18
4/22/2016 1 Connecting the Last Mile through Underground Pipelines Experience of Sardar Sarovar Project, Gujarat K. A. Patel and Dr. M. B. Joshi Sardar Sarovar Project, Gujarat, IP 1.8 Million Hectare

Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

  • Upload
    donga

  • View
    234

  • Download
    7

Embed Size (px)

Citation preview

Page 1: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

1

Connecting the Last Mile through Underground Pipelines

Experience of Sardar Sarovar Project, Gujarat

K. A. Patel and Dr. M. B. Joshi

Sardar Sarovar Project, Gujarat, IP 1.8 Million Hectare

Page 2: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

2

• Irrigation – 19.05 Lakh Ha (18 Lakh Ha. In Gujarat)

• Increase in Agricultural Production

- 87 Lakh Tonnes per annum

• Hydro Power – 100 crore units per year

(installed capacity 1450 MW)

• Drinking water - 9490 villages (out of 18225 total)and 173 towns (out of 195 total)

• Flood Protection to 30,000 Ha

• 10 lakh jobs - mostly in rural areas

3

So far…..86,800 MCM of water conveyed

37,655 MU of ecofriendly hydro power generation

Sardar Sarovar Project, Gujarat, The Planned Benefits

Conventional System of Open Gravity Channels

Page 3: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

3

Physical Progress

Type of canal Total Length in Km

Completed Length in Km

Main Canal 458 458

Branch Canal 2731 2515

Distributaries 4569 3920

Minors 15670 11487

Sub-minors 48320 17404

Total 71748 35784

Major Challenge for Speedy completion of Sub-Minors

• Sub-Minors of 38,000 km / 13.7 lac ha to be executed

• 19,000 ha land to be acquired for Sub-Minors –without any compensation as per extant Policy

• 3 lac farmers will be affected against 86,000 farmers upto Minors – fragmentation of farmland

• Availability of borrow areas / contractors / laborers for canal construction ?

• Implementation period of about 6 - 7 years

• Poor response for participation by beneficiaries

Pre-Policy Scenario 2012

Page 4: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

4

BENEFITS LIMITATIONS

• Cost effective for large Discharges

• No Energy cost

• Permanent loss of land

• More time for construction

• Large nos. of Drainage Structures and Bridges

• Low Water Use Efficiency

• Vulnerable to damages / flooding

• Liable to Water-Logging and Soil Deterioration

• Reluctance of farmers due to limited land holding and fragmentation

6

Conventional System of Open Gravity Channels

Under Ground Pipe Line (UGPL)

Page 5: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

5

BENEFITS LIMITATIONS

• Land saving and water saving(up to 10-20 %)

• Less implementation period• Feasible even in flood zone /

Undulating area• Land fragmentation can be

avoided• Field Channels could be

integrated with the Sub-Minors• O & M expenditure will be less• Future integration with

PINS/MIS possible

• Requires energy forlifting operation in somepatches (~60 %)

• Suitable for fallingtopography

6

Under Ground Pipe Line (UGPL)

Page 6: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

6

HYDRAULIC GRADE LINE

TURNOUT

AVAILABLE WATER LEVEL

G.L.G.L.

F.S.L.

PARENT CANAL

PUMP

SCHEMATIC DIAGRAM SHOWING UGPL WITH GRAVITY AND PUMPING

WATER LEVEL IS ABOVE THE G.L.

(GRAVITY FLOW)

WATER LEVEL IS BELOW THE G.L.

(MULTIPLE PUMPING)

Page 7: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

7

Pros and Cons of the Solutions

Particulars Single

Point

Lifting

Linear

Multiple

Points Lifting

Lifting at the

Centre of Chak

and Radial

Pipes

Reduced cost due to common

infrastructure

Yes No Yes

Pump Installation and Operation

& Maintenance by

SSNNL or

WUA

WUA SSNNL or WUA

Uniformity in water distribution Yes No Yes

Effective control during operation Yes No Yes

Reduction in length of Field

Channels

No No Yes

Integration with Micro Irrigation

System (MIS)

No Yes Yes

Report of the Expert Group for Strategy for the Accelerated Development of Sardar Sarovar Project Command Area, May 2010Chairman : Shri B. N. Navalawala, Adviser (WR) to Hon’ble Chief Minister 14

Main Recommendations made by Expert Group (2010)

– Conventional open channel should be adopted forSub-Minors except for the topographical constraints(UGPL).

