Upload
matthew-bennett
View
33
Download
3
Embed Size (px)
DESCRIPTION
Hazid worksheet
Citation preview
HAZID WORKSHEET
: ANOA PHASE 4 - AGX COMPRESSION RECONFIGURATION PROJECT
: DLB Activities in the vicinity and moored alongside AGX Platform
: 25 May 2012
S L R S L R
1 Anchor Handling
(Running
Messanger Line
Under the
Bridge) using
Work Boat
Work Boat collision with
the platform / AHT
Boat damage / lost boat
Personnel injury
5 2 HR 1. Approved Anchor Handling Procedure
2. Reliable / maintained work boat
3. Weather limit
4. Adequate illumination of work area
5. Trained work boat operation
6. Maintain good communication
7. JSA for work boat operation
8. FRC/MOB Boat ready at all time
9. Suitable PPE: include work vest
1 1 LR
Lost control of wire due
to failure of
comunication or control
system
Damage to redundant
umbilical / subsea structure
3 2 MR 1. Approved Anchor Handling Procedure
2. DP Vessel as AHT
3. Reliable and well maintained vessel (with
MWS approval)
4. Competence Vessel Captain
5. Maintain good communication between
Anchor Tower and AHT
3 1 LR
AHT collision with the
platform / complex
Damage to vessel or
complex (damage to riser)
Personnel injury
Schedule delay
5 3 HR 1. Approved Anchor Handling Procedure
2. JSA for Anchor Handling
3. Weather limit for Anchor Handling
4. Parachute Buoy
5. DP Vessel as AHT
6. Reliable and well maintained vessel (with
MWS approval)
7. Competence Vessel Captain
8. Maintain good communication between
Anchor Tower and AHT
9. Weather limit
10. Briefing about the facility for all Vessel
Captain including the location of risers
11. Secondary AHT standby in the field at all
time
3 1 LR
Project
Node Description
Date of HAZID Study
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
2 Running Anchor
/ Anchor Wire
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 1 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Drop/Drag Anchor on
Subsea Facility
Damage Subsea Facility
Environmental HC
Discharge
Potential fire/explosion
Company reputation
5 3 HR 1. Subsea / Seabed Survey DONE
2. Approved Anchor Handling Procedure and
Approved Anchor Pattern
3. Anchor on Deck of AHT
4. Mooring Analysis
5. BMS/Survey Equipment Calibration
6. Pull test the anchors
7. Continue anchor wire tension monitoring by
Anchor Tower
8. Shut Down & Depressurize West Lobe line
9. Compliance with POI Marine Procedure
3 1 LR
3 DLB Approach /
Final Departure
of AGX
DLB colission with
platform and riser
Damage to both DLB and
Platform
Personnel injury / Lost of life
Schedule delay
Environmental impact
5 2 HR 1. Approved Anchor Handling Procedure
(Step by Step DLB Approach to AGX)
2. Weather limit
3. Maintain good communication with all
parties
4. Final approach only after all anchors are
installed / laid and DAY Light only.
5. Shut Down the platform and Depressurize
West Lobe line during Final Approach
6. AGX Riser is inside the Jacket
7. Responsible person on DLB monitoring the
gangway tip during final approach
8. Minimize personnel on AGX during DLB
final approach
9. Complete GO and No GO Checklist for the
DLB Final Approach to AGX
10. Anchor removal for final departure is
the reverse of anchor installation. (Meeting
will be performed with relevant parties
including MWS for removal anchors).
3 1 LR
2 Running Anchor
/ Anchor Wire
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 2 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Dropped loads / objects
on Topside of AGX /
Subsea Facilities
Damage asset causing HC
leak
Personnel injury
Schedule delay
Environmental delay
5 4 HR 1. Approved Lifting Procedure
2. Certified and good condition Crane (include
MWS inspection/approval)
3. Certified and good condition Rigging
4. Certified and experienced Crane Operator
and Rigging Personnel
5. Maintain good communication among
parties involved
6. All lift within the SWL of the crane / rigging
7. Weather limit
8. Stay clear from load
9. Suitable PPE
4 1 MR
Crane Boom collision
with the AGX Topside
and/or with Other Crane
Damage asset causing HC
leak
Personnel injury
Schedule delay
4 3 HR 1. All Cranes will be under the control of the
Project (CTR).
