40 private pay loader operators. Evenmore challenging was that a large majority of Hamden’shired contractors were from out of town and even out ofstate.

“These operators did not know the streets or how to get[to] the streets at which they were needed,” said Sweeney.

After some initial clearing to get major roads opened, thetown made a decision to send two loaders with each of their

plow trucks to the specified routes that the local plow truckdrivers knew very well. Plow truck drivers would then directthe loaders under their supervision. They were in constantcommunication with the Hamden Public Works main officeto monitor progress, setbacks and challenges.

“Personally, I found this to be a great solution to the prob-lems the town was facing at that point. Hamden has somegreat representation in Public Works, employees such asMike Siciliano, David Lockery and Joe Callella. These threesupervisors, as well as the countless town-employed driversand operators, really made a Herculean effort and rose to thechallenges in front of them, during some extremely difficultand stressful moments,” said Sweeney.

Little Rhody, Big StormRhode Island employed 400 private vendors during

Nemo, joining 150 state employees working the roads andhighways. The state used 100 DOT plow trucks, five loadersand other vehicles at 21 snow stockpile sites that wereopened to accommodate the untold tons of cleared snow.

The stockpiles were located in the state’s seven mainte-nance districts — Northwest, Providence, Bristol, Newport,Kent, Washington North and Washington South.

“There were other vendors [hired], also,” said HeidiGudmunson of the RIDOT Communications division. “Wehad a heavy tow plan in place, meaning four tractor trailer-sized tow trucks [otherwise known as heavy wreckers] werepositioned around the state readily available to help, as need-ed. We also had tree trimming vendors mobilized throughoutthe storm, to clear the way for plows etc., as necessary.

“The state DOT also had four front-end loaders to help digout emergency shelters, park and ride [bus stops], highwaydrifts, etc.,” added Gudmunson.

Blizzard Challenges Include Round-The-Clock ServiceNEMO from page 1

see NEMO page 11

For advertising rates: Contact Edwin M. McKeon Jr.

215/885-2900Toll Free 800/523-2200

Fax 215/885-2910

e-mail [email protected]

Contact Kent Hogeboom

• New York • New England

315/823-7668Toll Free 800/988-1203

Fax 315/823-4136

e-mail [email protected]

Construction Equipment Guide NortheastEdition (ISSN 1081-7034) is published bi-weekly by Construction Equipment GuideLtd. Advertising and Editorial Offices arelocated at 470 Maryland Dr., Ft. Washington, PA 19034. Toll Free800/523-2200 or Fax 215/885-2910.Annual Subscription Rate $65.00. Call forCanadian and foreign rates.

Periodicals postage paid at Ft. Washington,PA and at additional mailing offices. POSTMASTER: Send address changes toConstruction Equipment Guide NortheastEdition, 470 Maryland Dr, Ft. Washington,PA 19034.

Contents Copyrighted ©2013, byConstruction Equipment Guide, which is aRegistered Trademark, registered in the U.S.Patent Office. Registration number0957323. All rights reserved, nothing maybe reprinted or reproduced(including framing) in whole or part without writtenpermission from the publisher. All editorialmaterial, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publicationand copyright purposes and are subject toConstruction Equipment Guide's unrestrictedright to edit and comment editorially.Contributor articles do not necessarily reflectthe policy or opinions of this publication.

Call or write for advertising rates, publica-tion schedule and media kit. TheConstruction Equipment Guide is not respon-sible for clerical or printer's errors, everycare is taken to avoid mistakes.Photographs of equipment used in adver-tisements are not necessarily actual photo-graphs of the specific machine. Similar pho-tographs are used occasionally and everyeffort is taken to depict the actual equip-ment advertised. The right is reserved toreject any advertising.

Founder, Publisher & CEO Edwin M. McKeon Sr.

Northeast Publisher Edwin M. McKeon Jr.Editor In Chief Craig Mongeau

Associate Editor Christine RecknerEditorial Consultant Pete Sigmund

Production Mgr. John Pinkerton Controller Tom Weinmann

Circulation Mgr. Rolf Krog Asst. Circulation Mgr. Cathy Printz

Main office 470 Maryland Drive Fort Washington, PA 19034

215/885-2900 Toll Free 800/523-2200

Fax 215/885-2910

Web site www.constructionequipmentguide.comEditorial e-mail [email protected]

Advertising e-mail [email protected]

NEW ENGLAND EDITION

Private vendor loaders and dump trucks spent endless hours clearingsnow in hard-hit ares of New England. The coordination of all the ven-dors, not normally on 24-hour duty, was a challenge handled well by allinvolved.

Hundreds, if not thousands, of contractors were tem-porarily hired by state DOTs and municipalities asprivate vendors in the states of Connecticut, RhodeIsland and Massachusetts, among other New Englandstates, to dig out from the worst single snowstorm tohit the area in 40 years.

Page 5: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 5

Sales • Parts • Service • Rentals226 Selleck St. Suite C • Stamford, CT 06902

(203) 569-0339

“The RM60 crusher has been thebest investment that I have made

for my asphalt manufacturing plant.The low ownership costs, ease of

operation and consistent productionin both RAP & recycled aggregatesmakes the RM60 stand out. Day inand day out the RM60 gives me thehighest quality material that is usedin our daily productions. I have alsoreceived outstanding support from

our dealer and factory.

Jeff JoaquinPawtucket Asphalt, Pawtucket, RI

See Jeff and theRM crusher atthe World ofAsphalt Show booth #2955 inSan Antonio, TX

Chadwick-BaRoss, Inc.15 Katrina Road • Chelmsford, Massachusetts

(800) 804-0775 • (978) 256-9571Fax: (978) 256-8802

www.chadwick-baross.com • www.cbused.com

A STRONGCO Company

Page 6: NewEngland #7,2013

Page 6 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

The Maine Department of Transportation received bids fortransportation-related improvement projects.Following is a list of some of the projects let.

