DRAFT 19 Aug 2020 1(49) ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT dated [date] NORCEM AS and Norcem Plant Modifications Contractor regarding Norcem Cement Plant modifications for full-scale carbon capture APPENDIX A SCOPE OF WORK

ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

  • Upload
    others

  • View
    21

  • Download
    1

Embed Size (px)

Citation preview

Page 1: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 1(49)

ENGINEERING, PROCUREMENT AND CONSTRUCTION

CONTRACT

dated [date]

NORCEM AS

and

Norcem Plant Modifications Contractor

regarding

Norcem Cement Plant modifications for full-scale carbon capture

APPENDIX A SCOPE OF WORK

Page 2: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 2(49)

Table of Contents

1. INTRODUCTION .................................................................................................................... 5

1.1 Definitions ...................................................................................................................... 5

2. PROJECT OVERVIEW ........................................................................................................... 8

2.1 General ........................................................................................................................... 8

2.1.1 Plant Description ................................................................................................. 8

2.1.2 Project Execution ................................................................................................. 9

2.1.3 Run-in period and normal operation .................................................................. 10

2.2 Location and access ..................................................................................................... 11

3. SCOPE OF WORK ................................................................................................................ 12

3.1 General ......................................................................................................................... 12

3.2 Contract Object ............................................................................................................ 12

3.2.1 Modification of existing flue gas system, category (a) ...................................... 12

3.2.2 New tie-ins, ducts, fans, dampers, etc needed to connect the waste heat recovery units and

the carbon capture plant to the existing flue gas system, category (b) .............. 16

3.3 Interfaces, battery limits and scope of work splits ....................................................... 22

3.3.1 Introduction ....................................................................................................... 22

3.3.2 Norcem Plant ..................................................................................................... 23

3.3.3 CCC plant, including waste heat recovery ......................................................... 23

3.4 Plant Operability .......................................................................................................... 26

3.5 HSE Management ........................................................................................................ 26

3.6 Project Management and Administration .................................................................... 27

3.6.1 Project Management Plan .................................................................................. 27

3.6.2 Scope Management ............................................................................................ 27

3.6.3 Interface Management ....................................................................................... 27

3.6.4 Schedule Management ....................................................................................... 28

3.6.5 Cost Management .............................................................................................. 28

3.6.6 Quality Management ......................................................................................... 28

3.6.7 Project Organisation and Resource Management .............................................. 29

3.6.8 Project Communication ..................................................................................... 29

3.6.9 Risk Management .............................................................................................. 29

3.6.10 Change and Issue Management ......................................................................... 29

3.6.11 Benefits Realisation and Knowledge Sharing ................................................... 29

3.6.12 Document Management ..................................................................................... 29

Page 3: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 3(49)

3.7 Engineering .................................................................................................................. 30

3.7.1 General ............................................................................................................... 30

3.7.2 HSE in Design ................................................................................................... 31

3.7.3 Process ............................................................................................................... 32

3.7.4 Mechanical ......................................................................................................... 33

3.7.5 Structural Engineering ....................................................................................... 33

3.7.6 Piping and Layout .............................................................................................. 33

3.7.7 Electrical ............................................................................................................ 34

3.7.8 Instrumentation and Automation ....................................................................... 35

3.7.9 Materials, Surface Protection and Insulation ..................................................... 35

3.7.10 Surface protection and insulation ...................................................................... 36

3.7.11 Studies ............................................................................................................... 36

3.7.12 Engineering for Construction ............................................................................ 36

3.7.13 Engineering for Operations and Maintenance ................................................... 37

3.8 Procurement and Fabrication ....................................................................................... 38

3.8.1 Procurement ....................................................................................................... 38

3.8.2 Fabrication ......................................................................................................... 39

3.8.3 Pressure Equipment Directive (PED) ................................................................ 39

3.9 Packaging and Transportation ...................................................................................... 40

3.10 Construction and Installation at Company´s Site ......................................................... 40

3.10.1 Temporary Facilities and Services ..................................................................... 40

3.10.2 Construction Work by Disciplines ..................................................................... 41

3.11 Mechanical Completion (MC) ..................................................................................... 42

3.11.1 Preservation ....................................................................................................... 42

3.12 Mechanical Completion Protocol ................................................................................. 43

3.13 Commissioning Assistance .......................................................................................... 43

3.14 Plant Start-up, Performance Testing and Acceptance Test .......................................... 43

3.14.1 Plant start-up ...................................................................................................... 43

3.14.2 Performance Demonstration Period ................................................................... 44

3.14.3 Performance testing ........................................................................................... 44

3.15 Completion Certificate ................................................................................................. 45

3.16 Provision of Spare Parts ............................................................................................... 45

3.17 Documentation ............................................................................................................. 46

3.17.1 As-Built Documentation .................................................................................... 46

4. OPTIONS ............................................................................................................................... 47

Page 4: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 4(49)

4.1 Assistance in Run-in Period ......................................................................................... 47

5. ATTACHMENTS .................................................................................................................. 48

6. REFERENCES ....................................................................................................................... 49

Page 5: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 5(49)

1. INTRODUCTION

1.1 Definitions

The definitions included in the Conditions of Contract are also applicable to this Appendix.

Additional to the main Conditions of Contract definitions, the definitions in Table 1 and Table 2 apply

(whereas it is noted that certain other defined terms are spread throughout this Appendix):

Table 1: Definitions

Item Definition

Acceptance Test Such performance test that is to be performed of the completed CCS

Facility, as described in Section 3.15.3 below.

Commissioning Such process, which is to be determined by Company during the Contract

Period in consultation with Contractor, following Mechanical Completion and

Delivery, including (i) assuring that all systems and components of the CCS

Facility are designed, installed, tested, operated, and maintained according to

Company’s operational requirements, (ii) “cold” commissioning in applicable

parts, i.e. start-up, running and testing of applicable individual parts of the CCS

Facility on a stand-alone basis, (iii) “hot” commissioning, i.e. setting-to-work;

regulation (testing and adjusting/optimisation repetitively) to achieve the

designed performance and operation; calibration, setting up and testing of the

associated automatic control systems (including HMI); and recording of the

system settings, and (iv) all activities required to ramp-up the CCS Facility for

Performance Demonstration under normal operating conditions.

Factory Acceptance Test (FAT) Formal testing at the relevant manufacturing site conducted to determine

whether a system satisfies the acceptance criteria (specifications and other

contract requirements) to determine whether the system is ready for delivery.

This may involve chemical tests, physical tests, or performance tests and shall

include verification in accordance with applicable industrial standards, or if no

industrial standards exist, market practice.

High priority punch list items High priority punch list items from Mechanical Completion, listing work not

conforming to the Contract, defined by Company to be high priority, which

Contractor must complete prior to start of Commissioning.

Human Machine Interface (HMI) The graphical user interface between control room operators (humans) and

control system hardware (machines).

Mechanical Completion

(Mechanically Complete, MC)

Mechanical Completion (MC) shall for the purpose of the Work and the

Contract mean a level of completion where it has been established to

Company’s satisfaction that the following conditions are fulfilled with respect

to the Contract Object and each unit, system, phase, component or item

thereof.

(i) Contractor has completed all procurement, fabrication, assembly,

erection and installation activities, including the setting and

assembly on all foundations and connections or installation with

piping.

Page 6: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 6(49)

Item Definition

(ii) for pre-assembled procurement packages, skids and modules

delivered fully wired; wiring and safety systems are also

included.

(iii) pre-commissioning and testing as per manufacturing or

fabrication instructions, pressure test and other tests, except as

agreed by Company as necessary to perform after completion of

relevant electro, instrumentation and automation work

(iv) all parts of the Contract Object have been individually cleaned,

leak checked, aligned, calibrated, lubricated, pressure tested and

line checked (continuity check)

(v) the Contract Object is in a status that allows commencement of

Commissioning and initial operation of the Contract Object in a

safe and reliable manner.

(vi) the Mechanical Completion checklist prepared by Company has

been finalised.

(vii) Company has issued Mechanical Completion certificate(s) for the

entire Contract Object.

(viii) High priority punch list items have been completed.

Site Acceptance Test (SAT) Formal testing at Company’s site conducted to determine whether a system

satisfies the acceptance criteria (specifications and other contract requirements)

to determine whether to accept the system. This may involve chemical tests,

physical tests, or performance tests.

Work Package 01 (WP01) This work package consists of any and all Work required for the completion of

the following elements of the Contract Object, to be installed during Winter

Repair 2022 :

▪ Hovedventilator 1 (HV1) including ducts replacement

▪ Electro Static Precipitator 3 (ESP3)

▪ Gas Conditioning Tower 1 & 2 upgrade

▪ Electro Static Precipitator 4 (ESP4)

Work Package 02 (WP02) This work package consists of any and all Work required for the completion of

the following elements of the Contract Object, to be installed during Winter

Repair 2023:

▪ Tie-In to existing duct/equipment

▪ Dampers/covers for tie-in points

▪ Powdered Activated Carbon (PAC) storage and injection

▪ Hovedventilator 2 (HV2) including ducts replacement

Work Package 03 (WP03) Any and all Work required for the completion of the Contract Object in

accordance with the Contract that is not included in WP01 or WP02

Table 2: Abbreviations

Abbreviation Definitions

CCC Carbon Capture and Conditioning

Page 7: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 7(49)

Abbreviation Definitions

ESP Electro Static Precipitator

FF Fabric Filter

GCT Gas Conditioning Tower

GSA Gas Suspension Absorption

HV Hovedventilator (ID fan)

VSD Variable Speed Drive

WHRB Waste Heat Recovery Boiler

WHRU Waste Heat Recovery Unit

Page 8: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 8(49)

2. PROJECT OVERVIEW

2.1 General

2.1.1 Plant Description

The Project will detail the design, build and commission a carbon capture and conditioning plant capturing

CO2 from the flue gas from Norcem’s cement production plant in Brevik, Norway and conditioning it for

ship transportation and permanent storage below the sea bed on the Norwegian continental shelf within the

Northern Lights Project.

The carbon capture and conditioning plant shall have a design capacity of 55 tons liquid CO2 / hour, and the

target CO2 capture rate is 400 000 tons CO2 / year. The yearly CO2 capture capacity is based on available

waste heat (thermic energy) recovered from existing cement process and from the capture and conditioning

process itself. As a result, only electricity and no additional heat or fuels are required for CO2 capture.

The carbon capture and conditioning plant will be installed in parallel to the existing flue gas system with

focus on safe, easy and smooth changeover between cement production with and without carbon capture and

heat recovery thus securing the integrity of the cement production.

To integrate the carbon capture and conditioning plant with the existing cement plant, some modifications to

the existing cement plant are needed. The Contract Object, specified in section 3.2, comprises the necessary

modifications of the existing flue gas system due to modified operating conditions and new tie-ins, ducts,

fans, dampers, etc. needed to connect the waste heat recovery units and the carbon capture plant to the flue

gas system.

The Contract Object shall satisfy the requirements described in Norcem’s Overall Design Basis for the CCS

Project. The Contract Object shall with the exception of wear and tear parts have a technical design life of 25

years.

The elements of the CCS Facility can be divided into the following main categories:

▪ Carbon capture, conditioning, intermediate storage and loading (not Contractor’s scope)

▪ Waste heat recovery from existing cement production process (not Contractor’s scope)

▪ Modifications of existing flue gas system (Contract Object)

▪ Utility systems (split scope)

▪ Civil works (not Contractor’s scope)

Contractor is the EPC contractor for the necessary modifications of the existing flue gas system.

