34
AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCE The proposed project involves development of parallel taxi track along with associated facilities which is a modification to the existing layout, which includes civil and mechanical works. There will be no change in the baseline environmental levels of various parameters before and after the implementation of proposed project. There will be no change in the land use as the proposed development is within the existing Airport premises. Being the proposed project is for improving the operability of runway capacity and comfort for passengers, there will be no change in socio- economic status after development of proposed facilities. Environmental clearance is issued for the existing layout including new terminal buildings vide 10-144/2007-IA III dated 15/03/2008. Considering the above it is requested to issue an amendment to the already issued Environmental Clearance including the following facilities. a. Construction of Parallel Taxi Track of dimension approx. 3710 X 23 mts. and shoulders of 10.5mts. b. Widening and strengthening of Link Taxiways N5, N6 and N7 to width 23 mts. and provision of shoulders of 10.5mts. in addition to N3, N4, N2 & N1. c. Development of filets of Taxiways N1 & N2. d. Replacement of air washer unit e. Relocation of borewell and associated works f. Construction of a perimeter road around Dumbell 08 for runway crossing and diversion of road around Dumbell 26. g. Diversion/Rerouting of Cables/Drain etc. h. Relocation of boundary wall for widening of Perimeter Road, relocation of Bomb cooling pit & GTC hut fouling in the alignment of PTT. i. Installation of 5 Nos. CCR in the existing substation of Indian Navy with remote control panel and installation of DG set of 325 KVA. j. Replacement of CAT-I ILS with New CAT-I ILS.

AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCE

The proposed project involves development of parallel taxi track along with

associated facilities which is a modification to the existing layout, which includes civil

and mechanical works. There will be no change in the baseline environmental levels

of various parameters before and after the implementation of proposed project. There

will be no change in the land use as the proposed development is within the existing

Airport premises. Being the proposed project is for improving the operability of

runway capacity and comfort for passengers, there will be no change in socio-

economic status after development of proposed facilities. Environmental clearance is

issued for the existing layout including new terminal buildings vide 10-144/2007-IA III

dated 15/03/2008.

Considering the above it is requested to issue an amendment to the already issued

Environmental Clearance including the following facilities.

a. Construction of Parallel Taxi Track of dimension approx. 3710 X 23 mts. and shoulders of 10.5mts.

b. Widening and strengthening of Link Taxiways N5, N6 and N7 to width 23 mts. and provision of shoulders of 10.5mts. in addition to N3, N4, N2 & N1.

c. Development of filets of Taxiways N1 & N2. d. Replacement of air washer unit e. Relocation of borewell and associated works f. Construction of a perimeter road around Dumbell 08 for runway crossing and

diversion of road around Dumbell 26. g. Diversion/Rerouting of Cables/Drain etc. h. Relocation of boundary wall for widening of Perimeter Road, relocation of

Bomb cooling pit & GTC hut fouling in the alignment of PTT. i. Installation of 5 Nos. CCR in the existing substation of Indian Navy with

remote control panel and installation of DG set of 325 KVA. j. Replacement of CAT-I ILS with New CAT-I ILS.

Page 2: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

PRE-FEASIBILITY REPORT FOR

CONSTRUCTION OF PARALLEL TAXI TRACK AT DABOLIM AIRPORT, GOA

Page 3: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

1.0 EXECUTIVE SUMMARY In order to meet the growing Air Traffic in Goa AAI, has constructed and commissioned New Integrated Terminal Building in March 2014 with peak hour capacity of 2750 Pax. (2000 Domestic and 750 International) having 5 Nos. Aerobridges. Presently, the parking of Aircraft capacity is 2 Nos. B category and 8 Nos. C category or 2 Nos. B category plus 5 Nos. C category and 2 Nos. D/E category. Dabolim Airport is a Naval Airport wherein the ATC is handled by Indian Navy. CNS facilities are also handled by Indian Navy. Airport Authority of India (AAI) handles Aircraft on Civil Apron, Terminal Building and City side facilities. Due to the absence of Parallel Taxi Track on the northern side of Runway 08 - 26, landed Aircraft has to backtrack on the runway to reach the Civil Apron using the Taxiways N1/N2, N4, N5 or using curtailed Parallel Taxi Track on the southern side involving crossing of runway. This process limits the runway capacity of handling Aircraft. With the present arrangement/procedure of Aircraft movement during takeoff and landing, due to the absence of Parallel Taxi Track on the northern side of the Runway, it has negative effect on the turnaround time of the Aircraft. The runway efficiency is also getting limited due to backtracking of Aircraft after landing using either Taxiway N4 & N5 or using southern side part Taxi Track involving crossing of runway. In order to reduce the runway occupancy time by Civil Flights, a full length parallel taxi track suitable for B747 type of Aircraft is required to be constructed. AAI and Indian Navy entered into a MOU for the same as AAI and Indian Navy to share the cost of construction 50:50. It is proposed to modify the existing layout to accommodate parallel taxiway and associated facilities to improve runway capacity and comfort of passengers. The schedule of project is envisaged as 30 months with an estimated cost of Rs.183 crores. There will be no addition of water requirement and generation of wastewater, solid waste after modification of layout.

2.0 INTRODUCTION Goa Airport at Dabolim is in existence since 1966 serving the civilian flights apart from meeting the defence requirements (Indian Navy). The Airport has seen gradual expansion in line with the Air Traffic Growth. The Apron capacity as well as Terminal capacity (Old) has been expanded in the past. In the year 2009, Apron capacity has been augmented to park total 10 Nos. Aircraft of C category. Dabolim Airport at Goa has seen phenomenal growth in the Air Traffic since 2007 which has been shown in the graphical form. Goa has the distinction of attracting foreign tourists who visit by Charter flights. In the year 2013-14, the number of Domestic passengers were 31,53,302 Nos., International passengers were 7,36,340 Nos., number of Domestic flights were 25,376 Nos., International flights were 4,420 Nos. and Chartered Flights were 1,141 Nos. In order to meet the growing Air Traffic in Goa AAI, has constructed and commissioned New Integrated Terminal Building in March 2014 with peak hour capacity of 2750 Pax. (2000 Domestic and 750 International) having 5Nos. Aerobridges. Presently, the parking of Aircraft capacity is 2Nos. B category and 8Nos. C category or 2Nos. B category plus 5Nos. C category and 2Nos. D/E category. Dabolim Airport is a Naval Airport wherein

Page 4: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

the ATC is handled by Indian Navy. CNS facilities are also handled by Indian Navy. Airport Authority of India (AAI) handles Aircraft on Civil Apron, Terminal Building and City side facilities. Due to the absence of Parallel Taxi Track on the northern side of Runway 08 - 26, landed Aircraft has to backtrack on the runway to reach the Civil Apron using the Taxiways N1/N2, N4, N5 or using curtailed Parallel Taxi Track on the southern side involving crossing of runway. This process limits the runway capacity of handling Aircraft. With the present arrangement/procedure of Aircraft movement during takeoff and landing, due to the absence of Parallel Taxi Track on the northern side of the Runway, it has negative effect on the turnaround time of the Aircraft. The runway efficiency is also getting limited due to backtracking of Aircraft after landing using either Taxiway N4 & N5 or using southern side part Taxi Track involving crossing of runway. In order to reduce the runway occupancy time by Civil Flights, a full length parallel taxi track suitable for B747 type of Aircraft is required to be constructed. AAI and Indian Navy entered into a MOU for the same as AAI and Indian Navy to share the cost of construction 50:50. AAI entrusted the task of carrying out Environmental Impact Assessment (EIA) study to Engineers India Limited (EIL). This document is prepared by EIL as per guidelines for preparations of Pre-Feasibility Report issued by MOEF vide Letter No. J-11013/41/2006-IA.II (I) dated 30/12/2010.

3.0 PROJECT DESCRIPTION Goa airport is situated in Chikalim Village at Vasco-Da-Gama in south Goa District. It is located at a distance of about 30 KM from Panjim. It is well connected road or by rail, situated in the western part of the state. Goa is an undulating tableland, covered in parts by Iron, Maganese. It is lining the state’s eastern border are the thickly forested mountains of the Western Ghats (Sahyadris) that separate it from parched Deccan Plateau of Western Karnataka and is emerging as one of the fastest growing cities on the industrial map of India. It has well developed means of communication and infrastructural facilities and it appears that there is no constraint in the rapid growth of the region. The existing airport is situated in Chikalim village at Vasco in south Goa district at 15o 22' 48.94”N latitude and 73o 49'58.90” E longitude. NH-17A is at a distance of about 200 m from the project location. The district is surrounded by Panaji district at the north, Arabian Sea in the west, Mormugaon at the south and Ponda district at the east. Physiographically the study area of the project comes under Taluka namely Mormugao, Salcete and Tiswadi at an elevation above MSL is 44.5 m. The nearest railway station is Vasco Railway Station which is about 5 KM from the site at the north-west. The location map of existing airport is given in Figure 1.0:

Page 5: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Figure 1.0: Location map of Dabolim Airport, Goa

Page 6: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

The layout of the existing airport is shown in Figure 2.0.

Figure 2.0: Layout of the airport The proposed project involves the modification of existing layout to accommodate the following: a) Parallel Taxi Track of dimension approx. 3710 X 23 mts. and shoulders of 10.5mts. b) Widening and strengthening of Link Taxiways N5, N6 and N7 to width 23 mts. and

provision of shoulders of 10.5mts. in addition to N3, N4, N2 & N1. c) Development of filets of Taxiways N1 & N2. d) Replacement of air washer unit e) Relocation of borewell and associated works f) Construction of a perimeter road around Dumbell 08 for runway crossing. g) Diversion/Rerouting of Cables/Drain etc. h) Relocation of boundary wall for widening of Perimeter Road, relocation of Bomb

cooling pit & GTC hut fouling in the alignment of PTT.

i) Installation of 5 Nos. CCR in the existing substation of Indian Navy with remote control panel and installation of DG set of 325 KVA.

j) Replacement of CAT-I ILS with New CAT-I ILS. Details of estimates for each of activities are given in subsequent sections.

