SECOND DRAFT MEETING AGENDA
NFPA Technical Committee on Emergency Power Supplies (EPS-AAA)
Second Draft Meeting for 2019 Edition of NFPA 110 and NFPA 111
July 19, 2017
Teleconference / Web Meeting
Item No. Subject
17-7-1 Call to Order
17-7-2 Introduction of Members and Guests (Attachment A)
17-7-3 Approval of Previous Meeting Minutes (Attachment B)
17-7-4 Review of Regs and Committee Actions
17-7-5 Task Group Reports
17-7-6 Processing of Public Comments (Attachment C)
17-7-7 Old Business
17-7-8 New Business
17-7-9 Adjournment
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 1 of 30
Attachment A: Technical Committee Roster
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 2 of 30
Address List No PhoneEmergency Power Supplies EPS-AAA
National Electrical Code®
Christopher Coache07/06/2017
EPS-AAA
Dan Chisholm, Sr.
ChairMGI Systems, Inc.PO Box 2474Winter Park, FL 32790-2474Alternate: Dan Chisholm, Jr.
IM 10/1/1993EPS-AAA
Ernest E. Allen
PrincipalThe Doctors Company5001 Mayfield Road, Suite L55Lyndhurst, OH 44124NFPA Health Care Section
I 7/1/1990
EPS-AAA
Kenneth A. Cotton
PrincipalUS Energy/Donlee CropNetwork Operation Center140 East Stetson AveSuite 309Hemet, CA 92543Alternate: Joshua Dugger
M 10/1/1999EPS-AAA
Jason D'Antona
PrincipalThompson Consultants, Inc.525 Mill StreetMarion, MA 02738
SE 03/07/2013
EPS-AAA
David A. Dagenais
PrincipalPartners/Wentworth-Douglass Hospital789 Central AvenueDover, NH 03820
U 08/09/2012EPS-AAA
Richard L. Day
PrincipalMichigan State Fire Marshal's Office207 Jackson StreetAllegan, MI 49010-9156
E 03/03/2014
EPS-AAA
Dennis DeMoss
PrincipalSargent & Lundy55 East Monroe StreetChicago, IL 60603Alternate: David C. Skiba
SE 1/1/1990EPS-AAA
William H. Everard
PrincipalEverard Mid Atlantic Inc.8743 Center RoadSpringfield, VA 22152-2234
SE 1/1/1979
EPS-AAA
Louis J. Feller
PrincipalUS Army Corps of Engineers8212 126th Place SENewcastle, WA 98056-9132
U 03/03/2014EPS-AAA
James R. (Skip) Gregory
PrincipalHealth Facility Consulting4128 Zermatt DriveTallahassee, FL 32303-2252Florida Agency for Health Care Administration
E 3/21/2006
EPS-AAA
Ross M. Hardy
PrincipalThe University of Michigan Medical CenterPlant Hospital Maintenance1500 East Medical Center DriveAnn Arbor, MI 48073-6712
U 7/14/2004EPS-AAA
Jonathan Hartsell
PrincipalRodgers5701 North Sharon Amity RoadCharlotte, NC 28215
IM 07/29/2013
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 3 of 30
Address List No PhoneEmergency Power Supplies EPS-AAA
National Electrical Code®
Christopher Coache07/06/2017
EPS-AAA
Oleh Kowalskyj
PrincipalU.S. Department of Veterans AffairsVeterans Health Administration (10NAS)810 Vermont Avenue, NWWashingston, DC 20420US Department of Veterans AffairsAlternate: Gary Krauch
U 04/04/2017EPS-AAA
Pouyan Layegh
PrincipalUniversity of Texas MD Anderson Cancer Center3126 Barrons WaySugar Land, TX 77479
U 11/30/2016
EPS-AAA
Chad E. Loomis
PrincipalCornell University2336 South Balch HallIthaca, NY 14853
U 3/2/2010EPS-AAA
Alan Manche
PrincipalSchneider Electric1601 Mercer RoadLexington, KY 40511-1025
M 10/23/2003
EPS-AAA
George Mills
PrincipalThe Joint CommissionDepartment of EngineeringOne Renaissance BoulevardOakbrook Terrace, IL 60181Joint Commission on Accreditation HealthcareOrganizations
E 3/15/2007EPS-AAA
Dermott Murphy
PrincipalWashington State Patrol - Fire Prevention BureauPO Box 42642Olympia, WA 98504
E 11/30/2016
EPS-AAA
Hugh O. Nash, Jr.
