63
8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 1/63 SUMMER TRAINING REPORT SUBMITTED TOWARDS THE PARTIAL FULFILLMENT OF POST GRADUATE DEGREE IN INTERNATIONAL BUSINESS “CONTRACT & PROCUREMENT MANAGEMENT AT NTPC” SUBMITTED BY: Madan Nagar MBA-IB(2005-2007) Roll No. : A1200307E84 INDUSTRY GUIDE FACULTY GUIDE Sh. Dinesh Bahuguna Ms. Saurav Raina Senior Manager(Finance) Finance Faculty NTPC Noida AMITY INTERNATIONAL BUSINESS SCHOOL, NOIDA AMITY UNIVERSITY – UTTAR PRADESH

CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

Embed Size (px)

Citation preview

Page 1: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 1/63

SUMMER TRAINING REPORT SUBMITTED TOWARDS THE PARTIAL

FULFILLMENT OF POST GRADUATE DEGREE IN INTERNATIONAL

BUSINESS

“CONTRACT &

PROCUREMENT

MANAGEMENT AT NTPC”

SUBMITTED BY:

Madan NagarMBA-IB(2005-2007)

Roll No. : A1200307E84

INDUSTRY GUIDE FACULTY GUIDE

Sh. Dinesh Bahuguna Ms. Saurav Raina

Senior Manager(Finance) Finance Faculty

NTPC Noida

AMITY INTERNATIONAL BUSINESS SCHOOL,

NOIDA

AMITY UNIVERSITY – UTTAR PRADESH

Page 2: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 2/63

Company Certificate

(In the LETTER HEAD of the Company ) 

TO WHOM IT MAY CONCERN

This is to certify that _____________________, a student of Amity

International Business School, Noida, undertook a project on“___________________” at ________________________ 

from __________to _____________.

Ms./Mr.________________ has successfully completed the project under the

guidance of Mr./Ms.____________________. She/He is a sincere and hard-

working student with pleasant manners.

We wish all success in her/him future endeavours.

Signature with date

(Name)

(Designation)

(Company Name)

ii

Page 3: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 3/63

CERTIFICATE OF ORIGIN

This is to certify that Mr. Madan Nagar, a student of Post Graduate Degree in MBA-

IB (2005-2007), Amity International Business School, Noida has worked in the

 NTPC-Noida, under the able guidance and supervision of Mr.Dinesh Bahuguna,

designation: Senior Manager (Finance), Company: NTPC, Noida.

The period for which he was on training was for eight weeks, starting from 4th May

2006 to 30th July 2006. This Summer Internship report has the requisite standard for 

the partial fulfillment the Post Graduate Degree in International Business. To the

 best of our, knowledge no part of this report has been reproduced from any other report and the contents are based on original research.

Signature Signature

(Faculty Guide) (Student)

iii

Page 4: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 4/63

ACKNOWLEDGEMENT

I am thankful to Amity International Business School, for giving me an

opportunity to work with a prestigious organization like National

Thermal Power Corporation (NTPC). The experience has been highly

educative in terms of both theoretical and practical knowledge in the area

of Finance. The summer stinct at NTPC has strongly added value to my

learning curve.

I express my sincere gratitude to my industry guide Mr. DineshBahuguna, Designation: Senior Manager (Finance), Company: NTPC,

  Noida, for his able guidance, continuous support and cooperation

throughout my project, without which the present work would not have

 been possible.

I would also like to thank the entire team of NTPC especially Mr. V

Vasu, DGM (F), Mr. AA Sheikh, DGM (F), Mr. RS Sodhi, DM (F) and

Mr. Vishal Garg, for the constant support and help in the successful

completion of my project.

I am thankful to my faculty guide Ms.Saurabh Raina, of my institute, for 

her continued guidance and invaluable encouragement. Also, I am

thankful to my Prof. Mr. Ajeet Mittal, for his valuable guidance and

support during the project.

Signature

(Student)

iv

Page 5: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 5/63

TABLE OF CONTENTS

Chapter No. Subject Page No.

Ch.-1.0 Executive Summary………………….

Ch.-2.0 Research Methodology………………

1.1 Primary Objective(s)………….

1.2 Hypothesis……………………

1.3 Research Design………………

1.4 Sample Design………………..

1.5 Scope of the Study…………….

1.6 Limitations…………………….

Ch.-3.0 Critical Review of Literature………..

Ch.-4.0 Company Profile …………………….

4.1 Industry Profile………………..

4.2 Swot Analysis………………….

Ch.-5.0 Data…………………………………..

5.1 Collection………………………

5.2 Primary Data

5.3 Secondary Data….……………..

Ch.-6.0 Findings & Analysis………………….

Ch.-7.0 Recommendations……………………

Ch.-8.0 Bibliography………………………….

Ch.-9.0 Annexure……………………………..

9.1 Tables………………………….

9.2 Graphs…………………………

Ch-10.0 Case Study ……………………....…...

Ch-11.0 Synopsis of the project………………..

v

Page 6: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 6/63

EXECUTIVE SUMMARY

The report entitled “BIDDING AND FINANCIAL ANALYASIS OF N.T.P.C. ” is about the

 purchase practices followed at NTPC. These practices are followed during all procurement by

 NTPC. The purchase procedure starts at Indenting by the department that requires the material and

goes to the cost department and finance department for required approval. In between various

activities like Liquidated Damages calculation, Spare Parts procurement terms, Guarantee in

Liability Defect period etc are undertaken. Once all the terms and conditions are formulated and

approved, the tender document preparation starts. The tender documents are issued to the

 prospective bidder for a cost that starts from Rs 200 to Rs 3000. The content of the tender 

document is prepared in such a manner that the prospective bidder comes to know about all the

important details about the contract. The issuance of tender document is followed by the receipt of 

Bids from various vendors in the specified format. Once all the bids are received, they are opened

in presence of some nominated officials from Finance, Contracts and Materials department. The

representatives from the bidders may also be present. Then a comparative statement of the quoted

 bids is prepared and the contract is awarded to the lowest quoting bidder.

During the document preparation phase, payments terms are also decided and documented in the

General Condition of Contract, which is issued to the bidder with the tender documents. Apart

from payments, there are various other issues like Arbitration, which are dealt in the tender 

documents. Liquidated Damages is one of the very important clauses. Liquidated damage is a

 payment to be made by the contractor in case he fails to complete the project in the stipulated

time. In case of equipment, it is related to the performance of the equipment. The purchase is

followed by the evaluation, which is done for two things, the vendor’s performance and the

 purchase performance. The Vendor evaluation comes in handy for placing future orders where as

the Purchase Performance evaluation provides detailed insight into the procedures being followed

to procure the required material.

vi

Page 7: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 7/63

RESEARCH METHODOLOGY

Primary Objective :- The objective is to study the “BIDDING AND FINANCIAL ANALYASIS

OF N.T.P.C. ” procedures followed at NTPC .

The observations were carefully analyzed and some constructive facts and figures were revealed.

On the basis of those observations some recommendations and suggestions for NTPC have been

drafted.

The research methodology comprised of secondary data collected from various NTPC records

and through NTPC website and India Infoline.com.

Sample Design:- for the research activity to turnout into a success, a careful selection of various

Project was made. All possible effort was made to choose the unbiased data to get the fruitful

result.

Scope of the Study :- This effort is to understand the procurement practices followed at NTPC and

understand what they keep in mind before awarding a particular bid contract to the specific bidder.

It will also recommend the points to NTPC to improve upon to get the maximum chunk in the

 power industry.

Limitations :-

• Time factor.

1

Page 8: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 8/63

Industry Profile

The electricity services in India were generally provided by the State Electricity Boards (SEBs),

as it was believed that being under the control of the State governments, they could protect the

consumer interests against exploitation. Over a period of time, it however, came to be realized that

  because of their monolithic nature, the State Electricity Boards suffered from operational

inefficiencies on account of which they had incurred heavy losses. The services rendered by them

were also of poor quality. These factors forced the governments to think in terms of 

commercialization of the services so that the additional investments necessary for infrastructure

development become available through private sector involvement and the services rendered

 become globally competitive.

Central Government issued a policy resolution dated 22-10-1991 on private sector participation in

 power sector. It was followed by necessary changes in the legal framework. Despite the policy of 

liberalization, the entry of new players continued to be regulated by the government who

remained the final arbiter in all matters, including tariff fixation. It became necessary, therefore, to

 provide a level playing field to new players and to provide for competition. It was decided to

encourage private sector participation in the generation, transmission and distribution since future

expansion could not be achieved through public resources alone. Thus, the phenomenon of private

sector involvement in power sector is a relatively modern reaction to the revealed concerns and

issues associated with complete reliance on the public sector provision of infrastructure.  It should

also be decided to set up independent Central and State Regulatory Commissions.

Promotion of competition, efficiency and economy in electricity industry can be conveniently

achieved through the process of competitive bidding. The Central Government issued detailed

guidelines for competitive bidding of power projects in January 1995 whereby the competitive

 procurement of power sector projects was made mandatory. These guidelines laid emphasis on

 project identification, justification and development before taking up competitive bidding.

Growth of economy calls for a watching rate of growth in infrastructure facilities. Power sector is

one of the major aspects of this infrastructure building. Some prominent people like the Ex

Chairman of GE Jack Welch have gone to the extent of saying, “you don’t have a chance to stand

in the 21st century without lots of power………Without this you miss the next revolution.”

 

2

Page 9: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 9/63

Moreover, the growth rate of demand for power in developing countries is generally higher than

that of GDP. In India, the elasticity ratio was 3.06 in 1 st plan, and peaked at 5.11 during 3rd plan

and came down to 1.65 in 80’s. For 90’s a ratio of around 1.5 was projected. Hence, in order to

support a growth of GDP of around 7% the rate of growth of power supply of 10%is required.

If we look at current scenario, electricity consumption in India has more than doubled in the last

decade, outpacing the economic growth. If we analyze the various statistics of Indian power 

sector, we will find that the generating capacity has gone up tremendously from a meager 

1712MW in 1950 to a whooping 112000MW today.

 

GROWTH OVER YEARS:

INSTALLED CAPACITY AROUND THE END OF PERIOD:

13000

28000

66000

112000

212000

2012200019901980197019601950

460017000 

50000 

100000 

150000 

200000 

250000 

1 2 3 4 5 6 7 8 9

 YEARS

   C   A   P   A   C   I   T   I   E   S

 At the same as a result of growing installed capacity, the power produced has also gone up. In

1950, the total power produced by Indian power sector was a meager 50BU and that is now

587.3BU.

