34
© Frontier Economics Ltd, London. Ex post evaluation of cohesion policy interventions 2000-2006 financed by the Cohesion Fund Work Package B: Cost-benefit analysis of selected transport projects FINAL REPORT EXECUTIVE SUMMARY 20 th June 2011

Title of report/proposal - European Commissionec.europa.eu/regional_policy/sources/docgener/evaluation/pdf/... · Domatas (Transporto ir kelių tyrimo institutas); Zita Dubickienė

  • Upload
    hoangtu

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

© Frontier Economics Ltd, London.

Ex post evaluation of cohesion policy

interventions 2000-2006 financed by the

Cohesion Fund – Work Package B:

Cost-benefit analysis of selected

transport projects

FINAL REPORT – EXECUTIVE SUMMARY

20th June 2011

Acknowledgements

Acknowledgements

This report has been written by a team led by Frontier Economics together with

Atkins and the Institute of Transport Studies (University of Leeds), following the

call for tenders 2009CE160CAT051.

The report has been completed thanks to the help, feedback and information

received from a series of individuals and officials both in the Commission and in

Member States.

First, the authors are grateful for the helpful comments and advice received from

members of the Evaluation Unit in DG REGIO, including Veronica Gaffey,

Jurate Vaznelyte, Adam Abdulwahab, Lucia Pacillo, Patty Simou and Kai

Stryczynski; and from Commission officials who participated in several meetings

of the Steering Committee which oversaw the implementation of the study.

Second, we are also grateful to the national representatives who participated in

the Workshop with Member States on Ex Post Evaluation of Cohesion Fund (including

former ISPA) 2000-2006 held in Brussels on the 3rd of February 2011 for sharing

their experience about the Cohesion Fund instrument and their views about the

findings of our study.

Third, we would like to extend our thanks to the three external experts who

advised the team throughout the implementation of the study providing detailed

feedback on methods and findings: (in alphabetical order) Professor Antonio

Estache (ECARES, Université Libre de Bruxelles), Professor Emile Quinet (Paris

School of Economics - Ecole des Ponts ParisTech) and Professor András Timar

(Professor Emeritus, University of Pécs, Faculty of Engineering Mihály Pollack).

Finally, this study could have not been completed without the support of staff in

the DG REGIO Geographic Unit and project stakeholders at Member State

level. Specifically, we received invaluable help from the following individuals:

High Speed railway Madrid – Barcelona in Spain

Javier Asensio (Ajuntament de Barcelona); Carme Bellet Sanfeliu (Universitat de

Lleida) ; Miguel Benito (DG REGIO, European Commission); Alfonso

Abengozar Tejero (RENFE); Oriol Clos (Ajuntament de Barcelona); Ana Raquel

García Rubio (Ministerio de Economía y Hacienda); Sergi Lozano (Institut

d‟Estudis Territorials); María Muñoz (Ministerio de Economía y Hacienda);

Isabel Meléndez (Ajuntament de Barcelona); José Antonio Nieves (Ministerio de

Economía y Hacienda); Luis Nistal Martínez (ADIF); Antonio Rodríguez

(RENFE); Gaspar Ros Moreno (DG REGIO, European Commission);

Concepción Sanz (Ministerio de Fomento); Rosa Sebastián Escolano (ADIF);

Manuel Villalante (Departament de Política Territorial i Obras Públiques,

Generalitat de Catalunya).

iv Frontier Economics, Atkins, ITS | June 2011

Acknowledgements

A2 motorway in Poland

Magdalena Adamczuk (CUPT); Malgorzata Bronowicz (GDDKiA - Warsaw);

Michal Grzybowski (CUPT); Andrzej Jankowski (Gmina of Strykow); Roman

Jankowski (Town office in Konin); Krzysztof Jan Kalinski (Mayor of Lowicz);

Rafal Karolczak (Lodz Special Economic Zone); Barbara Kielar (GDDKiA -

Lodz); Paul Knight (EIB); Szymon Milczarek (GDDKiA - Lodz); Monika

Milwicz (GDDKiA - Warsaw); Gregorz Obara (GDDKiA - Warsaw); Emilia

Pieczara (Ministry of Infrastructure); Ewelina Rapela (Konin County Council);

Steve Richards (EIB); Tomasz Smollen (GDDKiA - Warsaw); Wieslaw Tomczyk

(Gmina of Strykow); Robert Wojdynski (GDDKiA - Warsaw); Przemyslaw

Wrobel (CUPT)

Algarve railway in Portugal

Marta Albuquerque (REFER); Helena Azevedo (POVT); Ana Paula Barreiros

(REFER); Duarte Ladeira (POVT); Maria Lopes (CP); Germano Martins

(POVT); Edoardo Pires (REFER); Mario Rodrigues (DG REGIO, European

Commission); Luisa Maria Soares (REFER); Lilia Sousa (CP); Helena Vieira

(POVT); Miquel Vila (DG REGIO, European Commission)

A23 motorway in Spain

Miguel Benito (DG REGIO, European Commission); Carlos Casas (Unidad de

carreteras del Estado en Teruel); Justo Borrajo Sebastián (Ministerio de

Fomento); Pedro Galán Bueno (Ministerio de Fomento); Antonio Garcia Cañada

(Ministerio de Fomento); Jesús Iranzo (Unidad de carreteras del Estado en

Teruel); Rafael López Guarga (Ministerio de Fomento); Joaquín López Sanchez

(Ministerio de Fomento); Gaspar Ros Moreno (DG REGIO, European

Commission).