2. Designated Person In Charge for Every Lift
3. Good illumincation
4. Procedure control for Cranes Operations
(SIMOPS)
5. Detail planning meeting for Crane
Operations
6. Trained and experienced Crane Operator
and Rigging Personnel
7. Maintain good communication among all
involved parties
3 1 LR
1 1. Risk Assessment to be
performed for using the
Crawler Crane for Personnel
Transfer related to the
visibility (ability of the Crane
Operator to see the FROG)
Timas/POI
2 2. Review Crawler Crane
Operation Procedure
Timas
3 2 MR 1. Weather limit
2. Barge rails in place
3. Certified and good condition crane
4. Certified and good condition rigging
equipment
5. Certified and experienced Crane Operator
and Rigging Personnel
6. Operate cranes within the design limit
3
4 DLB Crane
Operation
Crawler Crane fall over
the side due to bad
weather related during
lifting (overloaded /
dynamic load)
Damage asset causing HC
leak / Environmental impact
Personnel injury
Schedule delay
1 LR
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 3 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
DLB Exhaust Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR 1. DLB Exhausts are located on the STBD
Forward.
2. Gas is lighter than air (Gas-Gas Exchanger
is +16 elevation)
3. F&G and ESD System on AGX
4. ERP Procedures
5. Platform will inform the DLB in case of F&G
detection system on platform is activated
6. PM on platform e.g. leaks prevention
7. Portable Multi-Gas Detector on Stern of
DLB
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
Electrical Equipment on
DLB (Lights, Etc)
Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR 1. Gas is lighter than air (Gas-Gas Exchanger
is +16 elevation)
2. F&G and ESD System on AGX
3. ERP Procedures
4. Platform will inform the DLB in case of F&G
detection system on platform is activated
5. PM on platform e.g. leaks prevention
6. Switch off the light on Crane Boom during
the Day Light
7. Weather proof lighting/electrical system on
the barge deck and crane boom
8. DLB can be pulled / winched away (winch
speed approx 60m per minute)
9. Construction activities around process area
controlled by PTW asper integrated project
plan
10. Portable Multi-Gas Detector on Stern of
DLB
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR 3 Explore the possibility to
switch off the lights and other
ignition source on crane
Timas
5 Ignition Source
on DLB
- Gas Release
(10mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 4 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Crawler Crane Exhaust Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR 1. Crawler Crane is located more than 60
meters away
2. Crawler Crane Exchaust is fitted with Spark
Arrestor
3. Gas is lighter than air (Gas-Gas Exchanger
is +16 elevation)
4. F&G and ESD System on AGX
5. ERP Procedures
6. Platform will inform the DLB in case of F&G
detection system on platform is activated
7. PM on platform e.g. leaks prevention
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
Welding Machines on
DLB
Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR 1. During SIMOPS, Welding Machines are
located on DLB are 60m away from the
platform.
2. Standby Persons to disconnect the welding
leads to Platform and shut down (turn off) the
welding machines on DLB.
3. Gas is lighter than air (Gas-Gas Exchanger
is +16 elevation)
4. F&G and ESD System on AGX
5. ERP Procedures
6. Platform will inform the DLB in case of F&G
detection system on platform is activated
7. PM on platform e.g. leaks prevention
8. Portable Multi-Gas Detector on Stern of
DLB
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
5 Ignition Source
on DLB
- Gas Release
(10mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 5 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Hot Works on DLB Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR 1. All Hot Works on DLB Deck will be covered
by PTW
2. Standby Persons to disconnect the welding
lead to Platform and shut down (turn off) the
welding machines on DLB.
