UNIVERSITAS DIPONEGORO
PROYEK PEMBANGUNAN GEDUNG MAHKAMAH AGUNG
REPUBLIK INDONESIA, JALAN MEDAN MERDEKA UTARA NO. 9
13 JAKARTA
The Construction Project of The Main Building of The Supreme Court of The
Republic of Indonesia on 9 13 Medan Merdeka Utara Jakarta
KERJA PRAKTEK
Diajukan untuk memenuhi syarat menyelesaikan Pendidikan Sarjana Teknik
FAHMI AKMAL HASANI
21010111130116
JURUSAN TEKNIK SIPIL
FAKULTAS TEKNIK
SEMARANG
APRIL, 2015
ii
UNIVERSITAS DIPONEGORO
PROYEK PEMBANGUNAN GEDUNG MAHKAMAH AGUNG
REPUBLIK INDONESIA, JALAN MEDAN MERDEKA UTARA NO. 9
13 JAKARTA
The Construction Project of The Main Building of The Supreme Court of The
Republic of Indonesia on 9 13 Medan Merdeka Utara Jakarta
FAHMI AKMAL HASANI
21010111130116
Semarang, April 2015
Mengetahui,
Ketua Jurusan/Program Studi Teknik Sipil
Fakultas Teknik Universitas Diponegoro,
Ir. Sumbogo Pranoto, MT.
NIP. 19580604.198602.1.001
Disetujui
Dosen Pembimbing Kerja Praktek
Parang Sabdono, Ir., M. Eng.
NIP. 196205161990011001
iii
KATA PENGANTAR
Puji syukur penulis panjatkan ke hadirat Allah SWT yang telah melimpahkan rahmat
dan hidayah-Nya sehingga penulis dapat menyelesaikan dan menyusun laporan kerja praktek
Pembangunan Gedung Mahkamah Agung RI.
Laporan kerja praktek ini disusun untuk memenuhi salah satu persyaratan akademis
dalam menyelesaikan pendidikan program studi strata satu (S1) bagi mahasiswa jurusan
Teknik Sipil Fakultas Teknik Universitas Diponegoro, Semarang. Kerja praktek ini menjadi
tambahan pengetahuan lapangan sebagai pelengkap pengetahuan teoritis para calon sarjana
teknik sipil. Waktu yang diberikan selama 60 hari kerja praktek semoga menjadi bekal yang
cukup bagi penulis mengambil berbagai pengetahuan dari proyek ini.
Pada kesempatan ini penulis menyampaikan terima kasih, atas segala bantuan dan
bimbingan yang telah diberikan selama kerja praktek sampai tersusunnya laporan ini. Penulis
mengucapkan terima kasih kepada :
1. Ir. Sumbogo Pranoto, MT., sebagai Ketua Jurusan Teknik Sipil Universitas Diponegoro,
Semarang sekaligus sebagai dosen wali penulis yang memberikan banyak pengarahan
bagi penulis.
2. Ir. Moga Narayudha, SP1., selaku koordinator Kerja Praktek Jurusan Teknik Sipil Faultas
Teknik Universitas Diponegoro
3. Ir. Hari Budieny, M.T., selaku koordinator bidang akademik Jurusan Teknik Sipil
Fakultas Teknik Universitas Diponegoro
4. Bapak Parang Sabdono, Ir., M. Eng, selaku dosen pembimbing Kerja Praktek yang telah
memberikan bimbingan hingga selesainya Laporan Kerja Praktek ini.
5. Ir. M. Nugerahanto, selaku Kepala Proyek Pembangunan Gedung Mahkamah Agung RI
6. Mahardhika Agit ST., selaku Kepala Teknik pembangunan Gedung Mahkamah Agung RI
sekaligus sebagai pembimbing penulis selama kerja praktek
7. Mas Defri, selaku Quality Control pembangunan Gedung Mahkamah Agung RI yang
membagi pengalamannya seputar proyek.
iv
8. Mas Rahmat sebagai senior yang selalu memberikan semangat dan motivasi bagi penulis.
9. Ibu dan Bapak tercinta yang telah mendukung penulis dalam selama kerja praktek ini
melalui doanya.