PrincipalNash-Consult964 General George Patton RoadNashville, TN 37221Alternate: Bogue M. Waller
SE 10/3/2002EPS-AAA
Daniel J. O'Connor
PrincipalJENSEN HUGHES/AON Fire Protection Engineering4 Overlook PointLincolnshire, IL 60069-4302Alternate: Raymond J. Battalora
I 1/1/1984
EPS-AAA
Gary L. Olson
PrincipalkW Rx, LLC12979 Killdeer Street NWMinneapolis, MN 55448-7018
SE 08/09/2011EPS-AAA
Steve R. Sappington
PrincipalCaterpillar Inc.175 Cutstone CourtFayetteville, GA 30215-6206
M 08/11/2014
EPS-AAA
Ronald A. Schroeder
PrincipalASCO Power Technologies, LP160 Park AvenueFlorham Park, NJ 07932Alternate: Brian J. Escott
M 1/10/2008EPS-AAA
Randy H. Schubert
PrincipalEricsson444 Hoes LanePiscataway, NJ 08854-4104Alliance for Telecommunications Industry SolutionsAlternate: Richard G. Kluge
U 12/08/2015
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 4 of 30
Address List No PhoneEmergency Power Supplies EPS-AAA
National Electrical Code®
Christopher Coache07/06/2017
EPS-AAA
Ronald M. Smidt
PrincipalCarolinas HealthCare SystemPO Box 901Troutman, NC 28166American Society for Healthcare Engineering
U 7/24/1997EPS-AAA
Raymond J. Stanko
PrincipalUL LLC333 Pfingsten RoadNorthbrook, IL 60062-2096
RT 8/9/2011
EPS-AAA
David Stymiest
PrincipalSmith Seckman Reid, Inc.2995 Sidco DriveNashville, TN 37204
SE 1/12/2000EPS-AAA
Herbert V. Whittall
PrincipalElectrical Generating Systems Association19 Park AvenueVero Beach, FL 32960Alternate: James Hunt
M 11/30/2016
EPS-AAA
Timothy P. Windey
PrincipalCummins Power Generation1400 73rd Avenue NEMinneapolis, MN 55432-3702
M 08/03/2016EPS-AAA
Michael J. Lang
Voting AlternateMersen1135 Arva DriveRoswell, GA 30076National Electric Fuse Association
M 10/29/2012
EPS-AAA
Rich Scroggins
Voting AlternateCummins Power Generation3850 North Victoria StreetShoreview, MN 55126-2907
M 10/28/2014EPS-AAA
Raymond J. Battalora
AlternateJensen Hughes/AON Fire Protection EngineeringProject Director1701 North Collins Boulevard, Suite 235Richardson, TX 75080-3553Principal: Daniel J. O'Connor
I 4/3/2003
EPS-AAA
Dan Chisholm, Jr.
AlternateMGI Systems, Inc.412 Page StreetOrlando, FL 32806Principal: Dan Chisholm, Sr.
IM 7/14/2004EPS-AAA
Joshua Dugger
AlternateFacility Shield International14419 Veterans WayMoreno Valley, CA 92553-9059Principal: Kenneth A. Cotton
M 10/29/2012
EPS-AAA
Brian J. Escott
AlternateASCO Power TechnologiesVice President, Power Control Systems160 Park AvenueFlorham Park, NJ 07932-1419Principal: Ronald A. Schroeder
M 07/29/2013EPS-AAA
James Hunt
AlternateHostrat Inc.5723 East AlkiSpokane, WA 99212Electrical Generating Systems AssociationPrincipal: Herbert V. Whittall
M 08/03/2016
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 5 of 30
Address List No PhoneEmergency Power Supplies EPS-AAA
National Electrical Code®
Christopher Coache07/06/2017
EPS-AAA
Richard G. Kluge
AlternateEricsson1 Ericsson DrivePiscataway, NJ 08854Alliance for Telecommunications Industry SolutionsPrincipal: Randy H. Schubert
U 12/08/2015EPS-AAA
Gary Krauch
AlternateVirginia New England Healthcare System2000 Springs RoadBuilding 61Bedford, MA 01730US Department of Veterans AffairsPrincipal: Oleh Kowalskyj
U 04/04/2017
EPS-AAA
David C. Skiba
AlternateSargent & Lundy LLC55 East Monroe StreetSuite 2710Chicago, IL 60603-5821Principal: Dennis DeMoss
SE 10/28/2014EPS-AAA
Bogue M. Waller
AlternateGresham Smith & Partners1400 Nashville City Center511 Union Street, Suite 1400Nashville, TN 37219Principal: Hugh O. Nash, Jr.
SE 10/23/2013
EPS-AAA
Christopher Coache
Staff LiaisonNational Fire Protection Association1 Batterymarch ParkQuincy, MA 02169-7471
8/7/2011
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 6 of 30
Attachment B: Previous Meeting Minutes
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 7 of 30
National Fire Protection Association
1 Batterymarch Park, Quincy, MA 02169-7471
Phone: 617-770-3000 • Fax: 617-770-0700 • www.nfpa.org
TO: Technical Committee on Emergency Power Supplies DATE: September 7, 2016 SUBJECT: Minutes of NFPA 110 and 111 First Draft Teleconference/Web Meeting Meeting Location: Teleconference/Web Agenda Item 16-9-1 – Call to Order The teleconference/web meeting was called to order by Chair Dan Chisholm, Sr at 10 am (Eastern Time). Agenda Item 16-9-2 – Introduction of Members and Guests Attendees participating in the teleconference/web meeting were as follows: TECHNICAL COMMITTEE MEMBERS PRESENT
NAME COMPANY
Dan Chisholm, Sr., Chair MGI Systems, Inc.
Herbert Daugherty, Secretary Electric Generating Systems Association
Kenneth A. Cotton, Principal US Energy/Donlee Crop
Jason D’Antona, Principal Thompson Consultants, Inc.
Dennis DeMoss, Principal Sargent & Lundy
Louis Feller, Principal US Army Corps of Engineers
James Gregory, Principal Health Facility Consulting
Jonathan Hartsell, Principal Rodgers
James Hunt, Principal HOTSTART Inc.
Chad Loomis, Principal Cornell University
Hugh Nash, Jr., Principal Nash-Consult
Gary Olson, Principal kW Rx, LLC
Steve Sappington, Principal Caterpillar Inc.
Ronald Schroeder, Principal ASCO Power Technologies, LP
Ronald Smidt, Principal Carolinas HealthCare System Rep.: American Society for Healthcare Engineering
David Stymiest, Principal Smith Seckman Reid, Inc.