 Now a days when world is transforming into a global village and economies are opening up, a

substantial and reliable infrastructure is a must for any economy to develop. Electricity is one of 

the most vital parts of any economic structure. The govt. of India had realized it way back in 60’s

that to develop the economy and be economically independent, one must be independent in one’s

 power generation. And hence the Indian govt. emphasized the need of independence in power 

generation and in all subsequent five-year plans the allocated budget for power sector 

development was increased. But despite all these efforts by our govt., there is an acute power 

shortage in the country. Despite all efforts, a no.of states particularly the northern and western

region are faced with severe power shortage. The projected power consumption for next 10 years

is not very comforting either. Capacity expansion in power sector is outpaced by economic

3

Page 10: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 10/63

development and hence widening the gap between the demand and supply of electricity. We can

see the projected figures for the coming years in the diagram below:

POWER DEVELOPMENT- 16TH EPS PROJECTIONS:

PEAK REQUIRMENT IN BILLION UNITS:

78037 85132 115705

1574107

507 529 719 9760 

200000 

400000 

600000 

800000 

1000000 

1200000 

1400000 

1600000 1800000 

MAR'01 MAR'02 MAR'07 MAR'12 

 YEARS

   P   E   A   K   A   N   D   E   N   E   R   G   Y   R   E   Q   U   I   R

   M   E

The growth rate of power sector is shown in the diagram below:

3.4

5.1 5.2

1

4

02-'03 03-'04 04-'05  

years

   b   i   l   l   i  o  n  u  n   i   t  s

Generation during the years has been as follows:

513 533552

587

202 213 226 240

0

100

200

300

400

500

600

700

01-'02 02-'03 03-'04 04-'05

years

   b   i   l   l   i  o  n  u  n   i   t  s

Series1

Series2

4

Page 11: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 11/63

Power availability has been as follows:

While energy shortage during the same period has been as follows:

7.2

7.25

7.3

7.35

7.4

7.45

7.5

7.55

01-'02 04-'05

years

   S   h  o  r   t  a  g  e   (   %   )

And peak deficit during the same period has been as follows:

11.2

11.4

11.6

11.8

12

12.2

12.4

12.6

12.8

01-'02 04-'05

years

   d  e   f   i  c   i   t   (   %

   )

 

450000

460000

470000

480000

490000500000

510000

520000

530000

540000

550000

01-'02 04-'05

years

  a  v  a   i   l  a   b   i

   l   i   t  y   (   M   U   )

5

Page 12: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 12/63

There has been an improvement in last three years with 13% increased power availability.

However, we could reduce energy shortage by a meager 0.2% while peak deficit by a meager 

0.9%. We could have generated 18b units more had we not suffered gas and coal shortages.

However, we are now set to achieve 10th plan target of about 41000 MW as the projects worth

10959 MW have already been commissioned and project worth 24152 MW are under execution.

In accordance with electricity policy a substantial portion of under utilized capacity plants are

targeted to be brought under the grid.

PROFILE OF NATIONAL THERMAL POWER CORPORATION

LTD. (NTPC)

 National Thermal Power Corporation Ltd. (NTPC) a global giant in the power sector was set up

on 7th November 1975, with an objective to accelerate the electricity generation by planning,

 promoting and organizing integrated development of thermal power in India.

Today; NTPC is the largest power generating company in India and contributes one-fourth of the

thermal energy generated in the country. It has 463 rank in the World Top Class 2000 Companies

which is improve from the last year rank i.e. 486.Over all these years NTPC has been an

organization which has delivered expected performance in all the spheres of its business activities

and meeting all the challenges for growth and operation through adoption of excellent

management system and practices.

The success of NTPC is the result of a modest but systematic beginning.

 NTPC known as the NAVRATANS of PSU’S have central govt. and the finding agencies as one

of their major stakeholder. Railways are the major supplier of NTPC.

If anything which is manufactured is to be sold out. In the same manner NTPC also has some of 

its buyers. The main buyer’s who purchase electricity from NTPC are the state electricity board

(SEB’S) and the state govt.

It will be much more clearly from the following diagram below:

6

Page 13: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 13/63

NTPC- BACKGROUND

NTPC –  a global giant in power sector 

Source: www.ntpc.co.in

 National Thermal Power Corporation Limited (NTPC) is the largest thermal power generating

company of India. A public sector company incorporated in the year 1975 to accelerate power 

development in the country as a wholly owned company of the Government of India. At present,

Government of India holds 89.5% of the total equity shares of the company and the balance

10.5% is held by FIIs, Domestic Banks, Public and others.

Based on 1998 data, carried out by Data monitor UK , NTPC is the 6th largest in terms of thermal

 power generation and the second most efficient in terms of capacity utilization amongst the

thermal utilities in the world.

 NTPC's core business is engineering, construction and operation of power generating plants and

also providing consultancy to power utilities in India and abroad. As on date the installed capacity

of NTPC is 23,749 MW through its 13 coal based (19,480 MW), 7 gas based (3,955 MW) and 3

Joint Venture Projects (314 MW). NTPC acquired 50% equity of the SAIL Power Supply

7

Page 14: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 14/63

Corporation Ltd. (SPSCL). This JV Company operates the captive power plants of Durgapur (120

MW), Rourkela (120 MW) and Bhilai (74 MW). NTPC is also managing Badarpur thermal power 

station (705 MW) of Government of India.

Source- www.indiainfoline.com

 NTPC’s share on 31 Mar 2004 in the total  installed capacity of the country was 19.4% and it

contributed 27.1% of the total power generation of the country during 2003-04.

 NTPC has set new benchmarks for the power industry both in the area of power plant construction

and operations. It is providing power at the cheapest average tariff in the country. With its

experience and expertise in the power sector, NTPC is extending consultancy services to various

organizations in the power business. NTPC has entered into a joint venture with Alstom, Germany

for renovation and modernizations of power plants in India.

 NTPC has taken proactive steps for ash utilization. In 1991, it set up Ash Utilization Division to

manage efficient use of the ash produced at its coal stations. This quality of ash produced is ideal

for use in cement, concrete, cellular concrete, and building material.

8

Page 15: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 15/63

 NTPC’s share on 31 Mar 2004 in the total installed capacity of the country was 19.4% and

it contributed 27.1% of the total power generation of the country during 2003-04.

NTPC

OIL

SUPPLY

CENTRA

L GOVT

COALSUPPLY

RAILWAYS EQUIPMEN

T

SUPPLY

FUNDING

AGENCIES

STATE

GOVT

SEB’

S

S

U

P

P

L

I

E

S

B

U

Y

E

S

STAKE HOLDERS

9

Page 16: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 16/63

CORPORATE PLAN

The company has formulated a long term Corporate Plan for 15 years upto 2017. The

Corporate Plan seeks to integrate the Company’s vision, mission and strategies for growth

with the national plans and to provide the company the cutting edge in the emerging

competitive environment. NTPC is targeting to become a ’46 000 MW Plus’ company by 2012.

(A) Projects under construction Total Capacity - 10990 MW 

Project(State)

Capacity(MW)

Fuel Commission Schedule

Vindhayachal - III(Madhya Pradesh)

1000

(2x500)

Coal Unit – IX Feb 2007

Unit – X Aug 2007

Unchahar III(Uttar Pradesh)

210(1x210)

Coal Unit – I Sep 2006

Kahalgaon Phase IIStage I (Bihar)

1000(2x500)

Coal Unit – V Nov 2006Unit – VI May 2007

Kahalgaon Phase IIStage II (Bihar)

500(1x500)

Coal Unit – VII Mar 2007

Sipat - I(Chhattisgarh)

1980(3x660)

Coal Unit – I Apr 2008Unit – II Feb 2009Unit – III Dec 2009

Sipat - II(Chhattisgarh)

1000(2x500)

Coal Unit – I Jun 2007Unit – II Dec 2007

Koldam(Himachal Pradesh)

800(2x400)

Hydro Unit – I Nov 2008Unit – II Jan 2008Unit – III Mar 2009Unit – IV Apr 2009

Barh(Bihar)

1980(3x660)

Coal Unit – I Mar 2009Unit – II Jan 2110Unit – III Nov 2010

Bhilai Exp. PowerProject,

JV with SAIL(Chhattisgarh)

500(2x250)

Coal Unit – I July 2007Unit – II Oct 2007

Total 8970MW

 

(B) New projects being pursued for capacity addition for Eleventh Plan and Beyond 

In addition to the above, a host of new power projects as given below are being pursued forfurther capacity addition in the 11th plan and beyond:

S. No. Project / State Capacity (MW)

1. Kawas - II, Gujarat 1,300

10

Page 17: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 17/63

2. Jhanor Gandhar - II, Gujarat 1,300

3. Nabinagar - JV with Railways, Bihar 1,000

4. Loharinag Pala, HEP Uttaranchal 600

5. Tapovan Vishnugad, HEP Uttaranchal 520

6. Lata Tapovan, HEP Uttaranchal * 171

7. North Karanpura, Jharkhand 1,980

8. Rajiv Gandhi CCPP-II, Kerala 1,950

9. Ennore (JV with TNEB ), Tamil Nadu 1,000

10. Farakka III, West Bengal 500

11. Lara, Integrated Power ChhattisgarhGeneration project,

4,000

12. Darlipalli, Integrated PowerOrissaGeneration Project,

3,200

13. Rammam III HEP, West Bengal * 120

14. Hutong II HEP, Arunachal Pradesh 1,250

15. Kalai II HEP, Arunachal Pradesh 1,200

*(To be implemented by NTPC Hydro Ltd, a wholly owned subsidiary of NTPC Ltd.)

AN OVERVIEW 

Projects  No. of Projects Commissioned

Capacity(MW) 

NTPC OWNED 

COAL  14 20, 685

GAS/LIQ. FUEL  07 3,955

TOTAL  21 24,640

OWNED BY JVCs 

Coal 3 314*

GRAND TOTAL  24 24,954

* Captive Power Plant under JV with SAIL

@Additional capacity under implementation 

Vindhyachal Stage III 1000 MW • Unchahar Stage III 210 MW 

11

Page 18: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 18/63

• Kahalgaon Stage II

- Phase I 1000 MW- Phase II 500 MW

Korba Stage III 500 MW

VISION OF NTPC:

"To be one of the world's largest and best power utilities, powering India's growth".

To realize this vision, NTPC has drawn up a detailed Corporate Plan for the period 1997-2012

which represents the company's collective optimism and enthusiasm, inspired by a glorious past, a

vibrant present and a brilliant future. The Plan has been prepared in-house in consultation the

committed, competent and confident members of the NTPC family. The road map that has been

charted out was after a thorough scan of the strengths and weaknesses within the organization as

well as opportunities and threats in the environment.

Considering multidimensional opportunities in the energy sector, NTPC will adopt a multi-

 pronged growth strategy for capacity addition through Greenfield sites, expansion of existing

stations, takeovers and joint ventures.

The capacity addition plans that we have drawn up for the fifteen-year period using all the abovestrategies to enable the corporation to become a 40,000 MW company by 2012 A.D.

In addition to the above, NTPC also has plans to venture into the following areas:

• Renovation & Modernization of old power stations through a separate joint venture

company;

• Investment in LNG terminal;

Investment in coal mining and washeries;• Setting up of power plants abroad;

• Joint ventures for ash-based industries;

• Setting up of small pilot plants using renewable energy sources;

• Setting up of hydel power plants to facilitate techno-economic operation of thermal-hydro

mix of NTPC stations;

Setting up of associated extra high voltage transmission lines / inter-regional EHV transmission

lines so as to ensure evacuation of power from NTPC stations.

