144
Irrigation Rehabilitation Project (RRP KAZ 50387) Supplementary Document 17: DUE DILIGENCE REPORT ON SOCIAL SAFEGUARDS August 2019 Prepared by the Executing Agency, the Republican State Enterprise “Kazvodkhoz” of the Republic of Kazakhstan for Asian Development Bank. This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

Irrigation Rehabilitation Project (RRP KAZ 50387)

Supplementary Document 17:

DUE DILIGENCE REPORT ON SOCIAL SAFEGUARDS

August 2019 Prepared by the Executing Agency, the Republican State Enterprise “Kazvodkhoz” of the Republic of Kazakhstan for Asian Development Bank. This due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction
Page 3: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

ABBREVIATIONS AND ACRONYMS ADB Asian Development Bank Akimat Local Executive Power in the regions and districts DDR Due Diligence Report DP Displaced Person EA Executing Agency GoK Government of Kazakhstan GRM Grievance Redress Mechanism IA Implementing Agency IP Indigenous People IR Involuntary Resettlement KVK “Kazvodkhoz “Republican State Enterprise responsible for rehabilitation,

operations and maintenance of irrigations and water facilities LARP Land Acquisition and Resettlement Plan MOA Ministry of Agriculture MOF Ministry of Finance PIU Project Implementation Unit PMO Project Management Office PMC Project Management Consultant ha hectare CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction Codes and Regulations

Page 4: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction
Page 5: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

Table of Contents

EXECUTIVE SUMMARY ............................................................................................................................... I

INTRODUCTION ........................................................................................................................................... 1

A. BACKGROUND .............................................................................................................................................. 1 B. OBJECTIVE, SCOPE AND METHODOLOGY ............................................................................................................ 1

PROJECT DESCRIPTION ........................................................................................................................... 2

A. PROJECT IMPACT, OUTCOME AND OUTPUTS ....................................................................................................... 2 B. DESIGN DETAILS INTRODUCED TO AVOID IMPACT IN REHABILITATION OF CANALS AND DITCHES ...................................... 3 C. THE PLANNED REHABILITATION WORKS .............................................................................................................. 4 D. WORK TECHNOLOGY AND MACHINERY SELECTION .............................................................................................. 10 E. THE CURRENT RIGHT OF WAY ......................................................................................................................... 14

DUE DILIGENCE FINDINGS ..................................................................................................................... 15

A. GENERAL ................................................................................................................................................... 15 B. OWNERSHIP OF THE CANALS AND STRUCTURES .................................................................................................. 15 D. SITE VISITS AND SATELLITE MAPS SCREENING ..................................................................................................... 16 E. LOCATIONS WHERE SOME DITCHES ARE NEAR THE HOUSES ................................................................................... 21 E. THE LAND PLOT FOR THE KVK HEADQUARTERS BUILDING .................................................................................... 26 F. PROJECT CATEGORY FOR INVOLUNTARY RESETTLEMENT AND INDIGENOUS PEOPLE IMPACT ....................................... 28

DISCLOSURE, PUBLIC CONSULTATION AND COMMMUNICATION PLAN .................................... 29

A. PROCEEDINGS OF SIX PUBLIC CONSULTATIONS IN ALL FOUR PROVINCES ................................................................... 29 B. SUMMARY OF THE QUESTIONS AND PROPOSALS PER PROVINCES ............................................................................ 30 C. COMMUNICATION PLAN WITH THE PROJECT STAKEHOLDERS ................................................................................. 32

GRIEVANCE REDRESS MECHANISM .................................................................................................... 33

A. OBJECTIVE AND RESPONSIBILITY...................................................................................................................... 33 B. THREE LEVELS OF GRIEVANCE RESOLUTION ........................................................................................................ 34 D. GRIEVANCE REDRESS COMMITTEES ................................................................................................................. 35

INSTITUTIONAL ARRANGEMENT AND MONITORING ........................................................................ 36

A. ASIAN DEVELOPMENT BANK .......................................................................................................................... 36 B. THE EXECUTING AGENCY – KVK ..................................................................................................................... 36 B. CAPACITY DEVELOPMENT NEEDS .................................................................................................................... 37 C. AKIMATS AND OTHER STATE AGENCIES ............................................................................................................. 38 D. SUPERVISION CONSULTANT AND CONTRACTORS ................................................................................................ 38

MONITORING AND REPORTING ............................................................................................................. 38

CONCLUSION ............................................................................................................................................. 38

ATTACHMENT 1. LIST OF THE CANALS AND DITCHES TO BE REHABILITATED ........................................................................ 39 ATTACHMENT 2. DECREE OF THE REGIONAL AKIMAT ABOUT THE CANALS’ OWNERSHIP (SAMPLE) .......................................... 65 ATTACHMENT 3. CANAL VOLUNTARY DONATION SIGNED DOCUMENTS ............................................................................. 70 ATTACHMENT 4. SAMPLE PHOTOS FROM SITE VISITS .................................................................................................... 73 ATTACHMENT 5. INVOLUNTARY RESETTLEMENT IMPACT CHECKLISTS .............................................................................. 87 ATTACHMENT 6. INDIGENOUS PEOPLE IMPACT CHECKLIST ............................................................................................ 89 ATTACHMENT 7. PROCEEDINGS OF THE DISCLOSURE AND PUBLIC CONSULTATIONS IN FOUR PROVINCES ................................ 91 ATTACHMENT 8. ASSIGNMENT OF THE GRM FOCAL PERSONS BY THE KVK .................................................................... 117 ATTACHMENT 9. CONFIRMATION OF STAFF OF REGIONAL AUTHORITIES AND KVK FOR GRM ............................................. 123

Page 6: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction
Page 7: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

EXECUTIVE SUMMARY 1. The report presents the findings of the due diligence for involuntary resettlement (IR) and indigenous people (IP) impact for the project to rehabilitate the existing irrigation network for 171,101 hectares (ha) lands in four provinces of Kazakhstan. Asian Development Bank (ADB) finances the project and the Kazvodkhoz (KVK) is an Executing Agency (EA).

2. The due diligence was conducted from November 2018 to June 2019 as per ADB Safeguard Policy Statement (ADB SPS 2009) to assess if the project design anticipates: (i) any involuntary resettlement, (ii) any adverse impact to indigenous people, and (iii) review project design details and technologies to avoid adverse impact, if any.

3. The due diligence found that all irrigation canals are state- and municipality-owned. A farmer has donated a 2.7 km long irrigation canal covering an area of 8.2 ha (0.87% of his total 939 ha of land). The canal has not been repaired for years and the farmer is interested in irrigation to increase the productivity of his land but cannot afford proper rehabilitation and maintenance of the canal. The donation is verified as per the laws of Kazakhstan and principles of ADB SPS (2009). The farm is well off and owns 16 tractors, 2 combine harvesters, and 150 large livestock. The farmer is a direct project beneficiary of the project and his household is not vulnerable.

4. The project works include rehabilitation and improvement of the existing irrigation canals to their original designs (with and without lining), restoration of the pipeline systems and installation of the new pumping stations without changes in the right-of-way. No changes are planned in the existing routes, layouts, and capacities of the canals. Analysed site specific civil works technologies were incorporated into the project design which allowed avoiding any adverse impact.

5. The land for the Water Centre building in Nursultan (Astana) city is owned by the municipality and located in the suburb of south-east of Nursultan city. The due diligence counted up 30 tracks using the site as temporary and ad-hoc parking place. According to the city regulations, parking of the trucks are not allowed in the Nursultan city. Therefore, there are number of parking lots for trucks and heavy construction vehicles in this suburb area of the city. The drivers consulted expressed that some of them have been using the site from two months to two years. The main reason for parking there included: (i) parking trucks are not allowed inner Nursultan city and/or (ii) the land plot was not fenced and used by anyone, (iii) land plot is located close to the main road to travel to other provinces. They park their trucks in this site until receiving new orders mainly through phones, online, or references. The parking here or somewhere close does not impact their business due to the nature of their business requiring them to travel and sometimes stay and work for weeks or months in different assignments locations. The trucks are parked there on ad-hoc basis just until they receive the next assignment often by phone calls from the clients they already have or client’s references. Besides, they use paper and digital media announcements to offer their services to the clients. Thus the site is used for parking the trucks until they receive a new assignment in different ongoing constructions sites within Nur-Sultan city as well as in other provinces of Kazakhstan such as Karaghandy and Pavlodar provinces, as well as Ekateringburg and other cities of Russia. Change of the location for parking their trucks to two alternative existing parking lots free of charge (150 and 700 meters away along the same street), while waiting for the orders and assignments from the clients, will not anticipate any adverse impact on their business.

6. There are two alternative parking lots located within the same street in distance about 150 and 700 meters from the site which the drivers are offered to use by Nursultan city Akimat. The drivers were consulted and interviewed about moving to two neighbouring parking lots, based on which, nearby alternative parking lots does not have any adverse impact to their

Page 8: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

ii

business due to the described nature of their business and communication methods they use to attract new clients. The drivers were informed about the established project specific GRM, and the contact information of Grievance Redress Mechanism (GRM) responsible persons from KVK were provided to the drivers for their references. Further monitoring is envisaged to follow-up and monitor the process.

7. Disclosure and public consultations were held with farmers and communities from all subprojects in four provinces and truck drivers in Nursultan city. The project outputs, IR and environmental safeguards of ADB SPS (2009) and laws of Kazakhstan, as well as the project GRM were discussed. Participants expressed support for the project, made proposals and raised questions about the project design and water tariffs (more details below). Site specific communication plan will be developed prior to the start of the civil works.

8. The project specific GRM is formed as per ADB SPS (2009) and laws of Kazakhstan. GRM is set at the district, regional, and central levels including the staff from the respective district and regional Akimats and KVK branches. KVK shall ensure regular internal monitoring to address any unanticipated resettlement impact during the project implementation. The outcomes of the monitoring shall be reflected in the project progress reports. ADB will arrange capacity building workshop and on-the-job-training to the KVK staff as KVK is new EA to ADB-assisted projects.

9. The project is Category ‘C’ for IR and IP impact as per ADB SPS (2009). Adverse impact was avoided through analysis of civil works technologies incorporated into the project design. Site specific communication plan will be developed by supervision consultant and contractor agreed with water users to align civil works schedule with irrigation schedule. Further monitoring of any unanticipated impact will be carried out and reported throughout the project implementation in semi-annual and annual social safeguards monitoring reports.

Page 9: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

INTRODUCTION

A. Background

1. The project will support the rehabilitation of irrigation networks serving about 171,100 hectares (ha) land in the East Kazakhstan, Karaghandy, Kyzlorda, and Zhambyl provinces of the Republic of Kazakhstan. The project will promote diversification from traditional low-yielding and low-value grain crops into high value cash crops and horticulture crops. Asian Development Bank (ADB) will finance the project and the State Republican Enterprise “Kazvodkhoz” (KVK) will be an Executive Agency (EA).

B. Objective, Scope and Methodology

2. The due diligence was conducted from November 2018 to June 2019 as per ADB Safeguard Policy Statement (ADB SPS 2009) to assess if project design anticipates: (i) any involuntary resettlement, (ii) any adverse impact to indigenous people, and (iii) review project design details and technologies to avoid adverse impact, if any.

3. The due diligence covers the outputs (i) rehabilitation and improvement of irrigation network for all 245 irrigation schemes in four provinces, and (ii) the land plot in Nursultan (Astana) city for the KVK Headquarters building. It was conducted from November 2018 to June 2019 and the methodology and approaches included:

(i) Review of the project related documents, available technical parameters, legal acts and maps, including those verifying the owners and the current rights of way of the irrigation canals and ditches;

(ii) Review project outputs as per ADB SPS (2009) requirements, (iii) Consultations with the stakeholders, the KVK management and specialists at

the central, regional and district levels, and local executive power; (iv) Screening the Project areas by satellite data (Geonomic

https://irr.geonomix.kz/ and Google Earth); (v) Site visits to the project canals and the site for construction the KVK

Headquarters building; and (vi) Consultations and interviews with the farmers and residents during the

disclosure and public consultations conducted for all 16 subprojects in all four project provinces and the drivers parking their trucks in the site proposed for construction of the KVK Headquarters in Nursultan city.

4. Site visits, review of satellite data, cadastral maps, canals and ditches title documents and other project related documents were reviewed and used in the screening of the whole project area.

5. A big volume of data and documents were reviewed but not all could be attached to the report. The documents are available in the central and regional offices of the KVK.

Page 10: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

2

PROJECT DESCRIPTION

A. Project Impact, Outcome and Outputs

6. The project will rehabilitate and improve the existing irrigation network with length of 3,100.28 km, ameliorative area 171,106 ha in East Kazakhstan, Karaghandy, Kyzylorda and Zhambyl provinces of Kazakhstan (table 1). This includes 245 old irrigation schemes, which lie in one or few hydrologic zones and therefore, they are grouped into 16 subprojects with consideration to their hydrologic boundaries and administrative jurisdictions.

Table 1: Irrigation areas to be rehabilitated by the provinces

Provinces Irrigation area (ha) No of irrigation schemes

Total To be rehabilitated

East Kazakhstan 104,717 79,256 22

Karaghandy 68,786 27,900 10

Kyzlorda 228,394 28,974 11

Zhambyl 63,191 34,977 202

Total 465,088 171,107 245

Map 1. Map of Kazakhstan: project provinces shown in green color

7. The project is aligned with the following impact: the share of agriculture production contribution to gross domestic production increased, as outlined in Strategy Kazakhstan

Page 11: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

3

2050.1 The project will have the following outcome: farm productivity increased in the East Kazakhstan, Karaghandy, Kyzylorda, and Zhambyl province of Kazakhstan.2

8. Project outputs. The project outputs largely remain unchanged and will comprise of four outputs: (i) irrigation infrastructure rehabilitated and/or improved; (ii) water management improved and beneficiary’s capacity enhanced; (iii) KVK’s capacity strengthened, including project administration and implementation support.

9. Output 1: Irrigation infrastructure rehabilitated and/or improved. The output will support the rehabilitation and/or improvement of about 245 irrigation schemes in the four provinces. For canals, the works would involve desilting and removal of vegetation in the lined and unlined canals, re-sectioning of the unlined canals, and repair of damaged sections of the lined canals. The total length of new concrete lined canals will be about 1,064 km while the improved earth canals will be about 1,976 km. A total of about 4,185 hydraulic structures including water measuring devices will be constructed or rehabilitated. About 358 km drainage collectors will be rehabilitated and/or improved. A drip irrigation system to cover 9,300 ha will be established in Zhambyl province. In addition, about 24 sets of the supervisory control and data acquisition (SCADA) system will be installed in the main canals of the four provinces.

10. Output 2: Water management improved and beneficiary capacity enhanced. The project will support (i) pilot-testing a system to monitor water and agricultural productivity using remote sensing technology in selected irrigation schemes; (ii) assisting in organizing the beneficiaries into the agricultural cooperatives established on hydrological boundaries, and develop the capacity of the cooperatives with respect to their functioning as well as with physical inputs like office furniture and equipment; (iii) training farmers on using improved irrigation management and climate change-related aspects; and (iv) providing consulting services for capacity development. This output will help KVK to extend its advice services to farmers on on-farm water management and crop choices.

11. Output 3: KVK’s capacity strengthened. The project will strengthen KVK’s governance and support its internal reforms by providing consulting services for (i) capacity development and training of KVK staff on financial, procurement, and water management aspects; the (ii) formulation and implementation of an asset management plan. The project will also support (i) provision of machinery, equipment, and vehicles for the four KVK branch offices to carry out their O&M function and improve system performance; (ii) rehabilitation and/or construction of repair workshops; (iii) construction of the KVK headquarters building; (iv) construction of an office building for KVK’s East Kazakhstan branch; (v) organization of a study tour for KVK staff and project beneficiaries to learn from advanced irrigation practices; and (vi) the operations of the project management office and project implementation units to ensure smooth implementation.

B. Design details introduced to avoid impact in rehabilitation of canals and ditches

12. In line with the main principle and objective of the ADB SPS (2009), the following design details were introduced into the project to avoid any adverse impact:

(i) Civil works for cleaning the canals’ and ditches’ beds and slopes will be carried out manually near the settlements areas (which are mainly ditches for irrigation and rain

1 Official Site of the President of the Republic of Kazakhstan. Address by the President of the Republic of

Kazakhstan, Leader of the Nation, N.A. Nazarbayev on Strategy “Kazakhstan-2050”: New Political Course of the Established State. http://www.akorda.kz/en/addresses/addresses_of_president/address-by-the-president-of-the-republic-of-kazakhstan-leader-of-the-nation-nnazarbayev-strategy-kazakhstan-2050-new-political-course-of-the-established-state.

2 The design and monitoring framework is in Appendix 1 of the Report and Recommendation of the President to

the Board of Directors.

Page 12: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

4

water drainage); The feasibility study provides manual works in many occasions and types of the project civil works as can be seen in the table 5 and 6 further below;

(ii) There will be no widening of canals and ditches, and no change in the canals capacities, layouts and right-of-way is considered;

(iii) Rehabilitation works should be arranged in the other sides of the canals where needed

to avoid adverse impact; since canals are many and scattered in different locations and directions and in some canals, the works can be carried in “north”, south, rear and front” pertinent for each site during the physical works which will be defined specifically for each canal prior to the civil works. All canals where machines can be used, have service roads and empty areas at least in one side;

(iv) Ensure continuous consultation with residents and farmers, through effective

communication plan to inform and agree about the civil works schedule and nature of civil works;

(v) The schedule of the civil works will be arranged in consultation with the farmers to ensure

the scheduled irrigation supply during the irrigation season.

