112
भारतीय वैानिक सवेण, Geological Survey of India वोतर े North Eastern Region संित प तक B B r r i i e e f f i i n n g g B B o o o o k k (अट बर /January’14 - दिसबर /March’14)

Geological Survey of India - GSI

Embed Size (px)

Citation preview

भारतीय भूवैज्ञानिक सवेक्षण,

Geological Survey of India पूवोत्तर के्षत्र

North Eastern Region

सकं्षिप्त पुस्तक BBrriieeffiinngg BBooookk

(अक्टूबर /January’14 - दिसम्बर /March’14)

Cover Page Photo: SSaatteelllliittee iimmaaggeerryy ooff NNoorrtthh EEaasstteerrnn RReeggiioonn ((ssoouurrccee--iinntteerrnneett))

CCoorrrreessppoonnddeennccee aaddddrreessss::

‘‘SSHHYYLLLLAA’’ BBUUIILLDDIINNGG,, NNOONNGGRRIIMM HHIILLLLSS

SSHHIILLLLOONNGG –– 779933000033

PPhhoonnee:: 00336644--22552200222288,, FFaaxx:: 00336644--22552200003333

EEmmaaiill:: hhoodd..nneerr@@ggssii..ggoovv..iinn

i

EXECUTIVE SUMMARY- BRIEFING BOOK, GSI, NER March, 2014

(January’14 to March’14)

MISSION-I & IB

STM (12 items): 3277.5 sq.km completed out of 3295 sq.km. Shortfall of 20 sq km

pertaining to item no: STM/NER/SAP/2013/004 will be covered in the

month of April, 2014 as per approval 1863/S1/1/1/fsp/NER(vol.1)/ 2014-

15/46F dated 04.04.2014.

SGM (4 items): 2640 sq.km completed out of 2640 sq.km.

GCM (7 items): 4948 sq.km completed out of 4850 sq.km

GPM (1 item): 1400 sq.km completed out of 1750 sq.km. Shortfall of 350 sq km

pertaining to item no: GPM/NER/RHQ/2013/014 will be covered in the

month of April, 2014 as per approval 1586/S/1/1/FSP/NER(vol.1)/ 2013-

14/46F dated 25.03.2014.

RSAS (1 item): 900 sq.km completed out of 900 sq.km (modified as per

5522/6/1/1/FSP/NER(vol.1)/ 2013-14/46F dated 09/10/2013.

MISSION-II

LSM (9 items): 395.4 sq.km completed out of 369.50 sq.km

Drilling(4 items): 872.95m and 750.6 m (extended item): total = 1623.55 m drilling

completed.

DM (5 items): 8.5 (100 %) sq.km completed out of 8.5 sq.km

MISSION-III

DRM:

Manipur-Nagaland: DRM’s of 4 districts of Manipur (Tamenglong, Ukhrul, Imphal East &

Senapati districts) completed.

Tripura- Mizoram DRM’s of 2 districts of Mizoram (Aizawl and Champhai districts on 1:

2,50,000 scale) completed.

Assam DRM’s of Kamrup, Darrang and Goalpara district is completed.

Modification and preparation of hard copy layout for Karimganj,

Hailakandi, Sibsagar, Golaghat, Cachar, Dibrugarh, Dhemaji & Tinsukia

DRM completed Compilation of Bongaigaon, Nagaon, Lakhimpur, North

Cachar Hills districts and Jorhat DRM is also completed. Digitisation of

Geology and mineral Layer of Karbi-Anglong district completed.

Meghalaya Compilation of West Garo Hills, East Garo Hills, South Garo Hills, East

Khasi, West Khasi and Ri-Bhoi districts of Mehgalaya is completed.

DRMs of East Khasi, West Khasi, Ribhoi and East Garo Hills districts of

Meghalaya have already been published. DRM of Jaintia district of

Meghalaya is completed.

Publication:

Adding of Accession Numbers of

Unpublished Progress Reports of GSI,

NER for the F.S. 2012-13 uploaded in GSI

portal.

During 2012-13, Assigned Accession number to 37

reports completed. Received Hard copies of Reports

for Regional Library.

Publication of Rec. GSI, Vol. 147, Pt.- 4

(Extended Abstract for F.S. 2012-2013).

Ext. Abstract Completed, Printed and Released on

31-3-2014.

Preparation of AGR for F.S. 2012-2013

(Rec. GSI, Vol. 147, Pt. 1)

Completed. Submitted already AGR on 23.7.2013 to

Director, PID CHQ, Kolkata.

GSI, News (NER), Vol. 23 (January 2012

to December 2012).

Completed. Submitted on portal On 12-2-2014

ii

Library Services:

Scrutiny and processing of scientific papers/ abstracts

submitted by the officers of the region

17 paper and 15 abstracts (upto

March, 2014) .

Information service: (a) Sale of publication

(b) Distribution of GSI

Publications

Total : Rs. 8382,

Total : 847 (upto March, 2014)

Library services-Modernization of Library, Updating of

bibliographic database on books, journals, GSI

publications etc.

a) Procurement of new books and journals.

Unpublished G.S.I progress report .

Library Facilities were extended to all

officers and Staff.

Geology Books: 14

Journals : 138.

Unpub. G.S.I progress report : (37)

Geoinformatics:

1.Scrutiny and finalization of Geological Map layer on

1:50K and uploading to the portal as Version 1: 4 sheets

(78J/2,6; 78G/13 & 14)

Scrutiny and Finalisation of

3 toposheet (78J/2, 78G/13 & 14)

completed

2.Creation of metadata of digitized Toposheet wise

geological maps for portal uploading : 4 sheets

3 sheets

3.Preparation and implementation of uniform legends at

regional level

Preparation of uniform legend up to

litho-unit level is Completed

4.Modification to the attribute and Graphic data of the

uploaded Digital geological maps as per the validation &

standardization at regional level and uploading them as

version - II

346 sheets completed

5. Extraction of data from unpublished geological reports

on to prescribed forms and validation:-

a. Map 50K (including QG)

b. Mining

c. Geophysics

d. Preparation of lexicons

61 reports

33 reports

25 reports

3 reports

Lexicon Updated

MISSION-IV

Palaeontological Studies: A search of fossils and preparation of geological map on 1: 50,000

scale was carried out along Shillong-Sohra, Shillong-Mawsynram and Shillong-Dawki in East

Khasi Hills district of Meghalaya. A dozen of oval to rounded egg fossil like samples were

collected in and around Dawki area, East Khasi Hills District, Meghalaya.

Geotechnical Investigations: Geotechnical Evaluation of Water Resource Development Projects

in Arunachal Pradesh was done which include Construction stage geotechnical investigation of

the Kameng H E Project: Package-I (Bichom Dam Complex), Package-II (Tenga Dam Group),

Package-III (Kimi Power House Complex),West Kameng District, Geotechnical Investigation of

Noa Dehing Multipurpose Project, Changlang District, and Geotechnical Investigation for Pare

H.E. Project, Papumpare District, Arunachal Pradesh were also attended. Geotechnical

Evaluation- Pre-Construction Stage of Water Resource development projects in Mawblei Hydro

Electric Project, West Khasi Hills District, Upper Khri Hydro Electric Project, West Khasi Hills

District, New Umtru Hydro Electric Project, Ribhoi District, Meghalaya were also completed.

Other geotechnical investigations carried out in Turial Hydroelectric Project, Kolasib District,

Mizoram pertaining to Water Resource Development Projects, Mizoram.

Medical Geology: Systematic spot analysis of groundwater and surface water by Merck Arsenic

Field kit were carried out in the field in Toposheet 83 B/12 & B/16 to study of arsenic

contamination in water and soil in parts of nagaon and marigaon districts, Assam. The arsenic

values in groundwater varies from nil to 100 ppb where as that of surface water varies from nil to

5 ppb. The high arsenic values occurring as zones were transferred over the geological map shows

iii

that most of the high values occur within the Newer alluvium sediments of Barpeta and Hauli

Formations. Older alluvium sediments are devoid of arsenic contamination thus having fresh

water.

Landslide Hazard Zonation:

Landslide Hazard Zonation Project (LHZP) was formed during 1995 to exclusively cater to the

needs of landslide studies in NER by GSI. Subsequently GSI was declared nodal agency for

landslides by Govt. of India in 2004. GSI has undertaken studies related to landslide at specific

request from State Governments and other organizations. The information has been often used by

Government and other organizations for better planning of their infrastructures, developmental

activities and disaster preparedness.

The problem of landslide hazard is multiplied in recent times due to increased developmental

activities like construction of road, building and various infrastructures. GSI has covered major

part of urban agglomerations, road corridors of the vulnerable hilly terrain in NE India through

macro scale landslide susceptibility mapping. GSI undertakes site specific landslide investigation

for containing the distressing in the hill slopes, comprehensive understanding of the processes, and

formulation of both short and long term mitigation measures. GSI also attempted monitoring of

few conspicuous slides in Sikkim and Meghalaya. GSI, NER regularly updates the landslide

database of the entire NE regions through landslide inventory work. After became a declared

nodal agency for understanding the coordinating landslide investigation and formulation for

mitigation measures. GSI’s activity for Landslide Hazard Risk Mitigation in region includes Pre-

Disaster Study, Landslide Zonation Mapping, Landslide Inventory Work, Detailed Site Specific

Study of landslide for identifying causative factor and most suitable remedial measures, Landslide

monitoring/real time monitoring by instrumentation for development of an early warning system.

During FS 2013-14, Landslide Hazard Zonation studies at macro scale in Anjaw District,

Arunachal

Pradesh and along Rangpo-Singtam-Dikchu-Chungthang road corridor, Sikkim were taken up

besides detailed study of the 13th mile landslide in East District, Sikkim and Site specific study of

proposed Pakyong Airport area, Sikkim.

Updation of existing landslide inventory of NER for FS 2013-14 is as follows:

Assam: 1 Earth-Soil slide & 1 Rock fall.

Arunachal: 7 cut-slope failures, 28 Rock slides, 4 Complex slides, 15 Debris slides.

Meghalaya: 1 rock fissure-ground crack.

Mizoram: 1 Complex slide & 1 Debris slide.

Nagaland: 1 Slope failure, 1 Rock fall, 1 Complex slide, 1 Earth slide, 7 Debris slides & 1

rock slide.

Sikkim: 1 mudslide & 1 debris flow.

Earthquake Studies: Study of Seismic and Landslide Hazard Assessment of Aizawl town,

Mizoram & Kohima City, Nagaland were carried out during FS 2013-14.

Aizawl town, Mizoram: An area of about 50 sq. km was covered by geological mapping and

landslide hazard assessment on 1:25,000 scale in the Aizawl master plan area. Synthesis of

seismicity data within 300 km radius in and around Aizwal area, involving conversion of Ms and

Mb earthquake magnitudes to Mw for assessing the recurrence period and to determine PGA of

the area was undertaken. It appears that the slope instability can be attributed to the inherent rock

mass condition, anthropogenic interference (unscientific slope cutting / static loading due to

constructional activities), unguided drainage, etc. Besides, ground water information based on the

available hand pump locations were recorded and are being analysed with other collateral

subsurface information collected from different Government agencies. The collected field data are

being processed for the preparation of relevant thematic maps for analysis and interpretation

regarding the Seismic Hazard Assessment of the area.

Kohima City, Nagaland: An area of 300 km radius around Kohima city was taken up to carried

out to analyse past seismicity data and delineation of potential seismic source area. The

Morphotectonic and lineament map covering 50 sq. km area was prepared using LISS-III and

iv

SRTM data of Kohima area. Surface Geological Mapping on 1:25,000 scale covering 50 sq. km

was undertaken. Facet wise data collection of about 50 sq. km in the southern part of the study

area was undertaken for landslide hazard zonation. Besides, study of groundwater information

along with borehole litho log collected from the Directorate of Geology and mining, Govt. of

Nagaland was also carried out. Presently the work is under progress and will be continued during

FS 2014-15, the second year of the study.

Gangtok, Sikkim: Seismic Hazard Assessment of Gangtok , Sikkim was carried out by Site

response study by three component digital seismograph (Kinemetrics make SS-1) using H/V

method developed by Nakamura (1989) to eliminate the source effects in the spectra of the micro

tremor signal.

MISSION-V

Training Institute: During the period of January, 2014 to March, 2014 the Regional Training

Institute, GSI, NER successfully conducted a 6 days (28.1.14 to 2.2.14) Field workshop –cum

training on active fault mapping, conducted a 30 days training to 37th OCG, Batch-G as part of

Orientation Course for Geologist of GSI. Organized 7 days (24.3.14 to 30-3-14) Training on

Landslide Hazard Zonation and Disaster Management for Geologist of DGM and GSI Officers,

NER, at GSI, Gangtok, Sikkim.

SUPPORT SYSTEM–I: STSS

Petrology Lab: Total No. of thin sections received = 342 nos, Total No. of thin sections prepared

= 101 nos, Total No. of polished sections received = 4 nos, Total No. of heavy minerals separation

= Nil. Participated in State level science & environmental fair, 2014 held on 13th & 14th of

March, 2014 by S.C.S.T.E, Meghalaya. As part of the research item carried out by Petrology

Division, 10 LKm of Geological Mapping on (1:12,500) in Mawpyut mafic-ultramafic complex

which is located approximately 10kms SW of Jowai towards Dawky along a N-S trending valley.

Field work was carried out in and around Mawpyut, Jowai, Pyngthorlantein, Mawgajai,

Sohmanang, Pohshadkhap, Pomiku and Mosakhia areas. 145 nos of samples of sandstone, granite,

porphyritic granite, pabbro, pyroxenite were collected for thin section, EPMA, SEM/ EDS study

and for Major/Trace/REE and PGE & Au analysis.

Chemical Lab: Sl

No

Item Particular

1. Total Nos.

of

Samples

Collected/

analysed

during FS

2013-14

Package Pkg.

‘A’

Pkg.

‘B’

Pkg.

‘C’

Pkg.

‘D’

Pkg.

‘E’

Pkg.

‘F’

Pkg.

‘G’

Pkg.

‘H’

Pkg.

‘I’

Pkg.

‘J’

Total

Submitted

To Lab.

Analyses

Reported

597 0 278 710 318 0 538 197 0 234 1064

Pendenc

y

467 1064 786 354 746 1064 526 867 1064 830

* All NGCM package ‘A’ and Non-NGCM samples for major, minor oxides & trace by XRF will be

cleared by 31st July, 2014 including package ‘D’ (As, Bi, Se, Sb) & package ‘G’ (Hg)

NB: Upto 31.03.2014

Non-NGCM samples send to CHQ, Kolkata for Major & Minor Oxides (XRF) analyses = 1109 nos.

Analytical reports received– 817 nos.

Pending Non-NGCM samples- 292 nos.

Trace Elements & REE (ICP-MS) samples send to CHQ, Kolkata for analyses – 501 nos.

Analytical reports received -195 nos.

Pending REE samples- 306 nos.

PGE samples sent to CHQ, Kolkata for analyses - 17 nos.

Analytical reports received - 2 nos

Pending PGE samples- 15 nos.

v

SUPPORT SYSTEM–II: ASS

Administration:

a) Pay-roll data regularly updated.

b) HRMIS data is being updated regularly.

c) Tour applications of all gazetted officers are processed through portal.

d) Leave Module in portal implemented.

e) Claims Module in portal implemented.

f) Purchases under ME & IT Heads are being monitored. PAC and TAC are being held regularly.

SUPPORT SYSTEM–III: PSS

RAC: 7th RAC on 21.01.2014.

भारतीय भूवैज्ञानिक सवेक्षण, Geological Survey of India

पूवोत्तर के्षत्र North Eastern Region

संक्षिप्त पुस्तक BRIEFING BOOK

(Updated up to March, 2014) C O N T E N T

Page

No.

1. Introduction

(i) State-wise Geology and Mineral Resources

(ii) Status Map (s)

1

2. Organisational Structure of the Region (updated) 12

3. Activity Domain of the Region 13

4. Mission Wise Information For Field Season 2013-14 (updated) 14

5. Financial Performance (updated) 39

6. Mission Wise RCA Expenditure (updated) 39

7. Scientific workshops / Meetings / Seminars / Symposium, Exhibitions etc., organised /

participated (updated)

39

8. HRD, Establishment, Payroll, HRMIS, e-service book, etc. (updated) 39

9. Vehicles & Transport Infrastructure including outsourcing and age of vehicles, Vehicles MIS

(updated)

39

10. Modernization 39

11. Drilling Infrastructure (updated) 39

12. Outsourcing of routine services [housekeeping, security, garden, etc.] 39

13. Other Activities (updated) 39

14. Special Scientific Study. 40

15. Perception Management Activies in NER (updated) 40

16. Savottam (updated) 40

17. Consolidated List of Group A & B (Gaz.) Officers in NER (as on 31.12.2013) (updated) 40

ANNEXURES (updated):

Annexure-1A Major Minerals Resources [Under Various Unfc Categories] Estimated By The

Region, Showing State-Wise Five-Yearly Increment, For The Last 15 Years.

41

Annexure-1B National Mineral Inventory –

No. Of Reports Converted As Per Unfc Compliance

41

Annexure-2A Activity Domain Pertaining To Mission I & Ii Of The Region And Achievements

[Fsp Related Items] During The Xi Plan Period [2007-12] & Xii Plan Period

42

Annexure-2B Fsp Rolling Plan For F.S. 2012-13 & 2013-14 43

Annexure-3A Quarter-wise, Head-wise Allotment of Plan Fund Versus Expenditure Booked

During the Financial Year 2013-14 (2nd Year Of The Xiith 5-Year Plan) IN

RESPECT OF NORTH-EASTERN REGION OF GSI

53

Annexure-3B Head-Wise & Quarter-Wise Allotment of Plan Fund Versus Expenditure for the

Financial Year 2013-14 (2nd Year Of The Xiith 5-Year Plan) in Respect of North-

Eastern Region of GSI

54

Annexure–4 Mission Wise Pro-Rata Rca Expenditure In Different Projects Visa-Vis Targets

And Achievements

55

Annexure-5 Progress & Pendency Report Of Chemical Analyses Of Ngcm Samples 77

Annexure-6 Year-Wise, State-Wise, Report Pendency Progress 79

Annexure-7 Status Of Uploading In Gsi Portal 80

Annexure-8 Case Studies Uploaded In Gsi Portal (All Cases As Well As Cases Uploaded

During The Quarter)

83

Annexure-9 List Of Publications Brought Out In The Last Five Years 84

Annexure-10 Courses Conducted At Ftc’s Along With List Of Faculty Members 86

Annexure-11 List Of Rac / Oac / Stage Review / Sgpb Meetings With Date And Status Of

Uploading Of Minutes

88

Annexure-12 Employment Position In The Region 89

Annexure-13 Vehicle Position In North Eastern Region 91

Annexure-14 Procurement Status Of Major Equipments/ Modernization Items/ Machinery

Proposed For Procurement During F.Y. 2013-14

92

Annexure-15A Status Of Existing Drilling Equipments Under Deployment 94

Annexure-15B Status Of Existing Drilling And Other High-End (Rs >1 Core) Equipments To Be

Procured During Fy 2013-14

95

Annexure-16 Status Of Pending Legal Cases Of North Eastern Region 96

Annexure-17 Consolidated List Of Group A & B Officers In Ner (Gaz.) 97

1

REGIONAL BRIEFING BOOK OF GEOLOGICAL SURVEY OF INDIA

NORTH EASTERN REGION

1. INTRODUCTION

The North Eastern Region with an area of 262,093 sq km (7.92% of Indian Territory) represents varied

geomorphological & geological set up, which is ranging from Precambrian to recent age. It is manifested by

spectacular Himalayan mountain belt in the north, the vast Brahmaputra plain in the central portion, Shillong

Massif plateau in the south and Indo-Myanmar range in the East.

GEOLOGY & MINERAL RESOURCES

A summarised description of geology & mineral recourses of different states of NER is given below:

Arunchal Pradesh: Arunachal Pradesh, borders Bhutan, China and Myanmar, with the Naga Hills to the

south-east. The northern and north-western parts of Arunachal Pradesh comprise mainly ancient metamorphic

rocks, which are called Sela Group towards west and Lohit Granodiorite toward east. The Siang Valley

exposes an extensive sequence of metamorphosed Mesozoic rocks with intercalated volcanic flows. A narrow

strip of Gondwana sandstones and shales with discontinuous coal occurrences, usually crop out along the

southern flank of the metamorphics. The southern foot hills of the Himalayan belt are composed of the

younger Siwalik / Assam Tertiary sedimentaries - silty sandstone, clay and sandstone deposited during the last

stage of mountain-building. Massive and vesicular basaltic and andesitc rocks of Abor volcanics associated

with Miri Quartzite occur in the western flank of Subansisri valley, Igo valley, Basar-Along areas and in Siang

valley areas in Arunachal Pradesh. The easternmost part of the state, namely the Changland and Tirap,

represent a segment of the Naga-Patkoi range comprising the northern tip of Indo-Myanmar (Arakan)

mountain range made up of folded Tertiary sediments, mostly sandstone and shale.

The state is rich in mineral deposit of graphite, limestone, coal along with significant deposits of

quartzite, basemetals and minor PGE mineralization. Reserve of 342mt limestone, 246.75mt dolomite,

86.15mt graphite, 90.23mt coal and 5.15mt quartzite are the main mineral deposit of the state. Beside these,

state has hydro-electric potential of 33,850 MW in different basins.

The coal is located mainly in Namchik-Namphuk area and Miao Bum area in the eastern part of Tirap District.

A linear belt of 350 km from Haflong in Assam in SW to Namchik-Namphuk area of Arunachal Pradesh in

NE holds promise of presence of more Tertiary coal.

DEPTH-WISE RESOURCE OF COAL IN ARUNACHAL PRADESH

(Resource in million tonne)

STATE COAL

TYPE

DEPTH

RANG

E (m)

PROVE

D

INDICATE

D

INFERRED

TOTAL (Exploration) (Mapping)

UNCF Code G1 G2 G3 G4

TERTIARY

ARUNACHAL

PRADESH

HIGH

SULPHU

R

0-300 31.23 40.11 12.89 6 90.23

GRAND TOTAL 31.23 40.11 12.89 6 90.23

Ref: Coal News, Natural Energy Resources, GSI, vol.32

Assam: The major part of the state is covered by recent alluvium of east - west trending Brahmaputra plain.

The Karbi Anglong Hills & North Cachar Hills located at the central portion comprising of gneisses and

schists with granite intrusions and folded Tertiary sedimentaries of the Naga-Arakan sequence respectively

and the Cachar plain in the south comprises of recent alluvium. Crude oil is the most important natural

resource of Assam. The state has a reserve of 513.31mt of coal, 394mt of limestone, 30mt of iron ore, 13.4mt

of silica sand, 2.0mt of fireclay, 13mt of clay along with high potential of granite, sandstone and mica.

Crude oil is found in upper part of Tertiary Barail sequence, where largest amount of oil is discovered

in this region so far, while Tipam sandstone is another important oil productive horizon. In the shelf zone, oil

was discovered just above the basement at Borholla and gas in Eocene sand near Tengakhat

2

The coal occurrences in Assam are reported from two geological horizons viz., Gondwana and

Tertiary of which Tertiary coal deposits of Makum, Mikir Hills and Dilli-Jeypore are the most important

coalfields. The Tertiary coal deposits of Makum, Dilli –Jeypore and Mikir Hills area are the major coal

resource of the state. The coal deposits in Mikir Hills occur within Sylhet Formation of Jaintia Group and are

located in the southern part of Mikir Hills and to the north of the railway line between Lumding and Dimapur.

DEPTH-WISE RESOURCE OF COAL IN ASSAM

(Resource in million tonne)

STATE COAL TYPE DEPTH

RANGE (m) PROVED

INDICATE

D

INFERRED TOTAL

(Exploration) (Mapping)

UNCF Code G1 G2 G3 G4

GONDWANA

ASSAM NON-

COKING 0-300 0 2.79 0 2.79

TERTIARY

ASSAM HIGH

SULPHUR

0-300

300-600

278.93

185.85

26.55

16.15 0.5 2.52

308.52

202.00

TOTAL 348.65 35.85 0.5 2.52 510.52

GRAND

TOTAL 513.31

Ref: Coal News, Natural Energy Resources, GSI, vol.32

Manipur: Apart from the 1850 sq km of Imphal valley in the middle, the rest of Manipur comprises north-

northeast trending steep ridges of the Naga - Arakan Tertiary sedimentary sequence comprising sandstone,

shale, siltstone and limestone is emplaced by ultramafic suite of rocks along the Myanmar border. The

Manipur ophiolite belt composed of intimately juxtaposed slices of mafic- ultramafic rocks is a product of

“obduction” resulted due to the collision of Indian and Burmese plates during Tertiary period. The principal

mineral of some economic significance in Manipur is limestone (10.6mt). The proved reserve of lignite is of

the order of 12,262 tonnes, and that of clay is 2.52mt. Beside these Manipur is rich in chromite and dimension

stones.

Meghalaya: Geologically, Meghalaya is mainly comprised of Precambrian Gneissic Complex and Shillong

Group of sedimentary rocks, comprising of conglomerate-quartzite-phyllite sequence unconformably overlies

the Precambrian Gneissic Complex. The Khasi Basic-Ultrabasic Intrusives of Meghalaya comprising basic

intrusives like epidiorite, metagabbro, metadolerite, etc occur mostly as sills, dykes and rarely as phacoliths in

the various subfacies of the Shillong Group. A number of Neo-Proterozoic granite bodies, often of batholithic

size transect both Gneissic Complex and Shillong Group in Meghalaya. Notable among them are the Sindhuli,

Rongjeng, Kyllang, Mylliem, South Khasi, Kyrdem and Nongpog granite plutons, exposed along the eastern

and southern rims of the plateau, is a near complete sequence of Tertiary sediments overlying the volcanic

suite of Sylhet Traps. The state of Meghalaya is endowed with huge resources of limestone (9804mt.)

particularly in the Tertiary rocks occurring in Jaintia, Khasi and Garo Hills. Meghalaya has coal reserve of

576.48mt. Other important mineral resource of Meghalaya are Polymetallic basemetal mineralization of 1.18

lakh tonnes, 406,400 tonnes of glass sand, 6.5 million tonnes of crude clay, 4.56mt of apatite and considerable

amount of granite (for dimension stone). Tertiary coalfields of Garo Hills are located along the southern

extremity of Shillong plateau as scattered patches. Coal occurs in the Tura Sandstone (Eocene) of Jaintia

Group. The Gondwana coalfields of Meghalaya restricted only in the Garo Hills are exposed in the Singrimari

basin on the north-western corner of Garo Hills bordering Dhubri district of Assam. The coalfields of Khasi

Hills are located in the southern periphery along the international boundary with Bangladesh.

DEPTH-WISE RESOURCE OF COAL IN MEGHALAYA

(Resource in million tonne)

STATE COAL TYPE

DEPT

H RANGE

(m)

PROVED INDICATED

INFERRED

TOTAL (Exploration) (Mapping)

UNCF Code G1 G2 G3 G4

TERTIARY

MEGHALAYA HIGH

SULPHUR 0-300 89.04 16.51 27.58 443.35 576.48

3

GRAND

TOTAL 89.04 16.51 27.58 443.35 576.48

GONDWANA

SINGIMARI,

MEGHALAYA

& ASSAM

NON-

COKING 0-300 0.00 2.79 - -

2.79

GRAND

TOTAL 0.00 2.79 - -

2.79

Ref: Coal News, Natural Energy Resources, GSI, vol.32

Inferred reserve is 406,400 tonnes of white sandstone useful in glass industry occur in Cherrapunjee

and Laitryngew areas. Inferred reserve of 6.5 million tonnes crude clay is reported 2.4 km west of Sohrarim on

Cherrapunjee Road. White clay is also reported from Nongalbibre in South Garo Hills and Rongrengre in East

Garo Hills districts. Good quality Kaolin occurs around Smit and Laitlyngkot in East Khasi Hills,

Thandlaskein, Shangpung, Mulieh and Mynsngat in Jaintia Hills and Darugiri in East Garo Hills districts.

China clay, suitable for pottery manufacture, has been reported from several places in Sutnga area in Sylhet

Sandstone.

Mizoram: A repetitive succession of young Tertiary sediments, mostly shale, siltstone and sandstone, tightly

folded into a ridge and valley sequence comprise the whole state. Along the somewhat broad valleys in the

northern part, bordering Assam, recent alluvium covers the sediments. There is some potential for oil and gas,

lignite, decorative shell limestone, sandstone slabs (as dimension stone) and clay body within the

sedimentaries.There is some potential for oil and gas accumulation in the folded sedimentaries. There is scope

for hydel power generation in the state on a large scale along the Kolodyne and Tuivai rivers and as

microhydel schemes along many smaller streams. Indication of oil, saline springs and a few gas seepages in

the central part of Mizoram are reported. Salt spring has been located north of Sabual village in western part of

Mizoram. Occurrence of 3 metres long and 10 cms thick, grey, pyrite-bearing, lignite patch in ferruginous,

brownish, yellow, soft, Bokabil sandstone has been reported south of Chubel village. About 6.5 kms southeast

of Ngopa, a few lenticular pockets of coal have been recorded. Streaks, stringers and patches of coal are found

in the Upper Bhuban Sandstone. The Mizoram state Department of Industries (Geology and Mining Wing) has

proved 5200 cubic metres of decorative shell limestone at Ngrum Lui near Turial Bridge and 6000 cubic

metres at Sesawang. A thin horizon of clay is noticed northwest of Borai, near Momchera and in the valley

near Plura village. The clay has a vast potential for making bricks.

Nagaland : Geologically, Nagaland comprises Tertiary sedimentary rocks of Disang, Barail, Surma and

Tipam Groups that form the northern extension of Arakan-Yoma ranges, while the younger alluvial sediments

occupy valley areas. NNE-SSW trending ophiolite suite of rocks represented by mafic- ultramafic sequence is

juxtaposed with Naga metamorphic belt along the eastern margin all along the contact with Myanmar. In

Nagaland, occurrences of major minerals are limestone (375mt.), coal (315.41mt.) and nickel-cobalt bearing

magnetite. Sulphide (Cu-Fe) occurrences are noted in chert-volcanics and mafic-ultramafic association of

ophiolite belt at some places of Phek and Tuensang Districts. Oil and natural gas occur in western foothill

areas and Schuppen Belt, being trapped in fractured and weathered basement rocks, and in the overlying

Tertiary cover sediments of Kopili / Barail / Surma / Tipam rocks.Coal deposits, which occur in Tikak Parbat /

Jenam Formations of Barail Group, are located in Borjan-Tiru areas of Mon district, Changki-Chongliyimsen

and Lakhuni areas of Mokokchung district, Leo Longidang area of Wokha district and Konya area of

Tuensang district.

DEPTH-WISE RESOURCE OF COAL IN NAGALAND

(Resource in million tonne)

STATE COAL TYPE

DEPTH

RANGE

(m)

PROVE

D

INDICAT

ED

INFERRED

TOTAL (Exploration) (Mapping)

UNCF Code G1 G2 G3 G4

TERTIARY

NAGALAN

D

HIGH

SULPHUR 0-300 8.76 0 8.6 298.05 315.41

4

Ref: Coal News, Natural Energy Resources, GSI, vol.32

Sikkim: The state is mostly comprises low to medium grade Precambrian metamorphites of Daling Group,

high grade Darjeeling gneiss and Kanchendzonga gneiss, quartzite, calc-silicate rock, marble and graphite

schist of Chungthang Formation. Daling Group of rocks are classified into Gorubathan, Reyang and Buxa

Formations. Dolomitic limestone and stromatolitic limestone occurs in Buxa Formation. "Lingtse Gneiss"

occurs as a NE-SW to N-S trending strip and forms a general line of separation between the Daling and the

high grade Kanchendzonga gneiss. The folded Tethyan sedimentaries, exposed in the northern part of Sikkim

are fossiliferous at places and represented by Everest Formation (shale/phyllite), Mount Everest Limestone

Formation, Lachi Formation (conglomerate with thick diamictite base) and Tso Lhamo Formation (calcareous

shale, limestone band, calcareous sandstone).

The Gondwana Supergroup consists of sandstone, shale, and carbonaceous shale with occasional thin

bands of coal and pebbly shale horizon are best exposed at Namchi, South District of Sikkim. Strata bound

basemetal occurrences are located at Rangpo (Bhotang), Pachekhani- Rorathang, and Dikchu. The copper-zinc

vein type mineralization of Dikchu area (thickness-1.25m, strike length-600m and depth of 100m) occurs in

the garnet-staurolite-quartz-mica schist of Daling Group at the contact with Central Crystalline Gneissic

Complex. Coal seams of Gondwana Supergroup are exposed at Namchi & Rishi area. Dolomite in Buxa

Formation of Daling Group is found along Naya Bazar – Legship road and surrounding hills. Pink limestone

of cement grade with interbands of shale is exposed near Naya Bazar, Namgaon and Mangalbaria area.

Graphite occurrences with an estimated reserve of 6000 tonnes are recorded at Chitre. Asbestos has been

recorded within amphibolites of Daling Group at the southern foot of Tashiding ridge, while talc occurs in

association with quartzites of Daling Group around Mausari village. Coal seams belonging to Gondwana

Supergroup are best exposed at Namchi, South district of Sikkim. Other coal occurrences are recorded at

Namchi-Tinjir road section in the areas on eastern slope of Rangit river along Rishi – Sagbari section. At

Namchi bituminous to semi-anthracitic coal has been estimated. The coal is useful for local consumption.

