PERHITUNGAN RENCANA ANGGARAN PELAKSANAAN
PEKERJAAN STRUKTUR PADA TOWER ANDALUSIA
PROYEK PEMBANGUNAN APARTEMEN URBANTOWN
KARAWANG
REAL OF COST ESTIMATION FOR STRUCTURAL WORKS IN
ANDALUSIA TOWER THE PROJECT OF APARTEMENT
URBANTOWN KARAWANG
Laporan ini disusun untuk memenuhi salah satu syarat menyelesaikan pendidikan
Diploma III Program Studi Teknik Konstruksi Gedung
Di Jurusan Teknik Sipil
Oleh:
M VERREL BRAMASTA RIA RISMA SAGALA
171111022 171111026
POLITEKNIK NEGERI BANDUNG
2020
PERHITUNGAN RENCANA ANGGARAN PELAKSANAAN
PEKERJAAN STRUKTUR PADA TOWER ANDALUSIA
PROYEK PEMBANGUNAN APARTEMEN URBANTOWN
KARAWANG
REAL OF COST ESTIMATION FOR STRUCTURAL WORKS IN
ANDALUSIA TOWER THE PROJECT OF APARTEMENT
URBANTOWN KARAWANG
M Verrel Bramasta Ria Risma Sagala
NIM: 171111015 NIM: 171111026
Pembimbing
Yulianto Petrus Krisologus, Drs, MM
NIP. 196007301986031002
Tim Penguji
Ketua : Ahmad Solih, ST, MT.
NIP. 195911011985031003
Anggota 1 : Tatang Sumarna, ST, MSi..
NIP. 195907011990121001
Anggota 2 : Yulianto Petrus Krisologus, Drs, MM.
NIP. 196007301986031002
: ………………...
: …………………
: …………………
ABSTRAK
ix
Proses pelaksanaan proyek dapat berjalan dengan baik, apabila manajemen
perencanaan dikelola dengan baik sejak awal. Manajemen perencanaan yang
dimaksud adalah rencana anggaran pelaksanaan dan penjadwalan proyek. Rencana
anggaran pelaksanaan merupakan biaya proyek pembangunan yang dibuat untuk
memperkirakan besar biaya sesungguhnya yang dibutuhkan untuk menyelesaikan
suatu kontrak kerja proyek konstuksi. Penjadwalan merupakan kegiatan yang
mengatur durasi, jumlah tenaga kerja, dan progres setiap item pekerjaan yang tidak
boleh terlambat dalam proyek pembangunan ini.
Dalam menghitung rencana anggaran pelaksanaan (RAP), terdapat
beberapa hal yang perlu dilakukan, yaitu membuat work breakdown structure
(WBS), pehitungan produktivitas tower crane, perhitungan volume pekerjaan, dan
perhitungan analisa harga satuan (AHS). Data yang diperlukan untuk membantu
perhitungan berupa gambar kerja, metode pelaksanaan, RKS, dan harga satuan
bahan dan upah. Setelah perhitungan rencana anggaran pelaksanaan, dilaksanakan
penjadwalan ulang menggunakan perangkat lunak Microsoft Project 2016 dengan
metode bar chart. Durasi yang di dapatkan berdasarkan work breakdown structure
(WBS), perhitungan produktivitas tower crane dan penentukan jumlah pekerja.
Berdasarkan hasil perhitungan rencana angaran pelaksanaan dari Tower
Andalusia ini diperoleh biaya yang sebesar Rp. 7.253.882.657,42 pada pekerjaan
struktur atas dan bawah. Waktu pelaksanaannya selama 77 hari kerja, dimulai dari
tanggal 18 Juli 2020 sampai dengan 4 Oktober 2020.
Kata kunci: rancangan anggaran biaya, produktivitas tower crane, penjadwalan,
Microsoft Project 2016.