A 3D view of the complete new plant from the project 3D BIM model is shown in Figure 1 below. The

coloured elements are new, while the grey elements are part of the existing cement plant.

Page 9: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 9(49)

Figure 1: 3D view of the complete new plant

The transportation and storage of the captured CO2 is outside the scope of Company and will be managed

through the Northern Lights Project.

2.1.2 Project Execution

The main project execution phases are shown in Figure 2 below:

Figure 2: Main project execution phases

The main activities and deliverables included in these phases are described in the following subsections.

Detailed Engineering

The Detailed Engineering phase includes detailed engineering of the complete CCS Facility at the Site.

The deliverables from this phase are documentation of the complete plant design as required for procurement

and construction.

Procurement

The Procurement phase includes procurement, manufacturing, Factory Acceptance Testing (FAT) and

transportation from manufacturers site to the Site or, as the case may be, pre-fabrication site.

The deliverables from this phase are complete equipment packages and construction materials needed for

construction of the complete CCS Facility.

Construction

The Construction phase includes pre-fabrication, fabrication, installation and assembly, testing and

Mechanical Completion.

Detailed Engineering

Procurement Construction CommissioningPerformance

Demonstration

Page 10: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 10(49)

The end deliverable from this phase is the complete CCS Facility ready for commissioning

Commissioning

The commissioning phase comprises cold and hot system testing of the complete CCS Facility.

Contractor’s scope is to provide commissioning assistance and support to Company.

The main deliverable from this phase is the complete CCS Facility ready for start-up and performance

testing.

Performance Demonstration

After Mechanical Completion and commissioning, performance demonstration of the complete CCS Facility

is performed.

In this phase Acceptance Test of the plant shall be performed. The purpose of the Acceptance Test is to

demonstrate that the Contract Object functions in accordance with the Contract. The Acceptance Test is

subject to approval by the Company.

The main deliverable from this phase is documentation of confirmed completion of the Acceptance Test.

Contractor’s scope is to provide assistance and support to Company during performance demonstration and

Acceptance Test.

2.1.3 Run-in period and normal operation

Upon approval of the Acceptance Test, by issue of Completion Confirmation, the CCS Facility is in

operation and the Operating Period commences. The Operating Period begins with a one (1) year run-in

period followed by the regular Operating Period, as shown in Figure 3 below:

Figure 3: Plant operations phases

The main activities included in these phases are described below.

Run-in period

The run-in period commences upon Completion Confirmation and expires one (1) year thereafter. Stable

operation of the complete CCS Facility shall be obtained by the end of this phase.

In this phase Run-in Test of the plant shall be performed. The purpose of the Run-in Test is to demonstrate

that the Contract Object functions in accordance with the Contract. The Run-in Test is subject to approval by

Company.

The main deliverable from this phase is documentation of confirmed completion of the Run-in Test.

Run-in period Operation

Page 11: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 11(49)

Contractor shall provide assistance and support to Company during Run-in period and Run-in Test upon

Company’s request.

Operation

Following the run-in period, the complete CCS Facility is expected to be in regular stable operation, in

accordance with Article 23.1 and 23.5 of the Conditions of Contract. In this phase, further optimisation of

Contract Object operations may be performed.

Contractor shall provide assistance and support to Company during operation upon Company’s request.

2.2 Location and access

The Cement Plant in Brevik is located approximately 165 km south west of Oslo and located on the far end

of Eidanger peninsula (Address: Setrevegen 2, 3950 Brevik).

The complete plant is located within Norcem’s property in Brevik, with three exceptions:

▪ The ship loading quay for CO2 export, located at “Kastolkaia”

▪ The main grid station, which will be upgraded to handle the increased power demands

▪ The CO2 storage tanks, which are partly located within Tangen Eiendom’s area

Access to the Site and transportation of goods to the site can be with road trucks or by sea vessels. Access

conditions are further detailed below and in Appendices E and F.

The quay for off-loading of heavy equipment arriving by sea will be the “Cementine quay”. The quay will be

upgraded by Company as a part of the project. Bulk and smaller components arriving by sea may also be

unloaded over this quay. Information on load bearing capacity and other quay features (access, water depth,

load bearing capability, dimensions) for the Cementine quay is provided in Appendix F.

Internal site transport from quay side can be performed by using ordinary flat truck transporters or fork lifts

for minor or less heavy equipment. For more heavy and large equipment, the use of Self Propelled Multi-

Wheel Trailers (SPMT) can be used.

The transportation vessel type must be considered wrt. specific quay features (access, water depth, load

bearing capability, dimensions) .

Page 12: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 12(49)

3. SCOPE OF WORK

3.1 General

The Contractor shall perform detail engineering, procurement and construction including pre-fabrication,

fabrication, installation and assembly, testing and Mechanical Completion of the Contract Object. Contractor

shall also perform required assistance and support to the Company during commissioning, start-up,

performance demonstration, Acceptance Tests, training and the Run-in period.

The description of work presented in this Appendix A is solely intended to enable the principle elements of

the Work to be identified. The description does not present exhaustive details of each activity required to

complete the Work and must be read in conjunction with all the Appendices, documents and attachments

within this Contract.

The Work shall be performed in accordance with Appendix E.

Contractor shall perform further detail engineering based upon Company’s Documents in Appendix E and

produce the necessary documentation and deliverables for procurement, construction, mechanical

completion, commissioning and operation of the Contract Object.

The Work shall be deemed to include any and all works, services, activities, materials, construction

machinery aids, auxiliaries, media and other items that are required in order to commission and complete the

Work and the Contract Object, with the sole exception of such works that shall be performed by Company in

accordance with the explicit terms of the Contract.

3.2 Contract Object

Contractor’s scope of work can be divided into the following main categories:

a) Modification of existing flue gas system due to modified operating conditions

b) New tie-ins, ducts, fans, dampers, etc needed to connect the waste heat recovery units and the carbon

capture plant to the flue gas system

The plant design is shown in the project 3D CAD model (Ref. 4).

Contractor’s scope of work includes all equipment and services required for both category (a) and (b). These

are described in the following sub-sections, and detailed in Appendix E and I.

The detailed design shall be according to the Overall Design Basis (Ref. 1). Flue gas design data are

provided in (2). Detailed technical specifications are provided in (Ref. 3).

3.2.1 Modification of existing flue gas system, category (a)

This category comprises all elements in the existing flue gas system which must be modified or replaced to

integrate the CCC plant and waste heat recovery systems, and to meet the new operating conditions. These

elements are described in more detail in the following subsections.

Gas Conditioning Towers string 1 and 2 (GCT 1 and 2)

The Gas Conditioning Towers (GCTs) shall be modified to serve new operating conditions.

Page 13: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 13(49)

To obtain maximum heat recovery from the flue gas, the GCT outlet temperature shall be kept stable and as

high as feasible with regards to downstream equipment. To achieve this, the GCTs shall operate with a

variable cooling service (water spray) based on variable incoming preheater gas temperatures in the range of

375-450°C providing a stable outlet temperature of approx. 375°C.

The cooling service (water spray) must be able to react immediately to changes in inlet gas temperature to

the GCTs to maintain the maximum allowable inlet temperature to downstream equipment. The cooling

water lances and nozzles must be protected against clogging, due to heavy dust load in the GCTs when not in

use, or when in use on less than maximum service.

The GCT’s must be able to operate also during current operational conditions without CCS plant (or heat

recovery units) in operation.

GCT1 and GCT2 dimensions are provided in Table 3: GCT1 and GCT2 dimensions

below.

Table 3: GCT1 and GCT2 dimensions

Dimension GCT1 GCT2

Diameter (m) 6,500 6,000

Height, cylindrical (m) 23,070 26,000

Height, inlet cone (m) 5,770 6,000

Height, outlet cone (m) 5,255 4,450

Internals Distribution bars in inlet Distribution plate in inlet

Contractor’s scope of work includes supply of all equipment and services required for upgrading of the water

spray system to handle new operating conditions and rapid changes in duty including gas distribution screens

if required.

Contractor shall supply the following main components:

▪ Water spray nozzle arrangement to be fitted on GCT1 and -2

▪ Water pumps, piping and instrumentation as required

The modification of the GCT’s must be executed during annual winter repairs with duration of 21 days from

production to production in accordance with Appendix C.

Main flue gas fans / Hovedventilator string 1 and 2 (HV1 and HV2)

The main flue gas fans shall be replaced to serve new operating conditions (higher flue gas temperatures).

The fans with electric motors shall be equal in size and model and of centrifugal type with one impeller

between bearings. The electric motors shall have a normal speed of approximately 1000 rpm and be

controlled by variable speed drives (VSD).

The HV1 and HV2 fans and electric motors shall be dimensioned based on the technical specifications in

(Ref. 3).

Equal size shall be targeted for HV1 and HV2 housing, impeller and other internals and for electric motors to

minimise spare part inventory and ease maintenance.

Page 14: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 14(49)

In addition to all conditions and specifications defined herein, the fans shall be supplied in accordance with

HeidelbergCement’s Mechanical DCS “Process Fans” (Ref .6).

The fan housings and internals shall be of materials suitable for the described service, and the fans shall be

insulated with 100 mm mineral wool covered with cladding plate designed, supplied and installed in

accordance with HeidelbergCement’s Mechanical DCS “Thermal Insulation”, (Ref .7). Due to very abrasive

dust containing quartz particles, impeller and housing must be made in wear resistant materials (hard face

welding).

The electric motors shall operate on IT 3x690V 50Hz.

Maximum continuous operating temperature for the downstream Electro Static Precipitators (ESPs) are

400°C.

Contractor’s scope of work includes supply of all equipment and services required for replacing the existing

HV1 and HV2 fans including electric motors and instrumentation. VSDs shall be provided by Contractor.

Contractor shall supply the following main components:

▪ Centrifugal fans HV1 and HV2 with el. motors

▪ Common base frame

▪ Instrumentation

The modification of HV1 and HV2 must be executed during annual winter repairs with duration of 21 days

from production to production in accordance with Appendix C.

Electro Static Precipitator / El. Filter string 1 and 2 (ESP4 and ESP3)

ESP3 and ESP4 shall be modified to ensure adequate reduction in the flue gas dust load, to reduce the risk of

fouling in the downstream Waste Heat Recovery Units (WHRUs).

Both ESPs shall be upgraded to meet a dust outlet requirement of 0,1 g/Nm3.

ESP 3 shall be upgraded with a third electrical field as well an extension in height, and a new fast reacting

high voltage controller. ESP 4 shall be upgraded with a new fast reacting high voltage controller.

Contractor’s scope of work includes supply of all equipment and services required for upgrading ESP3 and

ESP4 to meet the required outlet dust concentration.

All modifications of the existing ESPs shall be insulated with mineral wool covered with cladding plate

designed, supplied and installed in accordance with HeidelbergCement’s Mechanical DCS “Thermal

Insulation” (Ref .7).

Contractor shall supply the following main components:

▪ New ESP3 sections to meet the required volume, cross section area and collector area for adequate

dust handling

▪ Fast reacting high voltage controllers for ESP3 and ESP4

The modification of ESP 3 and ESP4 must be executed during annual winter repairs with duration of 21 days

from production to production in accordance with Appendix C.

Page 15: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 15(49)

Gas Suspension Absorption string 1 (GSA)

No modifications on the flue gas side of the GSA are required as the future process conditions are within the

original design values. The GSA water injection system, supplying the GSA with spray water and diluting

water for lime, shall however be upgraded to utilise process water from the CCC plant (DCC bleed and

EWTP filter reject) for dilution purposes, thus reducing the consumption of potable water.