DEPTH-WISE RESOURCE OF COAL IN SIKKIM

(Resource in million tonne)

STATE COAL TYPE

DEPTH

RANGE

(m)

PROVE

D

INDICAT

ED

INFERRED

TOTAL (Exploration) (Mapping)

UNCF Code G1 G2 G3 G4

GONDWANA

SIKKIM NON-

COKING 0-300 0 58.25 42.98 101.23

GRAND

TOTAL 0 58.25 42.98 101.23

Ref: Coal News, Natural Energy Resources, GSI, vol.32

Dolomite bearing blocks have been delineated with a reserve of one million tonne estimated down to a

depth of 30 m. Grey limestone is recorded at Rishi Khola, south of Namgaon. Pink limestone is exposed near

Naya Bazar. Graphite occurrences with an estimated reserve of 6000 tonnes are recorded at Chitre in rocks of

Chungthang Formation of Central Crystalline Gneissic Complex in West Sikkim. Asbestos has been recorded

at the southern foot of Tashiding ridge, while talc occurs around Mausari village. A preliminary estimate of

quartzite and talc reserves up to 25m depth is around 15 million tonnes.

Tripura: Geologically, Tripura is comprised of Surma, Tipam and Dupitila Group of sedimentary rocks of

Miocene to Pleistocene age. Repetitive sequence of deformed and folded sequence of sandstone, shale and

clay occur along north-south trending ridges and valleys. The most important mineral resources are oil and

natural gas being explored by ONGC. Besides, there are glass sand (0.49mt), limestone and plastic clay

(13.32mt) deposits suitable for commercial exploration, apart from hard rock resources (sandstone and

limestone) useful as construction material. The major water resources projects of the state are Gumti Hydel

Project (construction stage), multipurpose Juri river Project (feasibility stage) and Longlai Valley Project

(feasibility stage) with power benefits of 22 MW.

Few occurrences of Lignite/coal (15 to 60 cms) are reported at Ujan-Tangang area in North Tripura

District. Minor occurrence of coal has been reported from west of Ambassa near purbaraipara chhara and

Hathimara Chhara in Dhalai district, which requires further detail study.

5

STATUS MAP (S)

GEOLOGICAL MAP OF NORTH EASTERN REGION:

6

STATUS OF SYSTEMATIC GEOLOGICAL MAPPING IN NER

ALONG WITH AREA PROPOSED FOR F.S. 2013-2014

State Wise Item distribution: Assam (2), Manipur (1), Nagaland (1).

Target for FS 2013 -14 is 2640 sq.km. Achievement till 31 March 2014 is 2640 sq.km (100%)

7

STATUS OF SPECIALISED THEMATIC MAPPING IN NER

ALONG WITH AREA PROPOSED FOR F.S. 2013-2014.

State Wise Item distribution: Arunachal Pradesh (3), Assam (1), Manipur (1), Mizoram (1),

Meghalaya (4), Sikkim (1) & Tripura (1).

Target for FS 2013-14 is 3295 sq.km. Achievement till 31st March, 2014 is 3277.5 sq.km

(99.46%).

** Shortfall of 20 sq km pertaining to item no: STM/NER/SAP/2013/004 of SU: Arunachal

Pradesh will be covered in the month of April, 2014 as per approval

1863/S1/1/1/fsp/NER(vol.1)/ 2014-15/46F dated 04.04.2014.

8

STATUS OF NATIONAL GEOCHEMICAL MAPPING IN NER

ALONG WITH AREA PROPOSED FOR F.S. 2013-2014.

State Wise Item distribution: Arunachal Pradesh (1), Meghalaya(3), Nagaland (2) & Tripura (1)

Target for FS 2013-14 is 4850 sq.km. Achievement till 31 March, 2014 is 4948 sq.km 102.02%)

All 7 items are completed.

9

STATUS OF GEOPHYSICAL MAPPING IN NER

ALONG WITH AREA PROPOSED FOR F.S. 2013-2014

State Wise Item distribution: Meghalaya (1)

Target for FS 2013-14 is 1750 sq.km. Achievement till 31 March, 2014 is 1400 sq.km. Shortfall

of 350 sq km pertaining to item no: GPM/NER/RHQ/2013/014 will be covered in the month of April,

2014 as per approval 1586/S/1/1/FSP/NER(vol.1)/ 2013-14/46F dated 25.03.2014.

10

STATUS MAP OF MINERAL INVESTIGATIONS CARRIED OUT

IN GSI, NER DURING F.S. 2013-14

Work carried out during F.S. 2013-14

Mission – IIA: Limestone (AP) – 2, PGE & Gold (AP) – 1, REE (Assam) – 1, PGE (Nagaland) – 1,

Ti-V-Magnetite (Meghalaya) – 1, Limestone (Meghalaya) –2, REE (Meghalaya) – 1,

Base metal s (Sikkim) – 1, Chromite (Manipur)- Chromite investigation is carried

using Geophysical magnetic survey. Mission – IIB: Coal - Tertiary (Meghalaya) – 1,

Coal – Gondwana (Assam / Meghalaya) – 1

11

STATUS OF 50K MAPS IN NER

12

2. ORGANISATIONAL STRUCTURE: (As on 31.03. 2014)

13

3. ACTIVITY DOMAIN OF THE REGION

Geological Survey of India, NER encompasses states of Arunachal Pradesh, Assam, Meghalaya,

Tripura, Mizoram, Nagaland, Manipur and Sikkim and has carried out surveys in NER.

The important activities of NER includes –

Mission–I : SURVEY & MAPPING

Mission - I, IA Systematic geological mapping, Specialised thematic studies,

Geochemical mapping, Geophysical mapping / surveys

Mission - IB Airborne Mineral Survey,Photogeology and Remote Sensing

Mission–II : MINERAL EXPLORATION

Mission – IIA Mineral Resource assessment

Mission – IIB Natural Energy Resource (Coal)

Mission–III : INFORMATION / DISSEMINATION

Mission - III Geodata and Geoinformatics,

Map compilation and map publication,

Publication and Information delivery

Mission–IV : SPECIAL INVESTIGATION, RESEARCH & DEVELOPMENT

Mission - IV Fundamental Science (Petrology, Palaeontology and Mineral Physics),

Multidisciplinary Geoscience (Engineering Geology, Landslide Hazard Zonation

and Earthquake Geology, Environmental Geology, Glaciology)

Mission–V : HUMAN RESOURCES DEVELOPMENT

Mission - V Regional Training Institute, Shillong

Field Training Centre, Aizawl

STSS : MODERNISATION, ASSETS PROCUREMENT & MANAGEMENT

Support System -

I

Analytical Chemistry and Chemical Laboratory network

Drilling & Workshop, Transport

Capital Asset Procurement & Management

Map & Cartography, Infrastructure & Connectivity

Laboratory Network (Geophysical Instrumentation)

Laboratory Network (Petrology Division)

Laboratory Network (Palaeontology Division)

Laboratory Network (Mineral Physics Division)

Support System -

II (ASS)

Finance, Personnel, Legal Cell, HRD, Information and Publication, Libraries, Park

and Museum, Estate

Policy Support

System - III

Science Policy & Coordination , Planning & Monitoring

CGPB Secretariat, Commercial Operation,

Geoscience Partnership

14

4. MISSION WISE INFORMATION FOR FIELD SEASON 2013-14

MISSION-WISE ITEMS

(FS 2013-14)

MISSION-I

Systematic Geological Mapping (SGM):

Systematic Geological Mapping was taken up in states of North Eastern Region in which 2,

06,953 sq.km (includes 1, 44,966 sq.km hard rock and 61,987 sq.km quaternary) has been completed upto

FS: 2012-13. During FS: 2013-14 Systematic Geological Mapping was taken up in the states of Assam,

Nagaland and Manipur in which out of the proposed target of 2640 sq.km, 100% of targets was achieved

upto March, 2014.

Specialised Thematic Mapping (STM):

Multidisciplinary Specialised Thematic Mapping was undertaken in the geologically critical

areas, mineral potential areas covering Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram,

Tripura and Sikkim. During FS: 2013-14, 3277.50 sq.km is completed upto March, 2014, out of the

proposed total target of 3295.00 sq.km. Shortfall of FS 2013-14 pertaining to the item of Specialised

Thematic Mapping in Tertiary Coal belt in Changlang and Tirap Districts, Arunachal Pradesh will be

covered in the month of April, 2014 as per approval 1863/S1/1/1/FSP/NER(vol.1)/ 2014-15/46F dated

04.04.2014.

National Geochemical Mapping (NGCM):

GSI has launched National Geochemical Mapping of the entire country from FS 2000-01

onwards with a view to generate baseline data, which will be useful in locating/developing natural

resources and in wide application in environmental studies, agriculture, public health and other social

concerns. Geochemical mapping is conceived as a multistage procedure involving analysis of

systematically collected Stream-Sediment-Samples for 66 Elements and creation of a database and

national as well as regional level geochemical maps – all aimed at delineating scale dependent

geochemical patterns. When fully documented these maps will portray the geochemical diversity of the

earth’s land surface and cater to a wide range of needs related to sustainable long term management of

15

environment and natural resources. The geochemical database can be utilised for targeting mineral

exploration, land use, agriculture, forestry, management of environment, animal and human health etc.

An area of 25196 sq.km (Assam: 7970 sq.km, Arunachal Pradesh: 3631 sq.km, Meghalaya: 8346

sq.km, Mizoram: 1136 sq.km, Nagaland: 1150 sq.km, Sikkim: 2963 sq.km and Tripura: 1746 sq.km) has

been covered till F.S. 2012-13. Out of the proposed target of 4850 sq.km for FS: 2013-14, 4948 sq.km is

completed upto March, 2014.

Geophysical Mapping:

North Eastern Region of the Geological Survey of India has capability of high precision, high

resolution geophysical equipments, which have put us to a new digital era of Geophysical Surveys on

land. Now, it is possible to utilize Gravity and Magnetic Surveys also in the areas of Environmental

Studies, Landslides, Geotechnical and Seismotectonics surveys.

Gravity-Magnetic mapping have been conducted over the last few years in parts of Meghalaya

and Assam to generate gravity and magnetic maps on 1:50,000 scale. Out of the 1750 sq.km proposed for

FS:2013-14, GPM of 1400 sq.km area is completed upto March, 2103. Gravity-magnetic Survey has been

carried out along different roads and tracks in 1: 50,000 scale pertaining to toposheet no. 78 O/6, 7 and

parts of 8 in west Khasi hills in order to delineate subsurface geological structures and preparations of

Gravity-Magnetic Map. Shortfall of 350 sq km of FS: 2013-14 pertaining to item Gravity-Magnetic

Mapping in Parts of West Khasi Hills District, Meghalaya will be covered in the month of April, 2014 as

per approval 1586/S/1/1/FSP/NER(vol.1)/ 2013-14/46F dated 25.03.2014.

RSAS:

In FS: 2013-15 Geological mapping of 2000 sq km on 1:50,000 scale using remotely sensed data

with selected field checks covering T.S. Nos. 78 G/15; 78 K/3,4, 8, 12, 16 is proposed to be mapped.

During FS: 2013-14, 900 sq km in covering T.S. 78 K/4,8,12 & 16 is to be carried out of which 900

sq.km has been completed upto March 2013 (the targets of original proposal has been modified as per

PPM letter no. 5522/6/1/1/FSP/NER(vol.1)/ 2013-14/46F dated 09/10/2013.

Sl.

No.

Item Utility

1. ERADAS Image 2010 installed Digital image processing and interpretation for

geological studies.

ERDAS IMAGINE version 2010,

classic interface.

Digital image processing and interpretation for

geological studies.

2. Geo-coded IRS Images of area part

of NER

219 No

3. IRS Images soft copy Total 112 No, For geological studies and survey

work.

4. Aerial photographs on 1;50,000 and

30,000 scale

For Geological mapping and studies.

5. Mirror Stereoscopes Total 4 No, For generating optical model of the

terrain and study of geology and structure.

6 CARTOSAT-1 (IRS-P5) Terrain modeling , mapping in different terrain,

monitoring of environmental parameters, glacial

monitoring etc.

16

MISSION-II

The mineral occurrences in this region include limestone, ferrosilicon grade quartzite, graphite,

dimensional stone (granite), Kaolinite, SMS grade dolomite and coal. The ultramafics of ophiolites

sequences of Manipur containing pods of high grade chromite, often with high content of Ni, Co along

with presence of platinoids. The North Eastern Region is endowed with various mineral deposits of

economic significance. Arunachal Pradesh accounts for 43% of the total national graphite resource,

Meghalaya accounts for 9% of total national limestone resource and 5% of total apatite resources.

During the F.S. 2013-2014 upto the month of March, 2014 the total target of the various

components pertaining to Mineral Investigations in NER is summarized in the following table.

17

TABLE: PROGRESS OF MINERAL INVESTIGATION OF NER UPTO MARCH, 2014.

MISSION – II Commodity

TARGET

F.S. 2013-

14

ACHIEVEMENT TILL MARCH, 2014

LSM in 9 items 369.50

SqKm 395.4 SqKm (107 %)

DM in 5 items 8.5 SqKm 8.5 SqKm (100 %)

DRILLING in 4 items (including extended items)

Total

Grand

Total

ME/NER/SME/2013/018

Drilling started on 23-12-13

Limestone(Larket

block, Litang

valley, Jaintia Hills

District,

Meghalaya)

800m

281.75

m

364.85

872.95

1623.55m

ME/NER/SME/2013/019

Limestone

(Mawlong –

Ishamati Block of

Shella-Bholaganj

Belt, East Khasi

Hills District,

Meghalaya)

800m 83.1m

ME/NER/NEnR/SAS/2012/030

Coal (Shalibhuin in

Dhubri District of

Assam and

Nakaigiri-Ujanggiri

in West Garo Hills

District of

Meghalaya.)

300m 161.65

m

508.1

ME/NER/NEnR/SME/2013/022

Coal (Sukchar-

Singrimari area,

Singrimari Coal

Field, Dhubri

district, Assam)

600m 346.45

m

ME/NER/NEnR/2010/014

(EXTENDED ITEM)

75.2m

750.6 ME/IM/NER/SME/2010/015

(EXTENDED ITEM) 675.4m

RECONNOITARY in 1 item 150 SqKm 150 SqKm (100%)

PITTING TRENCHING In 4 item 105 cu.m 113 SqKm (107.61 %)

GP Magnetic for Chromite in 1

item 5.6 SqKm 6.09 SqKm (108.75 %)

GP magnetic for Titaniferous-

Vanadiferous Magnetite in 1 item 10 L Km 10.1 L Km (101 %)

Investigations for limestone was taken up in Litang valley, Jaintia Hills District, Shella-

Bholaganj belt, East Khasi Hills District, Meghalaya, around Daba Gamlin area, West Siang and East

Siang Districts, Arunachal Pradesh, Titaniferous-Vanidiferous Magnetite in West Khasi Hills Distict,

Meghalaya, REE in Ri-Bhoi District, Meghalaya & in Sujukona Hill and Tukureswari Hill, Goalpara

District, Assam, PGE in Ophiolite Belt of Nagaland & PGE and Gold mineralization in mafic-ultramafic

suites in Anjaw, Lohit and Lower Dibang Valley Districts, Arunacha Pradesh, basemetals and associated

Gold in extension areas of Dikchu basemetal prospect, East District, Sikkim were also taken up.

Limestone Investigations: Investigation for Limestone (G3) is in progress in North of Larket Block,

Litang Valley, Jaintia Hills District and Mawlong-Ishamati Block of Shella - Bholaganj Belt, East Khasi

Hills District, Meghalaya. Earlier investigation for Limestone in Umphyrluh Block, Litang valley, Jaintia

Hills District was completed in November, 2013 as an extended item of FS 2012-13 in which 1.5 sq. Km

of detailed mapping was carried out. Drilling of 907.85m and 692 core sampling was done in which

drilling of 675.40 m and 417 core sampling was achieved upto Dec, 2013 for FS 2012-13 which makes a

18

total of 1583.25m and 1109 nos of core sampling. In addition to 439.29 million tonnes of different grade

of limestone estimated during F.S 2010-12 which is based on fifteen boreholes, a resource of about 64.43

million tonnes of different grade of limestone was estimated for the three boreholes of this block.

Geologically the Larket block exposes mainly the Middle Tertiary Sedimentary sequence comprising

Kopili and Shella Formation of middle to upper Eocene age with cover recent to sub recent alluvium. The

Shella Formation is represented by nummulitic limestone. The limestone is grey to dark grey in colour,

medium grained, massive, compact and highly fossiliferous, dominant fossils being nummulites while the

Kopili Formation is represented by shale and ferruginous nummulitic argillaceous limestone/marl. Shale

is dark in colour, thinly laminated and splintery in nature.

The general trend of the Formation is sub horizontal with strike varying from NNE- SSW to NE-

SW and dip varying from 30º to 50º towards ESE to SE. Three sets of joints are developed in the

limestone, out of which two are vertical to sub vertical trending NW-SE and NNE-SSW. Stylolite with

varying magnitude and wavelength are the common solution structure present in the limestone.

Disseminations of pyrite is observed along the fractures of drill cores, Oolitic structures showing

concentric carbonate rims of various shapes and size ranges from few mm to 2.30 cm across. Ball and

pillow structure are also seen in the drilled core.

During FS 2013-14, in the Larket block, drilling commenced on 23.12.2013 and progressed up to

281.75m in which 112 nos of core sampling was done till March, 2014. The remaining drilling target of

FS 2013-14 will be carried over during FS 2014-15. Borehole no.JNLK-1 was closed at depth of 89.10m.

Borehole no. JNLK-2 commenced on 10.02.2014 and attained a depth of 51.50m in which limestone band

ranging in thickness from 79.00 m to 95.00 m has been intersected at shallow depth. Limestone resource

of 43.89 million tonnes of unclassified category has been estimated from borehole no. JNLK-I and JNLK-

2. To assess the potentiality of limestone along the western continuity of Mawlong-Ishamati Block, Shell-

Bholaganj belt in which 1.5 sq. km area has been mapped on 1:5000 scale. The lithounits encountered in

the area are limestone, shale and sandstone. The northern part of mapped area occupied by E-W trending

limestone ridge of 80 m to 100 m in height with steep slope. Limestone is hard and grey in colour and

trend along E-W direction with variable dip from 35° to 45° towards north. The limestone belongs to

Shella Formation of Palaeocene-Eocene age. Petrographic studies of limestone shows predominant

presence of foraminifers with large amount of other fossil shells. Few veins of pyrite were observed

within limestone in western part of the area.

Shale of Kopili formation of Palaeocene-Eocene age occurs in south of limestone ridge. It is

highly weathered, splintery in nature and shows variable dips in the area. The contact between limestone

and shale is faulted and trends E-W. The Kopili shale is younger but in the area it lies in down thrown

block. Sandstone band of 20m to 30m wide was also demarcated within the shale. Sandstone is fine to

medium grained and grey in colour.

Analytical results of 7 grab samples collected from of limestone ridge shows an average CaO

50.75%, Fe2O3 0.21%, MgO 0.81% and SiO2 3.51%. The analytical data indicate chemical grade of

limestone. In this block subsurface exploration by drilling (RD-30; Unit No:441) commenced on

28.03.2014 in which three boreholes has been taken up (one completed and two in progress). Total

meterage achieved in all the boreholes in this Block was 83.10 meters in which 22 nos. core samples were

generated till March, 2014. The first borehole ISBH-1 was planned to intersect the western continuity of

limestone of Mawlong-Ishamati block. This borehole drilled up to 54.75m and intersected boulders of

limestone, sand and clay. Borehole no. ISBH-2 was planned at 120m west of borehole no. ISBH-1 to find

the lateral continuity of limestone bands towards west. The borehole ISBH-2 progressed up to 23.85m

and was suspended due to break down of drill machine (Unit-462). It has intersected fossiliferous

limestone with occasional calcite veins. 22 nos. of core samples were collected and submitted for

analysis. Results of core samples are still awaited. Borehole ISBH-3 was planned further 400m west of

Borehole no. ISBH-2 and drilled up to 4.50m depth (31.03.2014). It has intersected fossiliferous

limestone and bore hole is in progress.

19

Coal Exploration: Study of Gondwana Coal was carried out in Sukchar-Singrimari Block, Singrimari

Coal Field, Dhubri district, Assam which is located at the border of Assam and Meghalaya in which two

coal seam of thickness 0.55 m and 2.15 m have been found at 257.90 m and 262.70 m depth respectively.

During FS 2012-13, borehole no. SN-05 was closed at a depth of 281.00 m on 22.05.13 out of total

562.55m, drilling of 75.20 m was achieved in FS 2013-14 as extended target.

In FS 2013-14, 3.00 sq km of Large Scale Mapping (1:10000) was achieved. A basic dyke of

about 10m width and also another ultramafic dyke of about 5m width, intrusive within the gneissic

complex have been mapped near Shalibhuin.

Drilling (Unit: 422) of 346.45 meters has been achieved till March, 2014. The maiden borehole

no. SK-01 commenced on 25.11.13 and closed on 12.03.14 at a depth of 243.45m within basement

metamorphic rock. A coal seam of 0.90 m thickness has been intersected at 109m depth while a thick

carbonaceous zone of about 25m has been intersected at a depth of 193m. Second and the last borehole

no. SK-02, located downdip of borehole no.SK-01, was commenced on 19.03.14 and attained the depth

103m.

Geological study in Coal Zone in Tertiary sequence around Shalibhuin in Dhubri district, Assam

and Nakaigiri-Ujanggiri in West Garo Hills, Meghalaya was kept in abeyance from November, 2013 in

which 1.4 sq. km of LSM (1:10K scale with 5m contour interval) and 161.65m drilling was carried out.

The Tertiary sequence trends NW-SE with very low dips varying from 5 to 10° towards SW. Based on

these existing coal pits in the area, one scout borehole USD-01 was done and was closed on 23.10.13 at a

depth of 161.65m.

REE Investigation: During the FS 2013-14, Preliminary investigation for REE (G4) in parts of

Nongpoh pluton, Ri-Bhoi district, Meghalaya located in parts of Nonghkhyllem Reserve Forest and

western part of the area, Umran, Shangbangla, Nongpoh is in progress in which LSM: 60 sq.km (scale

1:12,500) was done.

Lithounits observed in the area includes sillimanite-biotite gneiss, granite gneiss and diorite

gneiss of Precambrian gneissic complex, mafic rock/lamprophyre (?), diorite-granodiorite, porphyritic

granite and non-porphyritic granite of Nongpoh pluton. Three generation of Nongpoh granite/granitic

events have been identified on the basis of field relationships. These are Early Non-porphyritic Granite,

Porphyritic Granite and Late Non-porphyritic Granite. Three types of enclaves viz; xenolith of country

rock, dark grey porphyry and black biotite rich microgranular enclaves were observed in Nongpoh

porphyritic granite. The mafic enclaves (MEs) in the area have various shapes including circular,

rounded, ellipsoidal, angular to sub angular, as dykes. The mixing compatible textures observed during

petrographic study viz; acicular and stubby apatite, resorbed plagioclase xenocrysts, titanite-feldspars

ocellar relation, ocellar quartz, poikilitic microcline, plagioclase, hornblende and quartz, combined with

frequent occurrence of MEs of various shapes and size suggest magma mixing and mingling was a major

process during the evolution of Nongpoh Granitoids. SSS data of 8 nos. samples yield ∑REE (La-

Lu+Sc+Y) value range between 226 to 2984 ppm with an average value of 900ppm. One sample contains

2984 ppm at the contact of porphyritic granite and basement gneiss. BRS analysis of 9 samples of

Porphyritic granite yield ∑REE (La-Lu+Sc+Y) ranges between 562 to 980ppm with an average value of

813ppm. 6 samples of Non-porphyritic granite yield ∑REE (La-Lu+Sc+Y) ranges between 578 to

2148ppm with an average value of 1152ppm. Two granite samples yield ∑REE (La-Lu+Sc+Y) value

1803 and 2148 ppm have visible spindle shaped sphene (titanite) and allanite (?) in hand specimen. One

sample of Granodiorite (?) from Garikhana area yield ∑REE 813ppm. 06 nos. soil samples yield ∑REE

(La-Lu+Sc+Y) value ranges between 653.57 to 1614.50ppm with an average value of 1041.92ppm.

EPMA analysis of Nongpoh Granitoids indicated presence of REE Carbonate (70.65% tREO), Monazite

(61.16% tREO), Allanite (18.52% tREO) and Sphene (2.4-4.1 %tREO). Apatite and zircon contains very

less (<1%) total REO.

20

Specks and disseminated grains of pyrite and chalcopyrite are observed in gneisses,

diorite/granodiorite, mafic intrusive rock, porphyritic granite, quartz and pegmatite veins. Sheelite grains

have been identified by EPMA study in garnet-epidote rock which are observed in porphyritic and grey

non-porphyritic granite. Disseminated magnetite crystals in the pegmatite intruding in grey granite was

observed (west of Mawdaran). Two samples collected from granite and associated pegmatite near

Mawdaran village shows 7 ppmm & 36 ppm Mo at Mawdaran quarry.

Titaniferous-Vanadiferous Magnetite Investigation: Titaniferous-Vanadiferous Magnetite

Investigation around Rambrai in West Khasi Hills district, Meghalaya is in progress. An area of 25

sq.km has been mapped on scale 12,500 in which lithounits encountered in the area are granite gneiss,

banded gneiss, granite and mafic granulite. The granite gneiss is medium to coarse grained with a crude

foliation. It is mainly composed of quartz, Plagioclase, feldspar, biotite. Tourmaline and magnetite are

accessory minerals. At places granite gneiss is highly weathered and shows a typical banded nature

defined by 3-4cm thick quartzo-feldspathic layers intervened by thin mafic layers. Three meta norite

bodies of different length and width have been identified and delineated in the area viz., (i) Northwest of

Moulih, (ii) West of Rambrai, (iii) Southwest of Rambrai. These bodies trending NW to WNW direction.

The rock is dark grey colour, fine to medium grained and massive. The first two meta-norite bodies are

having bands of titaniferous-vanadiferous magnetite and partially laterised. The dominant foliation within

the gneiss is trending NW-SE with moderate to steep dips towards NE. Two prominent set of sub-vertical

joints trending NE-SW and E-W also observed in the area.

Large Scale Mapping on scale 1:2000 was done of an area of 1.10 sq.km near Moulih

village and pitting and trenching of 3.20 cu m was carried out. The meta-norite body is bouldery in nature

and trending NW-SE dipping towards 40°-60° SW. The bed rock samples were collected for XRF, PGE

and REE analysis. Mineral phases identified by EPMA study are. Ilmenite, Titaniferous - Vanadiferous

magnetite, Chalcopyrite and Pyrite. A total of 60 nos. of bed rock samples were collected for which

analysis of 26 samples (XRF) received so far shows Fe2O3 ranges between 6.82% to 30.96% (average

14.03%),TiO2 0.72% to 4.30% (2.06%), Vanadium 81ppm to 1398ppm (688ppm), Zr 47ppm to 1802ppm

(205ppm) and copper from 5ppm to 566ppm(188ppm).

Assistance to State Government and other Agencies

GSI, NER has taken up investigation for PGE of ophiolite belt in association with the

DGM, Nagaland state. Besides, an investigation for coal is taken up in Singrimari area, Assam at the

request of Assam state.

21

Mission–III: INFORMATION / DISSEMINATION

Publication:

GSI, NER has brought out several publications in the form of books and maps to disseminate

information in earth science. The region has already published the miscellaneous publication No. 30 for

the states of Meghalaya & Assam, Arunachal Pradesh, Nagaland- Manipur and Tripura and Mizoram.

Publication of Rec. GSI, Vol. 147, Pt. 4 (Extended Abstract for F.S. 2012-13): Finalized, printed and

released on 31.01.2014. GSI, e- News (NER), Vol. 23 (January, 2012 to December, 2012): Manuscript

finalised and published on GSI Portal on 12.02.2014.

Library Services: Procured 14 nos. Geology books and 24 nos. of journals in Regional Library till

March, 2014. Seven scientific papers and 14 abstracts were processed for different national and

international seminars/ journals. Generated a resources of Rs 4260.00/- through sale of GSI publications.

Distributed 202 copies of GSI publications to all the Regions of GSI in India and extended library

facilities to departmental officers and others.

22

Map & Cartography :

DRM: A brief highlights of the Compilation of District Resource Maps of different states of NER is

given below:

Manipur-Nagaland: Prepared digitized and finalized the DRM’s of 4 districts of Manipur (Tamenglong,

Ukhrul, Imphal East & Senapati districts).

Tripura- Mizoram: Finalisation of the main map consisting of all layers of Aizawl and Champhai

districts on 1: 2,50,000 scale and finalized Inset Maps of geomorphology and Geotechnical details of

these two districts on 1: 1 million scale along with geological notes for DRM.

Assam: Digitisation & Digital Layout Preparation of Kamrup, Darrang and Goalpara district (Pertaining

to FS 2010-12) DRM is completed in all respect. Modification and preparation of hard copy layout for

Karimganj, Hailakandi, Sibsagar, Golaghat, Cachar, Dibrugarh, Dhemaji & Tinsukia DRM (FS 2012-13)

completed and the layouts have been sent to RMH-III for vetting. Compilation of Bongaigaon, Nagaon,

Lakhimpur, North Cachar Hills districts and Jorhat DRM is also completed. Digitisation of Geology and

mineral Layer of Karbi-Anglong district completed.

Meghalaya: Compilation of West Garo Hills, East Garo Hills, South Garo Hills, East Khasi, West Khasi

and Ri-Bhoi districts of Mehgalaya is completed in all respects. DRMs of East Khasi, West Khasi, Ribhoi

and East Garo Hills districts of Meghalaya have already been published. DRM of Jaintia district of

Meghalaya is completed.

For the creation of theme based 50K Geological Database, modification of graphic elements and

attribution of lithology as per the standardized legend is completed for 346 portal uploaded toposheets.

Digitization and attribution of three compiled geological maps of Assam is completed. Preparation and

uploading of metadata of three sheets is completed.

Preparation of Quadrangle Geological Map of Degree-sheet 78O on 1: 250,000 scale covering parts of

Meghalaya and Assam is competed in all respects including Geological section.

Geoinformatics: Creation of theme based database of degree sheet no 78O covering parts of East Garo

Hill, West Khasi Hill, Jaintia & Ri-Bhoi Districts of Meghalaya and Kamrup & Goalpara Districts of

Assam, extraction and entry of data of Seven (07) reports pertaining to Mining (Mineral Exploration)

theme, Three (03) reports of Map 50K theme and Two (02) reports of Geophysics theme were completed.

A total of 177 nos. of lithological records in individual sub-form of respective toposheets were inserted in

the Map 50K domain. The standardized Geometry ID’s of the lithological units as prepared by the M&C

Division were used for Oracle data entry. The modified data was supplied to the Geodata Division for

updation of NER repository on Portal. Data were extracted and inserted for around 2000 cells in sub-forms

viz. Lithological Unit (Geometry ID, Notation, Lithology, Supergroup, Group, Formation, Member,

Minimum/Maximum thickness), Standard Lithology (Lithology, Texture, Remarks),

Microscopic/Macroscopic Minerals, Quaternary description (Intensity of Oxidation, Pedogenesis,

Vegetation cover type etc.)

Lexicon for Locality names was updated with 67 new values for the sub-form Mineral

Occurrence of Mining Exploration Domain. A total of 81 nos. of mineral occurrences in degree sheet 78O

have been extracted from the reports for their entry into the Mining Exploration Domain. The Geometry

IDs of the each mineral location were modified with 6 digit integer values ranging between 781501 and

781581. The Mineral Occurrences were attributed with fields on the Geological Settings, derived from the

overlay of LI layer. The modified MI layer was supplied to Geodata Division for Spatial Repository of

NER and uploading to portal. Data have been extracted for various headers viz. Mineral Occurrence Id,

Latitude, Longitude, Mean Sea Level, Toposheet subdivision, Host rock age, Structural setting, Macro

alteration, Worker name, Year, Bibliographic reference, Comments and Other information. There are five

other sub-forms namely Commodity, Structural Elements, FSP Numbers, Samples (s) and Field

observation (s) to enter specific data.

23

A report of the database was generated through SQL at the central server of the Oracle Database.

Discussions were held with Geodata, CHQ regarding input of chemical data in Drilling Domain and with

the officers of Chemical Division, NER regarding creation of Protocol ID and Lab Lexicon ID for Oracle

Database entry of NER which will include Laboratory Code, Element Code, Analytical Method Code,

Sample Digestion details, Unit Code, Lower Detection Limit, Upper Detection Limit, etc. List of Protocol

and Lab Lexicons for entry of Chemical Data were finalised.

Geodata : There are two linked program with M&C Division for Geodata component. Edge-matching of

different feature elements of graphic geological data and extraction of unpublished reports under

Geoinformatics item.

Mission–IV: SPECIAL INVESTIGATION, RESEARCH & DEVELOPMENT

Palaeontological Studies:A field investigation was taken up along Shillong-Sohra, Shillong-Mawsynram

and Shillong-Dawki in East Khasi Hills district of Meghalaya for search of fossils and preparation of

geological map on 1: 50,000 scale. Twenty four (24) specimens have been collected covering 17 sq km of

the area. 10 L.km. mapping was done and 5 sections measured. Trace fossils like burrows, bi-valve resting

impressions etc. were collected from Mahadek and Langpar Formation along Shillong-Sohra, Shillong-

Mawsynram and Shillong-Dawki sections. Numerous wood fossils were collected from Langpar Formation

along these sections. In case of invertebrate fossils, Allectryonia sp., Nummulites sp. etc were collected

from Mahadek Formation and Shella Limestone respectively. Most interesting part is that, about dozen of

oval to rounded egg fossil like samples were collected in and around Dawki area, East Khasi Hills District,

Meghalaya and these were examined physically and thin sections were prepared at different directions

(tangential & radial). The SEM-EDX study and thin section study of the suspected egg shell were carried

out at Palaeontology Division - I Laboratory, CHQ, Kolkata. EDX study shows that these samples contains

very high calcium which in turn suggests that these are fossils not phosphatic nodules. SEM study shows

presence of pore spaces in some samples. Few thin section studies show egg shell structure and pore spaces

in tangential section. Radial thin section was prepared and studied but they do not shows typical

canaliculae of tubocanaliculate pore system which is the characteristic feature of egg shell of reptiles.