County: WaldoContract ID: 016350.00Location: Stockton Springs.Project:New and upgraded sidewalks and drainageimprovements.Contractors and Bid Amounts:

• R F Jordan & Sons Construction Inc. — $561,916• Gary M Pomeroy Logging Inc. — $573,908• Gardner Construction Enterprises LLC — $575,495• Maine Earth — $577,357• R A Paradis & Son — $645,000• Sargent Corporation — $679,889• Pratt & Sons Inc. — $684,883• Sitewerx — $689,800• Farley & Son Inc. – $706,777• CPM Constructors — $717,077• T. Buck Construction Inc. — $795,500• Lane Construction Corporation (The) — $884,991• Hughes Brothers Inc. — $898,100

County: OxfordContract ID: 019292.00Location: Bog Brook Bridge.Project: Bridge replacement.Contractors and Bid Amounts:

• Nelson Communications Services Inc. — $334,302• Wyman & Simpson Inc. — $369,533• K & K Excavation Inc. — $383,963• N F Luce Inc. — $399,961• T. Buck Construction Inc. — $420,400• CPM Constructors — $430,933• E L Vining & Son Inc. — $458,238• McGee Construction — Irregular

County: WaldoContract ID: 017532.00Location: Frankfort.Project: Strut replacement.Contractors and Bid Amounts:

• Gardner Construction Enterprises LLC — $229,525• Maine Earth — $231,798• CPM Constructors — $253,800• Sargent Corporation — $253,807• Farley & Son Inc. — $256,926• R F Jordan & Sons Construction Inc. — $258,955• Wyman & Simpson Inc. — $264,609• N F Luce Inc. — $284,674• Stetson & Watson J. V. — $288,081• Sitewerx — $297,690• Bowman Constructors — $299,180• T. Buck Construction Inc. — $312,312• Lane Construction Corporation (The) — $313,978• Hughes Brothers Inc. — $319,994

County: AroostookContract ID: 019322.00Location: Island Falls.

Project: Bridge scour counter measures.Contractors and Bid Amounts:

• Gardner Construction Enterprises LLC — $434,361• Sargent Corporation — $565,297• T. Buck Construction Inc. — $588,123• Wyman & Simpson Inc. — $594,535• CPM Constructors — $672,527

County: CumberlandContract ID: 012757.00Location: Standish.Project: Intersection reconstruction.Contractors and Bid Amounts:

• Shaw Brothers Construction Inc. — $497,793• Shaw Earthworks — $524,699• Peters Construction Inc. — $528,086• Brown Industrial Group Inc. — $543,080• Gendron & Gendron Inc. — $559,999• Pratt & Sons Inc. — $572,122• A H Grover Inc. — $588,520• R. J. Grondin & Sons — $606,948• T. Buck Construction Inc. — $686,197• CPM Constructors — $695,566

County: PenobscotContract ID: 018320.00Location: Bangor and Brewer (Joshua ChamberlainBridge).Project: Bridge painting.Contractors and Bid Amounts:

• Olympus Painting Contractors Inc. — $2,147,353• Gulf Coast Contracting LLC — $2,870,999• Blastech Enterprises Inc. — $3,041,442

• Panther Industrial Painting LLC — $3,596,939• Atlas Painting & Sheeting Corporation — $3,939,000• Abhe & Svoboda Inc. — $4,158,240• Odyssey Contracting Corporation — $4,236,915• Spartan Contracting LLC — $4,277,000• Vimas Painting Company Inc. — $4,336,505• North Star Painting — $4,737,872

County: HancockContract ID: 017258.00Location: Blue Hill.Project:New roundabout.Contractors and Bid Amounts:

• R F Jordan & Sons Construction Inc. — $843,047• Maine Earth — $883,724• Sargent Corporation — $940,028• Lane Construction Corporation (The) — $954,822• T. Buck Construction Inc. — $999,300• CPM Constructors — $1,023,245• Pike Industries Inc. — $1,342,105

County: PiscataquisContract ID: 019306.00Location:Abbot.Project: Bridge rehabilitation.Contractors and Bid Amounts:

• T. Buck Construction Inc. — $1,319,688• Reed & Reed Inc. — $1,396,298• Wyman & Simpson Inc. — $1,514,477• CPM Constructors — $1,582,639• Technical Construction Inc. — $1,762,433• Lane Construction Corporation (The) — $2,078,971• New England Infrastructure Inc. — $2,794,446

Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc• Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford• Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York • Androscoggin • Aroostook • Cumberland • Franklin •Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc • Somerset • Waldo • Washington • York •Androscoggin • Aroostook • Cumberland • Franklin • Hancock • Kennebec • Knox • Lincoln • Oxford • Penobscot • Piscataquis • Sagadahoc

Maine...

‘Pine Tree State’ Highway Projects Let

Page 7: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 7

The N.i.c.e. CompanyNortheast International Construction Equipment Co., Inc.

“Your Newest Source for Quality Equipment”

Now Off 495 in Franklin!!! 76 Grove St., Franklin, MA

Call Bryn Smith at: 508-966-4888Fax: 508-966-4887

Email: [email protected]

See all of my machines atwww.thenicecompany.com

2008JD160D,QC, HydThumb,2600 Hrs,REDUCED$99,000

2009 Cat336DL,12’10”Stick, 6000 Hrs$169,000

2006 Cat930G,3300 Hrs,QC Nice!$89,000

2009 Cat315DL,VERYNICE!!,2200 Hrs,Plumbed$119,000

I Buy Machines

1999 Cat950G,Runs Good,CommandControl,16K Hrs$49,000

Cat 420DIT,Very NiceMachine!$38,500

Also inStock:420E &420EIT

2008KomatsuD51,EROPS,Very Nice!Only$99,000

2008DoosanDL200Loader,Only 1000Hrs!Only$79,000!