10. Hifdzi Ulil Azmi sebagai kakak yang selalu memberi semangat bagi penulis
11. Keluarga besar wisma Al-Fath yang selalu memberikan semangat baru.
12. Keluarga Teknik Sipil angkatan 2011 yang memberikan bantuannya baik moril maupun
materil kepada penulis dalam penyelesaian laporan ini.
13. Semua pihak yang tidak mampu ditulis satu persatu yang telah membantu penulis
menyelesaikan laporan kerja prektek ini.
Penulis mengharapkan kritik dan saran yang membangun. Semoga laporan ini dapat
bermanfaat dan memberikan amal bagi penulis.
Semarang, April 2015
Penulis
v
DAFTAR ISI
HALAMAN JUDUL .................................................................................................................. i
LEMBAR PENGESAHAN ....................................................................................................... ii
KATA PENGANTAR .............................................................................................................. iii
DAFTAR ISI ............................................................................................................................. v
DAFTAR GAMBAR .............................................................................................................. viii
DAFTAR TABEL ................................................................................................................... xii
BAB I PENDAHULUAN
1.1 LATAR BELAKANG PROYEK ........................................................................... I-1
1.2 MAKSUD DAN TUJUAN PROYEK ................................................................... I-2
1.3 LOKASI PROYEK ................................................................................................ I-2
1.4 DATA PROYEK .................................................................................................... I-3
1.5 RUANG LINGKUP PEKERJAAN ....................................................................... I-3
1.6 RUANG LINGKUP KERJA PRAKTEK .............................................................. I-4
1.7 METODE PENGUMPULAN DATA .................................................................... I-5
1.8 SISTEMATIKA PENULISAN LAPORAN ........................................................... I-6
BAB II MANAJEMEN PROYEK
2.1. TINJAUAN UMUM ............................................................................................ II-1
2.2. UNSUR UNSUR PENGELOLA PROYEK ..................................................... II-2
2.3. STRUKTUR ORGANISASI PROYEK .............................................................. II-3
2.4. HUBUNGAN KERJA ANTAR UNSUR ORGANISASI ................................... II-4
2.5. STRUKTUR ORGANISASI PELAKSANA PROYEK ..................................... II-5
2.6. STRUKTUR ORGANISASI PELAKSANA PROYEK ................................... II-11
BAB III PERENCANAAN PROYEK
3.1 TINJAUAN UMUM ......................................................................................... III-1
3.2 TAHAP PERENCANAAN ................................................................................ III-1
vi
3.3 TINJAUAN PERENCANAAN ARSITEKTUR ................................................ III-4
3.4 TINJAUAN PERENCANAAN STRUKTUR ................................................... III-5
3.5 PERATURAN PEMBEBANAN STRUKTUR ................................................. III-6
3.6 TINJAUAN PERENCANAAN STRUKTUR ATAS ........................................ III-10
3.7 PERENCANAAN MEKANIKAL DAN ELEKTRIKAL.................................. III-17
3.8 PERENCANAAN SANITASI DAN PENGOLAHAN LIMBAH .................... III-19
BAB IV ALAT DAN BAHAN
4.1 TINJAUAN UMUM ......................................................................................... IV-1
4.2 PERALATAN YANG DIGUNAKAN .............................................................. IV-1
4.3 BAHAN YANG DIGUNAKAN ........................................................................ IV-14
BAB V PELAKSANAAN PEKERJAAN
5.1 TINJAUAN UMUM ......................................................................................... V-1
5.2 PEKERJAAN KOLOM...................................................................................... V-2
5.3 PEKERJAAN BALOK DAN PLAT LANTAI .................................................. V-10
5.4 PEKERJAAN SHEARWALL .............................................................................. V-31
5.5 PEKERJAAN TANGGA ................................................................................... V-38
BAB VI PENGENDALIAN PROYEK
6.1 TINJAUAN UMUM ......................................................................................... VI-1
6.2 MEKANISME PENGAWASAN DAN PENGENDALIAN ............................. VI-2
6.3 PENGAWASAN DAN PENGENDALIAN MUTU .......................................... VI-2
6.4 PENGAWASAN DAN PENGENDALIAN WAKTU ...................................... VI-11