Detailed study of thin section in SEM and EDX graphs suggests these are not egg fossils but are

invertebrate fossils falling within gryphoid group, most of them are possibly algal balls and a very few are

possibly erosional features within limestone.

Geotechnical investigations:NER may be termed as the ‘power house’ of India as it possesses

hydropower potential, which is about 30% of the total hydel potential of the country. The hydel potential

of major river basin of Arunachal Pradesh like Kameng, Subansiri, Siang, Lohit and Dibang totals

production of 34920 MW at 60% load factor (CEA) i.e. about 90% of the total hydropower resources of

NER.

A large number of major and minor hydroelectric projects have been completed or are under

various stages of investigation/construction with the active help and support of geoscientific inputs by the

GSI, e.g. Ranganadi, Doyang, Umiam (Barapani), Pare, Kopili, Turial, Kameng, communication projects

and border roads.

Arunachal Pradesh contributes a major share of the water of the Brahmaputra river system and the high

relief offers extensive scope for hydel power generation. Geotechnical evaluation of water resources

development projects in North Eastern Region has been taken up at the request of the project authorities.

GSI has carried out geotechnical studies for various hydro power projects in the NER:

Feasibility studies: (Dihang (AP), Pare (A.P.), Dikrong (AP), Subansiri (AP), Lohit Dam Project, (A.P),

Dimwe (AP.), Kameng (AP), Atnring (Assam), Amuna (Assam), Kulsi (Assam), Dalaima (Assam),

Loktak (Manipur),Barak (Manipur)

24

Pre-construction and detailed investigations: (Sessri (AP.), Ranganadi Stage-II, (A.P.), Kamleng (AP.),

Lower Kopili ((Assam)),Intermediate Barapani (Meghalaya), Pagladiya Dam Project (Assam), Tuivai

Project (Mizoram), Tunal Project (Mizoram), Doleswari (Bharvi) project (Mizoram), Mat Valley Project,

(Mizoram), Kolodyne Stage-I, (Mizoram), Kolodyne Stage-II, (Mizoram), Kapak Leyak H.E. Project,

Arunachal Pradesh, Mawhu H.E. Project, Meghalaya, Myntdu – Leshka H.E. Project Stage-II,

Meghalaya, Myntdu – Leshka H.E. Project Stage-II, Meghalaya, Umngot Combined Stage-I & II, H.E.

Project, Meghalaya, Umngi H.E. Project Stage-I, Meghalaya, New Umtru H.E. Project, Meghalaya,

Ganol H.E. Project, Meghalaya, Simsang (Someswari) Multipurpose Project, Meghalaya, Kynshi

(Jadukata) Multipurpose Project (Stage-I), Meghalaya.

Construction Stage investigations: Ranganadi (AP.), Kameng HEP (AP), Kopili (Assam), Lower

Borpani (Assam), Doyang HEP, (Nagaland),Thoubal Project (Manipur), Singda Project, (Manipur),

Khuga Project (Manipur),Myntdu – Leshka H.E. Project Stage-I, Meghalaya)

Geotechnical evaluation of Water Resource Development Projects were taken up during FS 2013-14 in

Kameng H.E.Project, West Kameng District, Arunachal Pradesh, Kulsi Multipurpose Dam Project,

Kamrup District, Assam, Turial H.E.Project, Aizawl District, Mizoram and Mawblei H.E.Project, West

Khasi Hills District, Meghalaya.

Landslide Hazard Studies:

GSI has carried out landslide studies on different scales in following areas of NER:

MACRO SCALE LHZ

(1:50,000 SCALE)

MACRO SCALE

LHZ

(1:250,000 SCALE)

MESO SCALE

LHZ

(1:10,000 SCALE)

SITE SPECIFIC

STUDIES

SU: Assam

Kalapahar, Guwahati, Kamrup

district, Assam (FS 1998-99)

Kalapahar,

Guwahati, Kamrup

district, Assam (FS

1998-99)

Kalapahar,

Guwahati, Kamrup

district, Assam (FS

1998-99)

Cachar, Assam & Jaintia district,

Meghalaya (FS 1998-99)

Guwahati Urban Complex, Assam

(FS 2002-03)

Guwahati Urban

Complex, Assam

(FS 2002-03)

Kolsaib district, Mizoram and

Cachar district, Assam

(FS 2003-04)

Guwahati, Assam (FS 2004-05) Guwahati, Assam(

FS 2004-05)

Guwahati,

Assam(FS 2004-05)

SU: Arunachal Pradesh

Itanagar Capital Complex,

Arunachal Pradesh (FS 1998-99)

Bomdila & Tawang, West

Kameng And Tawang Districts,

Arunachal Pradesh( FS 2012-13 &

FS 2013-14)

Bomdila &

Tawang, West

Kameng And

Tawang Districts,

Anjaw & Lohit

Districts Arunachal

Pradesh( FS 2012-

13 & FS 2013-14)

NH-52a Corridor From

25

Banderdewa To Gohpur (Holongi)

Via Itanagar, Papumpare Districts,

Arunachal Pradesh

(FS 2012-13)

SU: Tripura-Mizoram

Lunglei, Lawngtlai & Saiha

districts, Mizoram (FS 1995-98)

Lunglei area,

Mizoram (FS 2005-

06)

Kolsaib and Aizawl districts,

Mizoram (FS 2001-02)

Lunglei area, Mizoram (FS 2005-

06)

Lunglei Town, Mizoram (FS

2006-07)

Lunglei Town,

Mizoram (FS 2006-

07)

Serchip, Chiahtiang Townships,

Serchip district, Mizoram

(FS 2000-01)

Serchip, Chiahtiang

Townships, Serchip

district, Mizoram (FS

2000-01)

Serchip, Hmar Veng, Serchip

district, Mizoram (FS 2000-01)

Serchip, Hmar

Veng, Serchip

district, Mizoram

(FS 2000-01)

Serchip, Hmar

Veng, Serchip

district, Mizoram

(FS 2000-01)

SU: Manipur-Nagaland

Mao Song, Senapati district,

Manipur (FS 2003-04)

Mao Song, Senapati

district, Manipur (FS

2003-04)

Mao Song, Senapati

district, Manipur

(FS 2003-04)

Kohima, Nagaland (FS 2004-05) Kohima, Nagaland

(FS 2004-05)

Imphal, Manipur (FS2004-05) Imphal, Manipur

(FS2004-05)

NH-39 (Imphal-Kohima), (FS

2005-06)

NH-53 (Imphal-Nungba), (FS

2006-07)

Zubza, Kohima district, Nagaland

(FS 2008-09 & 2009-10)

Zubza, Kohima

district, Nagaland

(FS 2008-09 &

2009-10)

Zubza, Kohima

district, Nagaland

(FS 2008-09 &

2009-10)

SU: Meghalaya

East Khasi Hills and Ri-Bhoi

districts, Meghalaya (FS 1999-

2000)

NH-40 (Shillong-

Phalangpongtung (Dawki)),

Meghalaya (FS 2007-08)

Shillong Town, Meghalaya

(FS 2009-10 & 2010-12)

Shillong Town,

Meghalaya (FS

2009-10 & 2010-12)

Macro-scale landslide hazard Zonation (1 : 50,000) of the Hayulinag –Challagam and Teju- Hayuliang

road sector of Lohit and Anjaw district of Arunachal Pradesh was carried out with the aim to prepare a

landslide susceptibility map of the selected stretch and evaluate the overall stability of the area in respect

to future landslide initiation. As a part of the exercises the 150 line km of the road bench between Teju in

26

the Lohit district and Chaglagam in the Anjaw district has been covered for augmentation of thematic

data bases and preparation of the landslide susceptibility map. A significant observation made during the

study is the nature and quantum of coarse debris being carried out by all the mountain streams. A huge

volume of debris mostly boulder laden is found to be transported by nearly all the streams and the trunk

rivers in the area. The same along with near absence of finer fractions in the riverine material may be

explained in terms of rejuvenation of the stream under the influence of neo- tectonic activities. As a part

of the work 56 numbers of the active and reactivated landslides were identified and mapped. Among these

31 are rockslides, 22 are debris slide and 3 are debris flow. Along the observed section the rock slides

found to be the dominant one. Both old rock slides and large/prominent new rock slides found traversed

the slope and affecting the road bench, upslope and down slope in the studied area. Planar failures,

combination of planar and wedge failure as well as toppling are the major identified failure mechanism.

Apart from the rockslides the other major kind of slope distressing that was observed and documented in

the area are Confined/at places unconfined debris flow initiated at high slope and descended through

majority of the mountain streams. The major outcome of the work besides the preparation of thematic

maps is i) Identification and documentation of the predisposing, triggering and revealing factors for

landslide initiation .ii). Detailed inventory of the observed slope instabilities encountered in the studied

corridor. iii) Detailed evaluation of a few trouble spots for understanding of the causative factors, failure

mechanism and formulation of suggested remedial measures. iv) Perspective assessment of the landslide

initiation process based on the revealing factors, slope morpho-metry, stream configuration and nature&

amount of sediments load in the drainage.

Detailed (1:1000) Site Specific Geological Studies of the Landslides near Tawang Monastery,

Tawang district, Arunachal Pradesh has been carried out for comprehensive evaluation of the various

attributes across the large dynamic slope mass of the conspicuous landslides near famous historic Tawang

Monastery.The slope failures initiated at least before 1985 is being continuously evolving in space and

time covering more than 0.6 sq km area is responsible for significant administrative and social concern

due to its proximity to the famous Tawang Gaden Namgyal Lhatse (TGNL) Monastery (popularly known

as Tawang Monastery), founded in the year 1680-81. The studies reveals presence of multi-level slide

scrap of varying dimension and geometry, initiated and evolved in varying slope forming material was

identified along and across the landslide complex. The prominent among the slide scars is the

conspicuous curvilinear crown scar extending over 100 m and subsequently found joined with the

prominent left side scars. Corresponding to the zone of depletion proximal to the scarps, a prominent

zone of accumulation in the form of gently sloping bench could be identified. The material identified

along and across the affected slope are isolated exposure of slight to moderately garnetiferous quartzo-

feldspathic gneiss, highly weathered Gneiss, in-situ soil, failed debris mass, mud flow and debris flow

deposits. The attitude of gneissosity varies from N180-300E/160-280→S780E (dipping inside hill) to

SW. Besides, the rockmass is traversed by three joint sets. Deep rotational failure in the in-situ soil and

failed debris mass, shallow and deep translational failure in the weathered rock mass, large block

subsidence in the flank were identified for initiation of slope failures at various space and time. Multiple

episode of debris/mud flow of varying run out length initiated in pulses is identified as one the important

mode of slope failures. The unconfined debris/ mud flow with significant momentum descended down

slope and are found partially submerged a school (Kendriya Vidyalaya). The most prominent debris flow

observed was initiated from upslope accumulated debris found descended along the moderately steep left

bank slope of Kangteng River through two branching type of confined flow path and accumulated heap

near bank of the Kangteng River. Partial blockade of the river due to the flowing debris mass was also

noticed along the left bank for more than 100 m. Reactivation of some of the failure surfaces along the

prominent scars is also anticipated. The controlling law and parameters of the different stages of failure

and consequences of the same to the element at risks are being evaluated through detailed studies. As a

part of the endeveour nine (9) suitable borehole locations were delineated to understand the spatial and

temporal variation of the bedrock across the landslide complex. The field based findings will form the

basis for comprehensive understanding of triggering mechanism and causative factors responsible for

initiation and further continuation of failures to the upslope.

Detailed Study of 13th mile slide on Gangtok-Nathula Road, East District, Sikkim was carried

out. An attempt was made to study the slope stability on the eastern flank of the slide using slicing

method of Morgenstern-Price. During the stability analysis, the Factor of safety values ranging from 0.76

to 0.89 (in dry conditions) and from 0.72 to 0.84 (in wet conditions) were acquired indicating that the

slope is more vulnerable in the wet season. As the road passes mostly through the crest of the distress

27

zone, it is proposed from one Stability analysis, that the road may be shifted above the exposed rock line

upslope of road bench or to construct a retaining wall up to a depth of 48m for the road in its current

position. Using the monitoring data, strain analysis indicating the parts of the landslide where pillar nos.

1,2,3,5,6,7,9 and 16 are present in a compressive zone relative to others. The velocity and displacement of

installed pillars indicates a general displacement of the landslide in the SE direction.

Macro scale landslide hazard zonation on 1:50,000 scale along Rangpo-Singtam-Dikchu-

Chungthang road corridor, Sikkim Macro scale (1:50,000) was carried out to categorize the hill slope

into zones of varying degree of hazards (instability) and understanding the extent of new landslide

initiation and reactivation of the old landslides aftermath of the 18th September, 2011 (6.8 Mw) Sikkim

earthquake. As it is very much important to look into the landslide hazard zonation map from time to time

specially after every major earthquake (>5 on Richter’s Scale), and the selected corridor which is one of

the major passage connecting towards North Sikkim and densely populated townships viz. Rangpo,

Singtam, Dikchu, Mangan, Chungthang and major hydel projects namely Teesta stage III, IV and V falls

along this road corridor and in view of the post Sikkim earthquake scenario. A total of 42 nos. of

landslide incidences were recorded from Rangpo to Tung road corridor and most of them are of Rock

cum debris slide in nature. Almost 81% of the study area from Rangpo to Tung is falling under

moderately steep to steep slope having range from 26⁰ to 45⁰. Minimum relative relief is 35m near

Rangpo where as the maximum is 1835m found near Mangkha village. Landuse/Landcover map have

been prepared by using all available satellite imageries including LISS-III data and which has been

validated with field checks. About 80% land is barren with forest cover, 15% have agriculture and 5%

land is utilized by settlements.

A total of 23 sq. km area is covered out of 25 sq. km under geological mapping on 1:25,000 scale

was carried out for the Site specific study of proposed Pakyong airport area, Sikkim. The main lithounits

in and around Pakyong area belongs to Gorubathan Formation of Daling Group represented by low grade

metapelitic rocks, phyllite and schist with thin intercalations of quartzites. The trends of foliation are

varying from NE-SW to NW-SE dipping either easterly or westerly. Slope morphometry map has been

prepared which was derived from DEM. Major part of the study area belongs to gentle slope, followed by

very gentle slope and moderately steep slope and steep slope. The highly steep slope category occupies

very small portion of the area. The lineament map has been prepared for 100 sq.km. area in and around

Pakyong area. Majority of large lineaments follow NE-SW to NEE-SWW trend, whereas some

lineaments also have N-S, E-W and NW-SE trends. Drainage map has also been prepared from the

toposheet. The main drainage of the area is Pachey Khola which is a tributary of Rangpo Chhu. Slope

facet being basic unit of Landslide Hazard Zonation (LHZ), the map was prepared from toposheet and a

total of 1025 nos. of facets have been identified from 100 sq. km area. Relative relief map has also been

prepared from which it can be found that, major part of the studied area is characterized by high relief

(49.48%). Next to this, medium relief occupies 45.70% and rest of the area (4.8%) belongs to low relief

category. Landuse and landcover map, which is an indirect parameter governing slope stability have

been prepared after field check. Major part of the study area is agricultural land with isolated houses. The

densely populated land is mainly concentrated in the Pakyong town. The landslide incidences and

subsidence are mostly concentrated in the moderately steep slope of the northeastern part of the proposed

airstrip as compared to the other parts of the study area and various sinking zones are observed which are

mostly concentrated in the vicinity of the perennial nalas.

Earthquake Studies: During FS 2013-14, study of Seismic and Landslide Hazard Assessment of Aizwal

town, Mizoram & Kohima City, Nagaland and Gangtok and surrounding areas of Sikkim were taken up.

Aizawl town, Mizoram: In the Aizawl master plan area and an area of about 50 sq. km geological

mapping on 1:25,000 scale covering facet wise data collection on various Geofactors for Landslide

hazard zonation along with 5 L km section / Measurement was carried out. The areas covered include

Laipuitlang, Falkland, ITI Veng, Zemabawk, Lungleng, Samtlang, Hlimen, Tlangnuam, Maubawk,

Khatla, Reickai, Muallungthu, Falkawn, Kelsih, Melriate, Kulikawn, Mualpui, Sairang, Tanhril, Khalta,

Electric Veng, etc. Landslide hazard assessment studies were also carried out in an area of about 25 sq.

km within the Aizawl master plan. Collected 10 nos. of undisturbed soil samples and 5 nos. of rock

samples for analysis of different geotechnical parameters. The collected rock and soil samples were

submitted to Geotechnical Laboratory, Eastern Region for analysis of relevant geotechnical parameters.

Geologically the area is represented by a thick sequence of arenaceous and argillaceous sediments

28

belonging to the Bhuban Formation of Surma Group. The litho units occurring in and around the

Muallungthu to Hualngohmun areas are dominantly by bedded silt shale / shale sequence with few bands

of siltstone and sandstone intercalation. Various thickness of over burden in the form of colluvial

material and highly weathered mantle rocks occupy the gentle slopes, whereas along the spur surfaces

the thickness of overburden ranges from 1 to > 5 m in the above mentioned areas. Lungleng, Sairang and

Tanhril areas are occupied by dominantly massive thickly bedded sandstone interbedded with thin bands

of shale/ silty shale overlained by thick weathered mantle and soil on the gentle slope and spur surface.

Aizawl master plan area falls on the N-S trending broad and asymmetric antiform with axes shifted

laterally at places. These are traversed by sets of E-W trending fault systems which are having distinct

geomorphic expressions of faulting. Different slope forming materials like highly weathered mantle

rocks and colluvial materials ranging its thickness from 1 to 8 m thick were studied and mapped for

arriving at the site response / landslide hazard assessment. In general the rocks in the study area trends

NNE-SSW to NNW-SSE with moderate to high dips on either sides. Synthesis of seismicity data within

300 km radius in and around Aizwal area, involving conversion of Ms and Mb earthquake magnitudes to

Mw for assessing the recurrence period and to determine PGA of the area was undertaken.During the

course of the study Landslide inventory were carried out in and around the Aizawl master plan area as

well as along Sairang – Kanpui road section. It appears that the slope instability can be attributed to the

inherent rock mass condition, anthropogenic interference (unscientific slope cutting / static loading due

to constructional activities), unguided drainage, etc. Besides, ground water information based on the

available hand pump locations were recorded and are being analysed with other collateral subsurface

information collected from different Government agencies. The collected field data are being processed

for the preparation of relevant thematic maps for analysis and interpretation regarding the Seismic

Hazard Assessment of the area.

Kohima City, Nagaland: Analysis of past seismicity data of 300 km radius around Kohima city was

carried out to delineate potential seismic source area. The analysis has indicated high seismic activity

along the Eastern Boundary Thrust Fault which is located about 83kms south/southeast of Kohima.

Moderately high seismic activity along the Belt of Schuppen, Kopili Fault and Shillong massif

Seismogenic zone was also observed, which is located within 100kms and 200kms respectively from the

Kohima area. Study and synthesis of rainfall data for 30 years of the study area, provided by the

Department of Soil and water conservation, Government of Nagaland was also undertaken. Synthesis of

this data was undertaken for estimating the recurrence period and PGA value. The Morphotectonic and

lineament map covering 50 sq. km area was prepared using LISS-III and SRTM data of Kohima area.

The study area is located in a fold thrust tectonic set up of the Belt of Schuppen comprising of 5-6

tectonic slices bounded by the Naga Thrust and the Haflong - Disang thrust in the north and the Eastern

Boundary subduction zone in the south. Surface Geological Mapping on 1:25,000 scale covering 17 sq.

km around the areas of New Secretariat complex, Merema, High school area, IG stadium and Zubza

river section of the Kohima Master Plan area was undertaken. Highly weathered carbonaceous shale of

the Disang Group of rocks are exposed in this area, which trends NW-SE with moderate dips towards

NE. Facet wise data collection on different geo-factors like lithology, structure, landuse / landcover,

hydrological condition, etc. covering an area of about 17 sq. km in the southern part of the study area

was undertaken for landslide hazard zonation. This data is being synthesised to arrive at different hazard

levels in the area. Slope instabilities studied in this part of the area revealed that the weak rock mass

(highly weathered shale), toe erosion of the slope, saturated slope wash material and construction of new

road across the slope have resulted in the instability of these slopes. Although some part of the area is

slightly away from the main settlement, the instability in this zone has an impact on the agricultural land

and the settlement on the top part of the slope. Besides, study of groundwater information along with

borehole litho log collected from the Directorate of Geology and mining, Govt. of Nagaland was also

carried out. Four soil and two rock samples were collected and all the samples were submitted to

Geotechnical Laboratory, Eastern Region for analysis of relevant geotechnical parameters. Presently the

work is under progress and will be continued during FS 2014-15, the second year of the study.

Study of active landslide incidences within the Master plan area like the Phesama slide, old dumping

slide along NH-29 and Merema slide along NH-61 were also undertaken and the causative factors of the

slide, morphology of the slide, etc. were studied and appropriate remedial measures were suggested.

Three rock samples of fine grained sandstone of Laisong Formation (Barail Group) and one rock sample

of Shale (Disang Group) were collected for analysis of different geotechnical properties.

29

Gangtok, Sikkim: The Seismic Observatories installed at Agartala (Tripura), Itanagar (Arunachal

Pradesh) and Adampool, Gangtok (Sikkim), which are equipped with broadband seismographs, are being

used to record the seismicity round the clock of the North Eastern Region and its adjoining neighboring

countries, such as Bhutan, Nepal, Bangladesh, and Myanmar. These Observatories are very useful for

providing potential information on earthquake genesis of the eastern Himalayan region as well as sub-

oceanic earthquakes from the Bay of Bengal, which will be helpful in evolving earthquake mitigation

model for the region as a long-term goal. Study of toposheet and SRTM data to delineate different

geomorphic /morphotectonic units and Lineaments. Seismic Hazard Assessment of Gangtok and

surrounding areas of Sikkim were initiated by State Unit: Sikkim. Seismic Hazard Assessment of

Gangtok , Sikkim was carried out by Site response study was carried out by three component digital

seismograph (Kinemetrics make SS-1) using H/V method developed by Nakamura (1989) to eliminate the

source effects in the spectra of the micro tremor signal. Preliminary analysis shows a moderate site

amplification factor (HVSR) varying between 3-5 in the eastern part of the study area which includes the

Gangtok town and extends to the station G1 (Gairgaon area) in the south. Recording of ambient noise for

Seismic site response study in Gangtok and surrounding areas was carried out. For 50sq area, Site

response study by measuring ambient noise using short period Seismograph at every 1-2 km. station

spacing have been completed. Surface Geological mapping on 1:25,000 of 50 sq. km Geological

mapping on 1:25,000 scale was completed in and around Gangtok along with 5 L.km Profile section /

measurement. 25 nos. soil samples for Geotechnical properties were collected and send to GT Lab, ER,

Kolkata. High site amplification is observed close to site S6, (Slave ground) in the northern side of the

study area which lies in the flat ground with gentle slopes on both sides, whereas, high amplification in

the south near to N2, lower Nagdok, is on the steep slope side near to the valley. The site P8 (Pastanga) in

the south also shows high amplification on the gentle slope in the valley edge. Most of the area in the

western part has comparatively low amplification zones where HVSR varies between 1 and 3, except at

stationT4, where the site is on a flat hill top with a thick soil cover.

Medical Geology: Systematic spot analysis of groundwater and surface water by Merck Arsenic Field kit

were carried out in the field in Toposheet 83 B/12 & B/16 to study of arsenic contamination in water and

soil in parts of nagaon and marigaon districts, Assam. The arsenic values in groundwater varies from nil

to 100 ppb where as that of surface water varies from nil to 5 ppb. Exceeding the WHO’s permissible

limit i.e. 10 ppb, 47 nos. samples of groundwater collected from handpumps and tubewells have recorded

arsenic values of 25 ppb. One sample in TS 83 B/16 has arsenic 100 ppb in Nis Daboka and two samples

have arsenic values 50 ppb. The depth of handpumps varies from 30 to 50 ft b.g.l and tube wells vary

from 200 to 400 ft b.g.l within younger floodplain in the area. The concentration of high arsenic values in

groundwater occurs as small zones/clusters near villages Raha, Chapermukh, Kusigaon, Darangigaon,

Guimari, Saragoan, Tetchgarh, Bhagtakagaon, Charaihagi, Jamunamukh, Kampur and Tetlisarah villages.

10 ppb values of arsenic have been recorded in Tapakushi, Molankata, Jorabari, Kothiatoi, Kampur,

Barkula, Atikampur, Tetlibora, Saraipather,Kondoli, Bindura, Paraiguri, Middaimargaon, Hariamukh. In

other villages, the value of arsenic ranges from 0 to 5 ppb. The surface water samples values of Arsenic

range from 0 to 5 ppb. The high arsenic values occurring as zones were transferred over the geological

map shows that most of the high values occur within the Newer alluvium sediments of Barpeta and Hauli

Formations. Older alluvium sediments are devoid of arsenic contamination thus having fresh water.

30

Mission–V : HUMAN RESOURCES DEVELOPMENT

Month Title of the course

conducted

Location of

training

Duration

Of

training

No of

Participant

Remark

April,13 36th OCG, Batch-

F

FTC-

Aizwal/RTI-

Shillong

30 days 27 Successfully conducted

June,13 36th OCG, Batch-

G

FTC-

Aizwal/RTI-

Shillong

30 days 25 Successfully conducted

July,13 36th OCG, Batch-

H

FTC-

Aizwal/RTI-

Shillong

30 days 26 Successfully conducted

Aug,13 Capsule course on

Chemical analysis

RTI,

Shillong

6 days

19.08.13

to

24.08.13

9 4-Officers from DGM, Sikkim

could not attend due to

Gorkhaland-Darjilling strike.

Conducted suceesfully and

very good to excellent

feedback given by traine

officers and course report

uploaded in portal.

Sept,13 Refresher course

on Petrology

Training

RTI,

Shillong

12 days

26.8.13 to

6.9.13

15 Conducted suceesfully and

very good to excellent

feedback given by traine

officers and course report

uploaded in portal.

Oct,13 Computer

application

RTI,

Shillong

6 days

From

16.10.13

to

24.10.13

Total -19,

SU.Assam-3,

SU.Tripura-2

SU.Nagaland-1

Su.Meghalaya-

13.

Conducted

refresher Training course on

computer application GSI,NER

Oct,13 Guest Lectures

during vigilance

awareness week

on “Promoting

Good Governance

–Positive

Contribution of

Vigilance”

RTI,

Shillong

1 day

29.10.13

Total-70

GSI,NER,

Shillong

Lectured delivered by

shri.G.H.P.Raju,IPS.

Inspector General of Police,

Govt of Meghalaya.

Jan/Feb,

14

Field workshop –

cum training on

active fault

mapping

GSI,

Guwahati

6 days

28.1.14 -

2.2.14

15

DGM-3;

Meghalaya-1,

Nagaland-2.

NEHU-2,

GSI-10,

SU-ASSAM-3,

SU-

ARUNCHAL

PRADSH-2

SU-SIKKIM-2

NER,

SHILLONG-1,

CR,NAGPUR-

1,

Conducted suceesfully and

very good to excellent

feedback given by traine

officers and course report

uploaded in portal.

31

WR, JAIPUR-1

Jan,14 37th OCG, Batch-

G

FTC-

Aizwal/RTI-

Shillong

30 days 27 Successfully conducted

Feb,14 Management

Training Course

for JAG and Sr.

STS level officers

of Geological

Survey of India

and Gr.A officer

of DGM’s of

NER.

AASC,

Guwahati

Govt Of Assam

10.2.14-

14.2.14

20 Differed due to less number of

nominations received (only 5 )

and fresh application has

submitted to the DG,GSI

through proper channel for

financial approval of 2.4 lakh.

Mar,14 Landslide Hazard

Zonation and

Disaster

Management for

Geologist of

DGM and GSI

Officers, NER, at

GSI, Gangtok,

Sikkim

GSI

Sikkim

7 days

24.3.14-

30-3-14

15 Training on LHZ has

announced and uploaded in

portal to be conducted at

Gangtok in last week of March,

14.

STSS : MODERNISATION, ASSETS PROCUREMENT & MANAGEMENT

Chemical Lab:

Sl. NO. Instruments Description

1 XRF Analysis of Package ‘A’ of NGCM samples and Non-NGCM samples

2 AAS Flame Analysis of Package ‘C’ of NGCM samples and Non-NGCM samples

3 AAS FIAS Analysis of Package ‘D’ of NGCM samples and Non-NGCM samples

4 Ion Analyser Analysis of Package ‘E’ of NGCM samples and Non-NGCM samples

5 D.M.A Analysis of Package G of NGCM and Non-NGCM samples

Output

October 2012 to Dec 2012 2204 samples with 17785 determination Norms Achieved

January 2013 to March 2013 3792 samples with 39,346 determination Norms Achieved

April 2013 to June 2013 3152 samples with 37,387 determination Norms Achieved

July 2013 to September 2013 3127 samples with 26,707 determination Norms Achieved

October 2013 to December 2013 2271 samples with 19,732 determination Norms Achieved

January 2014 to March 2014 2706 samples with 27,730 determination Norms Achieved

Note : Above output includes analysis of NGCM & Non-NGCM Samples

32

AMC.

INSTRUMENTS PERIOD NO. OF VISITS AMOUNTS

(Rs.)

XRF

(CAMC)

01.11.2013 to 31.10.2014 2 Rs. 11,23,600/-

AAS (P.E.-100).AMC 01.07.2013 to 30.06.2014 2 Rs. 98,876/-

AAS (AA-240 DUO) CAMC. 01.02.2014 to 31.01.2015 2 Rs. 2,37,040/-

UPS for the above Instruments 01.10.2013 to 30.09.2014 On Call No. limit Rs. 80,023/-

DMA (AMC) 01.12.2013 to 30.11.2014 2 Rs. 98,876/-

Budget

2013 - 2014 97 Lakhs

Petrology Lab: Laboratory Infrastructure-Items and Output

EQUIPMENT/ITEM PROCURED FROM JANUARY, 2014 TO MARCH, 2014

Sl.

No.

Name of Item Qnty Price Date of received

1. Digital Camera (Sony Model-

DSC-HX50)

10 nos. 22,790/- each 31-3-2014

2. GPS (Etrex-30) 10 nos. 15,900/- each 31-3-2014

3. Web Camera (Model C920)

Logitech

6 nos. 7,250/- each 28.3.2014

SECTION CUTTING

Sl.

No

Name of Item Qnty Price Date of

received

Remarks

1. Semi Automatic Machine

for thin sections

preparation.

1 no. 65, 873/- 11-11-2013 New machine has been

installed and in used.

2. Single Disc grinding / rock

polishing machine

1 set. 65,873/- 7-2-2014 -do-

3. Heater – 2KW 1 no. 3350/- 21-3-2014 -do-

4. Blower – 2KW 1 no. 2130/- -do- -do-

5. Geyser- 3ltr 1 no. 3430/- -do- -do-

6. Portable rock cutting

machine

1 no. 5900/- 06-02-2014 -do-

SURVEY EQUIPTMENTS

Sl.

No.

Name of Item Qnty Price Date of received

1. Rechargeable Battery BDC-70 5 nos. 19, 000/- each 19-3-2014

2. Plumbob 5 nos. 150/- each 28-3-2014

3. Survey Umbrella 10 nos. 1400/- each -do-

4. Levelling Staff 10 nos. 1300/- each -do-

33

FIELD ITEMS ISSUED TO OFFICERS IN SHILLONG

Sl.

No.

Division/Project Digital

Camera

Brunton

Compass

GPS Geological

Hammer

Pocket

Lens

Magnet Streak

Plate

Steel

Tape

1 NGCM 3

2. STM

3. MMIP

4. Geophysics

5. Earthquake

Geology

6. Publication

7. Engg. Geology 1 1

8. Palaeontology 1 1 1 1 1 1

9. Chemical

10. Petrology 2 1 1 1

11. RSAS

12. Engg. Divn

13. PSS

14. LHZP 1 1 1 1

15. RMH-I & II 1

Total 4 4 7 3 2 1 Nil Nil

LABORATORY INFRASTRUCTURE: ITEMS AND OUTPUT

Sl.

No

Name of the equipment Utility of the

equipment

AMC Output

(Jan 14 to Mar'14)

1. Leitz Orthoplan Polarising

microscope

Thin section and

polished section

studies (transmitted

and reflected light)

AMC with M/s

Star

Instrumentation

Kolkata

205 nos. PS were studied

by respective project

officers pertaining to FSP

items of GSI, NER.

Petrological

supports/guidance was

provided as and when

required.

Gem stone Study :Nil.

2. Carl Zeisss JENA

Polarising microscope

Petrographic studies

(transmitted light)

-do-

3. Stereozoom Carl Zeiss

Microscope

Thin section and

grain studies

-do-

4. Leical Stereozoom

(S8APO)

Thin section and

grain studies

-do-

5. Reichard Microscope Petrographic studies

(transmitted light)

-do-

6. * Optigem-4 Trinocular

Microscope

Gem Testing - Nil.

7 *Mettlers Toledo Balance

AB 204-S

Specific gravity

Determination (Gem

Testing)

- Nil.

8. *Refractometer (KRUSS) Refractive Index

determination (Gem

Testing)

- Nil.

9. *U.V. Lamp (KRUSS) Susceptibility for

ultraviolet light

(Gem Testing)

- Nil.

10. *Spectroscope (KRUSS) Optical

determination (Gem

Testing)

- Nil.

11. *Seive shaker equipment Sand analyses

(Grain size analysis)

- Nil.

34

12. *Hot air oven For drying samples. - Nil.

13. *Franz Isodynamic

separator

Mineral separation - Nil.

*These are required for Gem Testing & mineral separation

Mineral Physics:

Sl.No. Instrument Description

1 XRD PW-1730 The instrument is obsolete and not in working condition. The spare parts

are not available.