C. The planned rehabilitation works

13. A total of 614 irrigation canals and ditches will be rehabilitated, of which 548 canals (magistral, inter-farm, on-farm canals and ditches), 23 pipelines and 43 drains belonging to 245 irrigation schemes, which are grouped into 16 subprojects in four provinces as follows.

• East Kazakhstan: 101 canals (main canals, on- and off-farm canals);

• Karaghandy: 8 canals and 23 pipelines;

• Kyzylorda: 267 canals and 43 drains;

• Zhambyl 172 canals; and

14. Below is a summary of the major rehabilitation works:

• 1,976 km of earthen canals;

• 1,064 km of concrete-lined canals, flumes, and pipelines;

• 1,477 km of inspection road along canals;

• 4,185 hydraulic structures which include head regulators, outlets, pipe crossings, bridges, water meters, and underground pipelines;

• 358 km of collector drains in Kyzlorda province;

• 19 wells for irrigation in Zhambyl province;

• 34 mobile diesel pumping stations in Karaghandy province;

• 19 stationary pumping stations in Karaghandy province, with power lines and associated equipment;

• 27 vertical drainage wells in Kyzylorda province;

• 24 units of SCADA systems; and

• drip irrigation systems on vegetable clusters on 9,300 ha area in Zhambyl province.

15. Table 2 in the next page shows the numbers and length of the irrigation network. Attachment 1 provides the list of canals and drains, their length and rehabilitated areas.

16. The project will rehabilitate and improve the existing irrigation canals and drains. The works include cleaning the canals’ slopes from thickets of reeds, wild bushes, canals bottom

Page 13: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

5

silt cleaning, restoration of longitudinal and transverse profiles and the working section lining. No widening of any canal or ditches are planned.

17. The canals will be cleaned to the original capacity with or without lining, and the pipeline systems and new pumping stations will be restored without changing the right of way. Changes in the routes and layouts of the canals are not envisaged. The list of the canals included in the project and their capacities is not expected to change. The lengths of the canals may be refined during the detail design but the right of way will not be increased. The bed width of the canals will vary from 0.8 to 6 m depending on each canal’s capacity. The top width of the canals will be defined for each canal during the detail design. The figures 1, 2 and 3 show the typical cross-sections of the canals.

Page 14: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

6

Table 2. Length of the network and number of the structures

No. Name of projects

Can

al li

ning

Ear

th c

hann

el

Flum

e

Pip

elin

e

Col

lect

or

Hea

d st

ruct

ure

Cro

ss r

egul

ator

Out

lets

Flow

-mea

suri

ng s

truc

ture

Fish

pro

tect

ion

stru

ctur

es

Wel

ls

Syp

hon

Pip

e cr

ossi

ng o

n ca

nal

Pip

e cr

ossi

ng o

n co

llect

or

Bri

dges

Pum

p st

atio

n (P

ump

Д 6

30-9

0)

Pum

p st

atio

n (P

ump

Д 2

00-2

1)

Pum

ps o

f typ

e С

НП

and

СН

ПЭ

Tran

sfor

mer

sub

stat

ion

and

lines

Bui

ldin

gs o

f pum

p st

atio

ns

Air

rel

ease

val

ve fo

r un

derg

raou

nd n

etw

ork

Dis

trib

utio

n w

ell f

or u

nder

grou

nd n

etw

ork

Hyd

rant

for

unde

rgro

und

netw

ork

Esc

ape

for

und

ergr

ound

net

wor

k

Out

let f

or u

nder

grou

nd n

etw

ork

Pun

ctur

e ho

pes

km km km km km nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos. nos.

1Total: East

Kazakhstan oblast441.07 397.42 - - - 101 - 1 132 101 101 - - - - - - - - - - - - - - - -

1.1 Kurchum district 86.44 128.99 - - - 22 - 341.00 22 22 - - - - - - - - - - - - - - -

1.2 Tarbagatai district 55.98 57.00 - - - 8 - 129.00 8 8 - - - - - - - - - - - - - - -

1.3 Urdzhar district 118.10 108.65 - - - 12 - 285.00 12 12 - - - - - - - - - - - - - - -

1.4 Zharma district 40.25 13.00 - - - 5 - 84.00 5 5 - - - - - - - - - - - - - - -

1.5 Kokpekti district 2.20 0.00 - - - 1 - 3.00 1 1 - - - - - - - - - - - - - - -

1.6 Zaisan district 138.10 89.78 - - - 53 - 290.00 53 53 - - - - - - - - - - - - - - -

2Total: Karaganda

oblast88.78 - 0.81 90.724 - 9 - 33 9 - - 2 - 2 11 8 34 19 19 44 20 43 13 18

2.1 Abai district 29 - - 2.00 - 12 2.00 - - - - - - 1 - 1 1 - - - - 6.00

2.2 Buhar-Zhyrau district 29.8 - 0.81 48.60 - 5.00 - 13 5.00 - - 2 - 2 7 3 18 10 10 22 9 21 6

2.3 Zhanaarka district 14.18 - - 1.00 - - 1.00 - - - - - - - 4 - - 2 2 2 2

2.4 Zheskazgan c 15.8 - - 1.00 - - 1.00 - - - - - - 1 4 1 1 - - - -

2.5 Nura district - 3.17 - - 8 - - - - - - - 2 - - - - - - 12.00

2.6 Osakarov district - 38.95 - - - - - - - - 4 3 6 7 7 20 9 20 5

3Total: Kyzylorda

oblast- 1 117.24 - - 357.73 252 - 1 165 - - 27 5 149 127 11 - - - - - - - - - - -

3.1 Zhanakorgan district - 7.50 - - 0.00 4.00 - - - 3 - 60.00 - - - - - - - - - -

3.2 Shiely district 187.39 - - 59.70 62.00 - - - - - - - - - - - - - - -

3.3 Kyzylorda city - 78.38 - - 68.09 34.00 - - - - - - - - - - - - - - -

3.4 Syrdarya district - 193.42 - - 150.01 40.00 - - - 18 - 86.00 - - - - - - - - - -

3.5 Zhalagash district - 60.18 - - 0.00 13.00 - - - 6 - 51.00 11.00 - - - - - - - - - -

3.6 Karmakshy district - 122.44 - - 79.93 24.00 - 579.00 - - - - 63.00 16.00 - - - - - - - - - -

3.7 Kazaly district - 440.65 - - 0.00 70.00 - 586.00 - - - 5 - - - - - - - - - -

3.8 Aral district - 27.28 - - - 5.00 - - - - - - - - - - - - - - -

4Total: Zhambyl

oblast359.88 493.79 83.52 4.00 - 156 174 149 155 - 19 1 - - - - - - - - - - - - - -

4.1 Sarysu district 46.10 44.46 2.88 0.00 - 16.00 - 10 16 - - - - - - - - - - - - - - -

4.2 Talas district 78.74 122.14 36.36 0.00 - 42.00 - 117 42 - 1 - - - - - - - - - - - - -

4.3 T.Ryskulov district 64.05 83.55 5.75 4.00 - 18.00 - 16 17 - 19.00 - - - - - - - - - - - - - -

4.4 Shu district 170.99 243.64 38.53 0.00 - 80.00 174 6 80 - - - - - - - - - - - - - - -

TOTAL

QUANTITIES on 4

OBLASTS

889.73 2 008.45 84.33 94.72 357.73 518 174 2 479 265 101 46 8 149 127 13 11 8 34 19 19 44 20 0 43 13 18

Length of network and number of structures on project "Modernization of irrigation networks for irrigated lands",

of Kyzylorda, Karaganda, Zhambyl and East Kazakhstan oblasts of RK

Page 15: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

7

Figure 1. Typical cross section of concrete canals

Page 16: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

8

Figure 2. Typical cross-sections of earthen canals

Page 17: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

9

Figure 3. Typical cross-sections of earthen canals

Page 18: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

10

D. Work technology and machinery selection

18. Work technology on performance and ditch cleaning in earthen canals: The flow scheme of sediment removal operations on canals in the earthen channel with depth up to three meters depend on a type of used unit. In cleaning the canals, the sediments are removed by operating device of excavator or by ditch cleaner as they move along the canal. Alternate working movements of the basic machines are chosen depending on the sedimentation layer thickness, canal width and depth, canal situation and parameters of operating devices. With a single-pass working movement of the basic machine the canal is cleaned from one position and the operating device is able to influence the sedimentation layer throughout its entire cross-section. When it works from one position, it is cleaned in two or more passages of basic machine.

Figure 4. Flow charts of excavation and cleaning in earthen canals

Figure 4: a) a ditch cleaner with double-rotor operating device; в) a backhoe excavator with tilting ladle; г) an excavator with equipment of side dragline; д) a ditch cleaner with auger operating device; е) an in-the canal ditch cleaner based on narrow tractor with cleanup dumps and rotary operating device; ж, и) an excavator or ditch cleaner with multi-bucket or scraping operating device; к) an excavator with dragline equipment.

19. Weed removal process from side slopes and canal banks in the earthen channel includes the work operations presented in the table. Ditch cleaning process in the earthen channel from weeds depends on local conditions and equipment used. Under specific conditions, some technological operations listed in the table may be excluded from the technological process. For example:

Page 19: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

11

(i) at regular mowing of herbaceous vegetation on canal banks and side slopes (two to four times during the growing season), the need for specialized cutting of wild bushes and shrubs, removing it from the channel and utilization is dropped out, as wild shrubs do not succeed to develop up to sizes inaccessible for mowing by ameliorative mowing machines;

(ii) in case of massive overgrowing of banks and slopes with wild shrubs and bushes its

subsequent removal the herbaceous vegetation does not remain and it’s mowing doesn’t carried out.

Table 5. Technology of weeds removal from canal side slopes and banks in earth

canal

Ref. no

Working operation Ways and means of performance

1. Removal of foreign objects (stones, scrap metal etc.) from canal banks.

Tractor manipulators, excavators, bulldozers, loaders-buckets and manually.

2. Revelation and marking with a range rod the nearly invisible structures and invincible obstacles on canal side slopes and banks.

Manually.

3. Cut of wild bushes and shrubs on canal banks.

Brush-cutting machines, bulldozers, manually.

4. Gathering of cut shrub on bank and small forest in a pile.

Bulldozers, root extractors-gatherers, tractor rakes, loaders- buckets

5. Removal of foreign objects (stones, scrap metal etc.) from canal beds.

Tractor manipulators, excavators, loaders dozers, loader-buckets and manually.

6. Cut of wild bushes and shrubs on canal side slopes

Brush cutters, manually.

7. Extraction of cut vegetation from canal bed with its subsequent movement into the formed piles.

Loader-buckets, tractor rakes, bulldozers, root extractors-gatherers, gathering- transportation vehicles.

8. Stump pulling on canal bank and bed.

Root extractors-gatherers, single-bucket excavators with special buckets.

9. Hilling and shaking up piled wood and soil mass.

Root extractors-gatherers, loaders-buckets.

10. Processing of wild bushes and shrubs (stocking up firewood, chopping into chips and others).

Manually, choppers.

11. Loading the convertible bushes and shrubs and wood residues into vehicles.

Loaders, loader-buckets.

12. Removal the bushes and shrubs residues to consumers or to storage sites

Tractor trailers, motor transport.

13. Leveling of soil heaps, leveling of banks.

Bulldozers and graders.

14. Mowing of banks. Front mowing machines, and where there is a road any ameliorative or agricultural mowing machines.

15. Mowing of side slopes. Ameliorative mowing-machines and ditch cleaners with mowing operating devices.

16. Mowing of inaccessible places for mowing -machines.

Manually.

Page 20: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

12

20. Work technology of cleaning canal bed and drains from sediments: Cleaning the canals side slopes and bottom in the earthen canals from sediments will be carried out according to the technological process given in the table 4. Structure of technological operations depends on local conditions and equipment used during the process of cleaning the canals in the earthen channel from sediments.

21. Under specific conditions, some technological operations indicated in the table (removal of weed vegetation from canal banks and beds, clearing and levelling of banks, levelling of excavated soil) can be excluded from the technological process. For example, generally there is no need to level the excavated soil when using ditch cleaners with an active rotary working device (MP-14, MP-16).

22. Prior to excavation work in the presence of tree and shrubs and herbaceous vegetation in the cleared canal section, it is necessary to perform technological operations to remove weed vegetation from canal banks and side slopes.

23. If technological operations on weed removal from canal banks and side slopes were not performed immediately prior to performance of cleaning the canal bed from sediments, then the preparation of cleaned canal section and the route of unit movement are performed.

24. Preparatory technological operations include the removal of foreign objects from canal beds and banks, revelation and marking with range rod the nearly invisible structures and invincible obstacles on canal side slopes and banks, levelling of spoil bank and heaps of soil and berm levelling.

Table 6. Technological of cleaning canal beds in an earthen channel from sediments

Ref. No

Technological operation Ways and means of performance

1. Removal of weed vegetation from canal banks and side slopes.

In accordance with technological process, fore-quoted.

2. Removal of foreign objects (stones, scrap metal etc.) from canal side slopes and beds.

Tractor manipulators, excavators, dozers, loader-bucket and manually.

3. Revelation and marking with range rod the nearly invisible structures and invincible obstacles on canal side slopes and banks.

Manually.

4. Leveling of spoil banks and soil heaps, leveling of banks.

Bulldozers and graders.

5. Cleaning of canals from sediments. Ditch cleaners, dragline excavators and backhoe with ameliorative buckets.

6. Leveling of excavated soil on bank or loading into the vehicles with subsequent removal for utilization.

Bulldozers and graders.

25. After extraction of sediments from canal beds, they are unloaded onto the bank with subsequent levelling of excavated soil or loaded into the vehicles with subsequent removal for utilization.

26. When making canals with a top width of less than 3 m if it is impossible to complete the design section, after cleaning the canal from silt and vegetation, the canal is filled with a layer-by-layer compaction of 20 cm. Then cut of design section is performed.

27. This technology of excavation applies to all alternates for earthen canals.

Page 21: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

13

28. Technology of the concrete works: Complex technological process of concreting structures, according to the general scheme, includes preparing concrete and transporting it to a construction site, supplying, distributing, laying and compacting in the structure, curing of concrete during hardening.

29. Concrete mix will be prepared according to the brand of concrete specified in the project and with the water permeability requirements, frost resistance, preservation of mechanical properties in aggressive media. It must also have certain technical properties that provide its transportation and operational comfort. In this regard, the mixture should not segregate and have a certain consistency, which, depending on the placement conditions of mixture can vary from liquid to thick and hard.

30. Machinery selection: Cut of the aboveground portion of wild bushes and shrubs and growing on the canal banks is carried out using brush-cutting machines with an operating device (rotary saws, saw chains, cutter-type mechanisms, milling cutters, etc.) and machines with a passive operating device (one - and double knife brush cutters, bulldozers, knife rollers).

31. Mounted brush cutters with an active operating device based on a single-bucket excavator or universal telescopic brush cutters with an active device are used for cutting tree and shrubs on canal side slopes and edges, which on the strength of their design features can produce cutting of shrubs and small forest on the side slopes.

32. The canals banks and beds will be cleaned from stumps mechanically by removing the stumps and roots using specialized root extractors and equipment or other way.

33. At the same time the root extractors, root extractors and gatherers, root extractors-loaders, extracting borrows, rotary root extractors, single-bucket excavators with conventional or repair buckets are used on the banks. To remove stumps from canal side slopes, single-bucket excavators and root extractors are used the design of which allows stump extraction on the slopes.

34. Extraction of cut vegetation from the canal bed to the bank, as well as loading of convertibles of tree and shrubs and wood residues into vehicles is carried out by loader-buckets, special grippers based on single-bucket excavators and pick-ups and pick-up transport machines.

35. Hilling and shaking up of the cut and uprooted wood and earth mass is performed by root extractor-gatherers, loaders, buckets, etc.

36. Mowing of herbaceous vegetation on berms is done by front mowing machines and, if local conditions allow (presence of a road along the bank), by ameliorative mowing machines or ditch cleaners with mowing tools.

37. Mowing of herbaceous vegetation on canal side slopes is carried out by ameliorative mowing machines on tractors of various sizes or ditch cleaners with cutting tools. Cutting devices of mowing machines can be backward and forward action and rotating with an axis of rotation in the vertical and horizontal planes.

38. Selection of mechanism type for the work performance is done by comparing the canal parameters and the vegetation to be removed with performance of a machine.

Page 22: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

14

E. The current right of way

39. The current right of way for the irrigation canals and schemes vary from 3.5 to 45 meters depending on their individual capacity, width, depth and types, as per the reviewed legal acts and documents of the canals, and confirmation of KVK. Changes in the right of way of canals and schemes are not envisaged. If there will be any minor change, this will be known during the detail design.

40. According to the laws, the right of way for the irrigation canals are set by coordination of relevant authorities (Akimats, environmental protection agency, sanitary epidemic services, emergency services and others) and based on the requirements of the set of laws and regulations, including:

(i) The Water Code of the Republic of Kazakhstan dated July 9, 2003 No. 481; (ii) Civil Code of the Republic of Kazakhstan; (iii) Land Code of the Republic of Kazakhstan dated June 20, 2003 No. 442-II ЗРК; (iv) The Forest Code of the Republic of Kazakhstan dated July 8, 2003 No. 477; (v) Environmental Code of the Republic of Kazakhstan dated January 9, 2007 No. 212-III; (vi) Law of the Republic of Kazakhstan “On Architectural, Urban Planning and Construction

Activities in the Republic of Kazakhstan” dated July 16, 2001 No. 242-II; (vii) Law of the Republic of Kazakhstan dated March 1, 2011 No. 413-IV “On State

Property”; (viii) JV RK 3.04-09-2013 "Melioration systems and facilities"; (ix) GOST 26967-86 (STS EV 5183-85) “Hydro melioration. Terms and Definitions"; (x) GOST 7.5.3.06-85 Protection of the nature of the earth. Reclamation of land; (xi) GOST 17.5.03-78 Biological reclamation; and (xii) Set of Rules for Land allocation for amelioration channels, effective 2015-07-1 (3.04-

113-2014). 41. As per the SP RK 3.04-113-2014, the width of the right of way for irrigation canals, depend on their size, depth and widths, capacity and construction type, and vary from 3,5 to 45 meters for permanent use, and from 9 to 100 meters for temporary use3.

