Upload
hoangkhanh
View
282
Download
10
Embed Size (px)
Citation preview
17th March -2017
Sardar Sarovar Narmada Nigam Limited
K B Parmar Chief Engineer (Design)
Sardar Sarovar Project, GujaratCCA 17.92 Lakh Hectare
17 Districts
3112 Villages
13 Agro-climatic Regions
75% Draught Prone area is covered under Narmada command
Out of allocated water share of 9.0 MAF, 7.94 MAF for Irrigation(88.23%), 0.86 MAF (9.55%) for Domestic and 0.2 MAF (2.22%)for Industrial use.
The Project is Supplying Drinking water to 9490 villages and 173urban centers.
Water Scarcity Affected Area Project Beneficiary Area
Sardar Sarovar Narmada Nigam Limited, Government of Gujarat
Physical Progress
Type of canal Total Length in Km
Completed Length in Km
Main Canal 458 458
Branch Canal 2731 2541
Distributaries 4569 4103
Minors 15670 12250
Sub-minors 48320 25743
Total 71748 45095
Sardar Sarovar Narmada Nigam Limited, Government of Gujarat 17th March-2017
Narmada Canal Network
5
100%
93%88%
76%
53%
Irrigation Potential Developed
13.97 lac Ha.
Qd 0.5-1 Cusec
Sardar Sarovar Narmada Nigam Limited, Government of Gujarat
Open Channel Sub-Minors – Vulnerable to Damage
Failure due to..
Micro level Land fragmentation
Drainage issues
Obstruction in Transportation path
…..
Connecting the Last Mile through Underground Pipelines
Milestone achievement in the history of irrigation.
Total 6.17 lakh hectare area in 1 ½ Years is covered
under UGPL Subminor by June 2016.
Against,total 20.80 Lakh Hectare area have been
covered by Subminor/field channel etc. in 11th Five
Years Plan. (website of MoWR,RD & GR)
ISSUE FACED AND POLICY DECESION TAKEN TO
ACHIEVE THE MILESTONE
Report of the Expert Group for Strategy for the Accelerated Development of Sardar Sarovar Project Command Area, May 2010Chairman : Shri B. N. Navalawala, Adviser (WR) to Hon’ble ChiefMinister
Main Recommendations made by Expert Group (2010)
– Conventional open channel should be adopted for Sub-Minors except for the topographical constraints (UGPL).
– SSNNL should acquire land for Sub-Minors by payingcompensation.
– SSNNL should adopt the Micro Irrigation System [MIS] atthe Subchak level.
– PPP model should be adopted for MIS
– Pilot Project in area like Rajasthan can be done for study
Major Challenge for Speedy completion of Sub-Minors
• Sub-Minors of 38,000 km / 13.7 lac ha to be executed• 19,000 ha land to be acquired for Sub-Minors –
without any compensation as per extant Policy
• 3 lac farmers will be affected against 86,000beneficiary farmers by fragmentation of farmlandupto Minors
• Availability of borrow areas / contractors / laborersfor canal construction ?
• Implementation period of about 6 - 7 years
• Poor response for participation by beneficiaries
Pre-Policy Scenario 2012
Flood Prone Delta Region of Sabarmati River–UGPL Distributaries/Minors/Sub-Minors of Dholka Branch Canal for about 30,000 Ha area is partially completed.
Draught Prone Region Near Tharad for about 5000 Ha Area is completed.
Results of Pilot Projects is found satisfactory
UGPL Pilot Projects
BENEFITS LIMITATIONS
• Land saving and water saving(up to 10-20 %)
• Less implementation period• Feasible even in flood zone /
Undulating area• Land fragmentation can be
avoided• Field Channels could be
integrated with the Sub-Minors• Future integration with
PINS/MIS possible
• Requires energy forlifting operation in somepatches (~60 %)
• More suitable for fallingtopography
6
Under Ground Pipe Line (UGPL)
UGPL Policy 2014
• No restriction of technical options
• The group of farmers have to decide the alignment of
underground sub minor and therefore there is no
question of land acquisition. However, if open channel
is selected by farmers, farmers will be expected to
contribute their land.
• SSNNL will pay 97.5% of the total cost
• The group of farmers is expected to pay 2.5% of the
cost as a labour component to the cost of scheme.