3. Gas is lighter than air (Gas-Gas Exchanger
is +16 elevation)
4. F&G and ESD System on AGX
. ERP Procedures
5. Platform will inform the DLB in case of F&G
detection system on platform is activated
6. PM on platform e.g. leaks prevention
7. Portable Multi-Gas Detector on Stern of
DLB
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
5 Ignition Source
on DLB
- Gas Release
(10mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
COMMENT: The probability (frequency) of having leaks will be further elaborated (POI)
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 6 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
DLB Exhaust Increase risk of
Fire/Explosion in the event
of HC release
1 1 LR The release of HC with 100mm hole is demonstrated to unlikely because:
1. As per QRA
2. Process Integrity Management e.g. FLIR
Camera, rectification of significant TSS Matrix
Integrity Related Defect. All Integrity related check
and improvement are included on the GO and NO
GO Process.
3. No break of containment the process system
during SIMOPS
4. No Heavy Lifting over the process during
SIMOPS (Most construction activities involved
small weights - structure lifted in around the
platform edges west and south
5. Drop Object Protection is in place for Gas Gas
Exchanger
The risk of release of gas has been reduced to
ALARP, if it would occur the severity would be less.
Additional Safeguards:
1. DLB Exhausts are located on the STBD
Forward.
2. Gas is lighter than air (Gas-Gas Exchanger is
+16 elevation)
3. F&G and ESD System on AGX
4. ERP Procedures
5. Platform will inform the DLB in case of F&G
detection system on platform is activated
6. PM on platform e.g. leaks prevention
7. Portable Multi-Gas Detector on Stern of DLB
NOTE: based on 100mm hole during the study, the
dispersion of HC release / gas cloud would NOT
reach the DLB Exhaust.
1 1 LR6 Ignition Source
on DLB
- Gas Release
(100mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 7 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Electrical Equipment on
STERN of DLB (Lights,
Etc)
Increase risk of
Fire/Explosion in the event
of HC release
5 1 HR The release of HC with 100mm hole is demonstrated to unlikely because:
1. As per QRA
2. Process Integrity Management e.g. FLIR
Camera, rectification of significant TSS Matrix
Integrity Related Defect. All Integrity related check
and improvement are included on the GO and NO
GO Process.
3. No break of containment the process system
during SIMOPS
4. No Heavy Lifting over the process during
SIMOPS (Most construction activities involved
small weights - structure lifted in around the
platform edges west and south
5. Drop Object Protection is in place for Gas Gas
Exchanger
The risk of release of gas has been reduced to
ALARP, if it would aoccur the severity would be
less.
Additional Safguards are:
1. F&G and ESD System on AGX
2. ERP Procedures
3. Platform will inform the DLB in case of F&G
detection system on platform is activated
4. Close water tight doors on the crane tub
5. Portable Multi Gas Detector on the Stern of
DLB.
6. Any lifting over the process during the SIMOPS
shall be covered by PTW, Risk Assessment.
4 1 MR 4 Requirement of Multi Gas
Detector on the STERN of
DLB to be captured in Project
Procedure
Timas
6 Ignition Source
on DLB
- Gas Release
(100mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 8 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Crawler Crane Exhaust Increase risk of
Fire/Explosion in the event
of HC release
5 1 HR The release of HC with 100mm hole is demonstrated to unlikely because:
1. As per QRA
2. Process Integrity Management e.g. FLIR
Camera, rectification of significant TSS Matrix
Integrity Related Defect. All Integrity related check
and improvement are included on the GO and NO
GO Process.
3. No break of containment the process system
during SIMOPS
4. No Heavy Lifting over the process during
SIMOPS (Most construction activities involved
small weights - structure lifted in around the
platform edges west and south
5. Drop Object Protection is in place for Gas Gas
Exchanger
The risk of release of gas has been reduced to
ALARP, if it would aoccur the severity would be
less.