– SSNNL should acquire land for Sub-Minors by payingcompensation.

– SSNNL should adopt the Micro Irrigation System [MIS]at the Subchak level.

– PPP model should be adopted for MIS

Page 8: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

8

Conclusion of a

Study carried out

by IWMI (2010)… there are at least ten

strong reasons why

Gujarat should seriously

consider the ‘IWMI

Proposal’ for pipelining

the water distribution

system below the

minors in the

SSP command area.

16

Consensus in the Meeting of Expert Group on PIM

– Both the Options i.e. Conventional open channel andUGPL to be decided at VSA level or preferably at Chaklevel

– Licensing / franchise Model to be evolved under PPP

– WUAs may choose the energy option i.e. electricity ordiesel or combination thereof

– Integration of UGPL with MIS desirable

– Appropriate financial incentives efficient water use(MIS)

– Services of NGOs and model WUAs as Motivators

– Capacity building through specially designed Modulesfor different levels

Page 9: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

9

Open Channel Sub-Minors – Vulnerable to Damage

18

UGPL Policy 2014

• No restriction of technical options selected

• The group of farmers have to decide the alignment of

sub minor which is underground and therefore there is

no question of land acquisition. However, if open

channel is selected by farmers, farmers will be

expected to contribute their land.

• SSNNL will pay 97.5% of the total cost

• The group of farmers is expected to pay 2.5% of the

cost as a labour component to the cost of scheme.

The purpose is to inculcate a sense of ownership in

farmers.

• O&M of sub minor will be responsibility of beneficiary

farmers of chak.

Page 10: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

10

19

UGPL Policy - Highlights

Alignment of UGPL and locations of Turn-outs

to be decided in consultation with Farmers

Tri-partite Agreement (Beneficiary Farmers,

Implementing Agency & SSNNL) for each Chak

Time-limit for UGPL Work – 3 Months

5 years’ Defect Liability to ensure Quality

20

Tender Procedure

38 agencies working in GGRC & SSNNL and

29 through expression of interest in August

2014

Invited for unit rates for UGPL work

38 agencies filled up unit rates

Rates were moderated and approved by the

SSNNL by Price discovery accordingly.

Page 11: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

11

21

Under Ground Pipe Line (UGPL) - Implementation

• 5 lakh Hectare area in 54 Talukas taken up.

Approximate cost of Rs.2000 crore.

• Inauguration of UGPL Sub Minor works done by

Hon'ble CM & Hon'ble Ministers simultaneously at

17 places of State on 28/01/2015

• Beneficiary farmers to contribute 2.5% of cost

which can be in form of labour.

• Factory Testing and On-site Testing of Pipes

• TPI Agencies for Testing & Trial Runs

Consultation with Beneficiary Farmers after finalizing Chak

and Sub-chak (>2,75,000 so far)

Fixing the UGPL Alignment and locations of Turnouts

Preparation of Drawings

Preparation of Estimates

Technical Sanction to the Estimates

Under Ground Pipe Line (UGPL) - Implementation

Page 12: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

12

Under Ground Pipe Line (UGPL) - Implementation

Collecting 2.5% contribution from the Beneficiary Farmers

Issuance of Letter of Intent (LOI)

Issuance of Work Order

Tri-partite Agreement (Farmers, Agency & SSNNL)

Payment of 5% Security Deposit by the Agency

Under Ground Pipe Line (UGPL) – Planning Criteria

a) To plan Chaks (40-60 ha) / Sub-Chaks (5-8 ha)suitable to Rotational Water Distribution Schedule(RWS).

b) Alignment of UGPL Sub minor is selected, crossingthe contour to avail sufficient head to overcomefrictional losses in pipe flow.

c) Turnout outlet is kept on highest point of sub chakcommand as to serve the command area effectively.

d) As far as possible Length of Sub minor is kept minimum without compromising the efficiency of UGPL network system.