Contractor’s scope of work includes supply of all equipment and services required for upgrading the GSA

water injection system to utilise process water from the CCC plant (DCC bleed and EWTP filter reject) for

dilution purposes.

Contractor shall supply the following main components:

▪ Piping and valves as required

Fabric Filter/ Bag filter string 1 (FF1)

No modifications on the flue gas side of FF1 are foreseen to be required due to future operating conditions.

The FF1 dust handling system shall however be modified, as this dust will no longer be returned to the

cement process due to its possible content of dioxin, mercury and activated carbon. This dust shall be

extracted to a new big-bag loading system for further disposal.

Contractor’s scope of work includes supply of all equipment and services required for modification of the

FF1 dust handling system and installation of a big bag loading system.

Contractor shall supply the following main components:

▪ Screw conveyors, diverter gates and interconnecting chutes as required.

▪ Big bag loading system, including instrumentation, structures and access equipment as required

All screw conveyors shall be designed, supplied and installed in accordance with HeidelbergCement’s

Mechanical DCS “Screw Conveyor” (Ref .8).

Fabric Filter/ Bag filter string 2 (FF2)

The FF2 internal bypass shall be upgraded to react faster, for additional high temperature protection of the

filter.

Contractor’s scope of work includes supply of all equipment and services required for modifying the existing

internal flue gas bypass on the FF2 to a fast (1 second) reacting unit, including replacing the existing plate

damper and actuator.

Contractor shall supply the following main components:

▪ Fast reacting (1 second) internal bypass

Stack no. 3

This stack currently in use for flue gas from string 1. Its operation will be replaced by the new stack included

in the CCC plant. A damper shall however be installed upstream stack no. 3 making stack 3 accessible for

Page 16: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 16(49)

flue gas when the capture plant and the capture plant by-pass are out of operation while the cement plant is in

operation.

Contractor’s scope of work includes supply of all equipment and services required for installation of a

damper upstream stack no. 3.

Contractor shall supply the following main components:

▪ One damper in accordance with specification presented in section 0

Tie-in to stack for clinker cooler hot air

The clinker cooler hot air stack will be replaced by the new stack in the CCC plant during normal operation

of Waste Heat Recovery Unit (WHRU) 3, but will be used in case of WHRU3 shutdown. Control of gas flow

in the stack is necessary to prevent ambient air to be sucked in.

The tie-in to WHRU3 shall be above todays stack inlet to avoid changes in hot air flow inside the stack when

changing between WHRU3 operation and WHRU3 standstill.

The damper upstream the WHRU3 shall be “locked open” to secure a smooth changeover of hot air flow

direction and shall only be closed in case of maintenance requiring opening of the ductwork or boilers.

All the ducts related to this tie-in shall be insulated with mineral wool covered with cladding plate designed,

supplied and installed in accordance with HeidelbergCement’s Mechanical DCS “Thermal Insulation”, (Ref .

7).

Contractor’s scope of work includes supply of all equipment and services required for making the tie-in to

the stack, GS-112, and installation of a damper between the stack and the interface point GS-104.

Contractor shall supply the following main components:

▪ Tie-in to stack for clinker cooler hot air

3.2.2 New tie-ins, ducts, fans, dampers, etc needed to connect the waste heat recovery units and the

carbon capture plant to the existing flue gas system, category (b)

New tie-ins to the existing flue gas ducting

All tie-ins to the new plant shall be equipped with isolation dampers and shall be mechanically designed to

avoid dust build-up and high-pressure losses.

An overview of new tie-ins to the existing flue gas ducting is provided in Table 4 below.

Table 4: Tie-ins to existing flue gas ducting

Interface

ID out

Tie in to Interface

ID return

Tie in to

Carbon capture plant GS-117 Existing steel duct NA NA

WHRU1 circuit GS-109 Existing steel duct GS-114 Existing steel duct

Page 17: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 17(49)

Interface

ID out

Tie in to Interface

ID return

Tie in to

WHRU2 circuit GS-111 Existing steel duct GS-115 Existing steel duct

WHRU3 circuit GS-112 Existing brick stack GS-118 To Y-joint on absorber bypass

WHRU Bypass circuit GS-113 Existing steel duct GS-116 Existing steel duct

Crossover for flue gas

from string 2 to string 1

GS-110 Existing steel duct NA NA

Contractor’s scope of work includes supply of all equipment and services required for the establishment of

all new tie-ins into existing flue gas system

Contractor shall supply the following main components:

▪ Tie-ins according to Table 4.

Flue gas ducts

The new installations require both new ducting and modification of existing ducting. In tight spaces, existing

ducting shall be modified by Contractor to gain space for new dampers and tie-ins.

Circular ducts are preferred as they minimise the amount of steel required and are less expensive to fabricate.

However, in tight spaces ducting with rectangular cross section may be used. All ducts are made from mild

steel with external stiffeners. A corrosion allowance of 1-2 mm shall be included.

When selecting actual cross section area, a flue gas design velocity in the range 15-20 m/s is used to avoid

dust settling while maintaining an acceptable pressure loss. Pressure loss calculations shall be performed for

all new ducts to verify flue gas velocity and thus duct dimensions.

The only surface treatment required is a transport primer. To avoid heat loss and condensation of moisture in

the flue gas inside the ducts, they shall be insulated with 100 mm mineral wool covered with cladding.

Expansion joints shall be provided on new ducts and to tie-ins where necessary to handle vibration and

thermal expansion in accordance with HeidelbergCement’s Mechanical DCS “Expansion Joints” (Ref. 9).

Slide brackets, saddles and pendular supports will support the ducts in a way that allow, and control needed

movement due to thermal expansion. Supports shall where possible be attached to existing structures thus

reducing the need for additional foundations.

The ducts shall be equipped with manholes for internal inspection.

Stress calculations of ducts and supports shall be based on HeidelbergCement’s Mechanical DCS “Process

and de-dusting ducts” (Ref. 10) and with regards to dust-filling Norcem’s operational experience in Brevik.

Contractor’s scope of work includes the design, supply and installation of all equipment and services

required for the establishment of all new ducts from the various tie-ins to the new equipment and all required

modifications of existing ductwork.

Page 18: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 18(49)

Contractor shall supply general duct supports in steel. Civil works contractor will provided concrete

fundaments on ground level for steel support and larger bridges for ducts. The scope split with civil is shown

in the 3D CAD model (Ref. 4) where orange colour represents Contractor’s scope and blue colour represents

civil scope.

Contractor shall supply the following main components:

▪ New duct connecting ESP4 and GSA for use when WHRU1 is not in operation

▪ Duct going from outlet ESP4 (GS-109) to junction upstream WHRU1 (GS-100) including purging

connections in both ends.

▪ Duct going from outlet WHRU1 (GS-101) to tie-in at GSA inlet (GS-114)

▪ Duct going from tie-in at GS-117 to inlet capture plant (GS-106) including bypass and Y-junction on

absorber bypass duct (GS-118)

▪ Duct for crossover flue gas from tie-in downstream ESP3 (GS-110) to junction upstream WHR1

(GS-100) including purging connection

▪ Duct from tie-in downstream fan 25M018 (GS-111) to inlet WHRU2 (GS-102) including purging

connection

▪ Duct from outlet WHRU2 (GS-103) to tie-in (GS-15) on Raw mill bypass duct

▪ Duct from tie-in downstream fan 25M018 (GS-113) via WHRU Bypass fan and return to tie-in

upstream raw mill (GS-116)

▪ Ducting from tie-in in stack (GS-112) to inlet WHRU3 (GS-104)

▪ Ducting from outlet WHRU3 (GS105) to Y-junction on absorber bypass (GS-118)

Injection system for Powdered Activated Carbon (PAC) on string 1

Due to the new flue gas operating conditions maintaining a higher temperature over a longer period there is a

potential increased risk for formation of dioxins in the flue gas system. The GSA and the Raw mill will,

when in operation, remove dioxins from the flue gas (as for the current operation of the cement plant).

The GSA is not in operation when producing LA clinker (approx. 50% of the operating time), and therefore,

a system for injection of powdered activated carbon (PAC) shall be installed between the GSA and FF1 on

string 1 handling possible dioxin formation during LA clinker production.

The system shall comprise of a silo with a PAC capacity of 30 m3.

A similar system may be installed on string 2 (currently an option) if future operational data show that this is

required.

Contractor’s scope of work includes supply of all equipment and services required for installation of a PAC

storage and injection system on string 1.

Contractor shall supply the following main components:

▪ Silo with a PAC capacity of 30 m3, including:

o Silo including support

o Filling pipe including coupling for tank truck

o Filter

o Relief valve

o Aeration system

o Piping system incl. valves

o CO2/N2 firefighting system

o Instrumentation

Page 19: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 19(49)

▪ PAC dosing and injection system, including:

o Combined silo extraction and dosing device

o Rotary air lock

o Ejector/Transport tee

o Blower

o Piping system incl. valves

o Instrumentation

o Injection lance

Flue gas crossover fan from string 2 to string 1

Flue gas crossover from string 2 to string 1 is required as there is not enough CO2 to be captured from string

1 alone to reach the yearly capacity of 400 000 tones CO2. Flue gas must be added from string 2.

In addition, this adds operational flexibility dependent on final capture rate and heat transfer in the WHRUs

as a variable flow of flue gas may be added from string 2 to capture 55 t CO2/h. As the crossover fan is

equipped with a variable speed drive (VSD), this is only limited by the crossover fan capacity reserves and

turndown ratio.

The flue gas from string 1 and 2 is coming from the same kiln and is further mixed through string 1 securing

a homogenous gas entering the downstream capture plant.

The fan housing and internals shall be of materials suitable for the described service, and the fans shall be

insulated with 100 mm mineral wool covered with cladding plate.

The fan shall overcome the pressure loss from the ducting between tie-in at string 2 (GS-110) and the

junction upstream the WHRU1 (GS-100) and correspond to the pressure at GS-100 provided by WHRU Fan

1.

The electric motor shall operate on IT 3x690V 50Hz.

Contractor’s scope of work includes supply of all equipment and services for the new flue gas crossover fan

including el. motor.

Contractor shall supply the following main components:

▪ Centrifugal fan with el. motor

▪ Common base frame

▪ Instrumentation

WHRU fan 1

This is a new fan serving WHRU1 by compensating for the pressure drop in the flue gas caused by the 4

Waste Heat Recovery Boilers (WHRBs).

The fan shall overcome the pressure loss in ducting from the outlet of ESP4 including tie-in (GS-109) to the

inlet of WHRU1 (GS-100), pressure loss caused by WHRB 1.1, 1.2, 1.3 and 1.4 and from ducting from

outlet WHRU1 (GS-101) to the GSA inlet (GS-114) including the tie-in. The system operating pressure in

interface points GS-109 and GS-114 shall remain the same with and without the WHRU1 in operation.

Current operating pressure in existing ducting between the ESP4 and the GSA is -10 mbarg.

Page 20: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 20(49)

The fan shall be of centrifugal type with one impeller between bearings and the el. motors are controlled by

variable speed drives (VSD).

In addition to all conditions and specifications defined herein, the fans shall be supplied in accordance with

HeidelbergCement’s Mechanical DCS “Process Fans” (Ref .6).

The fan housings and internals shall be of materials suitable for the described service, and the fans shall be

insulated with 100 mm mineral wool covered with cladding plate designed, supplied and installed in

accordance with HeidelbergCement’s Mechanical DCS “Thermal Insulation”, (Ref .7).

The electric motor shall operate on IT 3x690V 50Hz. Normal speed is approx. 1000 rpm.

