Upload
tanya-ambler
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
Welcome
Introductions
Agenda
• Welcome
• Introductions
• Design Phase Overview
• Stakeholder Interview Findings
• Design Options
• Next Steps
Public Engagement Approach
To provide stakeholders opportunities to give input and
participate in the decision-making process for Olympian Drive Extension
Design Phase
Public Engagement Approach
• Stakeholder Engagement – re-group affected community members before preliminary engineering work
• Outreach Activities – bring project team and public together to exchange information and address issues and concerns
• Communication – keep the public informed about the project and its progress
Stakeholder Roundtable Meeting
• Stakeholders invited to roundtable discussions on:
• Tuesday, July 27, 2010
• Business Representatives at 12:00 p.m.
• Property Owners and Residents at 5:00 p.m.
• Thursday, July 29, 2010
• Area officials at 3:00 p.m.
• Elected officials at 7:00 p.m.
Stakeholder Roundtable Meeting Purpose
• Review what we heard during stakeholder interviews
• Seek other issues that need to be addressed
• Discuss ways to mitigate identified concerns
Design Phase Overview
Olympian Drive Overview
What is the Olympian Drive extension? How did it Start?Not on existing
OlympianNot on existing
OlympianWider Floodplain
CrossingWider Floodplain
CrossingIntersection on curve
Intersection on curve
Not on existing Olympian
Not on existing Olympian
Intersection on curve
Intersection on curve
Curved BridgeCurved Bridge
Limits AirportLimits
Airport
Curved Farm Severance
Curved Farm Severance
Curved Farm Severance
Curved Farm Severance Curved Farm
SeveranceCurved Farm
Severance
Longer BridgeLonger Bridge
Residential Impacts
Residential Impacts
Commercial Impacts
Commercial Impacts
IDOT1989IDOT1989
Wider Floodplain Crossing
Wider Floodplain Crossing
Intersection on curve
Intersection on curve
Olympian Drive Overview
What is the Olympian Drive extension? How did it Start?
Longer BridgeLonger Bridge
Wider Floodplain
Wider Floodplain
Residential Impacts
Residential Impacts
Farm Severances
Farm Severances
Olympian Drive Overview
What is the Olympian Drive extension? How did it Start?
DisplacementsDisplacementsWider
FloodplainWider
Floodplain
Longer BridgeLonger Bridge
More Public Support
More Public Support
Olympian Drive Overview
What is the Olympian Drive extension? How did it Start?
Recommended Alternative
Recommended Alternative
Olympian Drive Overview
What is the Olympian Drive extension? How has development occurred?
1940
1967
1982
1993
2002
2008
Olympian Drive Overview
What is the timeline?
Olympian Drive Overview
What is the Olympian Drive extension? What does it look like now?
Olympian Drive Overview
What is the Olympian Drive extension? How does it fit into the regional road plan?
Olympian Drive Overview
• What is the Olympian Drive extension? What is the land planning?
Olympian Drive Overview
What is the Olympian Drive extension? What are the limits of the design?
Project A Project BProject C
Olympian Drive Overview
What is the design phase?
•Public engagement to aid in Olympian Drive design
•Limited update of Location Study, including:
• Review approved alternative’s environmental effects
• Review pedestrian and bicycle accommodations
• Design intersections for interim two-lane construction
• Review typical sections and construction staging
•Preparation of construction plans
Olympian Drive Overview
Who is conducting the Design Phase?
• Hanson Professional Services Inc. (Springfield, IL) – Prime Design Consultant
• Vector Communications (St. Louis, MO) – Public Engagement
• Berns, Clancy and Associates (Urbana, IL) - Topographic Survey, Right-of-Way Survey and Right-of-Way plats (when necessary)
• Clark Dietz (Champaign, IL) - Traffic Signals and Lighting
• Midwest Engineering and Testing, Inc. (Champaign, IL) – Geotechnical Engineering
• Whitsitt & Associates , Inc. (Champaign, IL) – Land Appraisals (when necessary)
• James H. Webster and Associates, Ltd. (Urbana, IL) – Land Appraisal Review (when necessary)
Olympian Drive Overview
Why is the Design Phase necessary?
•Location Study only identified roadway’s location
•Provide public opportunities to give input and participate in design decision-making process
•Review environmental effects of approved alternative verifying it is still valid
•Gives the opportunity to include enhancements to the project based on public input
•Prepare detailed designs needed to construct roadway
• Allows for the use of federal funds for construction
Olympian Drive Overview
What is the process?
Stakeholder Findings
Stakeholder Engagement
• Interviews conducted with Urbana, Champaign and Champaign County representatives
• Elected officials (9)
• Area officials (3)
• Business community (7)
• Impacted property owners (4)
Stakeholder Interviews
• More than 20 stakeholder interviews• Eight respectfully declined
• Elected officials (3) and Property Owners (5)
• Average interview lasted 50 minutes
What are your expectations of the project and/or project team?
The project will be successful if _________________. (fill in the blank)
What concerns do you have?
What other community issues, developments or planning activities should the team consider?