Agiou Konstantinou bypass in Greece

John Krassakopoulos (Ministry of Transportation); Soultana Lyngeri (DG

REGIO, European Commission); George Logothetis (Ministry of Economy); Mr

Evangelos Psathas (Mayor of Agios Konstantinos); John Voloioutis (PATHE)

M1 northern motorway in Ireland

Jim Deane (Department of Finance); Richard Evers (NRA); John Fitzsimons

(NRA); Philip Hopkins (Department of Transport); Alan O'Brien (AECOM);

Fergal Trace (NRA)

Acknowledgements

Railway Thriassio-Pedio-Eleusina-Korinthos in Greece

Isaia Karamida Linta (Ergose); Soultana Lyngeri (DG REGIO, European

Commission); George Logothetis (Ministry of Economy); Ms Vitou Katerina

(OSE)

IX B corridor in Lithuania (including Vilnius Southern bypass)

Albertas Arūna (Transport Investments Directorate); Laura Bogušienė (Ministry

of Finance); Laura Danielutė (DG REGIO, European Commission); Arvydas

Domatas (Transporto ir kelių tyrimo institutas); Zita Dubickienė (Ministry of

Transport and Communications); Mantas Kaušylas (UAB "Kelvista"); Ieva

Kriščiūnaitė-Kačiuškienė (Ministry of Finance); Ilona Lankininkienė (Vilnius

Municipality); Jurgita Matiliauskaitė (Ministry of Finance); Aurelija Meškauskaitė

(Transport Investments Directorate); Mindaugas Pakštys (Ministry of Finance);

Kristina Petrauskienė (Lithuanian Road Administration); Gintautas Predkelis

(Transport Investments Directorate); Mindaugas Šidagis (Ministry of Transport

and Communications)

Bratislava Rača – Trnava Railway Upgrade in Slovakia

Rozália Dzvoníková (Ţeleznice Slovenskej Republiky); Stefan Elek (Národná

diaľničná spoločnosť, a.s.); Marian Hantak (Ministry of Transport, Posts and

Telecommunications); Zuzana Krajcirikova (Národná diaľničná spoločnosť, a.s.);

Juraj Majtan (Bratislava Regional Chamber of SCCI); Miroslav Matusek

(Ţeleznice Slovenskej Republiky); Štrba Peter (Ţeleznice Slovenskej Republiky);

Rastislav Prokopic (DG REGIO, European Commission)

M0 Budapest ring road (eastern section) in Hungary

György Bátovszki (Mayor of Csömör municipality); Péter Bucsky (Nemzeti

Infrastruktúra Fejlesztő Zrt.); Beatrix Horváth (Nemzeti Fejlesztési Ügynökség);

Csaba Kelen (KOZLEKEDES Ltd, Budapest); Kyriacos Ktenas (DG REGIO,

European Commission); Violetta Tarnócziné (Nemzeti Infrastruktúra Fejlesztő

Zrt.); Attila Tompos (Nemzeti Infrastruktúra Fejlesztő Zrt.)

Disclaimer

Disclaimer

The views expressed in this report are those of the authors and do not necessarily

reflect the official opinion of the European Commission or indeed of any of the

authors of the Work Packages. Any errors or omissions remain the responsibility

of the authors.

The European Commission and the authors accept no responsibility or liability

with regards to this report.

Specifically:

this report is of general nature and is not intended to address the

specific circumstances of any particular entity or individual; and

this report does not constitute professional or legal advice.

Reproduction or translation is permitted, provided that the source is duly

acknowledged and no modifications to the text are made.

Glossary

Glossary

Acronym Definition

AADT Average Annual Daily Traffic

ADIF Administrador de Infraestructuras Ferroviarias (The railway

infrastructure manager in Spain)

AHVV Average Hourly Value of time for one Vehicle

AVE Alta Velocidad Española (Spanish high-speed railway service)

B/C ratio Benefit cost ratio. Also BCR.

BIR Benefit investment ratio

BOE Boletín Oficial del Estado (Spanish official state gazette)

CBA Cost Benefit analysis. Also COBA

CF Cohesion Funds

CP Comboios de Portugal (A state-owned company which operates

freight and passenger trains in Portugal).

CSO Irish Central Statistical Office

CUPT Centre for EU Transport Projects, in Poland. Body set up to

implement programmes and projects of the transport infrastructure

development, particularly programmes and projects co-financed by

EU funds in the programming period of 2007 - 2013.

DIA Environmental Impact Declaration (Declaración de Impacto

Medioambiental), in Spain.

DoF Irish Department of Finance

EBRD European Bank for Reconstruction and Development

EC European Commission

EIA Environmental Impact Assessment

x Frontier Economics, Atkins, ITS | June 2011

Glossary

Acronym Definition

EIB European Investment Bank.

EIRR Economic internal rate of return.

ENPV Economic net present value.

ERDF European Regional Development Fund

FDI Foreign Direct Investment

FNPV(C) Financial net present value of the investment.

FNPV(K) Financial net present value of capital.

FRR Financial rate of return.

FRR(C) Financial rate of return of the investment.

FRR(K) Financial rate of return of capital.

GDDKiA Generalna Dyrekcja Drog Krajowych Autostrad (Polish General

Directorate for National Roads and Highways). Established in the

Polish Ministry of Transportation, GDDKiA is the authority in charge

of managing the national roads and the implementation of the state

budget in the sector.

GDP Gross Domestic Product

HEATCO EC funded research project in charge of "Developing Harmonised

European Approaches for Transport Costing and Project

Assessment".

HGV Heavy goods vehicle.

INE Instituto Nacional de Estadística (Spanish National Statistics Institute)

IRR Internal rate of return.

ISPA Instrument for Structural Policies for Pre – Accession

Glossary

Acronym Definition

JASPERS Joint Assistance to Support Projects in European Regions. A joint

initiative of the EIB, EBRD and EC to assist the 12 Central and

Eastern EU Member States in the preparation of major projects to be

submitted for grant financing under the Structural and Cohesion

Funds.

LAV Linea de Alta Velocidad (Spanish High-speed line)

LGV Light goods vehicle.

LRA Lithuanian Road Administration

MCA Multi-Criteria Analysis

NDS Národná diaľničná spoločnosť (Slovakian highway authority)

NRA National Roads Authority

NTDP Lithuanian National Transport Development Programme

OKA Hungarian National Highway Databank

PATHE Patras, Athens, Thessaloniki, Evzoni

PCU Passenger Car Units

PIA Personal Injury Accidents

PLN Polish Zloty

PSV Passenger Service Vehicle (i.e. bus or coach)

PTE Portuguese Escudos

POVT Programa Operacional Temático Valorização do Território (The

Portuguese government programme for the implementation of

infrastructure projects)

PVB Present Value Benefit

REFER Rede Ferroviária Nacional (The railway infrastructure manager in

Portugal)

xii Frontier Economics, Atkins, ITS | June 2011

Glossary

Acronym Definition

RENFE Red Nacional de Ferrocarriles Españoles (The railway public operator

in Spain).