Output:

During FS 2013 – 2014 XRD unit and its accessories are shifted to Rynjah, Shillong and

establishment of laboratory in new building in progress.

Geodata lab:

Geodata Division, Shillong has been a facilitation centre for extending computer hardware and software,

technical knowhow and infrastructure support to the technical divisions and administrative sections of

offices in RHQ and State Units of NER. At present the Geodata Laboratory is an IT infrastructure with

following systems and support:

Systems &

Support

Nos Output (Actual / Normal)

Desktop

Computers

9 These computers are support to the officers and staff and to guide upon

them on facing problem in taking up transactional application on GSI

Portal, i.e., FSPIMS, HRMIS, CLAIM etc. modules, besides portal

administration by Geodata Personnel/s. Printing and Scanning, etc.

capture, manipulate and maintain the regional spatial repository. Some of

these are extended as support for taking up Trainings (to RTI,

Workshops/Seminars etc.). A few of them are dedicated system carry out

FSP items like that of ‘Geoinformatics’.

A 0 Scanner 1 The divisions, projects and Administrative Sections of GSI, NER, Shillong

and State units have been utilising this support for scanning of A0 size

maps and documents for various purposes.

A 0 Plotter 1 The divisions and projects of GSI, NER, Shillong and State units have

been utilising this support for plotting large size compositions, like 1:50K

geological maps, DRM, GQM etc.

UPS 11 These are to supply uninterrupted power to the PC’s. During the period

(January 2014 to March 2014) office premise faced regular load shading

for longer durations and 2 to three cuts during office hours. The UPS

support was strengthened by 8 nos. new batteries for storage and supply in

the periods of cuts.

A 4 Scanner 1 This is to take up scanning of A4 size maps and documents.

Colour Laser

Printer (A3)

1 This is to support printing of official documents like that of colour maps

for Field Season Proposals, Unpublished Progress Reports, Briefing Books

and others documents on A3 & A4 size dimensions generated from

divisions and projects of GSI, NER, Shillong.

Colour Laser

Printer (A4)

1 For printing of colour maps for FSP, Progress reports and other official

documents.

Mono Laser

Printers (A4)

3

(+1)

For printing of the official documents and reports generated by the

divisions on the FSP work carried out for the previous season/s.

Colour Digital

Copier

1 For coloured Xeroxing required by different divisions.

LAN Switches

and Router

7 For local area network and GSI WAN

Arc GIS 10 2 For preparation of 1:50k maps and portal related works (1 license for

35

Shillong and 1 license for Itanagar). The GIS runs by reading on line

license from CHQ resident server.

Surfer 8 1 For preparation of maps.

Grapher 9.0 - The software is a support to carry out technical work.

IGPET 2010 – The software is a support to carry out a specific technical work.

Besides, the systems & support - as above, Geodata Laboratory extends infrastructure and

personnel support in carrying out various office work and technical work on digital concepts, as desired

time to time by the administration, RTI and divisions. The division is the centre for personnel support in

MAP items of FSPs and maintenance of regional spatial-data repository. The spatial data from the

repository is over plotted to compose maps for their delivery. Majority of the purchase of IT products,

i.e., Hardware and software have been carried out by the APM&D of the Region on the specifications

prescribed by the Geodata Division, on received requisitions from and requirements of divisions and

sections.

The www.portal.gsi.gov.in is the portal for the Geological Survey of India. This web based IT

development is catered through centralised servers at CHQ, Kolkata. The LAN or WAN/ WiFi connected

systems at RHQ and State Units in NER operate on BSNL Telephone Line (WWW) / Lease Line to run

the Portal. Like the other region, the desktops and systems are procured at / supplied to Guwahati,

Gangtok, Itanagar, Dimapur, Agartala - the HQs for SUs , and Shillong - the RHQ, in NER. Barring the

stand alone systems to carry out dedicated Office and Technical work, the other systems are on the Net.

Majority of these systems have foundation on Windows XP operating system switching to new supplies

with Windows 7 in light of migration from IPv4 to IPv6 address system on the NET. WAN / Lease Line

is in effect in the premises of NER from February 2009.

STATUS OF NETWORKING & IMPLIMENTATION OF PORTAL AT GSI, NER

Portal Phase I (Installation of LAN at RHQ and SUs):

Infrastructure: Installation of LAN at RHQ: GSI, NER, Shillong is operating from several rented

buildings at Shillong. Local Area Networking exist at three premises viz., Shylla building, Kumud villa

and building at Motinagar. Regional headquarters of NER, TCD, TCS and LHZP is functional from

Shylla building. Where as Petrology, Palaeontology, Publication, M&C and Chemical Divisions with

their laboratories form a clusture about Kumud Villa. With its laboratory of the Geodata division and

Administration run from a building located at Motinagar.

Lease line runs for portal access into the networks on upgraded 1 MBPS bandwidth. Internet connection

to the office premises frequently marred by interruptions or out of the reach situations on the networks in

Shillong which are on BSNL broadband and WiFi devices.

LAN infrastructure is not-feasible in buildings other than the stated three LAN net workings.

Recently, Wi-Fi access points have been put on broadband line to these buildings. This gives a lean

access to portal and internet in these deprived buildings. Since second quarter of 2013 offices of Mission-

I, II, III & IV and RTI have occupied two rented buildings close to Kumudvilla. These buildings are in

need to develop networking so that the divisions have the access to the portal. WiFi Access points on

BSNL Telephone Lines have been installed in these two buildings (Mission-I, II and Mission-III & IV) as

a temporary measure to extend the internet support to the DDGs (Missions, recently posted to NER). The

WiFi Systems started their operation in the last two quarters.

Portal Applications: All the officers and staff of State Units and RHQ have been given training on the

various transactional applications, in phases, on GSI Portal and modules therein.

With acquisition of approval on FSP items, the divisional heads start loading relevant items to GSI Portal.

Many a times, they come across problem in loading. On reporting the faced problem the Geodata tries to

resolve, at its laboratory, but at times when Geodata identifies some complex issues in process, it get this

rectified through the Help Desk at CHQ.

Officers and staff, on policy based - for short period (2 to 3 years) of time, are posted in NER. In

coming into and out going from the region on transfers, is normal phenomenon. A post holder leaves or

joins, affect the chain of reciprocation in between reporting to reported officers / officials. This gets

reflected into the HRMIS (organogram) of the Portal. In lack of a functional e-governance cell within the

region, re-smoothening of the reciprocation chains are being carried out at the Geodata Division.

36

In the year 2013-14, new induction of the DDGs for State Units and Missions and redistribution of

charge, so the chain smoothening been carried out in NER as an extra load on the Geodata. CHQ has

designed new sites into the Portal on creation and posting of the SU and RMH level HAG officers.

Migration of officials from the existed chains, which has become a history, to the newly inducted sites, is

now taking place, using a portal role of administrator at the RHQ (Geodata). The FSP items (Project

mode) for 2012-13 are approved on their links to the sites now become history (Project mode) but the

reports under gone their submission on the carried out work for the seasons have been loading on the

historical sites. Many a times, the post holders at these old sites, are retired, transferred, re-deployed to

other sites and posted to an inducted post for which intervening sites are inducted. This posed a complex

situation, being tackled in perusing cases to CHQ.

B.Portal Phase II:

Infrastructure:

1. Installation of LAN/WAN at SUs: All the State Units of NER, viz. Guwahati, Arunachal Pradesh,

Agartala, Dimapur and Gangtok are connected through intranet using MPLS from BSNL.

2. The service of BSNL (leased line provider for MPLS connectivity) is in utilisation at Guwahati,

Agartala, Itanagar, Gangtok and Shillong. This service has bleak consistency; thereby networks provide

off and on intermittent / frequently disrupted sessions on internet, so the portal access. Comprehensive

AMC of LAN/WAN equipment is awarded to M/s Hue Service Pvt. Ltd, Guwahati.

3. IP phones installed at all locations and video conferencing installed at RHQ.

The table below gives the data of routers, switches and ports to support the Networking in different

premises of in RHQ and SUs of NER.

SHILLONG

ITANAGAR AGARTALA GUWAHATI DIMAPUR GANGTOK Shylla Kumudvilla Motinagar

LAN Port/

(Quantity) 41/(1)

8+12+24=

44/(4) 48/(1) 24/(1) 24/(1) 24/1 8/1 24/1

Router /

Switches 1/1 1/6 1/1 1 1 1/1 1/1 1/1

IP Phones 6 6 4 6 2 2 1 2

4. IT infrastructure, videoconferencing & IP telephony: MLLN link is commissioned at Shylla Building,

Kumud Villa Complex and Motinagar Building in Shillong and at Guwahati, Gangtok, Dimapur and at

Itanagar offices. Video conferencing unit is installed at Dy.D.G office, Shylla building, Shillong. The

bandwidth for the link at Shylla building, Kumud Villa complex and Motinagar office was upgraded from

128 kbps to 1 Mbps now. IP telephones are installed where MLLN link is commissioned and are being

used for inter office communication.

5. GSI portal is accessible through WAN at Shillong (Shylla bldg, Kumud Villa complex and Motinagar

bldg.), Guwahati, Itanagar, Gangtok and Dimapur offices.

6. Connectivity issue/Networking and progress: GSI, Itanagar is under pursuance with BSNL authorities

and CHQ for upgrading the bandwidth for GSI Portal connectivity.

Upgradation of Network 2013:

A project titled “Replacement, upgradation and augmentation of networking devices at different offices of

GSI” has been taken up by CHQ. ‘Nodal Officer’ for each and every independently located LAN were

identified. Devices for replacement/upgradation of existing Network Devices were received through HCL

Comnet and taken into Stock. Installation and temporary configuration attempts were made in Shylla bldg

and Motinagar bldg.

C. Uploading of data and Portal Applications:

1.Uploading of 1:50K maps to GSI Portal: New set of layers after achieving (in FS 2013-14) inter-sheet

feature edge-matching, standardisation of data in stratigraphic fields ( Age, Supergroup, Group,

Formation, Member, Lithology) and assigning a patterned ‘Geometry_id’ values to the spatial extents to

each dimensional size of toposheet as unit have been re-loaded, during the quarter, replacing the place

holding immature layers on Spatial Data Warehouse at CHQ in ‘Map50k Domain’. This is besides the

metadata of the extents have been uploaded in GSI portal.

37

D. Transactional Applications: Transactional Applications on HRMIS, Payroll, FSPMIS and Claims

Modules are operational and are being used by various users in NER.

i) HRMIS: Four new MTS staff was inducted in RHQ, Shillong and their HRMIS data were uploaded

Data of all employees of NER uploaded and is being updated regularly.

ii) FSPMIS: Geodata extended its help to officers of different Projects/Divisions/ State units for

uploading FSP programs and FSP Technical Reports through FSPMIS.

iii) PAYROLL: Pay is being processed through portal at RHQ, Shillong, SU: Guwahati and SU:

Dimapur. Payroll data entered at SU: Agartala.

iv) TOUR and LEAVE: Applications of all officers & employees are being submitted through portal.

v) CLAIMS: RCA/NRCA is being processed by Accounts Sections on portal at RHQ, Shillong. Geodata

helps the Accounts Sections Staff in case of any problem faced by them.

The current usage is limited due to poor or intermittent connectivity and limited awareness about the

usage of transactional modules. Efforts are being made to resolve the problems of intermittent WAN

connectivity and poor services by providing alternate resources.

Other services rendered by Geodata division

Geodata provides software support, scanning on A0 size, other computer related services and

Plotting and printing of documents for the officers of divisions of GSI, NER. Besides, Geodata maintains

the stock registers for the computer hardware and software. Geodata also has a role extended towards

maintenance of hardware and software in the Divisions on AMC.

Geodata extend its service as a collaborator in the training course on GSI Portal applications to the

users in the usage of Transactional modules, conducted by RTI, NER. The division extend its expertise in

acquisition of map data into digital files to the projects of Regional Map & Cartography Division, so the

personnel have been instrumental in capture of 1:50,000 maps generated in process of the drive for

Systematic Geological Mapping and their loading to Spatial Data Warehouse located at CHQ. This digital

dataset is constantly under revision for a better collation, compilation across the toposheet boundaries,

query effective standard values, validated features and authentication of the digital layers to that of

physical maps and replacement of repository at the CHQ based SDW. Geodata Division maintains the

regional repository and versions of revised repository of the dataset.

In the start of a FS year the personnel contact the Regional Geodata for a base map which could help

them to understand geological setup of the area of their field for Thematic Mapping / mineral

investigation / basic data for DRM or similar compositions. The Geodata compose the maps using the

layers exist in the regional repository it has and deliver them promptly.

List of all major Instruments/equipment:

Sl.N

o.

Name of Instruments Quantity Usefulness Remarks

1. CG-5 Gravitymeter 1 no. Gravity Survey Functional.

2. ENVI MAG (SCINTREX)Total

field Magnetometer

1 no. Magnetic Survey Functional.

3. GEM Systems(Model GSM-19T)

Total field Magnetometer

2 nos. Magnetic Survey Functional.

4. TSQ-3 Transmitters 2 nos. IP/Resistivity

Survey

Functional.

5. IPR-10A Receiver 1 no. IP/Resistivity

Survey

Functional.

6. RDC-10 Receiver 1 no. Resistivity Survey Functional.

7. CG-3 Gravitymeter 1 no. Gravity Survey Obsolete.

Needs Upgradation.

38

Laboratory Infrastructure : Items and Output.

Sl.No. Instruments Description

1. CG-5 Gravitymeter Gravity Data Acquisition

2. ENVI MAG Total field Magnetometer Total field Magnetic data Acquisition

3. GSM-19T Total field Magnetometer Total field Magnetic data Acquisition

4. DC Resistivity Meter unit , Model SSR-

MP1

Resistivity Survey work

5. Altus Digital Micro Earthquake Recorder

(DMEQ) (Nanometrics)

MEQ Surveys/Seismic Microzonation studies

Output:

During FS 2013-

14

Deployed in “Gravity-Magnetic mapping in

parts of West Khasi Hills District,

Meghalaya”. Mission-IA, GPM-

/NER/RHQ/2013/014.

Instruments were serviced and

thoroughly tested and deployed in

field.

During FS 2013-

14

Deployed in “Titaniferous- Vanadiferous

Magnetic around Rambrai, West Khasi Hills

district, Meghalaya (M-II)”,

ME/F/NER/SME/2012/023

Instruments were serviced and

thoroughly tested and deployed in

field.

During FS 2013-

14

Deployed in “Magnetic Survey for Chromite

Bearing Ultramafics Bodies in Mantum

ching block, Chandel District, Manipur”.

(M-IIA) .

GPS-/NER/RHQ/2013/021.

Instruments were serviced and

thoroughly tested and deployed in

field.

During FS 2013-

14

Deployed in “Seismic and Landslide

Hazards Assessment of Aizawl town ,

Mizoram”. (M-IV)

SEI-/NER/RHQ/2012/038.

Instruments were serviced and

thoroughly tested and deployed in

field.

Newly procured Resistivity meter

SSR-MP1 unit is also field tested.

AMC: AMC for upgradation, Maintenance of Geosoft licence is under process.

Procurement / Modernisation:

1. DC Resistivity meter Unit(SSR-MP-1) 1no. Procured and deployed in the field.

2. Digital Micro earthquake recorders 5nos. Procured and Installed.

Technical Consultancy Services

Sponsoring Agencies namely Brahmaputra Board, MeECL, NEEPCO, NF Railway, CWC,

NHPC etc for current project works were interacted for resource generation and recovery of service tax.

The cost estimate for raising the bills in respect of geotechnical investigation item taken up during FS

2012-13 has been carried out. In addition, bills pertaining to petrological and chemical analysis were

computed and raised as and when samples were received from the party. As a government policy, the

pricing of the reports of restricted area were carried out as and when the demand was placed by the user

agencies. Besides these bills, subsequent reminders were sent to the sponsoring agencies for the payment

of pending service taxes particularly for the period between 2000 and 2005.

The internal resource generated in FS 2013-14 is given in following table upto March, 2014:

Internal Resource: Rs.5,40,131/- (Rupees Five lacs forty thousand one hundred and thirty

one only)

Service Tax: Rs.30,656/- (Rupees Thirty lac seventy six hundred and fifty six only)

Pending Service: Tax

(2000-05)

Rs.23,406/- (Rupees Twenty three thousand four hundred and six only)

Amount Received: Rs. 5,94,193/- (Rupees Five five lacs ninety four thousand one hundred

and ninety three only)

39

5. FINANCIAL PERFORMANCE

Financial outlay and expenditure during XI plan period has been given in Annexure -3A. Scheme-wise,

quarter-wise distribution of approved plan funds and actual expenditure during 2013-14 (2ND

quarter) are

given in Anneure-3b &3C.

6. MISSION WISE RCA EXPENDITURE

The details of RCA expenditure in different projects visa-vis targets and achievements of FS 2013-

14 are given in annexure-04.

7. SCIENTIFIC WORKSHOPS / MEETINGS / SEMINARS / SYMPOSIUM, EXHIBITIONS

ETC., ORGANISED / PARTICIPATED.

Stage Review Committee was held on the 3rd

& 4th October, 2013, the 8

th meeting to review the

Progress of Ongoing Mineral Development Projects was held at GSI, NER, Shillong on the 21st Nov,

2013 and 9th Central Geological Programming Board Committee VIII on the Geology and Mineral

Resources of North Eastern Region was held on the 29th November, 2013. SGPB/RAC meetings for

different states of NER were held from time to time the detail of which is given in annexure-11.

8.HRD, ESTABLISHMENT, PAYROLL, HRMIS, E-SERVICE BOOK, ETC.

Statement on RTI Act : 31 cases received, and all cases have been disposed and no case is pending

Statement on Grievance cases : No case is pending on Grievance.

Statement on Vigilance cases : No case is pending on Vigilance.

Statement of pending VIP reference cases in the Region : Nil

The information on Employment position in the Region is given in Annexure – 12. The HRMIS details in

respect of Group A, B & C have already been uploaded to GSI Portal.

9. VEHICLES & TRANSPORT INFRASTRUCTURE INCLUDING OUTSOURCING AND AGE

OF VEHICLES, VEHICLES MIS.

The required information is given in the attached Annexure – 13.

10. MODERNIZATION

As a part of the efforts for meeting emerging challenges, GSI is constantly upgrading its

technology both for field and laboratory equipments and efforts are being made to modernize the

Geodata, Petrology and Chemical Laboratories

11. DRILLING INFRASTRURE

Status of drilling activities, performance and cost effectiveness: The status of drilling in NER during FS

2013-14 is given in Annexure – 15A.

Efforts for Modernizing Drilling Machinery: Indents are being prepared for replacement of old

machineries and accessories keeping in view the type of drilling assignment to be taken up in the near

future.

12. OUTSOURCING OF ROUTINE SERVICES (HOUSKEEPING, SECURITY, GARDEN,

ETC.)

The housekeeping of GSI offices in NER is being done by the Departmental personnel. Security

at GSI, Itanagar office is outsourced. Contractural workers are employed for durwan duty, other office

work as and when required.

13. OTHER ACTIVITIES

Details of Museums and curatorial activities in the Region and operational units:

Nodal officer with Museum committee visited Don Bosco Museum for Surveying, which would provide

guidance to establish geological museum in NER, Shillong. Other procedures of sample selection/

collection and arrangement for display etc are in progress.

Two Museums each in Petrology and Palaeontology Division, RHQ, Shillong are being maintained

by respective units. One Rock Garden, GSI, Itanagar is being maintained by SU: Arunachal Pradesh, GSI,

Itanagar. Nodal Officers in all State Units have been nominated for maintenance/upkeep for museum at

40

state units and the of newly established geological museum of NER, Shillong in Petrology Division,

NCERT building.

Library: Library facilities are available in the Publication Division, RHQ, Shillong and in all the State

Units of North Eastern Region.

Core Library: The Cores of Litang Valley Limestone investigation, Jaintia Hills district, Meghalaya and

Mawmaram basemetal investigation, East Khasi hills district have been skeletonised and preserved at

Shillong. Core Library is The Regional Core Library of GSI, NER is functional at Guwahati.

14. SPECIAL SCIENTIFIC STUDY: NA

15. PERCEPTION MANAGEMENT ACTIVIES IN NER

RTI, Shillong organized training for Officers of State DGMs of North Eastern Region. (Photographs of

training given in field, lab and lectures in classroom are in back page).

16. SAVOTTAM: Service Quality Improvement initiative was taken & declared DDG & RMH as Nodal

Officer for Quality Management. They will look after implementation of an appropriate Service Quality

Management System i.e - Successful implementation of Citizen’s Charters, identification of services

rendered, the quality of service delivery process, its control and delivery requirements. NER also has a

good Public Grievance Redress Mechanism headed by Joint Director (P&A).

17. CONSOLIDATED LIST OF GROUP A & B OFFICERS IN NER (GAZETTED)

Please see attached Annexure – 17.

41

ANNEXURE-1A

MAJOR MINERALS RESOURCES [UNDER VARIOUS UNFC CATEGORIES] ESTIMATED

BY THE REGION, SHOWING STATE-WISE FIVE-YEARLY INCREMENT, FOR THE LAST

15 YEARS.

ANNEXURE-1B

NATIONAL MINERAL INVENTORY

NO. OF REPORTS CONVERTED AS PER UNFC COMPLIANCE

Nodal Officer: Shri Brij Kumar, DDG & RMH, GSI, NER, Shillong.

Upto December 2010 Upto March 2012 Upto March 2013

Meghalaya 2004 – 05 onwards – 08 nos. Completed

Pre-F.S. 2004-05 – 22 nos. Completed

Arunachal Pradesh 2004 – 05 onwards – Nil Nil

Pre-F.S. 2004-05 – 05 nos. Completed

Agartala 2004 – 05 onwards – Nil Nil

Pre-F.S. 2004-05 – 18 nos. Completed

Guwahati 2004 – 05 onwards – Nil Nil

Pre-F.S. 2004-05 – 06 nos. Completed

Sikkim 2004 – 05 onwards – Nil Nil

Pre-F.S. 2004-05 – 04 nos. Completed

Dimapur 2004 – 05 onwards – Nil Nil

Pre-F.S. 2004-05 – 05 nos. Completed

COMMODITY/

MINERAL

STATE 1995 -

2000

2001-

2005

2005-

2007

2010-

2012

2012-

2013

2013-

2014

Limestone Meghalaya 3062.71mt

(332)

2678.24mt.

(332) 366.62mt

(333)

261.46mt

(333)

177.83mt

(333)

42

ANNEXURE-2A

ACTIVITY DOMAIN PERTAINING TO MISSION I & II OF THE REGION AND ACHIEVEMENTS [FSP RELATED ITEMS] DURING

THE XII PLAN PERIOD [2012-17] (AS ON 31.03.2014)

Sl.

No

Major Activity area Programme

Target

F.S. 2012-13

Achievement of

F.S. 2012-13

Programme

Target

F.S. 2013-14

Achievement of

F.S. 2013-14

Programme

Target

F.S. 2014-15

Achievement of

F.S. 2014-15

Programme

Target

F.S. 2015-16

Achievement of

F.S. 2015-16

I. Survey and Mapping

a) Ground Survey

i) Special Thematic

Mapping

(sq. km) (1:25000)

3520 3594.5 3295 3277.5 2750 + 25 L

Km T.M.

ia) Systematic Geological

Mapping (sq. km)

(1:50000)

1280 1289 2640 2640 660

ii) Geochemical mapping

(sq. km) 3892 3697 4850 4948 7600

iii) Geophysical Mapping

(sq. km) 700 700 1750 1400 1000

II. Mineral Exploration

i) Large Scale Mapping

(sq. km.) (1:12,500)

332 341 369.5 395.4

407 sq km

LSM and 50 L

km

Geophysical

survey

ia) Reconnoitary

geological traverse

mapping

(sq. km.) (1:50000)

150 150 150 150 Nil

ii) Detailed Mapping

(sq. km.)

(1:5000/2000)

5 5 8.5 8.5 09.5

iii) Drilling (metre) (M-

IIA) 1575 1418.65* 1600

364.85 & 750.6

(extended item) 2200

Drilling (metre) (M-

IIB) 800 637.75* 900 508.1 900

Drilling extended in FS 2014-15 (as per decission of Term Review)

43

ANNEXURE-2B

FSP ROLLING PLAN FOR F.S. 2013-14 & 2014-15

MISSION: I

SL.

NO.

FSP CODE TITLE OF THE ITEM TOPOSHEET NO PERSONNEL F.S. TARGET

(2013-14)

1 GM/NER/SAS/2012/003 SYSTEMATIC GEOLOGICAL MAPPING ON

1:50,000 SCALE IN TOPOSHEET NO. 78 J/9 &

J/10 IN GOALPARA DISTRICT, ASSAM

78 J/9 & 10 Varun Vara &

Yhunyelo Tep

2013-

14

865 sq.km

2 GM/NER/SAS/2013/001 SYSTEMATIC GEOLOGICAL MAPPING ON

1:50,000 SCALE IN TOPOSHEET NO. 78 J/1, 5 &

13, 78 N/1, 5, 9 & 13 IN KAMRUP, GOALPARA

AND DARRANG DISTRICT, ASSAM

78 J/1, 5 & 13; 78

N/1, 5, 9 & 13

Rajkumar Tapon

Kumar & Satrughan

Majhi

2013-

14

955 sq.km

3 GM/NER/SMN/2013/002 SYSTEMATIC GEOLOIGICAL MAPPING IN

PARTS OF PEREN, DIMAPUR, KIPHIRE,

KOHIMA AND PHEK DISTRICTS, NAGALAND

ON 1:50,000 SCALE

83 G/6, 7, 10, 12, 13,

14; 83 K/1, 10, 14; 83

O/1

B.Behera(

transferred), C.

Yanthan & T. S.

Kom

2013-

15

360 sq.km

4 GM/NER/SMN/2013/003 SYSTEMATIC GEOLOIGICAL MAPPING IN

PARTS OF CHURACHANDPUR DISTRICT,

MANIPUR ON 1:50,000 SCALE

83 H/12 P. Enos Ezung, V.

Zaphu, 1G & 1G

from DGM, Manipur

2013-

14

460 sq.km

5 STM/NER/SAP/2012/001 SPECIALISED THEMATIC MAPPING IN

PARTS OF ANJAW DISTRICT, ARUNACHAL

PRADESH

91 D/12 Rupesh Kumar &

Sebabrata Das

2012-

14

220 sq.km

6 STM/NER/SAP/2012/002 SPECIALISED THEMATIC MAPPING FOR

STUDY OF EVOLUTION OF GONDWANA

AND SIWALIK GROUPS IN SIANG RIVER

BASINS IN PARTS OF WEST SIANG AND

EAST SIANG DISTRICTS, ARUNACHAL

PRADESH

83 I/5, 9, 13, 14 B.N.Mahanta

(transferred to T.C

Div), B. R. Syngai(

Transferred to GSI,

Shillong), Raman

Kumar, K. Sekhose

& V. Vitso

2012-

14

330 sq.km

7 STM/NER/SAP/2013/004 SPECIALISED THEMATIC MAPPING IN

TERTIARY COAL BELT IN CHANGLANG

AND TIRAP DISTRICTS, ARUNACHAL

PRADESH

92 A/3, 7 & 11 Amit Kumar, ,

Ranjita

Bhattarcharjee,

Diethovilie Pieru,

Welhitshou Mero, V

K Bendre

(APMDTCL) & A S

2013-

15

110 sq.km

44

Rawat (DGM, AP)

8 STM/NER/SMN/2013/005 SPECIALISED THEMATIC MAPPING OF

OPHIOLITE SUITE OF ROCKS OF MANIPUR

BETWEEN NINGTHI TO NUNGBI KHULLEN,

UKHRUL DISTRICT, MANIPUR

83 K/8; 83 L/5 J.K. Angami,

K.Theoneou &1G

(DGM, MANIPUR)

2013-

15

220 sq.km

9 STM/NER/SAS/2012/077 SPECIALIZED THEMATIC MAPPING TO

DECIPHER LITHOLOGICAL SEQUENCE AND

STRUCTURAL SET-UP IN WESTERN PART OF

BATGURI, GOALPARA AND BONGAIGAON

DISTRICTS, ASSAM

78 /11 B.Baruah, Ramesh

Chandra Kishan &

Parusharama

Gangaikoppa

2013-

14

300 sq.km

10 STM/NER/SME/2012/006 SPECIALISED THEMATIC MAPPING OF THE

GNEISS AND GRANITOIDS TO DECIPGER

THEIR STRATIGRAPHIC RELATION WITH

THE SHILLONG GROUP AND ASSOCIATED

MINERALISATION BETWEEN NONGPOH,

JIRANG AND PATHARKHMAH, RI-BHOI

DISTRICT, MEGHALAYA

78 N/16; 78 O/9 & 13 Balbir Singh,

Vekhoto Shijoh &

Imrongtola Pongen

2012-

14

450 sq.km

11 STM/NER/SME/2012/007 SPECIALISED THEMATIC MAPPING TO

CHARACTERISE THE ANORTHOSITE-

MANGERITE- CHARNOCKITE-GRANITOID

(AMCG) SUITE OF ROCKS WITH SPECIAL

EMPHASIS ON TECTONOMAGMATIC

HISTORY AND MUTUAL RELATIONSHIPS OF

ROCKS BETWEEN RANGBLANG AND

MANAD MAWBIDONG AREAS, WEST KHASI

HILLS DISTRICT, MEGHALAYA

78 O/7 & 11 S.R. Mishra &

Lalneo Haokip

2012-

14

450 sq.km

12 STM/NER/SME/2012/008 SPECIALISED THEMATIC MAPPING FOR

CHARACTERISATION OF HIGH GRADE

META-SEDIMENTS, GRANULITES AND

GNEISSIC COMPLEX SOUTH OF

SONAPAHAR, WEST KHASI HILLS DISTRICT,

MEGHALAYA

78 O/2 Lalboi T. Haokip, A.

Ranjith & Shampita

Das

2012-

14

220 sq.km

13 STM/NER/SME/2013/006 SPECIALISED THEMATIC MAPPING TO

DECIPHER THE TECTONO-MAGMATIC AND

METAMORPHIC HISTORY OF THE GNEISSIC

COMPLEX, MIGMATITES AND SHILLONG

83 C/2 Sougrakpam Sujata,

Imlishila Imchen &

Avi Mero

2013-

14

330 sq.km

45

GROUP OF ROCKS, EAST KHASI HILLS AND

JAINTIA HILLS DISTRICTS, MEGHALAYA

AND MIKIR HILLS DISTRICT, ASSAM

14 STM/NER/SSK/2012/009 STUDY OF LINGTSE GNEISS IN SIKKIM

HIMALAYA FOR ELUCIDATING THE ROLE

OF PROTEROZOIC GRANITOIDS IN

HIMALAYAN OROGENY

78 A/11 & 12 Jiji Kumar S &

Hiten Kumar

Jalutharia

2012-

14

225 sq.km

15 STM/NER/STM/2013/007 SPECIALISED THEMATIC MAPPING IN

TERTIARY FOLD BELT IN PARTS OF AIZAWL

DISTRICT, MIZORAM (PARTS OF T.S. NO.

84A/14)

84 A/14 Pankaj P Vaidya &

A. Elow

2013-

14

220 sq.km

16 STM/NER/STM/2013/008 SPECIALISED THEMATIC MAPPING IN

TRIPURA-MIZORAM FOLD BELT IN PARTS

OF SOUTH TRIPURA AND DHALAI

DISTRICTS, TRIPURA

79 M/10 & 14 Omnath Saha,

Watitemsu &

Jayanta Pramanik

(P/T)

2013-

15

220 sq.km

17 GCM/NER/SAP/2013/009 GEOCHEMICAL MAPPING IN LESSER

HIMALAYA IN PARTS OF EAST SIANG

DISTRICT, ARUNACHAL PRADESH

(TOPOSHEET NOS. 82P/12 & PART OF 82P/11)

82 P/11 & 12 S. C. Keshari,

S.M.Toppo &

W.Swer(

Transferred) + D.

Gurung (Chemist)

2013-

14

800 sq.km

18 GCM/NER/SAS/2012/016 GEOCHEMICAL MAPPING IN TOPOSHEET

NO. 78 O/1 AND IN PARTS OF 78O/5 IN

GOALPARA & KAMRUP DISTRICTS, ASSAM

AND EAST GARO HILLS & WEST KHASI

HILLS DISTRICTS, MEGHALAYA

78 O/1 & 5 Amit Kumar &

Mukesh Kumar

Mishra + N.P.

Nagmote (Chemist)

2013-

14

800 sq.km

19 GCM/NER/SMN/2013/010 REGIONAL GEOCHEMICAL MAPPING IN THE

OPHIOLOIE BELT IN PARTS OF PHEK

DISTRICT, NAGALAND

83 K/10 & 14 Chubala Shijoh, V.

Savio Peter, Tokheli

Phuchu (DGM,

Nagaland) & R.