Hebert Whittall, Principal Electrical Generating Systems Association
Timothy Windey, Principal Cummins Power Generation
Michael Lang, Voting Alternate Mersen Rep.: National Electric Fuse Association
Joshua Dugger, Alternate to K. Cotton Facility Shield International
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 8 of 30
National Fire Protection Association
1 Batterymarch Park, Quincy, MA 02169-7471
Phone: 617-770-3000 • Fax: 617-770-0700 • www.nfpa.org
TECHNICAL COMMITTEE MEMBERS NOT PRESENT
NAME COMPANY
Ernest Allen, Principal The Doctors Company Rep.: NFPA Health Care Section
David Dagenais, Principal Wentworth-Douglass Hospital
Richard Day, Principal Michigan State Fire Marshal’s Office
William Everard, Principal Everard Mid Atlantic Inc.
Ross Hardy, Principal The University of Michigan Medical Center Plant Hospital Maintenance
Alan Manche, Principal Schneider Electric
Daniel O’Connor, Principal JENSEN HUGHES/AON Fire Protection Engineering
Ralph Patterson, Principal Power Products & Solutions Inc. Rep.: InterNational Electrical Testing Association
Raymond Stanko, Principal UL LLC
Larry Lau, Voting Alternate US Department of Veterans Affairs
Rich Scroggins, Voting Alternate Cummins Power Generation
Raymond Battalora, Alternate AENSEN HUGHES/AON Fire Protection Engineering
GUESTS
NAME
Sarah English
Vicky Giroux
Alisha Younts
Agenda Item 16-9-3 – Approval of Previous Meeting Minutes Minutes of the Second Draft meeting of the 2016 edition were approved. Agenda Item 16-9-4 – Review of NFPA Regulations and Committee Actions NFPA Staff Liaison Christopher Coache gave a presentation on the NFPA Standards Development Process for First Draft meetings.
Richard Kluge, Alternate to R. Schubert Telcordia Technologies (Ericsson) Rep.: Alliance for Telecommunications Industry Solutions
David Skiba, Alternate to D. DeMoss Sargent & Lundy LLC
Bogue Waller, Alternate to H. Nash, Jr. Gresham Smith & Partners
Christopher Coache, Staff Liaison National Fire Protection Association
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 9 of 30
National Fire Protection Association
1 Batterymarch Park, Quincy, MA 02169-7471
Phone: 617-770-3000 • Fax: 617-770-0700 • www.nfpa.org
Agenda Item 16-9-5 – Task Group Reports There were no active task groups in effect prior to the commencement of this meeting. Agenda Item 16-9-6 – Processing of Public Inputs NFPA 110 public inputs were processed. NFPA 111 public inputs were processed. Agenda Item 16-9-7 – Old Business No old business was brought up. Agenda Item 16-9-8 – New Business A task group (Dan Chisholm, Sr, Skip Gregory and Gary Olson) was formed to reword 5.6.5.6. Agenda Item 16-9-9 – Adjournment The teleconference/web meeting was adjourned at 7 PM (Eastern Time). (Meeting minutes prepared by C. Coache.)
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 10 of 30
Attachment C: Public Comment Report
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 11 of 30
Public Comment No. 11-NFPA 110-2017 [ Section No. 4.4 ]
4.4* Level.
This standard recognizes two levels for equipment installation, performance, and maintenancerequirements.
4.4.1*
Level 1 systems shall be installed where failure of the equipment to perform could result in loss of humanlife or serious injuries.
4.4.2*
Level 2 systems shall be installed where failure of the EPSS to perform is less critical to human life andsafety.
4.4.3*
All equipment shall be permanently installed.
4.4.4*
Level 1 and Level 2 systems shall ensure that all loads served by the EPSS are supplied with alternatepower that meets all the following criteria:
(1) Of a quality within the operating limits of the load
(2) For a duration specified for the class as defined in Table 4.1(a)
(3) Within the time specified for the type as defined in Table 4.1(b)
Additional Proposed Changes
File Name Description Approved
Correlating_Committee_Note_No_1.pdf 110_CCN1
Statement of Problem and Substantiation for Public Comment
NOTE: This Public Comment appeared as CC Note No. 1 in the First Draft Report on First Revision No. 2 and is also related to Public Input No. 51.
Substantiation: This section recognizes the two levels of systems that are used throughout the document. The correlating committee directs the technical committee to review 7.2.1 and 7.11.1, as well as the remainder of the document, for correlation and consistency in the application of these two levels. This will be considered as a public comment.
Related Item
FR 2
PI 51
Submitter Information Verification
Submitter FullName:
CC on NEC-AAC
Organization:NFPA NATIONAL ELECTRICAL CODE CORRELATINGCOMMITTEE
Street Address:
City:
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 12 of 30
State:
Zip:
Submittal Date: Tue May 09 16:43:46 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 13 of 30
Correlating Committee Note No. 1-NFPA 110-2017 [ Section No. 4.4 [Excluding any Sub-Sections] ]
Submitter Information Verification
Submitter Full Name: Mark Earley
Organization: National Fire Protection Assoc
Street Address:
City:
State:
Zip:
Submittal Date: Fri Jan 20 13:18:14 EST 2017
Committee Statement and Meeting Notes
Committee Statement:
This section recognizes the two levels of systems that are used throughout the document. The correlating committee directs the technical committee to review 7.2.1 and 7.11.1, as well as the remainder of the document, for correlation and consistency in the application of these two levels. This will be considered as a public comment.
Ballot Results
This item has passed ballot
12 Eligible Voters
0 Not Returned
12 Affirmative All
0 Affirmative with Comments
0 Negative with Comments
0 Abstention
Affirmative All
Brunssen, James E. Deike, Jr., Roland E. Dressman, Kevin L. Hickman, Palmer L. Hittinger, David L. Holub, Richard A. Johnston, Michael J. Kovacik, John R. Manche, Alan McCullough, Robert A. Pierce, James F. Saporita, Vincent J.
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 14 of 30
Public Comment No. 3-NFPA 110-2017 [ Section No. 5.2.1 [Excluding any Sub-Sections]
]
Energy converters shall consist only of rotating equipment as indicated in 5.2.4, or fuel cells as described inNFPA 852, Standard for Installation of Stationary Fuel Cell Power Systems .
