Upload
akintoye-asaolu
View
98
Download
2
Embed Size (px)
Citation preview
Structured Checklist Approach should be used to identify hazards during the entire life of the facility. To achieve this aim, the facility Life has been divided to Pre-operational phase, Operational phase, Post Operational Phase
The preoperational phase consists of
Drilling of new wells and well completion Construction and Tie in of Flow lines and Pipelines Hook up and commissioning of well heads and Flow lines
Operational phase consist of
Normal well production operations Well maintenance activities Simultaneous operations
Post Operational Phase Involves
Pipeline decommissioning Well Kill operations/ well decommissioning
The following will be considered
The impact of the natural environment on plant operations The Impact of the Plant/activity on the Human environment Effects of manmade hazards on the plant Effects of infrastructure supporting the facility where applicable Process Hazards where applicable Utility system Hazards Health hazards Other hazards within the facility
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
1 Well heads Subject Infill wells Impact of natural environment
Lightening during drilling
Thunder storms Possible Damage to electronic drilling equipment
Possible well kick Possible Blowout Explosion/Fires Injuries/ fatalities
Ensure drilling contractor demonstrates adequate preparation for this hazard by checking that the following items are met at minimum
By use of full-size ground conductor to earth rig equipment
The use of bare copper conductor or braided wire, sized not less than 2/0 AWG, connected between all electric motors to the building or skid. All buildings or skids should be interconnected with the same size conductor
An earth rod will be driven as close as possible to low wet areas to achieve desired grounding. Rods should be at least eight feet (2.4 meters) long and 3/4” (1.9 cm) in diameter. Outer surface of rods should be either galvanized or copper coated.
If rock is encountered, the rod should be driven at an angle not to exceed 45 degrees from vertical or should be buried in a trench that is at least 30 inches (76.2 cm) deep. Fill trench with a 3/32” (2mm) layer of salt. Backfill with native earth. Earth substructure to conductor in order to
1
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
achieve desired grounding.
Bond all skids and auxiliary equipment together to form a “loop” type system, wherever possible, so that the continuity of the grounding circuit will be maintained even if one conductor is severed.
Grounding connections on skids should be rust-proof (stainless steel bolts are recommended).
2 Well heads Subject Infill wells Impact of natural environment
Continuous/ Frequent Plant discharges to air from nearby facilities during drilling
Discharge from Flow station Cold vents
Toxic Combustion Products from adjacent flow station Flare
Flammable gas around drilling Vicinity
Flash Fire/ JET Fire Explosion
Company consideration has been given to emissions from existing nearby facilities
Hazardous area classification should be in place for the well sites during drilling operations
Electrical equipment should be rated for use within defined hazardous zones
TPENG should put in place (PTW) systems for operations likely to increase the probability of ignition, if not in existence
3 Well heads Subject Infill wells Impact of natural environment
Emergency/ Upset Plant discharges to air from nearby facilities during drilling
Discharge from Flow station Cold vents
Toxic Combustion Products from adjacent flow station Flare
Flammable gas around drilling Vicinity
Flash Fire/ JET Fire Explosion
Verify if Company consideration has been given to emergency emissions from existing nearby facilities
Hazardous area classification should be in place for the well sites during drilling operations
Electrical equipment should be rated for use within defined hazardous zones
TPENG should put in place (PTW) systems for operations likely to increase the
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
probability of ignition, if not in existence
4 Well heads Subject Infill wells Impact of drilling on natural environment
Noise emanating from well site during drilling operations
Heavy Duty and Vibrating equipment
Hearing impairment to drillers due to excessive noise levels
Brain stress leading to concentration loss
Occupational hazards
Speech Interference Community
annoyance (subject to confirmation of community closeness)
Facility has been located far from inhabited areas
Establish baseline noise tolerability criteria if not in place
Carry out a noise assessment study for the drilling operation
Ensure drilling contractor presents a valid noise control plan for the facility
Ensure appropriate PPE are worn during noise drilling operations
5 Well heads Subject Infill wells Impact of Drilling on the Natural Environment
Vibrations from drilling operations
Drilling equipment Vibrations
Torsional Vibrations
Well conditions Poor Adherence to
drilling plans
Drilling equipment failure
Geophysical studies have been done to ensure that a durable drilling plan would be prepared