Contractor’s scope of work includes supply of all equipment and services required for the new WHRU fan 1

including el. motor.

Contractor shall supply the following main components:

▪ Centrifugal fan with el. motor

▪ Common base frame

▪ Instrumentation

WHRU fan 2

This is a new fan serving the WHRU2 by compensating for the pressure drop in the flue gas caused by the 3

Waste Heat Recovery Boilers (WHRBs).

The fan shall overcome the pressure loss in ducting from tie-in (GS-111) and to the inlet of the WHRU2

(GS-102), pressure loss caused by WHRB 2.1, 2.2 and 2.3 and from ducting from outlet WHRU2 (GS-103)

to the Raw mill bypass ducting (GS-115) including the tie-in. The system operating pressure in interface

point GS-115 shall remain the same with and without the WHRU2 in operation. Current operating pressure

in the raw mill bypass ducting is -5 to -4 mbarg

The fan shall be of centrifugal type with one impeller between bearings and the el. motors are controlled by

variable speed drives (VSD).

In addition to all conditions and specifications defined herein, the fans shall be supplied in accordance with

HeidelbergCement’s Mechanical DCS “Process Fans” (Ref .6).

The fan housings and internals shall be of materials suitable for the described service.

The electric motor shall operate on IT 3x690V 50Hz. Normal speed is approx. 1000 rpm.

Contractor’s scope of work includes supply of all equipment and services required for the new WHRU fan 2

including el. motor.

Contractor shall supply the following main components:

▪ Centrifugal fan with electric motor

▪ Common base frame

▪ Instrumentation

Page 21: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 21(49)

WHRU bypass fan

This is a new fan used only when producing LA clinker and the WHRU 2 is in operation. Its purpose is to

supply the raw mill with high-temperature flue gas in addition to the cooled flue gas coming from WHRU2

when producing LA clinker.

In addition to all conditions and specifications defined herein, the fans shall be supplied in accordance with

HeidelbergCement’s Mechanical DCS “Process Fans” (Ref .6).

The fan shall be of centrifugal type with one impeller between bearings and the electric motor is controlled

by a Variable Speed Drive (VSD). The fan housing and internals shall be of materials suitable for the

described service.

The electric motor shall operate on IT 3x690V 50Hz and be controlled by a variable speed drive (VSD). Its

maximum speed is 1000 rpm.

Contractor’s scope of work includes supply of all equipment and services required for the new WHRU

bypass fan including el. motor.

Contractor shall supply the following main components:

▪ Centrifugal fan with el. motor

▪ Common base frame

▪ Instrumentation

WHRU fan 3

This is a new fan serving the WHRU3 by compensating for the pressure drop in the flue gas caused by the 2

Waste Heat Recovery Boilers (WHRBs).

The fan shall overcome the pressure loss in ducting from tie-in (GS-112) and to the inlet of the WHRU3

(GS-104), pressure loss caused by WHRB 3.1 and 3.2 and from ducting from outlet of WHRU3 (GS-105) to

the Y-junction on the Absorber bypass (GS-118). The fan shall be of centrifugal type with one impeller

between bearings and the el. motors are controlled by variable speed drives (VSD).

In addition to all conditions and specifications defined herein, the fans shall be supplied in accordance with

HeidelbergCement’s Mechanical DCS “Process Fans” (Ref .6).

The fan housings and internals shall be of materials suitable for the described service.

The electric motor shall operate on IT 3x690V 50Hz. Normal speed is approx. 1000 rpm.

Contractor’s scope of work includes supply of all equipment and services required for the new WHRU fan 3

including el. motor.

Contractor shall supply the following main components:

▪ Centrifugal fan with el. motor

▪ Common base frame

▪ Instrumentation

Page 22: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 22(49)

Dampers

All new dampers, on-off and modulating, shall be of louvre type with two shafts and double acting

pneumatic actuators and limit switches. All dampers must be gas tight and equipped with sealing air to allow

for manual inspection inside sealed off ducting while cement production is ongoing.

Sealing air is ambient air and shall be provided to each damper by installation of a local fan. The electric

motor shall operate on IT 3x690V 50Hz.

The damper housing and internals shall be of materials suitable for the described service, and the fans shall

be insulated with 100 mm mineral wool covered with cladding plate.

Contractor’s scope of work includes supply of all equipment and services required for the installation of all

the dampers shown on the flow diagram NC03-NOCE-P-XA-0001, page 1 and 2 (Attachment A02).

In addition to all conditions and specifications defined herein, the dampers shall be supplied in accordance

with HeidelbergCement’s Mechanical DCS “Guillotine Gates & Louvre Dampers” (Ref .11).

Contractor shall supply the following main components:

▪ Modified damper downstream HV1 fan

▪ One damper at tie-in (GS-109) downstream ESP4 on new duct to WHRU1 – On/ off, gastight

▪ One damper downstream ESP4 on direct duct between ESP4 and GSA – Regulating

▪ One damper at tie-in (GS-114) upstream GSA on new duct from WHRU1 – On/ off, gastight

▪ Three dampers for purging air on new ducts to/ from WHRU1 – on/ off

▪ One damper for Stack. no. 3 – On/ off

▪ One damper at tie-in (GS-106) for CO2 capture plant – On/ off, gastight

▪ One damper for CO2 capture plant bypass – Regulating, gas tight

▪ One damper at tie-in (GS-110) for flue gas crossover – On/ off, gastight

▪ One damper at tie-in (GS-111) on duct to WHRU2 – On/ off, gastight

▪ One damper at tie-in (GS-115) on duct from WHRU2 – On/ off, gastight

▪ One damper for purging air on new ducts to WHRU2 – on/ off

▪ One damper at tie-in (GS-113) on duct to WHRU Bypass fan – On/ off, gastight

▪ One damper at tie-in (GS-115) on duct from WHRU Bypass fan – On/ off, gastight

▪ One damper downstream 25M018 on direct duct between 25M018 and Raw mill – Regulating

▪ One damper at tie-in (GS-112) on duct to WHRU3 – On/ off, gastight

▪ One damper upstream Y-junction at absorber bypass (GS-118) on duct from WHRU3 – On/ off,

gastight

3.3 Interfaces, battery limits and scope of work splits

3.3.1 Introduction

An overview of the main systems included in Contractor’s scope of work is provided in section Feil! Fant

ikke referansekilden..

A detailed description of the interfaces between Contractor, Company and the other contractors are provided

in the following subsections.

The technical interfaces are defined in the Interface Matrix (Attachment A03) and are detailed in the Project

Interface Register (Attachment A04) with datasheets for each interface point.

Page 23: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 23(49)

3.3.2 Norcem Plant

Norcem Plant will provide the complete electrical power supply system with required transformers, MCCs,

VSD, cabling, safety switches, etc. Interface point is on terminal box on el. motors.

Norcem Plant will provide the complete communication system with required I/O cabinets, servers, PLCs

operator stations etc. Interface point is on terminal box on instruments, regulating valves and dampers.

3.3.3 CCC plant, including waste heat recovery

There are eight interface points between Norcem Plant Modifications and the CCC plant:

▪ Inlet of Flue gas fan, GS-106

▪ Inlet to Absorber bypass line, GS-118

▪ Inlet of Waste Heat Recovery Unit1 (WHRU1), GS-100

▪ Outlet of Waste Heat Recovery Unit1 (WHRU1), GS-101

▪ Inlet of Waste Heat Recovery Unit2 (WHRU2), GS-102

▪ Outlet of Waste Heat Recovery Unit2 (WHRU2), GS-103

▪ Inlet of Waste Heat Recovery Unit3 (WHRU3), GS-104

▪ Outlet of Waste Heat Recovery Unit3 (WHRU3), GS-105

These interface points are shown on the Flow diagram NC03-NOCE-P-XA-0001, page 1 and 2 (Attachment

A02) and further specified in the Interface register (Attachment A04).

Flue Gas Fan and DCC

The CO2 capture plant will extract flue gas from the flue gas tie-in (GS-117), which is located between

existing Fabric Filter Fan on String 1 and existing stack (Stack No 3) at Norcem. The existing stack will not

be used after implementation of the CO2 capture plant, except for special occasions when the CO2 plant needs

to be entered for maintenance inside flue gas ducts or columns.

Flue gas is routed through a new duct from the flue gas tie-in to the CO2 capture plant main process area

where the new Flue Gas Fan is located. There is a bypass duct from upstream of the Flue Gas Fan and into

the new stack located on top of the Absorber. There is a bypass damper at the entrance to the bypass duct,

and there is an inlet damper at the entrance to the Flue Gas Fan and CO2 capture plant.

The bypass damper is provided with 'Lock Open' arrangement to secure free flue gas flow path without

depending on a control system to open it.

The Flue Gas Fan located downstream of the inlet damper fan will be equipped with Variable Speed Drive

(VSD). Flue gas flow and temperature measurements in the bypass duct will be used for controlling the fan

speed, aim is to maintain close to zero flow in the bypass during normal operation. The pressure conditions

downstream of the existing Filter Fan will be approx. 5 mbar higher than today due to increased pressure loss

in new ductwork, mixing device in stack and the stack itself. Since the bypass damper is locked open,

pressure will be maintained fairly constant and nearly independent of CO2 capture plant operation or flue gas

bypass operation.

Downstream of the Flue Gas fan, the flue gas enters the Direct Contact Cooler (DCC), where the flue gas

flows counter-currently to water in a packed bed with structured packing. The flue gas is cooled beyond its

dew point and the DCC is therefore a net water producer. Hence a condensate bleed is established,

containing traces of sodium sulphite, sodium sulphate and possibly traces of suspended fines from the flue

Page 24: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 24(49)

gas. The bleed will be partially utilized as process water for Norcem’s existing cement plant, i.e. as makeup

water to the Gas Suspension Absorption (GSA). The remaining bleed is sent to an Effluent Water Treatment

Plant (EWTP) for purification before released to sea. During Low- Alkali (LA) clinker production, the GSA

is out of operation, hence the whole DCC bleed will be treated in the effluent water treatment plant (6 m3).

During standard clinker production, the GSA is in operation and the flue gas has higher water content, which

implies the bleed rate becomes larger (11 m3/h). The increased bleed corresponds to the water injected in the

GSA (approx. 5 m3/h). This excess bleed is then routed to the GSA where the water is reused as GSA feed

water.

Waste Heat Recovery Arrangement

Waste heat from the following three gas streams in the existing cement plant is recovered:

▪ Flue gas from preheater String 1

▪ Flue gas from preheater String 2

▪ Excess hot air from clinker cooler

The waste heat is recovered from the three gas streams by several steam generating boilers/ Waste Heat

Recovery Boilers – (WHRBs). The WHRBs for each string forms a Waste Heat Recovery Unit (WHRU)

where all boilers are operating in series on the flue gas side.

The WHRU installations are installed in parallel to the existing flue gas ducting. In this way the cement

production plant can operate independently of the WHRUs as these can be bypassed when not in operation.

WHRUs for string 1 and 2 are arranged downstream the existing Gas Conditioning Towers (GCT 1 and 2)

and the Electro Static Precipitators (ESP 4 and 3 respectively). To achieve highest possible heat recovery a

high flue gas temperature on the boiler inlet is required. The cooling service in the cooling towers are

therefore reduced/ stopped during operation of the waste heat recovery units.

The WHRU installation for the hot air from clinker cooler are arranged downstream the existing hot air

chimney.

The WHRU integration to existing plant is shown in Figure 4.