2006 TerexTXC300-2,LongReach,3300 Hrs$99,000

2008 VolvoECR88,QC, TiltingBucket,RotatingGrapple,2600 Hrs$59,000

800-269-6520 • www.petersoncorp.com • PO BOX 40490 • Eugene, OR 97404

Maximum Output

At the lowest

cost perton!

A At t h e

c

At At t h e lowwewestt

c o st st p e r

C l e a n C B i o m a

ton! C h i p s . M i c r o c hs s s. L a n d C l e a r i

h i p s . i n g .

F o r 3 0 c h i p p e

wwwwwww.p

y e a r s s, P e t te r rson o e r s h av v e l e d t th

pettersoncorp.c

o n e

com

800-269-6520 • www.petersoncorp.com • PO BOX 40490 • Eugene, OR 97404

800-269-6520 • www.petersoncorp.com • PO BOX 40490 • Eugene, OR 97404

PH: 508.949.000530 Birch Island Road, Webster, MA

800-269-6520 • www.petersoncorp.com • PO BOX 40490 • Eugene, OR 97404

www.barryequipment.comPH: 508.949.000530 Birch Island Road, Webster, MA

y q p

www.barryequipment.com

Page 8: NewEngland #7,2013

Page 8 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

The New Hampshire State Department of Transportationreceived bids for transportation-related improvementprojects.Following is a list of some of the projects let.

Counties: Rockingham and StraffordProject: Resurfacing District VI 16166B and Strafford25124.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Pike Industries Inc. — $1,676,880• Continental Paving Inc. — $1,751,112• Brox Industries Inc. — $1,947,175

Scheduled Completion Date: Sept. 27, 2013

Counties: Hillsborough, Merrimack and RockinghamProject: Resurfacing District V 16165B, Canterbury25561.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Continental Paving Inc. — $1,879,525• Pike Industries Inc. — $2,183,375• Brox Industries Inc. — $2,271,352

Scheduled Completion Date: Sept. 27, 2013

Counties: Cheshire and HillsboroughProject: Resurfacing District IV 16164B and Rindge24944.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Continental Paving Inc. — $1,604,537• Frank W. Whitcomb Construction Corporation —

$1,723,445• Brox Industries Inc. — $1,725,700• Pike Industries Inc. — $1,726,362• The Lane Construction Corporation — $1,954,465

Scheduled Completion Date:Aug. 23, 2013

Counties: Belknap, Carroll and GraftonProject: Resurfacing District III, 16163B Sanbornton,25616.Scope of Work: Roadway rehabilitation.Location:N/A.Contractors and Bid Amounts:

• Pike Industries Inc. — $1,854,820• Continental Paving Inc. — $1,918,690

Scheduled Completion Date:Aug. 23, 2013

Counties: Coos and GraftonProject: Resurfacing District I, 16161B Easton, 24037 andMilan, 25522.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Pike Industries Inc. — $2,121,118

• Continental Paving Inc. — $2,130,100Scheduled Completion Date: Sept. 13, 2013

County: StraffordProject:Dover 16448.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Continental Paving Inc. — $2,476,341• Pike Industries Inc. — $2,543,125• Brox Industries Inc. — $2,642,179

Scheduled Completion Date: Sept. 13, 2013

Counties: Hillsborough and MerrimackProject: Central turnpike resurfacing 16446.Scope of Work: Roadway resurfacing.Location:N/A.Contractors and Bid Amounts:

• Continental Paving Inc. — $4,105,271• Pike Industries Inc. — $4,645,523• Brox Industries Inc. — $5,045,692

Scheduled Completion Date: Sept. 13, 2013

County: HillsboroughProject: Bedford 16447.Scope of Work:Median box guardrail replacement.Location: F.E. Everett Turnpike in Beford.Contractors and Bid Amounts:

• F.L. Merrill Construction Inc. — $924,897• R.S. Audley Inc. — $924,900• Northeast Earth Mechanics Inc. — $1,047,851• Weaver Bros. Construction Company Inc. —

$1,053,867• CPM Constructors — $1,099,972• R.M. Piper Inc. — $1,169,227

• New England Infrastructure Inc. — $1,179,252Scheduled Completion Date:Aug. 9, 2013

Counties: Belknap and CarrollProject: Statewide X-A001(284), 16416.Scope of Work: Sign upgrading.Location:N/A.Contractors and Bid Amounts:

• American Flagging and Traffic Control Inc. —$232,499

• CPM Constructors — $271,242• Liddell Brothers Inc. — $311,842• Roadsafe Traffic Systems Inc. — $323,442• Nelson Communications Services Inc. — $330,108

Scheduled Completion Date:Aug. 23, 2013

Counties: Grafton and CaledoniaProject: Littleton, N.H.-Waterford, Vt. A001(041), 15926and A001(217), 16195.Scope of Work: Bridge rehabilitation.Location: I-93 northbound and southbound over theConnecticut River.Contractors and Bid Amounts:

• Reed & Reed Inc. — $8,189,764• SPS New England Inc. — $8,369,832• Northern Construction Service LLC — $ 8,975,912• Beck & Bellucci Inc. — $8,981,079• E.D. Swett Inc. — $8,998,825• CPM Constructors — $9,161,725• J.P. Sicard Inc. — $9,646,277• R.M. Piper Inc. — $10,473,840• Winterset Inc. — $11,401,366• MIG Corporation Inc. — $11,968,160