42. The service road for canals with discharge rate of up to 1 m3 /sec will be unpaved. The width of the road is taken 5m, according to SNiP 2.05.11-83, as an off-farm road of the lower category. The service road of canals with discharge rate of more than 1 m3/sec are taken as 6.5m wide, including those with a gravel cover 3.5 m with thickness of 20 cm, category III. At the current pre-project conditions, open areas and service roads also exist along the canals within the right of way.

3 Set of Rules of the Republic of Kazakhstan, SP RK 3.04-113-2014, Land allocation for amelioration channels,

effective 2015-07-1 (“Свод правил Республики Казахстан, СП РК 3.04-113-201, Отвод земель для мелиоративных каналов, Дата введения – 2015-07-01”).

Page 23: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

15

DUE DILIGENCE FINDINGS

A. General

43. The due diligence of all project canals and structures, including 614 irrigation canals and drains belonging to 245 schemes which are grouped into 16 subprojects in four provinces in respect to the project design has been conducted, where rehabilitating of the canals and ditches to original design conditions without changing the canals right of way, routes and layouts is planned. No adverse impact on people’s land and properties, and livelihoods upon implementation of the provided design and work technologies.

44. The land plot for the Water Centre building is 0.62 ha and located near Koshkarbaeva - Tulebaeva streets’ crossing in the suburbs of Nursultan (Astana) city. It is owned by the city municipality. The due diligence identified up to 30 tracks using the area as an ad-hoc parking. Akimat of Nursultan city provided the drivers two parking lots to use free of charge which are located about 150 and 700 meters from the site in the same street. No adverse impact is anticipated for the drivers for using the two nearby parking lots.

45. More detailed due diligence findings of the project sites are given in the report further below.

B. Ownership of the canals and structures

46. As per the reviewed documents, all the irrigation canals and structures are state- and municipality owned and registered in the balance of the EA and the Communal Services under the regional Akimats (Table 7). The sample documents on ownership are in attachment 2.

Table 7: Ownership status of the irrigation schemes to be rehabilitated Province Irrigation area, ha No of

schemes No of canals/

structures Ownership

Total To be rehabilitated

EA Communal Services

Private

East Kazakhstan

104,717 79,256 22 101 56 45 0

Karaghandy 68,786 27,900 10 31 (8 canals, 23 pipelines)

17 14 0

Kyzylorda 228,394 28,974 11 310 (267 canals, 43 drains)

310 0 0

Zhambyl 63,191 34,977 202 172 154 18 0

Total 465,088 171,107 245 614 537 77 0

47. Voluntary donation: A farming company “Erzhan” donated an irrigation canal of 2.7 km length (8.2 ha) on 1 November 2018, that makes less than 0.87% of 939 ha of lands owned by the farm (including 255 ha arable land, 133 ha hayfields, 551 ha pastures). The voluntary donation is documented as per the laws of Kazakhstan and good practices and principles of ADB SPS (2009)4. The donated canal has not been repaired for years and the farmer is interested in irrigation and increasing the productivity of his farmland but cannot afford the

4 Resettlement Safeguards. A Planning and Implementation Good Practice Sourcebook – Draft Working

Document, ADB. Para 15, and criteria for acceptable donation (Appendix 2, page 85): a)The impacts are marginal (based on percentage of loss and minimum size of remaining assets); (b) Impacts do not result in displacement of households or cause loss of household’s incomes and livelihood; (c) The households making voluntary donations are direct beneficiary of the project; (d) Land thus donated is free from any dispute on ownership or any other encumbrances; (e) Consultations with the affected households is conducted in a free and transparent manner; (f) Land transactions are supported by transfer of titles; and (g) Proper documentation of consultation meetings, grievances and actions taken to address such grievances is maintained.

Page 24: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

16

costs rehabilitation and further maintenance costs of the canal. He had voluntarily donated the canal based on his signed agreement.

48. The farm is established in 1997. It owns also 16 tractors, 2 combine machines and 150 large livestock. The voluntary donation does not severely affect the living standards of the farmer, the household is not vulnerable and he is a direct beneficiary of the project. The farmer was interviewed and donation documents and the farmer’s signed agreement are in the attachment 3.

D. Site visits and satellite maps screening

49. It is found that most of the canals in all four provinces are in open steppe and fields with no or minimum settlement or structures nearby. At the same time, in Zhambyl and Kyzylorda provinces, houses and structures are found close to sections of some canals.

50. Review included all 16 subprojects (245 irrigation schemes) of the project in all four provinces and site for the KVK Headquarters in Nursultan city. 160 canals including all the canals close to the villages were visited. The sample photos given below per provinces describe the characteristics in all canals’ areas that have no or minimum settlement or house around (photos 1 to 10). The photos of the sites where houses and structures are found close to the canals follow after (photos 11-15). More photos are provided in attachment 4.

Page 25: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

17

East Kazakhstan province

Photo 1: Canal Bogenbay

Photo 2: Canal Goltsovskiy

Page 26: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

18

Karaghandy province

Photo 3: Canal Tuzdi

Photo 4: Canal Shartaz

Page 27: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

19

Kyzylorda province

Photo 5: Kyzylorda city canal К-1-3

Photo 6: Kyzylorda City canal

Page 28: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

20

Zhambyl province

Photo 7: Talas Zhiembet main canal

Photo 8: Oyik main canal

Photo 9: Talas LVMK Oiyk interfarm canal

Photo 10: Talas Zhiembet main canal

Page 29: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

21

E. Locations where some ditches are near the houses

51. The project provides cleaning of irrigation ditches as described in the section of the report about the project description. Some ditches found in Zhambyl and Kyzylorda provinces (listed below) close to the houses. The project design technologies include the manual works for cleaning the ditches close to the houses. No widening of ditches are planned. Civil works will include only cleaning the beds and slopes of the ditches from the dirt which will be carried out manually (see tables 5 and 6 above about the types and technology of works in report chapter about the Project Description).

52. In Zhambyl province:

(i) Abay; (ii) MC Noviy Kartogan; (iii) МC Stariy Kartogan; (iv) Interfarm Bayshakhan; (v) Interfarm Kultobe-Sarisu; (vi) Orta Aryk; (vii) Zhanatogan; (viii) Salyamopv; (ix) Saydakas; (x) Turksib; (xi) Pioner; (xii) Bayshakhan; (xiii) Melnichniy; (xiv) Bolnichniy; (xv) Koskuduk; (xvi) Chu; (xvii) Taylak 1; (xviii) Taykak 2; and (xix) Boribay.

53. In Kyzylorda province:

(i) Baygekum canal; and (ii) Mayzhama canal.

Map 2. Orta Aryk interfarm canal and the Zhanatorgan interfarm canal divided by road

Page 30: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

22

54. The irrigation network is not efficient because some of the ditches have been partially cleaned by communities while some other sections were not. The project aims to clean the whole irrigation network in the target area at once so the water use will be efficient, and households will be able to benefit from irrigation water to increase agriculture products for livelihoods and sale. No risk of adverse impact is expected in the operation stage. These ditches and irrigation schemes have been in place and used for decades.

55. There are also MC Sultant and MC Orynbasar canals whereas per the feasibility study the physical works for improvement will be carried out only at the beginning of these canals that are far from the settlements. No work will be carried out in other parts of these canals which are in concrete and good conditions.

56. The types of dwellings near those above-stated canals and ditches are residential rural houses built of bricks and mud bricks. The household plots are from 0.10 to 0.25 ha. Average income per work able body family member is 50,000-60,000 tenge per month (about as 131-157 USD as of 30 May 2019) as reported during consultations. The average family members are 5-6 persons (2-3 children). In addition, many households produce crops in their household plots for own consumption and sale. The crops they grow are the household plots (tomato, onions, watermelons, potato, carrots) for own consumption and sale.

57. According to the Operational Manual (Section F1/BP, 2013), para 8, point (i) and (ii), the households survey and census is required for the projects classified as category A or B for involuntary resettlement as part of activities for preparation of Resettlement Plans. Therefore, under this due diligence, the household’s surveys were not conducted. However, the field surveys, public consultations, focus group discussions (FGDs), and Key Informant Interviews (KIIs) that were carried out both in conducting this due diligence as well as in conducting the Poverty, Social and Gender Assessment for the project, vulnerable and/or poor people were not identified. The poverty line in Kazakhstan is low and estimated at 2.6% (ADB. Basic Statistics 2018). The project beneficiaries are farmers and households that expressed their needs for the project and expect reliable irrigation water supply, as result, increased agriculture products for livelihoods and sale.

58. Project design includes (i) training and capacity building for the EA and stakeholders before the project starts as well as ongoing on-job training for EA during the project implementation, (ii) continuous public consultation, and (iii) the project-specific GRM is established with responsible persons assigned by district and regional Akimats, and KVK district, regional and central offices. These responsible persons will be included in the capacity building trainings planned in the start of the project. The contact information and phone numbers of responsible agencies for grievances have been distributed to people during the public consultation under this due diligence activities. The contact information of responsible persons will be disseminated in the project area and more public consultation will be conducted as needed during the canals rehabilitation works to ensure the people have good awareness about the GRM and know where to contact if they have complain or questions.

Page 31: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

23

Zhambyl province

Photo 11: Canal Abay, Chuy district. As seen from the photo, this is not a canal but a small ditch for

irrigating the household’s plots and rain water drainage. Very minimal cleaning works may be needed carried out manually and no risk is anticipated (the concrete will not be removed, only cleaning and

weeds removal will be carried out as needed).

Photo 12: Abay Chuy district: As can be seen from the photo, this is not a canal but part of the

settlements ditches network for irrigating the households plots and (rain) drainage. Any minimal work will be carried out manually and no impact is anticipated.

Page 32: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

24

Photo 13: Canal Bolnichniy. This is also a part of the settlements ditches network for irrigating the household’s plots and (rain) drainage. Cleaning works weed and bush removal will be carried out

manually with no risk to damage or remove the structures (dirt canal, no concrete).

Page 33: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

25

Kyzylorda province

Photo 14: Canal Mayzhama: No risk is anticipated as there is the service road next to the canal (left

side), houses are located about 20 meters away.

Photo 15: Canal Baygekum: no risk is anticipated to the structures on the left sides (about 10 meters away). The works will be carried out in the right side of the canal where the service road and right-of-

way is located.

Page 34: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

26

E. The land plot for the KVK Headquarters building

59. The construction of the KVK Headquarters building was added as a new element in the project design. The identified land plot for this building is the state/municipality owned and located. There are no building, structures or shops on it.

60. The land for the KVK Headquarters building in Nursultan (Astana) city is owned by the municipality. It is about 0.62 ha and located near the Koshkarbaeva-Tulebaeva streets’ cross section in the south-east and outside of Nursultan (Astana) city. The due diligence counted up 30 tracks using the site as temporary and ad-hoc parking place. According to the city regulations, parking of the trucks are not allowed inside the Nursultan city. Therefore, there are number of parking lots for trucks and heavy construction vehicles in this suburb area of the city. The drivers consulted expressed that some of they have been using the site from two months to two years. The main reason for parking there included: (i) parking trucks are not allowed to park inside Nursultan city, (ii) the land plot was not fenced and used by anyone, (iii) it is located close to the main road to travel to other provinces. Drivers park their trucks in this site until receiving new orders mainly through phones or references. The parking here or somewhere close does not impact their business due to the nature of their business requiring them to travel and sometimes stay and work for weeks or months in different assignments locations. The trucks are parked here on ad-hoc bases until they receive the next assignment often by phone calls from the clients they already have or clients’ references. Besides, they use newspaper and digital media announcements to offer their services to the clients. Thus, the site is used for parking the trucks temporary until they receive new assignment in different ongoing constructions sites within Nursultan (Astana) city as well as in other provinces of Kazakhstan such as Karaghandy and Pavlodar provinces, as well as Ekateringburg and other areas of Russia near Kazakhstan border. Change of the location for parking their trucks to two nearby parking lots while waiting for the orders and assignments from the clients do not have any adverse impact to their business.

61. There are two alternative parking lots located within the same street in distance about 150 and 700 meters from the site, which the drivers are offered to use by Nursultan city Akimat. The drivers were consulted and interviewed about moving to two neighbouring parking lots, based on which, nearby alternative parking lots does not have any adverse impact to their business due to the described nature of their business and communication methods they use to attract new clients. The drivers were informed about the established project-specific GRM, and the contact information of Grievance Redress Mechanism (GRM) responsible persons from KVK were provided to the drivers for their references. Further monitoring is envisaged to follow-up and monitor the process.

62. Parking lot 1 is located about 150 away from the site. It is about 500 m2. The parking lot 2 is located about 700 meters and the area is about 150000 m2). These two parking lots currently being used by about 65 trucks but they can accommodate up to 400 trucks.

Page 35: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

27

Photo 16. Site for construction of the KVK Headquarters building

Photo 17: Parking lot 1.

Page 36: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

28

Photo 18: Parking lot 2.

F. Project Category for Involuntary Resettlement and Indigenous People Impact

63. Based on the above-listed due diligence findings no involuntary resettlement impact is anticipated. No Indigenous People or such minority groups live in the project area. The project is Category “C” both for involuntary resettlement and indigenous people impact as per ADB SPS (2009). Attachment 5 and 6 present the Involuntary Resettlement and Indigenous People Impact Checklists.

Page 37: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

29

DISCLOSURE, PUBLIC CONSULTATION AND COMMMUNICATION PLAN

A. Proceedings of six public consultations in all four provinces

64. Six project disclosure and public consultations were conducted in all four project provinces covering all the project districts and subprojects:

(i) In East Kazakhstan province – two disclosure and public consultations (15 November 2018, and 26 February 2019);

(ii) In Karaghandy province – two disclosure and public consultations (27 November

2018, and 28 February 2019);

(iii) In Kyzylorda province – one disclosure and public consultations (20 November 2018); and

(iv) In Zhambyl province- one disclosure and public consultations (22 November 2018).

65. The residents and farmers from all the projects districts and subprojects participated in the public consultations, which were chaired by the Heads and Deputy Heads of the respective districts and regional branches of KVK and Akimats. Announcements about the date and time of all the six public consultation were made in the local newspapers at least a week ahead.

66. KVK and Aklimats staff presented the key aspects of the project, the project proposed works. Following this, the social (resettlement) and environmental safeguards requirements of ADB’s SPS (2009) were presented and discussed with the participants including:

(i) The proposed works and outputs of the project; (ii) Environmental, gender policy and social (resettlement) safeguards of ADB’s SPS

(2009) and national laws that will be applied in the project, if there will be such impact;

(iii) GRM developed for the project following the ADB’s SPS (2009) and laws of Kazakhstan to resolve the complaints the affected persons or public may have during the project implementation;

(iv) Questions and suggestions of participants about the project design and implementation; and

(v) The project’s tentative implementation timeline. 67. All presentations and discussions were carried out in Kazakh and Russian languages. The project information brochures including the resettlement safeguards principles of ADB’s SPS (2009) and laws of Kazakhstan in case of unanticipated impact, and GRM were handed out to the participants in two languages. Power point presentation were used in the public consultations.

68. The farmers and residents expressed their need for the project and raised number of questions and proposals about the technical design and implementation of the project. Detail proceedings of all six public consultations in Kazakh and Russian and the list of participants are given in the attachment 7 for all four provinces. Summary of the key questions and proposals are given below for each province.

Page 38: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

30

B. Summary of the questions and proposals per provinces

69. East Kazakhstan province: The summary of the questions and proposals the farmers and residents discussed in the first public consultations in the province:

a) Proposal 1: Include in the detailed design the reconstruction of inter-farm distribution canals that go from the main canals during the project implementation;

b) Proposal 2: To finance and introduce new technologies in the irrigation systems; and c) Proposal 3: Include the raising of water level in Aktogan Canal in the detailed design

(geotags) because the water level in Aktogan Canal is below the ground level at this time.

70. The summary of the farmers and residents’ questions and proposals discussed in the second public consultations in the province:

a) Proposal 1: As the project will restore the existing canals which are in poor conditions now as all are aboveground canals, the concrete lining canals are needed in our area.

b) Question 1: What is the ADB gender policy?

Answer: According to the ADB Gender Development Policy, the gender issues shall be mainstreamed in the projects to improve social and economic conditions for women, and their participation in the project implementation. In this project, the activities under the project Gender Actions Plan will be implemented for gender and development.

c) Question 2: Will the losses (if any) compensated as per ADB Policy or laws of

Kazakhstan? Answer: The LARP will be prepared as per the laws of Kazakhstan and ADB ‘s SPS (2009) that provides the principle of compensation at the replacement cost. In case of discrepancies of the Kazakhstan’s laws and ADB ‘s SPS (2009), the later will prevail. Also, on January 21, 2019, the law of Kazakhstan "On State Property" was amended that provides compensations of losses due to land acquisition for the state needs shall be paid at market value.

d) Question 3: If the project envisages the inputs of the marketing consultant, will he/she

promote the products of certain farms in the market? Is this a competitive advantage? Answer: It will not be promotion of products in the market, but training on marketing.