Ensure Drilling contractor prepares a well drilling plan
Select appropriate contractor for drilling task
Consider putting systems in place to ensure compliance with drilling plan
6 Well heads Subject Infill wells Impact of Drilling on the Natural Environment
Environmental pollution during drilling operations
Hydrocarbon Effluent discharge to environment
Solid and hazardous waste discharge to environment
Pool fire Environmental
concerns Potential liability
concerns Company Image
concerns
The drilling location and the associated roads should be planned so that they are constructed such that storm water runoff is diverted away from the location and that the location's storm water runoff
Appropriate waste minimization techniques should be incorporated into drilling mud system design in drilling plan
Reserve Pit design should ensure pit is V-shaped so that muds wont channel away from the suction
Equipment modifications
Process or procedural
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
modifications Inventory control Good housekeeping
and preventive maintenance
Contractor selection Drilling Contractor
should consider the options of recycling
6 Well heads Subject Infill wells Impact of manmade hazards on the facility during drilling operation
Security Breach on drill site during drilling operations
Internal sabotage Inadequate
security plan Inefficient
resources to implement security plans (poor lightening, communication gadgets, e.t.c)
Injuries/ fatality Drilling equipment
theft Vanadalization of
existing equipment
Injuries/ fatality Drilling equipment
theft Vanadalization of
existing equipment
Update security plan to continually cater for present security realities during the entire facility life
Employee security background check should be in place for staff and drilling contractors of not in place
Emergency Response plan should be in place (check if applicable)
Ensure lightening is in place at all times during drilling operations
Adequate escape and evacuation plans should be in place
7 Well heads Subject Infill wells Effects of infrastructure supporting the facility
Support supply failure to facility during drilling operations (shortage of drill muds, shortage of vital drilling chemicals,
Poor road condition
Contractor oversight
Project Monitoring oversight
Accident Project delay
resulting in financial loss
Injury Fatality Chemical Exposure
(occurs if there is a loss of containment)
None as at the moment (subject to TPENG verification)
Good selection process for drilling contractor
A Detailed drilling plan , completion and testing plan should be in place
Prepare Journey management plan and subject it to several layers of verification
Prioritize local procurement of materials
8 Well heads Subject Infill wells Release of Flammable /toxic Inventory during drilling
Emissions from power generation equipment/ combustion engines
Asphyxiation (carbon monoxide poisoning)
Explosion
Hazardous area classification of the drilling site has been carried out
If combustion engines are in place, ensure flue gas orientation is oriented towards a safe area.
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
Well testing operations
Mud degassing In efficient rig
commissioning and decommissioning opeartion
A plume dispersion studies should be conducted to verify this
Ignition sources should be verified by ensuring only equipment rated for the given haxardous zones are permitted into the drilling site
Good drilling plan Good completion plan Good testing plan
9 Well heads Subject Infill wells Blow out Failure of blow out preventers
Well bore ruptures Gas Migration
from reservoir
Injury Fatalities Explosion/ Fire
Good drilling plans should be put in place by drilling contractor
Drilling operations should be monitored to ensure that drilling plans are followed
10 Well heads Subject Infill wells Lifting operation hazards during drilling
Dropped objects and swing loads
Damage to Drilling equipment
Fatality or Risk Mud discharge Pollution
Ensure lifting equipment is certified fit for use
Ensure Crane operator is certified
Ensure measures are taken to keep workers and vulnerable equipment off lifting radius
Drilling Plan Develop emergency
response plan
11 Well heads Subject facilities Onsite traffic hazards during Drilling operations
Vehicular damage to existing flow lines and manifold
Increase risk of accidents within the facility due to the increased movement frequencies
Driver fatigue Non adherence to
speed limits
Loss of containment Fire Explosion Damage to existing
well heads Financial loss Injury Fatality
Access roads to the drilling site have been marked
There is a fence barrier within the well enclosure
Fire and Gas detection system is installed on existing well heads
Shutdown procedures in place to control hazards
Ensure speed limits are enforced
Consider a vehicle tracking system to help enforce speed limits
Consider discouraging private transportation for drilling site workers. Provide public transportation systems for every drilling worker to minimize the frequency of
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
Vehicular activity Ignition suppression
measures should also be in place.