Vittal (Chemist)

2013-

14

800 sq.km

20 GCM/NER/SMN/2013/011 REGIONAL GEOCHEMICAL MAPPING IN THE

OPHIOLITE BELT IN PARTS OF

MON,TUENSANG & KIPHIRE DISTRICTS,

NAGALAND

83 N/3,4 ; 83 O/1 E. John, Keneylo

Rengma (DGM,

Nagaland) &

R. Vittal (Chemist)

2013-

15

400 sq.km

21 GCM/NER/SME/2013/012 GEOCHEMICAL MAPPING IN MEGHALAYA

GNEISSIC COMPLEX IN PARTS OF JAINTIA

AND EAST KHASI HILLS DISTRICT,

83 C/07 & 03 H. Sumar & A.S.

Bora (Chemist)

2013-

14

800 sq.km

46

MEGHALAYA (TOPOSHEET NOS. 83C/07 &

PART OF 83 C/03)

22 GCM/NER/SME/2012/014 GEOCHEMICAL MAPPING IN TOPOSHEET

NO 83C/03 IN PARTS OF EAST KHASI AND

JAINTIA HILLS DISTRICTS, MEGHALAYA

83 C/03 Ajay C Limbu &

T. Myelvaganan

(Chemist)

2012-

14

400 sq.km

23 GCM/NER/STM/2013/013 GEOCHEMICAL MAPPING IN TERTIARY

FOLD BELT OF SOUTH TRIPURA DISTRICT,

TRIPURA (IN PARTS OF T.S. NOS. 79M/12, 16

& 79N/9)

79 M/12 & 16, 79 N/9 J.M. Umlong, M.P.

Singh & Rajendra

Kumar (Chemist)

2013-

14

850 sq.km

24 GPM/NER/RHQ/2013/014 GRAVITY-MAGNETIC MAPPING IN PARTS

OF WEST KHASI HILLS DISTRICT,

MEGHALAYA

78 O/6, 7 & 8 S.M.Syiem, P.

Diwakar Reddy & 1

GP

2013-

14

1750

sq.km

25 PRS/NER/RHQ/2013/015 GEOLOGICAL MAPPING IN PARTS OF

MEGHALAYA WITH THE HELP OF REMOTE

SENSING STUDIES ON 1:50000 SCALE (9

TOPOSHEETS)

78 G/15; 78

K/3,4,8,12,16;

78O/16; C/4,8

H.K. Sahoo & S.

Sanyal( transferred)

2013-

15

900 sq.km

(modified)

MISSION: II

SL.

NO.

FSP CODE TITLE OF THE ITEM TOPOSHEET

NO

PERSONNEL F.S. TARGET

(2013-14)

1 ME/NER/SAP/2013/016 PRELIMINARY APPRAISAL OF ECONOMIC

POTENTIAL OF LIMESTONE/ DOLOMITIC

LIMESTONE IN EAST SIANG DISTRICT,

ARUNACHAL PRADESH (G4)

83 P/4 & 8 Bendangnuchit,

Rita Thurr &

V.K.Bendre

(APMDTCL)

2013-

14

LSM 75

sq.km

2 ME/NER/SAP/2013/017 PRELIMINARY ASSESSMENT FOR LIMESTONE

IN AND AROUND DABA GAMLIN, WEST SIANG

DISTRICT, ARUNACHAL PRADESH (G3)

82 L/12 Amit Kumar, P.S.

Mishra & A.K.

Singh+ 1G (DGM,

Arunachal

Pradesh)

2013-

15

LSM 50

sq.km

3 ME/PM/NER/SAP/2012/026 INVESTIGATION FOR PGE AND GOLD

MINERALIZATION IN MAFIC-ULTRAMAFIC

SUITES, ANJAW, LOHIT AND LOWER DIBANG

VALLEY DISTRICTS, ARUNACHAL PRADESH

(G4)

91 D/8, 12 &

92 A/5

Ravi Negi & Hiruj

Saikia

2012-

14

LSM 50

sq.km

DM : 2.5

sq.km

4 ME/NER/SAS/2012/084 PRELIMINARY INVESTIGATION FOR REE IN 78 J/12 K. Bora, Akshaya 2013- LSM 50

47

SOUTHERN PART OF AGIA AROUND

SUJUKONA HILL AND TUKURESWARI HILL IN

PARTS OF GOALPARA DISTRICT, ASSAM (G4)

Kumar Mishra, M.

Shyamkumar

Singh & Th N. B.

Singha (inducted

from Oct, 13)

14 sq.km

DM : 1.5

5 ME/PM/NER/SMN/2012/028 PRELIMINARY INVESTIGATION FOR

PLATINIUM GROUP OF ELEMENTS IN

OPHIOLITE BELT OF NAGALAND (G4)

83 K/10, 13,

14, 15 ; 83

N/3, 4 ; 83

O/1,2

N. Meribemo

Yanthan& 1G

(Petrology)

2012-

14

Rec.Traverse

: 150 sq.km

6 ME/F/NER/SME/2012/023 INVESTIGATION FOR TITANIFEROUS-

VANADIFEROUS MAGNETITE AROUND

RAMBRAI IN WEST KHASI HILLS DISTRICT,

MEGHALAYA (G4)

78O/6 V. Sreenivasiah 2012-

14

LSM 25

sq.km

DM : 1.5

sq.km

7 ME/NER/SME/2013/018 INVESTIGATION FOR LIMESTONE IN NORTH

OF LARKET BLOCK, LITANG VALLEY, JAINTIA

HILLS DISTRICT, MEGHALAYA (G3)

83C/11 Pius Sarkar &

T.G. Singh

2013-

15

DM : 1.5

sq.km

D : 800 m

8 ME/NER/SME/2013/019 ASSESSMENT OF LIMESTONE IN THE

EXTENSION AREA OF MAWLONG - ISHAMATI

BLOCK OF SHELLA - BHOLAGANJ BELT, EAST

KHASI HILLS DISTRICT, MEGHALAYA (G3)

78 O/12 Aravind & Rajesh

Kumar

2013-

15

DM : 1.5

sq.km

D : 800 m

9 ME/NER/SME/2013/020 PRELIMINARY INVESTIGATION FOR REE IN

PARTS OF NONGPOH PLUTON, RI-BHOI

DISTRICT, MEGHALAYA (G4)

78 O/13 Mohd Sadiq &

Ravi Kumar

Umrao

2013-

14

LSM 60

sq.km

10 GPS/NER/RHQ/2013/021 MAGNETIC SURVEY FOR CHROMITE

BEARING ULTRAMAFICS IN MANTUM CHING,

CHANDEL DISTRICT, MANIPUR, (G4)

83 L/7 K.V.

Sathyanarayana

M.K. Rai

2013-

14

GP : 5.6

sq.km

11 ME/BM/NER/SSK/2012/027 PRELIMINARY STUDY FOR THE BASE METALS

AND ASSOCIATED GOLD IN EXTENSION

AREAS OF DIKCHU BASEMETAL PROSPECT,

EAST DISTRICT, SIKKIM (G4)

78 A/11 Kailash Singh,

Tangtirenba

Longchari & 1G

(DMMG)

2012-

14

LSM 50

sq.km

12 ME/NER/NEnR/SAS/2012/030 PRELIMINARY APPRAISAL TO LOCATE

POTENTIAL COAL ZONE IN TERTIARY

SEQUENCE BY LARGE SCALE GEOLOGICAL

MAPPING ON 1:10,000 SCALE IN PARTS OF

TOPOSHEET NO. 78G/14 AROUND SHALIBHUIN

IN DHUBRI DISTRICT OF ASSAM AND

NAKAIGIRI-UJANGGIRI IN WEST GARO HILLS

78 G/14 Vizolto Sakhrie

(P/T) & D.V.

Whourie

2013-

14

LSM 6.5

sq.km

D : 300 m

48

OF MEGHALAYA (G4)

13 ME/NER/NEnR/SME/2013/022 REGIONAL EXPLORATION FOR GONDWANA

COAL IN THE AREA ADJACENT TO SUKCHAR -

SINGRIMARI AREA, SINGRIMARI COALFIELD,

DHUBRI DISTRICT, ASSAM AT THE BORDER

OF ASSAM & MEGHALAYA

78 G/13 Vizolto Sakhrie

(P/T) & D.V.

Whourie

2013-

14

LSM 3

sq.km

D : 600 m

MISSION: III

SL.

NO.

FSP CODE TITLE OF THE ITEM TOPOSHEET

NO

PERSONNEL F.S. TARGET

(2013-14)

1 MAP/NER/RHQ/2013/023 DIGITISATION, SCRUTINY, MODIFICATION,

UPLOADING OF 1:50,000 MAPS, VALIDATION

AND STANDARDISATION OF UPLOADED MAPS

IN THE PORTAL

P.K. Mukherjee

(M&C) (P/T)

&Darinia C. War

(P/T)

+ 1G (/PT) (Geodata)

2013-14 4 sheets

2 DB/NER/RHQ/2013/024 CREATION OF THEME BASED DATABASE OF

DEGREE SHEET NO 78 O COVERING PARTS OF

EAST GARO HILLS, EAST KHASI HILL, WEST

KHASI HILL, JAINTIA & RIBHOI DISTRICTS OF

MEGHALAYA AND KAMRUP & GOALPARA

DISTRICTS OF ASSAM

S. Banerjee 2013-14 122

reports

3 MAP/NER/RHQ/2013/025 COMPILATION, SCRUTINY AND PREPARATION

OF 1:250,000 (QUADRANGLE GEOLOGICAL)

MAP (78O) OF MEGHALAYA

78 O/1 - 15 P.K. Mukerjee

(M&C) (P/T) & 1G

(P/T) (Geodata)

2013-14 1 degree

sheet

4 SER/NER/RHQ/2012/033 COMPILATION OF DISTRICT RESOURCE MAP

(JAINTIA) OF MEGHALAYA (1:250,000 SCALE)

78 O/15 & 16 ;

83 C/2-4. 6-8,

10-12 & 15-16

P.K. Mukerjee

(M&C) (P/T)

2012-14 1 district

5 PUB/NER/RHQ/2013/026 PUBLICATION RELATED ACTIVITIES AND

PROCESSING OF SCIENTIFIC PAPERS

B.N. Gohain (P/T &

transferred) & Amit

Srivastava, S.M.

Singh

2013-14

6 MAP/NER/SAS/2013/027 PREPARATION OF DISTRICT RESOURCE MAPS

(DRM) OF ASSAM STATE AND DIGITIZATION

OF DISTRICT RESOURCE MAPS (DRM) OF

ASSAM

Rupali Thakur Bhuyan

(P/T),

N. Goswami & Anjan

Bora

2013-14 5 districts

7 MAP/NER/SMN/2013/028 COMPILATION OF DISTRICT RESOURCE MAPS 83G/8, 12, 15, R.L. Jat (P/T) 2013-15 4 districts

49

OF MANIPUR (1:250,000 SCALE) 16; 83 H/1, 2,

3, 5, 6, 7, 9,

10, 13, 14;

3K/3, 4, 7, 8,

11, 12; 83L/1,

2, 5, 6, 9, 10

8 MAP/NER/STM/2012/036 PREPARATION AND FINALISATION OF

DISTRICT, RESOURCE MAP OF MIZORAM

Srinanda Mukherjee &

T.S. Giritharan (PT)

2012-15 3 districts

9 DB/NER/HQ/2013/029 ONLINE CORE BUSINESS INTEGRATED SYSTEM

(OCBIS)

N. Devaraj (P/T), P.K.

Sinha (P/T), F.

Kharshing (P/T),

Hemraj Suryavanshi

(P/T), J.C. Dutta

(P/T), K.C.

Chandrasekharaiah

(P/T), G.C. Khandpal

(P/T), Balbir

Singh(P/T), C.A.

Limbu (P/T), Md.

Sadique (P/T), D.C.

War (P/T), Mego

Chasie (P/T)

2013-14

50

MISSION: IV

SL.

NO.

FSP CODE TITLE OF THE ITEM TOPOSHEET

NO

PERSONNEL F.S. TARGET

1 SER/NER/RHQ/2013/030 UPDATION OF EXISTING LANDSLIDE

INVENTORY OF NORTH EASTERN

REGION

All North

East

Megotsohe Chasie &

S.C.Keshari & P.K. Sarma &

E.John & Watitemsu &

Thrideep Kumar N. & P. K.

Theophilus & B.R.Syngai

(transferred) & Yhunyelo Tep

& N.Meribemo Yanthan &

Elow A. & Jagdish Nandan

Hindayar

2013-14 As nec

2 LHZ/NER/RHQ/2013/031 MACRO SCALE LANDSLIDE HAZARD

ZONATION (1:50,000) ALONG THE

HAYULIANG - CHAGLAGAM AND TEJU-

HAYULIANG ROAD CORRIDORS OF

ANJAW DISTRICT, ARUNACHAL

PRADESH

91 D/11 & 12 Megotsohe Chasie, & S.C.

Keshari (transferred to

NGCM, SU:AP) & P.K.

Theophilus

2013-14 150 sq.km

3 LHZ/NER/RHQ/2013/032 DETAILED (1:1000) SITE SPECIFIC

GEOLOGICAL STUDIES OF THE

LANDSLIDES NEAR TAWANG

MONASTERY, TAWANG DISTRICT,

ARUNACHAL PRADESH

78 M/14 Megotsohe Chasie & P.K.

Theophilus & 1G (P/T) from

EG Division

2013-14 D.M. 0.50

sq.km

4 LHZ/NER/SSK/2012/043 DETAILED STUDY AND MONITORING OF

THE 13TH MILE LANDSLIDE ON

GANGTOK - NATHULA ROAD, EAST

DISTRICT, SIKKIM

78 A/11 Jagadish Nandan Hindayar

(P/T) & P. N. Dasarwar (P/T)

2012-14 0.25

sq.km

5 LHZ/NER/SSK/2013/033 MACRO SCALE LANDSLIDE HAZARD

ZONATION ON 1:50,000 SCALE ALONG

RANGPO-SINGTAM-DIKCHU-

CHUNGTHANG ROAD CORRIDOR,

SIKKIM

78 A/12,

78 A/11, 78

A/6

Jagadish Nandan Hindayar

(P/T) & Thrideep Kumar N. &

Murali Mohan (P/T)

2013-14 100 sq.km

6 SEI/NER/RHQ/2012/038 SEISMIC AND LANDSLIDE HAZARD

ASSESSMENT OF AIZAWL TOWN,

MIZORAM

84 A/9, 10,

13, 14

P. Jana (transferred) & L. H.

Moirangcha, & D.

Chakraborty (PT) &S.N.

Chowdhury &

G.S.Dharamwal

2012-14 50 sq.km

51

7 SEI/NER/RHQ/2013/034 SEISMIC AND LANDSLIDE HAZARD

ASSESSMENT OF KOHIMA CITY,

NAGALAND

83K/2 V Shivgotra & Imtikumzuk,

& P.K. Chakraborty (GP) & 1

(GP)

2013-15 50 sq.km

8 LHZ/NER/SSK/2013/035 SITE SPECIFIC STUDY OF PROPOSED

PAKYONG AIRPORT AREA, SIKKIM

78A/12, 11 Lopamudra Bhol, Mohd.

Ibrahim & 1G (P/T) from EG

Division, Shillong + 1G

DMMG, Sikkim

2013-14 25 sq.km

9 SEI/NER/SSK/2012/039 SEISMIC HAZARD ASSESSMENT OF

GANGTOK AND SURROUNDING AREAS

OF SIKKIM

78A/11 Murali Mohan (P/T), P.N.

Dasawar (P/T), S.N.

Chowdhury (GP) (P/T) & G.S.

Dharamwal (GP) (P/T)

2012-14 50 sq.km

10 EG/C/NER/RHQ/2013/036 GEOTECHNICAL EVALUATION OF

WATER RESOURCE DEVELOPMENT

PROJECTS IN ARUNACHAL PRADESH

83 A/11 &

12, 83I/6, 78

M/13, 14 and

83 A/1, 2, 5

D. Chakraborty (P/T) &

G.Rongmei (P/T)

2013-14

11 EG/C/NER/RHQ/2013/037 GEOTECHNICAL EVALUATION OF

WATER RESOURCE DEVELOPMENT

PROJECTS IN ASSAM

78 O/5, 83

D/14 and 15

83 C/14

D. Chakraborty (P/T) & 1G

(P/T)

2013-14

12 EG/C/NER/RHQ/2013/038 GEOTECHNICAL EVALUATION OF

WATER RESOURCE DEVELOPMENT

PROJECTS IN MIZORAM

84 E/3, 84

A/10,13, 84

B/13, 83 D/15

Vinod Kumar (P/T) &

G. Rongmei (P/T)

2013-14

13 SEI/NER/SSK/ 2012 /039 SEISMIC HAZARD ASSESSMENT OF

GANGTOK AND SURROUNDING AREAS

OF SIKKIM

78A/11 Murali Mohan (P/T) & P.N.

Dasarwar (P/T)& S.N.

Chowdhury (GP) (P/T) & G.S.

Dharamwal (GP) (P/T)

2012-14

14 EG/C/NER/RHQ/2013/040 GEOTECHNICAL EVALUATION OF

TRANSPORT AND COMMUNICATION

PROJECTS IN NORTH EASTERN REGION

84 A/9 G.Rongmei (P/T) & Vinod

Kumar (P/T)

2013-14

15 RP/NER/SAS/2012/082 STUDY OF ARSENIC CONTAMINATION IN

WATER AND SOIL IN PARTS OF NAGAON

AND MARIGAON (WITH IN EARSTWHILE

NAGAON DISTRICT) DISTRICTS, ASSAM

83 B/12 &16 P.C. Srivastava, Amiya Kumar

Mondal

John Kevi

Angami(transferred), Nitin P

Nagmote (Chemist) & S.

Dutta (STA-(C)

2013-14

16 RP/NER/RHQ/2013/041 STUDIES AND PREPARATION OF

PALAEONTOLOGICAL AND

Degree sheet

78O, 84C

Surendra Prasad & Abir Gupta

(P/T)

2013-14

52

STRATIGRAPHICAL SECTIONS ALONG

SHILLONG – SOHRA, SHILLONG –

MAWSYRAM AND SHILLONG – DAWKI

IN EAST KHASI HILLS DISTRICT OF

MEGHALAYA

17 RP/NER/RHQ/2013/042 PETROGRAPHY AND GEOCHEMISTRY OF

MAWPUT MAFIC-ULTRAMAFIC SUITE

AND ASSOCIATED MINERALIZATION,

JAINTIA HILLS DISTRICT, MEGHALAYA

83 C/3 Sushree Mishra 2013-14

MISSION-V

SL.

NO.

FSP CODE TITLE OF THE ITEM F.S.

1 RC/NER/RTI/2013/048 REFRESHER COURSE ON PETROGRAHIC TECHNIQUES FOR GEOLOGISTS OF DGMS

OF NORTHEASTERN INDIA AND GSI

2013-14

2 RC/STM/NER/RTI/2013/049 A COURSE ON COMPUTER APPLICATIONS AND DATA ENTRY FOR NON-GAZETTED

GROUP ‘B’ AND GROUP ‘C’ OF GSI

2013-14

3 FWS/AFM/NER/RTI/2013/050 FIELD WORKSHOP ON ACTIVE FAULT MAPPING 2013-14

4 WS/OM/NER/RTI/2013/051 MANAGEMENT TRAINING FOR JAG AND SENIOR STS LEVEL OFFICERS OF GSI

AND GROUP ‘A’ OFFICERS OF DGMS OF NER

2013-14

5 LHZ/RTI/NER/2013/052 A COURSE ON LANDSLIDE HAZARD ZONATION AND DISASTER MANAGEMENT

FOR GSI AND DGMS OF NER

2013-14

6 CP/CA/NER/RTI/2013/053 CAPSULE COURSE ON CHEMICAL ANALYSIS OF ROCK SAMPLES FOR DGMS OF

NER

2013-14

53

ANNEXURE – 3A

QUARTER-WISE, HEAD-WISE ALLOTMENT OF PLAN FUND versus EXPENDITURE BOOKED DURING THE FINANCIAL YEAR 2013-14 (2nd year of the XIIth 5-year Plan) IN RESPECT OF NORTH-EASTERN REGION OF GSI

QUARTER-WISE, HEAD-WISE ALLOTMENT OF PLAN FUND versus EXPENDITURE BOOKED DURING THE FINANCIAL YEAR 2013-14 (2nd

year of the XIIth 5-year Plan) IN RESPECT OF NORTH-EASTERN REGION OF GSI

Financial Year & FSP (April to March)

HEAD OF EXPENDITURE (Classification as MoM/GSI and MoF)

HEAD OF EXPENDITURE (Classification as MoM/GSI and MoF)

Total of ASS {Sal. + Hqrs.Wages + OTA + Med. + DTE + FTE + OE (v) + OE(c) + RRT + OAE + PS}

Mission-I Mission-II Mission-III (Information Dissemination) Mission-IVA Mission-IVB Mission-V (Human Resource Development)

Total of Mission I, II, III, IVA, IVB & V

STSS (Modernisation & Replacement) Total of ASS, all Missions & STSS

Minor Works (Minor Civil, Electrical and Operarational-Machine etc. related for protection / maintenance /addition / alteration / modification etc. of Govt. properties)

Major Works (Major Civil Exp. related to development of new premises/ complexes/ compounds, new Construction and/or New Major Electrical Installations

SC/ST Welfare related Expdr.

Total of ASS, all Missions, STSS, Minor Works, Major Works and SC/ST Welfare

Survey & Mapping (Wages + POL +

OC)

Mineral Exploration

(Wages + POL + OC)

Other expdr. (Publication + OAE + Adv. &

Publicity)

Other Expdr. {IT (OAE)}

Total of Mission - III [i.e., Total of

Other Expdr. {i.e., Pubn. + OAE +

Adv. & Pub. + IT (OAE)}]

Research & Development

(Wages + Sup. & Mat + POL + OC)

Investigation (Wages + POL +

OC)

Training & Capacity Building

(OAE)

Other Expdr. (Sup. & Mat.+

Clothing & Tentage)

Capital Assets (MV + ME)

Total of STSS {i.e., Total of

Other Expdr. (i.e., Sup. & Mat. +

Clothing & Tentage + MV +

ME)}

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Allotment (+) OR ( - ) during the Qtr.

Expdr. (during the Qtr.)

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

Rs. In Lakh

2013-14 (For the 1st Qtr.)

1188.00 589.33 50.00 13.85 50.00 23.54 25.00 1.24 20.00 5.93 45.00 7.17 30.00 4.58 25.00 1.15 5.00 0.03 205.00 50.32 2.00 360.00 48.40 362.00 48.40 1755.00 688.05 25.00 1780.00 688.05

2013-14 (For the 2nd Qtr.)

10.00 470.18 8.68 16.31 2.94 6.99 0.00 9.93 6.23 2.74 10.00 4.25 10.00 48.14 31.07 0.00 31.07 20.00 549.39 43.12 6.87 40.00 6.34 103.12 562.60

2013-14 (For the 3rd Qtr.)

0.00 71.05 17.43 7.52 10.42 0.49 0.00 10.91 5.12 1.63 2.82 0.00 45.43 0.35 76.62 0.00 76.97 0.00 193.45 -7.00 49.60 29.91 -7.00 272.96

2013-14 (For the 4th Qtr.)

16.47 76.25 9.96 2.62 0.20 9.97 6.03 0.20 16.00 12.47 1.50 20.81 1.00 8.43 2.70 70.29 1.53 177.48 0.00 179.01 19.17 325.55 3.60 5.00 8.61 24.17 337.76

Total (at the end of filled-up Qtr.) --->

1214.47 1206.81 50.00 49.92 50.00 49.99 25.20 24.57 20.00 19.44 45.20 44.01 30.00 28.40 26.50 26.33 16.00 15.53 217.70 214.18 2.00 1.88 360.00 333.57 362.00 335.45 1794.17 1756.44 61.12 60.07 0.00 0.00 45.00 44.86 1900.29 1861.37

54

ANNEXURE – 3B

HEAD-WISE & QUARTER-WISE ALLOTMENT OF PLAN FUND versus EXPENDITURE FOR THE FINANCIAL YEAR 2013-14 (2nd year of the XII

th 5-year Plan) IN RESPECT OF NORTH-EASTERN REGION OF GSI

Sl. No.

Head of Expenditure 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER TOTAL

Fund Allocated during the Qtr.

Expenditure Booked during the Qtr.

Fund Allocated during the Qtr.

Expenditure Booked during the Qtr.

Fund Allocated during the Qtr.

Expenditure Booked during the Qtr.

Fund Allocated during the Qtr.

Expenditure Booked during the Qtr.

Fund Allocated upto the end of the filled-up Qtr.

Expenditure Booked upto the end of the filled-up Qtr.

Classification as per MoM/GSI

Classification as per MoF Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh Rs. In Lakh

Total of ASS {Sal.+ Hqrs. Wages + OTA + Med. + DTE + FTE + OE(v) + OE(c) + RRT +

OAE + PS} --> 1188.00 589.33 10.00 470.18 0.00 71.05 16.47 76.25 1214.47 1206.81

16 Mission-I Survey & Mapping (Wages + POL + OC)

50.00 13.85 8.68 17.43 9.96 50.00 49.92

17 Mission-II Mineral Exploration (Wages + POL + OC)

50.00 23.54 16.31 7.52 2.62 50.00 49.99

18 Mission-III (Information Dissemination)

Other Expdr. (Pubn. + OAE + Adv. & Publicity)

25.00 1.24 2.94 10.42 0.20 9.97 25.20 24.57 Other Expdr. {IT (OAE)} 20.00 5.93 6.99 0.49 6.03 20.00 19.44

Total of Mission III ----> 45.00 7.17 0.00 9.93 0.00 10.91 0.20 16.00 45.20 44.01

19 Mission-IV A Research & Development (Wages + Sup. & Mat.

+ POL + OC) 30.00 4.58 6.23 5.12 12.47 30.00 28.40

20 Mission-IV B Investigation (Wages + POL + OC) 25.00 1.15 2.74 1.63 1.50 20.81 26.50 26.33

21 Mission-V (Human Resource Development)

Training & Capacity Building (OC)

5.00 0.03 10.00 4.25 2.82 1.00 8.43 16.00 15.53

Total of Mission I, II, III, IVA, IVB & V ----> 205.00 50.32 10.00 48.14 0.00 45.43 2.70 70.29 217.70 214.18

22 STSS (Modernisation & Replacement)

Other Expdr. (Sup. & Mat.+ Clothing & Tentage) 2.00 0.35 1.53 2.00 1.88

Capital Assets (MV + ME) 360.00 48.40 31.07 76.62 177.48 360.00 333.57

Total of STSS ------------> 362.00 48.40 0.00 31.07 0.00 76.97 0.00 179.01 362.00 335.45

Total of ASS, all Missions, STSS ------> 1755.00 688.05 20.00 549.39 0.00 193.45 19.17 325.55 1794.17 1756.44

23 Minor Works (Minor Civil, Electrical and Operational-Machines etc. related Exp. for protection/ maintenance/ addition/ alteration /modification etc. of Govt. properties) 25.00 43.12 6.87 -7.00 49.60 3.60 61.12 60.07

24 Major Works (Major Civil Exp. related to development of new premises/ complexes/ compounds/ new Construction or New cum Major Electrical Installations etc.) 0.00 0.00

25 SC/ST Welfare related Expdr. 40.00 6.34 29.91 5.00 8.61 45.00 44.86 Total of ASS, all Missions, STSS, Minor Works, Major Works, SC/ST Welfare ---> 1780.00 688.05 103.12 562.60 -7.00 272.96 24.17 337.76 1900.29 1861.37

55

ANNEXURE – 4

MISSION WISE PRO-RATA RCA EXPENDITURE IN DIFFERENT PROJECTS VISA-VIS TARGETS AND ACHIEVEMENTS FS 2013-14 (Upto 31.03.2014)

MISSION-I

Major Activity Areas Name of

Officers

Target for the

Field season

Achievement

during F.S. 2013 -

2014

(since Apr. 13)

Field

Days

Total Exp. Per day Exp.

(Tentative)

MISSION-IA (BASELINE GEOSCIENCE DATA GENERATION)

Programme : Ground Surveys – Geological Survey

1. SYSTEMATIC GEOLOGICAL MAPPING ON 1:50,000 SCALE IN TOPOSHEET NO. 78 J/9 & J/10 IN

GOALPARA DISTRICT, ASSAM.

Code No.: GM/NER/SAS/2012/003

Varun Vara

&

Yhunyelo Tep

1) SGM (1:50,000 scale) : 865 sq.km

2) Sampling

a) PS : As necessary

b) Sediment samples for Grain Size Analysis : 35 nos

3) Section studies : 10 nos.

865

35

37

32

265 139647 Rs. 526.97/-

2. SYSTEMATIC GEOLOGICAL MAPPING ON 1:50,000 SCALE IN TOPOSHEET NO. 78 J/1, 5 & 13, 78 N/1,

5, 9 & 13 IN KAMRUP, GOALPARA AND DARRANG

DISTRICT, ASSAM

Code No.: GM/NER/SAS/2013/001

Rajkumar Tapon

Kumar

&

Satrughan Majhi

1) SGM (1:50,000 scale) : 955 sq.km

2) Sampling

a) PS : As necessary

b) Sediment samples for Grain Size Analysis : 40 nos

c) PCS# (Major, Trace and REE) : 10 nos.

3) Section studies : 12 nos.

4) Chemical Analysis : 10 nos.

955

40

35

20

20 10

268 227138 Rs. 847.53/-

3. SYSTEMATIC GEOLOIGICAL MAPPING IN

PARTS OF PEREN, DIMAPUR, KIPHIRE, KOHIMA AND PHEK DISTRICTS, NAGALAND ON 1:50,000 SCALE

Code No.: GM/NER/SMN/2013/002

B. Behera(

Transferred), C.

Yanthan &

T.S. Kom

(Initiated)

1) SGM (1:50,000 scale) : 360 sq.km

2) Sampling

a) PS : 12 nos. b) PCS# (Major, Trace and REE) : 24 nos.

3) Chemical Analysis : 24 nos.

360

25 24

22

216 176389 Rs. 816.62/-

4. SYSTEMATIC GEOLOIGICAL MAPPING IN

PARTS OF CHURACHANDPUR DISTRICT, MANIPUR ON 1:50,000 SCALE

Code No.: GM/NER/SMN/2013/003

P. Enos Ezung

&

V. Zaphu

1) SGM (1:50,000 scale) : 460 sq.km

2) Sampling

a) PS : 30 nos.

b) PCS# (Major, Trace and REE) : 20 nos.

3) Chemical Analysis : 20 nos.

460

30 20

20

294 233452 Rs. 794.05/-

5. SPECIALISED THEMATIC MAPPING IN PARTS OF ANJAW DISTRICT, ARUNACHAL PRADESH.

Code No.: STM/NER/SAP/2012/001

Rupesh Kumar

&

Sebabrata Das

1) STM (1:25000 scale) : 220 sq.km 2) Sampling

a) PS : 40 nos

b) BRS : 25 nos

c) EPMA : 10 nos

3) Chemical Analysis : 25 nos.

220

43

30 10

30

163 206365 Rs. 1266.04/-

6. SPECIALISED THEMATIC MAPPING FOR STUDY OF EVOLUTION OF GONDWANA AND SIWALIK

GROUPS IN SIANG RIVER BASINS IN PARTS OF WEST

SIANG AND EAST SIANG DISTRICTS, ARUNACHAL

B.N. Mahanta

(Transferred to

TC),

B.R. Syngai

1) STM (1:25,000 scale) : 330 sq.km

2) Sampling a) PS : 20 nos

b) PCS : 15 nos

330

21

19

271 338337 Rs. 1248.47/-

56

PRADESH.

Code No.: STM/NER/SAP/2012/002

(Transferred to

GSI, Shillong) &

Raman Kumar,

K.Sekhose,

V. Vitso

c) BRS : 25 nos

d) Geochemistry of coal : 5 nos

e) Clay mineralogy by XRD : 5 nos

f) SEM / EPMA : 10 nos

g) Palaeontological study : As necessary

h) Sampling of Coal / Carbonaceous horizon

for Carbon Isotope study : As necessary

3) Chemical Analysis : 45 nos.

25

8 7

10

13

0

49

7. SPECIALISED THEMATIC MAPPING IN TERTIARY COAL BELT IN CHANGLANG AND TIRAP

DISTRICTS, ARUNACHAL PRADESH

Code No.: STM/NER/SAP/2013/004

Amit Kumar &

Ranjita

Bhattacharjee,

Diethovilie Pieru

& Welhitshou

Mero

1) STM (1:25,000 scale) : 110 sq.km 2) Sampling

a) PS : 20 nos

b) BRS : 15 nos

c) PCS : 5 nos

d) Coal Petrography : 10 nos

e) Clay mineralogy by XRD : 10 nos

f) SEM : As necessary

g) Palaeontological study : 5 nos

3) Chemical Analysis : 45 nos.

90

23

21 7

14

12 3

6

18

81 133583 Rs. 1649.17/-

8. SPECIALISED THEMATIC MAPPING OF

OPHIOLITE SUITE OF ROCKS OF MANIPUR BETWEEN NINGTHI TO NUNGBI KHULLEN, UKHRUL DISTRICT,

MANIPUR

Code No.: STM/NER/SMN/2013/005

J.K. Angami+ 1G 1) STM (1:25,000 scale) : 220 sq.km

2) Sampling

a) PS : 25 nos b) PCS : 15 nos

c) BRS : 20 nos

d) XRD : As necessary

e) EPMA : As necessary

f) Ore microscope Studies : 5 nos

g) PGE analysis : 5 nos

3) Chemical Analysis : 35 nos.

220

25 15

20

0

0

5

5 35

185 136778 Rs. 739.34/-

9. SPECIALIZED THEMATIC MAPPING TO

DECIPHER LITHOLOGICAL SEQUENCE AND STRUCTURAL SET-UP IN WESTERN PART OF BATGURI

AREA IN ERSTWHILE GOALPARA DISTRICT, ASSAM

Code No.: STM/NER/SAS/2012/077

Ramesh Chandra

Kishan

&

Parusharama

Gangaikoppa &

Binod Baruah

1) STM (1:25,000 scale) : 300 sq.km

2) Sampling a) PS : 50 nos

b) BRS : 20 nos

c) PCS : 50 nos

d) EPMA : 5 nos

3) Chemical Analysis : 70 nos.