12

Page 19: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 19/63

NTPC CORE VALUES: -

Known as one of the NAVRATAN’S of the PSU’S NTPC has its following core values. They are:

• CUSTOMER FOCUS

• ORGANISATIONAL PRIDE

• MUTUAL RESPECT & TRUST

• INITIATIVE & SPEED

• TOTAL QUALITY

Every firm, be it a manufacturing concern or a trading concern has to buy something either to

trade it as it is or add some value to it. In both the cases the firm is buying and selling the goods

or services generated. The value generated between two points in the value chain is the profit

generated by that particular chain partner. These values. Be in terms of place, time, quantity of 

form etc. in the case of NTPC. NTPC buys coal, diesel, and other capital goods and converts it

into electricity. Since the raw material is changing form during the value addition process hence

 NTPC is a manufacturing firm. For every manufacturing concern, the raw material is the cost

center after the initial expenditure relating to the capital goods. It is also the most important factor 

affecting the quality of the product and in case of NTPC the performance. A low-grade coal may

not only reduce the efficiency of the plant but may also make it malfunction or might even lead to

a sudden breakdown. Hence the plant but may make it malfunction or  might even lead to a

sudden breakdown. Hence the right quality of fuel is not only desired but is required.

Similarly the plants and equipment required to generate the electricity is also to be procured and

hence one more purchasing comes into picture. Once the plant is erected and commissioned,during its normal operations the plant may require some spare parts as well as some replacement

and maintenance parts. Hence for that also the firm has to maintain a constant supply. So for all

this purchase system is another big question. To get an appropriate purchase system structure we

must identify the actual requirement NTPC has some plants as old as 25 years old, which are

using a very aged or aging technology; on the other hand some of its required for these two plants

will obviously be different. Similarly some of the plants are located in a well-connected city like

Delhi, others are located in very distant places where even the transport is a big problem. So these

two types of plant may require different amount of the same material for the same time period.

The purchasing procedures at NTPC should be such that it can take care of such extreme

differences and provide both the locations with the required material at the right time,. If NTPC  procure all the material through a centralized purchasing  division which will club all the

requirements of various projects together and order on the basis of his clubbed requirement, of 

13

Page 20: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 20/63

various projects together and order on the basis of the clubbed requirement, then NTPC can

achieve economies of scale as the quantity bought will be significantly high considering that it has

more than 20 projects running in its fold this trade of between the economic efficiency and

response is very important as all the plants of NTPC run on 365x24 basis.

FINANCIAL

STATEMENT

ANALYSIS

14

Page 21: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 21/63

A financial statement analysis consists of application of analytical tools and techniques to the data

in financial statement in order to derive from these measurement and relationships that are

significant and useful for decision making.

Financial analysis can be used as the preliminary screening tool in selection of stock in secondary

market .It can be used as a forecasting tool of future financial condition and results. It may be

used as a process of evaluation and diagnosis of managerial, operating, or other problem areas.

The principal tool for the analysis of financial statement is RATIO ANALYSIS.

ANALYSIS OF FINANCIAL STATEMENTS :-

A ratio gives the mathematical relationship between one variable and another. Ratio analysis

mainly helps in valuing the firm in quantitative terms.

Financial tool can be grouped as

1) Profitability or efficiency ratio

2) Ownership ratio

Earning ratio

Leverage ratio

Capital structure ratio

Coverage ratio

Dividend ratio

LIQUIDITY RATIO

15

Page 22: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 22/63

Liquidity is firm’s ability to pay its debt in short term. Short-term liquidity involves the

relationship between the current asset and current liability. If the firm has sufficient net working

capital (excess current asset over the current liability) the firm is said to be highly liquid.

Current Ratio

  Current AssetIt is define as

  Current liability 

Current asset includes cash; marketable securities, debtors, inventories, loan and advances, and

 pre-paid expenses, current liability includes loan and advances taken, creditors, accrued expenses,

and provisions.

In operating cycle the current assets are converted into cash to provide the payment for currentliabilities. So higher the current asset higher the short term liquidity.

Quick Ratio

Quick test is also defined as the acid-test ratio

  Quick AssetIt is define as

Current liability  

Current asset – inventories=

Current liability 

 The quick ratio is more stringent measure of liquidity, because the inventory which are liquid of 

current asset, and exclude from the ratio.

Inventory Turnover Ratio

The liquidity of firm’s inventory may be calculated by dividing the cost of good sold, by the

firm‘s inventory The inventory turnover measure that how fast the inventory is moving through

the firm and generating sales,

 Inventory turnover ratio

Cost of good sold=

16

Page 23: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 23/63

 Average inventory 

Higher the ratio the greater the efficiency of inventory management.

Presence of inventory involves two risks:

1 Running out the inventory due to low inventory (high turnover), which may indicate

future shortage.

2 Excess inventory causes the blockage of capital.

PROFITABILITY RATIO

These ratios measure the firm’s ability to generate profits. These are of two types. These are:-

1) Profit in relation to sales:

It is important from the profit standpoint the how much the firm is able to generate the profit

with the sales of each unit. Two popular ratios in this category is operating profit margin, net

 profit margin.

2) Profit in relation to asset

It is important that the profit be compared to the capital invested by the owners and creditors,

if the firm cannot produce a satisfactory profit on its asset base, it might be misusing its assets.

They are also referred to as rate of return. Ratio like   asset turnover ratio, earning power, and

return on equity fall in this category.

Operating Profit Margin

Operating profit is basically earning before interest and taxes, it profit generated by operation.

Operating profit margin

EBIT=

Net sales

Net sales = sales - excise duty 

17

Page 24: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 24/63

Net Profit Margin

It is defined as Net profit

  Net sales

This ratio shows the earning left for the shareholders as a percentage of net sales .It measures the

overall efficiency of production , administration , selling , financing, pricing, and tax

management,

Asset Turnover Ratio

Asset turnover ratio defined as

Sales

Average asset

It highlights the amount of assets the firm used to generate its total sales. The ability to generate a

large volume of sales on a small asset base is an important part of the firm’s profit picture .Idle or 

improperly used asset increase the firm’s need for costly financing and the expense for 

maintenance and upkeep.

Return on Equity

The return on equity (ROE) is an important indicator to shareholders of the firm. It is calculated

 by the formula:

Net Income

Average Equity 

The return on equity measure the profitability of equity fund invested in the firm. It reflects the

 productivity of capital employed in the firm. It is influenced by several factors: earning power,

debt-equity ratio, average cost of debt fund, and tax rate.

EARNING RATIO

The earning ratios are earning per share (EPS), Price-earning ratio (P/E) and capitalization rate.

From the earning ratios we can get information on the firm and their effect on price of common

stock.

18

Page 25: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 25/63

 Earning Per Share

Shareholders are concerned with the earnings of the firm in two ways, one the availability of 

dividends and other to expand their interest in the firm with the retained earning. EPS can bedefined as

Net Income (PAT)

Number of outstanding share

 Price–Earning Ratio

The price –earning ratio is also called P/E multiple.

   Market price of share

  Price-earning multiple =  Earning per share

This ratio gives the relationship between the market price of the stock and its earnings by

revealing how the earning of a firm affects the price of its stock. If a P/E ratio of the stock is very

small say 3/1 it may be considered as undervalued stock .If the P/E value of firm is 80/1 it may beconsidered as overvalued firm .

The Capitalization Rate

Earning per share

Capitalization rate =   Market price of share

The reciprocal of P/E ratio gives the return the investors generally expect before buying shares.

For example if a stock has Rs. 12 EPS and sell for Rs. 100, the market place expect a return of 

12/100, i.e. 12% .this is called stock’s capitalization rate. A 12% capitalization rate implies that

the firm is required to earn 12 % on the common stock value. If the investor expects less than 12%

they will be ready to pay more than current value and the capitalization rate of stock drops.

LEVERAGE RATIO

Debt-Equity

19

Page 26: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 26/63

The debt-equity ratio indicates the relative contribution of creditors and owners, it can be defined

as

Debt 

Equity

Depending on the type of business and the pattern of cash flow the component of debt-equity ratio

will vary .Normally the debt component consists of all liability including current. The equity

component consists of net worth and preference capital. It is the screening device in the financial

analysis .If the D/E ratio is relatively high, the owner is putting less money and that is the danger 

signal for the creditors .If the project of such firm fails the loss is major shared by the creditors

and the owner may act irresponsibly .high portion of debt can affect the operation of firm because

the creditors can interfere in the operational as well as managerial decision.

Debt-Asset Ratio

The debt-asset ratio measures the extent to which borrowed fund support the firm’s asset. It is

defined as

  Debt 

Asset 

The asset here indicates total of all asset in balance sheet.

It is usually held that fixed asset and long term asset should not be financed by short term loans.

The most appropriate kind of fund for financing of this kind of assets is equity capital.

Interest Coverage Ratio

One measure of a firm’s ability to handle financial burden is the interest coverage ratio, also

referred to as the times interest –coverage ratio. This ratio tells us how many times the firm can

cover or meet the interest payments associated with debt.

   EBIT Interest coverage ratio  =

Interest expenses

The greater the interest coverage ratio, the higher the ability of the firm to pay its interest expense.

Degree of Operating Leverage (DOL)

Operating leverage examine the effect of the change in the quantity produced on the EBITof company.

20

Page 27: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 27/63

Percentage change in EBIT  DOL  =

Percentage change in output 

Greater the DOL, the more sensitive is EBIT to a given change in unit sales, DOL is therefore

indicates the business risk.

Degree of financial leverage (DFL)

Financial leverage results from the presence of fixed financial charges in firm’s income stream

.These fixed charges do not vary with the EBIT. It is defined as the ability of a firm to use fixed

financial charges to magnify the effect of change in EBIT on firm’s EPS.

Percentage change in EPS  DFL  =

Percentage change in EBIT 

There will be no financial leverage if there is no fixed-charged financing.

Degree of total leverage (DTL)

It is combination of operating leverage and financial leverage .The degree of total leverage is themeasure of the output and EPS of company .DTL is product of DOL and DFL and can be

calculated as follows:

Percentage change in EPS  DTL  =

Percentage change in output 

OrDTL= DOL*DFL.At the break-even point of output the DTL is undefined.

At the output less than output DTL is negative.

At the output more than output DTL is positive.

DIVIDEND RATIO

Dividend Payout Ratio

21

Page 28: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 28/63

This is the ratio of dividend per share and earning per share (EPS).It indicates how much of the

earnings of company is being disbursed as dividend .If the company believes in high pay-out ratio

then it can be said that firm is retaining less that may hamper future growth of company .If the

firm need money for financing any project it can retain more and pay less dividend.

Dividend Yield

This is the ratio of dividend per share and market price of share.

DPS Dividend yield =

Market price of share

The ratio gives the current return on one’s investment .this is mainly interest of investor.

GROWTH

Growth of firm = retention ratio * ROE.

This value gives the annual growth of company taking assumption that whatever 

firm is retaining is investing and getting the rate of return equals to ROE.

COST OF CAPITAL

It is the cost of acquiring the fund required to finance the project .i.e. cost of capital is the borrowing rate of the firm, alternatively cost of capital in terms of lending rates may refer to the

opportunity cost of the funds to the firm .i.e. what the firm could be earned by investing funds

elsewhere.

