    S E M I N A R S K I R A D

    PLANIRANJE PROJEKTA

    Mentor: prof. dr. sc Vladimir imovi Studenti: Branka PaukoviKolegij: Informacijski sustavi Ivana Rajkovi

    Zagreb, rujan 2006.

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    2/17

    2

    SADRAJ

    1. Pojam i definiranje projekta ........................................................................ 3

    2. Projektkarakteristike................................................................................. 33. Uspjean projekt........................................................................................... 34.

    ivotni ciklus projekta................................................................................. 45.

    Korelacija broja aktivnosti i vremena ........................................................... 5

    6. Korelacija broja trokova i vremena ............................................................ 5

    7. Poetna faza................................................................................................. 6

    8. Kako napisati prijedlog projektaKorak po korak ..................................... 89.

    Pisanje prijedloga projekta ........................................................................... 810.Standardna struktura projekta ...................................................................... 9

    11.

    Uvodno/popratno pismo ............................................................................... 9

    12.

    Naslovna stranica ......................................................................................... 9

    13.

    Saetak projekta......................................................................................... 1014.Uvod o organizaciji .................................................................................... 10

    15.Opis problema/potrebe ............................................................................... 10

    16.

    Ciljevi ........................................................................................................ 1117.

    Logiko povezivanje elemenata projekta.................................................... 1218.

    Ciljane skupine/korisnici ............................................................................ 12

    19.Aktivnosti .................................................................................................. 13

    20.Monotoring i evaluacija ............................................................................. 1421.Evaluacija .................................................................................................. 15

    22.

    Odrivost.................................................................................................... 1523.

    Proraun..................................................................................................... 1524.

    Prilozi ........................................................................................................ 1625.

    Smjernice za izradu .................................................................................... 16

    26.Literatura ................................................................................................... 17

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    3/17

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    4/17

    4

    ivotni ciklus projekta

    faza kljuni zadaci i odluke temeljna pitanja

    1.

    poetna faza

    formuliranje vizije i strategijeprojekta, definiranje ciljeva

    modeliranje i planiranje,

    evaluacija trokova i koristianaliza resursa

    Izrada prorauna(budetiranje)

    to treba uraditi zato to treba initi kako e se to ostvariti tko e to raditi i tko je sve

    ukljuen tko je sponzor i menader kad je poetak, a kad zavretak

    projekta

    koliko e to stajati

    2.

    faza provedbe

    prikupljanje tima,

    organizacija, kontrola,

    voenje, donoenje odluka irjeavanje problema,konflikata, ugovaranje,

    provedba, predaja projekta

    na koji nain e se rukovoditiprojektom

    tko e obavljati kontrolu nadprojektom

    hoe li projekt biti zavren navrijeme i u okvirima budeta

    3.

    zavrna faza

    procjena procesa i

    uinkovitosti, evaluacija,prikupljanje i implementacija

    znanja u sustav, promjene za

    budunost

    kakvi su rezultati ostvareniprojektom

    kako kontinuirano poboljavatii razvijati projektni menadment

    je li korisnik zadovoljanprojektnim rezultatom

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    5/17

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    6/17

    6

    POETNA FAZA

    Svaki pothvat oznauje novi poetak...T.S. Eliot am. pisac, nobelovac

    Poetnafaza ivotnog ciklusa projekta podijeljena je na tri podfaze :

    Iniciranje projektaokida cijelog projektnog ciklusa.IDEJEmogu doi od strane internih i eksternih sudionika(menadment pozicija na tritu, radnici zbog nagrada i napredovanja,vlada sa zakonskom regulativom, klijenti radi zadovoljavanja potreba....,

    - prepoznaje se potreba, postavljaju ciljevi, izabiru izvritelji (menader i

    sponzor), utvruje rizik.....