6.5 PENGENDALIAN TEKNIS .............................................................................. VI-14
6.6 PENGENDALIAN BIAYA ............................................................................... VI-15
6.7 PENGENDALIAN K3LMP (KESEHATAN, KESELAMATAN KERJA
LINGKUNGAN, MUTU DAN PENGAMANAN) ........................................... VI-16
6.8 PENGENDALIAN TENAGA KERJA .............................................................. VI-20
vii
BAB VII PERMASALAHAN PROYEK
7.1 TINJAUAN UMUM ......................................................................................... VII-1
7.2 PERMASALAHAN PROYEK ......................................................................... VII-1
7.3 SOLUSI TERHADAP PERMASALAHAN PROYEK .....................................VII-3
BAB VIII PENUTUP
7.1 KESIMPULAN .................................................................................................. VII-1
7.2 SARAN............................................................................................................... VII-1
DAFTAR PUSTAKA
LAMPIRAN A GAMBAR PROYEK
LAMPIRAN B DATA-DATA PROYEK
LAMPIRAN C SURAT-SURAT KERJA PRAKTEK
viii
DAFTAR GAMBAR
Gambar 1.1. Batas-batas Lokasi Proyek .................................................................................. I-2
Gambar 2.1. Skema Hubungan Kerja Pengelola Proyek ........................................................ II-4
Gambar 2.2. Struktur Organisasi Kontraktor Pelaksana ..................................................... II-5
Gambar 2.2. Struktur Organisasi Konsultan Manajemen Konstruksi .............................. II-10
Gambar 3.1. Detail Plat Tipe s5 .......................................................................................... III-11
Gambar 3.2. Detail Kolom K1 dan K2 ................................................................................ III-14
Gambar 3.3. Detail Shearwall SW1 ................................................................................... III-15
Gambar 3.4. Detail Balok G1 .............................................................................................. III-16
Gambar 3.5. Detail Tangga.................................................................................................. III-17
Gambar 4.1. Tower Crane .....................................................................................................IV-2
Gambar 4.2. Truck Mixer .....................................................................................................IV-3
Gambar 4.3. Concrete Pump ................................................................................................IV-4
Gambar 4.4. Air Compressor ................................................................................................IV-5
Gambar 4.5. Concrete Vibrator ............................................................................................IV-6
Gambar 4.6. Bar Bender .......................................................................................................IV-7
Gambar 4.7. Bar Cutter .........................................................................................................IV-8
Gambar 4.8. Cutting Wheel Machine ...................................................................................IV-8
Gambar 4.9. Las gas (a), Las Listrik (b) ...............................................................................IV-9
Gambar 4.10. Gerinda ..........................................................................................................IV-9
Gambar 4.11. Waterpass dan Bak Ukur ..............................................................................IV-10
Gambar 4.12. Pemasangan PCH ........................................................................................IV-10
Gambar 4.13. Standart ........................................................................................................IV-11
Gambar 4.14. Ledger ..........................................................................................................IV-11
Gambar 4.15. Jack Base ....................................................................................................IV-11
Gambar 4.16. U-Head ........................................................................................................IV-12
Gambar 4.17. Props ............................................................................................................IV-12
Gambar 4.18. Couplers / Swivle .........................................................................................IV-12
ix
Gambar 4.19. Quickshore Beam Bracket ...........................................................................IV-12
Gambar 4.20. Base Plate ....................................................................................................IV-13