Page 25: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 25(49)

Figure 4 - Overview of the cement production process flow with WHRU systems and tie-ins

Waste Heat Recovery Boilers (WHRB) / Waste Heat Recovery Units (WHRU)

Two or more Waste Heat Recovery Boilers (WHRB) forms a Waste Heat Recovery Unit (WHRU) where all

boilers are operating in series.

Boiler design

The WHRBs are of standard shell boiler type where the hot flue gas is led through the internal flue gas tubes

being submerged in water. The hot flue gas heats the water to its boiling point before it evaporates as steam.

To recover as much heat as possible from each unit the WHRBs are designed for an optimum flue gas

velocity through the flue gas tubes to avoid excessive pressure loss and prevent scaling and erosion

dependent on type of dust in the flue gas. The average flue gas speed through WHRU 1 and 2 is 40 m/s (to

limit scaling), and through WHRU 3 it is 30 m/s (to limit erosion).

WHRU 2 will operate with two different flue gas flow rates depending on clinker production mode, LA or

Standard. The WHRU 2 boilers are designed for a flue gas flow related to Standard clinker production (high

flue gas flow). During production of LA clinker the flue gas flow will be approx. 30% lower than during

production of Standard clinker, and this consequently reduces the flue gas velocity in the boiler tubes. If

operational experience shows that scaling becomes an issue due to this reduced velocity, the solution will be

to block some of the boiler flue gas tubes by a damper. The inlet ducting is prepared with space for a damper

by installing a straight ducting upstream the WHRB 2.1.

Dust handling for boilers

Page 26: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 26(49)

The flue gas contains dust. Normal operating value for dust concentration on WHRU1 and 2 inlets is 0,1

g/Nm3, but they are designed to operate with a dust concentration of 1 g/Nm3. For WHRU 3 the normal

operating value for dust concentration on inlet is 0,005 g/Nm3.

The inlet and outlet duct/ chamber of the boilers are designed as a semicircle to match with the inlet section

of the flue gas pipes inside the boilers to avoid large variations in flow profile in and out of the boiler. The

inlet duct of each boiler is designed without hoppers for dust collection, thus all dust will pass through the

WHRUs. However, both inlet and outlet chambers on each boiler are equipped with hatches (typ. 500 x 700

mm) for inspection and cleaning purposes.

3.4 Plant Operability

All new plant shall be designed, arranged and equipped so the change-over between operating the cement

production with or without the CCC plant and the waste heat recovery units in operation is smooth and can

be done without stopping the cement production.

For further details, please see NC03-NOCE-Z-RA-0027 Functional Design Specification (FDS) Tie-ins (Ref.

5).

3.5 HSE Management

Contractor shall ensure that the Work is planned, organized and carried out with the highest standard of

safety precautions and at all times in compliance with applicable health, environmental and safety

legislation and regulations. Contractor shall adhere to and ensure compliance with Company’s at each

time applicable site regulations, OHS related instructions and work environment plans.

Contractor shall be responsible for all HSE aspects in all parts of the Work, and HSE considerations shall be

an integral part of the Work.

Contractor shall ensure that systematic measures are taken to ensure that the Work is planned, organized,

performed and maintained in accordance with requirements laid down in or pursuant to the Norwegian

authorities' health, environment and safety legislation.

Contractor shall ensure effective HSE management that can be safeguarded by adopting the ISO 14001

“Management systems for the environment” and ISO 45001 “Management systems for the working

environment”.

HSE management of the scope of work shall be performed, by active involvement at all levels in its

organization including Subcontractors, in accordance with the specifications in Appendix D and E.

All Work shall be executed in accordance with Company's zero harm goal.

Contractor shall require and verify that all their subcontractors carry out their work in accordance with the

HSE requirements in this contract. Major Subcontractors shall also be an integrated part of Contractor's HSE

program and HSE management system.

Contractor shall establish a SHA Plan in accordance with the requirements in Appendix D.

Company shall be invited to relevant HSE activities planned by Contractor and its subcontractors.

Contractor shall attend all project HSE activities, as requested by Company, in accordance with the

requirements in Appendix D.

Page 27: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 27(49)

Contractor shall ensure that opportunities exist for trade union activity among Contractor's employees,

Subcontractor's employees and hired-in labour, in accordance with Norwegian practice.

3.6 Project Management and Administration

Contractor shall be responsible for the management of all aspects of the Work.

Contractor shall provide the required personnel and perform all management and administration tasks

required for the Work, throughout all phases of the Work and on all Sites including Subcontractors' sites.

This includes:

▪ Project Management Plan

▪ Scope Management

▪ Interface Management

▪ Schedule Management

▪ Cost Management

▪ Quality Management

▪ Project Organisation and Resource Management

▪ Project Communication

▪ Risk Management

▪ HSE Management (described in section 3.4 above)

▪ Procurement Management

▪ Change and Issue Management

▪ Benefits Realisation and Knowledge Sharing

▪ Document Management

These are further detailed in the following subsections and/or in Appendix D.

Contractor shall have a project management system that satisfies the requirements set out in Appendix D.

Contractor shall provide all the information technology equipment and systems (hardware and software)

required for the performance of the Work, according to requirements in Appendix D.

3.6.1 Project Management Plan

Contractor shall have a project management plan that satisfies the requirements set out in Appendix D.

3.6.2 Scope Management

Contractor is responsible for the planning, organization, follow-up and execution of the Work in accordance

with this contract and the requirements in Appendix D.

3.6.3 Interface Management

Company is responsible for the overall coordination of project interfaces across Company’s contractors and

with Northern Lights.

Contractor shall be responsible for coordination and handling of all interfaces related to the Work and shall

take a proactive approach in seeking necessary information from Company and relevant interfacing parties

(other project contractors and project external parties).

Page 28: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 28(49)

Contractor shall actively follow up own and its Subcontractors’ engineering to ensure that the required

interface information is delivered to the relevant interfacing parties in accordance with the interface schedule

and milestone dates defined in Appendix C.

Company’s requirements to interface management in Appendix D shall be followed for all interfaces across

other project contractors and towards project external parties (e.g. Northern Lights).

3.6.4 Schedule Management

Contractor is responsible for project schedule management according to the requirements set out in

Appendix D.

Contractor’s schedule shall comply with the milestones defined in Appendix C.

Contractors schedule shall be fully integrable with Company’s project schedule and reflect all

Subcontractor(s)’ schedules with the required level of detail in accordance with the requirements in

Appendix D.

Contractor shall ensure that schedule baselines are updated in accordance with the requirements in Appendix

C.

3.6.5 Cost Management

Contractor is responsible for project cost management according to the requirements set out in Appendix D.

3.6.6 Quality Management

Contractor shall establish, maintain and follow up a quality management system that satisfies the

requirements set out in Appendix D. The quality management system shall cover all Contractor’s Work,

including Work to be performed by Subcontractors.

Contractor's Work shall be performed according to Contractor’s quality management system, where this is

not in conflict with the prevailing requirements in the Contract including Appendices.

Contractor and its main Subcontractors shall be certified according to ISO 9001:2015 and ISO 14001:2015.

Contractor shall establish, implement and maintain a Project Quality Plan (PQP) in accordance with the

requirements in ISO 9001:2015, Appendix D.

Contractor shall establish, implement and maintain an Inspection and Test Plan (ITP) in accordance with the

requirements in Appendix D.

Contractor shall establish, implement and maintain a project audit and examination program in accordance

with the requirements in ISO 9001:2015, ISO 19011, and Appendix D. Contractor’s program(s) for audits

and examinations shall be submitted to Company for review and comment.

Company shall have the right to participate in the planning of and to participate as an observer in the

execution of all Contractor's audit and examination activities related to the Work.

Company Representative and personnel authorised by him shall at any time have the right to undertake

unrestricted quality audits and verification of Contractor's and Subcontractor’s quality management.

Page 29: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 29(49)

Contractor shall ensure that relevant experience and lessons learned from previous projects are taken into

account throughout project execution.

3.6.7 Project Organisation and Resource Management

Contractor shall ensure a safe and cost-effective organization of the Work in accordance with this contract.

Contractor shall ensure that its own project organization and the organization of its Subcontractors satisfy the

requirements set out in Appendix D.

Contractor is responsible for timely mobilization of facilities, personnel and resources required for the

successful performance and completion of the Work.

3.6.8 Project Communication

Contractor is responsible for project communication management (including project reporting) according to

the requirements set out in Appendix D.

Contractor shall perform the Work in a proactive way and cooperate closely with Company personnel.

3.6.9 Risk Management

Contractor shall establish, implement and maintain a project risk management system and manage project

risks according to the requirements set out in Appendix D.

3.6.10 Change and Issue Management

Contractor shall establish, implement and maintain a change and issue management system and manage

changes and issues according to the requirements set out in Appendix D.

3.6.11 Benefits Realisation and Knowledge Sharing

Contractor shall throughout the Contract Period contribute to benefits realisation and knowledge-sharing in

accordance with the requirements set out in Appendix D.

Contractor shall identify and execute activities and measures which contribute to the realisation of the

benefits outlined in Company’s benefits realisation plan according to the requirements in Appendix D.

3.6.12 Document Management

Contractor shall establish, implement and maintain a document management / control system and manage

documentation according to the requirements set out in Appendix D.

Contractor shall throughout all phases of the Work, utilize an electronic document control system for

identification and control of all project documentation. The system shall be accessible to Company for

monitoring.

Contractor shall establish, implement and maintain an agreed master document register (MDR), including all

project documents to be delivered by Contractor as part of the Work. The Master Document Register

(MDR) shall include planned, forecast and actual issue dates for all relevant project documents. Company

has the right to review any document listed in the MDR and define which documents to be issued for

review and information respectively (to be marked with "review" or "info" in the MDR). Contractor shall

Page 30: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 30(49)

make sure that the MDR and document chains are kept up to date throughout project execution. The

MDR shall be developed, maintained and handled according to the requirements in Appendix D.

Contractor shall ensure that all their document deliveries as part of the Work is delivered to Company in

accordance with the requirements in Appendix C and D.

Contractor shall facilitate the transfer of electronic data to Company's technical information systems as

requested by Company.

3.7 Engineering

3.7.1 General

Contractor shall perform all engineering activities required for the Work, and is responsible for securing the

required, and agreed functionality, capacity and performance of the Work, in accordance with the

requirements in Appendix E. This includes input to the design and functionality of the existing systems

affected by the Work.

During early stages of Detail Design, Contractor shall perform a regulation/standard/governing documents

compliance assessment for all parts of the Work.

All equipment and systems shall be CE marked and delivered with a Declaration of Conformity as required

by applicable laws, rules and regulations.

Company's tag number system shall be used exclusively throughout project execution.

Contractor shall ensure that the HSE requirements are implemented into all engineering activities.

Contractor shall ensure that the Detail Design is practical, operable and fully meets the requirements given in

Appendix E.

A systematic approach to risk reduction shall be utilized in Contractors' activities. Priority is to establish and

document inherent safe solutions in layout and design followed by implementation of risk reduction

measures according to the ALARP principle and cost-benefit considerations. The ALARP register shall be

kept updated throughout the whole project period to ensure a traceable ALARP process.

Contractor shall ensure that throughout the Detail Engineering, adequate provisions are made for multi-

discipline check of system design, inter-discipline clash checking and constructability analysis. Contractor

shall, when planning the Work, allow sufficient time to perform all checking and analysis, and implement

possible corrections.

Further to the above, Detail Engineering shall also include activities such as:

▪ Perform all engineering in accordance with Contractor’s scope and ensure safe and functional overall

system and area design, with strong focus on operability and maintainability.

