Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

Embed Size (px)

Citation preview

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    1/10

      Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, October 2009 / Copyright © 2009 Japan Concrete Institute  287 

    Invited paper

    Seismic Damage of and Seismic Rehabilitation Techniques for RailwayReinforced Concrete Structures

    Tadayoshi Ishibashi1 and Daisuke Tsukishima2 

    Received 6 June 2009, revised 20 August 2009

    Abstract

    The Miyagi Prefecture Earthquake in 1978 was the first earthquake to cause serious damage to railway concrete structures

    in Japan. This was followed by the South Hyogo Prefecture Earthquake in 1995, which caused shear failure of columns of

    RC viaducts carrying the Shinkansen (Bullet Train) and old railroad lines predating the 1983 seismic design standard. As

    the result of various concrete structures sustaining extensive damage never experienced before, the seismic design stan-

    dard was greatly revised, and the seismic rehabilitation of existing structures was started on a full scale.Basic concept of seismic rehabilitation is to prevent shear failure of columns that led to the collapse of RC viaducts and

     bridges catastrophically occurred in whole structural frame during the past large earthquakes. To enhance the seismic

    capacity of the whole structural frame, increase in ductility of each column through seismic rehabilitation capable ofabsorbing seismic energy is needed.

    As the space under many railway viaducts is used by stations and shops, negotiations regarding the relocation of busi-

    nesses, the removal of large obstacles such as heavy machinery, and the development of valid seismic rehabilitationmethods to reinforce a large number of massive columns were called for. At present, we are trying to enhance seismic

    capacity as much as possible for new structures in order to prevent serious damage and enable early restoration.

    1. Introduction

    The Miyagi Prefecture Earthquake in 1978 was the first

    earthquake to cause serious damage to railway concrete

    structures in Japan. As a result, the seismic design stan-

    dard was revised in 1983. However, as the revision of theseismic design standard was not retroactively applied to

    existing structures, these structures did not undergo

    seismic rehabilitation. Afterwards, the South Hyogo

    Prefecture Earthquake occurred in 1995 and columns of

    RC viaducts carrying Shinkansen and old railroad lines

    constructed with pre-1983 seismic design standards

    suffered shear failure. As the result of various concrete

    structures sustaining extensive damage never experi-

    enced before, the seismic design standard was greatly

    revised, and the seismic rehabilitation of existing struc-

    tures was started on a full scale. The subsequent occur-

    rence of several severe earthquakes further underlined

    the urgency and importance of the seismic rehabilitationof existing railway structures to secure the safety of

    railway transportation (Table 1). This paper describes

    the damage to railway RC structures caused by earth-

    quakes in Japan and various seismic rehabilitation

    methods developed in the process of advancing seismic

    rehabilitation.

    2. Seismic damage of railway RC structure

    The Miyagi Prefecture Earthquake in 1978 caused shoe

    damage at many railway facilities such as RC viaducts

    and RC piers (Fig. 1). In response, restrainer cables have

     been installed in bridge movement joints and bracketshave been attached to abutments on all railway lines in

    Japan. However, before the South Hyogo Prefecture

    Earthquake in 1995, no seismic rehabilitation for RC

    structures had been conducted except for measures pro-

    viding against the Tokai Earthquake. In the 1980s, an RC

    viaduct for the Shinkansen in the Shizuoka area was

    reinforced with steel plate jacketing and a connecting

    adjacent viaduct with prestressing cable. 

    Due to the South Hyogo Prefecture Earthquake in

    1995, many columns of RC viaducts suffered shear fail-

    ure (Fig. 2). As a result, the beams and bridges that hold

    up railway tracks suffered serious damage. The failure

    mode of these damaged structures became shear failure before yielding of the longitudinal reinforcement of

    column members. Fortunately, as the earthquake oc-

    curred in the early morning, accidents involving trains

    falling from RC viaducts and bridges did not occur.