Additional Safguards are:
1. Crawler Crane is located more than 60 meters
away
2. F&G and ESD System on AGX
3. ERP Procedures
4. Platform will inform the DLB in case of F&G
detection system on platform is activated
5. PM on platform e.g. leaks prevention
6. Crane Crawler will be shut down upon the
detection of Gas Release after operation is
secured.
4 1 MR
6 Ignition Source
on DLB
- Gas Release
(100mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 9 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Welding Machines on
DLB
Increase risk of
Fire/Explosion in the event
of HC release resulting:
- Personnel injury
- Asset damage
5 1 HR The release of HC with 100mm hole is demonstrated to unlikely because:
1. As per QRA
2. Process Integrity Management e.g. FLIR
Camera, rectification of significant TSS Matrix
Integrity Related Defect. All Integrity related check
and improvement are included on the GO and NO
GO Process.
3. No break of containment the process system
during SIMOPS
4. No Heavy Lifting over the process during
SIMOPS (Most construction activities involved
small weights - structure lifted in around the
platform edges west and south
5. Drop Object Protection is in place for Gas Gas
Exchanger
The risk of release of gas has been reduced to
ALARP, if it would aoccur the severity would be
less.
Additional Safguards are:
1. During SIMOPS, Welding Machines are located
on DLB are 60m away from the platform.
2. Standby Persons to disconnect the welding lead
to Platform and shut down (turn off) the welding
machines on DLB.
3. F&G and ESD System on AGX
4. ERP Procedures
5. Platform will inform the DLB in case of F&G
detection system on platform is activated
6. PM on platform e.g. leaks prevention
7. Refer to Technical Note for Control of Welding
Machines Isolation
8. Portable Gas Detector on the STERN of the
DLB.
4 1 MR
6 Ignition Source
on DLB
- Gas Release
(100mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 10 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Hot Works on DLB Increase risk of
Fire/Explosion in the event
of HC release resulting:
- Personnel Injury
- Asset Damage
5 1 HR The release of HC with 100mm hole is demonstrated to unlikely because:
1. As per QRA
2. Process Integrity Management e.g. FLIR
Camera, rectification of significant TSS Matrix
Integrity Related Defect. All Integrity related check
and improvement are included on the GO and NO
GO Process.
3. No break of containment the process system
during SIMOPS
4. No Heavy Lifting over the process during
SIMOPS (Most construction activities involved
small weights - structure lifted in around the
platform edges west and south
5. Drop Object Protection is in place for Gas Gas
Exchanger
The risk of release of gas has been reduced to
ALARP, if it would aoccur the severity would be
less.
Additional Safguards are:
1. All Hot Works on DLB Deck will be covered by
PTW
2. Standby Persons to disconnect the welding lead
to Platform and shut down (turn off) the welding
machines on DLB.
3. F&G and ESD System on AGX
4 ERP Procedures
5. Platform will inform the DLB in case of F&G
detection system on platform is activated
6. PM on platform e.g. leaks prevention
7. Portable Gas Detector on STERN of DLB
4 1 MR
Fire as Ignition Source
and its Impact to the
Safety of the Platform
Complex
Increase Risk of Fire on
Platform (AGX) if there is
concurrent HC Release
2 2 LR 1. DLB can be pulled / winched away from the
Platform (winch speed is approx 60m per
minute).
2. F&G System and Fire Fighting System on
the DLB
3. ERP
4. Portable Gas Detector on the STERN of
the DLB.
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
6 Ignition Source
on DLB
- Gas Release
(100mm hole on
Gas-Gas
Exchanger) with
20knots wind
speed toward
the DLB
7 Emergency (Fire)
on DLB
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 11 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Helicopter Emergency
on DLB
Increase Risk of Fire on
Platform (AGX) if there is
concurrent HC Release
2 2 LR 1. DLB can be pulled / winched away from the
Platform (winch speed is approx 60m per
minute).
2. F&G System and Fire Fighting System on
the DLB
3. ERP
4. Portable Gas Detector on the STERN of
the DLB.