Scheduled Completion Date:Oct. 31, 2014

Hillsborough • Rockingham • Cheshire • Merrimack • Coos • Grafton • Sullivan • Carroll • Belknap •Strafford • Hillsborough • Rockingham• Cheshire • Merrimack • Coos • Grafton • Sullivan • Carroll • Belknap •Strafford • Hillsborough • Rockingham • Cheshire • Merrimack •Coos • Grafton • Sullivan • Carroll • Belknap •Strafford • Hillsborough • Rockingham • Cheshire • Merrimack • Coos • Grafton • Sullivan •Carroll • Belknap •Strafford • Hillsborough • Rockingham • Cheshire • Merrimack • Coos • Grafton • Sullivan • Carroll • Belknap •Strafford• Hillsborough • Rockingham • Cheshire • Merrimack • Coos • Grafton • Sullivan • Carroll • Belknap •Strafford • Hillsborough • Rockingham

New Hampshire...

‘Granite State’ Highway Projects Let

Page 9: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 9

Buy Proven HighQuality ConstructionEquipment from oneof the World’s LeadingManufacturers andSave $$$$ from

Competitor’s Brands.

Perfect where there is limited space. Yanmar introduced the first

Swing boom excavator, First Rubber tracked

excavator and First Zero Tail Swing excavator.

Crushing andScreening Plants as

well as Keestrack/OMparts in stock.

www.equipmenteast.comSALES • RENTALS • PARTS • SERVICE

Hydraulic Hammers for All YourDemolition Needs.

HEAVY CONSTRUCTION EQUIPMENT

61 Silva Lane Dracut, MA 01826

(978) 454-3320Fax: (978) 454-3325

Besides the eco-friendlysilenced design, which fitsinternational standards to beused in environmentally noisesensitive areas, the Ramfos TFseries hydraulic hammers boast

unbeatable performance. We perform complete hammerrebuilds and have a completeparts inventory in stock at ourfacility for all models of Ramfos

hammers.

550 ft lbs - 15,000 ft lbs available

• Pile Drivers• 360˚ free rotation & 90˚ tiltingrotation of jaw clamp• Tilting structure can easily beattached and detached

Page 10: NewEngland #7,2013

Page 10 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

Hyundai Construction Equipment Americas Inc. hasappointed Pete’s Equipment Sales & Rental as an authorizedHyundai dealer. Pete’s Equipment will provide sales andservice of Hyundai equipment from its Morrisville, Vt., loca-tion.“We are proud to be able to offer the complete Hyundai

line of equipment,” said Pete Couture, president of Pete’sEquipment Sales & Rental. “Hyundai manufactures qualityequipment that lasts and with more standard features, it’seasy for us to recommend their machines to our customers.”Established in 1974, Pete’s Equipment is a family-owned

business, serving the Newport, St. Johnsbury, Barre andBurlington areas. The company prides itself on being dedi-cated to its customers while providing sales and rental oftractors, loaders, skid steers, dozers, excavators, chippers,telehandlers, backhoes and light towers as well as attach-ments and implements. Pete’s Equipment also has an expe-rienced parts and service staff to keep their customer’smachines up and running, according to the company. Pete’s Equipment will now carry Hyundai’s full line of

construction equipment, which includes wheel loaders,crawler and wheeled excavators, mini-excavators and skidsteer loaders. The full stock of Hyundai equipment will bereadily available for sale or rent.The sales staff has been fully trained in the application,

sales, parts and service of Hyundai Construction Equipmentproducts and offers professional and efficient parts and serv-ice support to its customers.“Pete’s Equipment maintains a strong commitment to its

customers and provides prompt parts and service assistance,which are the exact qualities we are looking for in Hyundaidealers,” said Shane Sirmons, marketing manager ofHyundai Construction Equipment Americas Inc. “We areexcited to welcome Pete’s Equipment to our growing dealernetwork.”For more information, call 866/237-3189.(This story also can be found on Construction Equipment

Guide’s Web site at www.constructionequipmentguide.com.)

Hyundai AppointsPete’s Equipmentas Vermont Dealer

SOMETIMES MY HUMAN DOESN’T WEAR PANTS AT HOME. IT’S A RIOT.

— COLBY adopted 06-18-11

A.T.Office

(508) 865-0400Sales and Rentals

(508) 523-8852www.atequipment.comEquipment, Inc.

81 Worcester Providence Turnpike, Sutton, MA 01590

2008 Cat 345with auxiliary hydraulics,13,000 poundhammer andthumbP.O.R.

2009 YanmarVIO17

300 hours, show-room condition,

auxiliary hydraulics,thumb$18,500

2009 YanmarVIO45

1000 hours, auxiliary hydraulics,

thumb, cab, a/c,hydraulic quick

coupler$39,000

2006 JohnDeere 160CLC

auxiliary hydraulics, 3,500pound hammer,and thumbP.O.R.

1999 Komatsu PC400 w/auxiliary hydraulics,new bottom ..................................................$59,000Rammer E68 hammer completely rebuilt andnot used since the rebuild ............................$21,500Tramac BRH750 hydraulic hammer, 3,000pound completely rebuilt................................$7,5002002 John Deere 250 skid steer w/500 hours,cab, heat, a/c, 6-foot hydraulic snow plow, forks, excellent condition........................................$16,500

2009 YanmarVIO35

1000 hours, auxiliary

hydraulics, quickcoupler, thumb,cab with a/c$34,000

FOR SALE OR RENTALL OF THESE MACHINES AND ATTACHMENTS ARE IN EXCELLENT CONDITIONAND HAVE BEEN MAINTAINED IN OUR RENTAL FLEET AND ARE READY TO GO TOWORK ON YOUR JOB SITETODAY, WHETHER IT BE A PURCHASE OR A RENTAL

*Full Lineof Hydraulic

Hammers Available for Sale or Rent*Hydraulic

Hammer RepairAERIAL LIFTS

Manlifts

GRADALL / LULLSales - Service - Training

Modern EquipmentSales & Rental800-445-4381

AIR COMPRESSORS

Compressors

AIRMAN COMPRESSORS

Eagle Power & Equipment

Montgomeryville PA215/699-587

New Castle DE 302/652-3028

Eagle PA 610/458-7054

ASPHALT EQUIPMENT

Asphalt Rollers

2001 Sakai SW320, 47’’,ROPS, good condition, 3674hours ..........................$11,900.

800-222-8798

Asphalt - Misc.