    Following this earthquake, the Ministry of Land, Infra-

    structure and Transport instructed rail operators to con-

    duct seismic rehabilitation to prevent shear failure of

    columns. Thus seismic rehabilitation of existing RC

    railway structures that were constructed based on the old

    design standard officially started. At first, the target area

    of seismic rehabilitation was limited to overcrowded

    lines in the Sendai, Kanto, Tokai, Kinki, and Sanyo areas

    and around active faults in view of the active fault size

    and the influence of a damaging earthquake on human

    1Head, Structural Engineering Center, East Japan

    Railway Company, Tokyo, Japan2

    Structural Engineering Center, East Japan RailwayCompany, Tokyo, Japan

     E-mail :[email protected] 

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    2/10

    288  T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009

    life and living, and the regional economy (Fig. 3). Then,

    following the occurrence of a series of serious earth-

    quakes that damaged concrete structures after the South

    Hyogo Prefecture earthquake of 1995, seismic rehabili-

    tation of existing structures was conducted nationwide.For example, soon after the South Hyogo Prefecture

    earthquake in 1995 occurred, East Japan Railway Co.

     began conducting seismic rehabilitation of RC railway

    structures on a preferential basis in areas that have

    overcrowded lines in the Sendai and South Kanto areas

    and active faults with a high probability of earthquakes.Then, in 2003, the Sanriku Minami Earthquake oc-

    curred in an area where seismic rehabilitation was not

     planned. Since this earthquake damaged RC viaducts of

    the Tohoku Shinkansen, it was decided to reinforce all

    Shinkansen lines regardless of the area. As the rehabili-

    tation plan was underway, the Niigata Chuetsu Earth-

    quake of 2004 (Fig. 4) and the Niigata Chuetsu-okiEarthquake of 2007 occurred.  The Niigata Chuetsu

    Earthquake caused damage at the cut-off section of the

    river pier. As a result, seismic rehabilitation needed to be

    accelerated. However, the space under many railway

    viaducts is used for stations, shops, and other buildings.Thus seismic rehabilitation poses a number of challenges,

    including the relocation of shops and the removal of

    heavy machinery and other obstacles, which have to be

    overcome in order to allow the reinforcement of a large

    number of columns.

    3. Seismic rehabilitation technique

    3.1 Basic conceptThe basic concept of seismic rehabilitation is to prevent

    shear failure of column members caused by large earth-

    quakes resulting in the collapse of RC viaducts and

     bridges, which are catastrophes that have occurred in

     past earthquakes. To enhance the seismic capacity of the

    whole structural frame, the aim is to increase the ductilitycapacity of column members through seismic rehabilita-

    tion in order to allow better absorption of earthquake

    energy, but enhancing the flexural strength of the column

    members is not properly done. The reason for this is that

    if the flexural strength of the column members damaged

     by an earthquake is enhanced, future earthquake damage

    may occur in beam members and foundation members.

    Since repair and strengthening of beams and foundation

    members is more difficult than for column members, it is

    considered important to  restrict damage after seismic

    rehabilitation to column members.

    3.2 Main seismic rehabilitation methods for RCviaductsIn almost all RC railway viaducts, the space under the

    viaduct is used by stations, shops, and other buildings.

    Therefore seismic rehabilitation must deal with various

    obstructions such as partition walls and equipment. Inthis case, the construction site is a confined space, which

    means restrictions on the use of large construction

    equipment such as cranes. Often, construction schedule

    restrictions also apply, so that a suitable method designed

    taking into account the various conditions at each site

    must be adopted. The main seismic rehabilitation meth-ods are outlined below.

    Fig. 1 Damages to bearings during the Miyagi Prefecture Earthquake in

    1978. Fig. 2 Shear failure at viaduct piers during the

    South Hyogo Prefecture Earthquake in 1995.

    Table 1 Main occurrences of domestic seismic damage (since South Hyogo Prefecture Earthquake in 1995).