NOTE: based on 10mm hole during the study,
the dispersion of HC release / gas cloud
would NOT reach the DLB.
1 1 LR
Failure of Main
Generator / Black Out
on DLB
DLB cannot pull away in
case required
3 2 LR 1. Redundancy of Generators
2. Emergency Power Generator
3. Fail Safe Brake on the anchor winches
4. AHT / Tow Tug standby in the field at all
time
5. PM System on DLB
1 1
Increasing Flaring Rate
due to Blow Down Event
Increase Radiant Heat in the
vicinity of AGX Crane
NOTE: No Effect anticipated
to the DLB based on Flare
Radiation Study
2 2 LR 1. Radiant Heat Study for AGX shows that it
is safe for the Crane Operator to be inside the
Crane Cabin during Full Process Blow Down.
2. Proximity of DLB Crane Operator is farther
from the Flare Tip therefore impact of Radiant
Heat is minimal.
1 1 LR
ESD Event Causing
AGX Process Instability
Creates changes in Process
System Pressure,
Temperature, and Liquid
Inventory which could lead
to an increase potential for
HC release
2 2 LR 1. Process System is designed to fail safe
2. Process is continuosly monitored from
CCR
3. Process System will be maintained and
functional with no significant case to operate
in place during SIMOPS
4. Contingency Plan in place such that AGX
Project Team will be asked to leave AGX until
ESD event has been rectified
5. COntingency Plan in place such that HOFO
will communicate potential for escalation to
DLB such that preparation may made for DLB
withdrawl from AGX vicinity.
1 1 LR
7 Emergency (Fire)
on DLB
8 Process Upset
on AGX
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 12 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
Gas Release Anoa
Riser
Fire / Explosion
Personnel Injury
5 2 HR 1. Mitigation as per CTO Procedure
2. F&G System on AGX
3. ERP Procedures
4. Platform will inform the DLB in case of F&G
detection system on platform is activated
5. DLB can be pulled / winched away to clear
from platform (winch speed approx 60m per
minute)
5 1 HR
9 Helicopter
Operation on
DLB
Interference with Crane
Operation
Helicopter collision with
Cranes / Crash
Personnel injury / Lost of life
4 3 HR 1. Crane Operations on DLB will be shut
down and/or crane boom would be clear for
Helicopter Operations
2. Trained and experienced HLO
3. Inform Crane Operators of Incoming
Helicopters
4. ERP
3 1 LR
10 Vessel
Movement /
alongside on
DLB
Collision with the DLB /
Platform / Material
Barge / Anchor Buoy /
Anchor Wire
Asset damage
Personnel injury / Lost of life
Schedule delay
4 3 HR 1. Suitable Vessels (Include MWS
inspection/approval)
2. Competent Vessel Captain
3. Slack Anchor Wires if required
4. Good communication between paties
involved
5. Weather limit
6. Adequate fendering on DLB and vessels
7. Briefing to all Vessel Captain prior to
entering 500m zone
8. High Vis painted Anchor Buoys
9. Comply with POI Marine Operation
Procedure
10. Establish communication with HOFO prior
to entering 500m Zone and/or Marine
Supertindent prior to approaching DLB
2 2 LR
11 SIMOPS
Operation
Between DLB
Crane and AGX
Crane
DLB Crane Boom
collision with the AGX
Crane
Damage asset
Personnel injury
Schedule delay
4 3 HR 1. All Cranes will be under the control of the
Project (CTR).
2. Designated Person In Charge for Every Lift
3. Good illumincation
4. Procedure control for Cranes Operations
(SIMOPS)
5. Detail planning meeting for Crane
Operations
3 1 LR
8 Process Upset
on AGX
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 13 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
12 Personnel
Transfer
Personnel being
Transferred Fall from
Height
Personnel injury / Lost of life 5 3 HR 1. Certified and good condition Crane
2. Certified and good condition FROG
3. Certified and good condition rigging
4. Provision of safety sling
5. No personnel transfer untill the Vessel will
be securely moored
6. Distance of free board between DLB and
vessel is small
7. Provision of tag lines
8. Familiarization for transfer using FROG
9. Maintain good communicaton among
parties involved (CO, Bunksman, and
Riggers).