Page 13: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

13

REFERENCES

Minor

Sub Minor------

-Sump /Kundi

SR. NO

NAME OF SM

CH. IN MDIA OF

PIPE

1 SM-1 0 to 389 250 mm

2 BSM 0 to 331 250 mm

SR. NO

Sub ChakNo

Area In Ha

No of Beneficiary

1 SC-1 6.262 8

2 SC-2 6.121 8

3 SC-3 9.347 8

4 SC-4 5.045 8

5 SC-5 2.636 5

Total Ha 29.41 37

Chak map of Fatepura Minor

Under Ground Pipe Line (UGPL) – Design Procedure

INPUT DATA

a) Sub chak name and its chainage.

b) CCA of chak.

c) Available FSL of Parent Canal.

d) Ground Level at Turnout of Sub chak command.

OUTPUT

a. Design Discharge of the Sub minor.

b. Head loss due to friction in pipe line (Using Modified

Hazen-William formula).

c. Available FSL and Required FSL at Turnout point.

d. Flow Condition of sub minor i.e. Gravity Flow or Lift

flow.

e. Height of Well

Page 14: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

14

Under Ground Pipe Line (UGPL) – Design Procedure

Diameter of pipe line was selected considering the

following points

a) Velocity was kept between 0.5-1.5 m/s.

b) Height of well not to exceed 5.00 mt.

c) To ensure priority for Gravity flow condition with

minimum diameter

d) In Lift condition minimum diameter is ensured within

the allowed height of well (about 5.00 mt) and

maximum velocity.

e) L-Section of Sub-Minor is generated at 30 m intervals.