▪ Develop and maintain registers on equipment/items/component level by tag.

▪ Contractor shall continuously update and make available to Company updated 3D CAD model of the

Contract Object.

▪ Contractor shall perform all required calculations and analyses to complete the Work. All such

calculations and analyses shall be performed utilizing verified methods, algorithms, computer

programs and models.

Page 31: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 31(49)

The design of systems and areas shall focus on:

▪ Low personnel intervention; starts up and shutdown of production shall in general be performed

without manual intervention.

▪ Layout with adequate access for operation, maintenance and material handling

▪ Relevant equipment shall be designed so that it can easily be replaced during the lifetime.

3.7.2 HSE in Design

Contractor shall perform and document HSE engineering to meet governing regulations and project HSE

goals and requirements.

Work Environment

Contractor shall perform necessary studies and activities in order to ensure that the Work Environment (WE)

is in accordance with the Contract, including Appendices D and E.

The work environment activities to be performed include activities such as:

▪ Performance of work environment health risk assessment (WEHRA).

▪ Coordination of input to and review of equipment package and area design

▪ Performance of specific design reviews for areas and equipment as required

▪ Ensure that personnel exposure to chemical substances and products containing hazardous

substances is minimized

Noise control

Norcem Plant has a high focus on noise, to minimise noise at residential dwellings and noise exposure to

own employees. Contractor shall evaluate all aspects of its design and implement noise control features as

required.

Contractor shall provide noise data for the Contract Object to Company as required (in a format agreed with

Company).

Specific point source noise levels shall be provided for all equipment in all work areas included in the

Contract Object.

Contractor shall implement its design to meet the applicable regulatory noise requirements and issue noise

data sheets as required.

Contract Object noise levels shall be in accordance with HeidelbergCement’s Mechanical DCS “General

Mechanical Design” (Ref. 12).

A noise control report shall be prepared and issued to the Company for review.

Technical safety

Contractor shall in cooperation with Company update and further develop the safety strategy from the FEED

related to all parts of the Work. The safety strategy shall show and justify choices made related to safety

systems and barriers and their performance.

Page 32: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 32(49)

Location and number of safety equipment, including fire and gas detectors, and escape routes shall be shown

on layout drawings. This shall not to be included in the 3D model.

SIL (Safety Integrity Level) is not applicable.

HAZID workshop(s) shall be performed as required.

Contractor shall update, implement and maintain and detail out the FEED Risk Analysis.

3rd Party studies performed in FEED shall be updated if assumptions are changed, or design changes have

invalidated the conclusions. Further 3rd party studies shall be performed as required in accordance with the

Contract, including the requirements in Appendices D and E.

External Environment

Contractor shall conduct an ENVID/environmental design review to ensure proper attention to the

environmental issues.

3.7.3 Process

General

Contractor is responsible for and shall perform process design for all systems included in the Work.

Contractor shall as a minimum carry out the following process engineering work as required for the Contract

Object:

▪ Establish or update P&IDs, PFDs and UFDs for the Work, including legends

▪ Prepare utility load lists, line lists, valve lists, signal lists, functional design specifications, process

data sheets, system descriptions and complete any studies, calculations, simulations and

documentation necessary

▪ IFC P&IDs shall be updated based on 3D Model reviews and HAZOPs

▪ Process and utility system design review workshops shall be performed at an early stage of Detail

Engineering. The basis for the review shall be PFD, UFD and (FEED) P&IDs and system sketches

showing all main equipment and control philosophy for each system. Company shall be invited to

participate in the reviews. The reviews shall be executed prior to process HAZOP(s). All findings,

comments and actions relevant for the Work shall be documented, and all actions shall be closed-out

▪ Define insulation and frost protection requirements

▪ Perform hydraulic systems calculations

▪ Prepare Cause and Effect Diagrams

▪ Provide input to the overall chemical management plan for the plant as required

▪ Establish system engineering manuals for process and utility systems

HAZOP Analyses

HAZOP analyses shall be carried out during Detail Engineering according to IEC 61882 and the

requirements in the Contract, and the requirements in Appendix D and E. The HAZOP analyses shall include

all process, safety and utility systems for the Contract Object and all internal interfaces, as well as interfaces

towards other project contractors and external parties (e.g. Northern Lights).

Page 33: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 33(49)

The issue for HAZOP version of P&IDs shall have incorporated major findings from process design review

workshops to avoid re-HAZOP. Red-mark P&IDs shall not be basis for HAZOP. Changes to design either

caused by HAZOP findings or design development may require a new HAZOP for individual systems or

Subcontractor packages. Contractor shall give recommendation for items subject to re-HAZOP.

Selected Subcontractor packages shall be subject to HAZOP

3.7.4 Mechanical

Contractor shall execute all Mechanical equipment design for the Contract Object.

All mechanical equipment shall be identified in the Master Equipment List (MEL) with all relevant

information listed and the MEL shall be kept updated throughout project execution.

Contractor shall identify and perform any studies and verifications required, to document that the design of

the mechanical system(s)/equipment is in accordance with the functional and technical requirements for the

Work.

3.7.5 Structural Engineering

General

Contractor shall execute and document all structural engineering and analyses as required for the Contract

Object.

Contractor shall perform 3D modelling and prepare structural drawings.

Contractor shall specify structural loads and other relevant input parameters for civil engineering, according

to the requirements in Appendix C.

Structural design briefs shall be prepared and issued to Company for review before start of structural

analyses and design work. Design brief documents shall present methodology and principles for structural

design and analyses for the Contract Object.

Structural analyses shall be performed to confirm acceptable design criteria and document the required

structural load bearing capacity. Contractor shall perform ULS, SLS and ALS analysis of the structural

capacity for all governing load cases.

3.7.6 Piping and Layout

General

Contractor shall execute all ducting, piping and layout engineering and document according to the agreed

MDR for the Contract Object.

Contractor shall throughout the Detail Engineering seek optimization of layout to ease installation work and

find cost saving solutions without compromising safety or operational requirements.

The basic layout shall only be altered if:

▪ Significant layout/safety/functional/operations/cost improvements can be achieved

▪ Equipment design or dimensions are significantly altered

Page 34: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 34(49)

▪ Potential for reducing Construction Work

▪ Instructed by Company

All such alterations are subject to pre-approval by Company.

Contractor shall further develop and maintain their 3D CAD model and integrate this with the project 3D

CAD model. Contractor’s 3D model must have export file formats suitable for import to the project overall

3D CAD model. The 3D CAD model that shall be the source for all layout and area engineering information.

All piping and equipment identified on the P&IDs shall be engineered and modelled in the 3D CAD

model. Contractor shall perform regular clash- and constructability checks in the 3D model, with

subsequent resolutions. Timing shall be carefully considered to optimize the quality of the engineering

as well as the progress. Clashes shall be resolved prior to any issue of documentation for construction.

Design reviews shall verify 3D model quality and content, piping and process technical requirements and

layout functionality. The design reviews shall be carried out in due time before the layout is final

concluded in order to implement review findings and comments. 3D model design reviews shall be

coordinated with design reviews as required for material handling, technical safety and WE.

Contractor shall provide input to interface register and specify the coordinates, direction, size, class and

flange details of all interface piping. The interfaces shall include enough piping and supports beyond the

boundary point to give a realistic stress analysis on both sides.

Contractor shall establish plot plans (from the 3D model), engineering isometrics, interface drawings, pipe

support drawings, MTOs and any other documents required for verification of the design, fabrication and

operation in accordance with DFO requirements.

Material handling

Contractor shall perform all engineering related to material handling, transportation and installation.

Contractor shall have high focus on material handling, and the material handling solutions shall be

continuously evaluated as the design develops. The material handling design shall be described in the

Material Handling Report. Contractor shall use the material handling philosophy developed in FEED as basis

for further development of the material handling report.

Material handling including lifting arrangement shall be addressed during Purchase Order development.

3.7.7 Electrical

Company is responsible for the overall electrical system design and electrical area design (cable design,

cableways, heat tracing, earthing etc.).

Contractor is responsible for detail engineering and documentation of all electrical equipment included in the

Contract Object in accordance with Company’s requirements in Appendix E.

For skids/modules and large vessels Contractor is also responsible for design and documentation of

cableways and heat tracing (including junction boxes on the skids) in accordance with Company’s

requirements in Appendix E.

The required interface information shall be delivered to Company in accordance with the requirements in

Appendix C.

Page 35: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 35(49)

Contractor shall deliver the following engineering documentation, which shall be kept updated throughout all

phases of the Work:

▪ 3D model identifying the location of all interface connection points (earthing points, electrical

motors, other consumers, etc.) supplied and installed by Contractor

▪ Electrical Load Lists for motors and other consumers and any other lists that is needed to convey

required information needed for Company's own engineering, testing and commissioning as agreed

with Company

▪ Operational setpoints and alarm limits for motors and other consumers

3.7.8 Instrumentation and Automation

Contractor is responsible for detail engineering and documentation of all instrumentation included in the

Contract Object in accordance with Company’s requirements in Appendix E.

Contractor is responsible for the functional design specification (FDS) of the control systems related to the

Contract Object in accordance with Company’s requirements in Appendix E, and adequate for the

programming of the related control system by others. The FDS, including Cause and Effect Diagrams shall

provide the complete basis for programming of the control system and the Human Machine Interface (HMI).

Contractor shall be part of the Factory Acceptance Test (FAT) and upon request by Company, also the Site

Acceptance Test (SAT) of the process control system. During the FAT Contractor shall verify and confirm

that the control system programming and HMI is performed according to the FDS.

The required interface information shall be delivered to Company in accordance with the requirements in

Appendix C.

Contractor shall deliver the following engineering documentation, which shall be kept updated throughout all

phases of the Work:

▪ Signal (I/O) lists

▪ Functional Design Specification for control systems included in the Contract Object

▪ 3D model identifying the location of all interface connection points supplied and installed by

Contractor

3.7.9 Materials, Surface Protection and Insulation

Contractor is responsible for detail engineering and documentation of all materials, surface protection and

insulation relevant to the Contract Object in accordance with Company’s requirements in Appendix E.

Materials selection

Contractor is responsible for selecting the appropriate materials for the Contract Object.

Contractor shall:

▪ Update materials selection specifications from FEED, including corrosion evaluations

▪ Issue a final update of the materials selection specifications to reflect as-built status

▪ Verify that the selection of materials, surface protection and insulation defined in P&IDs and in

package specifications is in compliance with the requirements in Appendices E and I

▪ Verify that all Subcontractors and Subsuppliers adequately incorporate all relevant requirements

throughout the Work.

Page 36: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 36(49)

3.7.10 Surface protection and insulation

Contractor is responsible for selecting the surface protection and insulation for the Contract Object.

Contractor shall:

▪ Develop surface protection specification in accordance with ISO 12944. Corrosive Environment

Classification C3 and Durability Interval M.

▪ Develop ducting, piping & equipment insulation design specification

▪ Verify that all Subcontractors and Subsuppliers adequately incorporate all relevant requirements

throughout the Work.

Company shall review and approve the insulation design specification (including cladding principles) from a

maintenance point of view.

3.7.11 Studies

3rd Party studies and other studies shall be performed by Contractor as required in accordance with the

Contract, including the requirements in Appendices D and E.

Contractor shall conduct updated Freedom-to-Operate studies and issue study reports, and confirm that there

are no possible infringements to Intellectual Property Rights related to the Contract Object.

Additional to the studies identified throughout this Appendix A, Contractor shall identify the need for, and

plan and perform necessary studies, analyses, simulations and calculations required to complete the Work.