Adequate escape and evacuation plans should be in place
Wellheads Entire facility Construction/ hook up activity disruption due to bad weather conditions (Rain)
Wet season Slips, Trips and falls LTI Project delay Revenue loss
Look into the possibility of ensuring tie in and modification activities are carried out during dry season
12 Well heads Entire facility Lightening during Tie in and modification works to well head
Thunderstorms Electrical shock Injury Fatality
Flow lines, Piping and pipe supports should be earthed according to the prevailing standards
13 Entire facility Release of flammable inventory during hook up and commissioning
Dropped object on existing flow line during hook up
Rupture/ leak of existing flow station due to vehicular impact during loading and unloading operations
Lack of communication,
Poor lifting operations
Overpressure during pressure testing of pipelines
Leak during pressure testing of pipelines
Leak Fire Explosion Loss of revenue Flow line rupture
Fire and gas detectors have been installed on existing flow line configuration
Existing flow wells have flow and pressure monitoring in place. This helps isolate the ruptured or leaking section and minimizes inventory loss
Verify that existing flow line(s) from producing well(s) have/has been designed for relevant sizing cases.
Selection of hook up of contractor
As part of permit to work system, consider ensuring that the Pre Job JSA’s and hazard identification techniques are carried out before commencement of operations
To suppress the chances of ignition, welding operation should only be done after PTW systems must have taken effect
14 Entire Facility Loss of vital utility systems (power, air, fuel gas/oil)
Power failure Loss of supply of
fuel gas oil Loss of
containment of fuel gas oil
Disruption in hook up and tie in operations
Equipment or machinery failure
Project delays Loss of revenue
Consider ensuring hook up contractor carries out a pre-construction risk assessment and make a good construction plan . This ensures that utility requirement are
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
outlined and provided for before commencement of tie In and hook up operations.
Security Breach on construction site during hook up and Tie in operations
• Internal sabotage
• Inadequate security plan
• Inefficient resources to implement security plans (poor lightening, communication gadgets, e.t.c)
• Injuries/ fatality
• construction equipment theft
• Vanadalization of existing equipment
• • Update security plan to continually cater for present security realities during the entire facility life
• Employee security background check should be in place for staff and drilling contractors of not in place
• Emergency Response plan should be in place (check if applicable)
• Ensure lightening is in place at all times during construction operations
• Adequate escape and evacuation plans should be in place
Socio Political Unrest during hook up and tie in of flow lines
Riots Civil disturbances Political Unrest
Delay in construction operation due to industrial strike action
Project delay Revenue loss Increased security
around facility Subject take over by
new regime
It is assumed that adequate consideration has been given to the political situation around the country and it has been deemed fit to conduct the product for its entire life. However in the event of such occurrences , a viable exit strategy is in place
Ensure security plan on site during the entire life of the facility caters for incidents like this
Release of hazardous solid/gaseous materials to the environment during line flushing and purging respectively to the environment
Inadequate waste management plan
Leak around the flow line /piping segment
Environmental pollution
Asphyxiation if Nitrogen is used for purging
Injury Fatality
Ensure company guidelines for pipeline and flow line pre-commissioning tests are adhered due during these operations
Construction contractor / responsible party should prepare a pipeline/Flow line purging and pressure testing philosophy
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
Continuous emissions from nearby producing well head facilities
Well head blow out
Well head leak Flow line rupture/
damage due to dropped objects
Flow line damage due to drilling activity
Gas leak Ignition Fire Explosion Liquid pool
Design provisions for Fire and Gas detection systems on the subject site are in place
Minimize sources of ignition and ensure that only approved hot work is done in the vicinity of the existing flow lines
Ensure electrical equipment within the construction site are rated for the hazardous zones
Verify that existing flow line and pipelines on the subject are clearly marked
Consider ensuring contractor develops a construction risk management plan.