71. Karaghandy province: The summary of the farmers and residents’ questions and proposals discussed in the first public consultations:

a) Question 1: What will be the water tariff after the project implementation? Answer: Currently, there is single water tariff in Kazakhstan: 0.24 tenge per 1m3. Public consultations will be held if there will be any changes in the tariffs, which will be analyzed and approved by the Antimonopoly Agency and other authorities.

b) Question: Does the project include the area of my land plots for irrigation? Answer: As per local executive authorities, the feasibility study includes the lands of your Collective Farm, i.e. modernization of the main canals that will deliver water to your fields.

c) Proposal 1: Include in the project implementation works, the determination of soil

salinity and ameliorative and drainage activities (farmer).

Page 39: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

31

d) Proposal 2: As the project will modernize irrigation networks for irrigated lands (13,384 ha in Bukhar-Zhyrau district), it is requested to include additional extension of main canals (farmer).

72. The summary of the farmers and residents’ questions in the second public consultations:

a) Question 1: Does the project provide for the employment of the local population? Answer: During the project implementation, the normally the hiring of the interested local residents may be given preference and the hiring process will be managed by the contractors.

b) Question 2: Does the project envisage implementation in the Turkestan province?

Answer: There is another project in the Turkestan province, that is financed by other sources.

c) Remark: The Environmental Impact Assessment should provide information also about

possible emissions. It should be taken into account also the (a) protected zones and forest belts along the rivers and reservoirs, the presence of rare and endangered plant species listed in the Red Book of Kazakhstan, and (b) the migration routes and habitats of wild animals, prohibit the capture and hunting of wild animals, and (c) regarding the water resources, it is necessary to calculate the water consumption and water balance and possible negative impacts on water bodies (Head of Natural Resources and Regulation).

73. Kyzylorda province: The summary of the farmers and residents’ questions during the public consultations in the province:

a) Question 1: How will payments for environmental issues be handled? Answer: The project provides for a fee for the issue of environmental protection.

b) Question 2: Why a very small land area in Zhanakorgan district included in the project

(441 ha)? Answer: Another project (PUID-3) in the Kyzylorda province envisages rehabilitation of more than 143,000 hectares, including 35,000 ha in the Zhanakorgan district.

c) Question 3: What will be the water tariffs?

Answer: The water tariffs will be set and regulated as per the laws and procedures, and in consultation of the authorities, including the Antimonopoly Agency. There will be more public consultations which will also discuss the water tariffs with the farmers and residents.

d) Question 4: How compensation will be paid in case of acquisition and purchase of land

plots? Answer: Based on the feasibility study, the land acquisition and resettlement are not anticipated as the project will rehabilitate the existing canals that are mostly state-owned and municipality owned (KVK or Communal Services). If the acquisition of land and property will be identified safeguards and mitigation measures and compensations will be paid following the ADB’s SPS (2009) and the laws of Kazakhstan, based on the principle of replacement value. In case of discrepancies in laws and policies, the norms of ADB SPS (2009) will prevail. Sample entitlement matrix is given in the project information brochures distributed to all participants.

e) Question 5: What are the terms and period of the loan repayment to ADB?

Answer: All terms will be known after signing of the loan agreement.

Page 40: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

32

f) Question 6: Does the project provide for reconstruction of inter-farm roads?

Answer: The works on the feasibility study are at the completion stage now. Details will be known after the preparation of detail design and estimation documents.

g) Question 6: Will the topsoil be disturbed? Answer: The Environmental Management Plan includes activities to restore the lands.

74. Zhambyl province: The summary of the farmers and residents’ questions discussed in the public consultations:

a) Question 1: How quarries (stope pits) will be used? Answer: This will be defined by the detail design.

b) Question 2: Will the project consider water supply from Zhienbet water reservoir to

other concrete canals as soil canals are not profitable due to water loss? Answer: The feasibility study considers concrete canals from the Zhienbet water reservoir.

c) Question 3: How the loan from ADB will be repaid and what will be the new water tariff?

Answer: The repayment terms will be known after the loan agreement. Any changes in water tariff rates will be analyzed and agreed with the Antimonopoly Agency and authorities, and discussed in public consultations so everybody can express his/her concerns.

d) Question 4: Does the project consider the construction of water reservoirs?

Answer: As per the state program “Agricultural and Industrial Complex”, construction of a new water reservoirs Akmola in Talas river is considered for irrigation of 6,5 ha lands in Talas district.

e) Question 5: Will there be conducted public consultations at the district level too?

Answer: Yes, during the project detail preparation and project implementation, there will be conducted public consultation covering all aspects of the project in the districts.

C. Communication plan with the project stakeholders

75. Key stakeholders: The key project stakeholders identified at this stage are the farmers and residents of the project area communities, the EA/IA, Akimats, ADB, the Committee of Water Resources, PMU, Constructors and Supervision Consultant and NGOs. The detail stakeholders analysis will be undertaken and stakeholders consultation plan and engagement will be prepared at detail design to ensure their engagement and consultation in the project implementation.

76. Communication methods: Variety of communication and consultation methods will be applied depending on types of the information to be provided, subject and cases, including:

a) Public consultations; b) Individual and group meetings; c) Focus group discussion; d) Information boards and leaflets; e) Radio, posters and other media; f) Letters, etc.;

Page 41: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

33

77. Information to be disclosed/consulted: The approaches and information for stakeholders consultation and engagement will be updated on an on-going basis subject to the project progress and raised issues, and will include the followings:

a) Project disclosure, b) Regular updates to stakeholders on construction progress, timeline of physical works

and its corresponding with the schedule of the irrigation supply schedule, c) Social safeguards measures, including design alternatives and manual works to avoid

impact, d) The project specific GRM and contact information of the responsible persons, e) Location of the temporary bridges as necessary to allow the farmers to cross the

canals/access their farmlands; and f) Grievances resolution status (if any and with relevant claimants).

78. Documenting the process: Minutes of meetings, lists of participants and key issues discussed and decision taken.

79. Timeframe: Continuously during the project implementation, detail design preparation and implementation of the physical works on periodically bases every two or three months and/or as needed depending on needs and issues raised.

80. Detail communication plan with project stakeholders: The key stakeholders will be consulted during the detail design and the detail stakeholder’s consultation plan will be prepared, implemented and updated as needed during the project implementation.

GRIEVANCE REDRESS MECHANISM

A. Objective and responsibility

81. The Project-specific Grievance Redress Mechanism (GRM) is developed following the principles of ADB SPS (2009) and the Law of the Republic of Kazakhstan “On the procedure for considering appeals of individuals and legal entities” (2007 No. 221). GRM is formed to resolve the grievances of the DPs or public related to the project’s involuntary resettlement and environmental safeguards performance, and information disclosure. It will not replace the country’s judicial system, but aims resolve the grievances in effective and fair manner, and will be maintained for the duration of the Project. All grievances and their resolution status will be monitored and reflected in the project’s progress reports.

82. The Grievance Redress Committees (CRCs) are established with responsible staff of the authorities, Akimats and KVK at the district, regional and central levels to take actions and decisions for solving grievances that can be lodged during the project implementation. Awareness about the GRM and people’s access to it is important. Information about the GRM, contact information of the GRM focal persons assigned by KVK, and members of the in the project provinces that includes representatives of relevant authorities and stakeholders should be disseminated to the affected communities and DPs. Different communication means, such as distribution of the project information brochures, posters, local media, public consultations, community and individual meetings, can be used in awareness raising.

83. KVK is responsible for well-functioning of the GRM and should provide the required human and financial resources. KVK will lead the grievances resolution and the work of the GRC for resolving grievances. KVK has assigned 6 of its staff for social safeguards tasks and serve as focal persons for GRM; 1 staff at the central KVK, 2 staff in Karaghandy, 1 staff in Zhambyl, and 1 staff in East Kazakhstan provinces. The local authorities and Akimats have also assigned staff responsible for GRM in the district and regional levels, including their contact information and phone numbers made available for public access (see attachment X

Page 42: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

34

copy of the decisions of respective authorities, Akimats and KVK on assigned responsible persons for GRM).

84. The GRM and the GRCs given below were discussed with KVK staff at the central and regional levels as well as during the public consultations in all four provinces. Based on feedback, experience from other ADB-assisted projects in Kazakhstan, the project specifics and geographic scope, the following grievance resolution process is envisaged under the project.

B. Three levels of grievance resolution

85. The stakeholder’s consultation confirmed the current practice that the residents usually approach to the Akimats for complaints and issues they may have. In some cases, the complainants contact directly the Contractors or KVK. Therefore, the project GRM provides the grievances can be accepted at the offices of all these three actors, registered and forward it by email to the assigned focal person at the central KVK/PMO who will have a consolidated database of all grievances and their status. All complaints and resolution status will be recorded and reported at each level of the GRCs. The steps and the GRCs are given in the table 4 below.

86. The summary of key steps at the District level:

(i) The grievance registration: The staff of the district Akimats, the Contractors and the district KVK appointed as focal persons, will receive and register the grievances (they open a Project Grievance Log Book) and provide acknowledgement of receipt to the complainant. They will put efforts to resolve the grievance at the entry, if not possible, it will be reviewed by the GRC at the district level.

(ii) The grievance processing and resolution: The GRC will resolve the grievance within

seven working days. The complainant should be informed about the decision and actions to be taken.

(iii) The feedback and further actions: If the complainant is not agree with the decision, or if

the resolution of the complaint requires further assessment and actions on a higher level, it will be forwarded to the GRC at the regional level. The complainant should be informed in written form.

87. The summary of key steps at the regional level:

(i) Grievance processing and resolution: KVK will convene the meeting of the GRC to discuss the received grievance (s) and make decision, within ten working days. The minutes of GRC meeting and decisions shall be properly documented and forwarded to the concerned parties.

(ii) Feedback and further actions: If grievance was resolved at the regional level, the

complainant will be informed of the outcome in written form. If the complainant is not agreeing with the decision, or if the resolution of the complaint requires further assessment and decision on higher level, it will be forwarded to the GRC at the central level. The complainant should be informed accordingly.

88. The summary of key steps at the central level:

(i) Grievance processing and resolution: KVK will convene the meeting of the GRC at the central level to discuss the grievance(s) and resolve it within twenty working days.

Page 43: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

35

The minutes of GRC meeting and decisions shall be documented and forwarded to the concerned parties in written form.

(ii) Feedback and further actions: The decision of the GRC on the grievance will be informed

to the complaining party in written form. If the grievance was not satisfied, information will be provided to the complaining party about why the case was not resolved, and how the complaining party can make appeal to the country’s legal system, if wished so.

D. Grievance Redress Committees

89. GRM can resolve the complaints and issues effectively if the GRCs members have adequate authority to make decisions and take actions. In consultations with KVK, staff of the relevant authorities on the managerial levels are proposed for CRCs. KVK will coordinate with the authorities and the regional and district Akimats to confirm the proposed members of the GRCs at the district, regional and central levels respectively. Efforts should be made to include women staff in the CRCs to ensure women perspectives in resolving grievances.

Table 8. GRM levels and composition of the GRCs

District Review and resolving at the district within 7 working days

The entry points: District Akimat, KVK branch, Contractors The complainant (s) can visit, call or send a letter or e-mail or fax to the assigned staff of the Akimats or the Contractor. This local level will be important to give people easy access to GRM. In addition, minor issues can be solved immediately at this level. If not, the grievance will be forwarded for resolution by the GRC at the district level: The District GRC members: (i) Head or Deputy Head of the District KVK; (ii) Deputy of the District Akimat; (iii) Deputy Head of the District Agriculture Unit; (iv) KVK assigned focal person; (v) Representatives of the affected persons or communities; (vi) Supervision Consultant, Contractors (during the project implementation);

and (vii) Other specialized agencies and experts if required by the case specifics.

Regional Review and resolving at the province level within 10 working days

The regional CRC members: (i) Head or Deputy Head of the regional KVK; (ii) Deputy of the Regional Akimat; (iii) Deputy Head of Agriculture Unit, (iv) Representatives of the affected persons or communities; (v) Supervision Consultant, Contractors (during the project implementation);

and (vi) Other specialized agencies and experts if required by the case.

Central Review and resolving at the KVK Central level within 20 working days

The Central CRC members: (i) Head or Deputy Head of the Central KVK/ PMO; (ii) Representatives of the Committee of Water Resources; (iii) Representatives of the affected persons or communities; and (iv) Other specialized agencies and experts if required by the case.

Page 44: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

36

INSTITUTIONAL ARRANGEMENT AND MONITORING

90. Planning, implementing and monitoring social and resettlement safeguard mitigation measures, and when needed LARP(s), will require resources and coordination of all stakeholders in project implementation. Their key roles are summarized below.

A. Asian Development Bank

91. ADB will carry out monitoring and supervision on social and environmental safeguards performance during the project implementation. This will include periodical review and screening the project area and resettlement safeguards compliance and mitigation measures, and clear contract awards signing and initiation of civil works. If KVK fails to comply with the agreement covenants on safeguard requirements, including those described in the ADB’s SPS (2009), ADB will seek corrective measures and work with KVK to bring it back into compliance.

92. ADB will arrange capacity building activities, such as training workshops and on-job trainings to the staff of KVK and stakeholders as necessary.

B. The Executing Agency – KVK

93. KVK as an EA is responsible to ensure the social and resettlement safeguards compliance and timely identify any unanticipated resettlement impact. In case of unanticipated resettlement impact in any sub-project, KVK shall prepare and endorse LARP in compliance with ADB SPS (2009) and implement it before the commencement of physical works. KVK will coordinate with Akimats and other authorities’ preparation and implementation of LARP(s), provide adequate resources according to the impact scope, resolving grievances and conduct regular monitoring on the safeguard compliance.

94. KVK will ensure the Contractors compliance performance with social and environmental safeguards risks mitigation and management plans. KVK shall (i) include in contractors’ contracts relevant provisions on the social and environmental safeguards compliance, (ii) conduct regular monitoring for contractors safeguards performance are satisfactory, and (iii) ensure that no physical or economic displacement takes place until LARP (if needed) is implemented.

95. A project steering committee (PSC) will be established. To be chaired by the Minister of Agriculture, the PSC will comprise representatives from the Ministry of Finance, Ministry of National Economy, CWR, KVK, and other agencies. The PSC will (i) guide policy and strategic direction, (ii) review and evaluate project performance, (iii) resolve issues affecting project implementation as needed, and (v) facilitate inter-agency coordination. The PSC shall meet at least twice a year.

96. A Project Management Office (PMO) will be set up in the central KVK office to manage the project activities including ensuring compliance with ADB and the government’s environment and social safeguards’ requirements. A Project Implementation Unit (PIU) will be set up in KVK branch offices in the East Kazakhstan, Karaghandy, Kyzylorda and Zhambyl provinces.

97. The project manager will be supported by teams of specialists including the environmental and social safeguards, and gender and social development specialists. The PMO and PIUs will be supported by international and national consultants recruited by the project. The PIU will have a full-time designated safeguards specialist who, with support and coordination from other officials and agencies as needed, will oversee the social safeguards compliance in the project implementation.

Page 45: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

37

B. Capacity Development Needs

98. KVK is responsible to ensure the social safeguards compliance, identify and mitigate any unanticipated resettlement impact due to the project. Given this is a first ADB-assisted project for KVK, the staff needs capacity building and awareness about the social and involuntary resettlement safeguards concepts and requirements of ADB SPS (2009) to ensure the safeguards compliance and effective implementation of the project.

99. KVK has no designated staff for social and resettlement safeguards. In this project, 6 staff are assigned (1 at the central and 5 at the regional levels) for social safeguards tasks and perform as focal persons for GRM (attachment 8). Such workload cause concerns if these staff will be able to address the safeguards issues and requirements on-time to ensure compliance for a project with such a large scope.

100. To avoid risks of social safeguards incompliance and delays in the project implementation, it is recommended:

(a) KVK will assign designated staff and allocate budget: Given the large scope of the project and lack of institutional capacity and experience of KVK in social and resettlement safeguards, KVK should (i) assign designated staff on social safeguards: at least one staff unit per each project provinces and one at the central KVK, and (ii) allocate budget as required.

(b) ADB will arrange capacity building for KVK and stakeholders: (i) workshops on

social and environmental safeguards and the requirements of the ADB SPS (2009) and its good practices for the KVK and stakeholders (KVK, Akimats, consultants, contractors, valuation companies and others), and (ii) ongoing on-job training and guidance for KVK staff during the project implementation.

Page 46: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

38

C. Akimats and other state agencies

101. Akimats have key role to ensure the social safeguards during the project implementation. As per law, they are key agency to address the appeals and complaints of residents. They will provide administrative support to the EA in project implementation, assist in resolving grievances, as well as in conducting disclosure and public consultations with project communities. The representative of respective Akimats are part of the GRM.

D. Supervision Consultant and Contractors

102. The Supervision Consultant (SC) will assist KVK in all task related to resettlement safeguards compliance, including (i) regular monitoring and preparing bi-annual safeguards monitoring reports for ADB review, (ii) in case of unanticipated resettlement impact, assist the KVK to prepare and implement LARP, (iii) monitoring the Contractors safeguards performance and (iv) provide guidance and corrective actions for identified safeguards incompliances.

103. Contractors shall (i) follow the social, resettlement and environmental safeguards in the project sites, (ii) on a day-to-day basis, monitor their own environmental and social safeguards performance and that of all its subcontractors throughout the project duration, and (iii) submit periodic reports to KVK.