RSA Irish Road Safety Association

SEZ Special Economic Zone

SME Small and Medium size Enterprise

TEN-T Trans European transport network

TOR Terms of Reference

VAT Value Added Tax

VOC Vehicle Operating Costs

VOT Value of Time

ŢSR Železnice Slovenskej Republiky (Slovakian rail authority)

ŢSSK Železničná spoločnosť Slovensko (Slovak state-owned passenger

train operating company)

Executive Summary

Executive Summary

Frontier Economics, together with Atkins and the Institute for Transport Studies

(University of Leeds), is pleased to present this Final Report for the study “Ex

post evaluation of cohesion policy interventions 2000-2006 financed by the

Cohesion Fund – Work Package B: Cost-benefit analysis of selected transport

projects”.

Context

The Cohesion Fund was established in 1993 to strengthen the economic and

social cohesion of the European Union.1 The eligibility criterion is that the GNP

per capita in the applicant country is 90% or less than the EU average.

During the period 2000-2006, 17 countries have received funding from the

Cohesion Fund and ISPA (Instrument for Structural Policies for Pre-Accession,

aimed at accession countries) for transport and environment projects.

The Council Regulation2 states that “in order to ensure the effectiveness of Community

assistance, the Commission and the beneficiary Member States shall, in cooperation with the

EIB where appropriate, carry out a systematic appraisal and evaluation of projects,”.

This study focuses on the ex post evaluation of a selection of ten transport

projects in EU countries benefitting from EU Cohesion and ISPA funding

during the period 2000-2006. The study forms part of three studies

commissioned by DG REGIO to assess the effect of the Cohesion Fund and

ISPA on economic and social cohesion and draw lessons for the future. These

studies are package A (overall); package B (transport); and package C

(environment). The Terms of Reference (TORs) for Work Package B identify the

three key questions that this study addresses:

Question 1: What were the impacts of the examined projects?

Question 2: How can ex post cost benefit analyses (CBA) contribute to the

practice of ex ante cost-benefit analysis?

Question 3: What are the potential and the limits of ex post CBA as a tool

to identify the impact of infrastructure projects?

The first question is specific to the ex post evaluation of the ten transport

projects selected. During the period 2000-2006, there were 260 individual

1 Council Regulation (EC) No 1164/94 of 16 May 1994 establishing a Cohesion Fund [Official

Journal L 130, 25.05.1994].

2 Ibid.

2 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

transport projects co-financed by the Cohesion Fund, for a total eligible value of

about €8.6bn and contributions from the Cohesion Funds of about €7.2bn. The

TORs of this study shortlisted 40 transport schemes, covering a total of 103

individual transport projects. Therefore, out of the 40 schemes identified in the

TORs, we selected 10 of them for in-depth ex post evaluation. In aggregate,

these schemes encompass 38 individual transport projects, that is about 15% of

the individual projects co-financed by the Cohesion Fund in the period 2000-

2006.

Approach

To address the three questions above, as specified in the TORs, we completed

three tasks in sequence:

In Task 1, we selected, out of the list of 40 transport projects provided in the

TORs, a shortlist of 20 projects. For each project, we carried out an initial

review. We presented the results of this review in a three-page project

description, which included an initial overview of the quality of the ex ante

CBA, information on the degree of completion of the project, and the

identification of the data requirements to complete a full ex post CBA. We

used the results of this review to select ten transport projects for an in-depth

ex post CBA analysis.

Task 2 was the core of the study and focused on the ten selected transport

projects. In this task, we first undertook a review of any existing ex ante

cost-benefit analysis carried out at the time of the funding application. We

also reviewed any interim progress report where available. This initial review

acted as background material for the in-depth ex post evaluation of these

projects, which provided an assessment of the overall performance of the

investment. We based the ex post evaluations both on the data already

available and, where necessary, on data collected by the project team. We

then compared the results of the ex post evaluations with any available ex

ante evaluations, to assess the appropriateness of the CBA methodology

being applied and to identify any cause for possible discrepancies between

expected results and actual outcomes.

Finally, in Task 3, we assessed the potential for ex post cost-benefit analysis

to become an integral part of the infrastructure funding appraisal and

evaluation process in the EC and in Member States. We identified the

lessons that can be drawn from ex post evaluation to help improve the

methods of ex ante evaluation. In particular, we looked at the extent to

which the use of ex post CBA can strengthen the evidence base

underpinning the ex ante analysis in several areas of project appraisal. We

also focused on identifying methodological strengths and weaknesses of

cost-benefit analysis.

Executive Summary

Projects considered for the ex post evaluation

Before presenting the overall results of our analysis, Tables I and II contain a

brief summary of the ten projects included in the study..

Table I. Rail projects

Project Description

AVE Madrid -

Barcelona (Spain)

The railway Madrid – Barcelona – French border is a high speed line

connecting Madrid to the French border via Barcelona. At the moment of

writing, only the section Madrid – Barcelona is operational. The segment

between Barcelona and the French border is still under construction and it is

expected to be operational in 2013. The LAV is part of the TEN-T Priority

Project 3 (high-speed railway axis of south-west Europe), whose main

objective is to provide high-speed rail connections between the Iberian

Peninsula (Portugal and Spain) and the rest of Europe.

Algarve Railway

(Portugal)

This project covers the modernisation of the railway line between Coina (near

Lisbon) to Faro (in the Algarve region) in Portugal, including the branch to

Porto de Sines. The total extension of both rail segments is around 275 km

and 50 km respectively. The project is part of the TEN-T Priority Project 8

(Multimodal Axis Portugal/Spain – Rest of Europe).

Railway Thriassio –

Kiato (Greece)

The project covers a rail upgrade between Thriasio (north west of Athens)

and Kiato in Greece. The new line has replaced a former single track metric

line passing through a number of urban areas. The 112km section runs

parallel to the European TEN-T network Motorway Priority Axis 7

(Igoumenista-Patras-Athens-Sofia-Budapest) and forms part of longer term

proposals to upgrade the Piraeus-Athens-Patra line. The route is covered by

four funding applications for cohesion funding. Three of the sub-projects are

related to the section of track running from Thriasio to Korinthos. An

additional funding application was made for the section of track between

Korinthos and Kiato.

Bratislava Railway

Upgrade (Slovakia)

This project covers a rail upgrade between Bratislava Rača and Trnava in

Slovakia. The 39km section forms part of the Corridor Va TEN-T rail corridor

which runs in Slovakia between Bratislava, Ţilina and Košice, then onto the

border with Ukraine. The section of line also forms part of Priority Axis No.