Noise resulting from flow lines and Tie-in operations
Heavy noise generating equipment
• Hearing impairment to drillers due to excessive noise levels
• Brain stress leading to concentration loss
• Speech Interference
• Community annoyance (subject to confirmation of community closeness)
• Facility has been located far from inhabited areas
• Establish baseline noise tolerability criteria if not in place
• Carry out a noise assessment study for the construction operation
• Ensure drilling contractor presents a valid noise control plan for the facility
• Ensure appropriate PPE are worn during noisy construction operation
Increased Vibration around facility due to construction operation
Heavy equipment vibration
Vibration stress induced in existing flow lines and well head facilities
Pipeline/Flow line failure
Loss of containment Explosion Fire
Construction contractor should estimate the expected magnitude of vibration , its impact on existing facilities on subject and appropriate risk management decision should be noted.
This is part of the wider document called construction risk management plant
slips, trips and falls during Construction
Poor construction site layout
Cluttered construction site
Injury LTI Fatality
Company and construction contractor should agree on a proposed construction site layout as specified in
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
the construction risk assessments and construction Risk management plan that has been recommended earlier
Company should ensure compliance with appropriate construction site safety regulations with respect to contractor
Lightening during normal facility operation
Thunder storms Inadequate
earthening systems
Damage to well head control panels
Damage to electrical functions (lightening and other electrical dependent facilities) around the facility
All forms of electrical equipment have been designed to be appropriately earthed
Continuous /frequent discharges to air from nearby flow station during normal facility operations
Gas dispersion from adjacent flow station cold vents and flares
Toxic Combustion products from adjacent flow station flare
Explosion Injury/Fatality Asphyxiation
Sensitive fire and gas detection system has been provided for all zones of the facility in the design
Hazardous area classification has been done and a schedule of electrical equipment to be used within the zone has been generated
Plans are currently on the way to stop/minimize flaring at adjacent flow station facilities in the long run
Consideration has been given to the dispersion of flammable gas from the flow station to subject infill wellheads and associated
TPENG should put in place (PTW) systems for operations likely to increase the probability of ignition, if not in existence
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
flow lines within the subject facility , it is seen that emmisions from OFS does not in anyway constitute a risk to the subject facilities
Emergency/upset discharges from nearby flowstation during normal facility operations
Gas dispersion from adjacent flow station cold vents and flares during emergency operations
Toxic Combustion products from adjacent flow station flare during emergency operations
Explosion Injury/Fatality Asphyxiation
Sensitive fire and gas detection system has been provided for all zones of the facility
Hazardous area classification has been done and a schedule of electrical equipment to be used within the zone has been generated
Plans are currently on the way to stop/minimize flaring at adjacent flow station facilities
TPENG should put in place (PTW) systems for operations likely to increase the probability of ignition, if not in existence
Verification to be made as to whether flare studies where made for emergency flaring conditions
Noise emanating from well site during normal operations
Erosion of flow lines
Hearing impairment to drillers due to excessive noise levels
Brain stress leading to concentration loss
Occupational hazards
Speech Interference Community
annoyance (subject to confirmation of community closeness)
Facility has been located far from inhabited areas
Erosion has been reduced to the bearets minimum during line sizing
Establish baseline noise tolerability criteria if not in place
Carry out a noise assessment study for the normal operation
Ensure there is a valid noise control plan for the facility
Piping team should ensure that there are few sudden break and turns in pipe routing.