    Year 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Comment

      ☆ ☆

     South Hyogo Prefecture Sanriku Minami Noto Hanto

     Earthquake in 1995 (M7.3) Ear thquake in 2003 (M7.1) Earthquake i n 2007 (M6.9)

      ☆   ☆

    Western Tottori Prefecture Niigata Chuetsu Iwate-Miyagi Nairiku

    Earthquake in 2000 (M7.3) Earthquake in 2004 (M6.8) Earthquake in 2008 (M7.2)

    ☆ ☆ ☆

    Geiyo Earthquake North Miyagi Niigataken Chuetsu-Oki

    in 2001 (M6.7) Earthquake in 2003 (M6.2) Eart hquake in 2007 (M6.8)

      ☆   ☆ ☆

    Tokachioki West Fukuoka North Coast Iwate

    Earthquake in 2003 (M8.0)Earthquakein 2005 (M7.0) Earthquake in 2008 (M6.8)

    Main

    occurence

    s of 

    domestic

    seismic

    damage

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    3/10

      T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009   289 

    List of epicenters of various earthquakes

    ①  Miyagi Prefecture Earthquake ②  South Hyogo Prefecture Earthquake ③  Sanriku Minami Earthquake

    ④  Niigata Chuetsu Earthquake ⑤  Niigataken Chuetsu-Oki Earthquake

    Fig. 3. Epicenter of various earthquakes and target areas of seismic rehabilitation. Thicker lines are Shinkansen railways

    and thinner lines are local ones. Small open circles represent main station in the area.

    Fig.4 Damages to piers during the Niigata Chuetsu Earthquake in 2004.

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    4/10

    290  T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009

    (1) Steel plate jacketing method (Ishibashi et al .2004, Fig. 5)This method is the most common seismic rehabilitation

    technique used for railway RC viaduct columns. Jack-

    eting with steel plate 6 to 14mm thick enhances the shearstrength and ductility capacity of RC viaduct columns.

    After jacketing, the gap between the steel plate and ex-

    isting column is grouted with non-shrink mortar, etc..

    Although the joint method with site welding is common

    for steel plate joints, indented joints are used to ensure

    construction quality.

    A method using assembled steel plate panels has also

     been developed (Fig. 6). This method consists in as-

    sembling precast panels with projections by using per-

    forated connect plates around an existing column. Then,

    after securing these members by rivets, the gap between

    the steel plates and the existing column is grouted with

    non-shrink mortar. Besides enabling manual assembly,this method also has the merits of low noise and vibration

    levels, which makes it suitable for work under viaducts

    where there are shops or other buildings. In addition, as

    this method employs factory-made products, consistent

    quality is ensured and design aspects can be concen-

    trated.

    (2) Other jacketing methods (American Con-crete Institute 2008, Fig. 7)In the case of rehabilitation work in a confined con-

    struction site such as a space under a viaduct that has

    shops or other buildings and is near other buildings, use

    of the steel plate jacketing method, which requires theuse of large construction equipment such as cranes, is

    difficult. Therefore, various other jacketing methods

    including ones that apply fiber-reinforced plastics (car-

     bon fiber, aramid fiber, etc.) sheets, other ones that spray

    glass fiber and epoxy resin directly to the member faces

    with a spray gun or combine sprayed mortar with rein-

    forcing bars, and still other methods that use precast

    concrete panels, have been developed.

    (3) Rib-bar and rib-plate method (Ishibashi et al .2004.)The rib-bar method was developed to enhance shear

    strength and ductility capacity by reinforcing bars an-chored with supporting members arranged at each corner

    of RC viaduct columns (Fig. 8, Fig. 9). This method

    eliminates the need to remove partition walls and enables

    manual assembly in confined construction sites such as

    areas under viaducts that have shops or other buildings

    and facilities.

    Another method, the rib-plate method, which rein-

    forces RC viaduct columns with steel plate bands with

    indented joints, was also developed for the same purpose

    as the rib-bar method (Fig. 10, Fig. 11). The indented

     joints make this method easy to use, and as the bands are

    easy to fabricate, this method can be easily applied to

    columns with various cross-section shapes.