Page 7: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

3.1 Construction of Parallel Taxi Track Details of quantity estimation for each of work involved in construction of parallel taxi track are given in Table 1.0.

Table 1.0: Quantity estimation for works involved in construction of parallel taxi track

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

1 Excavation in soil with hydraulic excavator

Quantity calculation as per earth work calculation sheet 2,27,934.69 For laying NP4 pipe for diverting the existing

drain 1 x 190.00 x 4.00 x 4.00 3,040.00

Shoulder of new apron (Partly) 1 x 1 x 163.89 x 10.50 x 0.28 481.84

2,31,456.53

Say 2,31,457.00 Cum

Considering 20% as soil 1(a) 46,291.31 Cum

Considering 80% as ordinary rock 1(b) 1,85,165.22 Cum

2 Earth work in foundation tranches (0.9+3.35)/2=

Drain 1 x 2 x 2,948.00 x 2.13 x 1.225 15,348.03 Drain side 2 x 2 x 2,948.00 x 1.00 x 0.225 2,653.20

18,001.23 cum

3 Construction of embankment including

Quantity calculation as per earth work calculation sheet 6,79,588.83 6,79,588.83

Re-usable materails from excavation 2,03,352.00

4,76,236.83 SAY 4,76,237.00 Cum

4 Consolidation of sub-grade

Link taxi 2 x 127.50 x 44.00 11,220.00

New Apron Shoulder 1 x 163.89 x 33.50 5,490.32 Old Apron Shoulder 1 x 126.00 x 33.50 4,221.00

Bay No. 3 & 4 1 x 147.50 x 23.00 3,392.50

Service road 1 x 300.00 x 4.50 1,350.00

1 x 200.00 x 4.50 900.00 Parallel taxi 1 x 2,680.00 x 44.00 1,17,920.00

Fillet 2 x 1,100.00 2,200.00

1,46,693.82 sqm

5 Preparation of sub-grade

Connnecting road from peripheral road to parallel taxi track

1 x 300.00 x 4.50 1,350.00

Road connecting from localizer building to localizer antenna

1 x 200.00 x 4.50 900.00

2,250.00 sqm

6 Providing, laying, spreading and compacting graded stone(WMM)

Parallel Taxi-track 1 x 2680.00 x 23.00 x 0.25 15,410.00 Parallel Taxi-track shoulder 2 x 2680.00 x 10.50 x 0.25 14,070.00

Fillet for Parallel taxitrack 2 x 1100.00 x x 0.25 550.00

Service road connecting to parallel taxi 1 x 300.00 x 4.50 x 0.20 270.00

1 x 200.00 x 4.50 x 0.20 180.00 New apron shoulder 1 x 1 x 163.89 x 23.00 x 0.25 942.37

In between N1 & N2 1 x 1 x 126.00 x 23.00 x 0.25 724.50

1 x 1 x 126.00 x 10.50 x 0.25 330.75

Bay No. 3 & 4 1 x 1 x 147.50 x 23.00 x 0.25 848.13 North Side Shoulder 1 x 1 x 100.00 x 10.50 x 0.25 262.50

33,588.24

Say 33,589.00 Cum

7 Providing and laying Polythene Sheet Parallel Taxi-track i/c shoulder 1 x 2680.00 x 44.00 1,17,920.00

add for fillet 2 X 1100.00 2,200.00

Parallel taxi track in New apron area shoulder

1 x 1 x 163.89 x 33.50 5,490.32

In between N1 & N2 including shoulder

1 x 1 x 126.00 x 33.50 4,221.00

Page 8: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

Bay No. 3 & 4 1 x 1 x 147.50 x 23.00 3,392.50 North Side Shoulder 1 x 1 x 100.00 x 10.50 1,050.00

1,34,273.82

Say 1,34,274.00 Sqm

8 Providing and laying pavement quality cement concrete

Parallel Taxi-track 1 x 2680.00 x 23.00 x 0.52 32,052.80

Parallel Taxi-track shoulder 2 x 2680.00 x 10.50 x 0.28 15,758.40

Fillets 2 x 1100.00 x 0.46 1,012.00

New apron shoulder 1 x 1 x 163.89 x 23.00 x 0.52 1,960.12 Parallel taxi track shoulder 1 x 1 x 163.89 x 10.50 x 0.28 481.84

In between N1 & N2 1 x 1 x 126.00 x 23.00 x 0.52 1,506.96

shoulder 1 x 1 x 126.00 x 10.50 x 0.28 370.44 1 x 147.50 x 23.00 x 0.52 1,764.10

North Side Shoulder 1 x 1 x 100.00 x 10.50 x 0.28 294.00

55,200.66

Say 55,201.00 Cum

9 Providing, laying and fixing in position closed-cell, U-V resistant

Parallel Taxi-track 1 x 59 x 23.00 x 0.50 678.50

Parallel Taxi-track shoulder 2 x 59 x 10.50 x 0.26 322.14

Fillets 1 x 2 x 50.00 x 0.50 50.00 Parallel taxi track in New apron area

shoulder 1 x 4 x 23.00 x 0.50 46.00

1 x 4 x 10.50 x 0.26 10.92

In between N1 & N2 shoulder 1 x 5 x 3.00 x 0.50 57.50

1 x 5 x 10.50 x 0.26 13.65 Bay No. 3 & 4 1 x 4 x 23.00 x 0.50 46.00

North Side Shoulder 1 x 1 x 100.00 x 0.26 26.00

1 x 2 x 10.50 x 0.26 5.46 1,256.17

Say 1,257.00 Sqm

10 P&L expansion joints

Parallel Taxi-track 1 x 59 x 23.00 1,357.00

Parallel Taxi-track shoulder 2 x 59 x 10.50 1,239.00

Fillets 1 x 2 x 50.00 100.00 Parallel taxi track in New apron area

shoulder 1 x 4 x 23.00 92.00

1 x 4 x 10.50 42.00

In between t N1 & N2 including shoulder

1 x 5 x 23.00 115.00

1 x 5 x 10.50 52.50

Bay No. 3 & 4 1 x 4 x 23.00 92.00

North Side Shoulder 1 x 1 x 100.00 100.00

1 x 2 x 10.50 21.00 3,210.50

say 3,211.00 m

11 Providing tack coat a) ON WBM @ 0.75 kg/sqm

Roads 1 x 300.00 x 4.50 1,350.00 1 x 200.00 x 4.50 900.00

2,250.00 sqm

b) On bituminous surface@ 0.5 kg/sqm

Roads 1 x 300.00 x 4.50 1,350.00 1 x 200.00 x 4.50 900.00

2,250.00 sqm

12 Providing and laying Bitumen Penetration Macadam On Roads 1 x 300.00 x 4.50 x 0.05 67.50

1 x 200.00 x 4.50 x 0.05 45.00

112.50

say 113.00 cum

13 Providing and laying 4 cm thick bitumastic sheet with hot bitumen On Roads 1 x 300.00 x 4.50 x 0.05 67.50

1 x 200.00 x 4.50 x 0.05 45.00

Page 9: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

112.50 cum

14 Runway/apron/taxiway painting

For White, Yellow and Red Colour.

Link taxitrack 2 x 127.50 x 44.00 x 0.03 336.60

Parallel taxitrack 1 x 3240.00 x 23.00 x 0.03 ,235.60 Shoulder 2 x 3240.00 x 10.50 x 0.03 2,041.20

Bitumen Road 1 x 1500.00 x 4.50 x 0.03 202.50

1 x 300.00 x 4.50 x 0.03 40.50

1 x 200.00 x 4.50 x 0.03 27.00

4,883.40 say 4,884.00 sqm

15(a) C. Conc.(1:2:4)

1000 mm dia hume pipe crossing 1 x 2 x 50.00 x 3.20 x 2.00 640.00

450 mm dia hume pipe crossing 1 x 3 x 50.00 x 1.60 x 0.90 216.00

1 x 2 x 3.14 x 0.6^2 x 50.00 (113.11)

Deduction for 450 mm dia pipe 1 x 3 x 3.14 x 0.225^2 x 50.00 (23.86)

LS Qty for rampage works adjesent to PTT

1 x 4 x 50.00 x 3.20 x 0.30 192.00

LS qty for manholes adjesent to PTT 1 x 24 x 1.96 x 1.96 x 0.15 13.83

Retaining wall 1 x 1 x 100.00 x 3.20 x 0.10 32.00

956.86

SAY 957.00 Cum

16 R.C.C (1:1.5:3)

R.C.C Culvert

Bottom 1 x 4 x 50.00 x 3.1 x 0.35 217.00

Wall 2 x 4 x 50.00 x 2.00 x 0.40 320.00

slab 1 x 4 x 50.00 x 3.10 x 0.30 186.00

For diversion of existing NP4 pipe drain R.C.C Manhole(3 No) wall 3 x 4 x 4.00 x 5.00 x 0.5 120.00

Slab 1 x 3 x 4.00 x 4.00 0.35 16.80

Raft 1 x 3 x 5.00 x 5.00 0.50 37.50

Retaining wall Raft 1 x 1 x 100.00 x 3.00 x 0.40 120.00

Wall 1 x 1 x 100.00 x 7.00 x 0.30 210.00

1,227.30

say 1,228.00 cum

17 Centering and shuttering

LS qty for rampage, manhole works etc adjacent to PTT

2 x 4 x 50.00 x 0.30 120.00

R.C.C Culvert

Bottom 2 x 4 x 50.00 x 0.35 140.00

2 x 4 x 3.10 x 0.35 8.68

Wall outside 2 x 4 x 50.00 x 2.20 880.00 Wall inside 2 x 4 x 50.00 x 1.85 740.00

Slab 1 x 4 x 50.00 x 3.10 620.00

Slab side 2 x 4 x 3.10 x 0.30 7.44

For diversion of existing NP4 pipe drain R.C.C Manhole(3 No) wall 3 x 8 x 4.00 x x 5.00 480.00