Vibrations from normal operations
Vibrations resulting from fluid flow
Pipe/flow line failure Loss of containment Fire Explosion spill
The effects of vibration were duly factored in the piping design
Appropriate Fire
Ensure that only electrical equipment certified for use in hazardous zones are in place
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
and gas detection systems are in place to ensure successful detection and mitigation should a piping failure occour
Hazardous area classification has also been done to classify hazardous zones appropriately
6 Well heads/ flowlines and manifolds
Subject Infill wells Impact of normal plant operations on the well heads on the Natural Environment
Environmental pollution during normal operations
Loss of containment
Leak of piplines/ flowlines and well heads
Pipline rupture on flowlines and pipelines
Valve failure on well head
Pool fire Flash/ jet fire explosion spill Potential liability
concerns Company Image
concerns
Active fire and gas detection systems have been provided in the design of the facility
Active fire fighting systems have been provided to in the facility design
Appropriate shutdown levels are in place to minimize inventory loss as soon as it is detected
Flow monitoring and pressure sensing devices have also been factored into the design to rapidly detect leaks.
Ensure routine inspection and maintenance of well heads, flow lines and pipelines
Ensure the reliability of the fire and gas system meets the required specifications
Ensure reliable vendors for fire and gas detection systems are patronized. This is to ensure that fire and gas detection system don’t give spurious alarms or do not reamin ineffective.
6 Well heads Subject Infill wells Impact of manmade hazards on the facility during drilling operation
Security Breach on Subject facility during normal operations
Internal sabotage Inadequate
security plan Inefficient
resources to implement security plans (poor lightening, communication gadgets, e.t.c)
Injuries/ fatality Vanadalization of
existing equipment Theft of mobile
equipments Revenue loss
Perimeter fencing is in place to countger security threats
There is an existing provision for routine patrol on the installation
Update security plan to continually cater for present security realities during the entire facility life
Employee security background check should be in place for staff and maintenance personnel if not in place
Emergency
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
Response plan should be in place (check if applicable)
Ensure lightening is in place at all times during drilling operations
Adequate escape and evacuation plans should be in place
7 Well heads Subject Infill wells Effects of infrastructure supporting the facility
logistics failure during mobilization of critical supplies (lubricant fluids, hydraulic fuids) to site during normal operations
Poor road condition
Port Clearing issues for items to be imported
Inadequate transportation media
Wrong Journey management plan
Accident Fraud Project delay
resulting in financial loss
Injury Fatality Chemical Exposure
(occurs if there is a loss of containment while transporting them to well area for use)
Good Project Management
Good selection process for supply contractor
Consider smoothening access roads to facility
Consider selecting contract minimal transportation requirements
Prepare Journey management plan and subject it to several layers of verification
Prioritize local procurement of materials
8 Well heads Subject Infill wells Release of Flammable /toxic Inventory during normal operations
Erosion Corrosion Weld failure Pipeline/ flowline
rupture Well blow outs
Loss of containment Explosion Pool/ jet fire Leak Spill Revenue loss Company
environmental compliance concerns
Adequate line sizing to ensure that pipelines/ flow lines are not subject to overpressure
Provision of sand analyzer to detect presence of sand particles
Line sizing has factored in a corrosion allowance
Provision for corrosion inhibition systems have been factored into the design
Provision of methanol injection into wells during gas producing to
Piping team should ensure Adequate pipeline routing and flow sizing to prevent erosion
Ensure quality assurance of all facility items installed is carried out before use
Routine inspection and maintenance
Ensure specified corrosion inhibition and methanol injection dosage rates are strictly adhered to. Should well conditions or any other process condition change, appropriate dosage rates should be specified
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
phase to prevent hydrate formation along the pipeline. This could help prevent pipeline clogging and hence overpressures upstream the flow line/ pipeline