10. Weather limit defined for personnel
transferring using FROG and Crawler Crane
2 1 LR
Pool Fire on ANOA
coming from ANOA 8"
Riser Pipeline
Personnel injury / Lost of life
Impair both ANOA and AGX
Muster Area
5 1 HR 1. All personnel shall muster to DLB including
POI Personnel
2. Corrosion Monitoring and Pigging Pipeline
covered by FIMS
3. PSLL on the pipeline
4. Daily surface inspection
5. DLB will be pull / winched away
5 1 HR
Condensate on the sea
due SKIM pile overfilled
Personnel Injury / Lost of
Life
3 1 MR 1. Level Management
2. Daily surface inspection
3. DLB will be pull / winched away
1 1 LR
5 Verify the certification of the
storage tank and inspection
prior to mobilization offshore
Timas / PNS
6 Review the N2 handling and
storage procedure
Timas / PNS
N2 Spill Personnel Injury
Cryogenic
Embrittlement
3 3 MR 1. Engineered and certified ISO Storage
Tanks
2. Scaffold and bunded area
3. Use of planks and tarpaulin
3 2 MR
3
13 MAE on
AGX/ANOA
MR 1. Engineered and certified ISO Storage
Tanks
2. Scaffold and bunded area
3. Use of planks and tarpaulin
3 2 MR14 N2 Operation Extreme Temperature
(minus 160 - minus 200
C)
Personnel injury
Cryogenic
Embrittlement
3
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 14 of 15
HAZID WORKSHEET
S L R S L R
Initial RiskNo Type of Event Potential Hazards Consequences
Safeguards
(Existing and Recommended Control
Measures)
REC # Recommendation Action PartyResidual Risk
15 3rd Party Vessel
/ Security
Collision with the
Anchor Buoy / Anchor
Wire
Personnel Injury
Asset Damage
Schedule Delay
3 2 MR 1. High Vis Anchor Buoy
2. Standy By Vessels
3. Radar Watch
4. Intensity of Marine Activities would deter
the 3rd Party Vessel to stay away
5. Liaison Officer onboard of DLB
3 1 LR
16 Sabotage Construction Crew
tempering with Platform
and DLB system
Increase risk of incident 3 2 MR 1. Socialization of work to the offshore
construction team in advance
2. PTW, JSA, and workpacks
3. Involve operation team during work pack
review and execution of the works
4. Maintain positive working environment,
provide motivation
5. Restriction to sensitve areas (security
measures) e.g. safety / warning signs,
socialize restricted areas during
meeting/awareness, Access Control
6. Maintain adequate supervision / QC
7. Reward program
3 1 LR 7 Operation to review the
existing "security measures"
and improve as required
POI
17 Communication
between DLB
and its Support
Vessels and
between DLB
and AGX/ANOA
Clear Communication
Method NOT
established
Increase risk of
miscommunication /
interference leading to
incident resulting to:
- Personnel injury
- Asset damage
3 2 MR 1. ANOA HSE Induction / Awareness
2. Various coordination meeting e.g. daily
planning meeting
3. Provision of radio communication
4. English speaking key personnel
5. Permission to be obtained from HOFO prior
to entering 500m zone
6. Permission to be obtained from Marine
Superintendent for approaching DLB or
entering the Anchor Pattern
7. Competent Vessel Captain
8. Briefing of all support vessels include
socialization of procedures
9. Complete GO and No GO Checklist.
3 1 LR 8 Establish radio
communication channel for
all parties to minimize
interference
Timas/POI
HAZID Study for Premier ANOA Phase 4 - AGX Compression Reconfiguration Project N1 Page 15 of 15