TW@ESI 20 th March 2016 Hope that you and all your families had a good weekend. The following is a forecast of the next week..... I am on leave for the next week from snowy but very sunny Livigno.... Hope I to return in one whole piece

TW@ESI 20th March 2016

Embed Size (px)

Citation preview

Page 1: TW@ESI 20th March 2016

TW@ESI20th March 2016Hope that you and all your families had a good weekend.

The following is a forecast of the next week.....

I am on leave for the next week from snowy but very sunny Livigno.... Hope I to return in one whole piece

Page 2: TW@ESI 20th March 2016

A General Note before we startI would like to thank once again all the team for the efforts to complete the offices upstairs. The plan next for this week is: a) Finish all DALI terminations and controls upstairsb) Pass all PIR cables and AC control cablesc) Finish all paintwork upstairsd) Next stage will involve works in design and

technical office- before this is done the show room area must be closed off and electrical supply made permanent with Enemalta (to allow people to relocate to here)

Page 3: TW@ESI 20th March 2016

A General Note before we start

In the last two weeks we have had a further two resignations from the company.

Graziella has given her notice and will work her notice till 4th May 2016 whilst Lino has also resigned last week and will be working till 18th April 2016. These are difficult times to fill in gap these resources will leave within the organisation but we must all re group and pull the rope of success.

Page 4: TW@ESI 20th March 2016

Projects and deadlines• 15_033_Westin_7-AHU- With everyone’s effort we have

managed to change over the Banquet hall AHUs- not only but start these remotely from the engineering PC- Next target- finish all Testing and commissioning works by end of month (March 2016)

• 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project- All terminations possible are to be completed by 28/3

• 14_001_Fadalah- CVA will be going to site to a ship yard in Greece (not Istanbul) and commissioning this in first week of April 2016.

Page 5: TW@ESI 20th March 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring- Panels to be completed by 23/3/2016. All installation and manual start up by end first week of April 2016- Manual start-up, soon after. Full T&C by end of April 2015. We have given most of the installation works to Panta and we need to ensure that Panta’s work is to the required standard.

• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and 12_027 Security Systems Parliament- LVA and JPO will put whatever efforts necessary to close off whatever can be closed off by 1st April 2016.

Page 6: TW@ESI 20th March 2016

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We have made

progress on commissioning here- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Get the Automation in the new area offices ready by March 2016!! Make sure it is fully functional and de snagged- Installation upstairs are to be completed shortly.... Design and Technical offices will be moved soon after that!

Page 7: TW@ESI 20th March 2016

DesignLast week• Vibrant Helvar Ligting – Panel Design of LCP, submitted to

Client• Sterling Chemicals – Silvio update SAS-000928 (complete by

18-03-2016)• ESI Offices Development – sketched Power & Data

requirements for JGH office, CVA office (awaiting CVA feedback before releasing for cable pulling)/sketched DALI Grd floor, awaiting CCi various feedback before releasing for cable pulling

• Siggiewi – Stickers for Switches, after receipt of info from Cci• OVt New Residence 15_038 – Received full brief from SAA

Page 8: TW@ESI 20th March 2016

DesignNext Week:• City Gate Parliament – Additional Lift –

implement As Built update from Lva• City Gate Parliament DAC Panels As Built update• MDH MAU – conclude research & request

quote of Engraved labels & matching rivets for D00-CC1

• OVt New Residence 15_038 – create list of queries & discuss, start on Points Lists, P&IDs

Page 9: TW@ESI 20th March 2016

InstallationPast week:– Fitted dali fittings at ESI offices level 1– Continued with plastering and painting at ESI offices

level 1– Migrated remaining AHU’s to MCC 2 and can be

controlled through network at Westin– Migrated dehumidifier to work manually on MCC 1

at Westin– Modifications to supply utp extenders and switches

on MCC 2 and Existing panel at Westin– Started mesh tray In plant room at Hilton (by Panta)

Page 10: TW@ESI 20th March 2016

InstallationNext week:– Install and commission dali switches and sensors at

ESI offices level 1– Commissioning at Life sciences– Commissioning of cctv and DAC at parliament– Testing of all Hilton panels– Installation of panels at Hilton– Finish Mesh tray and start cable pulling at Hilton– Complete labelling and some small works at Westin– Continue with terminations at Smart City Lagoon

Page 11: TW@ESI 20th March 2016

Panel Build• Testing of Hilton Panels

Page 12: TW@ESI 20th March 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• FIELD DEVICES CHECKS FROM SITE/HMI C01-CC1, CP1-CC1, C01-CC2, (D03-CC1), C02-

CC1, C03-CC1, C04-CC1, C05-CC1, C06-CC1, C07-CC1, C07-CC2, C08-CC1, CP2-CC1• Coordinated Checks of Alarms from 3rd Party Devices D10-CC1, D10-CC2, D10-CC3, D11-

CC1, DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D10-CC1, D10-CC2, D10-CC3, D11-CC1, DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D11-CC2, D12-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL E01-CC1, E02-CC1. EP1-CC1, F01-CC1, F02-CC1,

F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES E01-CC1, E02-CC1, EP1-

CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - MARCH• PANEL THERMOGRAPHICAL IMAGES E01-CC1, E02-CC1, EP1-CC1• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1,

T01-CC1, T02-CC1• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Preparation work for new HMIs for D05-CC1, D06-CC1, D07-CC1

Page 13: TW@ESI 20th March 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• The plan for Life sciences is to complete all works by 18th March and training by 21st March 2016

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 14: TW@ESI 20th March 2016

Development and Commissioning

• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed –intruder alarm integration• Oncology 14_066- We have done most of the work here and

are waiting from Panta on this• The Siggiewi Primary school project – we need to close off –

there is very little left here• Aurobindo we are proceeding with software development and

we have done quite some progress – we now will be starting commissioning

Page 15: TW@ESI 20th March 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 16: TW@ESI 20th March 2016

Sales and Business Development

• We have been working on Home automation offerings and quotes for OTM (some of which are quite large) , a quote for CCTV at Enemalta and quotes for variations for existing projects.

Page 17: TW@ESI 20th March 2016

• More lessons to follow shortly

Page 18: TW@ESI 20th March 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 19: TW@ESI 20th March 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week