Slab bottom 1 x 3 x 4.00 x 4.00 48.00

Slab side 3 x 4 x 4.00 x 0.35 16.80

Raft 3 x 4 x 4.00 x 0.50 24.00 Retaing wall

raft 1 x 2 x 100.00 x 0.40 80.00

PCC 1 x 2 x 100.00 x 0.20 40.00

Wall 1 x 2 x 100.00 x 7.00 1,400.00 4,604.92

SAY 4,605.00 Sqm

18 Pre-cast reinforced cement concrete

LS Qty for manhole covers 1 x 24 x 1.96 x 1.96 x 0.30 27.66

SAY 28.00 cum

Page 10: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

19 Reinforcement ( TMT bars) RCC Culvert

Taking as 125 kg per cum 1 x 1,228.00 x 125 1,53,500.00

Chambers Covers

Taking as 90kg per cum 1 x 28.00 x 90 2,520.00 Considering 150m of parallel taxi as RCC instead of PQC

PQC = 1587cum @ 125kg/cum 1,587.00 x 125 1,98,375.00

3,54,395.00

SAY 3,54,395.00 kg

20 Brick Work (1:4)

Man Hole Chamber 24 x 4 x 1.73 x 0.23 x 1.80 68.76

say 69.00 cum

21 15mm rough cast plaster 1:4

Man hole chambers 1 x 24 x 4.00 x 1.5 x 1.8 259.20

say 260.00 sqm

22 Dry stone pitching 22.5 cm thick

Drain along parallel taxi

Perimeter= 2x1.00+2x1.58+0.9=6.06m

1 x 2 x 2,948.00 x 6.06 35,729.76

Considering 70% area 35,729.76 x 0.70 25,010.83

say 25,011.00 sqm

23 Pointing on stone work (1:3)

Considering 70% area 35,729.76 x 0.70 25,010.83

25,011.00 sqm

24 Demolishing c.conc. i/c disposal of material within 50 m lead (1:3:6 or

richer mix)

a) Crossing of N3, N4, N5 N6, N7 2 x 5 x 10.50 x 23.00 x 0.28 676.20

Shoulder of new apron 1 x 1 x 163.89 x 10.5 x 0.28 481.84

Bay 3 & 4 1 x 1 x 147.50 x 23.0 x 0.40 1,357.00

SAY 2,516.00 cum

25 Providing NP-4 pipe

a) 450 mm dia pipe

LS Qty 1 x 2 x 50.00 100.00

100.00

m

b) 1000 mm dia pipe LS qty 1 x 4 x 50.00 200.00

for diverting existing drain 1 x 2 x 190.00 380.00

580.00 m

26 Dismantling including stacking of serviceable material and disposal of unserviceable material within 50 metres lead Water Bound Mecadam road - (Wet Mix Mecadam consider as similar to WBM for dismantling )

Shoulder of new apron 1 x 1 x 163.89 10.50 1,720.85 Bay No 3$4 1 x 1 x 147.50 23.00 3,392.50

Crossing of N3, N4, N5, N6, N7 2 x 5 x 10.50 x 23.00 2,415.00

7,528.35

7,529.00 sqm

27 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

Total Excavation of All kind of soil 46,291.31

Total Excavation of ordinary rock 1,66,648.70

2,12,940.00

Take 95 % for filling 2,02,293.00

2,03,352.00 cum

28 Crushing of excavated ordinary rock boulders of 75 mm or more size in an integrated stone crushing unit of 200 tonners per hour capacity with arrangement of noise and dust adoptor comprising of primary and secondary crushing unit, belt converyor and vibrating

Page 11: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

screens to obtain soil of 75 mm or less size to meet Morth specification for filling material including transpoting to the embankment site with all lead and lift.

Total Excavation of ordinary rock 1,85,165.22

Taking 90% for filling 1,66,648.70

1,66,648.70 cum

29 Dismantling/Demolishing includingstacking of serviceable

material and disposal of unserviceable material with in

50 meters lead Bituminous road

Runway shoulder and parrallel taxi 1 x 4 x 10.50 x 60.00 2,520.00

intersection

GTC road 1 x 2 x 7.00 x 44.00 616.00

3,136.00 3,136.00 sqm

30 Designing, Providing, casting and erecting in position precast reinforced M-35 Grade For retaining wall 1 x 330.00 x 8.50 2,805.00

Reinforced facia panels 1 x 330.00 x 6.60 2,178.00

1 x 120.00 x 0.80 96.00 1 x 120.00 x 0.50 60.00

1 x 390.00 x 2.80 1,092.00

1 x 390.00 x 2.51 978.90

1 x 390.00 x 6.20 2,418.00 1 x 390.00 x 3.80 1,482.00

1 x 240.00 x 0.75 180.00

11,289.90 sqm

31 Runway/apron/taxiway painting

For Black Colour

Parallel taxitrack 1 x 3240.00 x 23.00 x 0.0225 1,676.70 Shoulder 2 x 3240.00 x 10.50 x 0.0225 1,530.90

Bitumen Road 1 x 1500.00 x 4.50 x 0.0225 151.88

1 x 300.00 x 4.50 x 0.0225 30.38

1 x 200.00 x 4.50 x 0.0225 20.25

3,410.10 say 3,411.00 sqm

Page 12: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

3.2 Widening and strengthening of Link Taxiways Details of quantity estimation for each of work involved in construction of parallel taxi track is given in Table 2.0.

Table 2.0: Quantity estimation for works involved in widening and strengthening of Link Taxiways

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

1 Excavation in soil with hydraulic excavator LS Qty 1 x 1 x 50.00 x 3.50 x 1.50 262.50

262.50

Say 263.00 Cum

Considering 20% as soil 1(a) 52.50 Cum

Considering 80% as ordinary rock 1(b) 210.00 Cum

2 Earth work in foundation tranches

LS Qty for drain crossing 2 x 5 x 10.00 x 2.00 x 2.000 400.00

400.00 cum 3 Construction of embankment including

LS qty for rampage works 500.00

SAY 500.00 Cum

4 Consolidation of sub-grade N3, N4 & N5 3 x 127.50 x 44.00 16,830.00

N6 & N7 2 x 127.50 x 44.00 11,220.00

Fillet 18 x 1,100.00 19,800.00

Crossing of N3, N4, N5 shoulder 3 x 2 x 10.50 x 23.00 1,449.00

49,299.00 sqm

5 Preparation of sub-grade LS Qty 200.00

200.00 sqm

6 Providing, laying, spreading and compacting graded stone(WMM)

Link taxitrack 2 x 127.50 x 23.00 x 0.25 1,466.25

Link taxitrack shoulder 4 x 127.50 x 10.50 x 0.25 1,338.75 N3, N4 & N5 3 x 127.50 x 23.00 x 0.25 2,199.38

N3, N4 & N5 Shoulders 6 x 127.50 x 10.50 x 0.25 2,008.13

N6 & N7 2 x 127.50 x 23.00 x 0.25 1,466.25

N6 & N7 shoulder 4 x 127.50 x 10.50 x 0.25 1,338.75 Fillet for Link taxitrack 4 x 1100.00 x x 0.25 1,100.00

Fillet for N3, N4, N5, N6 & N7 20 x 1100.00 x x 0.25 5,500.00

Crossing of N3, N4, N5 shoulder 3 x 2 x 10.50 x 23.00 x 0.25 362.25

16,779.75 Say 16,780.00 Cum

7 Providing and laying Polythene Sheet

Link taxitrack i/c shoulder 2 x 148.50 x 44.00 13,068.00

N3, N4 & N5 i/c shoulder 3 x 127.50 x 44.00 16,830.00

N6 & N7 i/c shoulder 2 x 127.50 x 44.00 11,220.00

add for fillet 24 X 1100.00 26,400.00

Crossing of N3, N4, N5 shoulder 3 x 2 x 10.50 x 23.00 1,449.00

68,967.00

Say 68,967.00 Sqm

8 Providing and laying pavement quality cement concrete

Link taxitrack 2 x 148.50 x 23.00 x 0.52 3,552.12

Link taxitrack shoulder 4 x 127.50 x 10.50 x 0.28 1,499.40

N3, N4 & N5 3 x 148.50 x 23.00 x 0.52 5,328.18

N3, N4 & N5 SHOULDER 6 x 127.50 x 10.50 x 0.28 2,249.10

N6 & N7 2 x 148.50 x 23.00 x 0.52 3,552.12

N6 & N7 SHOULDER 4 x 127.50 x 10.50 x 0.28 1,499.40

Fillets 24 x 1100.00 x 0.46 12,144.00

Crossing of N3, N4, N5 shoulder 3 x 2 x 10.50 x 23.00 x 0.52 753.48

30,577.80

Say 30,578.00 Cum

Page 13: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

9 Providing, laying and fixing in position closed-cell, U-V resistant

Link taxitrack 2 x 4 x 23.00 x 0.50 92.00

Link taxitrack shoulder 2 x 8 x 10.50 x 0.26 43.68

N3, N4 & N5 3 x 4 x 23.00 x 0.50 138.00

N3, N4 & N5 shoulder 3 x 8 x 10.50 x 0.26 65.52

N6 & N7 2 x 4 x 23.00 x 0.50 92.00

N6 & N7 shoulder 2 x 8 x 10.50 x 0.26 43.68

Fillets 1 x 24 x 50.00 x 0.50 600.00

Crossing of N3, N4, N5 shoulder 3 x 4 x 10.50 x 0.50 63.00

1,137.88

Say 1,138.00 Sqm

10 P&L expansion joints

Link taxitrack 2 x 4 x 23.00 184.00

Link taxitrack shoulder 2 x 8 x 10.50 168.00

N3, N4 & N5 3 x 4 x 23.00 276.00

N3, N4 & N5 shoulder 3 x 8 x 10.50 252.00

N6 & N7 2 x 4 x 23.00 184.00

N6 & N7 shoulder 2 x 8 x 10.50 168.00

Fillets 1 x 24 x 50.00 1,200.00

Crossing of N3, N4, N5 shoulder 3 x 4 x 10.50 126.00

2,558.00

say 2,558.00 m

11 Providing tack coat

a) ON WBM @ 0.75 kg/sqm

LS Qty 200.00

200.00 sqm

b) On bituminous surface@ 0.5 kg/sqm

LS Qty 200.00

200.00 sqm

12 Providing and laying Bitumen Penetration Macadam

LS Qty 20.00

say 20.00 cum

13 Providing and laying 4 cm thick bitumastic sheet with hot bitumen

LS Qty 20.00

0.00 cum

14 Runway/apron/taxiway painting

For White, Yellow and Red Colour.