23. The modernization project includes two separate applications for funding,

the first including the upgrade of the line between Bratislava Rača to

Šenkvice (FM001), and the second upgrading the line between Šenkvice and

Cífer and all the stations along the section between Bratislava Rača and

Trnava (FM003).

Source: Funding applications and supporting material

4 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

Table II. Road projects

Project Description

A2 Motorway

(Poland)

This project involved the construction of approximately 100km of new

motorway between the towns of Konin and Strykow in central Poland. The

route is of national and international importance and forms part of the

European Route E30 between Berlin and Belarus. This section of the A2 is

part of a wider package of projects to construct a high standard road

transport link between Berlin and Warsaw, as well as improving connectivity

at local and regional scale. The section between Strykow (at the eastern end

of the project) and Warsaw is currently under construction.

A23 Motorway

(Spain)

This project covers the construction of 75 km of the A23 motorway in Spain,

covering two separate segments, one of 63.5 km between Teruel and

Calamocha and another of 11.5 km between Huesca and Nueno. The A23

(also called Autovía Mudéjar) is a high capacity road, long 440 km (370km in

service), connecting Sagunto, on the Mediterranean coast north of Valencia,

and the Somport road tunnel, which connects France and Spain through the

central Pyrenees. The A23 partially belongs to the European route E07

connecting Pau (France) and Zaragoza (Spain).

Agios Konstantinos

Bypass (Greece)

This project involved the construction of a bypass around the town of Agios

Konstantinos and an upgrade of an existing Bypass around Kamena Vourla,

both in Greece. This is part of the PATHE (Patras-Athens-Thessaloniki-

Evzoni) corridor. The route is of national importance because it links the two

largest cities in Greece (Athens and Thessaloniki), internationally the route

supports an important link between Greece, Central Europe, and the

Balkans.

M1 Northern

Motorway (Ireland)

This project covers the construction of two sections of the M1 motorway in

Ireland. The first section runs from Cloghran to Lissenhall and the second

section joins this road with the Balbriggan Bypass further north. The M1

Motorway is part of the TEN-T Priority Axis 13 (Ireland – United Kingdom –

Benelux). The main objective of the investments in this corridor is the

reduction in journey times between Ireland, the UK and mainland Europe.

IX B Corridor

(Lithuania)

This project covers the modernisation of one of the two main motorway

routes in Lithuania. This is part of the IX B transport corridor, 315km of

motorway linking the port city of Klaipeda with the capital city of Vilnius, via

Kaunas. The route then links Lithuania with other destinations in Eastern

Europe. The project also involved the construction of the Vilnius Southern

bypass.

M0 Budapest Ring

Road (Hungary)

The M0 Eastern Sector is the eastern component of the Budapest orbital

motorway, whilst the M31 is a linking motorway between it and the M3 (the

motorway to the north east of Hungary). The project has important

international, national and local dimensions. Budapest sits on the junction of

three land based Helsinki corridors, is the focus of the national transport

network and is the economic centre and capital of Hungary. Congestion in

the city centre, particularly in the vicinity of the Danube is severe. This

project therefore performs an important function in facilitating the movement

of international and national traffic while also providing some traffic relief to

Budapest.

Source: Funding applications and supporting material

Table III shows the opening dates of the various projects. It also indicates when

the most recent ex ante CBA was undertaken for each project. We also obtained

Executive Summary

information on project capital costs and Cohesion Funds contribution from each

project‟s funding applications. Most projects were divided into various

subprojects, each with its own different completion dates and, in some cases,

different ex ante analysis.

Table III. Opening dates and cost of the projects considered

Opening date(s)

Date of ex ante appraisal

Capital costs - EURm

(% Cohesion Fund contribution)

Rail projects

AVE Madrid -

Barcelona (Spain) 2003 - 2008 2001

1,719 (61%)

Algarve Railway

(Portugal) 2003 - 2006 1999

419 (77%)

Railway Thriassio –

Kiato (Greece) 2005 - 2007 2000

619 (47%)

Bratislava Railway

Upgrade (Slovakia) 2003 - 2009 2001

234 (39%)

Road projects

A2 Motorway

(Poland) 2006 2003

476 (82%)

A23 Motorway

(Spain) 2001 - 2005 1999 and 2003

203 (83%)

Agios Konstantinos

Bypass (Greece) 2008 2002

441 (55%)

M1 Northern

Motorway (Ireland) 2003 1995

232 (66%)

IX B Corridor

(Lithuania) 2006 - 2009 1999

154 (79%)

M0 Budapest Ring

Road (Hungary) 2008 - 2010 2004 367

(74%)

Source: Funding applications

Table IV lists the main objectives of each of the ten projects as stated in their

funding applications. The table shows that safety was the main stated objective in

8 of the 10 projects, followed by the objectives of reducing travel time (6

projects) and increasing capacity (4 projects).

6 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

Table IV. Summary of main project objectives

Project Stated project objectives

Rail projects

AVE Madrid - Barcelona (Spain)

Reduction in travel times on the existing corridor.

Increase capacity and safety conditions on the rail line.

Algarve Railway (Portugal)

Reduction in travel times and increase productivity.

Reduction in operating costs on the line.

Increase safety conditions.

Railway Thriassio – Kiato (Greece)

Reduction in travel times.

Increase safety conditions on the rail line.

Bratislava Railway Upgrade (Slovakia)

Reduction in travel times.

Increase safety conditions on the rail line.

Meet interoperability requirements.

Road projects

A2 Motorway (Poland)

Reduction in congestion on existing roads.

Improve safety conditions.

A23 Motorway (Spain)

Increase capacity on existing corridor.

Improve communications in low density areas.

Improve safety conditions.

Agios Konstantinos Bypass (Greece)

Reduction in travel times.

Increase safety conditions.

Improve connectivity between Greece and the EU.

M1 Northern Motorway (Ireland)

Reduction in travel times.

Facilitate growth at Dublin airport.

IX B Corridor (Lithuania)

Increase pavement strength.

Divert traffic away from Vilnius city centre.

Improve safety conditions on the existing corridor.

M0 Budapest Ring Road (Hungary)

Reduction in transport costs (travel times and congestion).

Divert traffic away from Budapest city centre

Source: Funding applications

In the next section we present a summary of the results of the in-depth ex post

evaluation of these projects.