    -

    Inicijator je esto budui korisnik projektnog rezultataKorisniki projektni zahtjev definira:- to je problem

    - to se treba napraviti

    - kako e se projekt uklopiti u strategiju organizacije (korisnika)- koji su potrebni ljudski i financijski resursi

    - koje su oekivane koristi od projektnog proizvoda -

    preliminarni projektni plannatjeaji

    Selekcija projekta

    Izbor projektaproces procjene (evaluacije) na osnovi postavljenihposlovnih ciljeva organizacije, uvaavajui tehnike aspekte projekta,zahtijevane ljudske i ostale resurse, mogunost financiranja projekta

    Vanost(relevantnost)

    rizinost

    Linija prihvatljivosti

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    7/17

    7

    Zaselekciju projekatadva bazna sustava: nenumeriki i numeriki Bitni kriteriji ovise i o prirodi projekta Projekt u proizvodnoj organizaciji uvaava imbenike (faktore):

    proizvodnje, marketinga, financija, ljudskih potencijala i administrativne

    zahtjeve Projekt drutvenog znaaja: vanost, izvedivost i odrivost

    idiotizacija projekta financijska mjerila primarna bez obzira je li

    organizacija profitna ili ne

    Planiranje projekta Planovi nisu nita drugo do dobre namjere, do trenutka u kojem se

    degeneriraju u naporan rad P.Drucker

    Primarni razlog za planiranje jest uspostava jasnih smjernica : Svrha:kako i kada se projekt odvija te njegov obuhvat Ciljevi:specifini rezultati koje e projekt proizvesti Ogranienja:restrikcije na ono to elimo postii, kako i kada i koliko e

    to kotati Pretpostavke:nesigurne informacije koje uzimamo pri pripremi,

    implementaciji i zavretku projekta

    PRISTUPI PROCESU PLANIRANJAPROCES PLANIRANJA MOE SE RAZGRANIITI NA DESETFAZA*:

    Analizaproizvoda procesa iniciranja Odreivanje projektnihciljeva Definiranje projektnogobuhvata Izrada strukture ralanjenihposlova Izrada gantorgama i mrenih dijagrama Identificiranje uloga iodgovornosti Procjena kljunihparametaraprojekta Budetiranje i procjenatrokova

    Niveliranje i optimiziranjeresursa Identificiranje i procjena projektnihrizika *Projektni menadment; M.A.Omazi, S.Baljkas, Sinergija, Zagreb, 2005.

    http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#17.%20Slide%2017http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#17.%20Slide%2017http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#17.%20Slide%2017http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#18.%20%20%20odre%C4%91ivanje%20projektnih%20ciljevahttp://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#18.%20%20%20odre%C4%91ivanje%20projektnih%20ciljevahttp://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#18.%20%20%20odre%C4%91ivanje%20projektnih%20ciljevahttp://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#19.%20Slide%2019http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#19.%20Slide%2019http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#19.%20Slide%2019http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#20.%20Slide%2020http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#20.%20Slide%2020http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#20.%20Slide%2020http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#23.%20Slide%2023http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#23.%20Slide%2023http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#23.%20Slide%2023http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#24.%20Slide%2024http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#24.%20Slide%2024http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#24.%20Slide%2024http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#25.%20Slide%2025http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#25.%20Slide%2025http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#25.%20Slide%2025http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#26.%20Slide%2026http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#26.%20Slide%2026http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#26.%20Slide%2026http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#27.%20Slide%2027http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#27.%20Slide%2027http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#27.%20Slide%2027http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#27.%20Slide%2027http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#26.%20Slide%2026http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#25.%20Slide%2025http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#24.%20Slide%2024http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#23.%20Slide%2023http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#20.%20Slide%2020http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#19.%20Slide%2019http://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#18.%20%20%20odre%C4%91ivanje%20projektnih%20ciljevahttp://nastava.tvz.hr/Local%20Settings/Temporary%20Internet%20Files/Rad%20na%20projektu.ppt#17.%20Slide%2017
  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    8/17

    8

    Kako napisati prijedlog projektaKorak po korak

    Pisanje prijedloga projekta

    Kvaliteta prijedloga procjenjuje se po slijedeim kriterijima:

    prezentacijski stil projektna logika kao kriterijlogiko povezivanje elemenata projekta obrazloenje opravdanosti projekta kvantiteta pruenih informacija