NTPC (Rs. Millions)

 Years 2005 2004 2003 2002 2001

LIQUIDITY RATIOCurrent Assets,

Loans & Advances 129073 135468 194132 177771.98 160751.7Current Liabilities &Provisions 67467 80942 45851 58153.09 67324.34

Secured Loans 44407 45844 41226 16455 19655Current ratio( incl.ST loans) 1.15 1.07 2.23 2.38 1.85

Current ratio 1.91 1.67 4.23 3.06 2.39

Quick ratio 1.65 1.46 3.85 2.71 2.12

inventory 17777 17380 17712 20142 18356Operating Income(turnover ) 225402 188491 190475 177697 189449

Inventory Turnover Ratio 12.68 10.85 10.75 8.82 10.32

22

Page 29: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 29/63

Fixed asset (after depreciation ) 223148 212545 198650 176781 184657FIXED ASSETTURNOVER RATIO 1.010 0.890 0.960 1.010 1.030

INVESTORS RATIO

Retained Earnings 35600 40398 28600 28317 29106

Reported Net Profit 58070 52608 36075 35396 37338

RETENTION RATIO(RE/PAT ) 0.613 0.768 0.793 0.8 0.78

ROE (%) 14.16 15.02 11.59 12.44 14.59GROWTHg=RETENTION RATIO*ROE  8.68 11.535 9.191 9.952 11.38

Equity Dividend 19790 10823 7080 7079 7470Number of Equityshares outstanding 8245464400 7812549400 7812549400 78125494 78125494

DPS(DIV./OUT.SHARES  ) 2.4 1.385 0.906 90.611 95.615EPS (PROFIT/ OUT.SHARES) 7.043 6.734 4.618 453.066 477.923DIV.PAYOUTRATIO (%) 34.08 20.57 19.62 20 20.01

D+E 515404 447555 402336.61 356255.12 329877.86

TOTAL EQUITY (E) 410077 350167 311306 284621 255933

TOTAL DEBT (D) 170878 154528 132157 115812 98048

INTERST PAID (I) 16955 33697 9916 10414 12485COST OF DEBT(Kd=I/D*100)%(1-t) 6.59 14.48 4.98 5.97 8.46COST OF EQUITYCAPITAL(Ke)%=ROE 14.16 15.02 11.59 12.44 14.59OVERALL COST OF CAPITAL =Kd*(D/D+E)+Ke*(E/D+E)OVEALL COST OFCAPITAL(Ko) % 11.93 14.85 9.62 10.57 12.89

MARKET VALUEOF FIRM=EBIT/Ko 713185.25 639643.1 595072.77 530832.5 490768

WEIGHTED AVERAGE COST OF CAPITAL

WEIGHTED AVERAGE COST OF CAPITAL

WACC (FOR 2005)

average price of stock 2005(P) 86.32

dividend paid (D) 2.4

ygrowth (g) 8.68

expected dividend next year D1=D*(1+g) 2.60832

23

Page 30: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 30/63

REQUIRED RATE OF RETURN =D1/P+g

REQUIRED RATE OF RETURN (%) 8.71

CAPITAL PROPORTION(P CAPITAL

Equity Share Capital 82455 0.14193 Ke=14.16

Reserves & Surplus 327622 0.56394 Ke=14.16

Unsecured & Secured Loans 170878 0.29413 Kd=6.59TOTAL 580955

WACC=P1*Ke+P2*Ke+P3*K d

PROPORTION (P) COST OF CAPITAL

P*COSTOFCAPITAL

P1 0.142 14.16 2.01

P2 0.564 14.16 7.99

P3 0.294 6.59 1.94

WEIGHTED AVERAGE COST OF CAPITAL 11.94

24

Page 31: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 31/63

PROCUREMENT MANAGEMENT AT

NTPC LIMITED

INTRODUCTION

Procurement activities to be taken by NATIONAL THERMAL POWER CORPORATION

(NTPC) are to satisfy varying project requirement of equipment, materials and services. Any

 procurement-requiring adherence to the IDA procurement procedure, long equipment delivery

  periods, intense engineering co-ordination or specialized engineering knowledge during

 procurement etc. would be classified as category “A” contracts. All other procurement contracts

 pertaining to a project will be classified as category “B” contracts.

Procurement at NTPC is initiated on the basis of approved indents/requisitions and indicating

  budget and project estimate provisions. The contract services/materials management services

receive the requisition/indent for the procurement of materials/equipment/services duly approved

 by the competent authority and then plan and organize the procurement action.

 

OBJECTIVE

The basic objective of procurement management at NTPC is to make available, the needed

equipment, material, works and services in the right quality and quantity, at the right time and atthe right price after giving fair and equal chance to tenderers, so as to obtain the optimum value

for each unit of expenditure.

25

Page 32: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 32/63

PROCEDURE 

DOP (DELEGATION OF POWER)

All the activities undertaken at NTPC are regulated by a guideline called “DELEGATION OF

POWERS” or “DOP” in short. The guideline lays down the responsibility and authority of variouslevel executives in the PSE (Public Sector Enterprises). Based on this guideline the following

major procedure’s have been identified.

However, procurement of any material for any plant or the office of NTPC is done by two

 processes. These processes are:-

• Procurement through tenders.

• Emergent Procurement

Though in case of urgency the respective department is allowed to make procurement through

cash up to the limit of Rs. 10,000 only. But in case of the normal procurement that is done by

tendering, a standard procedure is followed where the intender sends the procurement list to the

finance department for the goods valued over Rs. 10,000 for vetting.

Once the finance department clears the cost aspect of the tender it is send for the required

approval from the competent authority as described in the DOP. After getting the required

authorization the indent is forwarded to materials, contracts or HR services as is suitable. From

there a tender notice is issued and the procurement process starts.

 

TENDERING PROCEDURE FOLLOWED

AT NATIONAL THERMAL POWER 

CORPORATION LTD.

26

Page 33: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 33/63

(NTPC)

PROCEDURE FOR INDENTING:

INDENT

COST ESTIMATION

FINANCE

CONTRACT MATERIAL HR

27

Page 34: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 34/63

For the purpose of indenting, material planning is required. It is nothing but classifying the

materials into various categories to facilitate a speedy and efficient procurement. In this process

all the materials which may be required at any of the NTPC projects or offices are classified in to

five major categories and their procurement is to be done on the basis predefined for them.

1.Stock item (Automatic Recoupment items/AR)

2.Insurance Items (I)

3. Unit Replacement item (UR)

4. Capital Item (P)

5 Other non-stock items (Not falling under any of the above category)

But since this classification is very vague and unspecific, a further classification is done to

exercise selective control over all Material Management activities. This classification is known

as the ABC analysis.

A- Class items: Items having Annual Consumption over Rs 1 lakhs are classified as class A

Items.

There are few points worth noting about the indenting process. The estimated value of the indent

should be as far as practicable. Basis of estimates should be either on the last purchase price with

escalation if any or market trend or on the basis of technical specification e.g. size weight etc. In

case of new items detailed justification & working sheet of estimated cost shall be furnished,

wherever possible. Similarly in case of proprietary items, PAC/OEM/DES or standardization

certificate must be furnished  by the competent authority that should be DGM or above. After these

details are checked and satisfied, the indent may be registered and further procurement processmay be started.

B- Class items: Items having Annual Consumption over Rs. 10000/- but less than Rs. 1 lakhs are

classified as B class item.

C- Class items: Items having annual consumption of less than Rs. 10000/- fall

under this category.

Cost estimation: Cost estimation process is the most important financial activity in the process of 

 budgeting and procurement. Whenever NTPC procures some material, it is either financed from

the budget allocated to the particular department requesting for the material or it will be financed

from the central fund. The procurement of the second kind requires financial clearance from the

Finance Concurrence department. For the purpose, cost estimate is made before forwarding the

indent document to the Finance department. There are various methods of cost estimation, which

are used at NTPC. Some of the methods use very technical details and procedures whereas others

are simple to implement and uses market rate to prepare a cost estimate.

a)Historical Cost Method: In this method of cost estimation. The cost engineering department

28

Page 35: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 35/63

at NTPC uses the latest cost incurred for a similar kind of project. For example, if a cost

estimate has to be prepared for· a new Thermal Power Plant, the latest executed Thermal

Power Plant rates will be used not any other. Hence the rates thus obtained are very near to

the actual that might be prevalent in the market at present. But to smoothen the effect of 

inflation and various other financial components in the price at the time of the execution of 

that project, an escalation factor is used. All the prices of previous projects are multiplied by

this factor and a very close estimation of market rate is thus obtained. The escalation factor 

calculation is discussed separately in the report.

 b) Market Rate Method: Market rate method is used for the procurements that are not in

very large numbers and value. In this method once an indent is prepared, some of the

vendors registered at NTPC or listed in trade journals are sent a request for quoting the

 prices of a particular good. This enquiry is not a tender and the rates provided by the

vendors are not part of the bid. After the information is received, the rates quoted by variousvendors are compared and the lowest quoted price is taken as base rate for calculation.

However if the difference in the price quoted by two vendors are reasonably high an average

of the two may be taken as the base. However for civil works component of the contract, the

wages rates are taken from the government gazettes and similarly for some homogeneous

 products like cement, steel etc a standard market prevailing rate is used.

TENDERING PROCEDURES

Purchasing at NTPC is not a very simple process. As we have discussed earlier, the purchasing

 process is not same for all kind of materials and equipments. The urgently required materials are

 procured through cash purchase and single  tendering, the routine purchase are routed through

Material Management Services and are procured by bidding. As we had seen the classification or 

the materials, the value frequency of purchase decides the mode of procurement. But as a policy,

all the items worth more than Rs. I lakhs must be procured through tenders. The materials

department or the HR Services department usually initiates the tender process .In case of 

construction and civil works; the tender is initiated  by Contracts Services. Tendering process is the

most important activity during the entire acquisition process and hence this is the main focus

during the project. Close monitoring of tendering process is required because there are lots of 

chances or fraud, Mis-representation of facts and various other legal and procedural

misrepresentations. To simplify the study of tendering process we have divided the topic in sub-

 parts, which will he discussed subsequently. But before we go any further we wi1I see a graphical

representation of the tendering process.

29

Page 36: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 36/63

I) TYPE OF TENDERS: Based on the materials classification and DOP, there are three types

of tenders

l.Open tender: Procurements or value Rs I lakh and above must be done through open

tendering . All the plant packages are procured through Open Tender. Open tender is accessible

to all known, reliable and proven sources of  particular equipment/material. For the purpose, a

notice inviting tenders must appear in two or more newspapers of all India repute in addition

to one or more local newspaper where the material/equipment is to be delivered. However to

avoid frivolous tenders, a pre-qualification procedure may be adopted. this process will take

 place once in every three years  by advertising in two or more newspapers of all India repute in

addition to one or more local newspaper where the material/equipment is to be delivered. The

criteria for pre-qualification will inter-alia consist of past performance, financial soundness,

technical competence, organizational capability etc. But for the items valued less than Rs 1

lakh the pre-qualification can be done on the basis of data available in Trade Journals,

Manufacturer's Directory, or approved vendors list of State Government/Central

Government/DGS&D vendors to whom enquiries were floated in past.

2.Limited Tender: Limited tender is a type of tender where instead of sending bid enquiry to all

the possible vendors through newspapers, a limited number of vendors arc intimated through

Tender Notification

Issuance of Tender

Document

Received Quotation

Has Tender Evoked

No

 Yes

Award of contract

30

Page 37: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 37/63

 post or fax. But a Limited Tender may be invited only for the procurements worth less than Rs.

