    L&T LDA Expansion ProjectS. Number: 169 &173 and plot A of CTS No. 170, 171/1 to

    12

    Old Mumbai-Pune Road, Lonavla, Dist. Pune.

    By

    Larsen & Toubro LimitedLarsen & Toubro Limited., Corporate HR L&D, 1st

    Floor, North Block II, Saki Vihar Road, Powai, Mumbai 400 072

  • ENCLOSURES

    Sr. No. Page No./ Description

    1. Appendix I 1 - 13

    2. Appendix II 1 - 11

    3. EMP 1 - 8

    4. Annexure I Location Map & Google Image

    5. Annexure II Master Layout Plan with Services Location

    6. Annexure III Area Statement

    7. Annexure IV Building Configuration and Occupancy Details

    8. Annexure V Parking Statement

    9. Annexure VI Parking Plan

    10. Annexure VII Water Demand & Water Budget

    11. Annexure VIII STP Details

    12. Annexure IX STP Layout & Schematic Diagram

    13. Annexure X Rain Water Harvesting Details

    14. Annexure XI Storm Water Drainage Layout

    15. Annexure XII Solid Waste Generation, Treatment and Disposal

    16. Annexure XIII Landscape Details & Plan

    17. Annexure XIV Energy Requirement & Conservation

    18. Annexure XV Fire Safety Details

    19. Annexure XVI List of Building Material

    20. Annexure XVII Environment Management Cost

  • Appendix I

  • Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

    Appendix I: L&T LDA Expansion Project by L & T Limited 1

    (See paragraph-6) Form 1

    (a) For item (I) relating to the Basic Information, the following shall be substituted, namely:-

    S. N. Item Details

    1 Name of the project L&T LDA Expansion Project by Larsen & Toubro Limited

    2 S. no in the scheduled 8 (a)

    3 Proposed capacity/ Area/ length/ tonnage to be handled/ command area/ lease area/ No. of wells to be drilled

    Area of Plot 71568.5 Sq. M

    Total BUA 27127.88 Sq. M

    4 New/Expansion /Modernization Expansion Project

    5 Existing Capacity/Area etc. Not Applicable

    6 Category of the project i.e. A or B Project category B2; Activity under Item 8 (a) of the EIA Notification dated 14th September 2006 as amended on 1st December , 2009 does not require scoping and public consultation

    7 Does it attract the general condition? If yes, please specify

    Not Applicable

    8 Does it attract the Specific conditions? If yes, please specify

    Not Applicable

    9 Location

    Plot/ Survey / Khasra No. S. Number: 169 &173 and plot A of CTS No. 170, 171/1 to 12 Old Mumbai-Pune Road, Lonavla, Dist. Pune

    Village Lonavla

    Tehsil Maval

    District Pune

    State Maharashtra

    10 Nearest railway station /Airport along with distance in Km

    ROADWAY: Old Mumbai - Pune Highway passes by the site as well as the site is connected through various roads

  • Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

    Appendix I: L&T LDA Expansion Project by L & T Limited 2

    RAILWAY: Lonavala railway station on Central Railway is at a distance 29.81 Km from the Project Site. AIRWAY: Lohgaon Airport at about 31.36 km from site

    11 Nearest town / city / district / Headquarters with distance in Km

    Pune City

    12 Village panchayats, Zilla Parishad, Municipal Corporation, Local body (complete postal addresses with telephone no. to be given

    Lonavala Municipal Council

    13 Name of the Applicant Mr. Neville Lobo

    14 Registered address Larsen & Toubro Limited., Corporate HR L&D, 1st Floor, North Block II, Saki Vihar Road, Powai, Mumbai 400 072

    15 Address for correspondence Larsen & Toubro Limited., Leadership Development Academy, Old Mumbai Pune Highway, Lonavala 410 401, Dist. Pune

    Name Mr. Neville Lobo

    Designation (Owner/Partner/CEO) Vice President, Corporate HR & Director Leadership Development Academy

    address Larsen & Toubro Limited., Corporate HR L&D, 1st Floor, North Block II, Saki Vihar Road, Powai, Mumbai 400 072