ABSTRACT
x
The project implementation process can go well, if the planning
management is managed well from the beginning. The planning management in
question is the project implementation and scheduling budget plan. The
implementation budget plan is the cost of a construction project created to estimate
the true cost required to complete a contract of construction work. Scheduling is an
activity that governs the duration, number of labor, and progress of each work item
that should not be late in this development project.
In calculating the implementation budget plan, there are several things that
need to be done, namely making work breakdown structure (WBS), calculating
tower crane productivity, calculation of job volume, and calculation of unit price
analysis. The data needed to help with the calculation of work images,
implementation methods, RKS, and unit prices of materials and wages. After the
calculation of the implementation budget plan, it is implemented rescheduling using
Microsoft software. Project 2016 with the bar chart method. The duration is based
on work breakdown structure (WBS), calculation of tower crane productivity and
determining the number of workers.
Based on the calculation of the implementation plan of the Andalusian
Tower, the cost was rp. 7,253,882,657.42 on the work of the upper and lower
structures. The implementation time is 77 business days, starting from July 18, 2020
to October 4, 2020.
Keywords: draft budget, tower crane productivity, scheduling, Microsoft Project
2016.
v
LEMBAR PERSEMBAHAN
Alhamdulillah, pertama-tama dan yang paling utama saya panjatkan puji serta
syukur saya kepada Allah SWT yang senantiasa memberikan saya umur dan nikmat
sehat hingga saat saya menyelesaikan Tugas Akhir ini.
Tulisan ini saya tujukan yang pertama-tama kepada kedua orang tua saya yang
tak pernah henti mendoakan, memotivasi,dan mendukung secara moril dan materiil.
Semoga Allah selalu menjaga dan memberikan ridho-Nya selama masih diberikan
umur dan semoga saya bisa membanggakan serta bisa sedikit membalas banyak sekali
kebaikan-kebaikan yang telah diberikan semenjak saya lahir.
Terima kasih yang sebesar-besarnya saya ucapkan kepada dosen pembimbing
kami bapak Yulianto Petrus Krisologus, Drs, MM. yang telah membimbing dan
memberikan ilmunya kepada kami, semoga apa yang telah bapak berikan kepada
kami hingga Tugas Akhir ini selesai dapat berguna bagi kami dan dapat menjadi amal
baik dikemudian hari.
Kepada Ria Risma Sagala saya ucapkan terima kasih banyak telah menjadi
partner saya selama mengerjakan Tugas Akhir ini dan telah salin mem-backup satu
sama lain meskipun banyak cobaan selama mengerjakan Tugas Akhir ini.
Kepada rekan-rekan MARKASCUY terima kasih sudah saling berbagi
semangat, suka duka, canda tawa, serta tempat bernaung hingga selesai masa
perkuliahan ini. Ingat MARKASCUY bukan hanya perihal siapa orang-orangnya dan
di mana tempatnya, lebih dari itu melibatkan seluruh memori dan kenangan ramai
bersama ataupun sepi sendiri. Dimasa depan tetaplah menjadi orang-orang yang
sama ya!
Terima kasih kepada kakak-kakak Sipil 2015 dan Sipil 2016, yang telah
berbagi segala ilmu untuk adikmu yang satu ini dari zaman mahasiswa baru hingga
kalian lulus satu persatu. Tak lupa juga untuk adik-adik Sipil 2018 dan Sipil 2019,
vi
tetap semangat kuliahnya ya walau ditengah pandemi seperti ini, maaf kalau
pertemuan kita terlalu singkat, sampai berjumpa di tempat lain dikemudian hari.
Terakhir, Terima Kasih kepada teman-teman Sipil 2017, khususnya KGA
17, Terima Kasih karena kita telah dipertemukan, Terima Kasih karena kita menjadi
rekan seangkatan, Terima Kasih karena telah berbagi canda tawa selama ini, dan
Terima Kasih akan setiap momen yang telah kita abadikan bersama-sama. Semoga
kalian baik-baik saja, sampai berjumpa lagi di tempat yang berbeda, diwaktu yang
berbeda, dan dalam rasa kekeluargaan yang sama. SIPIL 2017, Terima Kasih karena
kalian HEBAT.