    (4) Thin plates attachment method (Associationof Railway Advanced Construction Technology

    2008, Fig. 12)This method was developed to enhance the shear strength

    and ductility capacity of RC viaduct columns by attach-

    Fig. 5 Steel plate jacketing.

    Fig. 7 Method using FRP sheets. 

    Fig. 6 Assembled steel plate panels.

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    5/10

      T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009   291 

    ing thin plates about 0.8 mm thick by adhesion bond. The

     purpose of this method is the same as that of the rib-bar

    and rib-plate methods. This method has the advantage

    that following column reinforcement, the increase in

    member section thickness is only 20 to 30 mm, comparedto 40 to 50 mm for the jacketing steel plate method. This

    minimizes space reduction for shops and other buildings

    under viaducts.

    (5) Method using concrete segment and steelstrand wire (Okamoto et al . 2006)This method, which consists in attaching four

    washboard-shaped precast concrete segments to the

    member faces and banding them with galvanized spiral

    strand wire was developed for the same purpose as the

     previously described methods (Fig. 13). Advantages of

    this method include the use of factory-made reinforcing

     products enabling stability and easy control in quality,and visual inspections of existing column corners leading

    to rapid and easy emergency checkup at daily or

     post-earthquake operations.

    (6) Single-face method (Ishibashi et al . 2004, Fig.

    14, Fig. 15)

    This method, which uses a steel plate and reinforcing bars, is applied to only one face of the RC column for the

    same purpose as the previously described methods. This

    method is suitable when only one face of RC viaduct

    columns is exposed due to adjacent shops, storage sheds,

    etc., under a RC viaduct. This method eliminates the

    need to remove shops and suspend business during re-

    habilitation work.

    (7) Method using steel damper and braces(Shimada et al . 2005, Fig. 16)This method uses steel dampers and braces to reinforce

    mainly building frames. The role of the steel braces is to

    control deformation of the RC viaduct columns, whilethe role of the damper placed at the center is to absorb

    energy. In cases when it is impossible to apply a jacketing

    Fig. 8 Conceptual diagram of rib-bar method.  Fig. 9 End of rib-bar retrofit. 

    Fig.10 Conceptual figure of rib-plate method.  Fig. 11 End of rib-plate retrofit. 

    Supporting member 

    Reinforcing bar

    Steel plate band

    Indented joint

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    6/10

    292  T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009

    method owing to the presence of walls, etc., a pair of

    steel dampers and their respective braces can be placed

    inside the RC viaduct in the track direction and the di-

    rection perpendicular to the track, respectively, for

    seismic rehabilitation.

    3.3 Main seismic rehabilitation methods for RCpiersRC piers can also be reinforced using a number of

    methods for seismic rehabilitation. RC piers have a

    cut-off in their main longitudinal reinforcements. This

    cut-off area is a weak point of RC pier when an earth-

    quake occurs. The cross section of RC piers is larger than

    that of RC viaduct columns. Wall type piers and  piers

    with an elliptic cross section have different cross sections

    in the track direction and the direction perpendicular to

    the track, making it impossible to adopt the same seismic

    rehabilitation methods as for RC viaducts.Therefore, concrete or steel jacketing is used to in-

    crease the flexural and shear strength of the cut-off area

    to protect this area from damage. So the seismic reha-

     bilitation concept is based on enhancing the shear

    strength and ductility capacity of piers to avoid shear

    failure and absorb the energy generated by earthquakes

    through ductility capacity. Further, the concept that pre-

    vents the flexural strength of RC piers from increasing

    and suppresses the influence on other structural members

    is the same as for RC viaducts.

     

    The main seismic reha- bilitation methods are outlined below.

    (1) Reinforced concrete jacketing method (Fig.17)Reinforced concrete jacketing for RC piers increases

    shear and flexural strength around the cut-off area and

    enhances the shear strength of RC pier as the whole and

    the ductility capacity of the pier base. This method can be

    used to reinforce the area around the cut-off, the base of

    the pier, and other areas in need of seismic rehabilitation

    depending on the seismic capacity of the existing RC pier.

