Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes Hook-Up Procedure for Site Erection for OSX Ship Yard Cranes (Eletric Part) Rev. Date 2012.11.05 Kumoh

Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Embed Size (px)

DESCRIPTION

site erection procedure

Citation preview

Page 1: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

Hook-Up Procedure for Site Erection

for

OSX Ship Yard Cranes (Eletric Part)

Rev. Date 2012.11.05

Kumoh

Page 2: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

2 of 7 pages

Out-Line

This procedure is a guidance of erection works for the cranes designed and built by KUMOH which will be supplied to OSX.

All equipments in cranes have been so precisely designed and manufactured that care must be taken to maintain their original condition even after transportation.

“Qualified SPECIALIST” is the person has got used to installing products, loading, starting on, managing, and cleaning and in good repair. Qualified someone needs to have full attention to contents included all the warning and processing to cleaning and in good repair.

• According to established safety process, someone needs to have educated or qualified about a circuit and ground connection, tag of equipment.

• According to established safety process, you need to have educated or qualified about managing protective gear and using.

• Need to have educated first-aid treatment.

Qualified expert

Out-Line

Page 3: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

3 of 7 pages

Contents Out-Line ....................................................................................................................................................... 2

Contents ...................................................................................................................................................... 3

1. General Matters ...................................................................................................................................... 4 1.1. Working area must be fenced off, and tools are also needed to be well organized. ..................... 4 1.2. All managers must be informed of work details in advance. .......................................................... 4 1.3. Assembly work should be done by skilled and qualified persons. ................................................. 4 1.4. Check if all power supply is shut down before commencing any work. ......................................... 4 1.5. Make sure of no persons staying under moving oad and at its vicinity. ......................................... 4

2. Site Erection Flow .................................................................................................................................. 5 2.1. Flow Chart for Site Erection ........................................................................................................... 5 2.2. Explanation for Site Erection .......................................................................................................... 6 2.2.1. Erection each Equipments for cranes ......................................................................................... 6 2.2.2. Cable pulling Equipments to the others ...................................................................................... 6 2.2.3. Reconnection the pulled cables .................................................................................................. 7

3. Attachment (Typical Installing Drawing) .............................................................................................. 7

Page 4: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

4 of 7 pages

1. General Matters This Procedure covers Site Erection for OSX Ship Yard Cranes.

Site Erection must be cause followings ;

1.1. Working area must be fenced off, and tools are also needed to be well organized.

1.2. All managers must be informed of work details in advance.

1.3. Assembly work should be done by skilled and qualified persons.

1.4. Check if all power supply is shut down before commencing any work.

1.5. Make sure of no persons staying under moving oad and at its vicinity.

If this procedure is NOT contained adequacy, sufficient part or having any question, please contact our engineer(s) to ;

Kumoh heavy Industrial Co., Ltd / Design Team TEL: +82-55-521-5700 FAX: +82-55-521-4700 E-Mail: [email protected]

Page 5: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

5 of 7 pages

2. Site Erection Flow

2.1. Flow Chart for Site Erection

Confirm Erection

Preparing for Site Erection

Erection each Equipments for crane

NOChecking by Supervisor

YES

Cable pulling Equipments to the others

NOChecking by Supervisor

YES

Reconnection the pulled cables

NOChecking by Supervisor

YES

Page 6: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

6 of 7 pages

2.2. Explanation for Site Erection

2.2.1. Erection each Equipments for cranes

Erection each electrical Equipments as “Electrical Equipment Arrangement” which drawing No. is as following table ;