Salam Hangat
M. Verrel Bramasta
vii
LEMBAR PERSEMBAHAN
Segala puji serta syukur saya panjatkan kehadirat Tuhan Yesus Kristus karena
atas berkat karunia-NYA puji Tuhan saya dapat menyelesaikan tugas akhir ini.
Saya persembahkan tugas akhir ini untuk orang-orang tercinta dan teramat
berjasa dalam membantu dan mendukung menyusun tugas akhir ini.
1. Teristimewa untuk kedua orangtua saya, orang yang paling saya sayangi di dunia
ini, mama dan bapak. Terima kasih, atas segala jasa yang mama dan bapak
berikan kepada saya, perhatian, kasih sayang, rasa khawatir, keringat, air mata,
dan juga bantuan doa-doa dan motivasi yang selalu kalian berikan kepada saya
untuk selalu kuat dan mengandalkan Tuhan dalam hidup. Tak lupa juga saya
meminta maaf yang sebesar-besarnya atas segala tingkah laku saya yang membuat
hati dan perasaan mama dan bapak terluka.
2. Untuk kaka dan abang, mimi, jere, bang rudi, yang telah memberikan dorongan
dan motivasi sehingga saya menjadi semakin semangat untuk menyelesaikan
tugas akhir ini. Terutama adikku tersayang jeremia terima kasih selalu menemani
kaka begadang, bertemu dosen, dan mengantar kaka untuk keperluan tugas
akhir ini
3. Untuk teman-teman seperjuangan, GA’17. Yang dapat saling dukung dan
menjaga satu sama lain selama 3 tahun masa belajar. Semoga semua selalu dalam
lindungan Tuhan. Terutama Salwa dan Ayu terima kasih sudah menjadi teman
diskusi selama pengerjaan tugas akhir ini.
4. Untuk teman-teman UBSU 2017, Yang dapat saling dukung dan menjaga satu
sama lain selama 3 tahun. Senang sekali bisa berjumpa, bermain, ketawa, dan
jadi bagian dari UBSU 2017, di mana saya bertemu teman-teman baik, Tuhan
Yesus memberkati.
viii
5. Untuk teman-teman Sipil 2017, yang membantu dan menolong saya dalam
menempuh perkuliahan. Senang sekali bisa berjumpa kalian.
6. Tak lupa untuk dosen pembimbing, Yulianto Petrus Krisologus, Drs, MM. Yang
telah berhasil mengarahkan, membimbing, serta menasihati sehingga pengerjaan
Tugas Akhir ini dapat diselesaikan. Semoga kebaikan bapak sekalian dibalas
oleh Tuhan, amin.
Bandung, Oktober 2020
Ria Risma Sagala
xi
KATA PENGANTAR
Puji syukur penulis panjatkan ke hadirat Tuhan Yang Maha Esa, karena atas
berkat dan anugerah-Nya, penulis dapat menyelesaikan penyusunan Laporan Tugas
Akhir ini dengan judul “Perhitungan Rencana Anggaran Pelaksanaan
Pekerjaan Struktur Pada Tower Andalusia Proyek Pembangunan Apartemen
Urbantown Karawang”.
Laporan ini disusun untuk memenuhi salah satu syarat menyelesaikan
pendidikan Diploma III Program Studi Teknik Konstruksi Gedung Jurusan Teknik
Sipil Politeknik Negeri Bandung.
Penyusunan laporan ini dapat diselesaikan tidak lepas dari bimbingan,
arahan, dan dukungan dari berbagai pihak. Oleh karena itu, dalam kesempatan kali
ini, penulis mengucapkan terima kasih kepada semua pihak yang terkait dalam
penulisan Laporan Tugas Akhir ini, yaitu kepada:
1. Bapak Hendry, Dipl.Ing.HTL.,MT selaku Ketua Jurusan Teknik Sipil
Politeknik Negeri Bandung.