    As a result, it is possible to end seismic rehabilitation

    after reinforcing only the area around the cut-off. The jacketing thickness is on the order of 200 mm. Further-

    more, for the seismic rehabilitation of RC piers situated

    in valleys in mountain areas and near houses or along a

    road, a construction method using elevating scaffolds for

    workability and safety has been developed. (Association

    補強薄板Thin plates

    Fig. 12 Conceptual diagram of thin plates attachment

    method.

    Steel plate

    Reinforcing bar

    Wall

    Existing column

     

    Fig. 14 Conceptual figure of single-face method.

    Fig. 13 Using Concrete segment and Steel strand wire

    method.

    Fig. 15 End of retrofit.

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    7/10

      T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009   293 

    of Railway Advanced Construction Technology. 2008,

    Fig 18, 19)

    (2) Steel plate jacketing method (AmericanConcrete Institute 2008; Tamai et al . 1999.)Steel plate jacketing for RC piers increases the shear and

    flexural strength around the area of the cut-off and en-

    hances the shear strength of RC pier as the whole as well

    as the ductility capacity of the pier base. The thickness

    including the steel plate is 40 to 50 mm. Since the in-

    crease of the cross section after seismic rehabilitation by

    steel plate jacketing is smaller than RC jacketing, this

    method can be applied to constrained site conditions.And similarly to RC jacketing, it is possible to end

    seismic rehabilitation after reinforcing only the area

    around the cut-off, and depending on the type of pier, the

     base of RC pier can be confined for enhancing ductility

    after seismic rehabilitation.

    (3) FRP sheet jacketing method (AmericanConcrete Institute 2008)A fiber reinforced plastics (carbon fiber, aramid fiber,

    etc.) sheets jacketing method has been developed and is

    used for RC piers. A method that uses fiber reinforcedsheets pre-impregnated with ultraviolet curable resin for

     jacketing has also been developed. As FRP sheets arelightweight, they are easily carried to the construction

    site. As the resin becomes hard with ultraviolet, the

    sheets do not have to be impregnated with a curative

    agent, contributing to shorter construction time.

    (4) Method using concrete filled tube (Associa-tion of Railway Advanced Construction Tech-nology 2008, Fig. 20, 21)After removing any sediment inside steel tubes inserted

    into the ground, concrete is cast into the tubes. The con-crete filled tubes then serve as strut members supporting

    an cantilever concrete block attached to the RC pier. As a

    result, this structure mainly enhances the ductility ca- pacity of the pier base.

    Compared to the jacketing method with reinforced

    Fig. 16 Method using steel damper and braces. Fig. 17 Method using RC jacketing.

    Fig. 18 Example of RC pier in valley.

    Fig. 19 Elevating scaffold.

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    8/10

    294  T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009

    concrete and steel plate after sediment excavation, this

    method reduces construction cost since large sediment

    excavation and temporary works are not needed for this

    method.

    (5) Method using steel sheet pile (Associationof Railway Advanced Construction Technology2008, Fig. 22)After removing any sediment inside a steel sheet pile

    inserted into the ground around an RC pier, mortar

    casting is conducted into the space between the RC pier

    and the steel sheet pile to enhance the shear strength and

    ductility capacity of the RC pier. Since steel sheet plates

    are used as reinforced members for RC piers, temporary

    works need not be constructed in rivers, which signifi-

    cantly cuts down construction cost.