    STRATEKI

    PRISTUP

    OPORTUNISTIKI

    PRISTUP

    procjena potreba

    analiza (dionika,

    problema, ciljeva)

    pisanje projekta po

    standardnoj strukturi

    istraivanje

    donatora (investitota)

    prilagodba otvorenih

    projekata natjeajima

    za financiranje

    natjeaj

    donatora

    analiza problema u

    skladu s ciljevima

    donatora

    pisanje projektnog

    prijedloga

    PRIJEDLOGPROJEKTA

    PLANIRANJEPROJEKTA

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    9/17

    9

    Standardna struktura projekta

    uvodno/popratno pismo naslovna stranica

    saetak projekta uvod o organizaciji opis problema/potrebe ciljevi aktivnosti vremensko trajanje projekta mjesto provoenja evaluacija odrivost proraun

    prilozi

    Uvodno/popratno pismo

    poeljno je ukljuiti slijedee dijelove: pozvati se na natjeaj / prethodni dogovor s donatorom (investitorom) predstaviti osnovni cilj, potreban iznos, i organizaciju (osnovne

    djelatnosti/programi)

    zavriti s uobiajenim uljudnim frazama te navesti mogunost daljnjegkontakta

    popis materijala u privitku

    Naslovna stranica

    format A4, a moe sadravati: ime organizacije (memorandum)

    naziv projekta trajanje projekta (oddo) ime voditelja ili osobe odgovorne za daljnje kontakte) datum predaje prijedloga projekta

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    10/17

    10

    Saetak projekta

    Predstavlja sr prijedloga projekta, ne due odjedne stranice, jednostavanjezik. Ukratko dati informacijekratko odgovoriti na osnovna pitanja:

    opis problema/potrebezato? gdje? ciljevito? ciljane grupeza koga? aktivnostikako? do kada? ukupni troak koliko? osnovne informacije o organizacijitko?

    Uvod o organizaciji

    Kratak osvrt na vrijeme i razloge osnivanja Izjava o ciljevima i osnovne djelatnosti Pravni status osnovni programi, projekti, aktivnosti postignuti rezultati, uinak opis krajnjih korisnika ili klijenata struktura organizacije suradnja s drugim organizacijama, lanstvo krai citati iz relevantnih dokumenata

    Opis problema/potrebe

    Ovaj dio predstavlja sve razloge zbog kojih bi trebalo provesti projekt i njimeostvariti eljenu promjenu u zajednici

    Koje su potrebe iproblemi vaih korisnika? to e se dogoditi ako se nita ne poduzme?

    Moe li se to dokazati? to se dogaa ukoliko se neto napravi?

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    11/17

    11

    Ciljevi

    TO elimo promijeniti ili postii? KAKO elimo ostvariti promjenu?

    ZATO provodimo aktivnosti? KAKO emo postii cilj?

    Karakteristika reenica kojom definiramo CILJ:zapoinjeINFINITIVOM:

    unaprijediti, poveati, omoguiti, poboljati, razviti, ojaati,pospjeiti, pridonjeti, poticati, smanjiti, izgraditi

    Opi ciljeviostvaruju se kroz dugoronije razdoblje - nee biti upotpunosti ispunjen

    Specifini ciljevi: ostvaruju se kad projekt zavri Specific, specifini - smjer/podruje djelovanja Measurable, mjerljivi - stupanj promjene, broj Achievable - ostvarivi, dohvatljivi

    Realistic, realni - izvediva korist za korisnike

    Time -bouunded, vremensko ogranienje

    CILJ

    TO elimo

    promijeniti ili postii?

    Aktivnost

    ZATO provodimo

    aktivnosti?

    KAK

    O

    emo

    p

    osti

    icilj?

    KAK

    O

    elimo

    ostvaritipromjenu?

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    12/17

    12

    Logiko povezivanje elemenata projekta

    Smjer djelovanjapovezivanje specifinog cilja sa bitnim UINAK(mjerljiv, realan, vremenski ogranien) moemo mjeriti provedbu

    projekta.