50000/-. In limited tender, a minimum of four bidders are invited to quote the prices for the

required equipment/material /services and these four bidders must be from the approved list of 

vendors mentioned in the open tender. However a Limited Tender is a special case and cannot

 be issued without proper explanation and requirement. In case of urgency, items worth more

than Rs. 50000/- may also be procured with authorization of competent authority and the

reason must be recorded in the indent documents. However the next higher authority of the

 procurement department will decide the number and names of supplier.

3.Single Tender: This type of tendering is the easiest and fastest to acquire a good but requires

lot of paper work and authorization before the acquisition can be initiated. These acquisitions

take place on the ground of proprietary items or standardization. To initiate a single tender, a

Proprietary Article Certificate must be issued by a competent authority and the purchase will

not be made without authorization of a Genial Manager or to whom the power is delegated.

This type of tendering is monopolistic in nature and is avoided to the extent possible. However 

Single Tendering is done in many other cases which are not mentioned anywhere in the DOP.

4. E-Procurement at NTPC : E-Procurement is very important to achieve e-governance and for 

applicability of uniform procurement process to all units. It has ability to reduce procurement cost

 by reduction in the lead time, reduction in transaction cost and cycle time etc. E-Procurement also

help in building collaborative relationship with suppliers. E-Procurement enables greater transparency, it also enables best practices and increase vendor base. E-Procurement also reduce

the possibility of cartel formation and generate responsible competition. It also achieves saving in

administrative and process cost. E-Procurement enhance the security and it is also a step towards

ERP systems for the organization.

E-Procurement further promises the following gains to the supplier/ vendor community,

•  No geographical barriers: Sales/Marketing time reduction , which otherwise is spent on

 price negotiations, follow up etc., as this will lead to the quicker order finalisation at our 

end.

• Reduction in venders cost as they need not to travel our offices and there is not need to

make those umpteen calls (communication cost).

• Complete transparency in the process/ the operating community, leading to sound

decisions.

In pursuance to achieve e-governance, in the recent past Government of India has issued

necessary guidelines for implementation of e-business and Government is keen for 

31

Page 38: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 38/63

implementation of e-business in all the areas. It has been informed that many of public sector 

Organisations as well as Government Department have been benefited with E-Procurement.

Central Vigilance Commission (CVC) vide office order no 46/9/03 dated 11/09/03 has issued the

guidelines for procurement through E-Procurement /Reverse Auction.

CONCEPT AND SCOPE: E-Procurement is purchase and sales of supplies and services and

management of procurement process over internet. E-Procurement website allow qualified and

registered users to look for buyers or sellers for goods and services.

E-Procurement is an integrated system and can be adopted uniformly at all the units of NTPC, to

help reduce the procurement cost, procurement lead time and shall enhance the increased

transparency.

POLICY: NTPC is spread over all parts of the country and therefore a uniform system is

envisaged which shall be efficient, economic and transparent. The E-Procurement shall be

applicable to all the NTPC stations/ Projects / Regions and at Corporate Center. Procurement

 process shall gradually be taken electronically so that we achieve all possible procurement

through electronic media.

The present policy is for adaptation of procurement process through electronic media, therefore

the existing DOP shall remain same. THIS POLICY IS EFFCTIVE FROM 1-04-2006.

TARGETS: Implementation of e-procurement at all stations/regions have been targeted as detailed

 below:

• 60% of e-procurable items by Dec 2006.

• 100% of e-procurable items by Dec 2007.

E-TENDERING: The concerned executive C&M department shall examine the indent with

reference to type of items, complexity, technical specifications and other aspects and may decide

for e-tendering. Depending upon the type of items and value etc. It will be decided as single part

 bidding or double part bidding.

SECURITY CONCERN: In order to assure confidentiality, security and authenticity and non-

repudiation, following techniques shall be used. Security is not restricted to these but if felt

appropriate, at any time, additional features shall be applied.

• Public key Infrastructure

• Digital Signature

• SSL/Passwords

• Digital Certificate

• Tender preparation & Release….Work flow based

• Bid preparation-data resides on server only bidder is able to view

32

Page 39: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 39/63

• Bid submission-with HASH and Encryption

• Bid opening- can be viewed only upon Un-encryption

PROCESS: The process of e-procurement shall be taken up at Contracts & Materials department

after receipt of the requisition or the indent from the user department. The indent duly approved

 by the competent authority as per DOP, is a pre-requisite to initiate e-procurement actions. The

indent complete in all respect along with the all required information, documents, specifications,

quality plan shall be forwarded by indentor to Materials department.

The main steps involved are:

• Mode of tendering

•  Nomination of tender committee

• Defining tender documents

•Defining auction rules

• Obtaining digital certificates for each T.C member 

• Generation of passwords

• Defining of Server timing of clock 

• Hosting of tender documents

• Release and Uploading of documents

• Defining tender schedule

• Allowing download of tender documents

• Clarification on tender documents on line

• On line price bid clarification / Amendments

• Preparation of bids on line

• Submission of bids online

• Up-loading of bids

• Submission of EMD-off-line(online possible where e-payment facility is available)

• Opening of bids- online (upon applying individual digital certificate and passwords by

Tender committee)

• Opening of envelope –1..EMD

• Opening of envelope –2 ..QR (in case of open tender)

• Opening of envelope –3 ..Technical details & data sheets

Opening of envelope –4 …Technical deviation details• Online evaluation of technical bids and QR 

33

Page 40: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 40/63

• Online technical & QR clarifications

• Arriving at technical loading off line

• In corporation of loading logic

• Assessment of NEW vendor 

• Opening of envelope –5 …Price bid schedule

• Online generation of comparative statement

• Defining Auction Strategy/ date/ Time/Rules

• Intimation of Reverse Auction date & time to vendors

• Conducting reverse auction

• Providing of item wise break up by L1 bidder in the event of composite tender 

DETAILS OF PILOT PROJECTS ,UNDERTAKEN BY VARIOUS PROJECT:

1.Badarpur Forged steel balls Completed

2. Dadri Laptops & PCs Completed

3.Simhadri Conveyor Belts Under completions

4. Farraka Conveyor Belts Work in Progess

VALIDITY OF THE POLICY:

This policy document is valid for the period of one year w.e.f 1-04-2006. In the mean time any

suggestions / recommendation may be forwarded to corporate materials for review.

II) Tender Documents: Every time when an open tender is invited, the bidders are provided with

a set of documents, which provides various required information and terms and condition of the

contract The documents also contains the various contract forms which the  bidder is expected to

sign and return to NTPC to acknowledge the acceptance of the terms and condition of the contract.

The document also contains the guidelines for bidders for bank  guarantee. Earnest

money and the like, this document is issued for a cost that is decided on the basis of 

the total estimated value of the indent the costs of the documents are as follows:

ESTIMATED VALUE OF INDENT

COST OF TENDER  

DOCUMENT

1 Up to Rs. 10 lakhs 200

2 Above Rs 10 lakhs and up to 25 lakhs 300

3 Above Rs 25 lakhs and up to Rs 50 lakhs 500

4 Above Rs 50 lakhs and up to Rs 100 lakhs 750

5 Above Rs 100 lakhs and up to Rs 500 lakhs 1500

6 Above Rs 500 lakhs 3000

Every time a new tender is notified, a set of tender documents is issued against a payment of 

34

Page 41: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 41/63

stipulated fee according to the price list given above. This set of tender document consists of many

different documents meant for different purposes. The documents may vary from project to

 project. Here we will see what the documents that are generally issued to bidders are.

A)Instruction to Bidder (1TB): This document is meant to provide the bidders the vital

information required to understand and evaluate the tender offer. The document contains the

general instructions like the Terms of Payment, Bid Security, Contract Performance Security,

Liquidated Damages, Currencies conversion, Defects Liability and Work Schedule. The

document also specifics the Qualifying/Eligibility requirements of the bidder and the

goods/services supplied. The ITB also contains information for the foreign bidders.

Additionally the ITB contains various references to clauses of GCC (General Condition of 

Contract) and SCC (Special Condition of Contract). Finally the document specify about the

language and interpretation and implied terms and condition of all the documents provided

with the bid. ITB also contains information about how to modify and withdraw the bids

already submitted to NTPC. Hence in short we can identify this document as the guidelines

and information brochure to bidders before they submit their quotation for the notified work.

B)Bid Proposal Sheet or Bid Data Sheet: Bid proposal sheet is a set of documents, which

contains the formats for bidding, Summary price proposal, Break up of Bid. Price, Equipment

wise price break-up, civil works price break-up, commercial deviation, Technical deviations,

Guarantee declaration, Price Adjustment data, Price break up of recommended spares,

Construction Equipments, Special Maintenance Tools, QR Data and capacity data, Work 

completion Schedule, Declaration of Import content, Check list, Information regarding value

addition and Type test charges. This document is nothing but a standard format providing the

 bidder to -Furnish the details required by the NTPC in a standard format used at NTPC.

c)General condition of Contract: The document titled General Condition of Contract of 

GCC is a document that takes care of the legal aspect of the contract between the

 bidder and NTPC. This document also is an integral part of all the bid documents

with some minor changes or no changes at all. The document starts with the

definition for The terms used in various tender documents. This is worth noting that all theterms used in the bid document are predefined and have one and only meaning which is

defined in the GCC. The document also contains different formulae that are to be used on

some future dates to calculate the LD or the Price Escalation. Finally the document also

refers to the unforeseen events like Out Break of a War, Bankruptcy of the contractor or any

other  Force Majeure. The GCC also has a clause called RESOLUTION OF DISPUTES that

specifies the procedures to be followed if any dispute occurs, arising out of or in connection

with the Contract.

D)Special Conditions of Contract: Special Condition of Contract or SCC is not a standard

document that is issued with all the tender documents. The document takes care of the

35

Page 42: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 42/63

special issues that have come up or may come up in the course of the execution of that

 particular contract and has not been covered in the General Condition of Contract. The very

first clause of the document is TIME-THE ESSENCE OF CONTRACT. The document also

talks about the detailed Manufacturing plan and Master Schedule of the execution of the

contract. It is the SCC where we mention the issues related to Liquidated Damage Clause.

This is mentioned in the document itself that "The following Special Condition (if Contract 

  shall supplement the General Condition of Contract. Wherever there is a conflict. The

 provisions herein shall prevail over those in the General Conditions of contract. Hence the

document may also be considered as the amendments to the GCC.

E)Erection Condition of Contract: This document again is specific document which may not

 be issued with all the tenders. As the name itself suggests. The document deals with the

erection component of the contract (if any). In the document some particular issues

 pertaining to the erection component of the contract is dealt with. Typically, an Erection

Condition of Contract deals with the civil construction works undertaken at the site where

the equipment is to be installed and commissioned. This also takes into consideration the

statutory and local authority who may be in charge of monitoring the work in progress and

whose permission may be required. Hence this document is a must for all the work where

there is an erection component.

F)Technical Specification: The document is the thickest document or any bid document. This

document contains all the specification required for that particular project. The document is

 prepared by the Project Engineering department and contains the technical specifications of 

the equipments and spares to be procured. It may also contain the drawings of the equipment

or layout of the project. Similarly the document will also enlist all other possible alternatives

to the already mentioned specifications (if any). Since there are no financial aspects associated

with this document, a detailed study of this document is out of the scope of this report.