N3, N4 & N5 3 x 127.50 x 44.00 x 0.03 504.90

N6 & N7 2 x 127.50 x 44.00 x 0.03 336.60

LS qty 50.00

891.50

say 892.00 sqm

15(a) C. Conc.(1:2:4)

for bedding and encasing of one row of 1000 mm dia hume pipe crossing & 2rows of 450mm dia hume pipe crossing per one crossing (5 no's)

1 x 5 x 50.00 x 3.45 x 1.50 1,293.75

Deduction for 1000 mm dia pipe 0.5 x 5 x 3.14 x 0.6^2 x 50.00 (141.39)

Deduction for 450 mm dia pipe -1 x 10 x 3.14 x 0.225^2 x 50.00 (79.53)

1,072.83

SAY 1,073.00 Cum

15(b) Cement concrete (1:4:8)

Manhole 1 x 24 x 1.96 x 1.96 x 0.15 13.83

LS qty for floor bedding, merging 100.00

Page 14: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

etc

113.83

SAY 114.00 cum

16 R.C.C (1:1.5:3)

R.C.C Culvert

Bottom 1 x 5 x 50.00 x 3.1 x 0.35 271.25

Wall 2 x 5 x 50.00 x 2.00 x 0.40 400.00

slab 1 x 5 x 50.00 x 3.10 x 0.30 232.50

LS qty for manholes t junction of box & pipe culverts 50.00

Retaining wall Raft 2 x 5 x 5.00 x 1.40 x 0.30 21.00

Wall 2 x 5 x 5.00 x 0.40 x 1.50 30.00

1,004.75

say 1,005.00 cum

17 Centering and shuttering R.C.C Culvert

Bottom 2 x 5 x 50.00 x 0.35 175.00

2 x 5 x 3.10 x 0.35 10.85

Wall outside 2 x 5 x 50.00 x 2.20 1,100.00 Wall inside 2 x 5 x 50.00 x 1.85 925.00

Slab 1 x 5 x 50.00 x 3.10 775.00

Slab side 2 x 5 x 3.10 x 0.30 9.30

1000 mm dia hume pipe 2 x 8 x 50.00 x 1.50 1,200.00 450 mm dia hume pipe 2 x 12 x 50.00 x 0.95 1,140.00

LS qty for manholes t junction of box & pipe culverts 375.00

Retaing wall

raft 4 x 5 x 5.00 x 0.30 30.00 PCC 4 x 5 x 5.00 x 0.20 20.00

Wall 4 x 5 x 5.00 x 1.50 150.00

5,910.15

SAY 5,911.00 Sqm

18 Pre-cast reinforced cement concrete Man hole cover 2 x 5 x 1.96 x 1.96 x 0.15 2.88

SAY 3.00 cum

19 Reinforcement ( TMT bars)

Taking as 125kg per cum 1 x 1,008.00 x 125 1,26,000.00

1,26,000.00 SAY 1,26,000.00 kg

20 Brick Work (1:4)

LS Qty for Man Hole Chamber 2 x 5 x 1.73 x 0.23 x 1.80 7.16

say 8.00 cum

21 15mm rough cast plaster 1:4

LS Qty for Man Hole Chamber 2 x 5 x 4.00 x 1.5 x 1.8 108.00 say 108.00 sqm

22 Dry stone pitching 22.5 cm thick

Drain along parallel taxi

LS adjasent to crossing of drain etc 2 x 5 x 4.00 x 4.00 80.00

say 80.00 sqm

23 Pointing on stone work (1:3) LS Qty 10.00

10.00 sqm

24 Demolishing c.conc. i/c disposal of material within 50 m lead (1:3:6 or richer mix)

N3, N4, N5, N6 & N7 Demolishing 5 x 1 x 148.50 x 23.00 x 0.28 4,781.70

5 x 2 x 148.50 x 10.50 x 0.15 2,338.88

SAY 7,121.00 cum

25 Providing NP-4 pipe

a) 450 mm dia pipe

2 x 5 x 50.00 500.00

500.00 m

b) 1000 mm dia pipe 1 x 5 x 50.00 250.00

250.00 m

26 Dismantling including stacking of serviceable material and disposal of unserviceable material within 50 metres lead Water Bound Mecadam road - (Wet Mix Mecadam consider as similar to WBM for dismantling )

Page 15: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

N3, N4, N5 & N6 5 x 1 x 126.00 44.00 27,720.00

1 x 10 x 10.50 23.00 2,415.00

30,135.00 sqm

27 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

LS Qty adjacent to culverts, retaining walls etc

100.00

100.00 cum

28 Crushing of excavated ordinary rock boulders of 75 mm or more size in an integrated stone crushing unit of 200 tonners per hour capacity with arrangement of noise and dust adoptor comprising of primary and secondary crushing unit, belt converyor and vibrating screens to obtain soil of 75 mm or less size to meet Morth specification for filling material including transpoting to the embankment site with all lead and lift.

Total Excavation of ordinary rock 210.00

Taking 90% for filling 189.00

189.00 cum

29 Dismantling/Demolishing includingstacking of serviceablematerial and disposal of unserviceable material with in 50 meters lead

Bituminous road LS Qty 10.00

10.00 sqm

30 Runway/apron/taxiway painting

For Black Colour taxitrack 5 x 127.50 x 44.00 x 0.0225 631.13

Bitumen Road LS qty 50.00

681.13

say 682.00 sqm

3.3 Development of filets of Taxiways Details of quantity estimation for each of work involved in construction of parallel taxi track is given in Table 3.0.

Table 3.0: Quantity estimation for works involved in development of filets of Taxiway

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

1 Excavation in soil with hydraulic excavator

In between N1 & N2 1 x 1 x 126.00 x 10.50 x 0.28 370.44 In between N1 & N2 taxiway

shoulder 1 x 1 x 126.00 x 10.50 x 0.25 330.75

701.19

Say 702.00 Cum

Considering 20% as soil 1(a) 140.24 Cum

Considering 80% as ordinary rock 1(b) 560.95 Cum

2 Earth work in foundation tranches

100.00

100.00 cum 3 Construction of embankment including

LS Qty 500.00

SAY 500.00 Cum

4 Consolidation of sub-grade Pocket C & D For existing Apron 1 x 12,670.00 12,670.00

12,670.00 sqm

5 Preparation of sub-grade

LS Qty 100.00

100.00 sqm

6 Providing, laying, spreading and compacting graded stone(WMM)

Page 16: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

Pocket C & D 1 x 7428.00 x 1.00 x 0.25 1,857.00

Pocket C & D Shoulder 1 x 5242.00 x 1.00 x 0.25 1,310.50

3,167.50 Say 3,168.00 Cum

7 Providing and laying Polythene Sheet

Pocket C & D 1 x 7428.00 x 1.00 7,428.00

Pocket C & D Shoulder 1 x 5242.00 x 1.00 5,242.00

12,670.00 Say 12,670.00 Sqm

8 Providing and laying pavement quality cement concrete

Pocket C & D 1 x 7428.00 x 1.00 x 0.52 3,862.56

Pocket C & D Shoulder 1 x 5242.00 x 1.00 x 0.28 1,467.76

5,330.32 Say 5,331.00 Cum

9 Providing, laying and fixing in position closed-cell, U-V resistant

Pocket C & D 104.39

Pocket C & D Shoulder 39.67 144.06

Say 145.00 Sqm

10 P&L expansion joints

Pocket C & D 251.85

Pocket C & D Shoulder 95.70 347.55

say 348.00 m

11 Providing tack coat a) ON WBM @ 0.75 kg/sqm

LS Qty 100.00 100.00 sqm

b) On bituminous surface@ 0.5 kg/sqm

LS Qty 100.00 100.00 sqm

12 Providing and laying Bitumen Penetration Macadam

LS Qty 10.00

say 10.00 cum

13 Providing and laying 4 cm thick bitumastic sheet with hot bitumen

On Roads 10.00 10.00 cum

14 Runway/apron/taxiway painting

For White, Yellow and Red Colour.

Pocket C & D For existing Apron 1 x 12,670.00 x 1.00 x 0.03 380.10 LS Qty 50.00

430.10

say 431.00 sqm

15(a) C. Conc.(1:2:4)

1000 mm dia hume pipe crossing (4 no's)

1 x 1 x 50.00 x 3.20 x 2.00 320.00

Manhole 1 x 4 x 1.96 x 1.96 x 0.15 2.30

1000 mm dia hume pipe crossing (4 no's)

1 x 1 x 50.00 x 3.50 x 0.20 35.00

357.30

SAY 358.00 Cum

16 R.C.C (1:1.5:3)

For diversion of existing NP4 pipe drain

R.C.C Manhole(1 No) wall 1 x 4 x 4.00 x 5.00 x 0.5 40.00

Slab 1 x 1 x 4.00 x 4.00 0.35 5.60 Raft 1 x 1 x 5.00 x 5.00 0.50 12.50

58.10

say 59.00

cum

17 Centering and shuttering

1000 mm dia hume pipe 2 x 1 x 50.00 x 1.50 150.00

For diversion of existing NP4 pipe drain

Page 17: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

R.C.C Manhole(1 No) wall 1 x 8 x 4.00 x x 5.00 160.00

Slab bottom 1 x 1 x 4.00 x 4.00 16.00

Slab side 1 x 4 x 4.00 x 0.35 5.60 Raft 1 x 4 x 4.00 x 0.50 8.00

339.60

SAY 340.00 Sqm

18 Pre-cast reinforced cement concrete

Man hole cover 1 x 4 x 1.96 x 1.96 x 0.30 4.61 SAY 5.00 cum

19 Reinforcement ( TMT bars)

Taking as 120kg per cum 1 x 5.00 x 120 600.00

SAY 600.00 kg

20 Brick Work (1:4)

Man Hole Chamber 4 x 4 x 1.73 x 0.23 x 1.80 11.46

say 12.00 cum

21 15mm rough cast plaster 1:4

Man hole chambers 1 x 4 x 4.00 x 1.5 x 1.8 43.20

say 44.00 sqm

22 Dry stone pitching 22.5 cm thick Drain along parallel taxi

LS Qty 10.00

say 10.00 sqm

23 Pointing on stone work (1:3)

Considering 70% area 10.00 x 0.70 7.00 7.00 sqm

24 Demolishing c.conc. i/c disposal of material within 50 m lead (1:3:6 or richer mix) a)

N1 & N2 taxiway 1 x 1 x 126.00 x 10.5 x 0.28 370.44

1 x 4 x 10.50 x 11.50 x 0.28 135.24 SAY 506.00 cum

25 Providing NP-4 pipe

a) 450 mm dia pipe

LS qty 50.00

50.00 m

b) 1000 mm dia pipe

For pocket C & D pit nalha divertion 2 x 1 x 30.00 60.00

60.00 m

26 Dismantling including stacking of serviceable material and disposal of unserviceable material within 50 metres lead Water Bound Mecadam road - (Wet Mix Mecadam consider as similar to WBM for dismantling )