The purpose is to inculcate a sense of ownership in
farmers.
• O&M of sub minor will be responsibility of beneficiary
farmers of chak.
UGPL Policy - Highlights
Alignment of UGPL and locations of Turn-outs
to be decided in consultation with Farmers
Tri-partite Agreement (Beneficiary Farmers,
Implementing Agency & SSNNL) for each Chak
Time-limit for UGPL Work – 3 Months
5 years’ Defect Liability to ensure Quality
Survey, Network Planning, Designs & Estimate
of UGPL are being carried out by WAPCOS Ltd.
Tender Procedure
38 agencies working in GGRC & SSNNL and
29 through Expression Of Interest was selected
in August 2014
Tenders Invited for unit rates for UGPL work
Rates were moderated and approved by the
SSNNL by Price discovery accordingly.
Progressively ,35 No. of Pipe Manufacturers
and 234 No. of Agencies were involved in
execution
Under Ground Pipe Line (UGPL) - Implementation
• 5 lakh Hectare area in 54 Talukas taken up.
Approximate cost of Rs.2000 crore.
• Inauguration of UGPL Sub Minor works done by
Hon'ble CM & Hon'ble Ministers simultaneously at
17 places of State on 28/01/2015
• Beneficiary farmers to contribute 2.5% of cost
which can be in form of labour.
• Factory Testing and On-site Testing of Pipes
• TPI Agencies for Testing & Trial Runs
Consultation with Beneficiary Farmers after finalizing Chak
and Sub-chak (>2,80,000 so far)
Fixing the UGPL Alignment and locations of Turnouts
Preparation of Drawings
Preparation of Estimates
Technical Sanction to the Estimates
Under Ground Pipe Line (UGPL) - Implementation
Under Ground Pipe Line (UGPL) - Implementation
Collecting 2.5% contribution from the Beneficiary Farmers
Issuance of Letter of Intent (LOI)
Issuance of Work Order
Tri-partite Agreement (Farmers, Agency & SSNNL)
Payment of 5% Security Deposit by the Agency
Major Issues in Implementation of UGPL Sub-Minors
• Farmers were not willing to pay 10%, their
contribution was later on reduced to 2.5%
• Farmers continuously growing crops and hence not
willing to allow laying of UGPL – provision of crop
compensation
• Pipe suppliers unable / not willing to supply in
sufficient quantity at reasonable rates – persuading
them to maintain regular supply
Sr. no.Nos. of Taluka
Preparation of plan and Estimate after
consulting farmers at the unit rates of
implementing agency
Technical approval of estimate of chaks
Tri party agreement/work order
Ongoing works
Nos of chak Hectare Nos of chak Hectare Nos of chak HectareNos of chak
Hectare
Total 67 12604 617000 12604 617000 12604 617000 12604 617000
Detail of Pipes for ongoing works
Completion of work
Supplied at site Laid (Fix)
in Nos.of Chaks
Length (m)
in Nos.of Chaks
Hectare Nos of chak Hectare
12604 15507762 12604 617000* 12604 617000
Progress of UGPL (Sub-minor) as3.2016Progress of Sub-Minors (UGPL) as on 1st Mar, 2017
* A record in
the history of
Command Area
Development in
India in a year.
(2015-16).
Planning of Sub-Minors (UGPL)
Recently total 145 agencies have been given work
order of UGPL Subminor works for another 4 Lac
hectare area (6680 chaks)
at uniform rates, moderated after Tendering process.
For checking the quality of pipes in factory, at site ,
etc. following agencies have been appointed
1.CIPET
2.GIRDA
3.Other Six TPI agencies
As per the Guideline of CADWM for Concurrent
Evaluation Report by an independent agency, the
LASA is being appointed
Quality & Control of Piped Irrigation Network
%age CCA under Gravity Flow : 52.84
%age CCA under Partial Lift Flow : 25.58
%age CCA under Lift flow : 21.58
Average cost per Hectare : Rs.41016
(Approx.)
Energy requirement for lifting of water for SSP
For Single Point Lifting : 38.5 KW
For Multipoint Lifting System : 21.0 KW
Under Ground Pipe Line(UGPL)
LIFTING IS PROPOSED
L-SECTION OF CASE-I (GRAVITY FLOW)
PIPE LINEG.L. G.L.