3.7.12 Engineering for Construction

Contractor shall ensure that all aspects of construction are effectively controlled to complete the Contract

Object to agreed quality and schedule.

Contractor shall establish and implement appropriate procedures to support control of all aspects of

construction. All procedures shall be sufficiently detailed and shall be issued with all necessary approvals

prior to the planned start date of the actual work.

3.7.13 Engineering for Mechanical Completion (MC) and Commissioning.

Contractor is responsible for the necessary preparation for Mechanical Completion (MC) and preparation of

commissioning procedures related to the Work according to Company's requirements in Appendix E.

Engineering for Mechanical Completion and Commissioning shall form the basis for sequencing and

management of activities within Detail Engineering, procurement, fabrication and installation.

Contractor shall establish and maintain systems and procedures for planning, execution and documentation

of all MC and Preservation activities for the Work.

Suitable IT tools shall be used for preparation and execution of all MC and Commissioning activities. The IT

tools to be used shall be agreed with Company upfront.

Contractor shall:

▪ Define MC packages in line with Company’s commissioning plan

Page 37: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 37(49)

▪ Define recommended commissioning packages and sequence for the Contract Object

▪ Establish and maintain a dedicated MC database for the Work ▪ Establish commissioning procedures for the Contract Object

▪ Provide input to the project commissioning plans and procedures as requested by Company.

▪ Verify that all engineering documentation is in compliance with the commissioning requirements (in

accordance with Appendix C) ▪ Establish a schedule for handover of MC packages to Company for commissioning

▪ Establish a list of recommended spare parts for commissioning of the Work

▪ Establish list of recommended tools for MC and commissioning

3.7.14 Engineering for Operations and Maintenance

Operating Procedures

Contractor shall develop clear and understandable operating procedures for the Contract Object. The

operating procedures shall ensure safe and efficient operation of the CCS Facility and clearly define

recommended operating envelopes and limits. The procedures shall be sufficiently detailed and written in

Norwegian and English. The operating procedures are subject to approval by Company and the format for

the procedures shall be agreed with Company upfront.

The operating procedures shall be delivered in accordance with the requirements in Appendix C.

The operating procedures shall include:

▪ Procedures for normal operations

▪ Procedures for abnormal operations

▪ Emergency procedures

▪ Plant start-up procedures

▪ Plant shutdown procedures

▪ Material Safety Datasheets

▪ Procedures for handling of materials/chemicals/waste

▪ Control measures and personnel protective equipment (PPE)

▪ Equipment layout/location

▪ Sampling procedures

Maintenance Procedures

Contractor shall develop clear and understandable maintenance procedures for the Contract Object. The

maintenance procedures shall ensure safe and efficient maintenance and operation of the CCS Facility and

clearly define maintenance intervals. The procedures shall be sufficiently detailed and written in Norwegian

and English. The maintenance procedures are subject to approval by Company and the format for the

procedures shall be agreed with Company upfront.

The maintenance procedures shall be delivered in accordance with the requirements in Appendix C.

The maintenance procedures shall include:

▪ Procedures for planned (preventive) and corrective maintenance

▪ Maintenance work schedule / intervals with reference to operating parameters (e.g., hours, time,

number and type of use)

▪ Warning and caution statements / notes

Page 38: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 38(49)

▪ Equipment location, tag no., make, model and serial number and recommended spare parts (with

item number)

▪ Required / recommended maintenance tools, measurement and test equipment

▪ Cleaning requirements

▪ Replacement of wear-and-tear parts, operating fluids and tolerances

▪ Monitoring of operating parameters

▪ Recommended lubricants and lubrication frequencies

▪ OEM document library

▪ Maintenance logging

▪ Changeover instructions

3.8 Procurement and Fabrication

3.8.1 Procurement

General

Contractor is responsible for all project procurements related to the Contract Object in accordance with the

requirements in the Contract, including Appendices C, D and E.

All project procurements shall be carried out in accordance with Company’s contract and procurement

strategy (ref. Appendix D and E).

Contractor's procurement activities shall be performed according to Contractor’s established procurement

procedures and quality management system, where these are not in conflict with the prevailing requirement

in the Contract, including Appendices C, D and E.

Contractor shall ensure that procurement activities fulfil the requirements of the Contract in respect of HSSE,

ethics, anti-corruption and corporate social responsibility and all the requirements set forth herein and

conform to professional procurement practices and all applicable laws and regulations.

In all Subcontracts, Contractor shall strive to include regulations that limit project costs and risks while

facilitating a good project execution.

Contractor shall keep Company informed of any disputes or other circumstances related to Subcontracts that

may affect the establishment or operation of the Contract Object.

Contractor shall ensure that all project confidentiality requirements are implemented into all sub-contracts

and purchase orders and that all parties adhere to these requirements.

Contractor shall award Subcontracts to qualified, competent and professional contractors or suppliers who

have the experience and resources necessary to perform in accordance with the obligations of the Contract.

To ensure the required quality in project procurements, quality surveillance, expediting, examination, off-site

Mechanical Completion and FAT shall be performed in accordance with the requirements of the Contract,

the Procurement Package Follow-up Plan (PPFP) and the Purchase Orders.

Contractor shall ensure that noise requirements and necessary noise reducing measures are taken into

account in all purchases of equipment, to achieve the required noise levels for the Contract Object.

Page 39: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 39(49)

Standardization

Contractor shall comply with the standardisation philosophy in the Contract, including the requirements in

Appendix H. The Company may grant deviation if beneficial for use of Subcontractors’ standard designs,

cost and delivery time on a case by case basis.

Additional to the standardisation requirements in Appendix H, Contractor shall standardise the elements of

the Contract Object as far as reasonably possible, to reduce spare parts inventory, number of Subcontractors

and minimise the need for training.

Contractor shall follow-up all Subcontractors' performance with respect to standardization through all stages

of the manufacturing process.

Spare Part Procurement and Coordination

All procurement packages shall include Subcontractor recommended spare parts for commissioning and

plant start-up. Contractor shall provide an overview of Subcontractor recommended spare parts for

operations, including capital spares.

3.8.2 Fabrication

Contractor is responsible for all fabrication work necessary to complete the Work including but not limited

to:

▪ Prefabrication

▪ Fabrication

▪ Trial assembly (as required by Contractor)

▪ Assembly

▪ QC

▪ Preservation

▪ Preparations for transportation

All fabrication Work shall be performed in accordance with the specifications and requirements in

Appendices E and I.

Contractor shall continuously monitor and verify the quality of the fabrication according to the requirements

in Appendix D.

Contractor shall ensure that all welding, inspection and dimensional control is performed in accordance with

the project requirements and approved specifications and procedures.

3.8.3 Pressure Equipment Directive (PED)

Contractor shall ensure that all pressurised equipment, including piping systems, are designed and

documented to be in compliance with the governing rules and regulations, including the EU Pressure

Equipment Directive (PED), No. 2014/68/EU.

Contractor is responsible for CE marking of pressurised equipment, as required in the PED, and to obtain

Declarations of Conformity.

Company will engage a Third Party as Notifying Body, who will follow up the requirements of the PED in

Contractor’s Work.

Page 40: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 40(49)

3.9 Packaging and Transportation

Contractor is responsible for all packaging, load-out, transportation (including customs clearance and VAT

handling) and delivery to Company’s site of all elements of the Contract Object according to the terms and

conditions of the Contract.

Load-in, unloading, goods receipt and transports within and between Sites where the Work is performed

shall be planned, and performed by Contractor, and coordinated with Company in order not to jeopardize the

cement production and ongoing construction activities.

Contractor shall provide suitable means of transportation, and other equipment required for the transport

operations.

3.10 Construction and Installation at Company´s Site

Contractor shall ensure that all aspects of the construction are effectively controlled to complete the Contract

Object according to the Contract.

All installation operations shall be performed in such a way to avoid any personnel injury or damage to

existing structures, installations and equipment.

Contractor is aware that the Work at Company’s Site will be conducted in direct proximity, adjacent to and

from time to time integrated with a fully operational industrial production environment. It is acknowledged

that a continuous and stable operation of the Brevik Facility is of key importance to Company’s business

activities. Contractor shall at all times and in continuous cooperation and dialogue with Company use its best

commercial efforts to minimize any disturbance or impact of the Work on the cement production operations.

Contractor shall furthermore be responsible to take into account, sufficiently provide and plan for and to

mitigate any dependencies between the cement production operations and the Work.

No part of the Work that may cause disturbance or impact on the cement production operations shall be

commenced without Company’s prior written approval, such Work to be undertaken in close cooperation

with Company and in adherence to Company’s instructions from time to time. Contractor shall sufficiently

provide for any such parts of the Work in its production planning.

Contractor shall continuously monitor and verify the quality of construction according to the requirements in

Appendix D.

3.10.1 Temporary Facilities and Services

Contractor shall provide all construction facilities and site(s) outside Company’s site necessary for the

performance of the Work.

Contractor is responsible for accommodation of own and subcontractor’s personnel.

At Company’s site, Contractor shall provide the following facilities for performance of the Work:

▪ All necessary tools and equipment, including scaffolding

▪ Any necessary utilities, additional to those provided by Company (ref. Appendix F)

Utilization of Contractor’s scaffolding by other contractors shall be targeted and agreed in good faith when

feasible.

Page 41: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 41(49)

Facilities to be provided by Company are listed in Appendix F Company’s Deliverables.

The Contractor is responsible for all receiving and storage on site of materials required for the Work. All

materials and equipment shall be tagged and stored in such a way to allow for easy access for inspection and

identification.

3.10.2 Construction Work by Disciplines

Installation of Mechanical Equipment

Contractor shall provide and install the complete mechanical equipment and deliver the installations

inspected, documented and Mechanical Complete. The Equipment to be installed by Contractor is listed in

the Master Equipment List (MEL) to be provided by Contractor and included in Appendix I.

Structural Fabrication and Installation

Contractor shall prefabricate, assemble and install structural elements which shall be inspected, documented,

delivered Mechanical Complete.

Contractor shall ensure that all welding, inspection and dimensional control is performed in accordance with

the Contract requirements.

Ducting and piping Fabrication and Installation

Contractor shall prefabricate and install ducting and pipe spools including supports as required for the Work.

The ducting, pipes and supports shall be delivered documented and Mechanical Complete.

Contractor shall inspect, clean, surface protect and insulate all pipe work and instrumentation in accordance

with the Contract requirements, including Appendices A, E and I.

Contractor shall ensure that all welding, inspection and dimensional control is performed in accordance with

the Contract requirements.

Installation of Electrical

Contractor shall provide and install all motors and other electrical consumers and deliver the installations

inspected, documented and Mechanically Completed in accordance with the requirements in Appendices E

and I.

Equipment and structures that are metallic and do not have an electrically leading metal to metal connection,

shall be provided with earth studs/boss.

Installation of Instrumentation

Contractor shall provide and install all instrumentation, actuated dampers, control valves and other actuated

valves and deliver the installations inspected, documented and Mechanical Complete in accordance with the

requirements in Appendices E and I.

All instrumentation shall be installed with adequate support.

Page 42: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 42(49)

Installation of Technical Safety Equipment

Contractor shall provide and install all Technical Safety Equipment, including Personnel Protective

Equipment and deliver the installation inspected, documented and Mechanical Complete, in accordance with

Contract requirements, including Appendices E and I.

Surface Protection and Insulation

Contractor shall provide and install all surface protection and insulation and deliver the installations

inspected, documented and Mechanical Complete, in accordance with the requirements in Appendices E and

I.