Statement of Problem and Substantiation for Public Comment
Summary: To address the coordination of NFPA-70, NFPA-99 and NFPA-110, NFPA-110 should be changed to permit fuel cells as source of emergency power provided specific conditions are met.
Originally Proposed Changes to the Code:The following proposed changes were submitted by Walt Vernon during the public comment period on NFPA-110 as one way to permit fuel cells as a source of emergency power in NFPA-110 (Public Input #62 and Public Input #61 respectively):1. Change 5.2.1 to read: “Energy converters shall consist only of rotating equipment as indicated in 5.2.4, or fuel cells as described in NFPA 852, Standard for Installation of Stationary Fuel Cell Power Systems.
2. Additions to section 5.4 as follows: 5.4.1 Because Fuel Cells cannot come up to rated load within a reasonable time,
5.4.1.1. Fuel cell installations must consist of N+1 units operating in parallel, and continuously supplying power to the Emergency System.
5.4.1.2 Fuel cell installations shall have a normal utility supply available in case of total system failure. And
5.4.1.3 Fuel cell installations shall include a connection for portable diesel generator to supply the legally required life safety loads.
These changes were submitted to ensure coordination with NFPA-99 and NFPA-70 both of which permit the use of fuel cells for emergency power.
Committees initial Response:
The NFPA110 committee rejected these changes indicating that “currently fuel cells do not meet all of the performance requirements of NFPA 110.”
New Comment:The committee response in resolving PI 61 was that “fuel cells do not meet the requirements of Section 5.4.” The response to PI 62 was that “currently fuel cells do not meet all of the performance requirements of NFPA 110.” That is exactly what these proposals are trying to address and that resolution statement given by the committee on PI 61 and PI 62 do not address why the committee decided to reject this submittal.
We therefore suggest that the following be added to the text as section 5.4.1:5.4.1 Fuel cells shall be considered to meet the requirement of 5.4 where all of the following conditions are met: (1) Fuel cell installations consist of N+1 units operating in parallel, and continuously supplying power to the Emergency System. (2) Fuel cell installations have a normal utility supply available in case of total system failure. (3) Fuel cell installations include a connection for portable diesel generator to supply the legally required life safety loads.Additionally, section 5.2.1 should be modified as originally suggested, namely: Energy converters shall consist only of rotating equipment as indicated in 5.2.4 or fuel cells as described in NFPA 853, Standard for Installation of Stationary Fuel Cell Power Systems.
Additional Background Information
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 15 of 30
It does not appear the committee addressed the fact that fuel cells are already permitted as emergency power sources in other NFPA documents. The committee should further consider the change to ensure proper coordination between all NFPA codes.
Walt Vernon chaired the electrical systems committee for NFPA-99 at the time fuel cells were introduced for inclusion as a source of emergency power for health care facilities. He has indicated he would be happy to work with the NFPA-110 committee to ensure the NFPA-110 is appropriately changed to include fuel cells.
NFPA-99 has jurisdiction over healthcare:NFPA-99 was intended to have jurisdiction over healthcare facilities. Section 1.3.1 indicates that “This code shall apply to all health care facilities other than home care and veterinary care.” Section 1.2 states that “the purpose of this code is to provide minimum requirements for the installation, inspection, testing, maintenance, performance, and safe practices for facilities, material, equipment, and appliances, including other hazards associated with the primary hazards.”Furthermore, section 2.1 (2) notes “where the requirements of a referenced code or standard differ from the requirements of this code, the requirements of this code shall govern.” NFPA-110 is a referenced standard.
NFPA 99 explicitly recognizes use of fuel cells for emergency powerSection 6.4.1.1.7 permits fuel cell systems to serve as the alternate source for all or part of an essential electrical system under certain conditions. The National Electrical Code (NFPA-70) explicitly recognizes the use of fuel cells for emergency powerNFPA70 Already recognizes Fuel Cells as a source of power for emergency systems. Sections 700.12E speaks to this specifically: 700.12E“(E) Fuel Cell System. Fuel cell systems used as a source of power for emergency systems shall be of suitable rating and capacity to supply and maintain the total load for not less than 2 hours of full-demand operation.Installation of a fuel cell system shall meet the requirements of Parts II through VIII of Article 692.Where a single fuel cell system serves as the normal supply for the building or group of buildings concerned, it shall not serve as the sole source of power for the emergency standby system.”
As well, NFPA-70 section 701.12F speak specifically to fuel cell use for legally required standby systems:701.12F:“(F) Fuel Cell System. Fuel cell systems used as a source of power for legally required standby systems shall be of suitable rating and capacity to supply and maintain the total load for not less than 2 hours of full-demand operation.Installation of a fuel cell system shall meet the requirements of Parts II through VIII of Article 692.Where a single fuel cell system serves as the normal supply for the building or group of buildings concerned, it shall not serve as the sole source of power for the legally required standby system.”
Therefore, for coordination, changes should be made to NFPA-110:To ensure coordination of the NFPA documents, NFPA-110 should be changed to permit fuel cells as source of emergency power.The technical details of such a change can be deliberated to address concerns. However, NFPA-110 should recognize fuel cells as a source of emergency power, given that they are already explicitly permitted as a source of emergency power for healthcare facilities under the jurisdiction of NFPA-99 and are explicitly permitted more generally under NFPA-70.
Related Public Comments for This Document
Related Comment Relationship
Public Comment No. 4-NFPA 110-2017 [Section No. 5.4]
Related Item
Public Input#62
Public Input#61
Submitter Information Verification
Submitter Full Name: Walter Vernon
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 16 of 30
Organization: Mazzetti
Street Address:
City:
State:
Zip:
Submittal Date: Thu Apr 20 09:47:10 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 17 of 30
Public Comment No. 4-NFPA 110-2017 [ Section No. 5.4 ]
5.4* Energy Converters — Capacity.