III) Tender Committee: As we have mentioned earlier, Delegation of Power has a very

important role to play in purchasing process At  NTPC. For  every purchase value of exceeding Rs 50000/-.

The committee consists of three members, one representative each from the Indenting

department, Materials Department and Finance (Concurrence). The representatives are

nominated by competent authority varying from Senior Manager to DGM depending upon the

value of the contract. This committee will take into consideration every possible aspect of the

terms and conditions, prices, inspection procedures, phasing delivery if required etc. This

committee also formulates the QR (Qualifying Requirements) for the bidders of that particular 

tender.

.

36

Page 43: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 43/63

IV) Tender opening: Tender opening is the penultimate step in the purchasing process. Tenders

are opened on the due date and time mentioned in the tender notification without fail. If the data

mentioned is declared holiday, the next working day will be considered as the opening date but the

time will remain the same. The sealed envelopes containing the bid will be opened by the

 purchase and finance executives nominated by their Head of the Department. The representatives

of the bidders may also present themselves if they wish so however their absence will not hinder 

the process. The name and rates quoted by all the present bidders will be read out and any

omission or irregularity will be pointed out on the spot.

Alterations or erasures (if any) will be initiated by the officers present at the time or the opening

of the tenders. All the quoted figures should also be encircled and will be written in words if the

 bidder have not done so already and will be attested. Total number of erasures and correction will

also be written and attested. These all activities are done to ensure proper and transparent

 procurement process.

V) Late and Delayed Tender : Though the last dates for receipt of tender and tender opening dates

are mentioned in the bid invitation notice and all the bidders are expected to adhere to them, some

times some tender documents posted by the bidders get delayed in the post and reach the NTPC

office later than the date specified in the tender invitation notice. It can be caused by several

reasons within bidder's control or out of one's control. All such tenders are classified into two

categories, Late Tenders and Delayed Tenders.

a) Late tender :  The tenders that have been posted on or after the due date and received

subsequently are considered to be Late Tenders. Similarly all the tenders posted through courier 

 before the due date but received after the due date is also considered to be Late Tenders. As a

 policy All the Late Tenders are rejected out right.

 b) Delayed tender : When a tender document is posted before the due date but is received after the

due date. For such tenders which are posted through Registered Post/Speed Post before the due

date and is received within 6 working days of bids due date may be opened and considered with

the approval of competent authority. But this consideration has a condition that the date of  posting of the bids documents must be clearly visible On the postal stamp on the

envelope containing the documents. Tender those is posted by ordinary post and

are received after the due date and time will not be opened and will be returned to the party after 

finalization of bid except in case where:-

.

1) The number of acceptance offers is less than three

2) Lowest and acceptable tender is unreasonably high when compared with Lowest Purchase

Price.

3) Artificial manipulation of rates by forming a ring is suspected.

37

Page 44: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 44/63

4) All the tenderers are providing the make of only one manufacturer.

5) If a substantial savings in foreign exchange is possible.

VI) Negotiation: When adequate competition exists, the negotiation should and must be avoided.

This competition may be in form of many manufacturers making the same good or a single

manufacturer providing the goods through many retailers/suppliers and all the retailers/suppliers

are free to quote individually. However if it's found that the price quoted by all individual bidders

are unreasonably high in comparison to the last purchase price/estimate or in case of some

ambiguous technical/commercial terms and conditions, negotiations can be done with the

approval of competent authority as per DOP. In normal circumstances, the negotiation should take

  place with the technically and commercially evaluated lowest (Lt) vendor only. However,

depending upon the situation the negotiation may be carried out with more than one party at a

time. Normally the negotiation is carried out by the TC (Tender Committee). But in case a tender 

committee is absent i.e. no committee was formed to monitor the procurement, representatives

from finance and purchase may complete the task of negotiation. However, negotiation process is

not always for negotiating the prices of equipment/material/services supplied but it may also

involve terms and conditions of supply, future commitments for supply of spare parts and

consumables and many other aspect of the contract. For example a lowest price bidder may not

get the contract if it’s found that another bidder who is quoting higher than him but is offering

lower priced spares. Hence in this case a negotiation may be conducted with the L 1 to make him

offer the spares at the same rate as being offered by his competitor. Once the negotiation process

is finished and the two parties involved in the negotiation reach a consensus, the committee's

 purchase proposal/recommendation will be put up to the competent authority for approval and

subsequently the letter of intent may be faxed to the party.

6) Security Deposits: A refundable security deposit may be asked at the time of submission of the

 bid. This deposit is taken to ensure that the vendor who is awarded the contract will not refuse to

undertake the contract. If the bidder after successful bid refuses to undertake the contract, the

earnest money deposited by him will be forfeited. However there arc various instances where thisdeposit may be waived off. For example for all the purchases valued less than Rs 50000/- the

EMD may be waived off. Similarly for the PSUs, NSICs and SSI parties, the EMD can be waived

also. On successful completion of bidding the earnest money may either be returned to the bidder 

or may be adjusted towards the security deposit to be provided by the bidder. Another 

major deposit is in form of performance guarantee or Liquidity damage (LD) the

equipments provided by the vendor fail to perform as per the specification, the cost

for this shortfall may be recovered from the vendor. This guarantee is generally 10% of the

awarded value and is generally in form of bank guarantee. However  in cases of procurement from

OEM/OES or proprietary· vendor the same may be waived depending upon the merit of case.

38

Page 45: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 45/63

However in case of procurement of equipment/material/services there is a contract for 

 providing spares for the next three years. In case the prices of these spare parts goes up in the

future and the vendor refuses to supply the spares at the same rate this guarantee deposit will

 be forfeited. As a matter of fact, this guarantee is taken just to make sure that the contractor 

does not refuse to honor the contract in future after he realizes that the prices have gone up or 

for some similar reasons.

Post Purchase Activities:

Vendor Evaluation:

Once a vendor has supplied some material to NTPC, the vendor is registered with the NTPC

and it is given a performance rating which may be used in future to award of contracts in case of 

limited tender and single tender. This rating system is not very complex but some formulae are

used:

Parameter Measure Weightage

A) Quality Performance Rejection 4

B) Delivery Performance

1. Time schedule Delivery

Ratio of contracted

delivery to actual delivery

in weeks 2

2. Quantity schedule delivery Deviation in qty. 2

C) Commercial and contractual

Pre-post award

 performance 2

Per formance

Calculation of vendor ratings will be done as follows:

Rejected Quantity

a) Quality performance = 1 - * weightage

Supplied Quantity

Contract delivery in week 

 b) 1. Time Schedule = 1 - * Weightage

Actual delivery in week 

QTY received (acceptable)

2. Quantity Schedule = * weightage

39

Page 46: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 46/63

QTY. ordered

Parameter  Min %  Score

Quality 70%

Delivery   50%

Commercial Contractual Terms 50%

On the basis of points scored against each parameter categorization of vendor shall be done as

follows:

Vendor Rating Point Score

a) Outstanding 8 and above

  b) Very Good/Good 6-8

c) Unacceptable less than 6

Indices of performance

A)Adherence to lead-time: Against each purchase order the supplies arc to be affected as per the

declared lead-time with a cushion+I0%. In case the actual lead-time differs  by more than +10%

from the declared lead-time then the total lead time slippage shall be taken into account for rating

calculation.

Declared Lead Time Slippage

RATING =Declared Lead -Time

40

Page 47: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 47/63

B)Extent of Rejection: Supplier as per specification and without rejection should be the

aim of all the purchase executives. But at times the rejection is possible due to non – 

conformance of the specification or performance slippage. Hence a rating system is

developed to take care of that

 

Value of Material Supplied – Value of Material Rejected

RATING =

Value of Material Supplied

B) Budget Compliance: The responsibility of each purchase personnel is to keep the procurement

within the allocated budget. The additional responsibility is in form of maintaining the quality also

at the same time. The rating for budget compliance will be done as follows:

 

Budget allocated– Excess over budget

RATING =

Budget Allocation

And the overall rating will be done on following basis:

Sum of above rating X 100OVERALL RATING =

3

41

Page 48: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 48/63

 

A. INTRODUCTION

Source of Funds

42

Page 49: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 49/63

 National Thermal Power Corporation Ltd. (herein after called 'NTPC' or 'Employer)

intends to finance the Package named in the Bid Data Sheet (BDS), through external

commercial borrowings, internal and other sources.

 NTPC intends to make financing arrangements for the subject package by means of Buyers

Credit from International Banks through the Export Credit Agencies of the country

concerned to the extent the goods and services covered in the package are imported from

OECO countries. For the above purpose the Export Credit Agencies require certain. Procedure

formalities to be completed by the equipment supplier of their country. The bidder shall, in case of 

award of contract, facilitate completion of such formalities as may be required by the respective

export credit agency to enable NTPC to avail Buyers Credit for funding eligible goods and

services covered in the package. The aforesaid option of funding is also intended to be availed by

 NTPC for supply of goods and services from OECD countries by the sub-vendors/sub-contractor 

of the bidder. The bidder shall make similar compliance in respect of its sub-vendors/ sub-

contractors to the extent the goods are imported from concerned OECD country

ELIGIBLE PLANT, EQUIPMENT AND SERVICES

For the purposes of these bidding documents, the word "facilities" means the plant and equipment

to be supplied and installed, together with the services to be carried out by the contractor under 

the contract. The words "plant and equipment,” "installation services," etc., shall be construed in

accordance with the respective definitions given to them in the General Conditions of Contract.

All countries and areas are the eligible source countries for goods and services to be supplied

under this contract and accordingly goods and services to be supplied under this contract may

have their origin in any country and area

For purposes of this clause, "origin" means the place where the plant and equipment or component

 parts thereof are mined, grown, or produced. Plant and equipment are produced when, through

manufacturing, processing or substantial and major assembling of components, a commercially

recognized product results that is substantially different in basic characteristics or in purpose or utility from its components.

The origin of the plant, equipment and services is distinct from the nationality of the Bidder.

BID PRICES

Unless otherwise specified in the Technical Specifications. Bidders shall quote for the entire

facilities on a "single responsibility" basis such that the total bid price covers all the Contractor's

obligations mentioned in or to be reasonably inferred from the bidding documents in respect of the

43

Page 50: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 50/63

design, manufacture, including procurement and subcontracting (if any), delivery, construction,

installation and Completion of the facilities including supply of mandatory spares (if any). This

includes all requirements under the Contractor's responsibilities for testing, pre-commissioning

and commissioning of the facilities and, where so required by the bidding documents, the

acquisition of all permits, approvals and licenses, etc.; the operation, maintenance and training

services and such other items and services as may be specified in the bidding documents, all in

accordance with the requirements of the General Conditions of Contract and Technical

Specification.

Bidders are required to quote the price for the commercial, contractual and technical obligations

outlined in the bidding documents. If a Bidder wishes to make a deviation to the provisions of the

 bidding documents save those listed, such deviations shall be listed in Attachment 6 of its bid.

Bidders shall give a breakdown of the prices in the manner and detail called for in the Price

Schedules. The Bidders shall present their prices in the following manner:

Separate numbered Schedules shall be used for each of the following elements. The total amount

from each Schedule (1 to 4) shall be summarized in a Grand Summary (Schedule 5) giving the

total bid price (s} to be entered in the Bid Form.