300

55

22

55

413 229903 Rs. 556.67/-

10. SPECIALISED THEMATIC MAPPING OF THE GNEISS AND GRANITOIDS TO DECIPGER THEIR

STRATIGRAPHIC RELATION WITH THE SHILLONG

GROUP AND ASSOCIATED MINERALISATION BETWEEN NONGPOH, JIRANG AND PATHARKHMAH,

RI-BHOI DISTRICT, MEGHALAYA

Code No.: STM/NER/SME/2012/006

Balbir Singh,

Vekhoto Shijoh

&

Imrongtola

Pongen

1) PRS:INTMAP : 500 sq.km

2) STM (1:25,000 scale) : 450 sq.km

2) Sampling

a) PS : 35 nos

b) PCS : 15 nos c) BRS : 30 nos

d) EPMA / SEM-EDX : 25 nos

3) Chemical Analysis : 45 nos

500

450

35

15 30

0

45

367 272784 Rs. 743.28/-

11. SPECIALISED THEMATIC MAPPING TO

CHARACTERISE THE ANORTHOSITE-MANGERITE- CHARNOCKITE-GRANITOID (AMCG) SUITE OF ROCKS

WITH SPECIAL EMPHASIS ON TECTONOMAGMATIC

HISTORY AND MUTUAL RELATIONSHIPS OF ROCKS BETWEEN RANGBLANG AND MANAD MAWBIDONG

AREAS, WEST KHASI HILLS DISTRICT, MEGHALAYA

Code No.: STM/NER/SME/2012/007

S.R. Mishra,

Lalneo Haokip

&

N.P. Khedkar

1) PRS:INTMAP : 500 sq.km

2) STM (1:25,000 scale) : 450 sq.km

2) Sampling a) PS : 50 nos

b) PCS : 20 nos

c) BRS : 15 nos d) EPMA / SEM-EDX : 15 nos

3) Chemical Analysis : 35 nos.

500

450

50

20

15 0

35

346 323445 Rs. 934.81/-

57

12. SPECIALIALISED THEMATIC MAPPING FOR

CHARACTERISATION OF HIGH GRADE METASEDIMENTS, GRANULITES AND GNEISSIC

COMPLEX SOUTH OF SONAPAHAR, WEST KHASI HILLS

DISTRICT, MEGHALAYA

Code No.: STM/NER/SME/2012/008

Ranjith,

Lalboi Haokip &

Shampita Das

(inducted)

1) PRS:INTMAP (1: 50,000) : 400sq.km

2) STM (1:25, 000) scale: 220 sq.km

3) Sampling

a) PS: 50 nos

b) PCS: 20 nos

c) BRS: 35 nos

d) EPMA / SEM-EDX : 15 nos

3) Chemical Analysis : 55 nos

400

220

55

20 35

15

06

279 190918 Rs. 684.29/-

13. THEMATIC MAPPING TO DECIPHER THE TECTONO-MAGMATIC AND METAMORPHIC HISTORY

OF THE GNEISSIC COMPLEX, MIGMATITES AND

SHILLONG GROUP OF ROCKS, EAST KHASI HILLS AND

JAINTIA HILLS DISTRICTS, MEGHALAYA AND KARBI

ANGLONG DISTRICT, ASSAM

Code No.: STM/NER/SME/2013/006

Sougrakpam

Sujata,

Imlishila Imchen

&

Avi Mero

1) PRS:INTMAP : 500 sq.km

2) STM (1:25, 000) scale: 330 sq.km

3) Sampling

a) PS: 35 nos b) PCS: 15 nos

c) BRS: 30 nos

d) EPMA / SEM-EDX : 25 nos

3) Chemical Analysis : 45 nos

500 333

35 15

30

25 45

362 168958 Rs. 466.73/-

14. STUDY OF LINGTSE GNEISS IN SIKKIM HIMALAYA FOR ELUCIDATING THE ROLE OF

PROTEROZOIC GRANITOIDS IN HIMALAYAN

OROGENY.

Code No.: STM/NER/SSK/2012/009

Jiji Kumar S

&

Hiten Kumar

Jalutharia

1) STM (1: 25,000) : 225 sq.km

2) Sampling a) PS : 40 nos

b) PCS : 10 nos

c) BRS : 30 nos d) EPMA : 10 nos

3) Chemical Analysis : 40 nos

225

40

30

10 20

40

277 177168 Rs. 639.60/-

15. SPECIALISED THEMATIC MAPPING IN TERTIARY FOLD BELT IN PARTS OF AIZAWL DISTRICT,

MIZORAM (PARTS OF T.S. No. 84A/14).

Code No.: STM/NER/STM/2013/007

Pankaj P Vaidya

&

A. Elow

1) STM (1:25,000 scale): 220 sq.km 2) Section measurement As necessary

3) Sampling:

a) PS: 15 nos

b) BRS: 10 nos

c) Palaeontological samples: As necessary

d) Coal analysis: As necessary

3) Chemical Analysis : 10 nos

220 2 L.km

17 10

03

0 10

285 152836 Rs. 536.26/-

16. SPECIALISED THEMATIC MAPPING IN

TRIPURA-MIZORAM FOLD BELT IN PARTS OF SOUTH TRIPURA AND DHALAI DISTRICTS, TRIPURA

Code No.: STM/NER/STM/2013/008

Omnath Saha,

Watitemsu

&

Jayanta Pramanik

(P/T)

1) STM (1:25,000 scale): 220 sq.km

2) Section measurement As necessary 3) Sampling:

a) PS: 20 nos

b) PCS: 20 nos

c) XRF/ICPMS: As necessary

d) Palaeontological samples: As necessary

3) Chemical Analysis : 20 nos

220

05

26

23

0

2

23

319 131583 Rs. 412.49/-

MISSION-IA (BASELINE GEOSCIENCE DATA GENERATION)

Programme : Ground Surveys – Geochemical Mapping

1. GEOCHEMICAL MAPPING IN LESSER HIMALAYA IN PARTS OF EAST SIANG DISTRICT,

ARUNACHAL PRADESH (TOPOSHEET NOS. 82P/12 &

PART OF 82P/11).

Code No.: GCM/NER/SAP/2013/009

S.C.KESHARI &

S.M.Toppo

&

Wanbiang Swer

(Transferred)

&

D. Gurung

(Chemist)

1. GCM (1:50,000) scale : 800 sq.km

2. Sampling: a. SSS (2 km x 2 km): 200 nos

b. R (Regolith): 12 nos

c. C (C-horizon soil) : 12 nos

d. H (Humus): As necessary

e. SW (Water samples): 12 nos

f. F (Flood plain sediments): As necessary

g. 5 % duplicate samples: 12 nos.

800

200

12

12 3

12

0

12

240 319393 Rs. 1330.80/-

58

3. Analysis of samples: 248 nos. 248

2. GEOCHEMICAL MAPPING IN TOPOSHEET NO. 78 O/1 AND PARTS OF 78O/5 IN GOALPARA & KAMRUP

DISTRICTS, ASSAM AND EAST GARO HILLS & WEST

KHASI HILLS DISTRICTS, MEGHALAYA

Code No.: GCM/NER/SAS/2012/016

Amit Kumar &

Mukesh Kumar

Mishra

&

N.P. Nagmote

(Chemist)

1. GCM (1:50,000 scale) : 800 sq.km

2. Sampling: a. Stream Sediment sample (SSS)

(2 Km x 2 Km grid): 165 nos

b. Composite Stream Sediment samples (2 Km x 2 Km grid): 48 nos

c. Sediment Sample (SS)

(4 Km x 4 Km): 22 (11+11) nos d. C-Horizon(C): 8 nos

e. Regolith Sample (R) : 8 nos

f. Humus Sample (H) : 8 nos g. Stream Water Sample (SW) : 8 nos

h. Flood Plain Sample (FP) : As necessary

i. 5 % duplicate samples: 12 nos 3. Analysis of samples: 272 nos

800

145

48

24

8 8

8

8 0

12

0

269 232589 Rs. 864.64/-

3. REGIONAL GEOCHEMICAL MAPPING IN THE OPHIOLOIE BELT IN PARTS OF PHEK DISTRICT,

NAGALAND

Code No.: GCM/NER/SMN/2013/010

Chubala Shijoh,

D. Bharati

&

R.Vittal

(Chemist)

1. GCM (1:50,000 scale) : 800 sq.km 2. Sampling:

a. Stream Sediment Sample (SSS)

(2 Km X 2 Km) : 200 nos b. Soil Sample (C-horizon) : 12 nos

c. Regolith Sample (R) : 12 nos

d. Humus Sample (H) : As necessary

e. Stream Water Sample (SW) : 24 nos

f. Duplicate SSS (3 to 5% of the area) : 12

nos 3. Analysis of samples: 260 nos

800

200 12

12

0

12

12

353 182259 Rs. 516.31/-

4. REGIONAL GEOCHEMICAL MAPPING IN THE

OPHIOLITE BELT IN PARTS OF MON,TUENSANG & KIPHIRE DISTRICTS, NAGALAND

Code No.: GCM/NER/SMN/2013/011

E. John

&

R.Vittal

(Chemist)

1. GCM (1:50,000 scale) : 400 sq.km

2. Sampling: a. Stream Sediment Sample (SSS)

(2 Km X 2 Km) : 100 nos

b. Soil Sample (C-horizon) : 6 nos c. Regolith Sample (R) : 6 nos

d. Humus Sample (H) : As necessary

e. Stream Water Sample (SW) : 12 nos f. Duplicate SSS (3 to 5% of the area) : 6 nos

3. Analysis of samples: 130 nos

400

113

6 6

0

6 6

170 145909 Rs. 858.29/-

5. GEOCHEMICAL MAPPING IN MEGHALAYA GNEISSIC COMPLEX IN PARTS OF JAINTIA AND EAST

KHASI HILLS DISTRICT, MEGHALAYA (TOPOSHEET

NOS. 83C/07 & PART OF 83 C/03) Code No.: GCM/NER/SME/2013/012

H. Sumar

&

A.S.Bora

(Chemist)

1. GCM (1:50,000) scale: 800 sq.km

2. Sampling: a. SSS (Stream sediment sample): 416 nos

b. Composite samples:208 nos

c. R (Regolith): 11 nos d. C (C-horizon soil): 11 nos

e. H (Humus): As necessary

f. SW ( Water samples) : 22 nos

g. F (Flood plain sediments): As necessary

h. 5 % duplicate samples: 11 composites

3. Analysis of samples: 263 nos

205 207438 Rs. 1011.89/-

59

6. GEOCHEMICAL MAPPING IN TOPOSHEET NO

83C/03 IN PARTS OF EAST KHASI HILL AND JAINTIA HILL DISTRICTS, MEGHALAYA.

Code No.: GCM/NER/SME/2012/014

Ajay C. Limbu

&

T. Myelvaganan

(Chemist)

1. GCM (1:50,000) scale: 400 sq.km

2. Sampling: a. SSS (Stream sediment sample): 208 nos

b. Composite Samples: 104 nos

c. R (Regolith): 5 nos d. C (C-horizon soil): 5 nos

e. H (Humus): As necessary

f. SW (Water samples): 10 nos

g. F (Flood plain sediments): As necessary

h. 5 % duplicate samples: 5 composites

3. Analysis of samples: 129 nos

800

416

208

11 11

0

22 22

04

118 138758 Rs. 1175.91/-

7. CHEMICAL MAPPING IN TERTIARY FOLD BELT OF SOUTH TRIPURA DISTRICT, TRIPURA (IN PARTS OF

T.S. Nos. 79M/12, 16 & 79N/9)

Code No.: GCM/NER/STM/2013/013

J.M.Umlong &

M.P. Singh

&

Rajendra Kumar

(Chemist)

1. GCM (1:50,000) scale: 850 sq.km 2. Sampling:

a. SSS (Stream Sediment Samples) : 850 nos

b. CS (Composite samples) :216 nos c. R (Regolith) : 12 nos

d. C (C-horizon Soil) : 12 nos

e. H (Humus) : As necessary f. SW ( Water Samples): 24 nos

g. F (Flood plain sediments): As necessary

h. Duplicate samples : 5% : 11 nos 3. Analysis of samples: 275 nos

850

659*

220£ 12

12

0 24

0

11

319 193261 Rs. 605.83/-

MISSION-IA (BASELINE GEOSCIENCE DATA GENERATION)

Programme : Ground Surveys – Geophysical Mapping

8. GRAVITY-MAGNETIC MAPPING IN PARTS OF WEST KHASI HILLS DISTRICT, MEGHALAYA.

Code No.: GPM/NER/RHQ/2013/014

S.M.Syiem

&

P. Diwakar Reddy

GPM (1:50,000 scale) : 1750 sq.km

Gravity Obs.

Magnetic Obs.

1400 431

431

327 335418 Rs. 1025.74/-

MISSION: IB (BASELINE GEOSCIENCE DATA GENERATION)

Programme : Remote Sensing and Aerial Surveys : Photogeology & Remote Sensing

9. GEOLOGICAL MAPPING IN PARTS OF MEGHALAYA WITH THE HELP OF REMOTE SENSING

STUDIES ON 1:50000 SCALE (9 TOPOSHEETS)

Code No.: PRS/NER/RHQ/2013/015

S. Sanyal

(transferred),

H.C.Shahu

Geological mapping on 1:50,000 scale using

remotely sensed data with selected field checks in T. S. Nos. 78G/15; 78K/3, 4, 8, 12, 16; 78O/16; and

83C/4, 8 : 1150 sq.km

900 13 21363 Rs. 1643.31/-

60

MISSION-II

Major Activity Areas Name of

Officers

Target for the

Field season

Achievement

during F.S. 2013 -

2014

(since Apr. 13)

Field Days Total Exp.

Rs

Per day Exp.

(Tentative)

Rs/per day

MISSION: II (NATURAL RESOURCES ASSESSMENT)

Programme: Mineral Resource Assessment

10. 1.PRELIMINARY APPRAISAL OF ECONOMIC POTENTIAL OF

LIMESTONE/ DOLOMITIC LIMESTONE IN EAST SIANG DISTRICT,

ARUNACHAL PRADESH (G4)

Code No.: ME/NER/SAP/2013/016

Bendangnuchit

&

Rita Thurr

1. Geological Survey

i. LSM (1:12,500): 75 sq.km

2. Technological i. PT : 30 cu.m

3. SMPL

i. BRS : 50 nos ii. PTS: 20 nos

iii. PS : 20 cu.m

iv. PCS: 20 nos 4. Chemical: 90 nos

75

30

50 20

20

20 101

264 268393 Rs. 1016.64/-

11. 2.PRELIMINARY ASSESSMENT FOR LIMESTONE IN AND AROUND

DABA GAMLIN, WEST SIANG DISTRICT, ARUNACHAL PRADESH (G3)

Code No.: ME/NER/SAP/2013/017

Amit Kumar, P.S.

Mishra & A.K. Singh

1. Geological Survey

i. LSM (1:10,000 / 12,500): 50 sq.km

ii. DM (1:2,000): Nil 2. Technological

i. PT: 25 cu.m

ii. Drilling: Nil 3. SMPL

i. PTS : 25 nos ii. PCS: Nil

iii. PS : 15 nos

iv. PCS: 25 nos

v. Channel Sampling: 50 nos

4. Chemical: 100 nos

54

0

28

0

26 0

29

36 77

140

259 184441 Rs. 712.13/-

12. 3.INVESTIGATION FOR PGE AND GOLD MINERALIZATION IN MAFIC-ULTRAMAFIC SUITES, ANJAW, LOHIT AND LOWER

DIBANG VALLEY DISTRICTS, ARUNACHAL PRADESH (G4)

Code No.: ME/PM/NER/SAP/2012/026

Ravi Negi

&

Hiruj Saikia

1. Geological Survey

i. LSM (1:10,000 / 1:12,500) : 50 sq.km

ii. DM (1:2,000 / 1,000): 2.5 sq.km

2. SMPL

i. BRS: 50 nos

ii. PS: 20 nos

iii. Ore Microscopy: 05 nos

iv. EPMA / SEM: 10 nos v. PGE: : 10 nos.

3. Chemical: 60 nos

50 2.50

50

20

5

10 10

60

187 187889 Rs. 1004.75/-

13. 4.PRELIMINARY INVESTIGATION FOR REE IN SOUTHERN PART OF AGIA AROUND SUJUKONA HILL AND TUKURESWARI HILL IN

PARTS OF GOALPARA DISTRICT, ASSAM (G4)

Code No.: ME/NER/SAS/2012/084

Arup Kumar Bora,

M. Shyamkumar

Singh,

A.K.Mishra

(Transferred w.e.f

30.06.2013), Th. N. B.

Singha (inducted

since oct, 2013)

1. Geological Survey i. LSM (1:12,500) : 50 sq.km

ii. DM (1:2,000): 1.5 sq.km

2. Sampling i. BRS: 50 nos

ii. SSS: 80 nos

iii. PS: 25 nos

iv. EPMA: 15 nos

v. PCS: : 25 nos

77

1.50

103

70

43 0

30

339 242703 Rs. 716.00/-

61

3. Chemical: 155 nos 203

14. 5.PRELIMINARY INVESTIGATION FOR PLATINUM GROUP OF ELEMENT IN OPHIOLITE BELT OF NAGALAND (G4)

Code No.: ME/PM/NER/SMN/2012/028

N. Meribemo

Yanthan

&

1G (Petrology) (P/T)

1. Geological Survey

i. Reconnoitary Geological Traverse Mapping on 1:50,000 scale. :150 sq.km

2. SMPL

i. PS: 25 nos

ii. OM: 10 nos

iii. EPMA / SEM :15 nos

iv. PCS (Major/Trace/REE): 30 nos v. PGE: 25 nos

vi. Channel Sampling: As necessary

3. Chemical: 55 nos

150

25 10

15

30 25

0

55

132 197022 Rs. 1492.59/-

15. 6.INVESTIGATION FOR TITANIFEROUS-VANADIFEROUS

MAGNETITE AROUND RAMBRAI IN WEST KHASI HILLS

DISTRICT, MEGHALAYA (G4)

Code No.: ME/F/NER/SME/2012/023

V.Sreenivasiah

1. Geological Survey

i. LSM (1;10,000 / 1:12,500) : 25 sq.km

ii. DM (1:2,000): 1.5 sq.km 2. Technological

i. PT: 25 cu.m

3. Geophysical Survey i. GP (Magnetic): 10 L.km

4. SMPL

i. BRS: 50 nos

ii. PS : 10 nos

iii. OM: 05 nos

iv. EPMA : 05 nos

v. PCS (PGE) : 05 nos

vi. PCS (REE) : 05 nos

5. Chemical: 60 nos

25

1.50

30

10.10

60 10

5

5

5

5

70

176 294373 Rs. 1672.57/-

16. 7.INVESTIGATION FOR LIMESTONE IN NORTH OF LARKET

BLOCK, LITANG VALLEY, JAINTIA HILLS DISTRICT,

MEGHALAYA (G3)

Code No.: ME/NER/SME/2013/018

Pius Sakhar

&

T.G.Singh

1. Geological Survey

i. DM (1:5,000) : 1.50 sq.km

2. Technological i. Drilling (RD-30; Unit No:427) : 800 m

3. SMPL

i. CS: 300 nos ii. PS: 05 nos

4. Baseline Parameters on Environment

i. Surface Water (SW): 06 nos ii. Soil samples (SS): 06 nos

iii. Rock: 03 nos

5. Chemical: 315 nos

1

.50

281.70

112 5

6 6

3

127

237 370317 Rs. 1562.65/-

17. 8.ASSESSMENT OF LIMESTONE IN THE EXTENSION AREA OF MAWLONG - ISHAMATI BLOCK OF SHELLA - BHOLAGANJ BELT,

EAST KHASI HILLS DISTRICT, MEGHALAYA (G3)

Code No.: ME/NER/SME/2013/019

Aravind

&

Rajesh Kumar

1. Geological Survey i. DM (1:5,000) : 1.50 sq.km

2. Technological

i. Drilling (RD-30; Unit No:441) : 800 m 3. SMPL

i. CS: 300 nos

ii. PS: 05 nos 4. Baseline Parameters on Environment

i. Surface Water (SW): 08 nos

ii. Soil samples (SS): 08 nos iii. Rock: 05 nos

5. Chemical: 321 nos

1.50

83.10

22

8

8

9 6

0

209 296394 Rs. 1418.15/-

62

18. 9.PRELIMINARY INVESTIGATION FOR REE IN PARTS OF

NONGPOH PLUTON, RI-BHOI DISTRICT, MEGHALAYA (G4)

Code No.: ME/NER/SME/2013/020

Mohd Sadiq

&

Ravi Kumar Umrao

1. Geological Survey

i. LSM (1:12,500): 60 sq.km 2. SMPL

i. BRS: 50 nos

ii. SSS: 50 nos iii. SS: 15 nos

iv. PS: 25 nos

v. PCS: 25 nos vi. EPMA: 10 nos

vii. XRD: 10 nos

3. Chemical: 140 nos

60

55

50 29

31

25 10

20

172

250 249058 Rs. 996.23/-

19. 10.MAGNETIC SURVEY FOR CHROMITE BEARING ULTRAMAFICS IN MANTUM CHING, CHANDEL DISTRICT, MANIPUR, (G4)

Code No.: GPS/NER/RHQ/2013/021

K.V. Sathyanarayana

&

M.K. Rai

1. Geophysical Survey i. Magnetic Survey (100m x 50m Grid): 5.6

sq.km

6.09

254 250877 Rs. 987.70/-

20. 11.PRELIMINARY STUDY FOR THE BASE METALS AND

ASSOCIATED GOLD IN EXTENSION AREAS OF DIKCHU BASEMETAL PROSPECT, EAST DISTRICT, SIKKIM (G4)

Code No.: ME/BM/NER/SSK/2012/027

Kailash Singh

&

Tangtirenba

Longchari

&

1G (DMMG)

1. Geological Survey

i. LSM (1:10,000/12,500) : 50 sq.km

2. Ground Geophysical Survey i. GP: As necessary

3. Technological

i. PT: 25 cu.m 4. SMPL

i. BRS: 40 nos

ii. SSS: 15 nos iii. PTS: 25 nos

iv. PS: 30 nos

v. OM: 10 nos vi. Fluid inclusion studies: 05 nos

5. Chemical: 80 nos

50

0

25

40

15

25 30

10

10 80

33

276 222411 Rs. 805.84/-

MISSION: II (NATURAL RESOURCES ASSESSMENT)

Programme: Natural Energy Resource (Except Oil & Gas)

21. 12.PRELIMINARY APPRAISAL TO LOCATE POTENTIAL COAL

ZONE IN TERTIARY SEQUENCE BY LARGE SCALE GEOLOGICAL MAPPING ON 1:10,000 SCALE IN PARTS OF TOPOSHEET NO. 78G/14

AROUND SHALIBHUIN IN DHUBRI DISTRICT OF ASSAM AND

NAKAIGIRI-UJANGGIRI IN WEST GARO HILLS OF MEGHALAYA (G3)

CodeNo.: ME/NER/NEnR/SAS/2012/030

Vizolto Sakhrie (P/T)

&

D.V. Whourie (P/T)

1. Geological Survey

i. LSM : 6.5 sq.km (1:10K scale with 5m contour interval)

2. Technological

i. PT: As necessary

ii. Drilling (RD-60; Unit No:422) : 300 m

3. Sample

i. CS : As necessary ii. PS : 10 nos.

iii.Coal Petrology : 05 nos.

4. Chemical: As necessary

1.40

161.65

0 4.0

0

0

36 63236 Rs. 2873.54/-

22. 13.REGIONAL EXPLORATION FOR GONDWANA COAL IN THE AREA ADJACENT TO SUKCHAR - SINGRIMARI AREA,

SINGRIMARI COALFIELD, DHUBRI DISTRICT, ASSAM AT THE BORDER OF ASSAM & MEGHALAYA

Code No.: ME/NER/NEnR/SME/2013/022

Vizolto Sakhrie (P/T)

&

D.V. Whourie (P/T)

1. Geological Survey

i. LSM : 3 sq.km

2. Geophysical Survey

i. GP (Resistivity): As necessary

ii. B.H. Logging: As necessary

3. Technological

i. Drilling (RD-60; Unit No:422) : 600m

4. Sample

i. CS : As necessary

3.00

0 0

346.45

0

91 261492 Rs. 1756.56/-

63

ii. CPS : 03 nos.

5. Updating of Coalfield Map (1:50,000):

3 sq.km

6. Resource Assessment: As necessary

1

3 0

MISSION: IV (FUNDAMENTAL AND MULTIDISCIPLINARY GEOSCIENCE AND SPECIAL STUDIES)

Major Activity areas Name of Officers Target for the Field season Achieve during FS 2013-14

(since April 2013)

Fild Days Total Expenditure Per day

Expenditure

(Tentative)

Programme : Geotechnical, Landslide & Seismic Studies

1.UPDATION OF EXISTING LANDSLIDE INVENTORY OF

NORTH EASTERN REGION

Megotsohe Chasie,

S.C.Keshari, P.K. Sarma,

E.John, Watitemsu,

Thrideep Kumar N. , P. K.

Theophilus, B.R.Syngai ,

Yhunyelo Tep, N.Meribemo

Yanthan, Elow A. & Jagdish

Nandan Hindayar

Preparation of Landslide Inventory for the reported

landslides in the group of eight

states of NER and updating the inventory with index maps and

photographs: As

necessary

Database prepared for A total of 69 nos field days were spent by the

officers of LHZP, RHQ,

Shillong in carrying out the work.

Rs. 29,983/- Rs. 434.53/-

Assam: 1 Earth-Soil slide & 1 Rock fall

(Total-2 nos.).

CodeNo.:SER/NER/RHQ/2013/

030 Arunachal: 2 cut-slope failures, 29 Rock slides, 2 Unconfined debris flow, 2 Confined

debris flow and 21 Debris slides (Total-56

nos.).

Meghalaya: 1 rock fissure-ground crack and

1 debris slide (Total-2 nos.).

Mizoram: 5 rock slides & 3 Debris slides (Total-8 nos.).

Nagaland: 1 Slope failure, 1 Rock fall, 1

Complex slide, 1 Earth slide, 7 Debris slides & 1 rock slide (Total-12 nos.).

Sikkim: 1 mudslide & 1 debris flow (Total-2

nos.).

NER TOTAL : Database prepared for 82

cases

2. MACRO SCALE LANDSLIDE

HAZARD ZONATION (1:50,000)

ALONG THE HAYULIANG -CHAGLAGAM AND TEJU-

HAYULIANG ROAD

CORRIDORS OF ANJAW DISTRICT, ARUNACHAL

PRADESH

Megotsohe Chasie, S.C.

Keshari & P.K. Theophilus A)PRE-FIELD

COMPONENTS (HQ based):

150 sq.km

88 nos field days

Rs. 88,050/- Rs. 1000.56/-

1. Compilation of geological map

on 1:50,000 scale 150 sq.km

2. Preparation of slope facet map on 1:50,000 scale

150 sq.km

3. Preparation of slope

morphometry map on 1:50,000 scale

150 sq.km

CodeNo.: LHZ/NER/RHQ/ 2013/

031 4. Preparation of relative relief

map on 1:50,000 scale

150 sq.km

64

5. Study of satellite imageries and

preparation of lineament map on 1:50,000 scale

150 sq.km

B) FIELD COMPONENTS:

150 sq.km

150 sq.km

Collection of relevant field

attributes for preparation of

landslide hazard zonation on 1:50,000 scale following GSI

Guidelines (2005) pertaining to

the various themes, viz. Slope morphometry, Relative relief,

Lithology, Structure, Landuse,

Landcover, Landslide incidences, Slope erosion, Hydro-geological

condition and Rainfall (Average

Annual Rainfall)

3. DETAILED (1:1000) SITE

SPECIFIC GEOLOGICAL

STUDIES OF THE LANDSLIDES NEAR TAWANG MONASTERY,

TAWANG DISTRICT,

ARUNACHAL PRADESH

Megotsohe Chasie , P.K.

Theophilus & 1G (P/T) from

EG Division

1.DM on 1:1000 scale* ( contour

map on required scale to be

provided by PWD Dept, Government of Arunachal): 0. 50

sq.km

0.50 sq. km.

74 nos field days Rs.60,512/- Rs.812.86/-

2.Geological profile ( along and across the slope): As necessary

4-along and 1-across Profile sections taken.

Code No.:LHZ/NER/RHQ/ 2013/

032 3.Geological profile ( along and

across the slope): As necessary1.

Collection of undisturbed soil

sample and determination of

physical parameters [size

analysis, moisture content ,

cohesion(c) and angle of

internal friction(f), etc ]: As

necessary

4 undisturbed soil samples and 4 disturbed

soil samples collected and the samples submitted to Geotechnical Lab, ER, Kolkata.

4.Collection of rainfall data ( pre

and post monsoon): As necessary

Collected from the Rural Works Dept.,

Tawang.

5. Geophysical survey*:

Electrical and resistivity survey

to be taken up by Arunachal Government:2 line km

6.Drilling* ( to be taken up by Arunachal Government): 8 bore

holes down to bed rock/

competent foundation

Identified nine suitable borehole locations

7. Logging of drill cores from

65

Boreholes: As necessary

8. Stability analysis: As

necessary

To be carried out after obtaining the required inputs

4. DETAILED STUDY OF THE

13TH MILE LANDSLIDE ON GANGTOK-NATHULA ROAD,

EAST DISTRICT, SIKKIM

Megotsohe Chasie , P.K.

Theophilus , 1G (P/T) from

EG Division, Jagadish

Nandan Hindayar (P/T) & P.

N. Dasarwar (P/T)

1. Delineation of slide-scars

within the distressed zone: As

necessary

1) 32 slide scars 111 nos field days by

officers and 8 days by the Supervisory officer

Wages : 46,206/-

POL : 30,005/- OC: 33,881/-

Rs.991.81 /-

Code No.: LHZ/NER/SSK/ 2012/

043

2. DM on 1:1000 scale of the

13th

Mile Slide : 0.25 sq.km

2) 0.25 sq km

3. Undisturbed soil samples: 3

nos

3) 8 nos. Total : 1,10,092/-

4. Identification of appropriate

locations for erection of Survey

Pillars for future monitoring:

Monitoring of the Survey

pillars

4) 8 locations have been identified for erection

of survey pillars

5. Erection of Survey Pillars and monitoring of Survey Pillars: 6

nos

5)16 nos pillars erected and monitored

6. Rainfall data: As necessary 6) Rainfall Data from Jan 13 to Feb 14

7. Profile (3 nos.): As necessary 7) 03 nos. Profile sections

5. MACRO SCALE LANDSLIDE

HAZARD ZONATION ON 1:50,000 SCALE ALONG

RANGPO-SINGTAM-DIKCHU-

CHUNGTHANG ROAD CORRIDOR, SIKKIM

Jagadish Nandan Hindayar

(P/T), Thrideep Kumar N. &

Murali Mohan (P/T)

A. Field components: 100

sq.km

1.Preliminary landslide hazard

zonation on 1:50,000 scale

through collection of field data for preparation of different

thematic maps, viz;

100 sq km mapping carried out in the study

area.

157 nos field days by

officers and 9 days by the Supervisory officer

Wages : 40,344/-

POL : 28,965/- OC: 25,286/-

Rs.602.51 /-

CodeNo.:LHZ/ NER/ SSK/ 2013/

033 a. Slope morphometry

map.

b. Relative relief map.

c. Lithological map.

d. Structural map. Total : 94.595/-

e. Landuse map.

f. Landcover map.

g. Landslide incidences

map.

h. Hydro-geological map.

66

2. Collection of average rainfall

data

Collected rainfall data of Sankalang, Sikkim

B. Headquarter components:

Pre-field components

100 sq.km

1. Preparation of slope facet map (1:50,000

scale)

Prepared the slope facet map for the study area (1:50,000 scale)

2. Preparation of slope morphometry map

(1:50,000 scale)

Prepared the Slope Morhometry & Relative Relief maps for the study area (1:50,000

scale)

3. Preparation of

lineament map* from

satellite imagery (1:50,000 scale)

Prepared the Lineament map for the study

area (1:50,000 scale)

Post-field component

a. Finalization of thematic maps on GIS

platform.

All thematic maps has been updated and finalised.

b. Preparation of DEM on GIS platform.

Digital Elevation Model (DEM) has been prepared.

6. SEISMIC AND LANDSLIDE

HAZARD ASSESSMENT OF AIZAWL TOWN, MIZORAM Code No.: SEI/NER/RHQ/ 2012

/038

P. Jana, L. H. Moirangcha,

D. Chakraborty (PT), S.N.

Chowdhury & G.S.

Dharamwal

A. PGRS component:

Analysis of past Seismicity data and seismotectonic features of the

area in 300 km radius around

Aizawl for characterization of seismic source parameters in the

area

1.Collection of data on past seismicity from

IMD, USGS, etc

B. Geological component: 50

sq.km Geological Mapping: (1: 25,000

scale)

2. Study of Seismic source area (Active Faults) from Seismotectonic Atlas &

Seismicity data. 50 sq.km

C. Profile section / measurement :

5 L.km

5 L Km

D. Determination of Geotechnical Properties of rocks and soil /

sediments: 10 nos.

10 Nos. (5 Nos. each of Soil and rock sample) 1 Collection of 13 year rainfall data

2. Study of Master Plan of the Area.

3. Demography – Collection of relevant data from the concerned State Govt. Officials.

4.Preparation of land use and land cover map from toposheet, Satellite data, etc.

5.Collection and synthesis of relevant sub

surface and ground water information for

67

certain locations of Aizawl master plan area.

E. Studies of Ground Water, Demography, Landuse map: 50

sq.km

50 sq.km

F. Landslide Hazard Assessment (1: 50,000 / 25,000 scale): 50

sq.km

G. Geophysical Study: i) Site response study by

measuring ambient noise using

short period Seismograph at every 1 - 2 km. station spacing:

50 sq.km

ii) Resistivity sounding at selected sites : 50 sq.km

50 sq km

7.SEISMIC AND LANDSLIDE HAZARD ASSESSMENT OF KOHIMA CITY, NAGALAND

V Shivgotra & Imtikumzuk, P.K. Chakraborty (GP) & 1 (GP)

A. Analysis of past seismicity data: Analysis of past Seismicity data and seismo-tectonic features of the area in 300 km radius around Kohima for characterization of seismic source parameters in the area.