The energy converters shall have the required capacity and response to pick up and carry the load withinthe time specified in Table 4.1(b) after loss of primary power.
5.4.1 Fuel cells shall be considered to meet the requirement of 5.4 where all of the followingconditions are met:
(1) Fuel cell installations consist of N+1 units operating in parallel, and continuouslysupplying power to the Emergency System.
(2) Fuel cell installations have a normal utility supply available in case of total systemfailure.
(3) Fuel cell installations include a connection for portable diesel generator to supply thelegally required life safety loads.
Statement of Problem and Substantiation for Public Comment
Summary: To address the coordination of NFPA-70, NFPA-99 and NFPA-110, NFPA-110 should be changed to permit fuel cells as source of emergency power provided specific conditions are met.
Originally Proposed Changes to the Code:The following proposed changes were submitted by Walt Vernon during the public comment period on NFPA-110 as one way to permit fuel cells as a source of emergency power in NFPA-110 (Public Input #62 and Public Input #61 respectively):1. Change 5.2.1 to read: “Energy converters shall consist only of rotating equipment as indicated in 5.2.4, or fuel cells as described in NFPA 852, Standard for Installation of Stationary Fuel Cell Power Systems.
2. Additions to section 5.4 as follows: 5.4.1 Because Fuel Cells cannot come up to rated load within a reasonable time,
5.4.1.1. Fuel cell installations must consist of N+1 units operating in parallel, and continuously supplying power to the Emergency System.
5.4.1.2 Fuel cell installations shall have a normal utility supply available in case of total system failure. And
5.4.1.3 Fuel cell installations shall include a connection for portable diesel generator to supply the legally required life safety loads.
These changes were submitted to ensure coordination with NFPA-99 and NFPA-70 both of which permit the use of fuel cells for emergency power.
Committees initial Response:The NFPA110 committee rejected these changes indicating that “currently fuel cells do not meet all of the performance requirements of NFPA 110.”
New CommentThe committee response in resolving PI 61 was that “fuel cells do not meet the requirements of Section 5.4.” The response to PI 62 was that “currently fuel cells do not meet all of the performance requirements of NFPA 110.” That is exactly what these proposals are trying to address and that resolution statement given by the committee on PI 61 and PI 62 do not address why the committee decided to reject this submittal.
We therefore suggest that the following be added to the text as section 5.4.1:5.4.1 Fuel cells shall be considered to meet the requirement of 5.4 where all of the following conditions are met: (1) Fuel cell installations consist of N+1 units operating in parallel, and continuously supplying power to the
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 18 of 30
Emergency System. (2) Fuel cell installations have a normal utility supply available in case of total system failure. (3) Fuel cell installations include a connection for portable diesel generator to supply the legally required life safety loads.Additionally, section 5.2.1 should be modified as originally suggested, namely: Energy converters shall consist only of rotating equipment as indicated in 5.2.4 or fuel cells as described in NFPA 853, Standard for Installation of Stationary Fuel Cell Power Systems.
Additional Background Information:It does not appear the committee addressed the fact that fuel cells are already permitted as emergency power sources in other NFPA documents. The committee should further consider the change to ensure proper coordination between all NFPA codes.
Walt Vernon chaired the electrical systems committee for NFPA-99 at the time fuel cells were introduced for inclusion as a source of emergency power for health care facilities. He has indicated he would be happy to work with the NFPA-110 committee to ensure the NFPA-110 is appropriately changed to include fuel cells.
NFPA-99 has jurisdiction over healthcare:NFPA-99 was intended to have jurisdiction over healthcare facilities. Section 1.3.1 indicates that “This code shall apply to all health care facilities other than home care and veterinary care.” Section 1.2 states that “the purpose of this code is to provide minimum requirements for the installation, inspection, testing, maintenance, performance, and safe practices for facilities, material, equipment, and appliances, including other hazards associated with the primary hazards.”Furthermore, section 2.1 (2) notes “where the requirements of a referenced code or standard differ from the requirements of this code, the requirements of this code shall govern.” NFPA-110 is a referenced standard.
NFPA 99 explicitly recognizes use of fuel cells for emergency power:Section 6.4.1.1.7 permits fuel cell systems to serve as the alternate source for all or part of an essential electrical system under certain conditions.
The National Electrical Code (NFPA-70) explicitly recognizes the use of fuel cells for emergency powerNFPA70 Already recognizes Fuel Cells as a source of power for emergency systems. Sections 700.12E speaks to this specifically:
700.12E:“(E) Fuel Cell System. Fuel cell systems used as a source of power for emergency systems shall be of suitable rating and capacity to supply and maintain the total load for not less than 2 hours of full-demand operation.Installation of a fuel cell system shall meet the requirements of Parts II through VIII of Article 692.Where a single fuel cell system serves as the normal supply for the building or group of buildings concerned, it shall not serve as the sole source of power for the emergency standby system.”
As well, NFPA-70 section 701.12F speak specifically to fuel cell use for legally required standby systems:701.12F:“(F) Fuel Cell System. Fuel cell systems used as a source of power for legally required standby systems shall be of suitable rating and capacity to supply and maintain the total load for not less than 2 hours of full-demand operation.Installation of a fuel cell system shall meet the requirements of Parts II through VIII of Article 692.Where a single fuel cell system serves as the normal supply for the building or group of buildings concerned, it shall not serve as the sole source of power for the legally required standby system.”