N1 & N2 taxiway 1 x 1 x 126.00 10.50 1,323.00

1,323.00 sqm

27 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

LS Qty 100.00 cum

28 Crushing of excavated ordinary rock boulders of 75 mm or more size in an integrated stone crushing unit of 200 tonners per hour capacity with arrangement of noise and dust adoptor comprising of primary and secondary crushing unit, belt converyor and vibrating screens to obtain soil of 75 mm or less size to meet Morth specification for filling material including transpoting to the embankment site with all lead and lift.

Total Excavation of ordinary rock 560.95

Taking 90% for filling 504.86

504.86 cum

29 Dismantling/Demolishing including stacking of serviceable

material and disposal of unserviceable material with in

50 meters lead

Bituminous road

LS Qty 10.00

Page 18: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

S.No. DESCRIPTION OF ITEM No. L B H QUANTITY Unit

10.00 sqm

30 Runway/apron/taxiway painting

For Black Colour

Pocket C & D For existing Apron 1 x 12,670.00 x 1.00 x 0.0225 285.08

285.08

say 286.00 sqm

3.4 Replacement of air washer unit

Details of quantity estimation for each of work involved in replacement of air washer unit is given in Table 4.0. Table 4.0: Quantity estimation for works involved in replacement of air washer unit

Sr. No. Description No L B H Qty

1 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) including disposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed. Ordinary rock

For Area 1.00 10.00 3.50 0.60 21.00

For pump roon 1.00 12.00 1.00 1.00 12.00

Say 35 cum 33.00

2 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - -All work upto plinth level: 1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)

For Ramp 2.00 15.00 1.00 0.10 3.00

For pump roon 1.00 12.00 1.00 0.10 1.20

Say 5 cum 4.20

3 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

80% of excavated area 26.40

Say 30 cum 26.40

4 Centring and shuttering, propping etc. and removal of form for: a) Foundation, footing, bases of columns etc for mass concrete.

Washer bay 1 16 - 0.1 1.6

ramp 2 10 - 0.1 2

For pump roon 1 12 - 0.3 3.6

7.2

Say 10 sqm

5 RCC

For washer bay 1 16 1 0.1 1.6

ramp 1 7 3 0.1 2.1

For pump room 1 12 0.3 1.2 4.32

Slab 1 4 4 0.15 2.4

10.42

Say 11 cum

6 Centring and shuttering including strutting, propping etc. and removal of form for:

a) Lintels, beams, plinth beams, girders, bressumers and cantilevers.

For pump room 2 12 1.2 28.8

Say 30 sqm

b) Slab

For pump roon 1 4 4 16

1 16 0.15 2.4

18.4

Say 20 sqm

7 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.

Thermo-Mechanically Treated bars.

Qty @ 100 kg/cum of Item No. 5 1042

Page 19: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr. No. Description No L B H Qty

Say 1050 kg

8 Providing & laying in position dressed laterite masonary in cement mortar 1:6 in foundation and plinth .

For washer bay 1 16 0.8 1.5 19.2

ramp 1 5 1.6 0.7 5.6

For pump room 1 12 0.3 3 10.8

Say 36 cum 35.6

9 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix :

1:4 (1 cement: 4 fine sand)

For washer bay 4 16 1.5 96

ramp 4 5 0.7 14

For pump roon 2 12 3 72

182

Say 185 sqm

10 6 mm cement plaster of mix:

1:3 ( 1 cement : 3 fine sand)

For pump room slab 1 4 4 16

1 16 0.1 1.6

Say 20 sqm 17.6

11 Finishing walls with water proofing cement paint of required shade

New work (Two or more coats applied @ 3.84 kg/10 sqm).

Qty of Item No. 9 + Item No. 10 205

Say 210 sqm

3.5 Relocation of borewell and associated works

Details of quantity estimation for each of work involved in construction of a perimeter road is given in Table 5.0.

Table 5.0: Quantity estimation for works involved in relocation of borewell and associated works

Sr.No. Description No L B H Qty

1 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) including disposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.

Ordinary rock

For pump room 1 12 1 1 12

Say 15 cum

2 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering -All work upto plinth level:

1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)

For pump room 1 12 1 0.1 1.2

Say 2 cum

3 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

80% of excavated area 9.6 9.6

Say 10 cum

4 Centring and shuttering, propping etc. and removal of form for: a) Foundation, footing, bases of columns etc for mass concrete.

For pump room 1 12 - 0.3 3.6

Say 5 sqm

5 RCC

For pump room 1 12 0.3 1.2 4.32

Slab 1 4 4 0.15 2.4

Say 7 cum 6.72

6 Centring and shuttering including strutting, propping etc. and removal of form for:

a) Lintels, beams, plinth beams, girders, bressumers and cantilevers.

For pump roon 2 12 1.2 28.8

Page 20: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr.No. Description No L B H Qty

Say 30 sqm

b) Slab

For pump roon 1 4 4 16

1 16 0.15 2.4

Say 20 sqm 18.4

7 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. Thermo-Mechanically Treated bars.

Qty @ 100 kg/cum of Item No. 5 672

Say 700 kg

8 Providing & laying in position dressed laterite masonary in cement mortar 1:6 in foundation and plinth

For pump room 1 12 0.3 3 10.8

10.8

Say 15 cum

9 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix : 1:4 (1 cement: 4 fine sand)

For pump room 2 12 3 72

72

Say 80 sqm

10 6 mm cement plaster of mix:

1:3 ( 1 cement : 3 fine sand)

For pump room slab 1 4 4 16

1 16 0.1 1.6

17.6

Say 20 sqm

11 Finishing walls with water proofing cement paint of required shade New work (Two or more coats applied @ 3.84 kg/10 sqm).

Qty of Item No. 9 + Item No. 10 100

Say 100 sqm

12 Borring and devloping borewell dia 200 mm

1 30 30

Say 30 mtr

13 casing paipe for borewell 200 mm dia

1 30 30

Say 30 mtr

14 GI pipe for connections 80 mm NB

LS Qty 1 100 100

Say 100 mtr

3.6 Construction of a perimeter road

Details of quantity estimation for each of work involved in construction of a perimeter road is given in Table 6.0.

Table 6.0: Quantity estimation for works involved in construction of a perimeter road

Sr. No. Description No L B H Qty

1 Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm. depth, dressing to camber and road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth lead upto 50 metres

For Widening of road (length of road to be widened is 1 km and width is 3.0 mtr

1 1650 4.5 7425

1 1450 10.5 15225

22650

Say 22650.00 sqm

2 Providing and laying Wet Mix Macadam base course including providing, mixing, laying and compacting clean, crushed and graded aggregates and granular material pre-mixed with water to a dense mass on a prepared sub based in accordance with the requirement of the specifications and as directed by the Engineer-in-Charge.

For widening of existing road 1 1650 3 0.25 1237.5

For new road 1 1450 7.5 0.25 2718.75

Page 21: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr. No. Description No L B H Qty

Say 3960.00 cum

3 (a) Providing and applying tack coat using hot straight run bitumen of grade 80/100 including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications: On W.B.M. @ 0.75 Kg / sqm.

For widening of existing road 1 1650 3 4950

For new road 1 1450 7.5 10875

15825

Say 15830.00 sqm

3 (b) Providing and applying tack coat using hot straight run bitumen of grade 80/ 100 including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications :

On bituminous surface @ 0.50 Kg/sqm.

For widening of existing road 1 1650 3 4950

For new road 1 1450 7.5 10875

15825

Say 15830.00 sqm

4 Providing and laying bituminous macadam using crushed stone aggregates of specified grading premixed with bituminous binder, transported to site by tippers, laid over a previously prepared surface with paver finisher equipped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specifications and directions of Engineer-in-Charge

50 to 100 mm average compacted thickness with bitumen ofgrade VG-30 @3.50%(percentage by weight of total mix) prepared in Drum Type Hot Mix Plant of 60-90 TPH capacity

For widening of existing road 1 1650 3 0.05 247.5

For new road 1 1450 7.5 0.05 543.75

791.25

Say 791.50 cum

5 Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directionsof Engineer-in-Charge.

40/50 mm compacted thickness with bitumen of grade [email protected]% (percentage by weight of total mix) and lime filler @ 3%(percentage by weight of Aggregate) prepared in drum Type HotMix Plant of 60-90 TPH capacity.

For widening of existing road 1 1650 3 0.05 247.5

For new road 1 1450 7.5 0.05 543.75

791.25

Say 791.50 cum

6 Construction of embankment with Good earth / Moorum brought from approved quarry out side the airport premises. The complete operation will include spreading the earth with dozer, dressing, levelling, providing camber, grading with motor grader and consolidating with vibratory roller 8-10 tonne capacity including making good the undulation etc. The compacted earth shall meet the requirement as per MORT&H Specifications.