104. They shall allocate designated staff and resources to ensure monitoring social and environmental safeguards, consultation with residents resolving grievances of people who believe are adversely affected by the project.

MONITORING AND REPORTING

105. KVK shall conduct a regular internal monitoring for safeguards compliance, resolving of grievances of people who believe are affected by the project, and identify any unanticipated involuntary resettlement impact raised during the project implementation. This will allow to plan and implement timely the resettlement safeguard mitigation measures in compliance with ADB’s SPS (2009) and Kazakhstan laws and avoid project delays. The monitoring outcomes should be reflected in the project progress reports to be submitted to ADB.

106. Bi-annual social and resettlement safeguards monitoring reports shall be submitted to ADB reflecting any changes in the project design and unanticipated impact, grievances and their resolution status and public consultations. In case of any unanticipated land acquisition and resettlement impact, the safeguards monitoring indicators and reporting requirements will be defined according to the significance of impact and ADB SPS (2009).

CONCLUSION

107. According to the due diligence findings no involuntary resettlement impact is anticipated. No Indigenous People or such minority groups live in the project area. The project is Category “C” both for involuntary resettlement and indigenous people impact as per ADB SPS (2009). Any unanticipated resettlement impact will be addressed according to ADB SPS (2009) and laws of Kazakhstan.

Page 47: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

39

Attachment 1. List of the canals and ditches to be rehabilitated

2.1. List of projects in East Kazakhstan province

Sl.No.

Name of project Length, km

Carrying capacity m3/sec

Location Area, thous.ha

command rehabilitation

1 MC Altai 11,00 1,06 Kurchum district

2,997 2,997

2 MC Tore-Togam 10,30 2,8 Kurchum district

4,754 4,754

3 MC Zhaugashty 7,73 1,2 Kurchum district

0,900 0,900

4 Canal Kerzhachii 11,32 1,2 Kurchum district

3,183 3,183

5 MC Shukinskii 14,20 1,44 Kurchum district

1,318 1,318

6 MC Cherepanovskii 2,34 0,3 Kurchum district

0,150 0,150

7 MC Srednii 11,43 1 Kurchum district

0,347 0,347

8 MC Karakya 25,00 1,05 Kurchum district

0,785 0,785

9 MC Pobeda 17,88 5,5 Kurchum district

0,600 0,600

10 Canal Derevenskii 10,00 1,55 Kurchum district

0,300 0,300

11 Canal Rovenskii 18,00 4 Kurchum district

0,595 0,595

12 Canal Derevenskii-Zhidely

17,00 0,5 Kurchum district

0,200 0,200

13 Canal Derevenskii-Buran

11,00 0,5 Kurchum district

0,250 0,250

14 MC "Еrezhep" 12,62 1,5 Kurchum district

0,200 0,200

15 MC Bolshoi Nikolaevskii 5,55 0,3 Kurchum district

0,217 0,217

16 MC "Levoshalinskii" 2,59 0,35 Kurchum district

0,100 0,100

17 MC Sandytogan 12,50 0,35 Kurchum district

0,105 0,105

18 MC Popovskii 3,22 0,35 Kurchum district

0,100 0,100

19 MC Lopatinskii 2,58 0,2 Kurchum district

0,100 0,100

20 MC "Ipatyevskii" 2,12 0,35 Kurchum district

0,007 0,007

21 MC "Zhana Togam" 3,49 0,054 Kurchum district

0,045 0,045

22 MC "Tentekskii" 3,56 0,2 Kurchum district

0,005 0,005

Total 215,43

17,258 17,258

23 MC Begetai 12,00 0,60 Tarbagatai district

0,650 0,650

24 MC Kazakbai 18,00 0,80 Tarbagatai district

0,563 0,563

25 MC Karasha 21,00 1,60 Tarbagatai district

0,743 0,743

Page 48: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

40

26 MC Bolat 24,00 1,30 Tarbagatai district

0,600 0,600

27 MC Karatogan 23,00 1,50 Tarbagatai district

0,909 0,909

28 Main canal Dauletbai 2,40 0,35 Tarbagatai district

0,640 0,640

29 on-farm canal Zhanbike 4,39 1,10 Tarbagatai district

0,900 0,900

30 MC Ryurikovskii (МC "Burymbet")

8,20 3,00 Tarbagatai district

1,200 1,200

Total 112,99

6,205 6,205

31 MC Otgonnyi 34,0 2,00 Urdzhar district

0,350 0,350

32 MC Nazar-Oral 7 1,50 Urdzhar district

0,700 0,700

33 MC Toktybai 9,1 1,50 Urdzhar district

1,259 1,259

34 MC Soedinitelnyi 25,0 4,00 Urdzhar district

3,800 3,800

35 MC "Amankeldy" 10 2,00 Urdzhar district

0,800 0,800

36 MC "Almaly" 5 0,50 Urdzhar district

0,762 0,762

37 MC "Shoshkaly" 2 0,50 Urdzhar district

0,150 0,150

38 MC "Kyzylshoky" 5,0 0,50 Urdzhar district

0,206 0,206

39 MC "Akbastau" 4 0,50 Urdzhar district

0,300 0,300

40 MC "Zhanai" 4 1,00 Urdzhar district

0,400 0,400

41 MC Koktal* 25 0,50 Urdzhar district

0,084 0,084

42 On-farm canals of river system Eginsu

96,65

Urdzhar district

2,895 2,895

Total 226,75

11,706 11,706

43 MC Goltsovskii 5,50 0,71 Zharma district

0,474 0,474

44 MC Bogenbai* 4,95 1,40 Zharma district

0,650 0,650

45 MC Korykshar 13,50 3,90 Zharma district

3,180 3,180

46 MC Trudovoi* 7,50 2,50 Zharma district

2,260 2,260

47 MC Aktogan 21,80 6,3 Zharma district

14,304 14,304

Total 53,25

20,868 20,868

48 On-farm canals of river system Chigilik

2,20 Kokpekti district

1,719 1,719

Total 2,20

1,719 1,719

On-farm canals of river system Uidene, including

49 ЛХ-4 3,70 Zaisan district

0,376 0,376

50 ЛХ-5 4,60 Zaisan district

0,375 0,375

51 ОХ-2 5,60 Zaisan district

0,423 0,423

Page 49: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

41

52 ОХ-2А 1,80 Zaisan district

0,135 0,135

53 ОХ-2Б 3,20 Zaisan district

0,547 0,547

54 ОХ-3 5,40 Zaisan district

0,429 0,429

55 ОХ-4 5,20 Zaisan district

0,528 0,528

56 ОХ-5 5,10 Zaisan district

0,381 0,381

57 ОХ-6 3,10 Zaisan district

0,513 0,513

58 ОХ-7 3,70 Zaisan district

0,449 0,449

59 ОХ-8 4,20 Zaisan district

0,669 0,669

60 ОХ-9 5,30 Zaisan district

0,699 0,699

61 ОХ-10 5,00 Zaisan district

0,469 0,469

62 ЛХ-3 2,90 Zaisan district

0,358 0,358

63 ОХ-1-1 4,10 Zaisan district

0,564 0,564

64 ОХ-1-2 4,30 Zaisan district

0,387 0,387

65 Ох-1-3 3,80 Zaisan district

0,546 0,546

66 Ох-1-4 1,90 Zaisan district

0,449 0,449

67 Ох-1-5 5,80 Zaisan district

0,258 0,258

68 АХ-1 7,90 Zaisan district

0,445 0,445

69 МХ-1 6,50 Zaisan district

0,393 0,393

70 МХ-2 5,00 Zaisan district

0,341 0,341

71 МХ-3 3,80 Zaisan district

0,348 0,348

72 МХ-4 4,20 Zaisan district

0,284 0,284

73 АХ-1-1 4,30 Zaisan district

0,220 0,220

74 ОПХ-1 2,70 Zaisan district

0,186 0,186

75 ОПХ-2 2,20 Zaisan district

0,114 0,114

76 ОПХ-3 1,90 Zaisan district

0,092 0,092

77 ОПХ-4 1,00 Zaisan district

0,083 0,083

78 ОПХ-5 1,60 Zaisan district

0,100 0,100

79 ОПХ-6 1,10 Zaisan district

0,041 0,041

80 ОПХ-7 2,60 Zaisan district

0,248 0,248

Page 50: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

42

81 ОПХ-8 2,80 Zaisan district

0,326 0,326

82 ОПХ-9 3,40 Zaisan district

0,228 0,228

83 АХ-2 4,30 Zaisan district

0,532 0,532

84 АХ-3 4,10 Zaisan district

0,464 0,464

On-farm canals of river system Kendirlik, including

85 Ak-Komei 2,70 Zaisan district

1,082 1,082

86 Sotnya-1 1,90 Zaisan district

1,082 1,082

87 Sotnya-1а 2,20 Zaisan district

0,582 0,582

88 Sotnya-2 1,00 Zaisan district

1,382 1,382

89 Sotnya-3 1,60 Zaisan district

0,582 0,582

90 Kok-Koshkar 1,10 Zaisan district

0,882 0,882

91 Konyr Buka 2,60 Zaisan district

0,582 0,582

92 Levyi -1 2,80 Zaisan district

1,582 1,582

93 Levyi -2 3,40 Zaisan district

0,882 0,882

94 Levyi -3 4,30 Zaisan district

0,482 0,482

95 Trudovoi 4,10 Zaisan district

0,682 0,682

96 Saryeshki 14,00 Zaisan district

0,182 0,182

97 Cholak Togam 14,00 Zaisan district

0,182 0,182

98 Zhymsak aral 14,00 Zaisan district

0,282 0,282

99 Kara Kas 7,08 Zaisan district

0,382 0,382

100 Koldenen tal 5,00 Zaisan district

0,382 0,382

101 Torbie 8,00 Zaisan district

0,282 0,282

Total 227,88

24,494 24,494

Total on EKO 838,49 82,250 82,250

* no longer included in the project scope.