3.11 Mechanical Completion (MC)

Contractor is responsible for all Mechanical Completion (MC) of the Contract Object, including quality

control checks to ensure that construction activities have been completed in accordance with governing rules

and regulations and the requirements in the Contract, including Appendices A, C, E and I.

Contractor will notify Company when any part system is Mechanically Complete and ready for hand-over

inspection. Any defects (including minor defects without any impact on the safety, performance or

functionality of the Contract Object, “punch list items”) shall be noted by Company in a protocol from such

inspection. After hand-over of any part system, both parties shall have access to the part system and its

designated area as agreed at handover.

Suitable IT tool(s) shall be used for follow-up of all MC activities, documenting MC complete on equipment

tag level. The IT tools to be used shall be agreed with Company upfront.

A manual for Mechanical Completion, describing how Mechanical Completion will be performed and

including checklists in a sufficient detail for Company and the State to verify the intended procedures for

Mechanical Completion, shall be delivered to Company and the State according to Appendix C.

The requirements of this section shall apply respectively to WP01, WP02 and WP03.

3.11.1 Preservation

Preservation and maintenance of preservation (re-preservation) shall be performed for all materials and

prefabricated items throughout all phases of the Work, i.e. with respect to WP01 in connection with WP02,

with respect to WP01 and WP02 in connection with WP03. Preservation shall be performed in accordance

with project requirements and in compliance with minimum requirements of vendor specifications for all

storage and transport conditions relevant for the Project.

3.12 Training

Contractor shall as part of the Work establish and perform a training program for Company's operational

personnel. The program shall be subject to Company’s approval and shall cover necessary training to operate

and maintain the Contract Object.

Contractor shall support the training of process operators and maintenance staff, by providing a training

program to be executed in connection with completion of each work package (WP01, WP02 and WP03) and

throughout Commissioning phase and plant start-up. The training of Company staff shall be completed prior

to plant start-up.

Page 43: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 43(49)

The parties shall in due time and good faith agree on the content and duration of the training program.

3.13 Mechanical Completion Protocol

Contractor shall establish and issue a Mechanical Completion Protocol confirming that the Contract Object is

MC complete, in accordance with Appendix C. The Mechanical Completion Protocol is subject to Company

approval.

The requirements of this section shall apply respectively to WP01, WP02 and WP03.

3.14 Commissioning Assistance

The requirements of this section shall apply respectively to WP01, WP02 and WP03.

Commissioning of all components included in the Contract Object shall be performed when Mechanically

Complete. Commissioning of the WP01 and WP02 components shall be performed in connection with the

relevant Winter Repair.

Company is responsible for Commissioning activities. Upon Company’s request, Contractor shall assist

Company in Commissioning.

Contractor shall provide the Commissioning assistance services as requested by Company from time to time

and/or as more precisely defined in a Commissioning plan (to be determined in collaboration between the

parties during the Contract Period). Such Commissioning services shall be provided by Contractor in

accordance with good engineering practice and Contractor is further expected to actively participate in the

planning and carrying-out of the Commissioning and to provide continuous feedback and suggestions to

Company in order to achieve the best possible result of the Commissioning.

Company may also request Contractor to provide personnel to be supervised and managed by Company with

Commissioning.

Subject to the above, Contractor shall provide, on a 24/7 basis, assistance personnel, temporary facilities and

services, equipment, tools etc. as requested by Company for the purpose of Commissioning. Company shall

provide the necessary raw materials, utilities, fuels and power.

3.15 Plant Start-up, Performance Demonstration Period, Performance Requirements and

Testing

3.15.1 Plant start-up

The requirements of this section shall apply respectively to WP01, WP02 and WP03.

Contractor shall assist Company in performing start-up of the Contract Object in accordance with

Company’s instructions. The terms of Section 3.13 above shall apply mutatis mutandis for start-up

assistance.

Contract Object shall be Mechanically Complete and fully commissioned, including Mechanical Completion

Protocol signed by Company, prior to start-up.

All procedures required for start-up and operation of Contract Object must be in place and approved by

Company before start-up.

Page 44: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 44(49)

3.15.2 Performance Demonstration Period after WP03

After Mechanical Completion of WP03, Commissioning and start-up of the complete CCS Facility,

performance demonstration of the complete CCS Facility shall be performed.

The purpose of the performance demonstration is to show that the complete CCS Facility functions in

accordance with the Contract.

Following the Performance Demonstration period, the Acceptance Test shall be performed (ref. section

3.15.3).

Contractor’s scope is to provide assistance and support to Company during performance demonstration and

Acceptance Test. The terms of Section 3.13 above shall apply mutatis mutandis for start-up assistance.

3.15.3 Performance requirements and testing

After each of WP01, WP02 and WP03, the relevant parts of the Works performed at each time shall be

subject to performance testing. The performed parts of the Contract Object shall at each performance test

satisfy the relevant requirements in the Technical Specification (Ref. 3) and this Contract, including

appendices A and E.

Obtaining a yearly CO2 capture capacity of 400 000 tonnes is of high importance to realise the intended

benefits of the Project. Optimised performance of the Contract Object is a critical pre-requisite to obtain the

target CO2 capture capacity. This will be an important focus area in the performance test following WP03

and throughout the Guarantee Period, based on cost benefit analyses.

All performance requirements will be subject to testing, as described in the following subsections. In

addition to the tests, long term verification of performance parameters will be executed throughout the

Guarantee Period, with the intent to verify that the parameters related to environmental emissions, noise and

CO2 specification are met, and to verify a positive development in performance of the Contract Object and

consistent long term and stable operations compliance.

Performance testing is not intended as a verification of all contractual requirements and for the sake of good

order it is explicitly noted that the performance tests do not limit Contractor’s obligations according to

Article 23.1 and 23.5 of the Conditions of Contract. It is specifically noted that some functions may not be

possible to test sufficiently in connection with WP01 and WP02, and Company is entitled to test the entire

Contract Object in connection with WP03 and Acceptance Test.

Acceptance Test

The purpose of the Acceptance Test is to demonstrate that the complete CCS Facility is finalised. For the

purpose of the Work and the Contract, the Acceptance Test will verify that the Contract Object functions in

accordance with the Contract.

The Acceptance Test shall as a minimum:

a) last for a period of 7 days

b) include all systems and utilities necessary for the CCS Facility to operate as intended;

c) deliver CO2 to interim storage;

d) include at least one loading operation of liquid CO2 to ship; and

e) comply with the relevant emission permits and regulatory requirements.

Page 45: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 45(49)

In case of failure to successfully complete the Acceptance Test, the Acceptance Test shall be repeated on the

same terms following rectification by Contractor as relevant.

Guarantee Period testing

Company intends to perform a comprehensive performance test of the Contract Object and its functioning in

connection with the expiry of the Guarantee period.

The purpose of the test is to demonstrate that the Contract Object satisfies the agreed performance

requirements. The test will be undertaken in a normal production and operating environment.

Notification, investigation and remedy process

In case of defects or deviations identified during any test or during operation of the cement plant and/or the

Contract Object, the Parties shall without delay jointly and in good faith investigate the cause of the defect or

deviation. Each Party shall provide each other with any information or access relating to the defect or the

deviation as may be reasonably required by the other Party to conduct its investigation.

Deviations and defects may be notified by Company at any time until the expiry of the Guarantee Period.

Rectification Work

If Contractor needs to make rectification work in order to meet the requirements of the Contract, Contractor

shall as soon as possible and no later than within two weeks after Company’s written notification prepare a

remedy plan for the faults/deficiencies for Company’s approval (not to be unreasonably withheld).

Rectification work shall be performed in accordance with Company’s instructions to ensure a minimum of

disturbances to the cement plant operations.

3.16 Completion Certificate

The Company shall issue a Completion Certificate to Contractor when Company has verified that the

Contract Object has been completed in accordance with the Contract:

▪ Scope of Work is completed

▪ Mechanical Completion Protocol is signed by Company

▪ Acceptance Test is successfully completed and approved by Company

▪ Completion Confirmation is issued by the State

▪ All punch list items are closed out

3.17 Provision of Spare Parts

Contractor shall provide an overview of all spare and wear parts with item numbers and prices, which

Contractor deems necessary for the following:

▪ To safeguard normal operation of the plant for two years of commercial production

▪ For critical equipment (capital spares)

Contractor shall deliver all spare and wear parts needed for commissioning, performance demonstration and

Acceptance Test.

Contractor shall also deliver a common capital spares (impeller and electric motor) for the main fans (HV1

and HV2).

Page 46: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 46(49)

All spare parts shall be properly packaged and labelled with the corresponding equipment tag number and

spare part item number.

3.18 Documentation

Contractor shall ensure that all their document deliveries as part of the Work is delivered to Company in

accordance with the requirements in Appendix C and D.

3.18.1 As-Built Documentation

In addition to the project documentation for operation (DFO) reflected in the MDR, the 3D model shall be

updated to reflect ,̧ as-built status (within such accuracy and level of detail which will be agreed in good

faith) of the Contract Object based on vendor drawings and mark-ups from the FC Contractor. Contractor

shall archive and keep available for Company following its request at any time and at no extra cost the raw

as-built data incorporated into the 3D model. 3D Model instructions are included in Appendix D.

The final 3D model is to be clash free, and shall as a minimum include all defined piping, equipment,

access/escape and mechanical handling routes, laydown and maintenance areas, obstruction volumes for

removal and withdrawal area, access platforms, stairs and ladders, in a common 3D model with all

structural elements, ducting, safety items, electrical and instrument items, insulation etc. All DFO shall

reflect As-Built status, but to ensure unambiguous status in operations, safety critical documents (P&IDs and

Cause & Effect diagrams) shall be re-issued in As-Built revision (irrespective of any changes to the

documents).

Page 47: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 47(49)

4. OPTIONS

4.1 Assistance in Run-in Period

Contractor shall provide necessary operational assistance during the Run-in Period when and as required by

Company. Operational assistance may be of different natures:

▪ Physical presence at site assisting in specific operations

▪ Remote assistance through analysis of operational data from historical database or real-time data and

recommended actions.

Further Operating Period assistance terms are set forth in the Conditions of Contract.

Page 48: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 48(49)

5. ATTACHMENTS

A01) NC03-NOCON-C-RA-0042 CCS Plot Plan, Rev. 03*

A02) NC03-NOCE-P-XA-0001, page 1 and 2 Process Flow Diagram Norcem Plant, Rev. XX*

A03) Interface Matrix

A04) Interface Register

*These drawings are included to illustrate the description of the Contract Object and will be subject to further

development in detailed engineering.

Page 49: ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT

DRAFT 19 Aug 2020 49(49)

6. REFERENCES

1) NC03-NOCE-Z-RA-0001 Overall Design Basis, Rev. 05

2) NC03-AKER-P-RA-0008 Estimated future process gas flows and conditions, Rev. C01

3) Technical Specification – Cement Plant Process Modifications

4) Norcem CCS Facility 3D CAD Model

5) NC03-NOCE-Z-RA-0027 Functional Design Specification (FDS) Tie-ins

6) HeidelbergCement’s Mechanical DCS “Process Fans”

7) HeidelbergCement’s Mechanical DCS “Thermal Insulation”

8) HeidelbergCement’s Mechanical DCS “Screw Conveyor”

9) HeidelbergCement’s Mechanical DCS “Expansion Joints”

10) HeidelbergCement’s Mechanical DCS “Process and de-dusting ducts”

11) HeidelbergCement’s Mechanical DCS “Guillotine Gates & Louvre Dampers”

12) HeidelbergCement’s Mechanical DCS “General Mechanical Design”