Therefore, for coordination, changes should be made to NFPA-110To ensure coordination of the NFPA documents, NFPA-110 should be changed to permit fuel cells as source of emergency power.The technical details of such a change can be deliberated to address concerns. However, NFPA-110 should recognize fuel cells as a source of emergency power, given that they are already explicitly permitted as a source of emergency power for healthcare facilities under the jurisdiction of NFPA-99 and are explicitly permitted more generally under NFPA-70.
Related Public Comments for This Document
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 19 of 30
Related Comment Relationship
Public Comment No. 3-NFPA 110-2017 [Section No. 5.2.1[Excluding any Sub-Sections]]
Both related to use of fuel cells foremergency power
Related Item
PI-61
Submitter Information Verification
Submitter Full Name: Walter Vernon
Organization: Mazzetti
Street Address:
City:
State:
Zip:
Submittal Date: Thu Apr 20 10:10:01 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 20 of 30
Public Comment No. 8-NFPA 110-2017 [ Section No. 5.6.4.7 ]
5.6.4.7
All chargers shall include the following characteristics, which are to be accomplished without manualintervention (i.e., manual switch or manual tap changing):
(1) At its rated voltage, the charger shall be capable of delivering energy into a fully discharged battery unitwithout damaging the battery.
(2) The charger shall be capable of returning the fully discharged battery to 100 percent of its ampere-hourrating within the time specified in Table 5.6.4.2, item (f).
(3) As specified in Table 5.6.4.2, item (e), meters with an accuracy within 5 percent of range shall befurnished.
(4) The generator set or charger The charger shall be permanently marked with the following:
(5) Allowable range of battery unit capacity that can be recharged within the time requirements ofTable 5.6.4.2
(6) Nominal output current and voltage
(7) Sufficient battery-type data to allow replacement batteries to be obtained
(8) The battery charger output and performance shall be compatible with the batteries furnished.
(9) Battery chargers used in Level 1 systems shall include temperature compensation for charge rate.
Statement of Problem and Substantiation for Public Comment
Article 5.6.4.7 is speaking to static automatic battery chargers (not prime mover driven chargers), as prefaced in 5.6.4.6. So, we should strike "generator set or" from (4), as it doesn't make sense.
Related Item
27-NFPA 110-2016
Submitter Information Verification
Submitter Full Name: Timothy Windey
Organization: Cummins Power Systems
Street Address:
City:
State:
Zip:
Submittal Date: Fri May 05 14:55:16 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 21 of 30
Public Comment No. 6-NFPA 110-2017 [ Section No. 5.6.5.1 ]
5.6.5.1
A control panel shall be provided and shall contain the following:
(1) Automatic remote start capability
(2) “Run-off-automatic” mechanical switch automatic” switch function
(3) Shutdowns as required by 5.6.5.2(3)
(4) Alarms as required by 5.6.5.2(4)
(5) Controls as required by 5.6.5.2(5)
Statement of Problem and Substantiation for Public Comment
The intent of the submitters PI was to make this more flexible, as many modern digital generator controls have HMI membrane panels that include the switch function. The intent was not to insert the word "mechanical" ahead of the word "switch". Don't think we should require a step backwards with technology.
Related Item
28-NFPA 110-2016
Submitter Information Verification
Submitter Full Name: Timothy Windey
Organization: Cummins Power Systems
Street Address:
City:
State:
Zip:
Submittal Date: Fri May 05 14:28:02 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 22 of 30
Public Comment No. 5-NFPA 110-2017 [ Section No. 5.6.5.5 ]
5.6.5.5
The cranking cycle shall be capable of being initiated by any of the following:
(1) Manual start initiation as specified in 5.6.5.2(2)(a).
(2) Loss of normal power at any automatic transfer switch (ATS) considered a part of the EPSS. Primemover shall start (or stop) after appropriate time delays, upon operation of a remote switch or set ofcontacts.
(3) Clock exerciser located in an ATS or in the control panel.
(4) Manually operated (test) switch located in each ATS that simulates a loss of power and causesautomatic starting and operation until this switch is reset, to cause the engine circuit to duplicate itsfunctions in the same manner commercial power is restored after a true commercial power failure.
Statement of Problem and Substantiation for Public Comment
I am the submitter of the original PI (49-NFPA 110-2016). The PI was passed in the first draft meeting, using my exact wording and substantiation. Unfortunately there was an error made with the wording of this article in the first draft report (and subsequent reports). Please restore wording per this PC (and my original PI 49).
Related Item
PI 49-NFPA-2016
Submitter Information Verification
Submitter Full Name: Timothy Windey
Organization: Cummins Power Systems
Street Address:
City:
State:
Zip:
Submittal Date: Fri May 05 13:46:16 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 23 of 30
Public Comment No. 2-NFPA 110-2017 [ Section No. 5.6.5.6 ]
5.6.5.6 *
All installations shall be provided with at least one remote tamperproof emergency stop switch locatedoutside the room housing the prime mover, where so installed, or elsewhere on the premises where theprime mover is located outside the building.
5.6.5.6.1
The remote manual stop station shall be labeled.
The remote stop should be an option not a mandatory component. I suggest the language in 5.6.5.6 bechanged from "All installations shall be provided with at least one remote tamperproof emergency stopswitch" to "All installation should be proided with at least one remote tamperproof emergenc stop switch"
I don't think it is imperitive in Level 1 applications to have this device installed. The specific operatingprocedure for each facility should dictate the need to incorporate the use of the remote switch. I have 30+years of oerational experience working for hospitals in the Engineering Department, I have yet to see aprocedure in place and staff training on the use of the remote stop switch. I have reached out to numerousmembers of the NFPA 110 committee for feedback on policies or procedures in place at other facilities, Ihave yet to receive any correspondance back with an active procedure that has been implemented. We takethe generation of emergency power very seriously here in NYC area, which is why we commit continuousmanpower for the observation and data collection of the emergency generator while in operation.