Schedule No. 1

Plant· and Equipment including Type Tests charges and Mandatory Spare Parts supplied from

Abroad

Schedule No. 2

Plant and Equipment including Type Tests charges and Mandatory Spare Parts to be manufactured

within Employer's Country

Schedule No. 3

Local Transportation including port handling, port clearance, port charges, Inland transit

Insurance and other local cost incidental to delivery of Plant & Equipment and Mandatory Spares

Schedule No. 4

Installation Services including Erection Works, insurance covers other than inland transit

insurance and other services as specified in the bidding document

44

Page 51: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 51/63

Schedule No. 5 Grand Summary (Schedules Nos. 1 to 4)

Schedule No. 6 Recommended Spare Parts

Schedule No. 7 Taxes and Duties not included in Bid Price

Schedule No. 8A Break up of type test charges quoted in Schedule -1

Schedule No. 8B Break up of type test charges quoted in Schedule -2.

BID SECURITY

The bidder shall furnish, as part of its bid, a bid security in a separate sea/ed envelope in the

amount and currency as stipulated in the Bid Data Sheet

The bid security shall, at the Bidder's option, be in the form of a Banker's cheque irrevocable letter 

of credit or a bank guarantee. , In case of domestic bidders the Bank Guarantee shall be from- a

Bank as specified in the Bid Data Sheets. In case of foreign bidders, the Bank Guarantee can be

from any other bank also in addition to the banks specified in Bid Data Sheet and if the Bank 

Guarantee is from a Bank not specified in the Bid Data Sheet, then the Bank Guarantee shall be

confined by any such Bank as specified in the Bid Data Sheet. The format of the bank guarantee

or letter of credit shall be in accordance with the' form of bid security included in the bidding

documents. Bid security shall remain valid for a period of forty five (45) days.

The bid security shall be furnished in a separate sealed envelope. Any bid not accompanied by an

acceptable bid security, in a separate sealed envelope, shall be rejected by the Employer as being

non-responsive and returned to the Bidder without being opened. The bid security of a joint

venture must be in the name of all the partners in the joint venture submitting the bid.

The bid securities of unsuccessful bidders will be returned as promptly as possible, but not later 

than twenty-eight (28) days after the expiration of the bid Validity period.

THE BID SECURITY MAY BE FORFEITED

(a) If the Bidder withdraws its bid during the period of bid validity specified by the Bidder in

the Bid Form

(b) If the Bidder does not accept the correction of its Bid Price pursuant

45

Page 52: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 52/63

(c) If the Bidder does not withdraw any deviations listed in Anachment-6 at the cost of withdrawal

indicated by him

(d) If the Bidder refuses to withdraw, without any cost to the Employer,

Any deviation not listed in Attachment 6 but found else...where in the bid.

In case of successful bidder, if the bidder fails within the specified time limit

To sign the contract agreement, in accordance with ITB.

To furnish the required performance security in accordance with ITB.

CONVERSION TO SINGLE CURRENCY

To facilitate evaluation and comparison, the Employer will convert all bid prices expressed in the

amounts in various currencies in which the bid price is payable to a single currency. The currency

selected for converting bid prices to a common base for the purpose of evaluation, along with the

source and date of the exchange rate.

TECHNICAL EVALUATION

The Employer will carry out a detailed evaluation of the bids previously determined to be

substantially responsive in order to determine whether the technical aspects are in accordance with

the requirements set forth in the bidding documents. In order to reach such a determination, the

Employer will examine and compare the technical aspects of the bids on the basis of the

information supplied by the bidders, taking into account the following factors:

a) Overall completeness and compliance with the Technical Specifications

And Drawings; deviations from the Technical Specifications as identified in Attachment 6 to the

 bid; suitability of the facilities offered in relation to the environmental and climatic conditions prevailing at the site; and quality, function and operation of any process control concept included

in the bid. The bid that does not meet minimum acceptable standards of completeness, consistency

and detail will be rejected for non-responsiveness.

Achievement of specified performance criteria by the facilities

(c) Type, quantity and long-term availability of mandatory and recommended Spare parts and

maintenance services.

(d) Any other relevant factors, if any, listed in the Bid Data Sheet, or that

46

Page 53: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 53/63

the Employer deems necessary or prudent to take into consideration.

COMMERCIAL EVALUATION

The comparison shall be of the EXW price of domestically manufactured plant and equipment

including Type Test charges and mandatory spares (within the Employer's country), such price to

include all costs as well as duties and taxes paid or payable on components and raw materials

incorporated or to be incorporated in the plant and equipment including mandatory spares plus the

CIF (Indian port-of-entry) price of the plant and equipment including Type Test charges and

mandatory spares named port of destination offered from outside the Employer's country, plus the

cost of local transportation, insurance covers, installation and other services required under the

contract. The Employer's comparison will also include the costs resulting from application of the

evaluation procedures .However, the Price of recommended spare parts quoted in Price Schedule

 No. 6 shall not be considered for evaluation of Bids.

The Employer's evaluation of a bid will take into account, in addition to the bid prices indicated in

Price Schedules Nos.1 through 4 (with summary in Schedule No.5) along with the corrections

 pursuant to ITB , the following costs and factors that will be added to each Bidder's bid price in

the evaluation using pricing information available to the Employer 

(a) The cost of all quantifiable deviations and omissions from contractual and commercial

conditions and the Technical Specifications as identified in Attachment 6 to the Bid.

(b) Compliance with the time schedule to the Form of Contract Agreement and evidenced as

needed in a milestone schedule provided in the bid

(c) The functional guarantees of the facilities offered.

(d) The extra cost of work, services, facilities etc., required to be provided by the Employer or 

third parties.

(e) Price Preference.

FUNCTIONAL GUARANTEES OF THE FACILITIES

(1) Bidders shall state the functional guarantees (e.g. performance,

Efficiency, consumption) of the proposed facilities in response to the Technical Specifications. In

case a minimum (or a maximum, as the case may be) level of functional guarantees is specified in

the Technical Specifications for the bids to be considered responsive, bids offering plant and

47

Page 54: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 54/63

equipment with such functional guarantees less (or more) than the minimum (or maximum)

specified shall be rejected.

2) For the purpose of evaluation, the adjustment specified in the Bid Data Sheet will be added to

the bid price for each drop (or excess) in the responsive functional guarantees offered by the

Bidder, below (or above) either a norm of 100 or the value committed in the responsive bid with

the most performing functional guarantees, as specified in the Bid Data Sheet. The Adjustment

Factors shall be converted to such currency as specified in Bid Data Sheet.

PRICE PREFERENCE

Any adjustments in price that result from the above procedures shall be added, for 

 purposes of comparative evaluation only, to arrive at an "Evaluated Bid Price." Bid prices quoted

 by Bidders shall remain unaltered.

The method of evaluation is illustrated below

ILLUSTRATIVE METHOD OF EVALUATION

Quoted Bid Price without taxes

& Duties (after considering

Arithmetical errors)

ClF price including Type Test charges N1

+ Inland transportation including inland transit

Insurance for equipment and mandatory spares

(b) Ex-works price including

Type Test charges + in- N2

land transportation including

inland transit insurance for 

equipment and mandatory spares

(c) Price for Installation Services N3

(d) Total price N=N1+N2+N3

48

Page 55: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 55/63

Cost compensation

- Technical R 

Cost compensation

- Commercial T

4 Deficiency in mandatory spares V

5 Adjustment works of Functional

Guarantee X

6 Additional work of employer Z1

7 Price preference PP= 0.15 x CIF

CIF value of import content of ex-work price quoted in schedule -2, shall be the value of import

content declared by Bidder in Attachment -9 to bid in respect of plant and equipment including

mandatory spares to be manufactured or fabricated within the Employer’s country and quoted on

Ex-works (India) basis.

8 Evaluated Bid Price EP1= (N+R+T+V+X+Z1+PP)

PRICE PREFERENCE

For granting price preference, the bid price of all bidders shall be increased by fifteen percent

(15%) of the CIF component contained in the bid.

Bidders seeking qualification on the basis of collaboration with manufacturer(s) of particular 

equipment (s) are required to quote the price of such equipment(s) including spares on CIF (Indian

 port-of-entry) basis, if the items are to be imported by the manufacturer or the bidder. In case,

such equipment and spares are not quoted by the bidder on ClF basis, then Employer shall assess

the CIF (Indian port-of-entry) price of such equipment and mandatory spares for the purpose of 

evaluation and the total bid price will be increased by 15% of such assessed CIF price also for the

 purpose of granting price preference.

PERFORMANCE SECURITY

49

Page 56: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 56/63

Within twenty-eight (28) days after receipt of the notification of award, the successful Bidder 

shall furnish. The performance security for ten percent 10% of the Contract Price and in the form

 provided in the section -Forms and Procedures of the bidding documents or in another form

acceptable to the Employer.

In case Joint Deed(s) of Undertaking by the Contractor along with his associate(s)/collaborator(s)

form part of the Contract, then, unconditional Bank Guarantee(s) from such

associate(s)/collaborator(s) for amount(s) specified in Sid Data Sheets shall be furnished within

twenty eight (28) days after Notification of Award. These Bank Guarantees shall be furnished in

the form provided in the section "Forms and Procedures· of the bidding documents and shall be

valid till such period as specified in the corresponding format for Deed of Joint Undertaking.

In case of a successful foreign bidder, if the Employer accepts to enter into the Second Contract

and I or Third Contract with the Assignee, pursuant to ITS Sub-Clause 28.4 above, then, within

twenty eight (28) days after Notification of Award, assignee shall furnish additional performance

security for ten percent (10%) of the value of the Contract entered into with assignee and the form

 provided in the section "Forms and Procedures· of the bidding documents.

5. SPARE PARTS PROCUREMENT

Most or the NTPC procurements are related to equipment. On an average the average economic

life of a NTPC owned plant is considered to be 25 years and depreciation is taken into account

considering these 25 years. Hence during the life lime of the equipment it will definitely require

spares as well as some consumables. Hence NTPC has incorporated a clause in the Bid

Documents issued to the bidders called SPARE PARTS. This clause has three sub clauses that take

care of different types of spare pans required during the lifetime of the plant

If NTPC finds -that certain spare parts are mandatory for the plant operation, it specifies so in the

Technical specification. In such cases, the item wise price breakdown of such spares on a ClF

(India Port)/Ex Work's (India) basis is to be included in the bid by the bidder. However these prices will be free form escalation and should be indicated separately. The prices of spare parts

shall also come into picture while evaluating the bid. During the six months starting from signing

the contract, NTPC will have the right to increase or decrease the number of spare parts to be

  procured. In addition, the bidder may by his own experience provide a complete list of 

recommended spare parts for an operational period of three (3) years for the equipment supplied.