2. Ibu Fisca Igustiany, SST.,MT selaku Ketua Program Studi D3 Teknik
Konstruksi.
3. Bapak Togar Sirait, Ir, SP1 selaku Wali Dosen Teknik Konstruksi Gedung A
2017.
4. Bapak Yulianto Petrus Krisologus, Drs, MM selaku dosen pembimbing yang
telah memberikan arahan dan masukan pada saat pelaksanaan dan penulisan
laporan Tugas Akhir.
5. Seluruh staf kontraktor PT PP Urbantown Karawang terutama Bapak Warsita
yang telah memberikan data dan bimbingannya pada saat di lapangan.
6. Rekan-rekan Teknik Konstrusi Gedung A atas dorongan semangat dan
solidaritasnya.
7. Orang tua yang selalu mendoakan dan memberikan dorongan demi kelancaran
penyusunan Tugas Akhir.
xii
Akhir kata, penulis berharapan semoga laporan ini dapat bermanfaat bagi
para pembaca. Dalam penyusunan laporan ini penulis menyadari terdapat banyak
kekurangan. Oleh karena itu, Penulis mengharapkan kritik dan saran pembaca demi
perbaikan di masa yang akan datang. Atas segala perhatiannya, penulis
mengucapkan terima kasih.
Bandung, Oktober 2020
Penulis
xiii
DAFTAR ISI
HALAMAN JUDUL ............................................................................................ i
LEMBAR IDENTITAS ...................................................................................... ii
LEMBAR PENGESAHAN ............................................................................... iii
PERNYATAAN PENULIS ............................................................................... iv
LEMBAR PERSEMBAHAN ............................................................................. v
ABSTRAK .......................................................................................................... ix
ABSTRACT .......................................................................................................... x
KATA PENGANTAR ....................................................................................... xi
DAFTAR ISI .................................................................................................... xiii
DAFTAR GAMBAR ....................................................................................... xvi
DAFTAR TABEL ........................................................................................... xvii
DAFTAR LAMPIRAN .................................................................................. xviii
DAFTAR ISTILAH ......................................................................................... xix
BAB I PENDAHULUAN ................................................................................... 1
1.1 Latar Belakang Masalah ................................................................................ 1
1.2 Tujuan ............................................................................................................ 4
1.3 Ruang Lingkup .............................................................................................. 4
1.4 Lokasi Proyek ................................................................................................ 5
1.5 Metode Penyelesaian Masalah ....................................................................... 5
1.6 Manfaat Penyusunan Tugas Akhir................................................................. 6
1.7 Sistematika Penulisan .................................................................................... 7
BAB II TINJAUAN PUSTAKA ....................................................................... 8
2.1 Rusunawa dan Apartemen ............................................................................. 8
2.2 Manajemen .................................................................................................... 8
2.2.1 Manajemen Proyek ................................................................................... 9
2.2.2 Tujuan Manajemen ................................................................................... 9
2.3 Metode Pelaksanaan Rusunawa atau Apartemen ........................................ 10
xiv
2.4 Rencana Anggaran Pelaksanaan (RAP)....................................................... 10
2.4.1 Identifikasi Aktivitas (Work Breakdow Structure) ................................. 11