Hazardous area classification has been doen to highlight hazardous zones within the subject scope
Ensuring a corrosion monitoring system on subject well head facility is in place
Ensure instrumentation meets the minimum required SIL ratings and any other relevant standard
Minimize ignition sources by putting PTW systems in place (if not in existence) to carry out ignition sensitive tasks
Ensure that only electrical equipment certified for use within hazardous zones have been approved for use
Ensure a spill contingency plan is in place
Ensure emergency response plans are in place
9 Well heads Subject Infill wells Blow out during normal operations
Failure of subsurface valves and surface valves
Well bore ruptures Gas Migration
from reservoir
Injury Fatalities Explosion/ Fire
s
10 Well heads Subject Infill wells Line rupture due to overpressures
Process blockage (clogging due to hydrate formation)
Sizing case (blocked outlet , fire case e.t.c)
Loss of containment Jet fire Flash fire Pool fire Spill Loss of revenue Company image
concerns
Most lines have been designed for the maximum pressure
Flow lines downstream of well heads have been installed with HIPPS system
There is provision for real time flow and pressure monitoring on well heads and flow
Routine inspection and maintenance
Ensure reliability of instrumentation
Itemize all safety critical elements and list out performance standards
Carry out measures to ensure that these performance standards are met
Put adequate emergency response plans in place
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
lines There is provision
for methanol injection to prevent hydrate formation
Sizing cases have been considered and blow down and depressurization philosophy have been designed to meet requirements
Fire and gas detection systems hare in place to contain the hazard
Active fire protection systems are also in place to combat fires
Operating procedures
Line rupture due to over/ under temperature during normal operations
Hydrate formation Thermal
expansion due to radiation from adjacent falre
Metal embrittlement due to low temperature
Loss of containment Jet fire Flash fire Pool fire Spill Loss of revenue Company image
concerns
Most lines have been designed for the maximum pressure
Flow lines downstream of well heads have been installed with HIPPS system
There is provision for real time flow and pressure monitoring on well heads and flow lines
There is provision for methanol injection to prevent hydrate formation
Provision has been made for temperature monitoring on well head installation
Facility has been
Routine inspection and maintenance
Ensure reliability of instrumentation
Itemize all safety critical elements and list out performance standards
Carry out measures to ensure that these performance standards are met
Put adequate emergency response plans in place
Operating procedures
No Node Unit Location Hazard Category Guide Word Causes Potential Consequences Safe Guards Recommendations Priority
located to ensure that flaring doesn’t impact on it. However there is a plan to phase out the existing flare in the adjacent flow station faciities
Fire and gas detection systems hare in place to contain the hazard
Active fire protection systems are also in place to combat fires
11 Well heads Subject facilities Onsite traffic hazards during normal operations
Vehicular damage to existing flow lines and manifold
Increase risk of accidents within the facility due to the increased movement frequencies
Driver fatigue Non adherence to
speed limits
Loss of containment Fire Explosion Damage to existing
well heads Financial loss Injury Fatality
Access roads to the drilling site have been marked
There is a fence barrier within the well enclosure
Fire and Gas detection system is installed on existing well heads
Shutdown procedures in place to control hazards
Ensure speed limits are enforced
Consider a vehicle tracking system to help enforce speed limits
Consider discouraging private transportation for drilling site workers. Provide public transportation systems for every drilling worker to minimize the frequency of Vehicular activity
Ignition suppression measures should also be in place.
Adequate escape and evacuation plans should be in place
Loss of vital utility systems (power, air, fuel gas/oil)
Power failure Instrument Tubing
failure Loss of supply of
fuel gas oil Loss of
containment of fuel gas oil
Loss of plant air
Disruption in normal operations
Instrument failure Project delays Loss of revenue
All instrumentation systems are designed to be fail safe
Ensure redundancy of critical instrument functions