Page 51: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

43

List of projects on Zhambyl province

No. Name Locations (r/d) Carrying capacity, m3/sec

Length, km

types of works Comm

and area,

ha

including

mechanical cleaning

concrete ЛР100 ЛР-80 ЛР-60 used not used

Sarysu district

1 mc Otvodyyashii-2 Saudakent 1,0 1,0 1,0

2 off-farm canal Balatogan Saudakent 0,5 11,0 11 70 70

3 mc Tasaryk Zhanatalap 4,0 15,0 15 600 358 242

4 off-farm canal Dyuker Zhanatalap 0,5 5,3 2,9 1,62 0,78 0 0 200 200

5 on-farm canal Saryozek Zhanatalap 3,0 5,0 5 256 256

6 mc Karitogan new Zhanatalap 3,0 7,982 7,982

7 mc Karitogan old Zhanatalap 0,5 3,763 3,763

8 off-farm canal Р-1 Zhanatalap 1,0 1,3 1,3

9 on-farm canal Kultobe Saudakent 0,5 2,5 2,5 100 100

10 on-farm canal Utes Igilik 1,0 6,7 6,7 795 795

11 off-farm canal Baishakhan Igilik 1,0 9,3 8,28 1,02 0 0 1021 1021

12 off-farm canal Kedei Zhanatalap 1,0 5,0 4,64 0,36 0 0 759 759

13 mc nizhnii Berkutty Zhaiylma 3,5 8,8 8,8 369 232 137

14 off-farm canal Berkutty Zhaiylma 1,0 8,0 7,28 0,72 0 0 180 0 180

15 off-farm canal Kirov Zhaiylma 0,5 0,9 0,9 387 387

16 off-farm canal Kyzyl Tu Zhaiylma 0,5 1,9 1,9 266 266

16 Total 93,445 44,463 46,10 2,88 0,00 0,00 5003 4374 629

Talas district

1 mc Zhiembet R/d Bostandyk 6,0 4,5 4,5

2 off-farm canal Abish R/d Bostandyk 0,5 6,7 3,196 3,504 267 66 201

3 off-farm canal LBMC Zhiembet

R/d Bostandyk 1,5 10,2 10,2 1039 282 757

4 off-farm canal Uzyn R/d Bostandyk 5,0 7,9 7,9

Page 52: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

44

5 off-farm canal PBMC Zhiembet

R/d Akkum 1,4 8,3 8,3 530 362 168

6 on-farm canal Akkum R/d Akkum 1,0 8,2 0 8,2 527 432 95

7 on-farm canal Kokkol R/d Bostandyk 0,4 4,2 0 4,2 210 90 120

8 on-farm canal Zhambas R/d Akkum 0,4 2,0 0 2 120 45 75

9 on-farm canal Zhambyl R/d Bostandyk 0,3 3,0 0 3 80 21 59

10 on-farm canal Lotok R/d Akkum 0,4 5,6 5,36 0,24 227 136 91

11 on-farm canal Sharyashylyk R/d Shakirov 3,0 12,2 12,2 924 21 903

12 mc Kydyr R/d Bostandyk 2,0 7,1 7,1 243 0 243

13 mc Kazakhbai R/d Shakirov 2,0 10,0 10 448 211 237

14 mc Zhumabek R/d Shakirov 5,0 12,9 12,9 925 71 854

15 mc Boribai R/d Uyk 6,0 27,1 27,1 350 197 153

16 off-farm canal Boribai-2 R/d Uyk 3,0 6,5 6,5 206 66 140

17 mc Zhadik R/d Uyk 1,0 3,8 3,8 80 60 20

18 mc Oiyk R/d Uyk 23,0 5,4 5,4

19 off-farm canal LBMC Oiyk R/d Uyk 10,0 27,1 17,1

20 on-farm canal УХ-1 R/d Uyk 1,0 2,8 2,8 586 120 466

21 on-farm canal УХ-2 R/d Uyk 0,5 2,1 2,1 307 160 147

22 on-farm canal КХ-1 R/d Uyk 0,5 2,0 2 355 118 237

23 on-farm canal КХ-2 R/d Uyk 0,5 3,7 3 0,7 1005 0 1005

24 on-farm canal ТХ-1 R/d Ucharal 0,7 2,7 2,7 758 0 758

25 on-farm canal ТХ-2 R/d Ucharal 0,5 5,0 5 921 0 921

26 on-farm canal ВХ-1 R/d Kenes 0,5 0,8 0,8 250 0 250

27 on-farm canal ВХ-2 R/d Kenes 0,5 1,0 1 350 0 350

28 off-farm canal PBMC R/d Uyk 13,0 1,9 1,9 0

29 off-farm canal МLR R/d Uyk 13,0 13,0 13 0

30 mc Bakhtymbet R/d Kenes 3,0 6,9 6,9 118 99 22

31 mc Sultan R/d Akkol 10,0 0,624 0

32 off-farm canal Orta Aryk R/d Akkol 5,0 7,618 7,618 290 290 0

Page 53: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

45

33 on-farm canal Orynbasar R/d Akkol 0,5 4,0 4

34 off-farm canal Zhanatogan R/d Akkol 3,0 4,939 2,465 2,474 20 20 0

35 off-farm canal Kyzyl R/d Kyzylaut 25,0 8,2 8,2 220 100 120

36 mc Aktogan R/d Tamdy 6,0 2,6 2,6 0

37 mc Kokoiyk R/d Tamdy 2,5 5,283 5,283 201 61 140

38 reservoir Zhartas R/d Tamdy 309 190 119

39 reservoir Mynchukir R/d Tamdy 260 131 129

40 reservoir Tamdy R/d Tamdy 207 107 100

41 reservoir Kyzylaut R/d Kyzylaut 736 299 437

41 Total 247,864 122,144 78,734 8,2 15,458 12,704 11557 3028 9317

Т. Ryskulov district

1 мк Karakystak Karakystak 6,5 6,4 4

2 on-farm canal ККPТ Zhanatyrmys 2,0 3,3 2,1 1,2 805 622 183

3 off-farm canal Botbai Karakystak 1,8 5,2 3,82 1,38 839 224 615

4 on-farm canal Botbai-Sikhym Karakystak 0,7 5,7 5,388 0,312 524 357 167

5 on-farm canal Karakat Karakat 0,5 12,4 10,672 0,582 1,146 517 270 247

6 on-farm canal Shonger Kulan 0,8 13,5 12,984 0,516 644 344 300

7 on-farm canal Kokdonen Abai 0,8 15,9 15,66 0,24 325 90 235

8 on-farm canal Kogershin Kogershin 0,8 9,8 9,428 0,372 630 466 164

9 on-farm canal Shal-su Kumaryk 0,5 9,5 9,5 537 481 56

10 Taldy-su Zher Aryk 0,5 17,2 17,2 103 103 0

11 on-farm canal Тuyк-тоr Ornek 0,5 10 10 119 29 90

12 on-farm canal Сulu тоr Ornek 0,5 16,8 16,8 151 41 110

13 on-farm canal Маkpal Teren ozek 0,5 10,25 10,25 262 62 200

14 on-farm canal Маmai kaiyndy

Kaiyndy 0,5 13,4 13,4 100 59 41

15 on-farm canal Kaiyndy Kaiyndy 0,5 6,4 6,4 403 179 224

16 Wells 19 nos. 0 0 2038 2038

35 Total 155,750 83,550 64,052 1,2 2,646 1,902 7997 3327 4670

Shu district

Page 54: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

46

1 MC "Таsotkel"

Eski-Shu, Zhana-zhol, Berlikustem,

Konayev, Zhanakogam

45,0 39,035 0

2 off-farm canal Р-1 Zhanakogam 5,0 13,7 8,82 1,5 1,38

3 off-farm canal Akshatogan Eski-Shu 1,5 9 9 220 100 120

4 off-farm canal ТБХ-1 Eski-Shu 0,9 6 3,12 1,5 1,38 640 400 240

5 off-farm canal ТБХ-2 Eski-Shu 1,0 5,5 2,08 1,02 2,4 1000 450 550

6 off-farm canal ТБХ-3 Eski-Shu 0,5 2,5 1,6 0,48 0,42 200 200 0

7 off-farm canal ТБХ-4 Eski-Shu 0,05 3 1,56 0 1,44 67 67 0

8 off-farm canal ТБХ-5 Eski-Shu 0,05 3 1,8 0 1,2 74 74 0

9 off-farm canal Yntaly Eski-Shu 0,06 2 0,996 1,004 500 400 100

10 off-farm canal Тнх-1 Zhana-zhol 0,5 8,685 4,545 1,62 2,52 800 690 110

11 off-farm canal ТНХ-1б Zhana-zhol 0,25 7,32 4,32 1,74 1,26 560 470 90

12 off-farm canal ТНХ-2 Zhana-zhol 2 10,5 2,05 5,45 0,84 2,16 771 601 170

13 canal Toganbai Zhana-zhol 0,25 1,5 0,78 0,72 39 39 0

14 off-farm canal Truba-2 Zhana-zhol 0,5 0,017 0 0,017 100 100 0

15 off-farm canal ТЧХ-1 Berlikustem 0,25 6,1 5,2 0,18 0,72 390 390 0

16 off-farm canal ТЧХ-2 Berlikustem 1,4 7,8 7,02 0,24 0,54 800 608 192

17 off-farm canal ТЧХ-3а Berlikustem 0,7 15,1 13,638 0,042 0,42 600 530 70

18 off-farm canal ТЧХ-3б Berlikustem 0,08 0,3 0,3 150 74 76

19 off-farm canal ТЛХ-1-1а Konayev 1,2 8,885 6,385 1,5 350 300 50

20 off-farm canal ТЛХ-1-1б Konayev 0,8 6 4,92 0,72 0,36 330 170 160

21 off-farm canal ТЛХ-1а Konayev 0,8 8,68 5,75 0,72 0,21 500 310 190

22 off-farm canal ТЛХ-1б Konayev 0,8 6 5,19 0,48 0,33 450 200 250

23 off-farm canal ТЛХ-2 Konayev 0,8 5,1 3,84 0,72 0,54 190 150 40

24 off-farm canal ТЛХ-3 Konayev 0,2 5,6 4,22 0,3 1,08 284 45 239

25 off-farm canal ТЛХ-4 Konayev 1,5 8 6,38 0,72 0,9 1073 669 404

26 off-farm canal ТЛХ-5 Konayev 0,7 9,8 5,288 1,02 0,492 700 550 150

27 off-farm canal ТДЖХ-1 Zhanakogam 0,7 15,32 13,32 800 565 235

28 off-farm canal ТДЖХ-2 Zhanakogam 0,6 8 8 700 530 170

Page 55: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

47

29 off-farm canal ТДЖХ-3а Zhanakogam 1,3 7 6 360 360 0

30 off-farm canal ТДЖХ-3б Zhanakogam 0,7 7 6 350 120 230

31 off-farm canal ТДЖХ-4а Zhanakogam 0,5 0,05 0,05 180 110 70

32 off-farm canal ТДЖХ-4б Zhanakogam 0,5 5 4,4925 0,375 107 70 37

33 off-farm canal ТДЖХ-5 Zhanakogam 0,5 0,066 0,066 364 274 90

34 off-farm canal ТДЖХ-6 Zhanakogam 0,5 2,1 2,1 1218 838 380

35 off-farm canal К-1 osnovnoi Zhanakogam 0,4 5,6 5,6 302 302 0

36 off-farm canal Р-1 Dalakainar 0,2 2 1,4 0,36 0,24 280 280 0

37 off-farm canal Р-2 Dalakainar 0,2 4 2,98 0,6 0,42 395 180 215

38 off-farm canal Р-3 Dalakainar 0,2 3,8 2,72 0,6 0,48 220 95 125

39 off-farm canal Р-4 Dalakainar 0,2 3 3 202 102 100

40 off-farm canal Dalakainar -2 Dalakainar 0,4 6 6 270 270 0

41 Levoberezhnyi MC Alga, Shu t.,

Tolebi, Koragaty 16,6 38,8 38,8 0

42 canal Lugovoi Alga 0,3 1,72 1,72 178 78 100

43 canal Kuigen Alga 1,5 18,81 18,783 0,027 1089 499 590

44 canal Zhaisan Alga 0,5 1,54 0,085 1,455 65 30 35

45 canal Novotroisk Alga, Shu t.,

Ondiris 1,0 7,743 7,743 600 0 600

46 canal Pioneer Shu t. 0,7 2,65 2,615 0,035 405 390 15

47 canal Salyamov Shu t. 0,5 1,34 1,3 0,04 50 15 35

48 canal Abai Shu t. 0,1 0,75 0,75 60 60 0

49 canal Togai Shu t. 0,5 0,38 0,38 47 47 0

50 canal Koskudyk Shu t. 0,3 3,13 3,13 190 165 25

51 canal Shu Shu t. 0,5 2,24 1,508 0,732 50 35 15

52 canal Aral Truba Tolebi 0,3 2 2 80 50 30

53 canal ЛНХ-2 Tolebi 2,0 5,61 5,61 1550 1050 500

54 canal Old Кarabas Tolebi 0,3 1,4 1,4 60 60 0

55 canal Saduakas Tolebi 0,3 3,07 3,07 48 48 0

56 canal Мelnichnyiй Tolebi 0,2 0,25 0,25 15 15 0

57 canal Bolnichnyi Tolebi 0,5 0,2 0,2 75 75 0

Page 56: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

48

58 canal ЛНХ-4 Tolebi 0,5 6,27 6,27 750 560 190

59 canal Тurksib Tolebi 0,4 1,61 1,61 150 100 50

60 canal Tailak-1 Tolebi 0,5 0,92 0,92 250 150 100

61 canal Tailak-2 Tolebi 1,1 1,82 1,82 290 198 92

62 canal Tailak-2-1 Tolebi 0,2 2,42 2,42 75 75 0

63 canal Tailak-2-2 Tolebi 0,2 1,63 1,63 224 125 99

64 canal Kunshygys Tolebi 0,4 1,34 1,34 80 80 0

65 off-farm canal Zhidebai-1 Tolebi 0,05 1,64 1,64 80 65 15

66 canal Zemlyanoi Karabas Ondiris 2,0 8,31 8,31 475 200 275

67 off-farm canal Sary Koragaty 0,6 9,47 9,47 350 230 120

68 off-farm canal Estemes-2 Koragaty 0,7 3,67 3,07 0,6 350 270 80

69 off-farm canal ЛДРХ-2 Koragaty 2,0 6,43 6,28 0,15 810 720 90

70 off-farm canal Bimenbet Koragaty 0,5 4,93 4,93 853 228 625

71 off-farm canal Aimanbet Koragaty 1,5 2,8 2,8 335 195 140

72 off-farm canal Asembai Koragaty 0,4 1,99 1,99 203 153 50

73 off-farm canal ЛДРХ-3 Koragaty 2,0 9,7 4,2 5,398 800 510 290

74 off-farm canal Masak Aktobe Aktobe 0,2 12,81 12,81 233 143 90

75 MC "Pravoberzhnyi"

Berlikustem, Konayev, Berlik, Zhanakogam,

Dulat

11,0 48,8 48,8

76 Canal "Bolnichnyi-1" Konayev 0,6 1,18 1,18 95 0 95

77 Canal "Birlik " Konayev, Berlik 0,2 3,24 3,24 82 0 82

78 Canal "Aktogan" Zhanakogam 0,3 5,49 5,49 313 0 313

79 Canal "Кarauyl-tobe" Zhanakogam 0,8 4,5 4,5 464 0 464

80 Canal "Тоkseit" Dulat, Kenes 3,5 4,77 4,77 1003 1003

Vegetable cluster 9300

80 Total 505,431 243,6425 170,988 16,602 21,929 0 29363 18302 20361

172 Grand total 1002,5 493,7995 359,876 28,882 40,033 14,606 53920 29031 34977

Page 57: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

49

List of projects on Karaghandy province

Sl. No.

Name of project Rehabilitated

area, ha

Length, km Carrying capacity, m3/sec

Parameters Type of existing lining Upper

width, m Bed width,

m Construction depth, m

1. Zhartas off-farm main canal, including Irrigation system Koksu

4021,5 18

3,0 from 3 to 4,5

from 1 to 1,5

1,7 reinforced concrete, earthen

2. Samar main canal 697,5 11 1,5 from 3 to 4

from 1 to 1,5

1,5 reinforced concrete, earthen

Total on Abai district: 4719 2 canals-29km

3. Zhazdi main canal 3028 15,812 3,2 from 3 to 4

from 1 to 1,5

1,5 reinforced concrete and flumes, earthen

Total on Zheskazgan с: 3028 1 canal-15,812 km

4. Bidaiik main canal 1117 14,18

1,8 from 3 to 4

1,3-1,5 1,5 reinforced concrete and flumes

Total on Zhanaarka district: 1117 1 canal-14,18 km

5. Shakai main canal r/d Baimyrza

570 8,8 0,83 from 3 to 7

from 0,5 to 0,8

1 reinforced concrete, earthen and steel pipes

6. Karazhar main canal 1156 5,4 1,4 from 3 to 4

from 1 to 2

1,2 Earthen and reinforced flumes

7. Tuzdy main canal 800 13,60 3,0 from 3 to 4

from 1,5-2,0

1,2 Earthen and concrete

8. Zhanatalap v. (r/d Molodetskii) 3496 4 pipelines -15, 8 1,4 1000÷300

9. Samarkandskii r/d 2300 3 pipelines -16,5 2,2 600÷250

Page 58: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

50

10. Central r/d 308 2 pipelines -2,59 0,20 200÷200

11. Gagarin r/d 1158 1 canal combined – 6,2 incl.: 4,21 pipeline and 1,99 - canal

1,0 600

12. Kyzylkaiyn r/d 520 3 pipelines- 3,00 0,70 250÷250

13. Sheshenkara r/d 1416 1 pipeline – 3,4 0,60 600÷600

14. Kokpekti r/d 1660 1 pipeline – 3,1 0,85 800÷800

Total on Buhar-Zhyrau district: 13 384

15 pipelines- 48,6 km, 4 canals -29,79km, Total: 78,39 km

15. Ahmet r/d 530 1 pipeline – 1,675

0,35 300

16. Ahmet r/d 321 1 pipeline – 1,360 0,35 300

17. Baitugan r/d 109 1 pipeline – 0,135 0,15 200

Total on Nura district: 960 3 pipeline -3,17km

18. Zvezdnyi r/d 1048 1pipeline-8,109 1,2 850

19. Karatomar r/d 1040 1 pipeline-9,428 1,2 800

20. Mirnyi r/d 900 1pipeline-10,148 1,0 650

21. Trudovoi r/d 1250 1pipeline-7,553 1,2 800

22. Shiderty r/d 454 1pipeline-3,716 0,6 400

Total on Osakarovsk district: 4692 5 pipelines -38,954 km

Grand total on Karaghandy

province:

27 900 23 pipelines 90,724 km, 8 canals- 88,78 km. Total: 179,5 km

A ruined part of canal Shukai from flumes ЛР8 of 810 m length was added to Karaghandy province. Flumes are on legs, which are supported by foundation blocks.

Page 59: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

51

List of projects on Kyzylorda province

No. Name Locations (r/d) Length,

km

including

Carrying capacity m3/s

Rehabilitated area, ha

earthen/clay sand

concrete

Zhalagash district.

1 ЛВ-5А, Myrzabai Ahun 11,32 11,32 - 8,20 1071,54

2 ЛВ-5А-2 Myrzabai Ahun 2,11 2,11 - 2,60 180,51

3 ЛВ-5Б Myrzabai Ahun 6,22 6,22 - 3,50 531,35

4 ЛВ-5А-6 Myrzabai Ahun 8,06 8,06 - 1,00 310,6

5 Sabit r/d Zhanatalap 2,12 2,12 - 1,50 357,14

6 ЛВ-10В-1, (Jana Shaihy) r/d Zhanatalap 0,13 0,13 - 2,00 105,25

7 ЛВ-10В-1 (Eski Shaihy) r/d Makpakol 1,64 1,64 - 2,00 371,61

8 Sabit r/d Makpakol 4,80 4,80 - 1,50

9 ЛВ-10В-1, (Jana Shaihy) r/d Makpakol 1,72 1,72 - 2,00

10 ЛВ-10В-1 (Eski Shaihy) r/d Makpakol 2,63 2,63 - 2,00

11 Belsendi r/d Karaketken 12,02 12,02 - 3,00 241

12 Р-1 r/d Aksu 3,65 3,65 - 3,00 736,07

13 Б-1 r/d Aksu 3,76 3,76 - 2,00 315,74

Total: 13 canals 60,17 4221

Zhanakorgan district.

1 Р-6-1 r/d Ekpindi 1,50 1,50 - 2,00 8

2 Р-6-4 r/d Ekpindi 2,00 2,00 - 2,00 161

3 Р-6-6 r/d Sunakata 3,00 3,00 - 2,00 182,29

Page 60: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

52

4 Р-6-3 r/d Sunakata 1,00 1,00 - 2,00 90

Total: 4 canals 7,50 441

Kazaly district.

1 Enbek Maidakol 2,67 2,67 - 4,00 97

2 Enbek Maidakol 5,20 5,20 - 4,00

3 Enbek Maidakol 2,73 2,73 - 4,00

4 Zhaikonak Arandy 9,20 9,20 - 2,00 352,5

5 Bozasha Arandy 15,50 15,50 - 3,00 144,9

6 Terikendi Arandy 3,40 3,40 - 2,00 75,6

7 Akaryk No.1 Akzhona 0,09 0,09 - 2,50 10

8 Akaryk No.2 Akzhona 3,81 3,81 - 2,50

9 Akshungil Akzhona 7,43 7,43 - 2,00 514,7

10 Taldy asha No.1 Akzhona 0,07 0,07 - 2,50 44

11 Taldy asha No.2 Akzhona 9,36 9,36 - 2,50

12 Sakybai Maidakol 9,75 9,75 - 6,00 110,7

13 Zhyluan-1 Urkendeu 2,78 2,78 - 2,00

14 Zhyluan-1 Urkendeu 3,37 3,37 - 2,00

15 Zhyluan-1 Urkendeu 2,38 2,38 - 2,00

16 1х-5 Urkendeu 5,33 5,33 - 1,50

17 1х-5 Urkendeu 2,00 2,00 - 1,50

18 1х-5-2-2, 1х-5-2-1 Urkendeu 5,50 5,50 - 1,50

19 1х 5-1-1, lx-5-2, 1х-5-4, 1х-5-6, 1х-5-1, 1х-5-5,1х-5-7 Urkendeu 8,20 8,20 - 1,50

20 Bahy Urkendeu 9,97 9,97 - 5,40 215,6

21 Bahy Urkendeu 0,04 0,04 - 5,40

22 Bahy Urkendeu 2,77 2,77 - 5,40

23 tail Bahy Urkendeu 1,57 1,57 - 2,00

24 tail Bahy Urkendeu 3,55 3,55 - 2,00

Page 61: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

53

25 5х-1-3 Karashengel 7,00 7,00 - 1,00

26 5х-1-3, 1х-5-4, 1х-5-5. Urkendeu 11,70 11,70 - 1,50

27 2х-2 G.Muratbayev 0,27 0,27 - 2,50 109,5

28 Р-2-2 G.Muratbayev 10,00 10,00 - 2,00 121

29 Р-2-2 G.Muratbayev 4,80 4,80 - 2,00 30

30 Kirgiz G.Muratbayev 14,69 14,69 - 2,50 1133,9

31 Зх-6 Kolaryk 7,00 7,00 - 4,50

32 1-7-1К Maidakol 7,30 7,30 - 1,50

33 1-7-3-1К, 1-7-3-2К Maidakol 4,30 4,30 - 1,50

34 4х-1-2-1, 4х-1-2-2,4х-1-2-3. Maidakol 11,40 11,40 - 1,00

35 4Х-1-1-1, 4х-1-1-2, 4х-1-1-5 Maidakol 8,10 8,10 - 1,00

36 Уч-2-1 Arandy 1,30 1,30 - 1,50

37 3-3-1К, section-2 Arandy 4,80 4,80 - 1,00

38 6-3-1К, 6-3-2К, 6-3-3К, 6-3-7К, 6-3-5К. Akzhona 8,56 8,56 - 1,00

39 6-1-1-1К, 6-1-2-1К, 6-1-1К Akzhona 7,90 7,90 - 1,50

40 2Х-1-1, 2Х-1, 2Х-1-2, 2Х-1-4 Akzhona 9,60 9,60 - 1,00

41 2Х-1-7, 2х-1-6, 2х-1-8, 2х-2-3, 2х-2-4 Akzhona 11,90 11,90 - 1,00

42 1х-5-1-2, 1х-5-1-3, 1х-5-1-5, 1х-5-1-1-6 Urkendeu 7,00 7,00 - 1,50

43 5х-1-2 Urkendeu 10,80 10,80 - 1,50 413,1

44 5х-1-2 Urkendeu 5,40 5,40 - 1,50

45 5х-4-5 Karashengel 8,00 8,00 - 1,00

46 5х-2-2 Karashengel 4,00 4,00 - 1,00

47 Р-1-3 Karashengel 4,00 4,00 - 1,00

48 6-2-2К Akzhona 3,10 3,10 - 1,00

49 2х-3-1, 2х-3-2 G.Muratbayev 8,30 8,30 - 1,00

50 2х-1-1, 2х-1-1-5, 2х-1-1-3 Akzhona 7,50 7,50 - 1,00

51 3-1-1К, 3-1-2К Arandy 7,08 7,08 - 1,50

Page 62: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

54

52

3х-6-2-1-1, 3х-6-2-1, 3х-6-2-1-2, 3х-6-2-1-3, 3х-6-2-1-4, 3х-6-2-2, 3х-6-2-2-1, Kolaryk 18,33 18,33 - 1,00 3х-6-2-2-2, 3х-6-2-2-3, 3х-6-2-2-4, 3х-6-2-2-0.