2.4.2 Perhitungan Volume ............................................................................... 14
2.4.3 Analisa Harga Satuan Pekerjaan (AHSP) ............................................... 14
2.4.4 Rencana Anggaran Pelaksanaan (RAP) .................................................. 16
2.5 Produktivitas ................................................................................................ 17
2.6 Penjadwalan Proyek .................................................................................... 18
2.6.1 Perhitungan Kurun Waktu (Durasi) ........................................................ 20
2.6.2 Diagram Batang (Bar Chart) .................................................................. 20
2.6.3 Kurva S atau Hanumm Curve ................................................................. 21
2.6.4 Microsoft Project 2016 ........................................................................... 22
BAB III METODOLOGI ................................................................................ 24
3.1 Skema Tahapan Penyusunan Tugas Akhir .................................................. 24
3.2 Pengumpulan Data ....................................................................................... 26
3.2.1 Data Primer ............................................................................................. 26
3.2.2 Data Sekunder ......................................................................................... 26
3.3 Perhitungan Rencana Anggaran Pelaksanaan (RAP) .................................. 27
3.3.1 Identifikasi Aktivitas (Work Breakdow Structure) ................................. 28
3.3.2 Perhitungan Volume Pekerjaan............................................................... 29
3.3.3 Perhitugan Produktivitas ......................................................................... 29
3.3.4 Perhitungan Analisa Harga Satuan Pekerjaan......................................... 29
3.4 Penjadwalan Pekerjaan ................................................................................ 29
3.4.1 Durasi Kegiatan ...................................................................................... 30
3.4.2 Penyusunan Jadwal dengan Microsoft Project 2016 .............................. 31
BAB IV ANALISA DAN PERHITUNGAN ................................................... 32
4.1 Data Umum Proyek ..................................................................................... 32
4.2 Tahapan Metode Pelaksanaan...................................................................... 32
4.3 Work Breakdown Schedule (WBS) .............................................................. 34
4.4 Perhitungan Volume Pekerjaan ................................................................... 51
4.3.1 Pile Cap .................................................................................................. 51
xv
4.3.2 Tie Beam ................................................................................................. 58
4.3.3 Pit Lift ..................................................................................................... 64
4.3.4 Kolom ..................................................................................................... 68
4.3.5 Balok ....................................................................................................... 74
4.3.6 Pelat Struktur .......................................................................................... 80
4.3.7 Shearwall ................................................................................................ 83
4.3.8 Tangga Struktur ...................................................................................... 89
4.5 Produktivitas ................................................................................................ 95
4.5.1 Produktivitas Alat Berat .......................................................................... 95
4.6 Rencana Anggaran Pelaksanaan ................................................................ 108
4.6.1 Bills of Quantity .................................................................................... 109