For widening 1 1650 4.5 0.3 2227.5

For new Road

a) For sketch of 950 mtrs 1 950 10.5 0.45 4488.75

b) For sketch of 520 mtrs 1 500 10.5 7.5 39375

46091.25

Say 46095.00 cum

7 Designing, Providing, casting and erecting in position precast reinforced M-35 Grade facia panels having area 2.25 Sqm (Block facia not allowed) for reinforced soil embankment for approach retaining walls with 40mm wide X 5mm thick or 50mm wide X 5mm thick corrosion protected (Galvanised) High Adherence (HA) steel strips as soil reinforcements as specified in approved design and drawings including all materials, labour, connections, joint filters, geotextile, drainage outlets, erection of panels etc. complete as per approved design & drawing and as per specifications & as per detailed drawings for all heights as directed by engineer in charge.

2 500 7.5 7500

Say 7500.00 sqm

8 Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete

Near extreme edge of Runway 08 to retain the existing slope

1 500 10 5000

Say 5000.00 sqm

9 Providing and laying NP-4 Heavy duty R.C.C. Pipe with a collars jointed with stiff mixture of cement mortar in the proportion 1:2 (1 Cement : 2 fine sand) including testing of joints etc. complete. 1000 mm dia R.C.C. Pipe

In low lying area in new proposed perimeter road (stretch of 500 mtrs at twenty locations

20 2 12 480

Say 480.00 mtrs

Page 22: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr. No. Description No L B H Qty

10 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level.

a) 1:2:4 (1 Cement : 2 Coarse sand : 4 graded stone aggregate 20 mm nominal size)

20 12 3.5 2 1680

40 3.14 0.25 12 -376.8

1303.2

Say 1305 cum

b) 1:4:8 (1 Cement : 4 Coarse sand : 8 graded stone aggregate 40 mm nominal size)

20 12 3.5 0.2 168

Say 168.00 cum

3.7 Diversion/Rerouting of Cables/Drain etc.

Details of quantity estimation for each of work involved in construction of a perimeter road is given in Table 7.0.

Table 7.0: Quantity estimation for works involved in diversion/rerouting of Cables/Drain etc.

Sr. No. Description No L B H Qty

1 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) including disposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.

Ordinary rock

For manholes 10 2 2 2 80

LS 20

Say 100 cum 100

2 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level:

1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)

For manholes 10 2 2 0.1 4

LS 2

Say 6 cum 6

3 RCC

For manhole cover 10 2 2 0.2 8

LS 2

Say 10 cum 10

4 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Thermo-Mechanically Treated bars.

Qty @ 100 kg/cum of Item No. 5 1000

Say 1000 kg

5 Providing & laying in position dressed laterite masonary in cement mortar 1:6 in foundation and plinth .

For manhole 10 8 0.3 1.5 36

LS 4

Say 40 cum 40

6 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix :

1:4 (1 cement: 4 fine sand)

For manhole 10 8 1.5 120

LS 10

Say 130 sqm 130

3.8 Relocation of boundary wall for widening of Perimeter Road, relocation of Bomb

cooling pit & GTC hut fouling in the alignment of PTT

Page 23: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Details of quantity estimation for each of work involved in construction of a perimeter road is given in Table 8.0. Table 8.0: Quantity estimation for works involved in relocation of boundary wall for

widening of Perimeter Road, relocation of Bomb cooling pit & GTC hut fouling in the alignment of PTT

Sr. No. Description No L B H Qty

1 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) including disposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.

Ordinary rock

For Columns 2 1.5 1.5 1.5 6.75

For Plinth beam 1 1 0.75 0.2 0.15

6.9

Say 7.00 cum

2 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - -All work upto plinth level:

1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)

For Columns footings 2 1.5 1.5 0.1 0.45

Under Plinth beam 1 2.2 0.75 0.1 0.17

0.62

Say 1.00 cum

3 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

60% on Item No. 01 4.14

Say 4.20 cum

4 Centring and shuttering, propping etc. and removal of form for: a) Foundation, footing, bases of columns etc for mass concrete.

Raft for column 2 2 2.4 0.3 2.88

Say 3.00 sqm

5 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement - All work upto plinth level :

1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)

For Raft for column 2 1.2 1.2 0.3 0.86

For Column from pedestal upto plinth beam bottom

2 0.3 0.3 0.9 0.16

For Plinth beam level bottom to top 2 0.3 0.3 2.6 0.47

Plinth Beam 1 2.2 0.3 0.45 0.3

1.79

Say 1.79 cum

6 Centring and shuttering including strutting, propping etc. and removal of form for:

a) Columns, Pillars, Piers, Abutments, Posts and Struts.

upto Plinth beam bottom 2 2 0.6 0.9 2.16

From Plinth beam bottom to plinth beam top 2 2 0.3 0.9 1.08

From Plinth beam top to column 2 2 0.6 2.15 5.16

8.4

Say 8.50 sqm

b) Lintels, beams, plinth beams, girders, bressumers and cantilevers.

For beams/columns 2 0.45 2.2 1.98

Say 2.00 sqm

7 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.

Thermo-Mechanically Treated bars.

Qty @ 125 kg/cum of Item No. 5 223.88

Say 176.00 kg

8 Providing & laying in position dressed laterite masonary in cement mortar 1:6 in foundation

Page 24: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr. No. Description No L B H Qty

and plinth .

For filling gaps between columns 1 2.2 0.23 2.15 1.09

Say 1.10 cum

9 Providing and laying cement Concrte in retaining walls, return walls (any thickness) including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks, plain window sills, fillets etc upto floor five level, excluding the cost of centring, shuttering and finishing:

1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

Over wall 1 2.2 0.23 0.75 0.38

Say 0.40 cum

10 Centering shuttering including struttings, propping etc. and removal of form work for:

Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses plinth and string courses fillets etc

For coping 2 2.2 0.075 0.33

Say 0.35 sqm

11 Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete:

Angle 50 x 50 x 6 m for overhang 2 1.7 4.5 15.3

Say 15.50 kg

12 Providing and fixing concertina coil fencing with required dia 600 mm upto 3m height of wall with existing angle iron ‘Y’ shaped placed 2.4 m or 3.00 m apart and with 9 horizontal R.B.T. stud tied with G.I. staples and G.I. clips to retain horizontalincluding necessary bolts or G.I. barbed wire tied to angle iron all complete as per direction of Engineer-in-charge with reinforced barbed tape (R.B.T.) / Spring core (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mm. with tape (0.52 mm thick) of Supreme make or equivalent and weight 43.478gm/ metre (cost of M.S. angle, C.C. blocks shall be paid separately)

1 2.8 2.8

Say 3.00 metre

13 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix :

1:4 (1 cement: 4 fine sand)

2 2.2 2.15 9.46

Say 9.50 sqm

14 6 mm cement plaster of mix: 1:3 ( 1 cement : 3 fine sand)

For Colum 2 2 0.3 2.15 2.58

Off Set 2 2 0.07 2.15 0.6

Beam 1 2 2.2 0.45 1.98

Coping 1 2.8 0.33 0.92

6.09

Say 6.10 sqm

15 Finishing walls with water proofing cement paint of required shade

New work (Two or more coats applied @ 3.84 kg/10 sqm).

Qty of Item No. 14 + Item No. 15 15.55

Say 15.60 sqm

16 Demolishing brick work/laterite masonary manually/by machanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.

In Cement mortar

1 2.2 0.23 2.2 1.11

Say 2.00 cum

17 Demolishing R.C.C. work, including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge

2 0.3 0.3 2.2 0.4

Say 0.5 cum

3.9 Installation of 5 Nos. CCR in the existing substation of Indian Navy with remote

control panel and installation of DG set of 325 KVA

Page 25: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Details of quantity estimation for each of work involved in Installation of 5 Nos. CCR in the existing substation of Indian Navy with remote control panel and installation of DG set of 325 KVA is given in Table 9.0.

Table 9.0: Quantity estimation for works involved in Installation of 5 Nos. CCR in the existing substation of Indian Navy with remote control panel and installation of DG set of 325 KVA

Sr. No. Description No L B H Qty

1 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) including disposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be levelled and neatly dressed.

Ordinary rock

For CCR room ext 1 30 1 1 30

Say 30 cum 30

2 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - -All work upto plinth level:

1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)

For CCR room ext 1 30 1 0.1 3

Say 5 cum 3

3 Filling available excavated earth (excluding rock) trenches, plinth, sides of foundations etc.layers not exceeding 20 cm in depth: consolidating each deposited layer by ramming watering, lead up to 50 m and lift upto 1.5 m

30% of excavated area 9

Say 10 cum 9

4 Centring and shuttering, propping etc. and removal of form for: a) Foundation, footing, bases of columns etc for mass concrete.

For CCR room ext 1 30 - 0.3 9

Say 10 sqm 9

5 Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

For CCR room ext (for band & roof beams) 1 30 0.3 1.2 10.8

Slab 1 10.9 5.9 0.15 9.65

Say 21 cum 20.45

6 Centring and shuttering including strutting, propping etc. and removal of form for:

a) Lintels, beams, plinth beams, girders, bressumers and cantilevers.

For CCR room ext 2 30 1.2 72

Say 75 sqm

b) Slab

For CCR room ext 1 10.9 5.9 64.31

1 30 0.15 4.5

Say 70 sqm 68.81

7 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.

Thermo-Mechanically Treated bars.

Qty @ 100 kg/cum of Item No. 5 2044.65

Say 2050 kg

8 Providing & laying in position dressed laterite masonary in cement mortar 1:6 in foundation and plinth .

For CCR room ext 1 30 0.3 6 54

for cable trenches 2 10 0.3 1 6

Say 60 cum 60

9 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix :

1:4 (1 cement: 4 fine sand)

For CCR room ext 2 30 6 360

for cable trenches 2 10 1 20

Say 380 sqm 380

10 6 mm cement plaster of mix:

1:3 ( 1 cement : 3 fine sand)

Page 26: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Sr. No. Description No L B H Qty

For CCR room ext 2 10.9 5.9 128.62

1 30 0.15 4.5

Say 135 sqm 133.12

11 Finishing walls with water proofing cement paint of required shade

New work (Two or more coats applied @ 3.84 kg/10 sqm).