53 3х-6-4-1-16, 3х-6-4-2-3. Kolaryk 4,10 4,10 - 1,00

54 Зх-6-3-2, Зх-6-З-З. Зх-6-З-2-I, Зх-6-3-2-2. Зх-6-3-2-3.

Kolaryk 14,10 14,10 - 1,50 Зх-6-3-2-4. Зх-6-3-3-2. Зх-6-З-З-З. Зх-6-3-3-4.

55 3х-6-3, 3х-6-3-1-1, 3х-6-3-1-2, 3х-6-3-1-3, 3х6-3-1-4, 3х-6-3-2-3. Kolaryk 10,70 10,70 - 1,00

56 Уч-2, Уч-5 Arandy 5,40 5,40 - 1,00

57 3-2К-1, 3-2К-2 Arandy 11,30 11,30 - 1,50 159

58 6-3К Alga 1,77 1,77 - 4,00 195

59 6-3-1-1К, 6-3-1К, 6-3-1-3К, 6-3-2-1К, Alga 10,18 10,18 - 1,50

60 3-1-2-1К, 3-1-2-2К Arandy 4,20 4,20 - 1,50

61 5х-1 canal Karashengel 9,88 9,88 - 1,50 259,1

62 5х-2 canal Karashengel 11,32 11,32 - 1,50 92

63 5х-2 canal Karashengel 1,48 1,48 - 1,50

64 5х-4 canal Karashengel 4,43 4,43 - 1,50 104

65 Р-1 canal Karashengel 6,19 6,19 - 1,50 97,8

66 Shalabai canal Karashengel 5,00 5,00 - 2,00

67 1-МК canal Sarykol 3,05 3,05 - 1,50 440,88

68 1-МК-З canal Sarykol 1,61 1,61 - 1,50

69 1 -МК-5 canal Sarykol 3,41 3,41 - 1,50

70 1-МК-5/1 canal Sarykol 1,73 1,73 - 1,50

Total: 105 canals (35-canal -227,28km, 70-distributing canal -213,33 km) 440,61

4720

Shiely district.

1 Л-4 Aktogan 5,31 5,31 - 2.5 110

2 Zhylandy Aktogan 3,41 3,41 - 2.2 -

Page 63: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

55

3 Р-12-6 Bestam 7,21 7,21 - 8,00 379

4 Р-12-8 Bestam 4,55 4,55 - 6,00 -

5 К-3-8 Bestam 1,40 1,40 - 4,00 -

6 Р-12-8 Bestam 1,69 1,69 - 6,00 -

7 Р-12-6-2-1 Bestam 2,62 2,62 - 3,20 -

8 К-3-8-2 Bestam 2,26 2,26 - 2,20 -

9 К-3-8 Bestam 4,18 4,18 - 4,00 -

10 Р-12-8-3 Bestam 2,91 2,91 - 3,20 -

11 P-12-8-4 Bestam 2,91 2,91 - 3,20 -

12 Р-12-8 Bestam 1,74 1,74 - 6,00 -

13 Р-12-9 Bestam 3,07 3,07 - 5,00 -

14 Р-12-6-4 Bestam 3,25 3,25 - 2,50 -

15 P-12-8-5 Bestam 3,73 3,73 - 2,20 -

16 К-3-11 Bestam 7,18 7,18 - 2,00 -

17 Р-12-6-2 Bestam 2,63 2,63 - 2,00 -

18 P-12-6-2-1 Bestam 1,33 1,33 - 2,00 -

19 Р-12-6-5 Bestam 4,03 4,03 - 2,00 -

20 P-12-8-2 Bestam 1,45 1,45 - 2,00 -

21 P-12-8 Bestam 7,35 7,35 - 6,00 -

22 Р-12-6 Bestam 3,06 3,06 - 8,00 -

23 Р-12-6-2 Bestam 6,36 6,36 - 2,30 -

24 Р-12-8-2 Bestam 2,41 2,41 - 2,00 -

25 Р-5-1 Gigant 1,15 1,15 - 2,50 307,7

26 Р-5-3 Gigant 4,65 4,65 - 2,50 -

27 Р-3-7 Gigant 4,57 4,57 - 2,00 -

28 Р-5-3-1 Gigant 1,26 1,26 - 2,00 -

29 К-4-10-10 Gigant 4,03 4,03 - 2,50 -

Page 64: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

56

30 К-4-3 Gigant 4,55 4,55 - 2,50 -

31 К-4-10 Gigant 1,24 1,24 - 2,50 -

32 К-4-6 Gigant 1,07 1,07 - 2,50 -

33 Р-3-8-2 Gigant 1,33 1,33 - 2,50 -

34 Р-5-1-1 Gigant 0,86 0,86 - 2,00 -

35 Р-3-8-1 Gigant 2,29 2,29 - 1,50 -

36 К-4-1 Gigant 0,45 0,45 - 2,00 -

37 Р-3-7-2 Gigant 1,86 1,86 - 2,50 -

38 Р-5-3 Gigant 1,30 1,30 - 2,50 -

39 P-5-3-3 Gigant 1,27 1,27 - 2,50 -

40 Р-5-1 Gigant 2,01 2,01 - 2,50 -

41 Р-3-7-1 Gigant 1,93 1,93 - 1,50 -

42 P-5-3 Gigant 1,51 1,51 - 2,50 -

43 Р-5-4-3 Gigant 1,24 1,24 - 2,00 -

44 P-5-3-3 Gigant 1,65 1,65 - 2,00 -

45 К-4-1 Gigant 2,25 2,25 - 2,00 -

46 К-4-9 Gigant 0,75 0,75 - 2,00 -

47 К-4-10-2 Gigant 0,91 0,91 - 2,00 -

48 Р-3-4 Gigant 1,95 1,95 - 2,50 -

49 Р-5-3 Gigant 1,41 1,41 - 2,50 -

50 Р-3-4 Gigant 1,24 1,24 - 2,50 -

51 P-5-1-2 Gigant 0,83 0,83 - 2,00 -

52 P-7-12 Iirkol 4,95 4,95 - 2,50 47

53 P-7-12-1 Iirkol 1,70 1,70 - 2,50 -

54 К-7 Iirkol 13,40 13,40 - 3,50 -

55 Р-12-1 Kerdeli 8,20 8,20 - 6,00 316,5

56 Р-12-10 Kerdeli 1,97 1,97 - 2,40 -

Page 65: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

57

57 Karakum Kerdeli 2,05 2,05 - 4,00 -

58 Р-12-10-1 Kerdeli 1,72 1,72 - 2,00 -

59 К-1-6-1 Kerdeli 3,43 3,43 - 2,00 -

60 К-4-8 Kerdeli 4,56 4,56 - 2,00 -

61 P-12-1-5 Kerdeli 2,25 2,25 - 2,00 -

62 P-12-1-4 Kerdeli 4,94 4,94 - 2,00 -

63 Р-12-1-4-2 Kerdeli 1,48 1,48 - 2,00 -

64 Р-12-10-2 Kerdeli 1,48 1,48 - 0,20 -

65 Р-12-1-3 Kerdeli 4,67 4,67 - 1,20 -

66 К-1-5-7 Kerdeli 1,04 1,04 - 1,50 -

67 Р-12-1-4-2 Kerdeli 2,11 2,11 - 4,00 -

68 Karakum Kerdeli 7,21 7,21 - 3,00 -

69 Beigekum Talaptan 5,90 5,90 - 11,80 294

70 Eski Tekturmys Talaptan 2,40 2,40 - 10,00 -

71 П-0-3 Telikol 2,66 2,66 - 7,00 -

72 Р-12-6 Telikol 8,39 8,39 - 8,00 212

73 П-0-3 Telikol 2,70 2,70 - 7,00 -

74 П-0-3 Telikol 4,05 4,05 - 7,00 -

75 Р-10-1 Tonkeris 2,86 2,86 - 1,80 -

76 Р-10-1 Tonkeris 5,12 5,12 - 1,80 106

77 Р-10-1-1 Tonkeris 1,73 1,73 - 0,40 -

78 К-1-1-2-3 Tonkeris 3,34 3,34 - 0,40 -

79 Р-10-0-6 Tonkeris 1,52 1,52 - 0,25 -

80 К-1-1-2-5 Tonkeris 3,66 3,66 - 0,40 -

Total: 62 canals -187,4 km, 18 drains -59,7 km

247,10 1772

Syrdarya district.

1 Р-1 r/d S.Seifullin 3,21 3,21 - 1,50 522

Page 66: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

58

2 Р-2 r/d S.Seifullin 7,00 7,00 - 1,50 -

3 Р-2-5 r/d S.Seifullin 7,85 7,85 - 0,60 -

4 Р-1-2 r/d S.Seifullin 4,50 4,50 - 0,60 -

5 Maizharma r/d S.Seifullin 10,80 10,80 - 3,00 -

6 К-3-5 r/d S.Seifullin 8,00 8,00 - 2,50 -

7 К-3-1-1 r/d S.Seifullin 9,40 9,40 - 1,50 -

8 К-6-3 r/d S.Seifullin 6,55 6,55 - 1,50 -

9 Аizhanketken r/d

A.Tokmagambetov 11,31 11,31 - 8,00 1503

10 Eltai-1 r/d

A.Tokmagambetov 7,85 7,85 - 3,00 -

11 Р-1-1 r/d

A.Tokmagambetov 6,97 6,97 - 3,00 -

12 Р-1-4 r/d

A.Tokmagambetov 3,18 3,18 - 3,00 -

13 К-1 r/d

A.Tokmagambetov 2,48 2,48 - 2,00 -

14 К-1-3 r/d

A.Tokmagambetov 10,58 10,58 - 1,50 -

15 К-11 r/d

A.Tokmagambetov 10,51 10,51 - 2,00 -

16 Orazbsi r/d Terenozek 10,29 10,29 - 3,00 46

17 Р-1-2 r/d Terenozek 4,70 4,70 - 1,50 -

18 К-6-1 r/d Terenozek 8,81 8,81 - 2,00 -

19 К-6-1-1 r/d Terenozek 4,80 4,80 - 1,50 -

20 ЛМК-11В-10 r/d Akzharma 6,00 6,00 - 3,00 636

21 ЛМК-18-3 r/d Akzharma 0,95 0,95 - 1,50 -

22 ЛМК-18В-1 r/d Akzharma 2,65 2,65 - 1,50 -

23 ЛМК-11В-10-2 r/d Akzharma 1,49 1,49 - 0,60 -

24 ЛМК-24А-3 r/d Akzharma 1,33 1,33 - 1,50 -

25 ЛМК-18В-2 r/d Akzharma 3,33 3,33 - 1,50 -

Page 67: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

59

26 ЛМК-24А-2 r/d Akzharma 1,04 1,04 - 1,50 -

27 ЛМК-11В-12 r/d Akzharma 4,05 4,05 - 3,00 -

28 ЛМК-9-4 r/d Akzharma 7,15 7,15 - 3,00 -

29 Д-1 r/d Akzharma 4,93 4,93 - 4,00 -

30 Д-1-1 r/d Akzharma 2,29 2,29 - 2,00 -

31 СК-11 r/d Akzharma 3,91 3,91 - 5,00 -

32 Д-1-2 r/d Akzharma 1,41 1,41 - 2,00 -

33 Д-1-3 r/d Akzharma 2,87 2,87 - 2,00 -

34 Д-2 r/d Akzharma 6,71 6,71 - 5,00 -

35 ЮК-12-7-1 r/d Akzharma 4,98 4,98 - 2,50 -

36 Д-1-4-1 r/d Akzharma 2,70 2,70 - 1,50 -

37 ЛМК-9-2 r/d Shagan 3,82 3,82 - 8,00 -

38 ЛМК-12-1 r/d Shagan 0,84 0,84 - 3,00 -

39 ЛМК-16-7-1 r/d Shagan 1,51 1,51 - 1,50 -

40 ЛМК-9-2В r/d Shagan 3,25 3,25 - 6,20 1510

41 ЛМК-11В-3-5 r/d Shagan 1,20 1,20 - 1,50 -

42 ЛМК-9-2А r/d Shagan 2,71 2,71 - 1,50 -

43 СК-11-6-2-4 r/d Shagan 1,38 1,38 - 0,50 -

44 СК-8В r/d Shagan 5,30 5,30 - 2,00 -

45 ЮК-12-16 r/d Shagan 4,71 4,71 - 8,00 -

46 ЛМК-8А-15-1 r/d Ilyasov 0,70 0,70 - 3,00 -

47 ЛМК-8А-15 r/d Ilyasov 3,00 3,00 - 1,50 701

48 ЛМК-8А-7 r/d Ilyasov 1,05 1,05 - 3,00 -

49 ЛМК-8Б-1 r/d Ilyasov 2,63 2,63 - 1,50 -

50 СК-6 r/d Ilyasov 6,98 6,98 - 8,00 -

51 СК-3 r/d Ilyasov 24,83 24,83 - 6,00 -

52 Р-1-1 r/d Kogalykol 3,61 3,61 - 1,50 1090

Page 68: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

60

53 Р-1-2 r/d Kogalykol 3,94 3,94 - 1,50 -

54 ЛМК-5 r/d Kogalykol 3,70 3,70 - 10,00 -

55 Zhanaaryk r/d Kogalykol 9,24 9,24 - 15,00 -

56 Р-11 r/d Kogalykol 5,40 5,40 - 3,00 -

57 Р-1-2 r/d Kogalykol 3,57 3,57 - 1,50 -

58 ЮК-4 r/d Kogalykol 3,48 3,48 - 6,00 -

59 ЮК-2-1 r/d Kogalykol 2,64 2,64 - 4,00 -

60 ЮК-1-1 r/d Kogalykol 6,74 6,74 - 3,00 -

61 ЮК-1Г-1 r/d Kogalykol 3,02 3,02 - 2,50 -

62 Kosaryk r/d Besaryk 10,50 10,50 - 6,00 405

63 Turdali r/d Besaryk 7,61 7,61 - 4,00 361

64 tail Zhaskairat r/d Amankeldi 15,58 15,58 - 4,00 346

65 Aktam r/d Aidarly 3,94 3,94 - 5,00 286

Total: 40 canals-193,6 km, 25 drains, -150,01 km 343,47 7 406

Karmakshy district.

1 ПВ-13-3Е Aldashbai Ahun 13,60 13,60 - 2,50 60

2 ПВ-13-3Б-1 Dauylkol 3,60 3,60 - 1,50 324

3 ПВ-11В Dauylkol 1,50 1,50 - 2,00 610

4 ПВ13-1Д Akzhar 5,40 5,40 - 1,00 503

5 ПВ-13-1Ж Akzhar 3,80 3,80 - 1,50 661

6 ПВ-13-2Б Aktobe 3,00 3,00 - 2,00 392

7 ПВ-13-2Г Aktobe 0,50 0,50 - 1,40 228

8 ПВ-15-7 III-international 11,80 11,80 - 1,90 684

9 ПВ-15-9 III-international 0,14 0,14 - 1,10 540

10 Zhosaly zharma Iirkol 11,40 11,40 - 2,00 187

11 Bala-Zharma Iirkol 3,00 3,00 - 2,00 523

12 ПВ-13-3-Е-1 Aldashbai Ahun 6,40 6,40 - 2,00 -

Page 69: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

61

13 ПВ-13-3Б-1-1 Dauylkol 7,50 7,50 - 1,00 -

14 ПВ-11В-1 Akzhar 6,20 6,20 - 1,00 -

15 ПВ-13-1Д-1 Akzhar 5,20 5,20 - 1,00 -

16 ПВ-13-1Ж-1 Akzhar 2,20 2,20 - 1,00 -

17 ПВ-13-2Б-1 Aktobe 10,00 10,00 - 1,00 -

18 ПВ-13-2Г-1 Aktobe 2,30 2,30 - 1,00 -

19 ПВ-15-7-1 III-international 6,30 6,30 - 1,00 -

20 ПВ-15-9-1 III-international 6,60 6,60 - 1,00 -

21 Zhosaly zharma-1 Iirkol 2,20 2,20 - 1,00 -

22 Tail Bala-zharma-1 Iirkol 3,10 3,10 - 1,00 -

23 Tail Bala-zharma-3 Iirkol 5,30 5,30 - 1,00 -

24 Tail Bala-zharma-5 Iirkol 1,40 1,40 - 1,00 -

25 К-1-1 Aldashbai Ahun 17,62 17,62 - 1,20 -

26 К-2-1 Dauylkol 10,32 10,32 - 1,20 -

27 ВКК-2А Akzhar 6,63 6,63 - 1,50 -

28 ВКК-5 Akzhar 10,52 10,52 - 3,00 -

29 ВКК-4 Akzhar 8,21 8,21 - 3,00 -

30 ЗК-5-4 Aktobe 10,97 10,97 - 1,50 -

31 ЗК-2-2 Aktobe 15,66 15,66 - 1,50 -

Total: 24 canals-122,44 km, drains -79,93 km 202,37 4712

Aral district.