LONGITUDINAL SECTION

L-SECTION OF CHICHODRA MINOR-I OF VARSADA DISTY/

Ch - 1478mA.V

BENDREDUCER

04 CHM-I

Ch - 1231mREDUCER03 CHM-I

Ch - 1138mA.VREDUCER02 CHM-I

Ch - 970mBOLW-OFF ASSEMBLY

Ch - 900mBEND

Ch - 394mA.V

BEND

REDUCER

01 CHM-I

Ch - 0mR.C.C WELL

DIA OF PIPE - 0.450 mDIA OF PIPE - 0.500 m

DIA OF PIPE - 0.600 m

DIA OF PIPE - 0.700 m

1.88

641

.254

43.7

3542

.790

1500

-41

.518

43.7

7742

.580

1478

1.51

241

.518

43.8

7742

.580

1478

1.83

041

.510

43.9

9342

.890

1470

1.71

041

.480

44.0

3742

.740

1440

1.60

041

.450

44.0

8142

.600

1410

1.49

041

.420

44.1

2542

.460

1380

1.56

041

.390

44.1

6942

.500

1350

1.63

041

.360

44.2

1342

.540

1320

1.77

041

.330

44.2

5742

.650

1290

1.94

041

.300

44.3

0142

.790

1260

-41

.271

44.3

4343

.350

1231

2.57

941

.271

44.4

4343

.350

1231

2.31

041

.270

44.4

6943

.080

1230

2.62

041

.240

44.5

0043

.360

1200

3.03

041

.210

44.5

3143

.740

1170

3.34

041

.180

44.5

6244

.020

1140

-41

.178

44.5

6444

.400

1138

3.82

241

.178

44.6

6444

.400

1138

2.67

041

.150

45.0

0943

.220

1110

2.06

041

.120

45.0

2642

.580

1080

1.63

041

.090

45.0

4342

.120

1050

1.60

041

.060

45.0

6042

.060

1020

1.62

041

.030

45.0

7742

.050

990

1.72

041

.000

45.0

9442

.120

960

1.73

040

.970

45.1

1142

.100

930

1.58

040

.940

45.1

2841

.920

900

1.56

841

.132

45.1

4542

.100

870

1.62

641

.324

45.1

6242

.350

840

1.75

441

.516

45.1

7942

.670

810

1.89

241

.708

45.1

9643

.000

780

2.01

141

.899

45.2

1343

.310

750

2.22

942

.091

45.2

3043

.720

720

2.31

742

.283

45.2

4744

.000

690

2.33

542

.475

45.2

6444

.210

660

2.30

342

.667

45.2

8144

.370

630

2.22

142

.859

45.2

9844

.480

600

2.11

043

.050

45.3

1544

.560

570

1.99

843

.242

45.3

3244

.640

540

1.62

643

.434

45.3

4944

.460

510

1.61

443

.626

45.3

6644

.640

480

1.53

243

.818

45.3

8344

.750

450

1.43

044

.010

45.4

0044

.840

420

-44

.176

45.4

1545

.320

394

1.84

444

.176

45.5

1545

.320

394

1.44

044

.180

45.6

1544

.920

390

1.51

044

.210

45.6

3045

.020

360

1.81

044

.240

45.6

4545

.350

330

1.86

044

.270

45.6

6045

.430

300

2.02

044

.300

45.6

7545

.620

270

2.05

044

.330

45.6

9045

.680

240

2.15

044

.360

45.7

0545

.810

210

2.26

044

.390

45.7

2045

.950

180

2.37

044

.420

45.7

3546

.090

150

2.50

044

.450

45.7

5046

.250

120

2.34

044

.480

45.7

6546

.120

90

2.12

044

.510

45.7

8045

.930

60

1.91

044

.540

45.7

9545

.750

30

1.70

044

.570

45.8

1045

.570

0

48

47

46

45

44

43

42

41

40

39

38

37

36

35

GL - GROUND LEVEL

UGPL

FSL LEVEL

(m)

(m)

(m)

(m)

(m)

DEPTH OF CUTTING

GROUND LEVEL

DISTANCE

FSL LEVEL

TOP OF RL OF PIPLINE

DATUM

0.000

362.114

0.25

45.81

46.06

2250M (TR)

CCA (ha)

GCA (ha)

W/Head (m)

FSL in O/T Canal(m)

FSL in Parent Canal(m)

O/Take Chainage(m)

L-SECTION OF CHICHODRA MINOR-I OF VARSADA DISTY OF KACHCHH BRANCH CANAL

Page 15: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

15

Baffle wall for heading upLocation : R&R Site

Pilot project of Under Ground Pipe Line (UGPL)MAHISA PILOT PROJECTMAHISA PILOT PROJECT

6

Under Ground Pipe Line (UGPL) – Pilot Project

Page 16: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

16

MAHISA PILOT PROJECTMAHISA PILOT PROJECT

7

Under Ground Pipe Line (UGPL) - Implementation

UGPL Turnout functioning

Page 17: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

17

33

Major Issues in Implementation of UGPL Sub-Minors

• Farmers were not willing to pay 10%, their

contribution was later on reduced to 2.5%

• Farmers continuously growing crops and hence not

willing to allow laying of UGPL – provision of crop

compensation

• Pipe suppliers unable / not willing to supply in

sufficient quantity at reasonable rates – persuading

them to maintain regular supply

34

Sr. no.Nos. of Taluka

Preparation of plan and Estimate after

consulting farmers at the unit rates of

implementing agency

Technical approval of estimate of chaks

Tri party agreement/work order

Ongoing works

Nos of chak Hectare Nos of chak Hectare Nos of chak HectareNos of chak

Hectare

Total 61 11580 551253 11312 532434 8977 422204 8202 344514

Detail of Pipes for ongoing works

Completion of work

Supplied at site Laid (Fix)

in Nos.of Chaks

Length (m)

in Nos.of Chaks

Hectare Nos of chak Hectare

7164 8884117 6472 306148* 5441 257701

Progress of UGPL (Sub-minor) as3.2016Progress of Sub-Minors (UGPL) as on 2.4.2016

* A record in

the history of

Irrigation

Infrastructure

Development

in India

Page 18: Experience of Sardar Sarovar Project, Gujarat - … of Sardar Sarovar Project, Gujarat ... Development of Sardar Sarovar Project Command Area, May 2010 Chairman : ... SSP command area

4/22/2016

18

More Crop Per Drop – Explaining the farmers about value of water

36

THANKS