Study and analysis of seismicity data covering 300Km radius around Kohima.

152 Days Rs. 1,11,564/- Rs.733.97 /-

Code No.: SEI/NER/RHQ/ 2013/034 B. PGRS component:

Preparation of Morpho-

tectonic map from Study

Satellite imageries and Aerial

photographs

PGRS of 250 sq.km area and

preparation of morphotectonic

map

250 sq. km

C. Geological component: 50

sq.km Geological Mapping: (1: 25,000 scale)

50 sq. km

D. Profile section /

measurement : 5 L.km

3.0 LKm

E. Determination of

Geotechnical Properties of

rocks and soil / sediments: 10

nos.

Six rock samples and 4 soil samples for

analysis of different geotechnical parameters.

F. Studies of Ground Water,

Demography, Landuse map: 50

Study of Master Plan area Map with landuse

pattern and Rainfall data of Kohima town

68

sq.km

G. Landslide Hazard

Assessment (1: 50,000 / 25,000

scale): 50 sq.km

Preparation of slope facet map, calculation of

RR and slope morphometry, collection of different Geo-factors for Landslide hazard

assessment covering 50 sq. km.

H. Geophysical Study: i) Site response study by

measuring ambient noise using

short period Seismograph at

every 1 - 2 km. station spacing:

50 sq.km

-Study of few landslide incidences.

- Processing of data for delineation of

different hazard zones.-

8. SITE SPECIFIC STUDY OF PROPOSED PAKYONG AIRPORT AREA, SIKKIM Code No.: LHZ/NER/SSK/

2013/035

Lopamudra Bhol & Mohd.

Ibrahim & 1G (P/T) from EG

Division

A. Field components: 25 sq.km 1. Preliminary landslide hazard zonation on 1:25,000 scale in and around Pakyong area through collection of field data for preparation of different thematic maps, viz;

25sq km

164 field days spent by officers. This includes officer 11 days of Officer from EG Division, Shillong as well and 10 days by Supervisory Officer

Wages : 50,436/-

POL : 39,890/-

OC: 35,274/-

Rs.765.85/-

1. Slope morphometry map

2. Relative relief map Total : 1,25,600/-

3. Lithological map

4. Structural map

5. Landuse map

6. Landcover map

7. Landslide incidences map

8. Hydro-geological map

2. D.M. (1:2000) in and around Pakyong airstrip by using total station survey instrument: 1 sq.km

01 sq km

3. Geotechnical properties of rocks and soil / sediments at (1x1) km grid pattern: 25 nos

25 nos. of soil and 5 nos. of rock samples

have been collectedand submitted in GT Lab GSI, ER, Kolkata

4. Stability analysis: As necessary

69

5. Rainfall data: As necessary/ available

Rainfall data has been collected

6. Geophysical study: 25 sq.km Nil

a.

Site response study by measuring ambient

noise using short period

seismograph at every 1-2 km station spacing in

and around Pakyong

area

Site response study by measuring ambient noise using short period seismograph at every 1-2 km station spacing in and around Pakyong area for 25 sq km area has been carried out by CGD, Kolkata.

b. Resistivity survey.

B. Headquarter components: Pre-field components Post-field component Finalization of thematic maps on

GIS platform: As necessary

a Preparation of slope facet map (1:25,000 scale): 100 sq.km

Digital Elevation Model (DEM), Slope facet map and Lineament density map for 100 sq. km. on 1:25,000 scale have been completed.

b Preparation of lineament density map from satellite imagery (1:25,000 scale):100 sq.km

9.SEISMIC HAZARD ASSESSMENT OF GANGTOK AND SURROUNDING AREAS OF SIKKIM Code No.: SEI/NER/SSK/ 2012

/039

Murali Mohan (P/T), P.N. Dasarwar (P/T), S.N. Chowdhury (GP) (P/T) & G.S. Dharamwal (GP) (P/T

A. Geological Mapping: (1:25,000 scale) : 50 sq.km

A. 50 sq. km Geological mapping on 1:25,000 scale has been carried out in and around Gangtok.

121 days Officers and

17 Days Supervisory officer

Wages : 47,608/-

POL : 38,125/- OC: 21340/-

Rs.884.90/-

B. Profile section / measurement : 5 L. km

B. Profile section / measurement : 5L.km Total : 1,07073/-

C. Determination of Geotechnical Properties of rocks and soil/ sediments: 25 nos.

C. 25 nos. soil samples for Geotechnical

properties collected and send to GT Lab, ER,

Kolkata.

D. Studies of Ground Water, Demography, Landuse map : 50 sq.km

D. Studies of ground water, demography & Landuse map : 50 sq.km

E. Geophysical Study: 100 sq.km i) Site response study by measuring ambient noise using short period Seismograph at every 1 - 2 km station spacing.

E. Geophysical studies completed

70

F. GPS study 1. Semi-permanent station preparation: 5 nos 2. GPS data collection (5 day / year): 1 set from 5 nos. stn 3.GPS data analysis by GAMIT/GLOBK software: 1 set data

DGPS data collection from all 5 Semi

permanent stations

10.GEOTECHNICAL EVALUATION OF WATER RESOURCE DEVELOPMENT PROJECTS IN ARUNACHAL PRADESH CodeNo.: EG/C/NER/RHQ/2013

/036

D. Chakraborty (P/T) & G.Rongmei (P/T)

1. Kameng H.E.Project, West Kameng district, Arunachal Pradesh. Geotechnical investigation for open and underground excavations.

KaHEP, Package- I, II & III (Sponsor: NEEPCO) a) Bichom Dam Complex (KaHEP, Package-I),

70 field days by

officers Dr. Vinod Kumar OC: Rs. 9027/- POL Rs. 10,000/- Dr. D. Chakraborty OC: 21,802/- POL: 7935/- Dr. G.Rongmei OC: 11,445/- POL:3000/- TOTAL: OC: 42,274/- POL: 20,935/-

Rs.902.98/-

1. Foundation grade geological mapping (1:100 scale) for Dam Block No. 13 & 12 (part) covering 841 sq.m area (approx.).

2. Geological logging (1:50 scale) of HRT face-II (heading) at chainage 3103.25m, 3104.75m, 3106.75m, 3109m, 3110m and 3111m.

3. Foundation grade geological mapping (1:100 scale) for Dam Block No. 7 covering 700 sq.m area (approx.).

4. Foundation grade geological mapping (1:100 scale) for Dam Block No. 10 & 9 (part), covering approximately 2291 sq.m area (approx).

5. Foundation grade geological mapping (1:100 scale) for Dam Block No. 8 covering 1070 sq.m area (approx.).

b) Tenga Dam Group (KaHEP, Package-II):

71

1. Foundation grade geological mapping (1:100 scale) for Dam Block No. 4, covering 330 sq.m area (approx.)

2. Foundation grade geological mapping (1:100 scale) for Dam Block no. 1 covering 108m2 and upstream apron area covering 20.5m2.

3. Foundation geological mapping (1:100 scale) for part of dam block number 2, covering approximately 200 sq.m area.

4. Foundation geological mapping (1:100 scale) for part of dam block number 2, covering approximately 120 sq.m area.

c) Kimi Power House Complex (KaHEP, Package-III).

1 Foundation grade geological mapping (on 1:100 scale) of Turbo Generator (T.G.) Unit-IV, totaling 320 sq.m. area.

2 Foundation grade geological mapping (on 1:100 scale) of anchor block number 8 for penstock unit 1 & unit 2, totaling 96 sq.m. area

3 Foundation grade geological Mapping (1:100 scale) at Kimi Power House area for Anchor Block-3 & 7A,

72

covering 180sq.m area.

4 Foundation grade geological Mapping (1:100 scale) at Kimi Power House area for Anchor Block-7B (Unit 1), covering 18sq.m area

Pare H E Project (Addl. Item), Sponsor: NEEPCO

1. Assessment of the quantum of geotechnical work to be generated at project site.

2. Drill core logging of boreholes DH-3 and DH-4 with cumulative length of 101.8m each 50.3m and 51.5m respectively

3. Drill core logging of boreholes DAH-5 for 67.50m depth.

4. Foundation geological mapping of Dam Block No. 4 covering 200 sqm on 1:100 scale.

Noa Dehing M P Project (Addl. Item), Sponsor: Brahmaputra Board

1. Reconnoitary traverse had been carried out towards left bank and right bank of proposed dam site along with drill core logging of 7 bore holes (at dam site area) totaling 313.50m.

2. Carried out drill core logging of 3 bore hole no.14, 16 &23 for a cumulative length of

73

136.30m.

11. GEOTECHNICAL EVALUATION OF WATER RESOURCE DEVELOPMENT PROJECTS IN ASSAM

D. Chakraborty (P/T) & 1G (P/T)

Killing Multipurpose Project, Karbi-Anglong district, Assam. (Addl. Item): Geotechnical investigation towards proposed surge shaft, penstock, power house and TRT area.

Killing Multipurpose Project, Karbi-Anglong district, Assam. (Addl. Item): Geotechnical investigation towards proposed surge shaft, penstock, power house and TRT area..

6 Days Officers

CodeNo.:EG/C/NER/RHQ/2013/037

12. GEOTECHNICAL EVALUATION OF WATER RESOURCE DEVELOPMENT PROJECTS IN MIZORAM CodeNo.:EG/C/NER/RHQ/2013/ 038

Vinod Kumar (P/T) & G.Rongmei (P/T)

1.Tuipui H.E.Project, Champhai dist, Mizoram Planning for sub-surface exploration, logging of drill holes, drift, tunnel other excavation, interpretation from sub-surface exploration, detailed mapping at structural sites

Turial H E Project (sponsor: NEEPCO): 1.Geological mapping of Power House site was taken up, particularly the area affected by slide. Traverse along benches at various elevations were also taken up to examine the cracks, seepage and stability of slope. 2.Geological mapping of power House site was carried out on 1:250 scale covering an 30,100m2. 3.Face logging of inclined penstock tunnel at Chainage 141m covering an area of 26.6m. 4.Geological section observed along Dam axis. 5. Geological mapping in power house area totaling 20000 sq.m on 1:1000 scale. 6. three geological cross sections have been observed along- a) turbine axis, b) 20m south of turbine axis c) 20m north of turbine axis. 7, Projected geological plan at 30m RL along penstock alignment and 8. Dam site mapping forl 150 sq.m area.

34 Days officers

2. Turial H.E.Project, Aizawl District, Mizoram Geological mapping of dam and spillway area, geological mapping/ logging of High Pressure Tunnel (HPT).

3. Tlawng H.E Project, Aizawl District, Mizoram Planning for sub-surface exploration, logging of drill holes, drift, tunnel other excavation, interpretation from sub-surface exploration, detailed mapping at structural sites.

4. Tuichang H.E.Project, Hnahthial District, Mizoram Logging of drill holes, detailed mapping at structural sites and survey for constructural material.

5. Mat-Sekawi H.E.Project, Lunglei District, Mizoram. Logging of drill holes.

13. GEOTECHNICAL EVALUATION OF WATER RESOURCE DEVELOPMENT

Vinod Kumar (P/T), G.

Rongmei & D. Chakraborty

1. Selim H.E.Project, Jaintia Hills District, Meghalaya.

Mawblei H.E.P, West Khasi Hills District: a) Geological line traverse mapping has been

74

PROJECTS IN MEGHALAYA CodeNo.:EG/C/NER/RHQ/ 2013/ 039

(P/T) Alignment survey and mapping,

planning of sub-surface exploration ,logging of drill

holes, drift, tunnel/other

excavation, preliminary geological mapping of structural

sites.

carried out on 1:2500 scale along the water conductor system from Ch. 0.00m to power house area covering ~2800.00 LM. b) Borehole logging of 411m. 2. Upper Khri Diversion H.E.P, West Khasi Hills District: Carried drill core logging of bore hole no.7 & 8 for 70.05m . 3. New Umtru H E Project (Addl. Item): a. Discussion on tackling a cross drainage on right bank of Umtru River and extension of rock fill dam / embankments in extension of main RCC dam. b. Carried out drilled core logging for a cumulative depth of 80m (DH-11, 13 & 14) of New Umtru H.E.P, Ribhoi District, Meghalaya. c. Carried out geological L-section for a cumulative length of 650 Sq M of New Umtru H.E.P,Ribhoi District, Meghalaya. 4. Field evaluation of reported ground cracks at Tynnai village, near Mawkyrwat, SW Khasi Hills District, Meghalaya (T.S. 78 0/7). 5. Carried out 650m geological section observed along Penstocks alignment of Ganol Stage-1 H.E.P,Garo Hills District, Meghalaya. 6. Carried out geotechnical investigation along Water Conductor System (TRT) from power house to TRT outlet for about 4.71km.

2. Mawblei H.E.Project, West Khasi Hills District, Meghalaya

Alignment survey and mapping,

planning of sub-surface

exploration, logging of drill holes, drift, tunnel/other

excavation, preliminary

geological mapping of structural sites and interpretation from sub-

surface exploration.

3. Upper Khri Diversion Project, West Khasi Hills District, Meghalaya

Alignment survey and mapping,

planning of sub-surface exploration, logging of drill

holes, drift, tunnel/other

excavation, preliminary geological mapping of structural

sites, interpretation from sub-

surface exploration and interpretation from sub-surface

exploration.

4. Ganol Stage-II H.E.Project, West Garo Hill District, Meghalaya Alignment survey and mapping, planning of sub-surface exploration, logging of drill holes, drift, tunnel/other excavation, preliminary geological mapping of structural sites, interpretation from sub-surface exploration and interpretation from sub-surface exploration.

5. Myntdu – Leshka H.E. Project Stage-II, Jaintia Hills district, Meghalaya.

75

Logging of drill holes, drift, tunnel other excavation, preliminary geological mapping of structural sites and interpretation from sub-surface exploration.

6. Simsang M.P. Project, South Garo Hills, Meghalaya. Alignment survey & mapping, logging of drill holes, drift, tunnel other excavation, detailed mapping at structural sites and slope stability studies.

7. Myntang H.E Project,

Jaintia Hills District,

Meghalaya. Alignment survey & mapping,

logging of drill holes, detailed mapping at structural sites and

slope stability studies.

`

14.GEOTECHNICAL EVALUATION OF TRANSPORT AND COMMUNICATION PROJECTS IN NORTH EASTERN REGION

G.Rongmei (P/T) & Vinod Kumar (P/T)

Communicated to the project authorities seeking quantum of geotechnical work upto September, 13.

Communicated to the project authorities seeking quantum of geotechnical work upto March, 14.

Nil

Code No.:EG/C/NER/RHQ /2013/ 040

15. STUDY OF ARSENIC CONTAMINATION IN WATER AND SOIL IN PARTS OF NAGAON AND MARIGAON (WITH IN ERSTWHILE NAGAON DISTRICT) DISTRICTS, ASSAM

P.C. Srivastava Amiya Kumar Mondal John Kevi Angami Nitin P Nagmote (Chemist) & S. Dutta (STA-(C)

1. INTMAPSPL (1:50,000): 1000 sq.km

1000 sq.km

198 Days Officers 11 days Supervisory Officer

Wages : 74,576/- OC : 67,124/- OC (Vehicle out sourced) : 2,34,087/- POL (NRCA) : Rs.10,000/-

Rs.1948.41/-

Code No.: RP/NER/SAS/2012/ 082 2. Sampling:

(i) Water analysis by arsenic kit: 500 nos

500 nos

(ii)Chemical analysis for As, major and trace elements in: (a) Surface water: 50 nos (b) Ground water: 100 nos

50nos 100nos

(iii) Soil (‘C’ - Horizon): 10 nos 13 nos

(iv) BRS: 5 nos 5 nos

76

(v) Collection of relevant data from Gov.vt. / non-Govt. agencies: As necessary

7 nos

16. STUDIES AND

PREPARATION OF

PALAEONTOLOGICAL AND STRATIGRAPHICAL SECTIONS

ALONG SHILLONG – SOHRA,

SHILLONG – MAWSYRAM AND SHILLONG – DAWKI IN EAST

KHASI HILLS DISTRICT OF

MEGHALAYA

Surendra Prasad & Abir

Gupta (P/T) Preparation of three sections 42 Days Officers

22 Days Supervisory

Officers

POL : 25,668/-

OC: 27,515/-Wages

23,544/-

Rs.1826.59/-

1. L.km mapping (1:50,000

scale): 10 L.km

10.0 L. Km.

2. Reconnoitary survey

(1:50,000): 20 sq.km

20.0 sq. km. Total 76,717/-

Code No.: RP/NER/RHQ/ 2013/

041

3. Section measurement: As

necessary

5

4. Collection, Maceration and

study of fossils: As necessary

33

17. PETROGRAPHY AND GEOCHEMISTRY OF MAWPUT

MAFIC-ULTRAMAFIC SUITE

AND ASSOCIATED MINERALIZATION, JAINTIA

HILLS DISTRICT, MEGHALAYA

Sushree Mishra 1.Traverse Mapping on (1:

12,500): 10 L.km

10 Lkm 19 Days officer 5 Days Supervisory

Officer

POL: 9345/- OC : 27,288/-

Wages : 39,998/-

Total : 76,631/-

Rs.4033.21/-

Code No.: RP/NER/RHQ/2013/

042 2. SAMPLE

a. PS: 40 nos 40

b. PCS: 25 nos

(Major/Traces/REE

analysis)

25

3. Trace elements & REE by

ICP-MS: 25 nos

25

4. PGE & Au : 15 nos

(by Fire-assay and ICP-MS)

15

5. SEM/EDS: 10 nos 10

6. EPMA: 20 nos 20

7. Chemical analyses : 25 nos

(Whole rock and trace

elements)

25

77

ANNEXURE - 5

PROGRESS & PENDENCY REPORT OF CHEMICAL ANALYSES OF NGCM SAMPLES (upto 31.03.2014)

Sl

No Item Particular

1 Machine

Capacity in the

Region (nos. of

samples) per

month

Pkg. ‘A’

Pkg. ‘B’ Pkg.

‘C’

Pkg. ‘D’ Pkg. ‘E’ Pkg. ‘F’ Pkg.

‘G’

Pkg. ‘H’ Pkg.

‘I’

400/02 Chemists 200/02

Chemists

150/02

Chemists

125/01

Chemist

400/1

2. Capacity to analyse

in the Region (nos.

of samples) per

month

Pkg. ‘A’

Pkg. ‘B’ Pkg.

‘C’

Pkg. ‘D’ Pkg. ‘E’ Pkg. ‘F’ Pkg.

‘G’

Pkg. ‘H’ Pkg.

‘I’

400/02 Chemist 120/1 250/2 125/1 400/1

3. Total Nos. of

Samples Collected,

and

Pendency up-to

Field

Season 2012 -13

(since

beginning of the

NGCM

program)

Month Jan.

2013

Feb.

2013

Mar.

2013

Apr.

2013

May

2013

June

2013

July

2013

Aug.

2013

Sep.

2013

Oct.

2013

Nov.

2013

Dec.

2013

Jan.

2014

Feb.

2014

Mar

2014

Collected

Submitted

To Lab.

139 190 148 362 13 16 0 0 0 0 0 0 1174

Analyses Reported [up-to the month of ] [up-to Field Season 2012 – 13.]

Pkg. ‘A’ 326 505 560 810 948 1086 1174 0 0 0 0 0 0 0 0 1174

Pkg. ‘B’ 0 0 102 102 246 246 246 639 863 1174 0 0 0 0 0 1174

Pkg. ‘C’ 278 399 479 529 634 830 905 1158 1174 0 0 0 0 0 0 1174

Pkg. ‘D’ 0 183 432 632 881 1015 1137 1162 1174 0 0 0 0 0 0 1174

Pkg. ‘E’ 0 102 218 379 560 723 868 1124 1174 0 0 0 0 0 0 1174

Pkg. ‘F’ 0 0 0 349 349 349 349 730 730 1174 0 0 0 0 0 1174

Pkg. ‘G’ 244 349 475 758 758 758 1135 1135 1174 0 0 0 0 0 0 1174

Pkg. ‘H’ 0 0 82 82 228 480 530 738 738 1174 0 0 0 0 0 1174

Pkg. ‘I’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Pendency [up-to the end of the month ] [up-to end of Field Season 2012 -13]

Pkg. ‘A’ 119 130 223 335 210 88 0 0 0 0 0 0 0 0 0 0

Pkg. ‘B’ 445 635 681 1043 912 928 928 535 311 0 0 0 0 0 0 0

Pkg. ‘C’ 167 236 304 616 524 344 269 16 0 0 0 0 0 0 0 0

Pkg. ‘D’ 363 452 351 513 277 159 37 12 0 0 0 0 0 0 0 0

Pkg. ‘E’ 445 533 565 766 598 451 306 50 0 0 0 0 0 0 0 0

Pkg. ‘F’ 445 635 783 796 809 825 825 444 444 0 0 0 0 0 0 0

78

Pkg. ‘G’ 201 286 308 387 400 416 39 39 0 0 0 0 0 0 0 0

Pkg. ‘H’ 445 635 701 1063 930 946 644 436 436 0 0 0 0 0 0 0

Pkg. ‘I’ 445 635 783 1145 1158 1174 1174 1174 1174 1174 1174 1174 1174 1174 1174 1174

4. Total Nos. of

Samples

Collected/

analysed during

the current

Field Season

2013-14

Month Jan.

2013

Feb.

2013

Mar.

2013

Apr.

2013

May

2013

June

2013

July

2013

Aug.

2013

Sep.

2013

Oct.

2013

Nov.

2013

Dec.

2013

Jan.

2014

Feb.

2014

Mar

2014

Total

Collected

Submitted

To Lab.

0 0 0 0 0 67 0 14 15 52 48 82 319 201 266 1064

Analyses Reported [up-to the month of ]

Pkg. ‘A’ 0 0 0 0 0 0 0 67 81 128 164 164 278 454 597 597

Pkg. ‘B’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Pkg. ‘C’ 0 0 0 0 0 0 0 0 81 81 81 81 81 81 278 278

Pkg. ‘D’ 0 0 0 0 0 0 0 67 29 67 67 112 160 467 710 710

Pkg. ‘E’ 0 0 0 0 0 0 0 67 67 148 148 148 278 318 318 318

Pkg. ‘F’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Pkg. ‘G’ 0 0 0 0 0 0 0 23 23 104 104 228 228 228 538 538

Pkg. ‘H’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 197 197

Pkg. ‘I’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Pkg. ‘J’ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 234 234

Pendency [up-to the end of the month]

Pkg. ‘A’ 0 0 0 0 0 67 67 14 15 20 32 114 319 319 467 467

Pkg. ‘B’ 0 0 0 0 0 67 67 81 96 148 196 278 597 798 1064 1064

Pkg. ‘C’ 0 0 0 0 0 67 67 81 15 67 115 197 516 717 786 786

Pkg. ‘D’ 0 0 0 0 0 67 67 14 67 81 129 166 437 331 354 354

Pkg. ‘E’ 0 0 0 0 0 67 67 14 29 0 48 130 319 480 746 746

Pkg. ‘F’ 0 0 0 0 0 67 67 81 96 148 196 278 597 798 1064 1064

Pkg. ‘G’ 0 0 0 0 0 67 67 58 73 44 92 50 369 570 526 526

Pkg. ‘H’ 0 0 0 0 0 67 67 81 96 148 196 278 597 798 867 867

Pkg. ‘I’ 0 0 0 0 0 67 67 81 96 148 196 278 597 798 1064 1064

Pkg. ‘J’ 0 0 0 0 0 67 67 81 96 148 196 278 597 798 830 830

Note 1) Packages A, C, D, E and G-Analyzed in the Chemical Division, NER, Shillong. 2) Package B, F and H Analyzed in the Chemical Division, CCL

Chemical Lab. Kolkata.

79

ANNEXURE - 6

YEAR-WISE, STATE-WISE, PROGRESS REPORT PENDENCY

(2002-03 to 2013-14)

(As on 31.03.2014)

Region Total no. of Progress Reports Released up to

31.03.13

Total no. of Reports to be generated in

F.S.2013-14

Total no. of Reports Released Up to 31.03.2014

NER 22 Nos. of reports (2012-13) 38 nos. nil

MISSION-WISE PENDENCY (As on 31.03.2014)

REGION MISSION-I MISSION-II MISSION-IV TOTAL NO. OF

PROGRESS

REPORTS

PENDING

STM SGM GCM GPM RSAS ME GPS LHZ RP SEI ENG SER

NER 12 4 7 1 1 12 1 38 nos.

Total – 37 nos

Total Non-NGCM Reports:

Total NGCM Reports:

STM= SPECIALISED THEMATIC MAPPING, SGM= SYSTEMATIC GEOLOGICAL MAPPING, GCM= GEOCHEMICAL MAPPING, RSAS= REMOTE

SENSING AND AERIAL SURVEYS, ME = MINERAL EXPLORATION, GPS= GEOPHYSICAL SURVEY, LHZ= LANDSLIDE HAZARD ZONATION,

RP= RESEARCH PROJECT, SEI= SEISMIC, ENG= ENGINEERING, SER=SERVICE

YEAR-WISE PENDENCY (as on 31.03.2014)

Region Total no. of Progress Reports Pending up to 31.12.13

20

08-0

9

earl

ier

20

09-1

0

20

10-1

2

20

12-1

3

NER nil

@ All NGCM reports up to 2009-10 have been upgraded as per the comments/suggestions/modifications by the external peer reviewers and have been circulated.

80

ANNEXURE – 7

STATUS OF REPORT UPLOADING IN GSI PORTAL FOR FS 2013-14 (UPTO MARCH 2014)

Sl.

No

Data

Universe

(total

volume of

data)

Total

(Cumulative

achievements)

upto Mar. 2013

Target for

F.S.

2013-14

Achievement

F.S. 2013-14

Total

(Cumulative

achievements)

for F.S. 13-14

Total

(Cumulative

achievements

) April 13

to June

13

July 13 to

Sept. 13

Oct13 to Dec.

13

Jan. 13 to

March 13

1. Uploading of

legacy FSP

and

Extended

abstract

(EA)

FSP 22 years

(1987-2009

Uploaded 22 Vol.

of FSP (1987-88

to 2008-09)

------- ------- ------- ------- ------- Uploaded 22

Vol. of FSP

(1987-88 to

2008-09)

E.A. 22 years

(1987-2009

Uploaded 22 Vol.

of E.A. (1987-88

to 2008-09)

------- ------- ------- ------- ------- ------- Uploaded 22

Vol. of E.A.

(1987-88 to

2008-09)

2. Metadata of

Unpublished

reports

a) Pre -

2004

1757

Uploaded 1757

reports

------- ------- ------- ------- ------- ------- Uploaded

1757 reports

b) Post-

2004

414

Uploaded 414

reports

------- ------- ------- ------- ------- ------- Uploaded

414 reports

3. Actual

unpublished

reports Post

2004

201 reports Uploaded 201

reports

------- ------- ------- ------- ------- ------- Uploaded

201 reports

4. Actual

unpublished

reports Pre

2004

1015 reports Soft copy

converted 1015

reports and

uploaded into

------- ------- ------- ------- ------- ------- Soft copy

converted

1015 reports

and uploaded

81

Portal. into Portal.

5. Adding of Acc. Nos. of Unpublished Progress

Reports of GSI, NER for the F.S. 2012-13

uploaded in GSI portal

As

necessary

--------- -------- 39 (FS:2012-

13)

1(FS:2012-

13)

40 (FS:2012-

13)

40 (FS:2012-

13)

6. Publication of Rec. GSI, Vol. 147, Pt. 4

(Extended Abstract for F.S. 2012-13).

Collection

, editing

and

printing.

Material

being

collecte

d from

different

division

s and

compile

d

received

material

s

Material

being

collected

from

different

divisions

and

compiled

received

materials.

Compiled

materials

scrutinised by

Editorial

Committee

and attended

corrections/

modifications

.

Finalized,

printed and

released on

31.01.2014

Material

collected,

compiled,

edited, printed

and released

on 31.01.2014

and uploaded

in portal.

Material

collected,

compiled,

edited,

printed and

released on

31.01.2014

and uploaded

in portal.

7. d) Preparation of AGR for (Rec. GSI, Vol. 147, Pt.

1) (F.S. 2012-13)

Collection

and

editing

Material

being

collecte

d from

different

division

s and

compile

d

received

material

s

Manuscript

finalised

and

submitted

to Director,

PID, CHQ,

Kolkata on

23.07.2013

------- ------- Material

collected,

edited,

Manuscript

finalised and

submitted to

Director, PID,

CHQ, Kolkata

on 23.07.2013

Material

collected,

edited,

Manuscript

finalised and

submitted to

Director,

PID, CHQ,

Kolkata on

23.07.2013

8. e) GSI, e- News (NER), Vol. 23 (January, 2012 to

December, 2012).

Collection

, editing

and

e-printing

Material

being

collecte

d from

different

division

s and

Material

being

collected

from

different

divisions

and

Compiled

manuscript

scrutinised by

Editorial

Committee

and attended

corrections/

Manuscript

finalised

and

published

on GSI

Portal on

12.02.2014

Material

collected,

edited,

Manuscript

finalised and

Manuscript

finalised and

Material

collected,

edited,

Manuscript

finalised and

Manuscript

finalised and

82

compile

d

received

material

s

compiled

received

materials.

modifications

.

published on

GSI Portal on

12.02.2014

published on

GSI Portal on

12.02.2014

9. Scrutiny and processing of scientific papers/

abstracts submitted by the officers of the region.

Papers as

necessary

4 5 1 7 17 17

Abstracts

as

necessary

7 4 3 - 14 14

10. Information

Services

Sale of publication (in Rs.) As

Necessary

1363 2109 650 4260 8382 8382

Distribution of GSI publications. As

Necessary

22 428 67 202 719 719

11. Library

services –

Modernizati

on of

Library.

Procured Books As

Necessary

8 6 -- ---- 14 14

Procured Journals As

Necessary

42 47 22 24 135 135

12. Hard copies of reports for FS 2012-13 received As

Necessary

20 2 1 41 41

83

ANNEXURE – 8

CASE STUDIES UPLOADED IN GSI PORTAL

(ALL CASES AS WELL AS CASES UPLOADED DURING THE QUARTER)

Mission I

State : Author(s) F.S

Arunachal Pradesh Geochemical mapping in Bomdila-Dirang-Mathow area, West Kameng

district, Arunachal Pradesh - A Case Study

A.K. Grover 2003-04

Meghalaya Transect mapping along Barapani – Jorabat road section in parts of

Ri-Bhoi and East Khasi Hills districts, Meghalaya

Avi Mero and Vizolto Sakhrie

2010-12

Mission II

State : Author(s) F.S

Manipur - Nagaland Crude oil seepage and gaseous emanation from Mokokchung district,

Nagaland

SU: Manipur-Nagaland, Dimapur.

Manipur - Nagaland Incidence of platinum group of elements in Ophiolite belt of Manipur S. Raju, T.L. Shitiri, E. John & Aparajita

Bhattacharya

GSI, NER, SU: Manipur–Nagaland,

Dimapur

2009-10

Tripura-Mizoram Study of hard sandstone occurrences in south mizoram for their suitability

as building stones

K.Raju & N.J.Sumanth 2010-12

Meghalaya REE anomaly reported in carbonatites of Sung Valley, Jaintia Hills,

Meghalaya

A. Ranjith & Mohd. Sadiq 2010-12

Meghalaya A preliminary study on the newly discovered Carbonatite - Ultramafic

dykes and associated Lamprophyres of Padu-Nongryngkoh Area, Jaintia

Hills and East Khasi Hills Districts, Meghalaya

M.A. Khonglah, Sougrakpam Sujata,

Imlishila Imchen, R. Baskaran & K.V.

Ramachandran

2010-12

Meghalaya REE occurrence in Nongpoh Granite, Ri-Bhoi District, Meghalaya Mohd. Sadiq & Ravi Kumar Umrao 2012-13

Meghalaya Occurrence of laterite cappings in parts of Ri-Bhoi District, Meghalaya Mohd Sadiq, Ravi K. Umrao and B.B.

Sharma

2012-2013

Manipur Awaruite, a natural alloy of nickel and iron from Manipur

Ophiolite

Tapan Pal, Anindya Bhattacharya,

S. Sengupta, S. K. Tripathy & S. Nandi,

Meghalaya Evidences of Magma Hybridization - A Case Study from Nongpoh

Granitoids, Ri-Bhoi District, Meghalaya

Mohd Sadiq, Ravi Kumar Umrao & B.B.

Sharma

2013-14

Mission III

State : Author(s) F.S

Nil

84

Mission IV (Fundamental & Multidisciplinary)

State : Author(s) F.S

Meghalaya Vehicular Tunnel Project of Aizawl city, Mizoram: A Geotechnical

Evaluation.

R. Pitchai Muthu

Meghalaya Active fault studies along foothills of Assam- Bhutan Himalaya,

Kokrajhar (BTAD) District, Assam

Officers from SU: Meghalaya, Shillong.

Meghalaya Geotechnical evaluation of some foundation problems at Kitpi MHS in the

Tawang Valley of Arunachal Pradesh

Officers from SU: Meghalaya, Shillong.

Meghalaya Sonapur Landslide, Jaintia Hills District, Meghalaya Officers from SU: Meghalaya, Shillong.

Meghalaya Kyllang Granite Pluton V.V. Sesha Sai et al 2009-10

Meghalaya Dinosaur remains from Meghalaya - A case history Officers from SU: Meghalaya, Shillong.