Qty of Item No. 9 + Item No. 10 515

Say 520 sqm

3.10 WATER REQUIREMENT

Construction: 10- 15 m3/hr for a period of 20 – 30 days. Operation: No additional water.

3.11 WASTE GENERATION Construction: Approximately 801.19 Cum of soil/rock, Approximately 100 Cum in a days for 20 – 30 days of demolition waste. Operation: None.

4.0 SITE ANALYSIS

4.1 CONNECTIVITY Goa airport is situated in Chikalim Village at Vasco-Da-Gama in south Goa District. It is located at a distance of about 30 KM from Panjim. It is well connected road or by rail, situated in the western part of the state. The district is surrounded by Panaji district at the north, Arabian Sea in the west, Mormugaon at the south and Ponda district at the east. Physiographically the study area of the project comes under Taluka namely Mormugao, Salcete and Tiswadi at an elevation above MSL is 44.5 m. The nearest railway station is Vasco Railway Station which is about 5 KM from the site at the north-west.

4.2 LANDUSE The land use of the study area has been studied by analyzing the secondary data from district census hand book and village wise census data - 2001. The land use pattern of the study area has also been presented though a self explanatory Fig- 3.0.

Page 27: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

52 .6%

2 .73%

9.14%

35.53%

Forest Irrigated

Un Irrigated Culturable waste

Area not available for cultivation

The land use pattern of the study area based on secondary data is given in Table – 10.

Table – 10: Land Use Pattern In The Study Area (Within 10km)

Sl. No. Particulars Area in ha Percentage (%)

1 Forest Land 0 0

2

Land under cultivation

Irrigated land 286.14 2.73

Un irrigated land 5515.56 52.60

3 Culturable waste land 958 9.14

4 Area not available for cultivation

3726.57 35.53

Total area 10486.27 100

Source: District primary census hand book (2001)

The village wise land use pattern of the study area are presented in Table 11.0. The land use is classified into four types – viz. forest, area under cultivation, culturable waste land and the area not available for cultivation.

Table – 11.0: Villagewise Land Use Pattern In Study Area

Sl. No.

Name of village Total

Area (HA) Forest Land

Cultivated Area Culturable

Waste Land

Area not available for cultivation

Irrigated Un-irrigated

DISTRICT SOUTH GOA

TALUKKA MORMUGAO

1 Dabolim village 740.95 0.00 2.05 88.93 68.15 581.82

2 Issorcim village 273.03 0.00 0.00 66.49 82.91 123.63

3 Quelossim village 1064.32 0.00 20.90 532.23 59.88 451.31

4 Sao Jacinto Island 14.9 0.00 0.00 3.15 9.83 1.92

5 Velsao village 161.84 0.00 0.00 126.26 2.83 32.75

6 Cuelim village 465.83 0.00 24.65 330.65 27.14 83.39

7 Cansaulim village 190.62 0.00 0.00 159.95 1.64 29.03

8 Cortalim village 833.38 0.00 44.64 348.51 165.06 275.17

9 Pale village 240.6 0.00 2.02 170.78 14.83 52.97

10 Sancoale (CT) 518.1 0.00 13.48 258.71 82.59 163.32

11 Mormugao (MCI) 340.01 0.00 0.00 285.90 12.91 41.20

12 Chicalim (CT) 188.68 0.00 3.03 33.33 14.76 137.56

Total 5032.26 110.77 2404.89 542.53 1974.07

DISTRICT SOUTH GOA

Page 28: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

TALUKKA SALCETE

13 Majorda village 437.59 0.00 8.19 386.09 3.03 40.28

14 Verna village 1490.06 0.00 76.34 620.10 330.42 463.20

Total 1927.65 0 84.53 1006.19 333.45 503.48

DISTRICT NORTH GOA

TALUKKA TISWADI

15 Siridao village 771.66 0.00 2.13 160.71 2.74 606.08

16 Carambolim village 1503.7 0.00 79.33 1082.78 32.91 308.68

17 Mercurim village 256.18 0.00 0.00 218.91 10.54 26.73

18 Goalim Moula village 319.78 0.00 5.56 172.42 8.41 133.39

19 Goa Velha (CT) 351.98 0.00 3.82 246.49 25.78 75.89

20 Bambolim (CT) 323.06 0.00 0.00 223.17 1.64 98.25

Total 3526.36 0 90.84 2104.48 82.02 1249.02

4.3 LAND FORM/TOPOGRAPHY/SOIL

The proposed project site is situated around 73049058.90o’ East longitude and 15o22o48.940’ North latitude. The study area is generally flat terrain. The general slope of the area from North-West to East -South. These are low-laying lands reclaimed from the sea around the coastal and river line stretches. Midland plateau sandwiched between the mountains and the coasts are plateaus of iron-rich red soil (leterite) that comprise the core of Goa’s topography. The soil cover is generally thin and cannot sustain forests. The main plateau vegetation is grasses, shrubs and wild flowers. However, low-laying areas like gullies and river basins have deeper soil and patches of monsoon forest occur there. The rivers transport a lot of rich fine soil from the highlands into the coast, forming very fertile alluvial lowlands. Major river-line plains are those of the Mandovi, Zuari, Chapora, Kushavati and Sal river. The approx. level of the area is 44.2 m above MSL. The topography of the study area is undulatory.

4.4 CLIMATE The climate of the region is characterised as tropical. The climate and wind pattern are governed by the annually monsoons and transition periods warmer towards interior and cools down in the hilly areas on account of elevation and vegetation. Only during the three monsoon months July, August and September the area experiences increased humidity, cloudiness and precipitation are observed. The year can broadly be divided into four seasons. The cold season starts from late November and extends to about the beginning of March. This is followed by the hot season which lasts till about middle of June when the monsoon arrives. The monsoon continues to the last week of September. The two post monsoon months October and November constitute a transition period from monsoon to winter conditions. Climatological normal data for the nearest station i.e. Panjim has been presented in Tables 12 -14. Rainfall & Humidity Climatological Normal Data on rainfall & humidity and cloudiness for the period 1951-1980 are presented in Table 12. The normal annual rainfall in the area is 2932.0 mm of which south-west monsoon accounts for the major part of the normal rain while North – East monsoon contributes around 25%. The air over the area is humid during the non-monsoon months and relative humidity is comparatively high. April and May are the hottest months of year with relative humidity of about 70.5% and 71.5% respectively. Other months, excepting May to October, it is practically rainless.

Page 29: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Table – 12: Climatological Normal Data - Rainfall & Humidity

Month

Rainfall Relative humidity

%

Cloud amount, Octas of Sky Monthly

Total, mm No. of

Rainy days All clouds Low Clouds

January I II

0.2 0.0 78 54

1.9 2.0

0.3 0.3

February I II

0.1 0.0 79 59

2.0 1.8

0.4 0.4

March I II

1.2 0.1 78 63

2.4 2.1

1.4 1.2

April I II

11.8 0.8 74 65

3.7 3.1

2.2 1.9

May I II

112.7 4.2 74 67

5.0 4.3

2.9 2.3

June I II

868.2 21.9 86 81

6.8 6.8

3.5 3.4

July I II

994.8 27.2 90 86

7.3 7.4

3.5 3.6

August I II

518.7 23.3 89 84

7.0 7.0

3.3 3.4

September I II

251.9 13.5 90 81

6.2 6.2

2.9 3.0

October I II

124.8 6.2 85 74

4.9 5.1

1.8 2.2

November I II

30.9 2.5 75 62

3.7 4.0

0.9 1.3

December I II

16.7 0.4 72 56

2.9 3.2

0.5 0.6

Annual Total/ Mean

I II

2932.0 100.1 81 69

4.5 4.4

2.0 2.0

Source: IMD, Climatological Table, Panjim Temperature Climatological Normal Data on monthly mean Values of daily maximum and minimum temperatures, highest and lowest values in the different months, and extremes of temperatures for the period 1951 to 1980 are presented in Table 13. The cold season starts towards the latter half of November. January is the coldest month, with the mean daily maximum temperature at 31.6oC and the mean daily minimum at 19.6oC. Mean lowest temperature during January is reported as 17.3oC. The temperature begins to rise fairly rapidly from the middle of March; May and June are the hottest months. In May and June, maximum temperatures may sometimes go above 33.0oC. With the arrival of monsoon in the area in the middle of June, day temperature drops appreciably while night temperature remains high. In October, the day temperatures are as during the monsoon months but the nights are cooler. Amongst the extremes of temperatures recorded during 1951-1980, the highest value is reported as 39.0oC & the lowest as 13.3oC.

Table – 13: Climatological Normal Data – Temperature

Month

Air Temperature, Mean, °C Extremes,°C

1951-1980

Dry Bulb

Wet Bulb

Daily Maxm

Daily Minm.

Highest in month

Lowest in month

High

Low

January I II

21.2 28.1

18.7 21.7

31.6 19.6 34.3 17.3 35.4 15.1

February I II

22.3 28.5

19.9 22.6

31.5 20.5 35.0 17.9 36.9 13.3

March I II

25.3 29.4

22.6 24.2

32.0 23.2 35.0 20.2 39.0 17.5

Page 30: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

April I II

28.1 30.5

24.6 25.5

33.0 25.6 34.5 22.8 36.3 19.4

May I II

28.8 30.5

25.2 25.7

33.0 26.3 34.4 23.1 36.4 21.5

June I II

26.8 28.0

25.0 25.5

30.3 24.7 33.4 22.3 35.5 21.2

July I II

26.1 26.9

24.8 25.1

28.9 24.1 30.7 22.4 31.7 20.5

August I II

25.9 26.9

24.5 24.8

28.8 24.0 30.5 22.5 34.0 21.8

September I II

25.5 27.3

24.3 24.7

29.5 23.8 31.4 22.3 32.6 21.0

October I II

25.8 28.6

24.0 25.1

31.6 23.8 34.8 21.8 36.0 20.2

November I II

24.6 29.0

21.6 23.6

32.8 22.3 35.0 19.7 36.5 15.3

December I II

22.7 28.6

19.4 22.2

32.4 20.6 34.5 18.0 35.6 16.0

Annual Total/Mean

I II

25.3 28.5

22.9 24.2

31.3 23.2 36.4 16.4 39.0 13.3

Source: IMD, Climatological Table, Panjim

Wind Flow Pattern

The Meteorological data obtained form IMD Panjim centre reveals that wind pattern is typical of the Indian subcontinent. Westerly wind prevail form April to September with a maximum intensity of 18.2kmh rest of the year i.e form October to January the prevailing winds are Easterly to Wasterly and in February and March the pattern shows diurnal variation predominant Westerly winds. The seasonal wind roses during study period are presented in Figure-III.1. Climatological Normal Data on wind flow pattern for the period 1951 to 1980 have been presented in Table - 14.