No. Item Number Q’ty Drawing No. Remarks1 OSX-CN-10-SPC-00001 1 Set UPA01-150.01-EI-DF-KUM-0102-15 2 OSX-CN-10-SPC-00002 4 Set UPA01-150.01-EI-DF-KUM-0202-15 3 OSX-CN-10-SPC-00015A 2 Set UPA01-150.01-EI-DF-KUM-15A02-15 4 OSX-CN-10-SPC-00015C 2 Set UPA01-150.01-EI-DF-KUM-15C02-15 5 OSX-CN-10-SPC-00016 1 Set UPA01-150.01-EI-DF-KUM-1602-15 6 OSX-CN-10-SPC-00017 1 Set UPA01-150.01-EI-DF-KUM-1702-14 7 OSX-CN-10-SPC-00018 4 Set UPA01-150.01-EI-DF-KUM-1802-14 8 OSX-CN-10-SPC-00020 1 Set UPA01-150.01-EI-DF-KUM-2002-14 9 OSX-CN-20-SPC-00010 1 Set UPA01-150.03-EI-DF-KUM-1002-14 10 OSX-CN-20-SPC-00012 1 Set UPA01-150.03-EI-DF-KUM-2002-15 11 OSX-CN-20-SPC-00013 1 Set UPA01-150.03-EI-DF-KUM-1302-14 12 OSX-CN-20-SPC-00017-1 8 Set UPA01-150.03-EI-DF-KUM-1702-14 13 OSX-CN-20-SPC-00019-1 4 Set UPA01-150.03-EI-DF-KUM-1902-15 14 OSX-CN-20-SPC-00024 1 Set UPA01-150.05-EI-DF-KUM-2402-14 15 OSX-CN-40-SPC-00012 1 Set UPA01-150.07-EI-DF-KUM-1202-14

And Refer 3. Attachment (Typical Installing Drawing)

2.2.2. Cable pulling Equipments to the others

After erection electrical equipments then, cable pulling must be done by “Interconnection wiring diagram” which conform wiring tag, numbering, location and etc. Its drawing No. for each cranes as following table ;

No. Item Number Q’ty Drawing No. Remarks1 OSX-CN-10-SPC-00001 1 Set UPA01-150.01-EI-DH-KUM-0103-00~ 2 OSX-CN-10-SPC-00002 4 Set UPA01-150.01-EI-DH-KUM-0303-00~ 3 OSX-CN-10-SPC-00015A 2 Set UPA01-150.01-EI-DH-KUM-15A03-00~ 4 OSX-CN-10-SPC-00015C 2 Set UPA01-150.01-EI-DH-KUM-15C03-00~ 5 OSX-CN-10-SPC-00016 1 Set UPA01-150.01-EI-DH-KUM-1603-00~ 6 OSX-CN-10-SPC-00017 1 Set UPA01-150.01-EI-DH-KUM-1703-00~ 7 OSX-CN-10-SPC-00018 4 Set UPA01-150.01-EI-DH-KUM-1803-00~ 8 OSX-CN-10-SPC-00020 1 Set UPA01-150.01-EI-DH-KUM-2003-00~ 9 OSX-CN-20-SPC-00010 1 Set UPA01-150.03-EI-DH-KUM-1003-00~ 10 OSX-CN-20-SPC-00012 1 Set UPA01-150.03-EI-DH-KUM-2003-00~ 11 OSX-CN-20-SPC-00013 1 Set UPA01-150.03-EI-DH-KUM-1303-00~ 12 OSX-CN-20-SPC-00017-1 8 Set UPA01-150.03-EI-DH-KUM-1703-00~ 13 OSX-CN-20-SPC-00019-1 4 Set UPA01-150.03-EI-DH-KUM-1903-00~ 14 OSX-CN-20-SPC-00024 1 Set UPA01-150.05-EI-DH-KUM-2403-00~ 15 OSX-CN-40-SPC-00012 1 Set UPA01-150.07-EI-DH-KUM-1203-00~

Page 7: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0

Hook-Up Procedure for Site Erection For OSX Ship Yard Cranes

7 of 7 pages

2.2.3. Reconnection the pulled cables

Reconnect already installed equipments. As “Interconnection wiring diagram” which is drawing for Interconnection.

3. Attachment (Typical Installing Drawing)

Page 8: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 9: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 10: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 11: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 12: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 13: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 14: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 15: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 16: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0
Page 17: Hook-Up Procedure for Site Erection(Erection Manual)_Brazil OSX_r0