I would have difficult time putting together an operational procedure for staff to follow for the implementationof the remote stop switch. We all strive to provide our staff the proper training, tools, education andoperatonal strategy for all of our equipment and systems, yet all my peers I've spoken to have yet to addressthe operational strategy for the remote stop switch for Level 1 applcations.
I would be happy to expound further on the topic and entertain any thought processess to safely implementthe use of the switch that would never jeopardize LIFE SAFETY in our hospital.
Please feel free to contact me if you would like to have further dialogue on the topic.
Best Regards,
Kenny Brengel
516-592-3692
Statement of Problem and Substantiation for Public Comment
The undue burden on the hospital to implement a strategic policy and procedure for the operation and training of staff on how, when and why they would use the remote manual stop station for the emergency generator for Level 1 facility.
The remote stop should be an option not a mandatory component. I suggest the language in 5.6.5.6to be changed from "All installations SHALL be provided with at least one remote tamperproof emergency stop switch" to"All installations SHOULD be provided with at least one remote tamperproof emergency stop switch"
I don't think it is imperative in Level 1 applications to have this device installed. The specific operating procedure for each facility should dictate the need to incorporate the use of the remote switch. I have 30+ years of hospital operational experience in the Engineering Department. I have yet to see a policy, procedure and staff training in place on the use of the remote stop switch. I have reached out to numerous members of the NFPA 110 committee for feedback on current policies and procedures in place at other facilities. I have yet to receive any correspondence back with an active program that has been implemented. We take the generation of emergency power very seriously here in the NYC area, which is why we commit resources and continuos manpower for the observation and data collection of the emergency generator while in operation.
I would have a difficult time putting together an operational procedure for staff to follow for the implementation of
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 24 of 30
the remote stop switch. We all strive to provide staff the proper training, tools, education and systems, yet all my peers I've spoken to have yet to address the operational strategy for the remote stop switch for Level 1 applications.
I would be happy to expound further on my concerns on this topic and entertain any thought process to safely implement the use of the switch that would NEVER jeopardize LIFE SAFETY in any hospital.
Please feel free to contact me if you would like to have further dialogue on this topic.
Best regards,Kenny [email protected]
Related Item
5.6.5.6
Submitter Information Verification
Submitter Full Name: Ken Brengel
Organization: KJB Facility Consulting Inc.
Street Address:
City:
State:
Zip:
Submittal Date: Thu Mar 30 09:34:38 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 25 of 30
Public Comment No. 7-NFPA 110-2017 [ Section No. 5.6.9.9 ]
5.6.9.9
The generator instrument panel for Level 1 applications shall contain the following:
(1) An ac voltmeter(s) for each phase or a phase selector switch
(2) An ac ammeter(s) for each phase or a phase selector switch
(3) A frequency meter
(4) A voltage-adjusting feature to allow ± 5 percent voltage adjustment
(5) An ac kW meter indicating total load on or kVA meter to show total power for the generator set
Statement of Problem and Substantiation for Public Comment
Need some flexibility for this new requirement, as some more basic generator control HMI's have kVA meters.
Related Item
29-NFPA 110-2016
Submitter Information Verification
Submitter Full Name: Timothy Windey
Organization: Cummins Power Systems
Street Address:
City:
State:
Zip:
Submittal Date: Fri May 05 14:34:29 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 26 of 30
Public Comment No. 10-NFPA 110-2017 [ Section No. 7.9.13 ]
7.9.13
Automatically actuated valves shall not be permitted in the fuel oil supply or fuel oil return lines for Level 1emergency power supply systems when the fuel supply is directly connected to the prime mover .
7.9.13.1*
Automatically actuated valves shall be permitted in the fuel oil supply or fuel oil return lines between a dayfuel tank and the main fuel tank for Level 1 emergency power supply systems.
A.7.9.13.1
The fuel supply is also a fire risk to the building and the occupants of that building. The main fuel tankprovides fuel for extended use of the emergency power system or to multiple emergency generators. Ifthere is an issue with the fuel delivery system to the day fuel tank, a large quantity of fuel can be fed intothe generator room. This fuel will feed a growing fire in the generator room and can escape the roomcreating a liquid fire hazard in an occupancy not designed for that type of fire hazard.
Statement of Problem and Substantiation for Public Comment
The reliability and availability of the direct fuel supply to a Level 1 emergency power supply system is critical. A properly sized day fuel tank will ensure the emergency power is available when needed.
A properly designed fuel/fire detection system interlocked to an automatically actuated valve between the main fuel tank and day fuel tank will help keep any potential spill and/or fire in the emergency generator room and limit the exposure to the main occupancy of the building. With an alarm system, personnel at the facility could respond to any potential false alarm and restore the main fuel supply to the day fuel tank long before the day fuel tank is exhausted. The provision of an automatic shut-off valve in the fuel supply lines between the main fuel tank and day fuel tank will not negatively impact the availability or reliability of the fuel supply to the generator.
The concern of a fuel exposure to the main occupancy of a building is real. There are upsets in the generator room that can lead to fuel from the main tank being pumped into the generator room and also escape the room. To date FM Global has had a couple of incident reported that involved fuel escaping the generator room. In one case the fuel entered a hospital. These events have not resulted in a fire but a liquid fuel fire in any occupancy that is not specifically designed for that exposure can be devastating to the occupancy.
Related Item
PI 57
Submitter Information Verification
Submitter Full Name: John LeBlanc
Organization: FM Global
Street Address:
City:
State:
Zip:
Submittal Date: Tue May 09 15:05:17 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 27 of 30
Public Comment No. 9-NFPA 110-2017 [ Section No. 7.11.6 ]
7.11.6 *
For systems in seismic risk areas, the EPS, transfer switches, distribution panels, circuit breakers, andassociated controls shall be capable of performing their intended function during and after being subjectedto the anticipated seismic shock.