    4. Considerations for the design of newstructures

     Next, we refer to matters that should be considered for

    new structures based on consideration of seismic damage

    and restoration. Figure 23  shows an example of the

    elasticity acceleration response spectrum applied to the

    current seismic design standard. The basis of the design

    is that the response displacement calculated by elasto- plasticity response analysis is below the ductility capac-

    ity of the structure. However, as the evolution of the

    seismic design standard shows, the demanded seismic

    capacity has grown with each new occurrence of earth-quake damage. Given this fact, there is a good possibility

    that the seismic design standard will again change in the

    future. Therefore, if construction costs remain un-

    changed, enhancing the seismic capacity as much as

     possible is desirable. Enhancing the strength of a struc-

    ture requires reinforcement of all the members including

    the foundation. However, the cost of construction would

    increases excessively as a result. On the other hand,

    enhancing the ductility capacity of the structure can be

    done by reinforcing only the plastic hinge part, for a

    minimal increase in construction cost. Therefore, the

    reinforcement arrangement for enhancing the ductility

    capacity should be designed in the plastic hinge zone.To this end, regardless of the level of ductility capac-

    ity required for the design, spiral reinforcement is ar-

    ranged inside the longitudinal reinforcements in the 1D

    area of the column of a new RC viaduct (D is the height

    of the cross section of the column) (Fig. 24, 25). Figures

    26  and 27  show the situation of the cyclic loading ex-

     periment and the relationship between the load and dis-

    CFT (strut member)

    Existing pier 

    Concrete block 

    CFT (strut member)

    Existing pier 

    Concrete block 

    Fig. 21 Conceptual diagram of concrete. filled tube

    method.

       R  e  s  p  o  n  s  e  a  c  c  e   l  e  r  a   t   i  o  n  s  p  e  c   t  r  u  m   (  g  a   l   )

    Period (s)

       R  e  s  p  o  n  s  e  a  c  c  e   l  e  r  a   t   i  o  n  s  p  e  c   t  r  u  m   (  g  a   l   )

    Period (s)

    Fig. 23 Example of elasticity acceleration responsespectrum (Gn shows ground classification (ground dif-

    ference)). 

    Fig. 20 Method using concrete filled tube.

    Water level

    Ground level

    Existing pier 

    RC or steel plate

     jacketing

    Steel sheet pile

    Water level

    Ground level

    Existing pier 

    RC or steel plate

     jacketing

    Steel sheet pile 

    Fig. 22 Conceptual diagram of steel sheet pile method.

     

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    9/10

      T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009   295 

     placement of a column with spiral reinforcement inside

    the longitudinal reinforcements. The placement of insidespiral reinforcement enhances the ductility capacity

    greatly compared to when sufficient hoop reinforcements

    are provided (Kanno et al. 2009). The fact that the in-

    ternal concrete in the plastic hinge zone breaks up out-

    ward through being freed from binding force by buckling

    of the longitudinal reinforcements and associate break oftie hoops causes rapid impairment of the flexural capac-

    ity of the column and settling down of the column (Sato

    and Ko 2008). Thus providing spiral reinforcement in-

    side the longitudinal reinforcements shackles the internal

    concrete inside the longitudinal reinforcements, pre-

    venting the collapse of the internal concrete and en-

    hancing the ductility capacity greatly.

    Since it involves the construction of new structures, it

    is important for seismic design to enhance the seismic

    capacity as much as possible. It does not suffice for the

    response displacement calculated by response analysis to

     be lower than the acceptable value; since the plasticity

    rotation capacity in the plastic hinge zone can be greatly

     boosted without an increase in cost, this bears consid-

    eration during actual design. Although restoration is

    extremely onerous after a structure collapses, the amount

    of displacement has little influence on the difficulty of

    restoration as long as the structure has not collapsed.

    Thus it is important to enhance the ductility capacity of

    columns as much as possible in order to prevent the

    collapse of a structure. Such consideration prevents se-

    rious damage and enables early restoration in addition to

    significantly boosting safety, even in the event of an

    earthquake that is larger than predicted.

    5. Conclusion

    Seismic design and rehabilitation techniques evolve

    along with earthquake occurrences. In other words, the

    experience of a number of earthquakes drives the de-velopment of various new technologies and techniques

    inside spiral reinforcement

    1D区間1D区間1D section

    inside spiral reinforcement

    1D区間1D区間1D section

    Fig 25 Example of RC viaduct fitted with inside spiral

    reinforcement.