Table – 14: Climatological Normal Data – Wind Pattern

Month

Percentage no of days of wind from* Mean Wind

Speed, km/h**

N

NE

E

SE

S

SW

W

NW

Calm

January I II

2 35 56 2 0 0 0 0 5 9.9

3 1 2 1 0 15 44 34 0

February I II

4 30 49 9 1 1 0 1 5 10.3

2 0 0 0 0 12 43 42 1

March I II

6 25 40 15 3 1 0 1 9 10.6

4 0 0 0 0 16 46 34 0

April I II

16 25 19 9 4 3 3 5 16 11.3

3 0 0 0 0 16 45 35 1

May I II

23 14 10 4 2 3 10 21 13 13.1

2 0 0 1 2 9 43 42 1

June I II

6 6 12 11 6 18 23 10 8 15.2

2 2 1 3 9 30 36 15 2

July I II

4 2 5 5 3 24 45 8 4 18.2

2 0 1 0 3 26 55 11 2

August I II

4 4 5 2 2 20 43 12 8 16.0

2 0 0 0 1 21 55 20 1

September I II

9 14 18 8 5 7 10 11 18 10.2

5 1 1 0 5 15 35 38 0

October I II

5 26 38 11 3 1 3 2 11 8.5

5 3 1 1 5 18 38 27 2

November I II

4 39 47 3 1 1 1 0 4 8.9

4 5 3 1 4 16 45 21 1

December I II

2 44 47 2 1 0 0 0 4 9.3

3 4 3 1 1 13 45 28 2

Page 31: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

Annual I II

7 22 29 7 3 7 12 6 7 11.8

3 1 1 1 3 17 44 29 1

Source: IMD, Climatological Table, Panjim

Micrometeorology The micrometeorological data generated during the study period are very useful for proper interpretation of the baseline information and it provides an input for prediction models for air quality dispersion. The transport and diffusion of the pollutants in the atmosphere are governed by meteorological factors. Factors like wind velocity, wind direction and atmospheric stability are known as primary/basic meteorological parameters since the dispersion and diffusion of pollutants depend mainly on these factors. Factors like ambient temperature, humidity, rainfall, atmospheric pressure, etc. are known as secondary meteorological parameters as these factors control the dispersion of the pollutants indirectly by affecting the primary factors. Thus, to assess the air pollution impact it becomes imperative to collect the above mentioned micrometeorological parameters in the project area.

4.5 SOCIAL INFRASTRUCTURE

As the Project site is located at a distance of about 10 km. from the heart of the Goa city, which is the capital of the state. All the amenities such as Hospitals, Schools, and Colleges etc. are naturally available. Medical facilities in the form of hospitals and dispensaries operated by the state government as well as private practitioners are adequate. Hospitals, PHC, and many private hospitals are present in the study area. Educational facilities available in the area are also adequate consist of engineering collages, medical & dental collages, degree collages, management collages and many more educational institution are present in Goa city. Thus, no impact on basic amenities is envisaged. Salient features of the basic amenities profile of the study area this presented in Table. 15.

Table – 15: Village Wise Basic & Civic Amenities

Sl. No.

Name of Village Educational Medical Drinking

Water Post &

Telegraph Communication

Approach to the Village

DISTRICT SOUTH GOA

TALUKKA MORMUGAO

1 Dabolim village P,M,S,C 1 W,TW,HP 2 2 KR,PR

2 Issorcim village P,M 1 W,TW,HP 0 1 KR,PR

3 Quelossim village P 1 W,TW,HP 0 1 KR,PR

4 Sao Jacinto Island 0 0 TW,HP 0 0 KR

5 Velsao village P,M 1 S,TW,HP 0 1 PR

6 Cuelim village P 0 S,TW,HP 0 1 KR,PR

7 Cansaulim village P 0 S,TW,HP 1 1 KR

8 Cortalim village P 0 W,TW,HP 2 0 KR

9 Pale village P 0 S,TW,HP 0 0 KR,PR

10 Sancoale (CT) P,M,S 2 W,TW,HP 2 2 KR,PR

11 Mormugao (MCI) P,M,S 2 W,TW,HP 1 2 KR,PR

12 Chicalim (CT) P,M,S 2 S,TW,HP 2 2 KR,PR

DISTRICT SOUTH GOA

TALUKKA SALCETE

13 Majorda village P.M 1 S,TW,HP 1 1 KR,PR

14 Verna village P 0 W,TW,HP 1 0 KR,PR

DISTRICT NORTH GOA

TALUKKA TISWADI

15 Siridao village P 1 W,TW,HP 1 1 KR,PR

Page 32: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

16 Carambolim village P 1 W,TW,HP 1 1 KR,PR

17 Mercurim village P 0 W,TW,HP 1 1 KR,PR

18 Goalim Moula village P 0 W,TW,HP 1 1 KR,PR

19 Goa Velha (CT) P,M,S 1 W,TW,HP 2 2 KR,PR

20 Bambolim (CT) P,M,S 1 W,TW,HP 2 2 KR

Legend 1 = (0-5) - Facility available within 5 KM 2 = (5-10) - Facility available within 5-10 KM 3 = (>10) - Facility available above 10 KM P = Primary School T = Tap W = Well M = Middle School TW = Tube Well HP = Hand Pump S = Secondary School PO = Post Office C = Canal H = Hospital TO = Telegraph Office KR = Kutcha R oad D = Dispensary BS = Bus Stop PR = Pucca Road

5.0 PLANNING

The existing layout of the airport is shown in Figure 2.0. It is proposed to modify the existing layout to accommodate taxi way and the proposed new layout is shown in Figure 4.0.

Figure 4.0 Modified Layout – Inclusion of taxiway

6.0 PROPOSED INFRASTRUCTURE No additional social infrastructure is envisaged. Also there will be no additional water, waste water, solid waste generation envisaged after modification of existing layout.

Page 33: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

7.0 REHABILITATION AND RESETTLEMENT PLAN

The proposed project is modification project to accommodate taxi way. No rehabilitation and resettlement plan is envisaged.

8.0 PROJECT SCHEDULE The period of execution for Parallel Taxi Track and associated works shall be 30 months

9.0 COST ESTIMATE Cost estimate is given in Table 16.0.

Table 16.0: Cost Estimate

Sr. No.

Description of works Amount for civil works(Rs.)

Amount for Elec. works(Rs.)

Total Amt. (Rs.)

1 Construction of Parallel Taxi Track on 08 - 26. (Cost sharing between AAI and Indian Navy)

116,55,72,643.40 3,40,54,624.00 119,96,27,267.40

2 Strengthening of Taxiways N3, N4, N5, N6 & N7. (Cost sharing between AAI and Indian Navy)

29,52,88,901.68 Included in Sl. No. 1 above

29,52,88,901.68

3 Development of fillets of Taxiways N1 & N2. (Cost to be borne by AAI)

4,96,86,097.48 Included in Sl. No. 1 above

4,96,86,097.48

4 Replacement of Air washer unit. (Cost sharing between AAI and Indian Navy)

5,59,769.51 13,82,157.00 19,41,926.51

5 Relocation of Borewell and associated works. (Cost sharing between AAI and Indian Navy)

7,23,402.45 9,21,438.00 16,44,840.45

6 Construction of Perimeter road around dumbell R 08 (Cost to be borne by AAI)

20,21,03,319.20 34,55,393.00 20,55,58,712.20

7 Diversion of cables. (Cost sharing between AAI and Indian Navy)

5,06,169.25 11,51,798.00 16,57,967.25

8 Relocation of existing pumps. (Cost sharing between AAI and Indian Navy)

2,70,933.09 4,60,719.00 7,31,652.09

9 Relocation of Boundary wall for widening of Perimeter road, relocation of Bomb cooling pit & GTC hut fouling in the alignment.. (Cost sharing between AAI and Indian Navy)

2,76,76,760.53 11,51,798.00 2,88,28,558.53

10 Installation of 5 Nos. CCR in the existing substation of Indian Navy with

10,79,520.27 1,23,67,483.00 1,34,47,003.27

Page 34: AMENDMENT REQUIRED IN ENVIRONMENTAL CLEARANCEenvironmentclearance.nic.in/writereaddata/... · Qu an tity ca lcu ation sper ear h work hee 6,79,588.83 6,79,588.83 Re-usable ma terails

remote control panel and installation of DG set of 325 KVA. (Cost sharing between AAI and Indian Navy)

11 Replacement of CAT- I ILS with New CAT-I ILS. (i/c Civil, Electrical & CNS) (Cost to be borne by Indian Navy)

3,50,00,000

Total of Packages (Civil + Electrical) 183,34,12,926.86

Say 183.35 Cr.

10.0 BENEFITS OF PROJECT Due to the absence of Parallel Taxi Track on the northern side of Runway 08 - 26, landed Aircraft has to backtrack on the runway to reach the Civil Apron using the Taxiways N1/N2, N4, N5 or using curtailed Parallel Taxi Track on the southern side involving crossing of runway. This process limits the runway capacity of handling Aircraft. With the present arrangement/procedure of Aircraft movement during takeoff and landing, due to the absence of Parallel Taxi Track on the northern side of the Runway, it has negative effect on the turnaround time of the Aircraft. The runway efficiency is also getting limited due to backtracking of Aircraft after landing using either Taxiway N4 & N5 or using southern side part Taxi Track involving crossing of runway. Thus the proposed project will improve the runway capacity and comfort of passengers.