Upload
salmaan-ayub
View
279
Download
4
Embed Size (px)
Citation preview
8/2/2019 Steel Erection Standard Orientation PART2
1/36
1926.7521926.752--754754
Subpart R Steel ErectionSubpart R Steel Erection
8/2/2019 Steel Erection Standard Orientation PART2
2/36
.752 Site Layout, Erection Plan,.752 Site Layout, Erection Plan,
Construction SequenceConstruction Sequence
8/2/2019 Steel Erection Standard Orientation PART2
3/36
Approval to begin steel erection - Beforeauthorizing the startof steel erection, thecontrolling contractormust ensure that
the steel erector is provided with thefollowing writtennotifications:
Written AuthorizationWritten Authorization
8/2/2019 Steel Erection Standard Orientation PART2
4/36
Concrete in footings, piers or walls mustreach 75% of the intended minimum
compressive strength or sufficient strength tosupport loads (as approved by the Engineerof Record)
Repairs to anchor bolts must be inaccordance with .755(b)
Written NotificationsWritten Notifications
8/2/2019 Steel Erection Standard Orientation PART2
5/36
All concrete and masonry testing
must be done in accordance withAmerican Society of Testing andManufacturing (ASTM) standards
Testing RequirementsTesting Requirements
8/2/2019 Steel Erection Standard Orientation PART2
6/36
Commencement of Steel erection -
Steel erection contractorshall not erectsteel unlesswritten notice that the
concrete in the footings, piers and wallsor mortar in the masonry piers hasattained 75% of minimum compressive
strength
Written NotificationsWritten Notifications
8/2/2019 Steel Erection Standard Orientation PART2
7/36
The controlling contractor
shall provide and maintain:Adequate access roads
Firm, properly graded,
drained area readilyaccessible with adequatespace for safe storage ofmaterials and equipment
Site LayoutSite Layout
8/2/2019 Steel Erection Standard Orientation PART2
8/36
Site LayoutSite Layout
8/2/2019 Steel Erection Standard Orientation PART2
9/36
Site LayoutSite Layout
Routes preplanned to
ensure no employeerequired to workunder a suspended
load except: Connectors
Employees
responsible forhooking/unhookingthe load
8/2/2019 Steel Erection Standard Orientation PART2
10/36
Erection PlanErection Plan
Site-Specific Erection Plan - Allowed as an
alternative to some specific provisions: 1926.753(c)(5) deactivating safety latches
1926.757(a)(4) setting some steel joists
1926.757(e)(4)(i) placing bundled decking
shall be developed by a qualified person and be
available Due to changing scope from project to project, a
plan may be good practice for ALL operations
8/2/2019 Steel Erection Standard Orientation PART2
11/36
.753 Hoisting and Rigging.753 Hoisting and Rigging
8/2/2019 Steel Erection Standard Orientation PART2
12/36
It happensIt happens
8/2/2019 Steel Erection Standard Orientation PART2
13/36
InspectionsInspections
Pre-shift visual
inspection ofcranes by acompetent
person
8/2/2019 Steel Erection Standard Orientation PART2
14/36
Main Inspection PointsMain Inspection Points
Control mechanisms
Drive mechanism
Safety devices
Air & hydraulic lines
Hooks & latches
Wire rope reeving
Electrical equipment
Hydraulic fluid levels
Tires Ground conditions
Level of equipment Level of equipment
after each move
8/2/2019 Steel Erection Standard Orientation PART2
15/36
InspectionsInspections
The operator shallbe responsible forthose operationsunder the operator'sdirect control.
Whenever there is
any doubt as tosafety, the operatorshall have the
authority to stop andrefuse to handleloads until safetyhas been assured
8/2/2019 Steel Erection Standard Orientation PART2
16/36
InspectionsInspections
A qualified rigger shall inspect the riggingprior to each shift
8/2/2019 Steel Erection Standard Orientation PART2
17/36
Crane Supported PlatformsCrane Supported Platforms
Cranes may hoistemployees with a
personnel platformmeeting therequirements of .550(g)
For steel erectionactivities, the
determination of noother feasible means
is no longer required
Still recommended,however
8/2/2019 Steel Erection Standard Orientation PART2
18/36
No Riding the Ball!!!No Riding the Ball!!!