L-SECTION OF CASE-II(PARTIAL LIFT)
PIPE LINE
G.L.G.L. G.L.PUMP PUMP
PUMP
LAYOUT OF CASE-II(PARTIAL LIFT)
FLOW POINT
LOCAL LIFTING
POINT
L-SECTION OF CASE-III(COMPLETE LIFT)
PIPE LINE
PUMP
PUMPPUMP
PUMPPUMP
LAYOUT OF CASE-III(COMPLETE LIFT)
(ALTERNATE OPTION FOR LIFTING AS PUMPING AT OFFTAKE-SINGLE POINT LIFTING)
L-SECTION OF CASE-II (PARTIAL LIFT CONDITION AFTER SINGLE POINT LIFTING)
PIPE LINE
G.L.
G.L.
PUMP
Pumping point
LAYOUT OF CASE-II(PARTIAL LIFT CONDITION AFTER SINGLE POINT LIFTING )
FLOW POINT
FLOW POINT
L-SECTION OF CASE-III (COMPLETE LIFT CONDITION AFTER SINGLE POINT LIFTING)
PIPE LINE
G.L.
PUMP
Pumping point
LAYOUT OF CASE-III(COMPLETE LIFT CONDITION AFTER SINGLE POINT LIFTING )
FLOW POINT
FLOW POINT
SAMPLE COMPARISON STUDY FOR LIFTING AT OFFTAKE POINT IN TWO CASES
Sr .No. FEATURE
PARTIAL LIFT CONDITION COMPLETE LIFT CONDITION
MULTI PUMPING AT TURNOUT WELL
PUMPING AT OFF-TAKE (0 Ch)
MULTI PUMPING AT TURNOUT
WELLS
PUMPING AT OFF-TAKE (0 Ch)
1 Name of Sub Minor 15 NVM OF NAVDA MINOR 03 CHM OF CHALA MINOR
2 Dia of Pipe line (mm) 280 225 280 250
3 Velocity (m/s) 0.44 0.68 0.46 0.58
4 Provision of Diesel Pump set At each turnout pointOnly At off-Take
PointAt each turnout
pointOnly At off-Take
Point
5 Type of structureRCC / Brick Masonry
Well & TurnoutTurnout except
offtake wellsRCC / Brick
Masonry WellTurnout except
offtake wells
6 Type of structure At OfftakeRCC / Brick Masonry
Well
RCC / Brick Masonry Well & Raised Delivery
well
RCC / Brick Masonry Well
RCC / Brick Masonry Well & Raised Delivery
well
7 CCA of Chak (Ha) 56.64 56.64 44.11 44.11
8 Total Cost (Rs In lac.) 18.22 12.40 31.05 23.08
9 Cost/Hectare (Rs) 32164 21884 70380 52382
10 Total Savings (Lacs) 5.82 7.97
11 Savings (Rs/Ha.) 10280 17998
12 Further Reduction in Dia. (Cost Saving Approx 1.50 Lac) ( Cost saving Approx 2.50 Lac)
CONCLUSION (Pumping at off-take point)
• Higher velocity is obtained.
• Lower diameter of pipe is needed.
• Depth of Cutting (Excavation) and pipe length is reduced.
• Chances of Silting in underground pipe is Less.
• Only one pump set is required instead of multi pump sets.
• Saving in cultivable land at every turnout point.
• Construction of well at turnout points is avoided.
• Less maintains in long run of project.
• Cost of construction of sub-minor can be reduced in between Rs 10000 to 17000 per hectare.
Pros and Cons of the Solutions
Particulars Single Point
Lifting
Linear Multiple
Points Lifting
Reduced cost due to common
infrastructure of pump
Yes No
Pump Installation and Operation &
Maintenance by
SSNNL or
WUA
WUA
Uniformity in water distribution Yes No
Effective control during operation Yes No
Compulsion of Participatory Operation Yes No
Delivery of Water Upto Sub-Chak
Without Pumping
No Yes
Har Khet Ko Pani – Explaining the farmers about value of water
THANKS
Under Ground Pipe Line (UGPL) – Planning Criteria
a) To plan Chaks (40-60 ha) / Sub-Chaks (5-8 ha)suitable to Rotational Water Distribution Schedule(RWS).
b) Alignment of UGPL Sub minor is selected, crossingthe contour to avail sufficient head to overcomefrictional losses in pipe flow.
c) Turnout outlet is kept on highest point of sub chakcommand as to serve the command areaeffectively.
d) As far as possible Length of Sub minor is keptminimum without compromising the efficiency ofUGPL network system.