FOR SALE

Puckett: T-650Gehl: 1438, 1448, 1648, 1649Lee Boy: 8515, (2) 8616, 8000,(3) 1000Blaw Knox: PF200, PF35, 540PSI Maintainer(4) Tri-Axle Trucks(10) Asphalt Rollers(4) TrailersSalsco PaverCat D3 DozerNeal Sealing 550

413-537-1892

COMPACTION EQUIPMENT

Pneumatic Rollers

Vibromax VM115, 125 hp, 83’’drum width, 25,000 lb oper. wt.,low hours. Pictures available ....................................$66,500.

908/625-0697

SCRAPERS

Motor Scrapers

(2) IHC 431 Scrapers, 21 cu ydopen bowls, rebuilt moldboardsnew cutting edges, one hasreconditioned 5th wheel andgooseneck. All work done bydealer, very good condition - putthem to work ........$15,000 Ea.

Call 908-781-2143 or cell; 908-581-4606

Other good used equipmentavailable!

TRAILERS

Drop Deck Trailers

2005 Felling FT-12-12, decjover wheels, 16’ deck, 5’beavertail with ramps ....$4995.

800-222-8798

Trailers - Misc.

NEW & USED TRAILERS

Eagle Power & EquipmentMontgomeryville PA

215/699-5871

New Castle DE 302/652-3028

Eagle PA 610/458-7054

TRUCKS

Bucket Trucks

ELLIOTT BUCKET TRUCKS

Modern EquipmentSales & Rental800/445-4381

Classified Rates: 30 Words or Less for $30.00. EachAdditional Word is 95¢. For just an additional $20 your ad canbe posted on our online searchable database for 30 days.Ad runs for 2 (two) insertions - no changes in second insertion.

PLEASE ENCLOSE PAYMENT WITH ORDER and mail to:470 Maryland Drive• Fort Washington, PA 19034

215/885-2900 • Fax 215/885-2910Toll Free 1-800/523-2200

DISPLAY ADS/CLASSIFIEDS

==============

RENTMACHINES.COM™

==============

============================

CATERPILLAR®

GENIE®

CHALLENGER®

SCREEN MACHINE®

DAILY AND WEEKLYEQUIPMENT RENTALSCLOSE TO YOUR JOB SITE

==============

RENTMACHINES.COM™

==============

============================

CATERPILLAR®

GENIE®

CHALLENGER®

SCREEN MACHINE®

DAILY AND WEEKLYEQUIPMENT RENTALSCLOSE TO YOUR JOB SITE

DAILY AND WEEKLYEQUIPMENT RENTALS

CLOSE TO YOUR JOB SITE

CATERPILLAR®

GENIE®

CHALLENGER®

SCREEN MACHINE®

RENTMACHINES.COM

Page 11: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 11

RIDOT Deploys 3,300 Tons of Sand, 15,000 Tons of SaltThough the smallest state in the

nation, RIDOT deployed some3,300 tons (2,994 t) of sand, alongwith 15,000 tons (13,608 t) of salton the approximately 1,100 linearmi. (1,770 km) or 3,300 lane mi.(5,310 km) of highways that weremaintained during Nemo.The traffic-free roads, mandated

by Gov. Lincoln Chaffee, made thedifference. “The highway restrictions

imposed by the Governor helped,as it enabled our plows get aroundduring the height of the stormwithout the obstacles of passengervehicles and trucks,” Gudmunsonsaid. “Other technologies, such asthe salt brine we used, enabled usto keep the roads cleared faster, aswe didn’t have snow and ice bond-ing to the highways. In addition,having access to the larger equip-ment certainly helped as this wasan extremely powerful storm, withhuge amounts of snow that neededto be moved in order to keep ourhighways clear.”When asked for a list of ven-

dors, or any that deserved specialmention, RIDOT instead praisedthe collective.“Certainly being able to supple-

ment the RIDOT crews with pri-vate vendors was an important partof our overall success in this storm.As you can imagine, with such alarge group of vendors we don’twant to leave anyone out. They allpitched in and responded to the callwhen needed,” said Joseph Baker,administrator of highways andbridges at RIDOT.“The most important thing I can

tell you, however, is that the prideand hard work of our maintenanceemployees should be commend-ed,” added Gudmunson. “Theygave it their all to keep up with thestorm and keep us safe. They aretruly unsung heroes.”