8/2/2019 Steel Erection Standard Orientation PART2
19/36
Hoisting OperationsHoisting Operations
May deactivate
safety latches onhooks for some
purlin and joisthoisting if doneunder an erection
plan. This nylon sling could cut
8/2/2019 Steel Erection Standard Orientation PART2
20/36
Working Under LoadsWorking Under Loads
Routes preplanned toensure no employee
required to workunder a suspendedload except:
Connectors
Employeesresponsible forhooking/unhookingthe load
8/2/2019 Steel Erection Standard Orientation PART2
21/36
Working Under LoadsWorking Under Loads
When working undersuspended loads:
Routes shall bepre-planned
Materials shall berigged to preventunintentional
displacement Hooks shall have
self-closing latches
8/2/2019 Steel Erection Standard Orientation PART2
22/36
Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure
(Christmas Treeing)(Christmas Treeing)
Multiple Lift Rigging
procedure - can be usedonly with:
Maximum of 5 members
Only structural members
Properly trained employees
Components shall bedesigned with a 5 to 1safety factor
8/2/2019 Steel Erection Standard Orientation PART2
23/36
Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure
(Christmas Treeing)(Christmas Treeing) Total load shall not exceed
the rated capacity of thehoisting or rigging equipment
Rigging assembly shall be
rigged with the membersattached at their center ofgravity and maintained
reasonably level; rigged fromthe top down; rigged at least7 ft apart
8/2/2019 Steel Erection Standard Orientation PART2
24/36
Multiple Lift Rigging ProcedureMultiple Lift Rigging Procedure
(Christmas Treeing)(Christmas Treeing)
8/2/2019 Steel Erection Standard Orientation PART2
25/36
.754 Structural Steel Assembly.754 Structural Steel Assembly
8/2/2019 Steel Erection Standard Orientation PART2
26/36
.754 Structural Steel Assembly.754 Structural Steel Assembly
Structural
stabilitymaintainedat all times
8/2/2019 Steel Erection Standard Orientation PART2
27/36
.754 Structural Steel Assembly.754 Structural Steel Assembly
Permanent floors no
more than 8 floorsbetween the erection
floor and the upper-
most permanent floor No more than 4 floors
or 48 ft. of unfinished
bolting above theuppermost unfinished
floor
8/2/2019 Steel Erection Standard Orientation PART2
28/36
.754 Structural Steel Assembly.754 Structural Steel Assembly
A fully planked or decked floor or nets
within 2 floors or 30 ft.
8/2/2019 Steel Erection Standard Orientation PART2
29/36
Walking/Working SurfacesWalking/Working Surfaces
Shear connectors shall not be attached to the
top flanges of beams, joistsor beam attachments so thatthey project vertically from orhorizontally across the top
flange of the member untilafter the decking has beeninstalled
shall not be laid out andinstalled until after thedecking has been installed,using the deck as a work
platform
8/2/2019 Steel Erection Standard Orientation PART2
30/36
Walking/Working SurfacesWalking/Working Surfaces
PerimeterBeam with
Bent Plate
Shear
studs onbridgebeams
8/2/2019 Steel Erection Standard Orientation PART2
31/36
Skeletal Steel Construction
Workers shall not be permitted to walk thetop surface of any structural steel memberwhich has been finish coated with paint or
similar material, due to the potential forslip and fall hazards (unless the surface isno more slippery than the original steel
finish requires specific testing) (five year moratorium)
Walking/Working SurfacesWalking/Working Surfaces
8/2/2019 Steel Erection Standard Orientation PART2
32/36
Decking
Do not use strapping for hoisting
Loose items on top shall be secured Land bundles on supports to allow unbanding
At the end of a shift (or when environmental
conditions require), all decking must be secured
Walking/Working SurfacesWalking/Working Surfaces
8/2/2019 Steel Erection Standard Orientation PART2
33/36
Roof and Floor openings -Metal deck shall be installed
as follows: Framed deck openings shall
have structural membersturned down to allow continuous deckinstallation
Roof and floor openings shall be coveredduring the decking process
Walking/Working SurfacesWalking/Working Surfaces
8/2/2019 Steel Erection Standard Orientation PART2
34/36
Covers for roof and floor
openings must support,
without failure, twice the
maximum intended load.
All covers must be secured
All covers marked with highvisibility paint and the word
HOLE or COVER
Skylights must meet thesame load requirements
Walking/Working SurfacesWalking/Working Surfaces
8/2/2019 Steel Erection Standard Orientation PART2
35/36
Holes and openings not cutuntil essential to the
construction process, andimmediately protected
Space around columnsprotected
Walking/Working SurfacesWalking/Working Surfaces
8/2/2019 Steel Erection Standard Orientation PART2
36/36
Floor decking laid tightlyand secured
Derrick floors fully decked(derrick floors defined as
completed floors whereerection is being performed,along with storage areas onthose floors)
Walking/Working SurfacesWalking/Working Surfaces