Eastern Region Palaeobotanical study of the Gondwana equivalent sediments exposed in

the Rangit window, Sikkim

Dr. K.M. Wanjarwadkar

Eastern Region Macroseismic Survey of Sikkim Earthquake, 14th February,

2006

S. K. Som, P. Jana & U. Bhattacharya

ANNEXURE - 9

LIST OF PUBLICATIONS BROUGHT OUT IN THE LAST FIVE YEARS

Sl.No Title of Publication Periodicity of

Publication

When last published

(Date)

Whether Available

Soft copy Hard copy

1. Records of Geological Survey of India Vol. 141, Pt. 4 (FS: 2006-07) 22.01.2009 Yes

Yes

2. i) Records of Geological Survey of India Vol. 140, Pt. 4

ii) GSI, NER, NEWS, Vol. 19

iii) Geology and Mineral Resources of Assam (Misc. Pub.

No. 30, Pt. 4, Vol. i)

iv) Geology and Mineral Resources of Meghalaya (Misc.

Pub. No. 30, Pt. 4, Vol. ii)

(FS: 2007-08)

Jan to Dec’ 08

2009

2009

06.11.2009

05.01.2010

06.11.2009

06.11.2009

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

3. i) Records of Geological Survey of India Vol. 143, Pt. 4

ii) GSI, NER, NEWS, Vol. 20

iii) Geology and Mineral Resources of Arunachal Pradesh

(Misc. Pub. No. 30, Pt. 4, Vol. 1, part-1)

(FS: 2008-09)

Jan to Dec ‘09

2010

28.10.2010

06.01.2011

28.10.2010

Yes

Yes

Yes

Yes

Yes

Yes

85

4. i) Geology and Mineral Resources of Manipur, Mizoram,

Nagaland and Tripura (Misc. Pub. No. 30, Pt. 4, Vol. 1,

part-2)

2011 28.03.2011 Yes

Yes

5. i) Records of Geological Survey of India Vol. 144, Pt. 4

ii) GSI, NER, NEWS, Vol. 21.

(FS: 2009-10)

Jan to Dec ‘10

04.03.2012

04.03.2012

Yes

Yes

Yes

Yes

6. i) GSI, NER, News, Vol. 22

ii) Records of Geological Survey of India Vol. 145-146, Pt.

4

Jan. to Dec. 2011

(FS: 2010-12)

17.09.2012

14.02.2013

Yes

Yes

Yes

Yes

7. Bull. Sr. A, No. 63 (Limestone deposit of Litang Valley,

Jaintia Hills district, Meghalaya)

2013 18.10.2013 Yes Yes

8. Abstract Volume of Regional Workshop on Landslide

Disaster Management, 22-23 Nov, 2013

2013 22.11.2013 Yes Yes

9. GSI, NER, e-NEWS, Vol. 23 Jan 2012 -Dec 2012 12.02.2014 Yes Yes

10. Records of Geological Survey of India Vol. 147, Pt. 4

(FS: 2012-13)

31.03.2014 Yes Yes

86

ANNEXURE -10

COURSES CONDUCTED AT RTI & FTC’S

Month Title of the course

conducted

Location of training Duration

Of training

No of Participant Remark

April,13 36th OCG, Batch-F FTC-Aizwal/RTI-

Shillong

30 days 27 Successfully conducted

June,13 36th OCG, Batch-G FTC-Aizwal/RTI-

Shillong

30 days 25 Successfully conducted

July,13 36th OCG, Batch-H FTC-Aizwal/RTI-

Shillong

30 days 26 Successfully conducted

Aug,13 Capsule course on

Chemical analysis

RTI,

Shillong

6 days

19.08.13 to

24.08.13

9 4-Officers from DGM, Sikkim could not

attend due to Gorkhaland-Darjilling strike.

CONDUCTED SUCEESFULLY AND VERY

GOOD TO EXCELLENT FEEDBACK

GIVEN BY TRAINE OFFICERS AND

COURSE REPORT UPLOADED IN

PORTAL.

Sept,13 Refresher course on

Petrology Training

RTI,

Shillong

12 days

26.8.13 to

6.9.13

15 CONDUCTED SUCEESFULLY AND VERY

GOOD TO EXCELLENT FEEDBACK

GIVEN BY TRAINE OFFICERS AND

COURSE REPORT UPLOADED IN

PORTAL.

Oct,13 Computer application RTI,

Shillong

6 days

From 16.10.13

to 24.10.13

Total -19,

SU.Assam-3,

SU.Tripura-2

SU.Nagaland-1

Su.Meghalaya-13.

Conducted

refresher Training course on

computer application GSI,NER

Oct,13 Guest Lectures during

vigilance awareness week

on

“Promoting Good

Governance –Positive

Contribution of

Vigilance”

RTI,

Shillong

1 day

29.10.13

Total-70

GSI,NER, Shillong

Lectured delivered by shri.G.H.P.Raju,IPS.

Inspector General of Police, Govt of

Meghalaya.

87

Jan/Feb,14 Field workshop –cum

training on active fault

mapping

GSI,

Guwahati

6 days

28.1.14 -2.2.14

15

DGM-3; Meghalaya-1,

Nagaland-2.

NEHU-2,

GSI-10,

SU-ASSAM-3, SU-

ARUNCHAL PRADSH-

2

SU-SIKKIM-2

NER, SHILLONG-1,

CR,NAGPUR-1,

WR, JAIPUR-1

CONDUCTED SUCEESFULLY AND VERY

GOOD TO EXCELLENT FEEDBACK

GIVEN BY TRAINE OFFICERS AND

COURSE REPORT UPLOADED IN

PORTAL.

Jan,14 37th OCG, Batch-G FTC-Aizwal/RTI-

Shillong

30 days 27 Successfully conducted

Feb,14 Management Training

Course for JAG and Sr.

STS level officers of

Geological Survey of

India and Gr.A officer of

DGM’s of NER.

AASC, Guwahati

Govt Of Assam

10.2.14-14.2.14 20 Differed due to less number of nominations

received (only 5 ) and fresh application has

submitted to the DG,GSI through proper

channel for financial approval of 2.4 lakh.

Mar,14 Landslide Hazard

Zonation and Disaster

Management for

Geologist of DGM and

GSI Officers, NER, at

GSI, Gangtok, Sikkim

GSI

Sikkim

7 days

24.3.14-30-3-14

15 Training on LHZ has announced and uploaded

in portal to be conducted at Gangtok in last

week of March, 14.

88

ANNEXURE 11

LIST OF RAC / OAC / STAGE REVIEW / SGPB MEETINGS WITH DATE AND STATUS OF UPLOADING OF MINUTES

REGION/STATE RAC/OAC/SGPB/ STAGE REVIEW PLACE DATE OF MEETING MINUTES STATUS

RAC Meeting

NER, Assam XII_NER_RAC_07 Meeting Guwahati 21.01.2014 Uploaded

NER, Meghalaya XII_NER_RAC_06 Meeting Shillong 05.10.2013 Uploaded

NER, Meghalaya XII_NER_RAC_05 Meeting Shillong 03.06.2013 Uploaded

NER, Meghalaya XII_NER_RAC_04 Meeting Shillong 06.03.2013 Uploaded

OAC Meeting

SU : Arunachal Pradesh XII_SAP_OAC_07 Itanagar 02.04.2014

SU : Assam XII_SAS_OAC_07 Guwahati 28.03.2014

SU: Manipur – Nagaland. XII_SMN_OAC_07 Dimapur 07.04.2014

SU : Sikkim XII_SSK_OAC_07 Gangtok 20.05.2014

SU : Tripura – Mizoram XII_STM_OAC_07 Agartala 28.03.2014

SU: Meghalaya XII_SM_OAC_07 Shillong 25.04.2014

89

ANNEXURE-12

Employment position in the region AS ON 31.03.2014

POSITION OF GROUP 'A' & 'B' GAZETTED OFFICERS IN GEOLOGICAL SURVEY OF INDIA,

NORTH EASTERN REGION

Sl.

No.

Designation Shillong Sikkim Guwahati Itanagar Dimapur Agartala TOTAL

A B C D E F G H

Additional Director General 01 01

1 Dy. Director General 2 - 1 1 - - 04

2 Director (G) 8 - 2 1 1 0 12

3 Superintending Geologist 9 2 2 2 2 2 19

4 Senior Geologist 22 0 8 3 3 4 40

5 Geologist 29 12 11 13 9 7 81

6 Director (Chemist) 1 - - - - - 01

7 Sr. Chemist 3 - - - - - 03

8 Chemist 5 - - - - - 05

9 Assistant Chemist Grade – I 0 - - - - - 0

10 Supdt Geophysicist 1 - - - - - 01

11 Senior Geophysicist 5 - - - - - 05

12 Geophysicist 2 - - - - - 02

Jr. Geophysicist 0 - - - - - 0

13 Assistant Geophy 1 - - - - - 01

14 Mineralogist 0 - - - - - 0

Executive Engineer (NFJAG) 1 - - - - - 01

15 Asstt. Executive Engineer 1 - - - - - 01

16 Joint Director (P&A) 1 - - - - - 01

17 Deputy Director (P&A) 1 - - - - - 01

18 Stores Manager 2 - - - - - 02

19 Asstt. Director (P&A) 1 - - - 1 - 02

20 Administrative Officer Grade – II 5 1 2 - 1 1 10

21 Artist 0 - 1 - - - 01

90

22 Pricipal Private Secretary 1 - - - - - 01

23 Senior P.S 1 01

24 P.S 3 - - - - - 03

25 Officer Surveyor 2 - 1 - 03

26 Stores Officer 1 - 1 - - 02

GRAND TOTAL 109 15 28 21 17 14

91

ANNEXURE- 13

VEHICLE POSITION AS ON 31.03.2014 IN NORTH EASTERN REGION

Field going vehicles / Office vehicles

Sl

No

Particulars /

Type of vehicle

Kilometer run Total Sanctioned

strength of

drivers as

per HPC

Drivers

in

position

Less than

25000

km

25001- <

50000

km

50,001 - <

1,50,000

km

>

1,50,000

km

1 Amb. Cars 08 08 52 34

2 Petrol Jeep 03 03

3 Diesel Jeep /

Bolero /

Armada/Van

18 39 57

4 Gypsy 02 02

5 Toyota Qualis 02 02

6 Pick-up

(Diesel)

02 02

7 LCV 05 05

8 HCV 03 03

Grand total 82 52 34

Age wise Status of Vehicles

Field vehicles / Office Vehicles

Sl.

No.

Particulars Vehicles less

than 6 years

old

Vehicles 6

years & less

than 10 years

old

Vehicles more than

10 years & less

than 15 years old

More than 15

years

1 Amb. Cars 02 01 05

2 Petrol Jeeps 03

3 Diesel Jeep /Bolero /

Armada/Van

18 01 33 05

4 Gypsy 02

5 Toyota Qualis 02

6 Pick-up (Diesel) 02

7 LCV 05

8 HCV 03

Total - 82

92

ANNEXURE – 14

ASSETS PROCUREMENT AND MANAGEMENT DIVISION, GEOLOGICAL SURVEY OF

INDIA, NORTH EASTERN REGION

LIST OF PROCUREMENT UNDER M.E. HEAD/STATUS FOR 2013-14.

As on 31.03.14

A. Procurement Status – Bill released

Sl. No. Item Cost in Rs. Status

1. Brunton Compass-75 nos. 1145813 Bill released

2. Brunton Compass-05 nos.(DGM) 86625 Bill released

3. Drilling Accessories Core Barrel 275933 Bill released

4. Microscopes-07 nos

(Custom Clearance)

403941 Payment released

5. Inverter-02 nos. 86125 Bill released

6. Microscopes-07 nos

(10% Balance Payment)

649488 Payment released

7. Pulveriser LC Charges 5285 Payment released

8. Pulveriser (Foreign Purchase) 2476800 Debited

9. UPS Battery-08 nos.(Chemical) 19600 Bill released

10. Water Analysis Kit-01 no. 261050 Bill released

11. Arsenic Test Kit-05 nos. (SU-Assam) 46478 Bill released

12. Magnetometer=01 752625 Bill released

13. AO Scanner-03 nos. 1527750 Bill released

14. Pulveriser (Foreign Purchase) (10%

Balance Payment)

291545 Payment released

15. Inverter – 2 KVA 43063 Bill released

16. LC Charges – 01 Microscope 3468 Payment released

17. DG Set 5KVA (SU-Dimapur) 315331 Bill released

Bill released in Rs. 83,45,515

B. Procurement Status – P.O. Placed

Sl. No. Item Cost in Rs. Status

1. Thin Section Grinding Machines-01 no. 65873 Bill released

2. Microscopes-01 no. SU-Dimapur 917011 Payment debited

Bill released in Rs. 9,82,884

C. Procurement Status – Budget Stage

Sl. No. Item Cost in Rs. Status

1. Color Photocopier Machine – 08 nos 1876161 LOA Issued/Bill released

2. DC Resistivity Meter-03nos. 425850 Bill released

3. Geotechnical Instruments 696937 Bill released

4. Holland Cathode Lamp-04 nos 209421 Bill released

5. A0 Plotter-02 nos. 629900 Bill released

Bill released in Rs. 3838724

D. Procurement Status – Indigenous Purchase- PAC/TEC/TAC Stage

Sl. No. Item Cost in Rs. Status

1. A-3 Color Printer – 01 no. (RTI) 210000 P.O. Placed

E. Procurement Status – Foreign Purchase- PAC/TEC/TAC Stage

93

Sl. No. Item Cost in Rs. Status

1. Seismic Recorder 63,26,000 100% Payment released including

custom clearance.

A-Bill Released B- P.O. Placed C- Awaiting

Budget

D-TAC/TEC E-Foreign

Purchase in Rs.

Total Amount

24956833 2786517

Procurement Status –Motor Vehicle

Sl. No. Item Cost in Rs. Status

1 Field Utility Vehicle – 08 Nos. (Bolero) 50,92,139 Payment released for 07 Nos

vehicle received out of 08 nos.

2 Mini Buses – 02 Nos (RTI) 1940000 Awaiting delivery

Total

44,55,622

Payment released for 07 Nos.

Vehicle (Bolero). Only.

Procurement Status – Foreign Purchase

Sl. No. Item Cost in Rs. Status

1. DGPS – 01 Set (Geophysics) 6000000 Review of TED/Re-Tendering

Procurement Status Supply & Materials (Mission – IV)

Sl. No. Item Cost in Rs. Status

1. Standard Reference Materials for

Chemical Division

1008088 Bill Released

94

Annexure – 15a

STATUS OF EXISTING DRILLING EQUIPMENTS UNDER DEPLOYMENT

Details of Drilling Rigs AVAILABLE (with Deployment DURING F.S. 2012-13)

Sl.

No.

Project Item Unit no. Drilling (m) FSP Code

Target Achivement

1 MMIP 34 U-422 800 562.55 ME/NER/NEnR/2010/014

2 MMIP 25 U-427

1575

907.80

ME/IM/NER/SME/2010/015

3 MMIP 25 U-441 ME/IM/NER/SME/2010/015

4 Assam 35 U-422 300# ME/NER/NEnR/SAS/2012-030

Item kept in abeyance due to the

existing adverse ground realities

TOTAL DRILLING 2375 1470.35

*Extended in fs 2013-14 ;#kept in abeyance & taken up in FS 2013-14

Total target revised to 2375m

Details of AUGER RIG (WITH DEPLOYMENT DURING F.S. 2013-14)

Sl.

No.

Project Item Unit no. Drilling (m)/

Target/

Achivement

FSP Code

Nil Nil Nil Nil Nil

TOTAL DRILLING Nil Nil

Details of Rigs AVAILABLE ( with Deployment DURING FS 2013-14) 31.12.2013

Sl.

No.

Project Item Unit no. Drilling (m) FSP Code

Target Achivement

1 MMIP 018 U-427 800 824.85 ME/NER/SME/2013-018

2 MMIP 019 U-462/441 800 215.40 ME/NER/SME/2013-019

3 MMIP 030

U-422

300 583.30 ME/NER/NEnR/SAS/030#

4 MMIP 022 600 ME/NER/NEnR/SAS2013-022

TOTAL DRILLING 2500 1623.55

#kept in abeyance FS 2012-13 & taken up in FS 2013-14

Total Drilling (All Rigs) from April, 13 to Dec., 13 (including extended items) is 246.50m+750.60m

=1097.10m

95

ANNEXURE 15B

STATUS OF EXISTING DRILLING AND OTHER HIGH-END (RS >1 CORE) EQUIPMENTS TO BE PROCURED DURING FY 2013-14

Type of instrument Indenting

Region

Qty Cost Lead

Time

PAC/

Sr.

PAC

DG’s approval &

CPMC

recommendation

Tendering/

Re-

tendering

TEC TAC PO

Placed

LC

opened

Delivery

to be or

Received

Utility of

the

Instrument

[Mission-

wise]

Geophysical

[STSS-MI, MII &

MIV]

NER NIL --- --- --- --- --- --- --- --- --- --- ---

TOTAL NER NIL --- --- --- --- --- --- --- --- --- --- ---

Geology

[STSS- MI, MII &

MIV]

NER NIL --- --- --- --- --- --- --- --- --- --- ---

TOTAL NER NIL --- --- --- --- --- --- --- --- --- --- ---

FIELD/ SURVEY

[STSS – MI, MII &

MIV]

NER NIL --- --- --- --- --- --- --- --- --- --- ---

Drilling NER NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL

TOTAL NER NIL --- --- --- --- --- --- --- --- --- --- ---

GRAND TOTAL NER NIL --- --- --- --- --- --- --- --- --- --- ---

96

ANNEXURE – 16 STATUS OF PENDING LEGAL CASES OF NORTH EASTERN REGION AS ON 31.03.2014

As on 31.04.2014, the following Court Cases are pending before the Tribunal/High Court for decision/order.

Sl.

No.

No of Court Case Name of the Court/Bench Remarks.

1. 05 CAT Guwahati OA.No. 86/2013

OA.No. 265/2013

OA.No. 321/2013

OA.No. 385/2013

OA.No. 260/2013 &

OA.No. 2/2014

2. 01 High Court of Imphal Bench WP.No. 328/2000

3. 03 MACT, Silchar MACT No. 781/2007

MACT No. 782/2007

MACT No. 783/2007

4. 01 Court of the Assistant District Judge Money Suit No. 1(H) of 2012

5. 02 High Court of Shillong Bench W.P. No. 271/2013

W.P. No. 245/2013

PRESENT STATUS OF VIGILANCE CASES IN THE NORTH EASTERN REGION, GEOLOGICAL SURVEY OF INDIA, AS ON 31.03.2014

Sl.

No.

Name &

Designation of the

Official

Allegation /

Charges in

brief

Whether

under Rule

14 of Rule 15

Date of issue

of Charge

Sheet

Date of

receipt of

C.O.’s reply

Date of

appointment

of I.O.

Date of

receipt of

I.O.’s Report

Date of issue

of final Order

Present

Status of the

case

Address of

the Inquiry

Officer

1 2 3 4 5 6 7 8 9 10 11

NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL

As per record no vigilance is pending in NER, GSI, Shillong.

STATEMENT REGARDING GRIEVANCE CASES as on 31.03.2014

GEOLOGICAL SURVEY OF INDIA, NORTH EASTERN REGION, SHILLONG

Sl.

No

Registration No. &

Date Name of Complainant Subject of grievance

Investigation / Action

taken / Reasons for

withholding

Remarks

NIL NIL NIL NIL NIL

As per record no grievance cases is pending in NER, GSI, Shillong.

97

ANNEXURE – 17

GEOLOGICAL SURVEY OF INDIA, NORTH EASTERN REGION

REGIONAL HEADQUARTER, GSI, SHILLONG

(AS ON 31/12/2014)

Shri Harbans Singh, Additional Director General & HOD, GSI, North

Eastern Region, Regional Head Quarter, Shillong.

NAME OF OFFICER DESIGNATION Division

Shri Gajendra Kumar Kesari Director(G) Policy Support System

Shri Navjeet Singh Nayyar Senior Geologist Policy Support System

Shri Amit Srivastava Senior Geologist Policy Support System

Shri Banteilang.Rapthap Syngai Senior Geologist Policy Support System

Shri Jiban Bhattacharya Asst Geophysicist (Instn) Policy Support System

Mission- I & II

Shri. Brij Kumar, Deputy Director General & Regional Mission Head- I & II, GSI, NER, Shillong.

NAME OF

OFFICER DESIGNATION DIVISION MISSION

Shri Srikanta

Guru

Superintending

Geologist TC

Shri S N

Mariappan Senior Geologist TC M-I & II

Mission- III & IV

Shri. Raghubir Singh, Dy. Director General & RMH-III & IV with additional charge of

SU: Meghalaya, GSI, NER, Shillong

NAME OF OFFICER DESIGNATION DIVISION

MISSIO

N

Dr. Mridul Srivastava Senior Geologist TC (P/T) & (TCS)

M-III &

IV

SU: MEGHALAYA.

NAME OF OFFICER DESIGNATION DIVISION

MISSIO

N

Dr. Subrata Chakraborti Superintending Geologist STM I

Shri Lalboi T Haokip Geologist STM I

Shri Soumya Ranjan Mishra*** Geologist STM I

Shri Ranjith Anburaj*** Geologist STM I

Shri Lalneo Haokip Geologist STM I

Shri Vekhoto Shijoh Geologist STM I

Shri Avi Mero Geologist STM I

Shri Niketan Prakash Khedkar*** Geologist STM I

Smt Imlishila Imchen Geologist STM I

Miss S.Saujata Geologist STM I

Shri Balbir Singh*** Geologist STM I

Shri Imrontolo Pongen Geologist STM I

Miss Sampita Das Geologist STM I

Shri Mukesh Nagar Superintending Geologist NGCM I

Shri Chemjong Ajay Limbu Senior Geologist NGCM I

Shri Sumar Geologist NGCM I

Shri Kezhasilie Chiezou Geologist NGCM I

Shri Lakhan Lal Vishwakarma Superintending Geologist RSAS IB

98

Shri Harish Chandra Shahu Senior Geologist RSAS IB

Shri Aloke Kumar Lahiri Superintending Geophysicist

Geophysics/

Mineral Physics IA/ STSS

Shri K V Satyanarayana*** Senior Geophysicist Geophysics IA

Shri Om Prakash Senior Geophysicist Geophysics IA

Dr Babul Pathak Senior Geophysicist Geophysics IA

Shri Syntai Manick Syiem Senior Geophysicist Geophysics IA

Shri Sumit Narayan Choudhuri Senior Geophysicist Geophysics IA

Shri Pranab Kumar Chakraborty Geophysicist Geophysics IA

Shri V Vidyasagar*** Geophysicist (Instt) Geophysics IA

Miss Saralin Khongwar Assistant Geophysicist Geophysics IA

Shri Neipekreizo Kesiezie Geologist Geophysics IA

MISSION- II

Shri Atanu Ray Supterintending Geologist

Addl Charge TC/

M-II II

Shri Brij Bhushan Sharma Superintending Geologist MMIP II

Dr. Sudip Bhattacharyya Superintending Geologist MMIP II

Shri Pius Sahkhar Senior Geologist MMIP II

Shri Arvind Geologist MMIP II

Mohd. Sadiq Geologist MMIP II

Shri Rajesh Kumar Geologist MMIP II

Shri Vizolto Sakhrie Geologist MMIP II

Shri Dzieseneituo Vincent

Whuorie Geologist MMIP II

Shri Ravi Kumar Umrao Geologist MMIP II

Shri Tongbram Guneshwar

Singh*** Geologist MMIP II

Shri Sreenivasaiah V*** Geologist MMIP II

Shri Anjan Jyoti Deka Geologist MMIP II

MISSION- III

Dr Bijay Kumar Sahu Superintending Geologist M & C III

Shri Rajinder Kumar Superintending Geologist

Publication

Division III

Shri Shougaijam Mohendro Singh Senior Geologist

Publication

Division III

Shri Amit Srivastava Senior Geologist

Publication

Division III

Shri Praveen Kumar Sinha Superintending Geologist Geodata Division III

Shri Subhash Banerjee Senior Geologist Geodata Division III

Smt Darnia C. War Senior Geologist Geodata Division III

Shri Asutosh Kumar Tripathy Senior Geologist Geodata Division III

Shri Y.C. Puttabasappa Officer Surveyor Geodata Division III

Dr Bijay Kumar Sahu Superintending Geologist

Map& Cartography

Division III

Dr Pradip Kr Mukherjee*** Senior Geologist

Map and

Cartography III

MISSION- IV

Shri Dinesh Vitthalrao Ganvir Director(G) Engineering Geology IV

Dr. Vinod Kumar Senior Geologist Engineering Division IV

Shri Gaikungam Rongmei Senior Geologist Engineering Geology IV

Shri Dhrubajyoti Chakraborty*** Senior Geologist Engineering Geology IV

Shri Wungmarong Shimrey

Rocky Senior Geologist Engineering Geology IV

Shri Konthoujam Kipgen Singh Geologist Engineering Geology IV

99

Shri R. Balaji Superintending Geologist Earthquake Geology IV

Shri L H Moirangcha Senior Geologist Earthquake Geology IV

Shri Imtikumzuk Senior Geologist

Earthquake Geology

Division IV

Shri Subhajit Kar Geologist Earthquake Geology IV

Dr. Surendra Prasad Superintending Geologist Palaeontology Division IV

Shri Amitabha Bhattacharjee Senior Geologist Palaeontology Division IV

Shri Abir Gupta Senior Geologist Palaeontology Division IV

Smt Sudipta Sarkar Superintending Geologist Petrology Division IV

Smt Sushree Mishra*** Senior Geologist Petrology Division IV

Shri. Niroj Kumar Sarkar Superintending Geologist Landslide Hazard Zonation IV

Shri Megotsohe Chasie Geologist Landslide Hazard Zonation IV

Shri Paongaomai Kho Theophilus Geologist Landslide Hazard Zonation IV

Miss Toshilila Geologist Landslide Hazard Zonation IV

MISSION- V

Dr. Basant Kumar Sareen Director(G)

Regional Training

Institute V

Shri. Muduru Lachhna Dora Superintending Geologist

Regional Training

Institute V

Shri Ishwar Dan Ashiya Superintending Geologist RTI (SU:T& M) V

Shri Benudhar Behera Senior Geologist RTI(SU:T& M) V

CHEMICAL DIVISION

Shri Francis Kharshiing Director(Chem) Chemical Division

Dr Gobin Chandra Saikia Senior Chemist Chemical Division

Shri Dipak Gurung Senior Chemist Chemical Division

Shri Debo Prasad Chakraborty Senior Chemist Chemical Division

Shri T.K. Myelvaganan*** Chemist Chemical Division

Shri Chandan Saha Chemist Chemical Division

Shri Amit Shankar Borah Chemist Chemical Division

Shri Rajendra Kumar Chemist Chemical Division

Shri. Rathla Vittal Chemist Chemical Division

ADMINISTRATION

Shri Khlainbor Kharmalki Joint Director (P&A)

Smt. Silian Nongkynrih Deputy Director

Shri Sunil Ghosh Asstt. Director

Shri Badal Das Administrative Officer

Shri Rajkishore Ram Administrative Officer

Shri Dale Wi Paswet Administrative Officer

Shri H.R.War Administrative Officer

Smt Anju Das Administrative Officer

Smt. Martina Pyngrope Principal Private Secretary

Smt. Mina Neilson Laloo Senior Private Secretary

Shri Shiba Prasad Sharma*** Private Secretary

Shri P. Bhattacharya Private Secretary

Shri Moawati Stores Manager

Shri Columbus Marbaniang Stores Manager

Shri Bijoy Dey Stores Manager

Shri Balmiki Pandit*** Store Officer

Shri Ioanis Pyngrope Officer Surveyor

Shri Tapan Deka Officer Surveyor

ENGINEERING DIVISION

100

Shri T Pongen Executive Engineer (NFJAG)

Shri Nirmalendu Goyari Asstt.Exeecutive Engineer

Shri. N. Devaraj, Dy. Director General, SU: Assam, with additional charge of SU: Sikkim & Tripura-

Mizoram, NER, Guwahati.

SU: ASSAM

Shri J.C. Dutta, Director Director (G) TC

Shri Amiya Kumar Mondal Senior Geologist TC

Shri P.K. Sharma Senior Geologist (P/T)/ Geodata TC

Shri Anjan Bora Superintending Geologist DRM/PGRS IB

Smt. Sanjukta Sahoo Superintending Geologist STM/ MI I & II

Shri P.R.Pai*** Superintending Geologist

NGCM/

Environment

Geology

I & IV

Shri Binod Boruah Senior Geologist STM I

Shri Yhunyelo Tep Geologist STM I

Shri Satrughan Majhi Geologist STM I

Shri P. C. Gangaikoppa Geologist STM I

Shri Rajkumar Tapon Kumar Geologist STM I

Shri Varun Vara Geologist STM I

Shri R.C. Kishan Geologist STM I

Shri Mukesh Kumar Mishra Geologist NGCM I

Shri Amit Kumar Geologist NGCM I

Shri A. K. Bora Senior Geologist MI

Shri Th. N.B. Singha Senior Geologist MI II

Shri M.Shyam Kr.Singh Geologist MI II

Shri N. Goswami Senior Geologist DDO/ DRM II

Smt. Rupali Thakur Bhuyan Senior Geologist DRM III

Shri G.C. Sarmah Senior Geologist Environment

Geology

III

Shri P.C. Srivastava, Geologist Environment

Geology

IV

Shri Dwijendra Nath Borah Artist IV

Shri N. Borah Officer Surveyor

Shri Ratan Baran Dey Administrative Officer

Shri Rajesh Ghose Administrative Officer

SU: SIKKIM

Dr. S. K. Som Superintending Geologist TC

Dr. Sanjay Wahi Superintending Geologist

Mrs. Lopamudra Bhol Geologist

Shri Kailash Singh*** Geologist

Shri S. Jijikumar*** Geologist

Shri N. Thredeep Kumar*** Geologist

Shri Murli Mohan Geologist

Shri Jagadish Nandan Hindayar Geologist

Shri Hiten Kumar Jalutharia Geologist

Shri Tangtirenba Longchari Geologist

Shri Mohd. Ibrahim Geologist

Ms P.N. Dasarwar Geologist

Shri. Laishram Sarjesh Singh Geologist

Shri. Nongmaithem Herojit Singh Geologist

Shri Dahiram Kalita Administrative Officer

101

SU: Tripura - Mizoram

Shri N. Padmaiah Superintending Geologist TC

Shri. Venkateshwara Rao Senior Geologist TC

Smt. Srinanda Mukherjee Senior Geologist Geoinformatics III

Shri Jayanta Pramanik Geologist STM I

Shri Pankaj Pralhadrao Vaidya Geologist STM I

Shri Omnath Saha Geologist STM I

Shri Watitemsu Geologist STM I

Shri A. Elow Geologist STM I

Shri Jefferson Mylliem Umlong Geologist NGCM I

Shri M P Singh Geologist NGCM I

Miss Pallabi Shome Geologist NGCM I

Dr. T.S. Giritharan Senior Geologist Geoinformatics III

Shri Utpal Halder Administrative Officer

Shri. Lokinder Singh Ravi, Dy. Director General, SU: Arunachal Pradesh with additional charge of

SU: Nagaland- Manipur, GSI, NER, Itanagar.

SU: Arunachal Pradesh.

Dr. B. R. Bejarniya Director TC/ M-II

Shri Bashab Nandan Mahanta Senior Geologist TC

Shri Swapan Kumar Guha Superintending Geologist STM/NGCM I

Shri Prem Shanker Misra Superintending Geologist Mineral

Investigation II

Shri Rupesh Kumar*** Geologist STM I

Shri Sebabrata Das Geologist STM I

Shri Raman Kumar Geologist STM I

Shri Vizokho Vitso Geologist STM I

Shri Deithovilie Pieru Geologist STM I

Miss Ranjita Bhattacharjee Geologist STM I

Miss Welhitshou Mero Geologist STM I

Shri Subash Chandra Keshari Sr. Geologist NGCM I

Shri Sudeep Manish Toppo*** Geologist NGCM I

Shri Bendangnuchit Sr. Geologist Mineral

Investigation II

Shri Ravi Negi*** Geologist Mineral

Investigation II

Miss Rita Thurr Geologist Mineral

Investigation II

Shri Amit Kumar Geologist Mineral

Investigation II

Shri Hiruj Saikia Geologist Mineral

Investigation II

Shri Apurva Kumar Singh Geologist Mineral

Investigation II

Shri Kaisar Wankhar Store Officer

Sh. Karpur Bagra PA

SU: Manipur - Nagaland.

Shri Deo Nath Director (G) TC

Shri R. L. Jat*** Senior Geologist TC

Shri N.L. Gera Superintending Geologist STM/ MI I & II

Dipayan Guha Superintending Geologist NGCM/ M-II I & II

Shri C. Yanthan Senior Geologist STM I

102

Shri P. Enos Ezung Geologist STM I

Ms. Visahono Zaphu Geologist STM I

Shri E. John Geologist NGCM I

Ms. Chubala Shijoh Geologist NGCM II

Shri Savio Peter Vales Geologist NGCM I

Shri J.K. Angami Senior Geologist MI II

Shri N. Meribemo Yanthan Geologist MI II

Shri Kevilhoutuo Theunuo Geologist MI II

Shri Shonglen Shon Telen Kom Geologist MI II

Mrs. Sentimongla Ao Asstt.Director(P&A)

Shri L. S. Ngaihte Administrative Officer

NB: *** OFFICERS APPLIED FOR TRANSFER.

103

Photographs of training given in field, lab and lectures in classroom by Regional Training Institute, GSI, NER, Shillong

GSI Faculty explaining to the trainees about the contact metamorphisim between Shillong quartzite-phyllit and Mylliem granite, East Khasi Hills District, Meghalaya.

Trainees being given training for mapping in Nongpoh Granite, South Khasi Hills District, Meghalaya.

Field discussions between GSI Faculty and trainees about fenitisation in Alkaline-caebonatite-ultramafic complex,Sung valley, Jaintia Hills District, Meghalaya.

Trainees being given training for mapping in Mylliem Granite, East Khasi Hills District, Meghalaya.