Statement of Problem and Substantiation for Public Comment
Rolling this back to the original wording after discussing with OSHPD. The California Electrical Code, 2016 (NFPA National Electrical Code, 2014) Section 517.31 requires that Life Safety and Critical Branch of Essential Electrical System (Alternative Power Source) be restored within 10 seconds after interruption of normal source, irrespective of the cause.
Related Item
46-NFPA 110 2016
Submitter Information Verification
Submitter Full Name: Timothy Windey
Organization: Cummins Power Systems
Street Address:
City:
State:
Zip:
Submittal Date: Fri May 05 15:18:28 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 28 of 30
Public Comment No. 13-NFPA 110-2017 [ Section No. 8.3.7 ]
8.3.7*
A fuel quality test shall be performed at least annually using appropriate ASTM standards.
Please see my additions and changes to the current 8.3.7* below as there is much confusion in theindustry due to the broadness of the testing recommendations and information. It would be my privilege toassist in the upcoming editions pertaining to this Chapter and Section.
8.3.7***
A fuel quality test shall be performed no less than annually using appropriate test methods approved underASTM D 975, Standard Specifications for Diesel Fuel Oils, to indicate fuel can be stored for a minimum of1 year without degradation. Not all approved testing under D 975 specifications shall be required, but aminimum testing of Bacteria/Fungi ASTM D6469, Water & Sediment ASTM D2709 and other foreignmaterials shall be performed as where there is a separation of water from the diesel fuel, microbialcontamination can occur. For fuels being stored for periods longer than 12 months, the diesel fuel shallalso be tested for ignition quality and performance by testing for a minimum of Cetane Index ASTMD4737 approved under ASTM D 975 standards.
Additional tests chosen should be recommended on several factors including but not limited to thefollowing:
1) Geographical location and climate in which diesel fuel is being stored. Climates where thetemperature does not get below freezing should not require the testing of the diesel fuels cold weatherproperties such as cloud point, pour point, and cold filter plug point.
2) The environment in which the fuel stored. See points referenced in Annex A 7.9.1.2 which suggestthat fuel degradation accelerates in tanks subjected to temperature variations as it can lead to thepresence of water and where there is a separation of diesel fuel and water microorganisms and fungi cangrow and contaminate the fuel supply which can lead to general or pitting corrosion of steel tanks andcomponents, possibly resulting in filter plugging, operational issues or a hydrocarbon release to theenvironment.
3) The material of the tank in which the fuel stored. See points referenced in Annex A 7.9.3.1 that states"Copper can promote fuel degradation and can produce mercaptide gels. Zinc coatings can react withwater or organic acids in the fuel to form gels that rapidly plug filters.” Tanks with copper and zinc materialcould recommend having Copper Corrosion testing performed by methods approved under ASTM D 975specifications.
4) ASTM D 975 specification allows biodiesel concentrations up to 5% (B5) in diesel fuel with noseparate labeling required at the pump. It is recommended to test for % Biodiesel Concentration ASTMD7371 in a fuel supply being stored for a minimum of 6 months as biodiesel blends are comprised oforganic substances which accelerate the degradation of fuel if not properly treated. Acceleration is greaterwith any presence of microbiological growth and could possibly lead to sludge like substances within thefuel supply leading to clogged filters and operational issues.
5) All diesel fuel tanks filled after 2014, when the ULSD diesel fuel was made required for all NRLMengines and equipment, it is recommended to test for the Sulfur Content ASTM D2622 to ensure allstored fuels meet the current USLD requirement which reduced Sulfur Content to 15ppm.
Additional documentation suggested to be added from the NFPA 25 - Standard for the Inspection, Testing,and Maintenance of Water-Based Fire Protection Systems—2017 Edition is as follows:
1) If diesel fuel is found to be deficient in the testing required in 8.3.7, the fuel shall be reconditioned orreplaced, the supply tank shall be cleaned internally, and the engine fuel filter(s) shall be changed.
2) After the restoration of the fuel and tank, the fuel shall be retested every 6 months until experienceindicates the fuel can be stored for a minimum of 1 year without degradation beyond that allowed in abovechapters.
Statement of Problem and Substantiation for Public Comment
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017
Page 29 of 30
As a provider of diesel fuel testing predominately within the power generation industry, I believe the clarification and guidelines within the fuel quality testing requirements would eliminate much confusion and inconsistency nationwide, particularly when it comes to critical and emergency power operations. As a member of several associations and hundreds of customers, I have experienced that lack of guidance and education is largest and most consistent challenge in the field not only at the service level but especially at the end user level. In addition, it would certainly assist other regulatory firms that reference the NFPA110 regulations in understanding what to look for when enforcing the requirements within their jurisdiction.
Related Item
Professional within Diesel Fuel Testing Laboratory
Member of the EGSA (Electrical Generator Systems Association
Member of the EGSA Dealer / Distributor Committee
Provider of Diesel Fuel Testing for Service Companies / Dealers / Distributors / End Users who arerequired to follow NFPA110 Guidelines
Submitter Information Verification
Submitter FullName:
Michelle Hilger
Organization:Titan Laboratories, Member of E.G.S.A (Electrical Generator SystemsAssociation), Member of the Dealer / Distributor Committee within theE.G.S.A
Street Address:
City:
State:
Zip:
Submittal Date: Wed May 10 08:31:27 EDT 2017
National Fire Protection Association Report http://submittals.nfpa.org/TerraViewWeb/ContentFetcher?commentPara...
NFPA 110 & 111 Second Draft Technical Committee Meeting Agenda Teleconference - July 19, 2017