Upload
aitthailand
View
3
Download
0
Embed Size (px)
Citation preview
KIVI 17 april 2003
S-lay J-lay
pipe made up at sea pipe made up on shore
reel pull and tow
surface tow
mid-depth tow
bottom tow
bottom pull
* Overall safety record was very good for the activity setinvolved(one high potential lifting incident during Solitaire mobilisation, onemedical treatment case on the survey vessel)* 105 km of 22" concrete coated pipe laid in under 18 daysincludingpull in and lay down. * Average lay rate of ~6.9 km/day (or over 4 meters/minute)* Peak lay rate ~7.8 km over a 24 hour period * No weather downtime & very minimal mechanical downtime* Program completed 11 days ahead of the 30 day plan (lump sumcontract)* 28 kilometres were laid between the live Magnus gas lines (100meters apart)
advantages of S-lay
whole length of barge can be used for operations at multiple stations (line-up, welding, radiography, field joint infill, tension)
disadvantages of S-lay
in deep water, tension has to be highand/or stinger has to be long
advantages of J-lay
tension can be much lower, particularly in deep watertouchdown point is closer to barge, and spans are shorterno stingerpipe less exposed to wave actionbarge can lower pipe and then weather-vane around
disadvantages of J-lay
welding all carried out at one or two stationsinflexible if breakdown occursnot suitable for very shallow water unless ramp can be rotated into horizontal position
mechanics of pipelayingV
U
in deep water (>100 m) the pipe is (almost) a catenary, and its shape is determined by the interaction between the submerged weight w per unit length and the horizontal tension U
only in small boundary layers near the seabed touchdown and the stinger lift-off is the flexural rigidity F significant
the maximum curvature is ≈ w/U
tow
for all tow methods, the pipe has to have a uniform low weight during the tow
for bottom tow, the route has to be surveyed carefully, and the pipe must have an abrasion-resistant coating that can stand up to being dragged across the seabed
PLUTO (Pipe Line Under The Ocean) England to France, 1944
100 km+, two kinds of 3-inch pipe, one steel ERW, no coating, the other a hollow submarine cable
vertical axis reel (e.g.Global Chickasaw, Hercules)
two types of reelships
horizontal axis (e.g. Apache, Deep Blue, Skandi Navica, Seven Oceans)
how much wall thickness is needed to prevent buckling during reeling ?
sometimes said: D/t < 20 or 22 not so!
larger diameters require a smaller D/t
quantify
pipe diameter D, wall thickness t
reel diameter b
+=
=−
=
−=
=
b
fDtD
b
fD
D
t
f
D
t
bD
01.0
1/
01.0
safety offactor geometric if so
0.85) < ileyield/tens and 1, asfactor girth weld taking(
01.0strain buckling DnV
/strain bending maximum
pipe with concrete weight coating cannot be reeled
links choice of construction method to design of pipeline
if stability is a governing factor, requires the steel thickness to be increased to give the pipeline enough weight
expensive (particularly for CRA pipe)
leads to other difficulties (such as upheaval buckling)
means that anti-corrosion coating has to resist potential mechanical damage
alternative flexible concrete weight coating
polymer-modified rubber-like concrete
more expensive than conventional concrete, but much cheaper than steel (per kg of submerged weight)
can be applied
gives mechanical protection to anti-corrosion coating
reeled bundles
simple pipe-in-pipe systems can be reeled (e.g. Seahorse and Tarwhine projects)
studies have shown that more complex bundles can also be reeled
possibility of helical bundles (Husham patent 1895)
carrier diameter and wall thickness limited by reeling capacity
reeled bundles compared with towed bundles
reeled
carrier diameter limited submerged weight can be largeroute can be curved
towed
carrier diameter not limitedsubmerged weight during tow needs to be smallfinal route must be straight