REFERENCES
Minor
Sub Minor -------
Sump /Kundi
SR. NO
NAME OF SM
CH. IN MDIA OF
PIPE
1 SM-1 0 to 389 250 mm
2 BSM 0 to 331 250 mm
SR. NO
Sub ChakNo
Area In Ha
No of Beneficiary
1 SC-1 6.262 8
2 SC-2 6.121 8
3 SC-3 9.347 8
4 SC-4 5.045 8
5 SC-5 2.636 5
Total Ha 29.41 37
Chak map of Fatepura Minor
Under Ground Pipe Line (UGPL) – Design Procedure
INPUT DATA
a) Sub chak name and its chainage.
b) CCA of chak.
c) Available FSL of Parent Canal.
d) Ground Level at Turnout of Sub chak command.
OUTPUT
a. Design Discharge of the Sub minor.
b. Head loss due to friction in pipe line (Using Modified
Hazen-William formula).
c. Available FSL and Required FSL at Turnout point.
d. Flow Condition of sub minor i.e. Gravity Flow or Lift
flow.
e. Height of Well
Under Ground Pipe Line (UGPL) – Design Procedure
Diameter of pipe line was selected considering the
following points:
a) Velocity was kept between 0.5-1.5 m/s.
b) Height of well not to exceed 5.00 mt
c) To ensure priority for Gravity flow condition with
minimum diameter
d) In Lift condition minimum diameter is ensured within
the allowed height of well (about 5.00 mt) and
maximum velocity.
e) L-Section of Sub-Minor is generated at 30 m intervals.
LONGITUDINAL SECTION
L-SECTION OF CHICHODRA MINOR-I OF VARSADA DISTY/
Ch - 1478mA.V
BENDREDUCER
04 CHM-I
Ch - 1231mREDUCER03 CHM-I
Ch - 1138mA.V
REDUCER02 CHM-I
Ch - 970mBOLW-OFF ASSEMBLY
Ch - 900mBEND
Ch - 394mA.V
BEND
REDUCER
01 CHM-I
Ch - 0mR.C.C WELL
DIA OF PIPE - 0.450 mDIA OF PIPE - 0.500 m
DIA OF PIPE - 0.600 m
DIA OF PIPE - 0.700 m
1.8
86
41
.25
44
3.7
35
42
.79
01
50
0
-4
1.5
18
43
.77
74
2.5
80
14
78
1.5
12
41
.51
84
3.8
77
42
.58
01
47
81
.83
04
1.5
10
43
.99
34
2.8
90
14
70
1.7
10
41
.48
04
4.0
37
42
.74
01
44
0
1.6
00
41
.45
04
4.0
81
42
.60
01
41
0
1.4
90
41
.42
04
4.1
25
42
.46
01
38
0
1.5
60
41
.39
04
4.1
69
42
.50
01
35
0
1.6
30
41
.36
04
4.2
13
42
.54
01
32
0
1.7
70
41
.33
04
4.2
57
42
.65
01
29
0
1.9
40
41
.30
04
4.3
01
42
.79
01
26
0
-4
1.2
71
44
.34
34
3.3
50
12
31
2.5
79
41
.27
14
4.4
43
43
.35
01
23
12
.31
04
1.2
70
44
.46
94
3.0
80
12
30
2.6
20
41
.24
04
4.5
00
43
.36
01
20
0
3.0
30
41
.21
04
4.5
31
43
.74
01
17
0
3.3
40
41
.18
04
4.5
62
44
.02
01
14
0 -
41
.17
84
4.5
64
44
.40
01
13
83
.82
24
1.1
78
44
.66
44
4.4
00
11
38
2.6
70
41
.15
04
5.0
09
43
.22
01
11
0
2.0
60
41
.12
04
5.0
26
42
.58
01
08
0
1.6
30
41
.09
04
5.0
43
42
.12
01
05
0
1.6
00
41
.06
04
5.0
60
42
.06
01
02
0
1.6
20
41
.03
04
5.0
77
42