4.6.2 Daftar Harga Satuan Bahan, Upah dan Alat ......................................... 126
4.6.3 Analisa Harga Satuan Pekerjaan (AHSP) ............................................. 127
4.6.4 Rencana Anggaran Pekerjaan (RAP) .................................................... 130
4.7 Penjadwalan Pekerjaan .............................................................................. 131
4.7.1 Perhitungan Durasi Pekerjaan ............................................................... 131
4.7.2 Pembuatan Penjadwalan mengunakan Ms. Project .............................. 133
BAB V PENUTUP .......................................................................................... 140
5.1 Kesimpulan ................................................................................................ 140
5.2 Saran .......................................................................................................... 141
DAFTAR PUSTAKA...................................................................................... 142
LAMPIRAN
xvi
DAFTAR GAMBAR
Gambar 1.1 Lokasi Urbantown Karawang .......................................................... 2
Gambar 1.2 Tower Andalusia Proyek Apartemen Urbantown............................ 2
Gambar 1.3 Lay out Apartemen Urbantown Karawang ...................................... 3
Gambar 1.4 Lokasi Proyek Apartemen Urbantown Karawang ........................... 5
Gambar 2.1 Contoh Work Breakdown Structure ............................................... 13
Gambar 2. 2 Skema Harga Satuan Pekerjaan .................................................... 15
Gambar 3.1 Skema Tahapan Penyusunan Tugas Akhir .................................... 25
Gambar 3.2 Diagram Alir Perhitungan RAP ..................................................... 28
Gambar 3.3 Diagram Alir Penjadwalan ............................................................ 30
Gambar 4.1 Work Breakdown Schedule Perhitungan Tower Andalusia ........... 34
Gambar 4.2 Denah Pile Cap Tower Andalusia ................................................. 52
Gambar 4.3 Denah detail Pile Cap tipe PC-3 .................................................... 52
Gambar 4.4 Potongan Pile Cap tipe PC-3 ......................................................... 53
Gambar 4.5 Denah Tie Beam tipe TB-1 ............................................................ 58
Gambar 4.6 Detail Tulangan Tie Beam tipe TB-1 ............................................. 59
Gambar 4.7 Denah dan Detail Tulangan Pit Lift Potongan 6 ............................ 64
Gambar 4.8 Denah dan Detail Tulangan Pit Lift Potongan 5 ............................ 64
Gambar 4.9 Denah Struktur Lantai GF as 3-G .................................................. 68
Gambar 4.10 Detail Tulangan Kolom tipe K-1 ................................................. 69
Gambar 4.11 Denah Struktur Balok lantai 1 ....................................................... 74
Gambar 4.12 Potongan Balok Tipe B-1 .............................................................. 75
Gambar 4.13 Denah Posisi Pelat Lantai 1 ........................................................... 80
Gambar 4.14 Floor Schedule ............................................................................... 80
Gambar 4.15 Denah Posisi Shearwall Ground Floor ......................................... 83
Gambar 4.16 Detail Shearwall Ground Floor tipe SW-1 ................................... 84
Gambar 4.17 Denah tangga struktur lantai dasar – lantai 1................................. 90
Gambar 4.18 Potongan tangga struktur lantai dasar – lantai 1 ............................ 90
Gambar 4.19 Denah Tower Crane, dan Penempatan titik supply dan Demand .. 96
xvii
DAFTAR TABEL
Tabel 4.1 Daftar Pekerjaan Struktur Bawah dan Struktur Atas.......................... 34
Tabel 4.2 Kebutuhan Tulangan Pile Cap tipe PC-3 ........................................... 57
Tabel 4.3 Kebutuhan Tulangan Tie Beam tipe TB-1 .......................................... 63
Tabel 4.4 Kebutuhan Tulangan Pit Lift .............................................................. 67
Tabel 4.5 Kebutuhan Tulangan Kolom Lantai GF tipe K-1 ............................... 73