Design Options
Olympian Drive DesignTypical Section Options
Olympian Drive DesignTypical Section Options
Olympian Drive DesignTypical Section Options
Typical Section Advantages Disadvantages
Open Large Median
• Safer design• Higher design speed for more capacity• Controls access• Allows for larger future facility expansion
• Requires more ROW• Higher operating speeds• Higher cost than closed median with
outside shoulder
Closed Smaller Median
• Requires less ROW• Lower speeds for safer design• Controls access• Landscaping in median• Lower cost than open median (outside shoulder)
• Lower design speed for less capacity• Smaller future facility expansion• Higher cost than open median (C&G on
both sides due to storm sewer costs)
Smallest Median
• Requires least amount of ROW• Least cost option with outside shoulders
• Costs more for left turn lanes in the future• No greenspace between roadways• No accommodations for future facility
expansion• Traffic very close together which is less
safe than the open and closed medians
What are your thoughts about the use of the grassed median, raised
curb median or small median for Olympian Drive?
Olympian Drive DesignConstruction Staging Options
• Existing land use would remain
• Property would still be acquired for corridor protection
• Land could be rented back to former property owners
Olympian Drive DesignConstruction Staging Options
Typical Section Advantages Disadvantages
Construct all Embankment
• Takes advantage of current prices and project available Federal funding
• Removes ground from existing land use for future lanes
Construct only what is
necessary for the first two
lanes
• Limits current impact on existing land use
• Will cost more in the future to build additional embankment
What are your thoughts on building the additional embankment at this
time or preserving the adjacent land use?
Olympian Drive DesignBicycle Accommodation Options
Olympian Drive DesignBicycle Accommodation Options
Olympian Drive DesignBicycle Accommodation Options
Bicycle Accommodation
Advantages Disadvantages
Separate Combined Use
Path
• Safest method to provide accommodations
• Would also include pedestrian accommodations, negating need for separate sidewalks
• Requires additional ROW• Adds additional costs to project• Adds bridge costs to railroad and stream
crossing• May not get used until development
occurs
Widened Shoulders
• Adds no additional cost to project• Adds no additional ROW to project
• Bicycle traffic close to vehicular traffic
None at this time• In line with the original study • Doesn’t take advantage of current prices
and project available federal funds
What are your thoughts on the needs for bicycle accommodations for
Olympian Drive?
Olympian Drive DesignPedestrian Accommodation Options
Olympian Drive DesignPedestrian Accommodation Options
Pedestrian Accommodation
Advantages Disadvantages
Located on back side of ditch
• Safest method of providing accommodations
• Requires additional ROW• Adds additional costs to the project• Adds bridge costs to railroad and stream crossing• May not get used until development occurs
Located behind curb and gutter
• Requires additional ROW• Adds additional costs to the project• Adds bridge costs to railroad and stream crossing• May not get used until development occurs
None at this time• In line with the original study • Doesn’t take advantage of current prices and
federal funds available for project
What are your thoughts on the needs for sidewalks for Olympian
Drive?
Olympian Drive DesignNorth Lincoln Avenue
• North Lincoln
Alternatives and
Recommended
Alternative (approved
in 1999)
Olympian Drive Overview
Recently Publicized Alternatives Challenges:
• Does not support purpose and need (both)
• Not approved by IDOT/FHWA (both)
• Road crosses at super-elevated angle at widest portion of rail yard (Oct. 2009)
• Does not meet IDOT criteria for roadway curvature, based on Location Study (both)
• Not geometrically feasible (June 2010)
• Suggests use of Leverett Road/Ford Harris for east-west connection (both)
• Limits development potential along rail line (both)
• Cost over twice as much more with local funds with no study and built as-is
• A combination of approved plans can achieve the same goal
Olympian Drive DesignNorth Lincoln Avenue (Project X)
• How does North Lincoln fit in?
Between projects A, B, C and X, what order do you feel is best for providing access and economic development opportunity for this region?
Project A Project BProject C
Proj
ect X
Olympian Drive DesignOther Design Elements
Location Study Detention Areas
• Designed for future development needs
• Excavation used for roadway embankment
• Requires larger ROW (100 ft)
• Detention not required for first construction stage W
illow
Lin
coln
Olympian Drive DesignOther Design Elements
Wetland Creation vs. Detention
What are your thoughts about the construction of wetlands or detention ponds and their implementation right now?
Advantages:
• More aesthetically pleasing
• Creates additional wildlife habitat
• Better at improving water quality
Disadvantages:
• Costs more than detention
• Not necessary for project
• Ongoing maintenance
Olympian Drive DesignOther Design Elements
Roundabout Intersection
Advantages:
• Fewer conflict points
• Reduce start/stops, less fuel used
• No signalization costs or maintenance
• Slower speeds
• Landscaping enhancements
• Safety
Disadvantages:
• Unusual for Central Illinois
• Possible higher initial costs
• Possible more ROW
• Slower speeds
Yield at roundabout
Yield at roundabout
Proceed throughProceed through
Truck ApronTruck Apron
Landscaping in middle
Landscaping in middle
What are your thoughts on the use of roundabout intersections for Olympian Drive (Olympian/Lincoln)?
Olympian Drive DesignOther Design Elements
•Recreation use at Saline Branch Crossing
Would recreational use access be an important feature you would like to see in Olympian Drive design?
Olympian Drive DesignOther Design Elements
Landscaping
What are your thoughts on the use of landscaping for Olympian Drive?
Olympian Drive DesignOther Design Elements
Tree Mitigation
• Mitigation Required
• 1:1 minimum ratio
Where do you feel the best Olympian Drive tree replacement location(s) should be?
Will
ow
Linc
oln
Olympian Drive DesignOther Design Elements
Are there other design elements/features that we haven’t discussed that you feel would be an important part of the Olympian Drive design?
Next Steps
Questions?