    Pin Code Mumbai 400 072

    E-mail E-Mail : neville.lobo@larsentoubro.com

    Telephone no. 022 67054010

    Fax No. --

    16 Details of alternatives sites examined, if any. Location of these site should be shown on topo sheet

    Please Refer Annexure I: Google Image Annexure II: Layout Plan Annexure III: Contour Map

    17 Interlinked Projects Not Applicable

    18 Whether separate application of interlinked project has been submitted?

    Not Applicable

  • Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

    Appendix I: L&T LDA Expansion Project by L & T Limited 3

    19 If yes, date of submission Not Applicable

    20 If no, reason --

    21 Whether the proposal involves approval/clearance ; Under if yes details of the same and their status to be given 1. Forest (Conservation) Act, 1980? 2. Wildlife (Protection) Act, 1972? 3. C.R.Z. Notification, 1991?

    Not Applicable

    22 Whether there is any government order/policy relevant relating to the site

    No

    23 Forest land involved (hectors ) No forest land involved

    24 Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? (a) Name of the court (b) Case no. (c) Orders/Directions of the court , if any and its relevance with the proposed project

    No, Not Applicable

    (II) ACTIVITY 1. Construction, Operation or decommissioning of the Project Involving actions, which

    will cause physical changes in the locality (Topography, land use, changes in water bodies, etc.)

    Sr. No

    Information/Checklist confirmation Yes/ No

    Details thereof (with approximate quantities / rates, wherever possible) with source of information data

    1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

    Yes Please Refer Annexure I: Google Image Annexure II: Layout Plan Annexure III: Contour Map

    1.2 Clearance of existing Land, vegetation and building?

    No No clearance of existing trees is required.

    1.3 Creation of new land uses? Yes As stated in Point 1.1

    1.4 Pre-construction investigation e.g. borehole, soil testing?

    Yes Soil testing is done on the project site.

  • Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

    Appendix I: L&T LDA Expansion Project by L & T Limited 4

    Sr. No

    Information/Checklist confirmation Yes/ No

    Details thereof (with approximate quantities / rates, wherever possible) with source of information data

    1.5 Construction works Yes The proposal pertains to construction of residential construction project. Please refer Annexure IV: Area Statement

    1.6 Demolition work No Not Applicable.

    1.7 Temporary sites used for construction works or housing of construction workers?

    No No housing at site. The workers from nearby areas will be engaged in construction activity.

    1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

    Yes Excavation for foundation is prominent activity. The debris and rubble removed would be used as filling material for leveling and for road construction. Top soil will be stored for landscaping

    1.9

    Underground works including mining or tunneling?

    No Not Applicable as the proposal pertains to construction of residential complex only.

    1.10 Reclamation works? No Not Applicable

    1.11 Dredging? No Not Applicable

    1.12 Offshore structures? No Not Applicable

    1.13 Production and manufacturing processes?

    No Not Applicable as the proposal pertains to construction project.

    1.14 Facilities for storage of goods or materials?

    No Temporary storage Godown will be provided for storage of construction material on site.

    1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

    Yes

    Please refer Annexure VII : Details of Solid Waste Generation, Treatment and Disposal

    1.16 Facilities for long term housing of operational workers?

    No Not Applicable since project under reference is expansion project.

    1.17 New road, rail or sea traffic during construction or operation?

    Yes The development will not have major impact on traffic pattern. Internal roads will be well constructed to manage traffic. Please refer Annexure XI: Parking Statement

    1.18 New road, rail, air waterborne or other Yes ROADWAY: Old Mumbai - Pune

  • Presented for Environmental Clearance under EIA Notification 2006 from SEIAA of Maharashtra

    Appendix I: L&T LDA Expansion Project by L & T Limited 5

    Sr. No

    Information/Checklist confirmation Yes/ No

    Details thereof (with approximate quantities / rates, wherever possible) with source of information data

    transport infrastructure including new or altered routes and stations, ports, airports etc?

    Highway is passing by the site as well as the site is connected through various roads RAILWAY: Lonavala railway station on Central Railway is at a distance 29.81 Km from the Project Site. AIRWAY: Lohgaon Airport at about 31.36 km from site.

    1.20 New or diverted transmission lines or pipelines?

    No Not Applicable

    1.21 Impoundment, damming, culverting, realignm