Executive Summary

Results of the ex post evaluation

Tables V and VI present the economic appraisal indicators (Present Value of

Benefits, Present Value of Costs, Net Present Value, Benefit Cost Ratio, and

Internal Rate of Return) for the ten transport projects included in the study. In

carrying out the ex post evaluation, we have calculated a High case (optimistic)

outcome and a Low case (pessimist) outcome. For each indicator, tables V and

VI show the values for both High and Low case.

Table V. Ex post evaluation of rail projects – economic appraisal indicators

PVB (€m)

High

Low

PVC (€m)

High

Low

NPV (€m)

High

Low

BCR

High

Low

IRR

High

Low

Rail projects

AVE Madrid -

Barcelona (Spain)

5,744

4,856

7,692

7,593

-1,948

-2,736

0.7

0.6

3.7%

2.6%

Algarve Railway

(Portugal)

410

379

331

331

79

48

1.2

1.1

7.4%

6.7%

Railway Thriassio –

Kiato (Greece)

583

358

326

326

258

32

1.8

1.1

9.3%

6.1%

Bratislava Railway

Upgrade (Slovakia)

443

291

231

231

98

40

2.0

1.4

10.4%

7.8%

Note: For all schemes except for Bratislava Railway Upgrade (Slovakia) and Railway Thriassio – Kiato

(Greece) figures reported are in factor prices as oppose to market prices.3

3 Market prices (MP) refer to the prices for which a good or service is offered in the marketplace.

Factor prices (FP) are equal to market prices excluding the effects of taxes and subsidies on

products.

8 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

Table VI. Ex post evaluation of road projects – economic appraisal indicators

PVB (€m)

High

Low

PVC (€m)

High

Low

NPV (€m)

High

Low

BCR

High

Low

IRR

High

Low

Road projects

A2 Motorway

(Poland)

1,168

791

268

268

900

523

4.4

3.0

22.8%

18.2%

A23 Motorway

(Spain)

253

198

225

225

28

-28

1.1

0.9

6.3%

4.6%

Agios Konstantinos

Bypass (Greece)

488

438

206

206

283

233

2.4

2.1

13.4%

12.6%

M1 Northern

Motorway (Ireland)

4,140

4,040

235

235

3,905

3,805

17.6

17.2

53.0%

53.0%

IX B Corridor

(Lithuania)

300

288

88

88

212

200

3.4

3.3

56.0%

55.0%

M0 Budapest Ring

Road (Hungary) 1,187 213 974 5.6 24.8%

As tables V and VI show, most projects yield a positive net present value,

indicating that their economic benefits exceed their costs. In the AVE Madrid –

Barcelona project the NPV is negative for both the High case and the Low case

due to the high upfront capital costs of the project. The cost-benefit analysis of

this project, however, does not account for the wider socio-economic impacts of

the investment. These wider economic benefits include the impact on mobility

and accessibility, socio-economic structures, urban image and spatial effects.

These impacts are expected to be significant, although it is still too early to

appreciate their extent. Moreover, the wider economic benefits are difficult to

quantify in monetary terms, and therefore be added to the cost-benefit analysis in

a consistent way, as there is no agreed methodology for doing so.

The benefit-cost ratio of the ten projects ranges from 0.6-0.7 (Low-High) of the

AVE Madrid-Barcelona high speed train project in Spain to 17.2-17.6 (Low-

High) of the M1 Northern Motorway project in Ireland. The average benefit-

cost ratios for the ten projects are 3.6 (Low) and 4.0 (High); while the average

IRRs are 19.1 (Low) and 20.7 (High). If we exclude the M1 Northern Motorway

project in Ireland and the IX B Transport corridor in Lithuania (both projects

have a very high IRR), the average IRRs are 10.4% (Low) and 12.3% (High).

Executive Summary

These findings confirm that, overall, the projects analysed have delivered value

for money with the exception of the AVE Madrid-Barcelona high speed line

whose high capital costsexplain its unfavourable cost-benefit ratio.

Tables VII and VIII present the financial appraisal indicators obtained from the

ex post financial analysis of the ten selected projects. For each project, the tables

present the Net Present Value and the Internal Rate of Return of Investment

(“I”), and the Net Present Value and the Internal Rate of Return of Capital (“C”),

showing the results for both the High and Low case scenarios.

Table VII. Ex post evaluation of rail projects - Financial appraisal indicators

FNPV (I)

(€m)

High

Low

FIRR (I)

High

Low

FNPV (C)

(€m)

High

Low

FIRR (C)

High

Low

AVE Madrid -

Barcelona (Spain) -4,288

-4,766

0.6%

0.4%

-351

-919

4.5%

3.7%

Algarve Railway

(Portugal) -299

-299

-3.6%

-3.6%

-111

-111

0.2%

0.2%

Railway Thriassio –

Kiato (Greece) -101

-184

3.4%

1.8%

98

10

7.3%

5.3%

Bratislava Railway

Upgrade (Slovakia) -11

-28

4.4%

3.3%

81

65

15.1

13.6

Source: Funding applications and supporting material

10 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

Table VIII. Ex post evaluation of road projects - Financial appraisal indicators

FNPV (I)

(€m)

High

Low

FIRR (I)

High

Low

FNPV (C)

(€m)

High

Low

FIRR (C)

High

Low

A2 Motorway

(Poland) -263

-263

-3.5%

-3.5%

47

47

11.6%

11.6%

A23 Motorway

(Spain) -230

-230 n/a

-55

-55 n/a

Agios Konstantinos

Bypass (Greece) -166

-173

-1.3%

-1.7%

-78

-85

1.0%

0.5%

M1 Northern

Motorway (Ireland) -235

-235 n/a

-81

-81 n/a

IX B Corridor

(Lithuania) -95

-95 n/a

-28

-28 n/a

M0 Budapest Ring

Road (Hungary) 220 n/a -49 n/a

Source: Funding applications and supporting material

The financial NPV of seven of the ten projects is negative. However, this is not

surprising since most of these projects do not generate direct commercial

revenues and the financial analysis does not take the Cohesion Fund

contributions into account. Without taking those EU contributions into account,

some projects have a negative financial NPV but a positive economic NPV. The

interpretation is therefore that Cohesion Fund contributions help to „unlock‟ the

economic benefits of these projects.

Wider economic benefits

Our analysis also considered the wider social and economic impacts of each

project. Quantifying these wider impacts of transport projects on economic,

social and physical environments can be challenging. Normally, these are

impacts which cannot be included in the standard CBA, for a variety of reasons:

the lack of an agreed methodology to identify their monetary value;

the lack of data, which would make the quantification impossible even if

an agreed methodology was available; and,

Executive Summary

the difficulty to isolate a project‟s true impacts with a great deal of

certainty, especially in the context of rapidly changing environments (for

example, in the new Member States).

Therefore, the approach we used to assess the wider economic impacts was

largely qualitative. Below we summarise our findings in this area for each of the

ten projects included in the study.

AVE Madrid - Barcelona (Spain)

Most studies carried out on wider socio-economic impacts conclude that high-

speed rail is not a sufficient condition to cause major transformations in the cities

and regions connected by it. High-speed rail only facilitates socio-economic

changes that may be already underway. Access to high-speed rail services may

provide important competitive advantages to those cities that are on the high-

speed rail network compared with those that are not on the network and have

therefore fewer train services. According to the economic literature and

experience in other European countries where high-speed rail services have also

been introduced, the main wider economic impacts of high-speed rail

infrastructure and services appear to be mobility and accessibility, socio-

economic structures, urban image and spatial effects. We have found this to be

the case for the cities connected by the Madrid-Barcelona high-speed line,

particularly Zaragoza and Lleida.

Algarve Railway (Portugal)

The lack of any form of impact monitoring since the opening makes identifying a

causal link between the project and any wider effect very problematic. In this

kind of situations, it is difficult to separate the impacts of the project from the

impact of other ongoing changes in the economy. Nonetheless, there is some

evidence that per capita income might have improved in the regions connected

by the railway line. It is however problematic to attribute these changes just to

this project.

Railway Thriassio – Kiato (Greece)

This new line is approximately three years into its expected economic life, whilst

economic and social impacts often take many years to materialise. In addition,

the recent economic downturn is likely to have offset some of the potential

benefits of the project. As a result, the wider impacts of the project are hard to

isolate. Nonetheless, we were able to identify the following findings:

a number of stations on the new line are in peripheral locations relative

to their previous town centre positions. As a result they are now less

accessible compared to the stations located on the old routes;

the new out-of-town stations do offer a focal point for development

and have been integrated into local town master planning exercises;

12 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

the removal of trains from the built-up areas, and associated level

crossings, has offered local congestion benefits;

We note, however, that the true wider socio-economic benefits of the

project are unlikely to materialise until the line completes the rail link

between Patra port and Athens.

Bratislava Railway Upgrade (Slovakia)

The project was implemented during a period of rapid economic growth and

increasing car ownership. As a result, passenger numbers on the line have actually

fallen relative to 2005 levels. Moreover, the continued works on other segments

of the line have caused delays and cancellations further contributing to the fall in

passenger numbers. Finally, due to the global economic recession in 2008-2009, it

is difficult to attribute regional development impacts directly to the project.

However, we found that the project had contributed to meeting aspirations of

Slovak transport policy to increase accessibility to wider EU markets. It has also

been successful in improving communication and trade links between the two

major economic centres of Bratislava and Košice. The improved link also offers

increased accessibility to jobs located in the major urban areas of Bratislava and

Trnava.

A2 Motorway (Poland)

The project was implemented against a backdrop of rapid economic growth in

Poland. Therefore, it is difficult to establish a causal link between the A2 project

and specific impacts. Nonetheless, it is clear from our consultation with

stakeholders that the project (and future proposals to extend the A2 to Warsaw

and proposals for the north south A1 route) is regarded as a key enabler of

economic growth in central Poland. Key benefits of the project identified by

stakeholders include:

faster and more reliable connectivity between Poland and neighbouring

countries;

increased foreign direct investment in Poland;

quality of life improvements through reduced traffic on the bypassed

routes;

increased land values along the corridor; and

supported tourism access

Adverse impacts reported include noise and poorer air quality on the existing

R14 (at the eastern end of the A2 motorway).

A23 Motorway (Spain)

We note that the subprojects under analysis in this evaluation are relatively minor

compared to the whole of the A23. It is therefore difficult to establish causality

Executive Summary

links between these investments and any wider impact. Moreover, the A23 is one

of the many interventions that affected the region during the same period.

However, for the purpose of this evaluation, we managed to isolate the impacts

that are more specific to the segments considered.

In relation to the three subprojects located in the province of Teruel, we

obtained information about two new infrastructure projects (an industrial park

and an airport) developed in the area since the opening of the first road

segments. In relation to the subproject Huesca – Nueno, new infrastructures (an

industrial park, a technology centre, and new university buildings) have been

developed along the A23 near Huesca since the opening of the new road.

Agios Konstantinos Bypass (Greece)

This project was implemented during a period of economic change, making it

difficult to isolate its wider impacts. That said, stakeholders felt that the project

had helped unlock the following benefits:

it allowed the removal of traffic from bypassed settlements to enable

urban re-modelling;

it facilitated drainage works to address historical flooding issues;

it led to improved air quality and noise conditions; and

it enhanced ferry port access.

Collectively such impacts are helping Agiou Konstantinos to develop as a tourist

location.

M1 Northern Motorway (Ireland)

It is difficult to establish a link between the project and wider socio-economic

impacts as the project was implemented during a period of rapid growth in the

Irish economy. It is however clear that the project has formed an important

component of the general upgrade of the Ireland‟s transport network. The

construction of the project was a key factor in facilitating the construction of the

second terminal at Dublin Airport. There is also evidence of substantial growth

in the towns adjacent to the project, where congestion levels have dropped as a

result of the M1 Northern Motorway.

IX B Corridor (Lithuania)

Due to the rapid economic growth experience by Lithuania during the

construction phase, the specific wider impacts of this project are hard to isolate.

Nonetheless, it is clear that the project contributed significantly to the upgrading

of the Lithuanian transport network. Together with other projects, it helped set

up Free Economic Zones and open new logistic centres. It also contributed to

the regeneration of brownfield locations along the motorway (for example with

the set up of new shopping and residential centres).

14 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

M0 Budapest Ring Road (Hungary)

The M0 Eastern Sector and M31 are youthful in terms of their expected

economic life. The M0 opened 2 years ago and the M31 four months ago. As

such, their impacts on society and the economy have so far been limited.

Additionally, the recession has affected the economy throughout the period the

M0 has been open. Primarily as a consequence of their youthfulness, quality of

life benefits/costs (accessibility, air quality and noise disturbance) are thoe

impacts most readily observable. Accessibility benefits have been included in the

CBA and therefore we have not taken them into account in this case. There has

been, however, some economic development along the M0 corridor (e.g. retail

and logistic centres) and it is expected that more will occur, as municipalities are

zoning more land in the locality of the M0.

Key findings from the ex post evaluation

Some of the main contributions of ex post evaluation programmes are:

raised transparency and accountability;

strengthening the evidence base; and

providing feedback on the ex ante process.

We use these categories to illustrate our findings from the ten transport projects

regarding the benefits of ex post evaluation to project stakeholders (including

promoters), Member States and the European Commission.

Transparency and accountability. Overall, the ten transport projects

examined in this report demonstrate an acceptable or good value for money

from the perspective of the European taxpayer. There were however some

exceptions. Whilst these general finding represent positive news, in the spirit

of transparency and accountability, the publication of such ex post findings,

including those that identify a less satisfactory outcome, does allow

stakeholders, Member States and the Commission to ask hard and

sometimes uncomfortable questions of each other and the Member State‟s

planning authorities, which fosters accountability.

Strengthening of the evidence base. With only 10 transport projects

considered, the sample is too small in itself to demonstrate the existence of

any statistically significant patterns. However, with a full ex post programme,

a more extensive evidence base can be developed. This can then aid in the

planning of future transport projects. We summarise below our findings in

key areas.

Capital costs. We have found that the average of the difference

between ex ante and ex post capital costs across the ten projects is

Executive Summary

13.5%. This value is rather low and in line with current experience.

Nine projects have experienced cost overruns. The following factors

may contribute to explaining this difference between ex ante and ex

post values:

Firstly, the large cost overrun is associated with ex ante costs that

were developed well in advance of construction;

then project delays, alterations in scope and other unforeseen

circumstances all increased capital costs;

finally, we note that some Member States took the opportunity

when applying for Cohesion Funds to update the ex ante CBA with

a more up to date set of capital costs.

Utilisation rates. Generally, the utilisation rates we found are

compatible with the objective to build in sufficient spare capacity to give

room for growth over a project‟s lifetime. However, in one case (A23

Motorway in Spain), the utilisation rate was very low, while another

project (M1 Northern Motorway in Ireland) shows very high levels of

utilisation. These examples sugges an imbalance between ex ante

demand forecasts and actual demand.

NPV. Seven out of the 10 case study projects yielded an NPV that was

lower ex post than expected ex ante. We have also found that in eight out

of ten transport projects differences between ex ante and ex post travel

demand are a primary cause of the differences in NPV, whilst in five

transport projects differences in capital costs also contribute to this

discrepancy. Whilst a sample size of 10 cannot provide any statistically

robust conclusions, it appears to us that these findings, in conjunction

with some low utilisation rates and the actual cost overruns, are

indicative of optimism bias being prevalent in the ex ante analysis.

Feedback. An important attribute of CBA ex post analysis is the feedback

it can provide on demand modelling, ex ante appraisal and infrastructure

design. Some of the lessons learnt from our analysis of the ten transport

projects are:

Modelling practice. Ex ante demand modelling would benefit from

improvements in study area definition, modal coverage and inclusion of

induced traffic/variable demand.

Improved definition of the counterfactuals. We have identified

inappropriate assumptions regarding travel demand, traffic growth

and vehicle speeds in the „without‟ project scenarios. For rail and

toll motorway projects it is essential that the pricing policy is

defined correctly. Not only does the pricing policy affect the

16 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

distribution of benefits between operators and users but it also

strongly influences the demand for a project.

CBA practice. The CBA analyses would have benefited from:

more consistency in scope, the inclusion of environmental

externalities in the CBA and the incorporation of network effects;

a disaggregation between business and non-work transport user

classes;

an opportunity to improve the comparability of CBAs for decision-

makers, by moving towards harmonised definitions, measures

(units), methods and assumptions where appropriate – so that for

example the values of time, safety and environmental impacts used

in CBA will be on the same basis, even if they will not (rightly) be

exactly the same throughout the EU.

Risk analysis. The main sources of differences between ex ante and ex

post economic analyses were capital costs and travel demand.

Differences in travel demand occurred due to variances between ex ante

and ex post in terms of economic growth, development impacts and

whether other transport projects in the locality had been constructed. A

more comprehensive risk analysis at the ex ante stage would have enable

the assessment of these effects.

Identification of wider impacts. The lack of project monitoring

frameworks, to be implemented at project opening, makes the

identification of wider impacts particularly challenging. This is especially

the case for projects being implemented as part of a wider

modernisation strategy, during periods of economic change. In these

cases, identifying a causal link between a project and wider socio-

economic impacts is challenging.

Project design. The ex post analyses did not identify any unintended

consequences aside from impacts on noise that should have been

mitigated against. This suggests improvements in the design of such

mitigation measures are needed, however, the sample size is too small to

make a general statement based on this study.

Good practice guides and regulation. The desire for and need of

good practice guides on economic appraisal and demand modelling was

identified both in our interviews and in the Member States workshop.

There was a mixed response to the need for more regulation.

Executive Summary

Cost-benefit analysis as a method

One of the objectives of the study was to assess cost-benefit analysis as a

method. To do so, we considered five aspects of such an assessment as specified

in the TORs.

Strengths and weaknesses of CBA (as applied by Member States): Ex

ante CBA is a mature method regularly used worldwide. There is a basic

level of consistency in the use of CBA methodology for the appraisal of

transport infrastructure across EU Member States. Our findings from the

ten transport projects confirm the following:

the CBA framework used for the appraisal of these projects is both

consistent with DG REGIO‟s guidelines and with good practice. All

the appraisals consider investment costs (including ongoing

maintenance costs) on one side and measure the user benefits as well as

some externalities. Future benefits are discounted correctly and some

risk analysis, albeit limited to a handful of assumptions, has been

undertaken;

however, we found that the scope of the ex ante analysis has often been

narrower than what would be ideal. Often, the analysis only considers

times savings, vehicle operating cost savings and safety benefits, while

other impacts (for example, CO2 emissions, noise, pollution) are not

always taken into account;

different EU Member States use different appraisal parameters. This in

itself is not an issue, but there appears to be little similarity in some

instances between the values used and other sources for these values,

such as HEATCO;

we also identified weaknesses in the demand modelling, the definitions

of the counterfactuals and the modelling of network effects. We note

that a robust treatment of demand and the counterfactuals is

fundamental to the reliability of a cost-benefit analysis.

Effectiveness of CBA in decision-making (supporting the project

generation and project decision of the Member States and the

Commission). Whilst cost-benefit analysis is regularly used worldwide, it

forms only part of a broader decision-making process – even in countries

with a long history of using it. For many of the projects we reviewed, we

found that CBA had been used mainly to confirm that the project offered

value for money and to support the application to access EU funding.

Furthermore, it is clear from our discussions with stakeholders that this

limited role still remains in some EU Member States. One of the reasons,

aside from the time it takes to embed CBA into existing planning processes,

18 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

is that often projects are motivated by environmental and regional

development objectives. As these factors are not generally fully included in

the CBA, there may be concerns that CBA may lead to the prioritisation of

less desirable projects. However, we think that even within these constraints,

CBA can offer relevant information and be a useful tool to decision-makers

compared to the extent to which CBA is currently used.

at a technical level, CBA is particularly strong in comparing projects

that have relatively similar impacts. Thus, it can be used to help make

design choices, alignments (depending on the environmental impact),

and help prioritise different elements of a transport investment strategy;

at a political level, CBA also adds transparency to the decision making

process, and improves the accountability of the decision-makers.

Utility of ex post CBA (from the point of view of the project

promoters, Member States and the Commission). Ex post CBA can add

value to the planning process. t adds transparency, strengthens the evidence

base and provides feedback on the methods and techniques used to design

and appraise the infrastructure. For these reasons, active ex post CBA

programmes have been in place for some time in the UK and in France, for

example. Perhaps one of their key contributions has been to develop an

improved understanding of “optimism bias”: the systematic bias during the

planning phases of a project, whereby the benefits are overestimated, whilst

costs and completion times are underestimated. Ex post evaluation

programmes can help identify instances of optimism bias by identifying cost

overruns and their causes.

Ex post CBA as a tool for evaluating project impacts. Ex post CBA‟s

main strengths are its holistic approach, that is, its ability to consider a

project as a whole, as well as its ability to deliver an unambiguous indicator

of a project‟s economic worth. A further strength of ex post transport CBA

is that it focuses on the direct impacts of the transport project and its

associated externalities. This makes the project monitoring programme

reasonably straightforward. The focus on direct impacts is also a weakness,

since there can be a gap between project objectives (e.g. increased

employment and wealth to a region) and the inputs to a CBA.

Relevance and potential utility of CBA for macro-economic modelling.

A key strength of CBA is its ability to deliver an unambiguous indicator of a

project‟s worth. Macroeconomic models on the other hand focus on a

narrow range of impacts. Transport impacts included in a CBA that are not

relevant for macroeconomic modelling include those associated with non-

work time savings, safety and environmental externalities. At best, therefore,

only a fraction of transport CBA output is relevant for macroeconomic

Executive Summary

modelling ,namely, that associated with business and freight impacts and any

productivity changes due to agglomeration benefits. The value of transport

CBA output as a GDP indicator is undermined for two reasons:

it is a „net‟ benefit, that is, a series of gains and losses will occur as the

economy adjusts to a change in transport supply and economic activity

relocates in response to changes in transport accessibility; and

transport CBA measures the added value of bringing new resources into

use (increased output and employment), while macroeconomic

modelling measures the gross value.

These differences between CBA and macroeconomic modelling mean that in

practice the macroeconomic impacts of changes in accessibility are best

modelled by linking transport accessibility models directly with

macroeconomic models. This can lead to some inconsistencies between the

economic forecasts from the macroeconomic model and those that underpin

the transport model. These inconsistencies can be overcome through either

the use of a Land Use Transport Interaction (LUTI) model or a Spatial

Computable General Equilibrium (SCGE) model – neither of which are

trivial modelling exercises.

Recommendations

The study offers a set of recommendations on how to improve the practice of ex

ante project appraisal in the context of current EU regional policy instrument

processes and practices. Specifically, based on the findings of our study, we

recommend the Commission to undertake a review of the following areas:

Quality and consistency of ex ante CBA. Consider changes that could be

introduced into current regulations to improve the quality and consistency of

the ex ante CBA analysis applied to major transport infrastructure projects

supporting EU funding applications. These changes could include a set of

objective indicators regarding scope and depth of the CBA that the

application of the DG REGIO CBA guidelines should adhere to. Such

indicators would relate to, among others, issues such as appropriate network

definition to account for induced and redistributed traffic; appropriate

demand analysis and forecast modelling; thorough assessment of

environmental impacts – including climate change impacts – on the basis of

the latest available guidelines in the CBA literature; quantified risk and

sensitivity analyses; or compulsory inclusion of a lower-cost alternative

option to the proposed investment projects in the analysis submitted as part

of the funding application.

Ability to undertake ex post evaluation. Examine the possibility of

changing current regulations to improve the “evaluability” of major

20 Frontier Economics, Atkins, ITS | June 2011

Executive Summary

transport infrastructure projects that benefit from EU funding to better

assess their “value for money” ex post. Such improvements would require,

for example, a definition of “value for money” in terms of the opportunity

cost of the public funds used in the project, reaching from control of costs

through to delivery of outcomes, including system-wide impacts and more

focused outputs; requirements to set up a monitoring framework for data

collection and evaluation; set up fixed intervals to monitor ramp-up and

distribution effects and carry out ex post evaluations; systematic data

collection efforts; and assessment of potential role of alternative project

appraisal techniques;

Provision of training and further guidance. Create or facilitate ways to

provide guidance and train public sector officials on the use of ex ante CBA

analysis and ex post project “evaluability” design. This could be achieved by,

for example, sharing examples of good practice amongst practitioners;

offering qualified and targeted training on specific aspects of the CBA

analysis; and, creating opportunities for project promoters and potential

consultants to learn and share their knowledge.

Frontier Economics Limited in Europe is a member of the Frontier Economics network, which

consists of separate companies based in Europe (Brussels, Cologne, London & Madrid) and Australia

(Brisbane, Melbourne & Sydney). The companies are independently owned, and legal commitments

entered into by any one company do not impose any obligations on other companies in the network.

All views expressed in this document are the views of Frontier Economics Limited.

FRONTIER ECONOMICS EUROPE

BRUSSELS | COLOGNE | LONDON | MADRID

Frontier Economics Ltd 71 High Holborn London WC1V 6DA

Tel. +44 (0)20 7031 7000 Fax. +44 (0)20 7031 7001 www.frontier-economics.com