1 Bekbaul Akbai 4,58 4,58 - 3 100

2 Beknazar Akbai 1,67 1,67 - 3 164

3 Kairolla Akbai 2,33 2,33 - 8 671

4 Kone Mendibai Akbai 14,89 14,89 - 10 1254

5 Priaral Akbai 3,81 3,81 - 5 456

Total: 5 canals 27,28 2645

Page 70: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

62

Kyzylorda c.

1 Karataban Aksuat 9,34 9,34 - 2,5 221,3

2 Р-2 Aksuat 2,94 2,94 - 1,5

3 Р-3 Aksuat 1,47 1,47 - 1,5

4 Р-4 Aksuat 1,93 1,93 - 1,5

5 Р-4-1 Aksuat 0,91 0,91 - 1

6 Zhusipbek Karauyltobe 3,40 3,40 - 2,50 351,8

7 Р-1-1 Karauyltobe 1,87 1,87 - 1,50

8 Р-1 Kosshynyrau 7,80 7,80 - 8,00 605,64

9 Р-2 Kosshynyrau 1,05 1,05 - 2,00 124,6

10 Ж-1 Kosshynyrau 2,60 2,60 - 1,50

11 Ж-2 Kosshynyrau 2,11 2,11 - 1,50

12 Ж-3 Kosshynyrau 1,30 1,30 - 1,50 281,8

13 7х-3 Kosshynyrau 2,40 2,40 - 2,00 182,7

14 А-3 Kosshynyrau 2,10 2,10 - 2,00 93,03

15 А-5 Kosshynyrau 2,71 2,71 - 2,00 300

16 Р-2-3 Kosshynyrau 5,97 5,97 - 2,00 345,1

17 Р-3-1-1 Kosshynyrau 4,00 4,00 - 1,00

18 Р-2-1 Kosshynyrau 1,31 1,31 - 1,50

19 Р-2-2 Kosshynyrau 0,80 0,80 - 1,50 94,37

20 Р-2-4 Kosshynyrau 2,22 2,22 - 1,50

21 Р-2-4-1 Kosshynyrau 1,42 1,42 - 1,50 78,47

22 Р-2-2 Kosshynyrau 0,58 0,58 - 1,00

23 Ж-2-1 Kosshynyrau 0,80 0,80 - 1,00

24 Р-2-7 Kosshynyrau 1,50 1,50 - 1,50 188

25 А-4-1 Kosshynyrau 0,71 0,71 - 1,00

26 Л-5-2 Kosshynyrau 1,60 1,60 - 1,00

Page 71: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

63

27 Л-5-3 Kosshynyrau 1,16 1,16 - 1,00

28 Л-5-3-1 Kosshynyrau 1,37 1,37 - 0,50

29 Р-2-4 Kosshynyrau 1,11 1,11 - 2,00

30 Р-2-4-2 Kosshynyrau 1,30 1,30 - 1,50

31 Р-2-2-1 Kosshynyrau 0,77 0,77 - 1,50

32 Р-2-2-2 Kosshynyrau 1,45 1,45 - 1,50

33 Р-1-2 Kosshynyrau 3,50 3,50 - 1,00 112,72

34 Р-1-5 Kosshynyrau 2,88 2,88 - 1.5 76,38

35 К-2 Kosshynyrau 3,50 3,70 - 6,00

36 К-3 Kosshynyrau 2,88 2,50 - 6,00

37 К-1-1 Karauyltobe 1,86 1,86 - 4,00

38 К-1-2 Karauyltobe 10,13 10,13 - 3,50

39 К-1-1 Kosshynyrau 12,78 12,78 - 4,00

40 К-5-1 Kosshynyrau 1,95 1,95 - 3,50

41 К-1-2 Kosshynyrau 5,96 5,96 - 4,00

42 К-1-3 Kosshynyrau 2,00 2,00 - 4,00

43 К-5-5-1-1 Kosshynyrau 0,68 0,68 - 2,00

44 К-5-5-1-2 Kosshynyrau 2,86 2,86 - 2,00

45 К-1-2-2 Kosshynyrau 1,50 1,50 - 2,50

46 К-6-1 Kosshynyrau 1,60 1,60 - 3,50

47 К-7 Kosshynyrau 4,77 4,77 - 8,00

48 К-7-1 Kosshynyrau 1,71 1,71 - 3,50

49 К-7-2 Kosshynyrau 1,70 1,70 - 4,00

50 К-7-3 Kosshynyrau 1,10 1,10 - 4,00

51 К-1-2-1-2 Kosshynyrau 1,25 1,25 - 1,50

52 К-1-2-1-3 Kosshynyrau 1,17 1,17 - 1,50

53 К-1-2-1-4 Kosshynyrau 2,60 2,60 - 1,50

Page 72: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

64

54 К-1-2-1-5 Kosshynyrau 0,79 0,79 - 1,50

55 К-4-1-3 Kosshynyrau 2,60 2,60 - 3,00

56 К-4-2-2 Kosshynyrau 2,70 2,70 - 2,50

Total: 34 canals -78,38km, 22 drains- 68,07 km 146,45 3056

Page 73: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

65

Attachment 2. Decree of the regional Akimat about the canals’ ownership (sample)

Page 74: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

66

Page 75: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

67

Page 76: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

68

Page 77: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

69

Page 78: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

70

Attachment 3. Canal voluntary donation signed documents

Page 79: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

71

Page 80: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

72

Page 81: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

73

Attachment 4. Sample photos from site visits

East Kazakhstan province

Photo 1: Canal Goltsovskiy

Photo 2: Canal Bogenbai, a single house close to the whole canal length located about 22 meters away from the canal.

Page 82: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

74

Photo 3: Canal МК Алтайский

Page 83: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

75

Karaghandy province

Photo 5: Canal Tuzdi

Photo 6: Canal Shartaz

Page 84: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

76

Photo 7: Canal Samara

Photo 8: Canal Zherdinskiy

Page 85: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

77

Kyzylorda province

Photo 9: Canal R-2

Photo 10: Canal Orazbay

Page 86: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

78

Photo 11: Canal LMK 9-2

Photo 12: Canal LMK 9-4 (the houses in left side are about 50 meters away and in right side

there is large open area and service road)

Page 87: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

79

Photo 13: Canal 3x6 Kazalinskiy (houses in left side are about 50 meters away and in right

side there is a large open area and service road)

Photo 14: Canal Zhiluan the structures are in one side and about 80 meters away)

Page 88: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

80

Zhambyl province

Photo 15: Talas LVMK Oiyk interfarm canal

Photo 16: Talas Zhiembet main canal

Photo 17: Talas Uzyn interfarm canal

Page 89: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

81

Photo 18: Talas PVMK interfarm canal

Photo 19: Zhanatorgan interfarm canal (a wagon by the tree can be moved inward the house

yard), however, there will not be any work in this part of the canal at it is in concrete and good conditions.

Page 90: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

82

Photo 20: Talas Orta Aryk interfarm canal : there will not be any work in this part of the canal

at it is in concrete and good conditions.

Page 91: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

83

Locations where some canals or ditches are near the houses

Zhambyl province

Photo 21: Canal Melnichniy; ditch for irrigation of households plots; wild bushes (one-year

plants) and dirt will be removed by manual works and choppers as planned in the feasibility study (table 5 and 6 of this report).

Photo 22: Canal Saduakas; ditch for irrigation of households plots; dirt will be removed by

manual work as planned in the feasibility study (table 5 and 6 of this report).

Page 92: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

84

Photo 23: Canal Salyamov; ditch for irrigation of households plots; cleaning will be by

manual work as planned in the feasibility study (table 5 and 6 of this report).

Photo 24: Canal Turksib; dirt will be removed by manual work as planned in the feasibility

study (tables 5 and 6 of this report).

Page 93: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

85

Photo 25: Canal Bayshakhan; dirt will be removed by manual work and choppers as planned

in the feasibility study (table 5 and 6 of this report).

Photo 26: Canal Noviy Kartogan; no work will be carried out in this section as this section of

the canal is in cement and in good condition.

Page 94: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

86

Photo 27: Canal Kultobe-Sarisu ; dirt will be removed by manual works as planned in the

feasibility study (table 5 and 6 of this report) and from the right side where there is no structure.

Photo 28: Canal Tuksib, Zhambyl province; cleaning and repairing works in this section will

be manually (table 5 and 6 of this report) and in right side of canal.

Page 95: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

87

Attachment 5. Involuntary Resettlement Impact Checklists ADB TRTA 9317-KAZ: Irrigation Rehabilitation Sector Project Site: 16 sub-projects for irrigation canals rehabilitation in four provinces of Kazakhstan Involuntary Resettlement Impact Category: C

Probable Involuntary Resettlement Effects

Yes No Not known

Remarks

Involuntary Acquisition of Land

1. Will there be land acquisition?

2. Is the site for land acquisition known? N/A: It is the existing canals.

3. Is the ownership status and current usage of land to be acquired known?

State-owned: 1 private canal donated by a farming company (project direct beneficiary)

4. Will easement be utilized within an existing Right of Way (ROW)?

5. Will there be loss of shelter and residential land use to land acquisition?

6. Will there be loss of agricultural and other productive assets due to land acquisition?

7. Will there be loss of crops, trees, and fixed assets due to land acquisition?

8. Will there be loss of business or enterprises due to land acquisition?

9. Will there be loss of income sources and means of livelihoods due to land acquisition?

Involuntary Restrictions on land use or on access to legally designated parks and protected areas

10. Will people lose access to natural resources, communal facilities and services?

11. If land use is changed, will it have an adverse impact on social and economic activities?

12. Will access to land and resources owned by the communally or by the state be restricted?

Information on Displaced Persons

13. Any estimate of the likely number of persons that will be displaced by the Project? If yes, approximately how many?

No Yes Not applicable

14. Are any of the poor, female-headed households, or vulnerable to poverty risks?

No Yes Not applicable

15. Are any displaced persons from indigenous or ethnic minority groups?

No Yes Not applicable

Page 96: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

88

ADB TRTA 9317-KAZ: Irrigation Rehabilitation Sector Project Site: Land plot for building the EA’s headquarters in Nursultan (Astana) city of Kazakhstan Involuntary Resettlement Impact Category: C

Probable Involuntary Resettlement Effects

Yes No Not known

Remarks

Involuntary Acquisition of Land

1. Will there be land acquisition?

2. Is the site for land acquisition known? It is municipality owned land

3. Is the ownership status and current usage of land to be acquired known?

4. Will easement be utilized within an existing Right of Way (ROW)?

5. Will there be loss of shelter and residential land use to land acquisition?

6. Will there be loss of agricultural and other productive assets due to land acquisition?

7. Will there be loss of crops, trees, and fixed assets due to land acquisition?

8. Will there be loss of business or enterprises due to land acquisition?

9. Will there be loss of income sources and means of livelihoods due to land acquisition?

Involuntary Restrictions on land use or on access to legally designated parks and protected areas

10. Will people lose access to natural resources, communal facilities and services?

11. If land use is changed, will it have an adverse impact on social and economic activities?

12. Will access to land and resources owned by the communally or by the state be restricted?

Information on Displaced Persons

13. Any estimate of the likely number of persons that will be displaced by the Project? If yes, approximately how many?

No Yes Not applicable

14. Are any of the poor, female-headed households, or vulnerable to poverty risks?

No Yes Not applicable

15. Are any displaced persons from indigenous or ethnic minority groups?

No Yes Not applicable

Page 97: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

89

Attachment 6. Indigenous People Impact Checklist ADB TRTA 9317-KAZ: Irrigation Rehabilitation Sector Project Site: 16 subprojects in four provinces and land plot for the KVK Headquarters building in Nursultan (Astana) city, Kazakhstan Indigenous Peoples Impact Category: C

KEY CONCERNS (Please provide elaborations on the Remarks column)

Yes No Not known

Remarks

A. Indigenous Peoples Identification

1. Are there socio-cultural groups present in or use the project area who may be considered as "tribes" (hill tribes, schedules tribes, tribal peoples), "minorities" (ethnic or national minorities), or "indigenous communities" in the project area?

No Indigenous People are in the project area

2. Are there national or local laws or policies as well as anthropological researches/studies that consider these groups present in or using the project area as belonging to "ethnic minorities", scheduled tribes, tribal peoples, national minorities, or cultural communities?

3. Do such groups self-identify as being part of a distinct social and cultural group?

4. Do such groups maintain collective attachments to distinct habitats or ancestral territories and/or to the natural resources in these habitats and territories?

5. Do such groups maintain cultural, economic, social, and political institutions distinct from the dominant society and culture?

6. Do such groups speak a distinct language or dialect?

7. Has such groups been historically, socially and economically marginalized, disempowered, excluded, and/or discriminated against?

8. Are such groups represented as "Indigenous Peoples" or as "ethnic minorities" or "scheduled tribes" or "tribal populations" in any formal decision-making bodies at the national or local levels?

B. Identification of Potential Impacts

9. Will the project directly or indirectly benefit or target Indigenous Peoples?

10. Will the project directly or indirectly affect Indigenous Peoples' traditional socio-cultural and belief practices? (e.g. child-rearing, health, education, arts, and governance)

11. Will the project affect the livelihood systems of Indigenous Peoples? (e.g., food production system, natural resource management, crafts and trade, employment status)

12. Will the project be in an area (land or territory) occupied, owned, or used by Indigenous Peoples, and/or claimed as ancestral domain?

C. Identification of Special Requirements Will the project activities include?

13. Commercial development of the cultural resources and knowledge of Indigenous Peoples?

14. Physical displacement from traditional or customary lands?

15. Commercial development of natural resources (such as minerals, hydrocarbons, forests, water, hunting or fishing grounds) within customary lands under use that would impact the livelihoods or the cultural, ceremonial, spiritual uses that define the identity and community of Indigenous Peoples?

16. Establishing legal recognition of rights to lands and territories that are traditionally owned or customarily used, occupied or claimed by indigenous peoples?

17. Acquisition of lands that are traditionally owned or customarily used, occupied or claimed by indigenous peoples?

Page 98: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

90

D. Anticipated project impacts on Indigenous Peoples (as applicable) – N/A

Project component/ activity/ output Anticipated positive effect Anticipated negative effect

1.

2.

3.

4.

Note: The project team may attach additional information on the project, as necessary.

Page 99: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

91

Attachment 7. Proceedings of the Disclosure and Public Consultations in four provinces Proceedings of the 1st public consultation in East Kazakhstan province (16 November 2018)

Page 100: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

92

Page 101: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

93

Page 102: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

94

List of participants in the 1st public consultations (16 November 2018)

Page 103: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

95

Proceedings of the 2nd public consultation in the East Kazakhstan province (26 February 2019)

Page 104: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

96

Page 105: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

97

Page 106: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

98

Proceedings of the 1st public consultations in Karaghandy Province (27 November 2018)

Page 107: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

99

Page 108: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

100

Page 109: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

101

Page 110: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

102

Page 111: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

103

Proceedings of the public consultations in Kyzylorda (20 November 2018)

Page 112: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

104

Page 113: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

105

List of participants of public consultations in Kyzylorda

Page 114: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

106

Page 115: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

107

Proceedings of public consultations Zhambyl province (22 November 2018)

Page 116: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

108

Page 117: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

109

Page 118: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

110

Attendance list in Zhambyl province

Page 119: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

111

Page 120: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

112

Photos from the disclosure and public consultations in four provinces

East Kazakhstan province

Photo 29: The 1st public consultations (16 November 2018)

Page 121: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

113

Photo 30: The 2nd public consultation (26 February 2019)

Karaghandy province

Photo 31: The 1st public consultation (27 November 2018)

Page 122: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

114

Photo 32: The second public consultation (28 February 2019)

Page 123: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

115

Kyzylorda province

Photo 33: Public consultation on 20 November 2018

Zhambyl province

Photo 34: Public consultations in on 22 November 2018.

Page 124: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

116

Announcement in the newspapers about the project disclosure and public consultations

Page 125: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

117

Attachment 8. Assignment of the GRM Focal Persons by the KVK

Page 126: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

118

Assignment of the KVK staff as focal person in Kyzylorda province

Page 127: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

119

Assignment of the KVK staff as focal person in Zhambyl province

Page 128: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

120

Assignment of the KVK staff as GRM focal person in Karaghandy province

Page 129: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

121

Page 130: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

122

Order for assignment of one staff as GRM focal person from East Kazakhstan province KVK

Page 131: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

123

Attachment 9. Confirmation of staff of regional authorities and KVK for GRM

Zhambyl province: Confirmation of Zhambyl province’s authorities for assigning staff as member of GRC

Page 132: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

124

Page 133: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

125

Confirmation of Zhambyl regional KVK branch on assigning staff as member of GRC

Page 134: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

126

Page 135: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

127

Page 136: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

128

Confirmation East Kazakhstan province’s authorities for assigning staff as members of GRC

Page 137: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

129

Page 138: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

130

Confirmation of Karaghandy province's authorities on assigning staff as member of GRC

Page 139: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

131

Confirmation of Karaghandy regional KVK branch on assigning staff as member of GRC

Page 140: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

132

Page 141: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

133

Confirmation of Kyzylorda regional authorities on assigning staff as member of GRC

Page 142: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

134

Page 143: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

135

Page 144: Irrigation Rehabilitation Project: Due Diligence on Social ...€¦ · CSC Construction Supervision Consultant SPS Safeguard Policy Statement (2009) of ADB km kilometer SNiP Construction

136

Confirmation of Kyzylorda regional KVK branch on assigning staff as member of GRC