In Massachusetts the CallWent Out

In Massachusetts, when a bliz-zard or major storm hits, a call goesout for assistance from MassDOT. “Typically,” said Michael

Verseckes, head of MassDOT’s

communications office, “Privatecontractors have approximately anhour and 15 minutes to respond.Most respond within a much short-er timeframe than that.”“Between 10 p.m. on Feb. 8 and

4 a.m. on Feb. 9, MassDOT hadapproximately 3,625 pieces ofequipment deployed around thestate. MassDOT has roughly 400pieces of equipment in-house, andaccess to 4,000 pieces of hiredequipment,” Verseckes added.Statewide, MassDOT is respon-

sible for more than 3,000 mi.(4,828 km) of roadway, translatinginto 15,200 lane mi. (24,462 km). “This winter, there have been 12

other storms — most outside of theBoston area — that have requiredsignificant amounts of coordina-tion and effort to clear roads,” saidVerseckes. “Our snow fightingefforts rely heavily on effectivecommunications, and duringstorms that is managed in ourHighway Operations Center(HOC) in South Boston.” HOC staff has access to more

than 850 roadway and security

cameras to detect and monitor traf-fic conditions and crashes. Ininstances of heavy traffic conges-tion or impending weather, theHOC can program approximately400 message boards around theCommonwealth to inform or warndrivers of hazards that are specificto one region or is applicablestatewide. “A travel ban was implemented

that was an effective means todrive home the point that the stormof Feb. 8 and 9 was serious. It alsohelped remind folks that we weregoing to have a continuous around-the-clock effort to keep up with theaccumulation, which would beimproved by having the roads clearof most other vehicular traffic,”said Verseckes.“Subsequent to Feb. 8, we had

crews out around the state continu-ing to clear road shoulders andbreakdown lanes, and in somecases, going over the right travellanes where needed. We had per-sonnel addressing areas where thesnow melt [caused by subsequentrain] may have turned to ice

overnight — with a particularfocus on our on-and-off-ramps,”said Verseckes. The travel ban in both

Massachusetts and Rhode Islandexcluded public safety vehiclesand workers, including contractpersonnel, public works vehicles,contracted vendor vehicles, gov-ernment officials, utility companyvehicles, health care workers andthe news media.

Early Sign Ups for VendorsIn Rhode Island and some other

states, vendors get extra bonusesfor so-called “green” equipmentand accessories which improvestate fuel costs. They also get anearly sign-up bonus, if their equip-ment completes the state registra-tion process by Oct. 26 in prepara-tion for winter storms.Rhode Island also is innovative

in another way, using special roadsalt brine that has greatly improvedhow state roads are treated bothbefore and after snowstorms.This brine, which is much

see NEMO page 14

NEMO from page 4

Place Your Business Card for...

Call now to reserve your space! 800-225-8448* pre-payment required

200 Codman Hill Rd., Boxborough, MA 01719978-429-8666

Hydraulic Cranes 6-365 Ton

Daily & HourlyServices

Fully Insured

3 months $300* only $50 an issue6 months $585* only $45 an issue

1212 months $1040* only $40 an issue

www.astrocrane.com

West Springfield,MA 01089-3850

(413) 788-LUBE

Bijur Automatic Lubrication SystemsVEI Wheel Loader Scales

Lubrication Engineers High Performance Lubricants

Professional Lubrication Management

Page 12: NewEngland #7,2013

Page 12 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

The Rhode Island Department of Transportation receivedbids for transportation-related improvement projects.Following is a list of some of the projects let.

R.I. Contract No.: 2012-CB-083Project:DBP C4 Anthony Road Bridge No 876.Contractors and Bid Amounts:

• Brito’s Landscaping Services LLC — $40,945• Cardi Corporation — $62,492• New England Building & Bridge Company Inc. —

$73,482• HK & S Construction — $74,900• Mas Building & Bridge Inc. — $74,923• J.H. Lynch & Sons — $88,975• Northern Construction Service LLC — $92,685 • Aetna Bridge Company — $113,850• D’ambra Construction Company Inc. — $123,005

R.I. Contract No.: 2012-CH-003Project: Sakonnet Point drainage improvements.Contractors and Bid Amounts:

• East Coast Landscaping & Construction Inc. —$235,310

• HK & S Construction — $247,515• Cardi Corporation — $277,777

R.I. Contract No.: 2012-CH-018Project: Reclamation.Contractors and Bid Amounts:

• Cardi Corporation — $8,199,915• D’ambra Construction Company Inc. — $8,383,000• J.H. Lynch & Sons — $9,280,003

R.I. Contract No.: 2012-CH-101Project: Type II emergency drainage repair Route 1 SB atWoodruff Ave. Narragansett.Contractors and Bid Amounts:

• Cardi Corporation — $146,171• American Site Corporation — $147,000• D’ambra Construction Company Inc. — $179,566• HK & S Construction — $248,860

R.I. Contract No.: 2012-DF-035Project: Statewide bridge scour remediation - Contract 1.Contractors and Bid Amounts:

• Aetna Bridge Company — $463,329• Northern Construction Service LLC — $497,500• HK & S Construction — $774,534• Cardi Corporation — $1,944,010

R.I. Contract No.: 2012-CB-092Project: Improvements to Interstate I-195 pier columncrack sealing repairs.Contractors and Bid Amounts:

• Aetna Bridge Company — $269,516• Cardi Corporation — $368,900

R.I. Contract No.: 2012-CB-078Project:New Providence Viaduct Southbound Bridge No.578.

Contractors and Bid Amounts:• Manafort Brothers Inc. — $66,864,640• Cardi Corporation — $74,869,872• Barletta — $79,952,200

R.I. Contract No.: 2013-CB-025Project:DBP C7 repairs to Jefferson Blvd. South BridgeNo. 634.Contractors and Bid Amounts:

• Cardi Corporation — $1,294,298• Aetna Bridge Company — $1,455,257• New England Building & Bridge Company Inc. —

$1,596,518• John Rocchio Corporation — $1,649,080• Northern Construction Service LLC — $1,849,048.• D’ambra Construction Company Inc. — $2,145,702

R.I. Contract No.: 2013-CH-004Project: I-195 Relocation — Contract 14 (West side citystreets).Contractors and Bid Amounts:

• Cardi Corporation — $12,992,494• D’ambra Construction Company Inc. — $15,450,673• J.H. Lynch & Sons — $18,290,386