"The list should be complete providing the details of how many of the suggested spare parts are

 present in the equipment supplied as well as their expected operational life. The bidder shall

further indicate item wise price break-up on for site basis. The prices quoted in the list shall be

valid without any escalation for a period of not less than six (6) months after the placement of 

order for Power Plant Turnkey Equipment Basis. But this additional recommended spare parts list

50

Page 57: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 57/63

will not be taken into consideration while evaluating the bid. However a specific clause in the

General Condition of Contract makes the supplier provide a list of addresses of all the sub-

supplier who provide the spare parts. The clause is "The Contractor will provide the Owner with

all the addresses and particulars of his sub-suppliers while placing the order on vendors for 

items/components/equipment covered under the Contract and will further ensure with his vendors

that the owner, if so desires, will have the right to place orders for spares directly on them on

mutually agreed terms based on offers of such vendors.

In addition, to cater to any exigency arising during the start-up and initial Operation stages up to

the satisfactory completion of Trial Operations due to enfant mortality of 

items/components/consumable hardware, the bidder shall at his own cost shall arrange and

maintain an inventory of such items so as not to have any major interruptions during the period

from start up to Trial Operations.

PROCUREMENT OF FOREIGN SPARE PARTS

Many of the plants of NTPC are manufactured by foreign manufacturer. Hence during the lifetime

of the equipment, it may require many spares parts and consumables. But to acquire these spare

 parts .there is no specific method followed by NTPC. However in such a case the list of 

authorized agents of manufacturer producing the parts is obtained from the manufacturer itself. If 

the listed dealer is only supplier of manufacturer, the procurement is made through single tender 

.Else a normal procurement procedure is followed.

For example a plant monitoring equipment was in need of batteries and a connecting cable. Both

the items were proprietary in nature and the firm had only one authorized dealer providing the

required material. Hence the dealer was issued a single tender for supplying the required spares.

Similarly in case of a Diesel Generator Set which was manufactured by a US firm had only one

authorized service provider in the locality and hence a price list for the components used in the

DG Set was acquired from the manufacturer and the contract was awarded to the sole service

 provider. In case of bigger value spare parts a three year supply of the spare parts is guaranteed by

the supplier at the time of supplying the equipment and for further requirement of the spares the

vendor may be contacted or a global tender may be issued high value spares not manufactured byany Indian firm or being imported by an Indian firm.

However the payments for both the types of spares will be made in following manner,

Upon dispatch and against invoices and shipping documents :75%

On receipt and storage at Site on physical verification by the engineer: 25%

6. PAYMENTS:

Payment is the most important term for any contract. Hence the General Condition of Contract

deals the terms of payment. There arc various sub clauses to this clause. The first clause deals

51

Page 58: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 58/63

with the currency of payment. The clause specifically mentions that “the Contract Price shall be

 paid in the currency or currencies in which the various price components have been stated and as

incorporated in the Contract”. Once the currency is settled and accepted by both parties, the due

date for the payment must be decided in advance. The payment is generally made in parts. Once

the contract is awarded, an Initial Advance payment is made to the Contractor and afterwards

 payments against dispatch, progressive completion of works and then a final payment is made to

the contractor. Whenever a payment has to be made it is divided into two parts (if applicable), the

Indian Rupee component and foreign currency component. The due date for initial foreign

currency component for the advance payment is 60 days from the award of the contract and 30

days for the Indian rupee component. The Initial Advance payment is done automatically however 

the payments against dispatch and payments against partial work completion are made after the

contractor applies for it. Once the contractor applies for payments, the validity of the application

is checked and the invoices or completion report by the engineer is sought. This report is known

as Interim Payment Certificate and it certifies the value of the contract executed till the date of 

completion. However if any part of the work completed docs not comply with the Contract or has

 been done prematurely according to the master schedule provided at the time of the contract, the

 NTPC shall not pay for that part of the work.

MODE OF PAYMENT: All the payment on the dispatch will be made in form of Letter Of Credit

(L/C) in favor of the contractor. The issue of Letter of Credit shall be valid for a period of three

months from the date of issue. The utilization of this L/C however is sole responsibility of the

contractor. Once the good is received at the site and possession is taken by NTPC only then the

 payment will be made to contractor’s Banker through Owner’s bank.

The payment for advance, Taxes and duties inland transportation, insurance and erection portion

of works and Type test charges (if any) will be directly made to contractor.

PART PAYMENT: - When NTPC agrees to pay the contractor in part with each additional phase

of plant completion, or each new lot of equipments/ material received follows a payment schedule

and regulation to make the payment. This schedule is arrived at by analyzing the various

component required in the delivery of the equipment / material received or dispatched or it may

issue at advance made to contractors supplies for the procurement of the equipment/material.For analysis purpose we have taken the schedule that has been used for TANDA Thermal Power 

Station.

  NATURE OF

PAYMENT

% OF TOTAL EX-

WORK PRICE OF

EQUIPMENT

% OF EX-WORK 

PRICE ON PRO-

RATA BASIS

CONDITION OF

PAYMENT

52

Page 59: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 59/63

a) Initial Advance

  b) Pro-rata payment

against dispatches

c) Pro-rata payment on

item received

d) On successful

completion of  

  performance and

guarantee test

10%

------------------

--------------------

10%

-------------------

60%

20%

-------------------

In ref. to GCC

On producing

invoice and

satisfactoryevidence.

Physical variation &

certificate by

Engineer of test

results.

7. ESCALATION FACTORS:

Escalation factors or Contract Price Adjustment is an Endeavor to protect the interest of the

contractor as well as that of NTPC. The escalation factor is a derived value by which the prices of 

materials vary or may vary on some date in future. The clause is a very detailed. Clause andcovers every aspect of the price.

For the price adjustment purposes, only following components will be considered.

Ex-factory price for the equipment / material for the Indian origin and FOB price component for 

the equipment / material of non-Indian origin (excluding spares) subject to ceiling of 20%. In case

of Indian contractor, for any equipment / material etc. imported by him for the purpose of 

 performance of the contract, which is dispatched directly from the port of disembarkation to the

site the words “ ex-factory price” shall be deemed to mean the price of equipment / material as it

is dispatched from the port of disembarkation to the project site.

2 ERECTION COMPONENT

For the escalation of price in case of equipment / material, all the ex-factory prices will be

fragmented as Fixed Portion of price and the variable portion of the price .The variable portion of 

 price, assume to fluctuate with the changing labor and material indices. The indices are obtained

from the list of industrial Indices published by the Ministry of Industries, Ministry of Labor and

53

Page 60: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 60/63

the Office of the Economic Adviser, Govt. of India. Labour Bureau, Simla, publishes the labour 

index or Consumer Price Index for Industrial Workers whereas the Economic Adviser of the Govt.

of India publishes the Material Index, or Index no of wholesale price under group "All

Commodities".

8. ARBITRATION

Despite all the care taken and all the irregularities avoided there are times when the relationship

 between the supplier and purchaser becomes bitter. In that case to avoid any legal complications a

set of arbitration rules are laid down and agreed upon in advance. These rules are indisputable and

are accepted by both the parties. Some of the important arbitration clauses are mentioned here.

1) In the event of any query, dispute or difference whatsoever arising under this contract or in

connection with any question relating to existence, meaning and interpretation of [his contract or 

any alleged breach thereof, the same will be referred to the sole arbitrator of the General Manager 

of the NTPC or to a person appointed by him for the purpose. The arbitration shall be conducted

in accordance will the provisions of Indian Arbitration Reconciliation Act, 1996

2) It will be no objection that the Arbitrator is an interested person and/or that he had to deal with

the matters to which the contract relates and/or in the course of his duties he expressed any view

on any mutter in dispute. The award of arbitrator shall be final and binding.

3) In the event of Arbitrator dying, neglecting, resigning or being unable to act for any reason or 

his award being set aside by the court for any reason, it will lawful for the General Manager of the

 NTPC to appoint another Arbitrator in place of the outgoing Arbitrator.

4) It is further terms of this agreement that no person other than the person shall act as an

Arbitrator and that, if for any reason that is not possible, the matter should not be referred to

arbitration at all.

5) The Arbitrator may from time to time, with the consent of nil parties enlarge the time ill makingthe award.

6) The cost incidental to the arbitration shall be at the discretion of the Arbitrator; the arbitration

shall be conducted in NEW DELHI or at such other places where arbitrator may decide.

7) Not withstanding any dispute between the parties Supplier shall not be entitled to withhold

delay or defer his obligation under the contract and same shall be carried out strictly in accordance

with terms and condition of contract.

54

Page 61: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 61/63

8) In the event of dispute or difference arising between parties the public sector enterprise and

Government, the provision of BPE office memorandum No BPE/GL001/76/MAN/2110-75-BPE

(GML-1) dated 1st January 1976 shall be applicable.

Conclusion

Purchase management activities at NTPC are one of the most vital activities undertaken by

the Rs.18000 Cr power giant of India. The process followed by NTPC is very objective in

nature and employs a very short term relationship with its supplier. The system tries to

take advantage of the competition in the field of heavy engineering where foreign

manufacturers like MHI, GE etc. are competing with Indian manufacturers like BHEL and

L&T. NTPC being a public sector company, to be free from nepotism and favouritism has

adopted a system where transparency and automation is at its utmost level. Transparency

was achieved by a multi member team and sealed tenders where no one knows in advance

the quotation offered by a particular bidder. Automation here signifies that almost all thecontracts are awarded following the same procedures, by awarding the contract to the

lowest bidder that is L1 without much consideration.

Together they constitute a very reliable and corruption free system. At times it seems that

the system is capable of saving lots of money of NTPC but in most of the cases the cost of 

maintaining the system itself combined with the poor responsiveness amounts to a lower 

level of efficiency. In today’s world of cutthroat competition only those firm are going to

survive who are committed to efficiency, as it were their core competency. Cost must be

reduced by means of optimum utilisation of resources and channelled into more profitable

55

Page 62: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 62/63

segments. It is an established fact that on operational level NTPC is one of the world’s

most efficiently run organisation.

Benefits can not be evaluated in isolation as there are certain features very unique to the

kind of domain NTPC is into. As we have discussed earlier that most of the item except

coal and gas have a very infrequent and unpredictable demand. This means that NTPC cannot anticipate its demand in advance and hence going into a long term supply contract is

very difficult. For some procurement which actually constitutes more than 70% of non fuel

 procurement, the items are manufactured to order. In these cases even the manufacturer is

not sure of the future price and availability of the equipment and hence going into a long-

term contract based on current prices may do more harm than benefits. Another factor 

which must be understood is that there are very few companies which are into

manufacturing of the kind of equipments or material required by NTPC. And since the

fixed capital employed by these firms are huge, many a times they offer huge discounts

 just to acquire a particular order so that they can fulfil some of their targets. NTPC has

witnessed one such offer in past where a substantial discount was offered by a vendor on

the condition that the contract should be awarded to him in a specific time period

mentioned by the manufacturer. These benefits could not have been availed by NTPC had

it been in a long-term relationship with a particular manufacturer.

References:

1. Purchase Management System Manuel, 2nd Edition, NTPC, New Delhi.

2. Delegation of Power Handbook, NTPC, New Delhi.

3. ANNUAL REPORT OF NTPC.

56

Page 63: CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

8/14/2019 CONTRACT & PROCUREMENT MANAGEMENT REPORT NTPC

http://slidepdf.com/reader/full/contract-procurement-management-report-ntpc 63/63

4. www.ntpc.co.in

5. www.power.alstom.com

6.www.ntpceoc.com

7.www.powermin.nic.in

8.www.edf.fr