Steel Erection Standard Orientation PART2

Embed Size (px)

Citation preview

  • 8/2/2019 Steel Erection Standard Orientation PART2

    1/36

    1926.7521926.752--754754

    Subpart R Steel ErectionSubpart R Steel Erection

  • 8/2/2019 Steel Erection Standard Orientation PART2

    2/36

    .752 Site Layout, Erection Plan,.752 Site Layout, Erection Plan,

    Construction SequenceConstruction Sequence

  • 8/2/2019 Steel Erection Standard Orientation PART2

    3/36

    Approval to begin steel erection - Beforeauthorizing the startof steel erection, thecontrolling contractormust ensure that

    the steel erector is provided with thefollowing writtennotifications:

    Written AuthorizationWritten Authorization

  • 8/2/2019 Steel Erection Standard Orientation PART2

    4/36

    Concrete in footings, piers or walls mustreach 75% of the intended minimum

    compressive strength or sufficient strength tosupport loads (as approved by the Engineerof Record)

    Repairs to anchor bolts must be inaccordance with .755(b)

    Written NotificationsWritten Notifications

  • 8/2/2019 Steel Erection Standard Orientation PART2

    5/36

    All concrete and masonry testing

    must be done in accordance withAmerican Society of Testing andManufacturing (ASTM) standards

    Testing RequirementsTesting Requirements

  • 8/2/2019 Steel Erection Standard Orientation PART2

    6/36

    Commencement of Steel erection -

    Steel erection contractorshall not erectsteel unlesswritten notice that the

    concrete in the footings, piers and wallsor mortar in the masonry piers hasattained 75% of minimum compressive

    strength

    Written NotificationsWritten Notifications

  • 8/2/2019 Steel Erection Standard Orientation PART2

    7/36

    The controlling contractor

    shall provide and maintain:Adequate access roads

    Firm, properly graded,

    drained area readilyaccessible with adequatespace for safe storage ofmaterials and equipment

    Site LayoutSite Layout

  • 8/2/2019 Steel Erection Standard Orientation PART2

    8/36

    Site LayoutSite Layout

  • 8/2/2019 Steel Erection Standard Orientation PART2

    9/36

    Site LayoutSite Layout

    Routes preplanned to

    ensure no employeerequired to workunder a suspended

    load except: Connectors

    Employees

    responsible forhooking/unhookingthe load

  • 8/2/2019 Steel Erection Standard Orientation PART2

    10/36

    Erection PlanErection Plan

    Site-Specific Erection Plan - Allowed as an

    alternative to some specific provisions: 1926.753(c)(5) deactivating safety latches

    1926.757(a)(4) setting some steel joists

    1926.757(e)(4)(i) placing bundled decking

    shall be developed by a qualified person and be

    available Due to changing scope from project to project, a

    plan may be good practice for ALL operations

  • 8/2/2019 Steel Erection Standard Orientation PART2

    11/36

    .753 Hoisting and Rigging.753 Hoisting and Rigging

  • 8/2/2019 Steel Erection Standard Orientation PART2

    12/36

    It happensIt happens

  • 8/2/2019 Steel Erection Standard Orientation PART2

    13/36

    InspectionsInspections

    Pre-shift visual

    inspection ofcranes by acompetent

    person

  • 8/2/2019 Steel Erection Standard Orientation PART2

    14/36

    Main Inspection PointsMain Inspection Points

    Control mechanisms

    Drive mechanism

    Safety devices

    Air & hydraulic lines

    Hooks & latches

    Wire rope reeving

    Electrical equipment

    Hydraulic fluid levels

    Tires Ground conditions

    Level of equipment Level of equipment

    after each move

  • 8/2/2019 Steel Erection Standard Orientation PART2

    15/36

    InspectionsInspections

    The operator shallbe responsible forthose operationsunder the operator'sdirect control.

    Whenever there is

    any doubt as tosafety, the operatorshall have the

    authority to stop andrefuse to handleloads until safetyhas been assured

  • 8/2/2019 Steel Erection Standard Orientation PART2

    16/36

    InspectionsInspections

    A qualified rigger shall inspect the riggingprior to each shift

  • 8/2/2019 Steel Erection Standard Orientation PART2

    17/36

    Crane Supported PlatformsCrane Supported Platforms

    Cranes may hoistemployees with a

    personnel platformmeeting therequirements of .550(g)

    For steel erectionactivities, the

    determination of noother feasible means

    is no longer required

    Still recommended,however

  • 8/2/2019 Steel Erection Standard Orientation PART2

    18/36

    No Riding the Ball!!!No Riding the Ball!!!