Tabel 4.6 Kebutuhan Tulangan Balok as 4 ; A-M tipe B-1................................ 79
Tabel 4.7 Kebutuhan Tulangan Pelat Struktur as 1-2 ; A-B’ ............................. 82
Tabel 4.8 Kebutuhan Tulangan Shearwall tipe SW-1 Ground Floor ................ 89
Tabel 4.9 Kebutuhan Tulangan Tangga Struktur Lantai Dasar- Lantai 1 .......... 94
Tabel 4.10 Koordinat dan Jarak Tower Crane, Supply, dan Demand Kolom ...... 97
Tabel 4.11 Perhitungan Waktu Pengangkatan pada Kolom Ground Floor ......... 98
Tabel 4.12 Perhitungan Waktu Kembali pada Kolom Ground Floor ................ 100
Tabel 4.13 Perhitungan Waktu Siklus Pengecoran Kolom Ground Floor ......... 102
Tabel 4.14 Faktor Koreksi Tower Crane ............................................................ 102
Tabel 4.15 Total Perhitungan Waktu Pelaksanaan Pengecoran Kolom GF ....... 103
Tabel 4.16 Rekapitulasi Produktivitas TC .......................................................... 105
Tabel 4.17 Rekapitulasi Koefisien produktivitas Tower Crane ......................... 108
Tabel 4. 18 Bills of Quantity............................................................................. 109
Tabel 4.19 Daftar Harga Upah Pekerja HSD Kota Bogor Tahun 2020 ............ 127
Tabel 4.20 Daftar Harga Bahan HSD Kota Bogor Tahun 2020 ........................ 127
Tabel 4.21 Daftar Harga Peralatan HSD Kota Bogor Tahun 2020 ................... 127
Tabel 4.22 Contoh Analisa Harga Satuan Pekerjaan ......................................... 129
Tabel 4.23 Rekap Rencana Anggaran Pekerjaan ............................................... 131
Tabel 4.24 Contoh Perhitungan Durasi Pekerjaan pada Ground Floor ............. 133
Tabel 4.25 Durasi Pekerjaan Struktur Bawah dan Atap ..................................... 133
Tabel 4.26 Hasil penjadwalan menggunakan Ms. Project 2016 ........................ 139
xviii
DAFTAR LAMPIRAN
LAMPIRAN I DATA ADMINISTRASI
LAMPIRAN II GAMBAR KERJA
LAMPIRAN III PERHITUNGAN VOLUME
LAMPIRAN IV BAR BENDING SCHEDULE
LAMPIRAN V DAFTAR HARGA SATUAN DAERAH BOGOR 2020 &
ANALISA HARGA SATUAN
LAMPIRAN VI RENCANA ANGGARAN PELAKSANAAN
LAMPIRAN VII PENJADWALAN PROYEK
xix
DAFTAR ISTILAH
B
Bar chart : Diagram batang
Bekisting : Cetakan sementara yang digunakan untuk
menahan beton selama beton dituang dan
dibentuk sesuai dengan bentuk yang
diinginkan.
Bills of Quantity : Suatu daftar rancangan pekerjaan yang
memberikan gambaran dan perhitungan
volume dari pekerjaan yang terdapat di
dalam kontrak kontruksi
Bar bending schedule : Daftar pola pembengkokan tulangan
yang meliputi data diameter, bentuk,
panjang dan jumlah tulangan
C
Cost : Semua pengorbanan (biaya) yang perlu
dilakukan untuk suatu proses produksi
D
Duration : Lama waktu suatu pekerjaan
F
Flowchart : Diagram alir atau langkah-langkah
G
Gantt chart : Diagram batang yang menunjukan aktivitas
suatu proyek.
K
xx
Koefisien : Koefisien adalah angka atau jumlah
kebutuhan tenaga kerja, bahan dan mungkin
juga beserta alat yang diperlukan untuk
menyelesaikan suatu pekerjaan per satu
satuan tertentu
M
Microsoft office project : Produk perangkat lunak manajemen proyek
Manpower : Tenaga kerja atau Tukang
Material : Bahan yang diperlukan untuk penyelesaian
proyek
Machines : Alat berat atau alat bantu yang diperlukan
untuk menyelesaikan suatu proyek
Money : Biaya yang diperlukan untuk
menyelesaikan suatu proyek
Method : Cara kerja yang dilakukan guna
menyelesaikan suatu poyek
O
Output : hasil dari penyusunan tugas akhir ini
berupa biaya dan waktu
R
Rekapitulasi : Ringkasan isi atau ikhtisar pada akhir
hitungan
T
Time : waktu atau durasi yang di butuhkan untuk
menyelesaikan suatu proyek
xxi
Task : alokasi waktu untuk menyelesaikan setiap
item pekerjaan proyek.
Time Schedule : alokasi waktu untuk menyelesaikan setiap
item pekerjaan proyek.
W
Work breakdown structure : Suatu metode pengorganisasian proyek
menjadi struktur pelaporan hierarkis
DIII – TEKNIK KONSTRUKSI GEDUNG POLITEKNIK NEGERI BANDUNG
M. Verrel Bramasta, Ria Risma Sagala, Perhitungan Rencana Anggaran..... 142
DAFTAR PUSTAKA
Ervianto, Wulfram I, “Manajemen Proyek Konstruksi”, Penerbit Andi,
Yogyakarta, 2003.
