Hello to all , hope you all had a good weekend.

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 5th March 2017

Miltiadis Charalampidis (AKA Miltos) joined us this week as

an assistant Projects co ordinator at MDH – John please ask him to make a

Linkedin profile and join the team ESI group

Some Points Before Starting

Shridar will be on long leave from 17 Feb 2017 to 20th March

Dennis Smith has resigned from his post as Projects Co Ordinator will

work till 17th March 2017 - We will struggle to fill in Dennis’ shoes and I will need everyone’s help until we

find his replacement- I would like to thank Dennis for the service he gave ESI and wish him luck on his

future

Page 4: TW@ESI 5th March 2017

Projects and Deadlines

16_025_DeLaRue_OFX

50% of the machines should ready for commissioning by CFH

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

16_066_Sterling_DCS_Line2

We have started some preliminary engineering here.... Kick off is scheduled for 7th March

16_040_Playmobil_Factory

We have started design and engineering here on MCC1 and 2 and I have started placing major orders .... Kick off is scheduled for 7th March

Page 5: TW@ESI 5th March 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

D20 ASRD being built by sub contractor and scheduled for 9th March 2017

15_023 Q012 [D10 Endicare 230V] - Beginning april 2017

D05 M 110 – scheduled for 1st May 2017

D20 ASRD 690 is presently in quotation stage

16_041_RSM_Security

We need to close off here – the sooner the better

SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)

16_058_Methode

Another fast tack project Jace Based AHU control system here

I know that CCI , DSH and installation team have done some real efforts here... Panel and most equipment has been energised- well done –

Next is testing and commissioning

Page 6: TW@ESI 5th March 2017

Projects and Deadlines

12_043_LSP

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

We also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 5th March 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 5th March 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OTM – Started SSA’s Q021 docs revision request

Playmobil HF80 – Status review with SAA- Started & Finished Panel Design sketching for MCC1, Compiled and released Material quote request

Design

Page 9: TW@ESI 5th March 2017

01 02 03 04

DesignAnd next week… we will work on

Start & complete new FM Env. Panel then send to CFH to submit

Playmobil HF80 – review Material quote, and release to Manuel to orderPlaymobil HF80 – release MCC1 to NFH for draughtingPlaymobil HF80 – Start Panel design of MCC2 and releas Material quote request

Design

OTM – Continue Q020 Netherlocks remaining DesignOTM – Start SSA’s Q021 docs revision request

Page 10: TW@ESI 5th March 2017

This is what the Installation team have been working on last week

Mounting of panel on site at Methode

Completed indoor PIR’s and started fixing power supplies at Graham

Installation

Energized panel and equipment at MethodeCompleted control cables pulling at Methode

Continued with commissioning at RSM

Page 11: TW@ESI 5th March 2017

….. And this is what is planned for next week

Complete snags on Methode panel

Start with panel terminations at Graham

Start commissioning at Methode

Installation

Continue with terminations at OVT

Complete commissioning at RSM

Page 12: TW@ESI 5th March 2017

Next week we will • FM Env D20-ASRD – This will be built by a sub contractor

Panel Build

Panel Build

Page 13: TW@ESI 5th March 2017

Week 09PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5

Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1

Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team member

Mater Dei Maintenance

Page 14: TW@ESI 5th March 2017

Crane Currency BMS and ELV Proposals

lighting control systems in Qatar

Offer for Neatherlocks at OTM

De La Rue BMS

Actavis Solvent area Process quoteThese are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 5th March 2017

\

HAPPY BIRTHDAYGLENN GHIRXI MARCH 6TH

Page 16: TW@ESI 5th March 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable