Use of Full Depth Shoulders on Wisconsin Highways

Steve Krebs, Bob Arndorfer, and Jed Peters – DTSD-Bureau of Technical Services

April 29, 2013

Literature Review Current Design Practices Pavement Performance Observations Full Depth Shoulder (FDS) Construction and Cost

Considerations FDS Life Cycle and Benefit-Cost Analyses Benefits Recommendations/Implementation Costs

Overview of presentation

2

Design Standards 1990 FHWA Advisory Mechanistic-Empirical Pavement Design Guide Wisconsin Highway Research Program (WHRP) Report

FDS Benefits Construction Maintenance of Traffic Incidents/Events Emergency Evacuations

Other State Practices

Literature Review

3

Geometry Thickness

Current WisDOT Design Practices

4

Pavement Distress NE Region SE Region NW Region

Preventative Measures

Pavement Performance Observations

5

10 Projects Analyzed 8 Concrete Mainline 2 HMA Mainline

As-built and Estimated FDS Costs

FDS Construction and Cost Considerations - Overview

6

FDS Construction and Cost Considerations – Cross-Sectional Assumptions

7

FDS Construction and Cost Considerations – Cross-Sectional Assumptions

8

Construction Cost Calculations

9

Concrete Mainline Projects As-built average (avg) cost: $182,920/mile FDS HMA avg cost: $346,430/mile FDS concrete avg cost: $265,000/mile

HMA Mainline Projects As-built average (avg) cost: $123,320/mile FDS HMA avg cost: $171,600/mile

Construction Cost Summary

10

Costs/Impacts not Considered Maintenance Schedules

Conventional FDS

Time Value of Money

Life Cycle Cost Analysis (LCCA) - Overview

11

Concrete Mainline Projects As-built avg net present value (NPV) life-cycle 50 year cost:

$276,720/mile FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile FDS concrete avg NPV life-cycle 50 year cost :

$345,140/mile

HMA Mainline Projects As-built avg NPV life-cycle 50 year cost : $198,050/mile FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile

* NPV calculated with 3.5% discount rate

LCCA– Summary

12

13

Split Axis LCCA Cash Flow

LCCA vs BCA Dissimilar Alternative: User Delay

Conventional Shoulder User Delay NPV = $146,830/mile

Benefit Cost Analysis (BCA)

14

Concrete Mainline Projects As-built avg NPV life-cycle 50 year cost: $423,550/mile FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile FDS concrete avg NPV life-cycle 50 year cost :

$345,140/mile

HMA Mainline Projects As-built avg NPV life-cycle 50 year cost : $344,880/mile FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile

* NPV calculated with 3.5% discount rate

BCA– Summary

15

Non-Denominated IH-43 IH-94

Denominated IH-39 – Shoulder Replacement IH-94 – Shoulder Widening USH 41 – Shoulder Widening

Additional Identified Benefits

16

Estimated As-Built Construction Cost/Mile $151,570/mile (1984 Dollars) $337,550/mile (2012 Dollars)

Estimated 10” FDS Construction Cost/Mile $190,840/mile (1984 Dollars) $425,010/mile (2012 Dollars)

LCCA Costs As-built NPV = $456,110/mile FDS NPV = $535,720/mile

2012 Project - 8” Shoulders Let Cost/Mile $333,850/mile

IH-39 Cost Summary

17

Adjusted LCCA Costs As-built NPV = $515,000/mile FDS NPV = $467,540/mile

IH-39 Cost Summary Cont…

18

USH 41 Existing Cross Section

19

USH 41 As-Designed/Built Cross Section

20

USH 41 Theoretical Widening with Incorporation of FDS

21

Actual Widening Cost = $7.28 Million Estimated Widening Cost with Incorporation of

FDS = $5.17 Million Cost Savings of $272,000/mile

USH 41 Cost Summary

22

Actual Widening Cost = $3.99 Million Estimated Widening Cost with Incorporation of

FDS = $3.07 Million Cost Savings of $178,000/mile

IH-94 Cost Summary

23

Selective Application of FDS High Volume Arterial Corridors Mass Evacuation Routes

Incorporate FDS (Existing and Future) into Emergency Planning

Recommendations

24

25

Volumes Estimated For Highest Direction in 30th Highest Hour in 2013

Average Outside FDS Cost: $248,575/mile Average Inside FDS Cost: $165,480/mile

HMA Conventional Shoulder to Concrete FDS Outside shoulder only: additional $108,100/mile Both shoulders: additional $164,000/mile

Concrete Conventional Shoulder to Concrete FDS Outside shoulder only: savings of $28,800/mile Both shoulders: savings of $41,500/mile

Cost to Implement

26

Southeast N-S and Zoo Freeways

Southwest IH-39 Corridor Reconstruction

Northeast USH 41 (Winnebago and Brown Counties)

Region Self Implementation

27