Gambar 4.21. Trigger Brace ..............................................................................................IV-13
Gambar 4.22. Kantilever ....................................................................................................IV-13
Gambar 4.23. Concrete Bucket ............................................................................................IV-14
Gambar 4.24. Semen Tipe 1 ...............................................................................................IV-16
Gambar 4.25. Baja Tulangan ..............................................................................................IV-19
Gambar 4.26. Kawat Bendrat .............................................................................................IV-19
Gambar 4.27. Beton Decking .............................................................................................IV-20
Gambar 4.28. Kayu .............................................................................................................IV-20
Gambar 4.29. Multipleks .....................................................................................................IV-21
Gambar 4.30. Bata Ringan .................................................................................................IV-22
Gambar 4.31. Concrete Bonding Agent ..............................................................................IV-22
Gambar 4.32. Mortar Siap Pakai (a) Thinbed (b) Skimcoat ...............................................IV-23
Gambar 4.33. Tulangan Kolom Praktis ..............................................................................IV-23
Gambar 4.34. Baja IWF ......................................................................................................IV-24
Gambar 5.1. Bagan Alir Pekerjaan Kolom ............................................................................. V-2
Gambar 5.2. Skema Pengukuran As Kolom ........................................................................... V-3
Gambar 5.3. Pengukuran Sumbu As Kolom .......................................................................... V-3
Gambar 5.3. Site Perangkaian Tulangan (a), Site Pemotongan dan Pembengkokan
Tulangan (b) .......................................................................................................................... V-6
Gambar 5.4. Pemasangan Sepatu Kolom .............................................................................. V-6
Gambar 5.5. Bekisting yang Siap Pakai ................................................................................ V-6
Gambar 5.6. Bekisting yang Sudah Terpasang ...................................................................... V-8
Gambar 5.7. Penuangan Beton pada Bekisting Kolom (a), Pemadatan Kolom dengan
Concrete Vibrator (b) ............................................................................................................ V-9
Gambar 5.8. Penambalan Kolom ......................................................................................... V-10
Gambar 5.9. Bagan Alir Pekerjaan Balok dan Plat ............................................................. V-11
Gambar 5.10. Pemasangan Balok Pikul dan Suri-suri.......................................................... V-12
x
Gambar 5.11. Pemasangan Bekisting Balok ....................................................................... V-13
Gambar 5.12. Perkuatan Bekisting Balok dengan Dowel dan Tie Rod ............................... V-13
Gambar 5.13. Pemasangan Bekisting Plat ........................................................................... V-14
Gambar 5.14. Bekisting Balok dan Plat Tampak dari Bawah ............................................. V-14
Gambar 5.15. Tulangan Utama Diganjal ............................................................................. V-15
Gambar 5.16. Panjang Penjangkaran ................................................................................... V-15
Gambar 5.17. Penulangan Balok ......................................................................................... V-16
Gambar 5.18. Penulangan Plat Lantai ................................................................................. V-17
Gambar 5.19. Ujung Pipa Concrete Pump .......................................................................... V-19
Gambar 5.20. Pengecoran Plat dan Balok ........................................................................... V-20
Gambar 5.21. Dimensi Plat yang Ditinjau ........................................................................... V-22
Gambar 5.22. Pemodelan Beban Trapesium Plat terhadap Balok B1 ................................. V-24
Gambar 5.23. Pemodelan Pembebanan pada Balok ............................................................ V-25
Gambar 5.24. Diagram Tegangan dan Regangan Balok pada Tumpuan ............................ V-26