R.I. Contract No.: 2012-CT-090Project: Statewide pavement striping — East Bay.Contractors and Bid Amounts:

• Traffic Markings Inc. — $1,954,630

• Roadsafe Traffic Systems Inc. — $1,974,347• Safety Marking Inc. — $2,362,242

R.I. Contract No.: 2013-CB-011Project:DBP C11 repairs to Wakefield Bridge No. 20.Contractors and Bid Amounts:

• J.H. Lynch & Sons — $259,031• New England Building & Bridge Company Inc. —

$265,432• Northern Construction Service LLC — $287,000• John Rocchio Corporation — $290,406• Aetna Bridge Company — $324,303• Cardi Corporation — $349,701• D’ambra Construction Company Inc. — $353,115• Rotha Contracting Company Inc. — $639,933

R.I. Contract No.: 2013-DF-034Project:Hurricane Sandy — repairs to Sachuest PointRoad.Contractors and Bid Amounts:

• Narragansett Improvement Company — $864,000• Northern Construction Service LLC — $873,238• American Site Corporation — $894,000• Cardi Corporation — $1,046,000• HK & S Construction — $1,215,534• D’ambra Construction Company Inc. — $1,333,333• East Coast Landscaping & Construction Inc. — $0• J.H. Lynch & Sons — $1,580,000

Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport •Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence• Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington• Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol •Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent •

Rhode Island...

“The Ocean State” Highway Projects

Page 13: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 13

160 Elm St. Unit 1Walpole, MA 02081

(508) 660-7600Fax: (508) 660-7614

www.lhequip.com

We’ve become attached to your machines.

Ho-Pac ® vibratory compactor/drivers

Rammer® Small Range hydraulic impact hammers

AR Series™ hydraulic impact hammers

Contractor’s Mechanical Grapplematerial and waste handling systems

Hy-Ram® hydraulic impact hammers

All-new AMS Series mobile shears

Rammer® Mid-Range all-new Model 2155 hydraulic impact hammers

© 2013 Allied Construction Products, LLC

We’ve become attached to your machines.

Rammer® Mid-Rangew Model 2155 all-new

impact hydraulic hammers

ve become attached to your machines.

AR Serieshydraulic

ve become attached to your machines.

Rammer® Small Rangeimpact hydraulic

hammers

AR Series™hammersimpact hydraulic

Small Rangeimpact

you can Where

For over 70 years, we’ve dconstruction and demolition industries that demand high performance. Names like Ho-Ram,Hy-Ram®, Rammer, Ho-Pa

Simple, proven design (Our attachments have high resale or trade-in value)Reliable performance (If you purchased an Allied attachment, you’re probably still using it)Superior productivity (Compare AE

performhigh get to go you boom-mounted ance

Products, Construction Allied 70 years, we’ve developed many attachments that are legendary in the

construction and demolition industries that demand high performance. Names like Ho-Ram,, Rammer, Ho-Pac® and Pedestal Breaker System™ are names that equal:

le, proven design (Our attachments have high resale or trade-in value)Reliable performance (If you purchased an Allied attachment, you’re probably

Superior productivity (Compare AEM– formerly CIMA– ratings, our attachments

attachments?boom-mounted

LLCeveloped many attachments that are legendary in the

construction and demolition industries that demand high performance. Names like Ho-Ram,are names that equal:

le, proven design (Our attachments have high resale or trade-in value)Reliable performance (If you purchased an Allied attachment, you’re probably

ratings, our attachments

hammers

hammers

Superior productivity (Compare AEget the job done faster)

And, now Allied adds to that great family background with the Rammerall-new Hy-Ram® hammers. Allied’s attachments don’t take a back seat to any competitor.In particular, our RammerProControl. All of our high performance boom-mounted attachments are supported by themost respected parts and service organization in North America. Customer satisfaction is jobone at Allied. Great products supported by people who know the industry and its customers.To put a high performance Allied attachment on your machine, visit the Tyler EquipmentCorporation location nearest you. We’ve become attached to your machines.

Superior productivity (Compare AEM formerly CIMA ratings, our attachments get the job done faster)ow Allied adds to that great family background with the Rammer

hammers. Allied’s attachments don’t take a back seat to any competitor.particular, our Rammer® product features a long-stroke design, all oil operation

ProControl. All of our high performance boom-mounted attachments are supported by themost respected parts and service organization in North America. Customer satisfaction is jobone at Allied. Great products supported by people who know the industry and its customers.To put a high performance Allied attachment on your machine, visit the Tyler EquipmentCorporation location nearest you. We’ve become attached to your machines.

CorporationEquipment Tyler

ratings, our attachments

ow Allied adds to that great family background with the Rammer®, AR Series™ and hammers. Allied’s attachments don’t take a back seat to any competitor.

product features a long-stroke design, all oil operation andProControl. All of our high performance boom-mounted attachments are supported by themost respected parts and service organization in North America. Customer satisfaction is jobone at Allied. Great products supported by people who know the industry and its customers.To put a high performance Allied attachment on your machine, visit the Tyler EquipmentCorporation location nearest you. We’ve become attached to your machines.