    Fig. 26 Situation of cyclic loading experiment (after load-

    ing up to 20δy).

    The colum with hoop reinforcement outside the axial reinforcements

    The colum with spiral reinforcement inside the axial reinforcements

    -2

    -1.5

    -1

    -0.5

    0

    0.5

    1

    1.5

    2

    -30 -20 -10 10 20 30

     plasticity rate δ/δyeild

       S   t  r  e  n  g   t   h  r  a   t   i  o   P   /   P  y

      e   i   l   d

    The colum with hoop reinforcement outside the axial reinforcements

    The colum with spiral reinforcement inside the axial reinforcements

    -2

    -1.5

    -1

    -0.5

    0

    0.5

    1

    1.5

    2

    -30 -20 -10 10 20 30

     plasticity rate δ/δyeild

       S   t  r  e  n  g   t   h  r  a   t   i  o   P   /   P  y

      e   i   l   d

     

    Fig. 27 Example of relationship between strength ratio

    and plasticity rate during cyclic loading.

    Fig. 24 Example of arrangement of spiral reinforcement

    inside longitudinal reinforcements.

    Column with hoop reinforcements outside of the longitudinal reinforcements

    Column with a spiral reinforcement inside of the longitudinal reinforcements

  • 8/18/2019 Seismic Damage of and Seismic Rehabilitiion Techniques for Railway Reinforced Concrete Structures

    10/10

    296  T. Ishibashi and D. Tsukishima / Journal of Advanced Concrete Technology Vol. 7, No. 3, 287-296, 2009

    for seismic design and seismic retrofitting and the sys-

    tematic seismic rehabilitation of existing structures. The

    authors hope that the various technologies and tech-

    niques introduced here will prove helpful for everyone. 

    ReferencesAssociation of Railway Advanced Construction

    Technology. (2008). “ List of construction methods

    approved for public relations.”

    http://www.rail-act.org/ (in Japanese)

    American Concrete Institute (2007). “Seismic

    rehabilitation of concrete structures.” IPS-2, 554P.

    Hujihashi, H. and Inakuma, H. (2001). “The seismic

    rehabilitation of reinforced concrete piers.” Journal of

     Japan Railway Civil Engineering Association, 39(11),

    907-909. (in Japanese)

    Ishibashi, T., Tsuyoshi, T. and Kobayashi, K. (2004).

    “Seismic retrofitting methods newly developed forrailway concrete structures.”  Journal of Advanced

    Concrete Technology, 2(1), 65-76.

    Japan Society of Civil Engineers (2006). “Special

    committee report of countermeasures to massive

    earthquake hazards.”

    http://www.jsce.or.jp/committee/kyodai-jishin/index.s

    html (in Japanese)Kanno, T., Ishibashi, T., Kino, J. and Kobayashi, K.

    (2009). “Deformation capacity under earthquake on

    reinforced concrete column reinforced by inside spiral

    reinforcement.” Concrete Research and Technology,20(2), 1-12. (in Japanese)

    Okamoto, M., Naganawa, T., Komatsu, A. and Aikyo, H.(2006). “A development on seismic retrofitting system

    for RC column using divided steel plates.” Concrete

     Journal , 48(8), 30-38. (in Japanese).

    Sato, Y. and Ko, H. (2008). “Modeling of reinforcement

     buckling in RC columns confined with FRP.” Journal

    of Advanced Concrete Technology, 6(1), 195-204.Shimada, Y., Umeda, H. and Yoshida, K. (2005).

    “Construction through the seismic rehabilitation of RC

    rigid-frame viaduct using steel damper and braces

    method.” Journal of Japan Railway Civil Engineering

     Association, 43(7), 509-511.(in Japanese)Tamai, S., Sato, T., Miyagi, T. and Okamoto, M. (1999).

    “Experimental studies on steel jacketing of wall type

     pier with terminated reinforcement.”  Proceedings of

    the Japan Concrete Institute, 21(3), 1315-1320. (in

    Japanese)