Gambar 5.25. Diagram Tegangan dan Regangan Balok pada Lapangan ............................ V-28
Gambar 5.26. Pembongkaran Bekisting Balok dan Plat Lantai .......................................... V-31
Gambar 5.27. Bagan Alir Pekerjaan Shearwall ................................................................... V-32
Gambar 5.28. Pembongkaran Bekisting Sherwall ............................................................... V-37
Gambar 5.29. Bagan Alir Pekerjaan Tangga ....................................................................... V-38
Gambar 5.30. Bekisting Tangga .......................................................................................... V-39
Gambar 5.31. Penulangan pada Ujung Tangga ................................................................... V-40
Gambar 5.32. Penulangan Tangga ....................................................................................... V-41
Gambar 5.33. Pengecoran Tangga ....................................................................................... V-42
Gambar 6.1. Kerucut Abrams dengan Ukurannya ...............................................................VI-4
Gambar 6.2. Pengujian Kuat Tekan Beton ...........................................................................VI-6
Gambar 6.3. Pengujian Kuat Tarik Baja ...............................................................................VI-8
Gambar 6.4. Grafik Hubungan Regangan dan Tegangan Baja Tulangan ............................VI-9
Gambar 6.5. Kurva S Proyek ...............................................................................................VI-13
Gambar 6.6. Rambu-rambu K3LMP ..................................................................................VI-19
xi
Gambar 6.7. Pekerja yang Tidak Menggunakan APD Lengkap ........................................VI-19
Gambar 7.1. Kolom Keropos (a), Balok Keropos (b) ........................................................ VII-4
Gambar 7.2. Bekisting Shearwall yang Jebol ..................................................................... VII-5
Gambar 7.3. Proses Grouting pada Beton ........................................................................... VII-7
xii
DAFTAR TABEL
Tabel 3.1. Berat Sendiri Bahan Bangunan dan Komponen Gedung .................................... III-6
Tabel 3.2. Beban Hidup pada Lantai Gedung ....................................................................... III-7
Tabel 3.3. Faktor Keutamaan Ie (SNI 03-1726-2012)........................................................... III-9
Tabel 3.4. Tulangan Plat Lantai .......................................................................................... III-11
Tabel 3.5. Panjang Penyambungan Tulangan (L) mm ....................................................... III-12
Tabel 3.6. Tipe dan Ukuran Kolom .................................................................................... III-13
Tabel 5.1. Perhitungan Persentase Kuat Tekan Beton Umur 7 Hari terhadap 28 Hari ....... V-21
Tabel 5.2. Perhitungan Standar Deviasi Kuat Tekan Beton ................................................ V-21
Tabel 4.1. Bagian-bagian PCH ...........................................................................................IV-11
Tabel 6.1. Hasil Uji Kuat Tekan Beton ................................................................................VI-7
Tabel 6.2. Konversi Beton ....................................................................................................VI-7
Tabel 6.3. Hasil Uji Kuat Tarik Baja Tulangan ....................................................................VI-9
xiii
DAFTAR PUSTAKA
Amrigunasti. 2011. Perencanaan Proyek .
https://amrigunasti.wordpress.com/tag/perencanaan-proyek/ . (diakses tanggal 25
Desember 2014)
Departemen Pekerjaan Umum. 1983. Peraturan Pembebanan Indonesia Untuk
Bangunan Gedung 1983. Bandung : Yayasan Lembaga Penyelidikan Masalah
Bangunan.
Dimyati, Hamdan & Kadar Nurjaman . 2014 . Manajemen Proyek. Pustaka Setia :
Bandung
Drymix. 2011 . Mortar Siap Pakai . http://drymix.co.id/mortar/ . (diakses tanggal 21
Februari 2015)
Ilmu Sipil. 2013. RAP Rencana Anggaran Biaya Proyek Pembangunan.
http://www.ilmusipil.com/rap-rencana-anggaran-biaya-proyek-pembangunan
(diakses tanggal 27 Januari 2015)
Muhammad Abdat, Jamal . Struktur Beton II . Universitas Mercu Buana : Jakarta
Panitia Teknik Standardisasi Bidang Konstruksi dan Bangunan . 2002 . SNI 03-2847-
2002 Tata Cara Perhitungan Struktur Beton Untuk Bangunan Gedung . Badan
Standardisasi Nasional : Bandung.
Panitia Teknik Konstruksi dan Bangunan. 2002. SNI-03-1726-2012 Tata Cara
Perencanaan Ketahanan Gempa untuk Bangunan Gedung dan Non Gedung.
Badan Standardisasi Nasional.
Winter, George & Arthur H. Nilson. 1993 . Perencanaan Struktur Beton Bertulang .
Pradnya Paramita : Jakarta.