.05
09
90
1.7
20
41
.00
04
5.0
94
42
.12
09
60
1.7
30
40
.97
04
5.1
11
42
.10
09
30
1.5
80
40
.94
04
5.1
28
41
.92
09
00
1.5
68
41
.13
24
5.1
45
42
.10
08
70
1.6
26
41
.32
44
5.1
62
42
.35
08
40
1.7
54
41
.51
64
5.1
79
42
.67
08
10
1.8
92
41
.70
84
5.1
96
43
.00
07
80
2.0
11
41
.89
94
5.2
13
43
.31
07
50
2.2
29
42
.09
14
5.2
30
43
.72
07
20
2.3
17
42
.28
34
5.2
47
44
.00
06
90
2.3
35
42
.47
54
5.2
64
44
.21
06
60
2.3
03
42
.66
74
5.2
81
44
.37
06
30
2.2
21
42
.85
94
5.2
98
44
.48
06
00
2.1
10
43
.05
04
5.3
15
44
.56
05
70
1.9
98
43
.24
24
5.3
32
44
.64
05
40
1.6
26
43
.43
44
5.3
49
44
.46
05
10
1.6
14
43
.62
64
5.3
66
44
.64
04
80
1.5
32
43
.81
84
5.3
83
44
.75
04
50
1.4
30
44
.01
04
5.4
00
44
.84
04
20
-4
4.1
76
45
.41
54
5.3
20
39
41
.84
44
4.1
76
45
.51
54
5.3
20
39
41
.44
04
4.1
80
45
.61
54
4.9
20
39
0
1.5
10
44
.21
04
5.6
30
45
.02
03
60
1.8
10
44
.24
04
5.6
45
45
.35
03
30
1.8
60
44
.27
04
5.6
60
45
.43
03
00
2.0
20
44
.30
04
5.6
75
45
.62
02
70
2.0
50
44
.33
04
5.6
90
45
.68
02
40
2.1
50
44
.36
04
5.7
05
45
.81
02
10
2.2
60
44
.39
04
5.7
20
45
.95
01
80
2.3
70
44
.42
04
5.7
35
46
.09
01
50
2.5
00
44
.45
04
5.7
50
46
.25
01
20
2.3
40
44
.48
04
5.7
65
46
.12
09
0
2.1
20
44
.51
04
5.7
80
45
.93
06
0
1.9
10
44
.54
04
5.7
95
45
.75
03
0
1.7
00
44
.57
04
5.8
10
45
.57
00
48
47
46
45
44
43
42
41
40
39
38
37
36
35
GL - GROUND LEVEL
UGPL
FSL LEVEL
(m)
(m)
(m)
(m)
(m)
DEPTH OF CUTTING
GROUND LEVEL
DISTANCE
FSL LEVEL
TOP OF RL OF PIPLINE
DATUM
0.000
362.114
0.25
45.81
46.06
2250M (TR)
CCA (ha)
GCA (ha)
W/Head (m)
FSL in O/T Canal(m)
FSL in Parent Canal(m)
O/Take Chainage(m)
L-SECTION OF CHICHODRA MINOR-I OF VARSADA DISTY OF KACHCHH BRANCH CANAL
Baffle wall for heading upLocation : R&R Site
Pilot project of Under Ground Pipe Line (UGPL)MAHISA PILOT PROJECTMAHISA PILOT PROJECT
Under Ground Pipe Line (UGPL) – Pilot Project
MAHISA PILOT PROJECTMAHISA PILOT PROJECT
Under Ground Pipe Line (UGPL) - Implementation
UGPL Turnout functioning
• Irrigation – 19.05 Lakh Ha (18 Lakh Ha. In Gujarat)
• Increase in Agricultural Production
- 87 Lakh Tonnes per annum
• Hydro Power – 100 crore units per year
(installed capacity 1450 MW)
• Drinking water - 9490 villages (out of 18225 total)and 173 towns (out of 195 total)
• Flood Protection to 30,000 Ha
• 10 lakh jobs - mostly in rural areas
So far…..98,500 MCM of water conveyed
40,800 MU of ecofriendly hydro power generated
Sardar Sarovar Project, Gujarat, The Planned Benefits