    Ciljane skupine/korisnici

    to detaljnije opisati ciljane skupine ovisno o vrsti projekta (spol, dob,obrazovanje, radno iskustvo, vjetine, sposobnosti...) Primarna ciljana skupinaili krajnji korisnici

    direktna korist, koriste proizvod ili usluge

    Sekundarna ciljana skupina

    indirektna korist, kroz utjecaje primarne skupine Tercijalna ciljana skupina(mali projekti je nemaju)

    ira javnost, radno sposobni, porezni obveznici

    REZULTATI

    UTJECAJ eljena promjena

    kojoj e projekt doprinijeti

    ali se nee dogoditi

    po zavretku projekta

    AKTIVNOSTI

    OPI CILJ

    UINAK eljena promjena

    vidljiva po zavretkuprojekta

    SPECIFIAN CILJ

    RESURSI: osoblje,

    novac, vrijeme,

    tehnologija,

    prostor, Know-how

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    13/17

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    14/17

    14

    Monotoring i evaluacija

    Slue poboljanju provoenja projekta, i analizi rada u organizaciji

    Monitoring je proces koji podrazumijeva:

    dobro izraen plan koji daje podatketo i kako prikupljati

    kontinuirano prikupljanje podataka u odreenim vremenskim razmacima vriti analizu prikupljenihinformacija

    provjera napredovanja

    POETAK

    PROJEKTA PROVOENJE PROJEKTA KRAJ

    PROJEKTA

    EVALUACIJA

    MONITORING

    Dinamika

    praenja

    odgovorna

    osoba

    Metoda

    vrsta obrasca

    Vrsta

    informacija

    aktivnost Dinamika

    praenja

    odgovorna

    osoba

    Metoda

    vrsta obrasca

    Vrsta

    informacija

    aktivnost

    Izlazni rezultat

    Planirano/ostvareno

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    15/17

    15

    Evaluacija

    Usporeuju se ciljevi iz napisanog projekta s onima koji su postignuti.kriteriji evaluacije:

    efektivnost/uinkovitost je li projekt postigao zadane ciljeve koje su aktivnosti uspjeno provedene

    efikasnost koja je povezanost izmeu trokova i koristi kako e se mjeriti ostvarivanje rezultata

    odrivost jesu li aktivnostiprojektatehniki, ekonomski, socijalno odrivi

    utjecaj

    kako su rezultati projekta utjecali na potrebe, boljitak i ope resurseciljane skupine

    Odrivost

    Stupanj do kojeg e podrka i korist proizala iz projekta nas taviti djelovatina ciljane skupine i po zavretku projekta

    Jednokratni projekti

    Financijska odrivost

    Proraun

    Faze:

    Na osnovu opisa, izlist svih vrsta trokova to preciznija procjena visine troka za svaku pojedinu aktivnost

    Zbroj svih trokova ukupni iznos prorauna Provjera i prilagodba ukupnog prorauna Prihvaanje prorauna od projektnog tima i organizacije

    Specifine kategorije trokova: Trokovi osoblja Direktni trokovi Indirektni trokovi Ostali trokovi

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    16/17

    16

    Prilozi

    sve to moe podii kredibilitet projektu, krajnjim korisnicima, organizaciji:

    statistiki podaci godinji izvjetaji strategije ivotopisi osoblja koje radi na projektu relevantne publikacije citati korisnika usluga fotografije pisma preporuke

    Smjernice za izradu

    EVALUACIJA PROJEKTNOG PRIJEDLOGA

    Koliko je projekt svrsishodan s obzirom na cilj,

    Koliko su jasno definirani subjekti ukljueni u projekt(posrednici, krajnji, korisnici, ciljane grupe)?

    Jesu li jasno definirane potrebe ciljnih grupa i krajnjih korisnika

    Da li su predloene aktivnosti prikladne, praktine i u skladu sciljevima i oekivanim rezultatima?

    Da li prijedlog uzima u obzir vanjske faktore i predviaevaluaciju?

    Da li je akcijski plan jasan i izvediv?

    Da li projekt sadri objektivno provjerljive pokazatelje za ishodprojektne radnje?

    Da li su oekivani rezultati predloene radnje odrivi?

    Da li su predloeni trokovi nuni za provoenje projekta

  • 8/11/2019 Paukovic Rajkovic Planiranje Projekta

    17/17

    17

    Literatura

    M. A. Omazi, S. Baljkas:Projektni menadment, Sinergija, Zagreb,2005. G. Fori, S. Novota:Korak po korak do uspjenog projekta, SMART,

    Rijeka 2006. G. Fori, S. Novota: Uokvirite svoju ideju, SMART, Rijeka 2006. Smjernice EU i MZOS za izradu CARDS projektnih prijedloga