Husen, Abrar. 2011. Manajemen Proyek (Perencanaan, Penjadwalan, dan
Pengendalian Proyek). Serpong: CV. Andi Offset.
Widiasanti, Irika dan Lenggogeni. 2013. Manajemen Konstruksi. Bandung:
Rosda.
https://www.urbantown.id/proyek/urbantown-karawang. Diakses pada
tanggal. 20 Februari 2020.
Assnuddin, Setyadi. 2018. “Penerapan Manajemen Konstruksi Pada Tahap
Controlling Proyek” dalam Jurnal Sipil Statik Volume 6 (hlm.895-
906). Manado: Jurusan Teknik Sipil, Universitas Sam Ratulangi.
Pratama, Hariyono Saputro Yongky. "Analisis Faktor
Penyebab Keterlambatan Penyelesaian Proyek Pembangunan Gedung
MIPA Center UniversitasBrawijaya Malang." JurnalIlmu-ilmu
Teknik–Sistem 12.2 (2017).
http://eprints.undip.ac.id/34042/10/1909_CHAPTER_VII.pdf. Diakses pada
tanggal. 9 Agustus 2020
Badan Standar Nasional. 2013. SNI 03-2847-2013 tentang Persyaratan Beton
Struktural untuk Bangunan Gedung.
Kementrian PUPR RI. 2013. PERMEN PUPR NO-11/PRT/M/2013 Pedoman
Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum.
Kementrian PUPR RI. 2013. PERMEN PUPR NO-11/PRT/M/2013 Pedoman
Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum.
DIII – TEKNIK KONSTRUKSI GEDUNG POLITEKNIK NEGERI BANDUNG
M. Verrel Bramasta, Ria Risma Sagala, Perhitungan Rencana Anggaran..... 143
Badan Standar Nasional. 2002. SNI 03-6816-2002 tentang Tata Cara
Pendetailan Penulangan Beton.
Badan Standar Nasional. 2002. SNI 07-2052-2017 tentang Baja Tulangan
Beton
Suhendi, Edi. "Panduan Mengelola Proyek Dengan Microsoft Office Project
2007. " Bandung: CV. Yrama Widya (2009).
Ardiansyah Ahmad, Iqafdi, and M. A. S. SURYANTO HS. "ANALISIS
PRODUKTIVITAS DAN BIAYA OPERASIONAL TOWER
CRANE PADA PROYEK PUNCAK CENTRAL BUSINESS
DISTRICT SURABAYA." Rekayasa Teknik Sipil 2.2/REKAT/18
(2018).
Terbitan : A Revisi no : 3 Tanggal : September 2020 Halaman : 1 dari 1
JURUSAN TEKNIK SIPIL Nomor Dok K8.R20.IK21.F03.1D.TA
Program Studi D3 - KG
PENGAJUAN SEMINAR LAPORAN TA Semester Genap
Tahun Akademik 2019/2020
Kepada Yth,
Koordinator Tugas Akhir (TA)
Jurusan Teknik Sipil
Yang bertandatangan di bawah ini, Pembimbing Tugas Akhir atas nama :
Nama : 1. M Verrel Bramasta 2. Ria Risma Sagala
Nim : 171111015 171111026
Kelas : 3A-TKGE 3A-TKGE
Program Studi : D3 Teknik Konstruksi Gedung D3 Teknik Konstruksi Gedung
Menerangkan bahwa Laporan Tugas Akhir mahasiswa di atas dengan judul :
Perhitungan Rencana Anggaran Pelaksanaan Pekerjaan Struktur Pada Tower Andalusia
Proyek Pembangunan Apartemen Urbantown Karawang
TELAH SELESAI dan dapat diajukan ke Seminar
Demikian untuk diketahui dan dapat dipergunakan sebagaimana mestinya.
Bandung, 26 September 2020
Pembimbing Utama / I
Yulianto Petrus Krisologus, Drs, MM
NIP. 196007301986031002