  • 8/2/2019 Steel Erection Standard Orientation PART2

    19/36

    Hoisting OperationsHoisting Operations

    May deactivate

    safety latches onhooks for some

    purlin and joisthoisting if doneunder an erection

    plan. This nylon sling could cut

  • 8/2/2019 Steel Erection Standard Orientation PART2

    20/36

    Working Under LoadsWorking Under Loads

    Routes preplanned toensure no employee

    required to workunder a suspendedload except:

    Connectors

    Employeesresponsible forhooking/unhookingthe load

  • 8/2/2019 Steel Erection Standard Orientation PART2

    21/36

    Working Under LoadsWorking Under Loads

    When working undersuspended loads:

    Routes shall bepre-planned

    Materials shall berigged to preventunintentional

    displacement Hooks shall have

    self-closing latches

  • 8/2/2019 Steel Erection Standard Orientation PART2

    22/36

    Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure

    (Christmas Treeing)(Christmas Treeing)

    Multiple Lift Rigging

    procedure - can be usedonly with:

    Maximum of 5 members

    Only structural members

    Properly trained employees

    Components shall bedesigned with a 5 to 1safety factor

  • 8/2/2019 Steel Erection Standard Orientation PART2

    23/36

    Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure

    (Christmas Treeing)(Christmas Treeing) Total load shall not exceed

    the rated capacity of thehoisting or rigging equipment

    Rigging assembly shall be

    rigged with the membersattached at their center ofgravity and maintained

    reasonably level; rigged fromthe top down; rigged at least7 ft apart

  • 8/2/2019 Steel Erection Standard Orientation PART2

    24/36

    Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure

    (Christmas Treeing)(Christmas Treeing)

  • 8/2/2019 Steel Erection Standard Orientation PART2

    25/36

    .754 Structural Steel Assembly.754 Structural Steel Assembly

  • 8/2/2019 Steel Erection Standard Orientation PART2

    26/36

    .754 Structural Steel Assembly.754 Structural Steel Assembly

    Structural

    stabilitymaintainedat all times

  • 8/2/2019 Steel Erection Standard Orientation PART2

    27/36

    .754 Structural Steel Assembly.754 Structural Steel Assembly

    Permanent floors no

    more than 8 floorsbetween the erection

    floor and the upper-

    most permanent floor No more than 4 floors

    or 48 ft. of unfinished

    bolting above theuppermost unfinished

    floor

  • 8/2/2019 Steel Erection Standard Orientation PART2

    28/36

    .754 Structural Steel Assembly.754 Structural Steel Assembly

    A fully planked or decked floor or nets

    within 2 floors or 30 ft.

  • 8/2/2019 Steel Erection Standard Orientation PART2

    29/36

    Walking/Working SurfacesWalking/Working Surfaces

    Shear connectors shall not be attached to the

    top flanges of beams, joistsor beam attachments so thatthey project vertically from orhorizontally across the top

    flange of the member untilafter the decking has beeninstalled

    shall not be laid out andinstalled until after thedecking has been installed,using the deck as a work

    platform

  • 8/2/2019 Steel Erection Standard Orientation PART2

    30/36

    Walking/Working SurfacesWalking/Working Surfaces

    PerimeterBeam with

    Bent Plate

    Shear

    studs onbridgebeams

  • 8/2/2019 Steel Erection Standard Orientation PART2

    31/36

    Skeletal Steel Construction

    Workers shall not be permitted to walk thetop surface of any structural steel memberwhich has been finish coated with paint or

    similar material, due to the potential forslip and fall hazards (unless the surface isno more slippery than the original steel

    finish requires specific testing) (five year moratorium)

    Walking/Working SurfacesWalking/Working Surfaces

  • 8/2/2019 Steel Erection Standard Orientation PART2

    32/36

    Decking

    Do not use strapping for hoisting

    Loose items on top shall be secured Land bundles on supports to allow unbanding

    At the end of a shift (or when environmental

    conditions require), all decking must be secured

    Walking/Working SurfacesWalking/Working Surfaces

  • 8/2/2019 Steel Erection Standard Orientation PART2

    33/36

    Roof and Floor openings -Metal deck shall be installed

    as follows: Framed deck openings shall

    have structural membersturned down to allow continuous deckinstallation

    Roof and floor openings shall be coveredduring the decking process

    Walking/Working SurfacesWalking/Working Surfaces

  • 8/2/2019 Steel Erection Standard Orientation PART2

    34/36

    Covers for roof and floor

    openings must support,

    without failure, twice the

    maximum intended load.

    All covers must be secured

    All covers marked with highvisibility paint and the word

    HOLE or COVER

    Skylights must meet thesame load requirements

    Walking/Working SurfacesWalking/Working Surfaces

  • 8/2/2019 Steel Erection Standard Orientation PART2

    35/36

    Holes and openings not cutuntil essential to the

    construction process, andimmediately protected

    Space around columnsprotected

    Walking/Working SurfacesWalking/Working Surfaces

  • 8/2/2019 Steel Erection Standard Orientation PART2

    36/36

    Floor decking laid tightlyand secured

    Derrick floors fully decked(derrick floors defined as

    completed floors whereerection is being performed,along with storage areas onthose floors)

    Walking/Working SurfacesWalking/Working Surfaces