Ho-Pac ® vibratory compactor/drivers

Hy-Ram® hydraulic hammersimpact

Contractor’s Mechanical Grapplesystemshandling waste and material

shearsmobile

systems

MAIN OFFICE:251 Shaker RoadEast Longmeadow, MA 010281-800-292-6351

©

MAIN OFFICE:

2013 Allied ©

251 Shaker RoadEast Longmeadow, MA 010281-800-292-6351

CT LOCATION:1980 Berlin TurnpikeBerlin, CT 060371-800-352-4473

www.tylerequipment.com

CorporationEquipment Tyler

Construction

CT LOCATION:

2013 Allied Products, LLC

1980 Berlin TurnpikeBerlin, CT 060371-800-352-4473

Page 14: NewEngland #7,2013

Page 14 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

Empire Crane’s Zerrillo SellsLoaded Manitex 40124SHL

Empire Crane New England Sales Representative Chester Zerrillo sold a Manitex40124SHL, 40 ton (36 t) boom truck to Rusty Williams of Rig-All Inc., Frankfort, N.Y.The 425 hp (317 kW) Peterbilt 367 chassis has aluminum Alcoa rims, air tanks andrails. (L-R) are Chester Zerrillo, Rusty Williams and Ryan Williams.

Workers Apply Salt Brine DaysBefore Storm to Bond to Roadsstronger that traditional sand or salt mixtures,has allowed the budget-strapped state to cutback on spreading sand to reduce snow andice on its 1,100 mi. of roads.

During Nemo, and other potent storms,the salt brine was applied two days beforethe storm, leaving a chalky coat that bondswith the roadway after the water evaporates.Sand reduction also means less clogging ofstorm drains and less sediment in rivers andstreams.

It is only a pre-treatment. Traditional saltand sand are still applied in storms.

Such innovations speak to the dilemmasof time and cost facing municipalities whena storm like Nemo shuts them down with nopower or travel for days.

“Our challenges [plowing roads] weresmall compared to that of the leaders of thetown of Hamden as well as many othermunicipalities who had similar challenges,”said Sweeney. “It was eye opening to spendsome time observing the challenges from theinside of this response effort and, at the sametime, listening to a percentage of the publiccriticizing the efforts of these people tryingto help them.

“Some of these people criticized throughtelevision and newspaper and websites;some people griped to all that would listen inthe local coffee shops and some people tooktheir frustrations out on the actual equipmentoperators as they cleared snow in front oftheir homes,” he added. “As a private con-tractor, I am not accustomed to this unedu-cated and uninformed criticism. It was not allnegative and I would be remiss if I did notacknowledge a very large percentage ofwonderful residents who were quite positivealong the routes and were quick to provideour operators with food, a hot cup of coffeeand a kind word or a thank you along theway.”

Sweeney added, “As a lifelong resident ofthe town of Hamden, I would like to say itwas a pleasure to work with this group, andcongratulations to all involved, from theMayor, to the Public Works Department tothe fire department to the police departmenton getting the cleanup completed. Great jobto all.”

(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.) CEG

NEMO from page 11

NEW ENGLAND SUPPLEMENTADVERTISER INDEX

The Advertisers Index is printed as a free editorial service to ouradvertisers and readership. Construction Equipment Guide is not

responsible for errors or omissions.

A QUICK PICK CRANE SERVICE INC ..........................11

A T EQUIPMENT INC ....................................................10

ARGUS INDUSTRIAL COMPANY ....................................1

ASTRO CRANE ..............................................................11

BARRY EQUIPMENT CO..................................................7

BOBCAT OF RHODE ISLAND..........................................9

CHADWICK BAROSS MA ................................................5

CLASSIFIED....................................................................10

CONTRACTOR’S CORNER............................................11

COR EQUIPMENT SALES ..............................................5

EQUIPMENT EAST ..........................................................9

FOLEY MARINE & INDUSTRIAL ENGINE ......................1

GORILLA HAMMERS ......................................................1

ITL AUCTIONEERING ......................................................1

J R VINAGRO CORPORATION ......................................1

KRAFT POWER CORP ....................................................1

LORUSSO HEAVY EQUIPMENT LLC ..........................13

LOU GIZA EQUIPMENT....................................................1

LUBRICATION TECHNOLOGIES INC ..........................11

MILTON CAT....................................................................10

ROGERS BROTHERS ....................................................15

SUMMIT SUPPLY LLC/MULTI MACHINE ........................1

THE N.I.C.E. COMPANY ..................................................7

THE W I CLARK CO ........................................................2

TYLER EQUIPMENT CO ............................................3,13

WOODCO........................................................................16

Page 15: NewEngland #7,2013

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • March 27, 2013 • Page 15

Tyler Equipment251 Shaker Road

East Longmeadow, MA 01028(413) 525-6351(800) 292-6351

1980 Berlin TurnpikeBerlin, CT 06037(860) 356-0840(800) 352-4473

Parts: (860) 356-0848

www.tylerequipment.com

C.N. Wood Co., Inc.200 Merrimac St.

Woburn, MA 01801(781) 935-1919

Avon, MA (508) 584-8484

Johnston, RI(401) 942-9191

www.cn-wood.com

Joseph Equipment Company300 Gay Street

Manchester, NH 03103603-641-8608

www.josephequipment.com

Page 16: NewEngland #7,2013

Page 16 • March 27, 2013 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

PARTS & service

REMARKETING

CUSTOMER SUPPORT AGREEMENTS

VOLVO FINANCIAL SERVICES

CARETRACK

Volvo Construction Equipment

140 Wales AvenueAvon, MA 02322508-584-8484

22 North Maple StreetWoburn, MA 01801

781-935-3377

60 Shun PikeJohnston, RI 02919

401-942-9191

www.woodcomachinery.com

Whatever you do, Woodco Machinery is there to help you do it. Dependable equipment – from construction and road building to forestry, utilities and more. Support – from sales and remarketing to reliable parts and service. Offerings – to get you working and keep you working – from Customer Support Agreements and CareTrack telematics to full-service fi nancial solutions through Volvo Financial Services. It’s all delivered directly through one source: Woodco Machinery.

We’re the solution you can trust – before and after the sale. Let’s work together. Contact your nearest Woodco location today.

Get it done from one source: your Volvo dealer. Let’s work.