19
mTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Embed Size (px)

Citation preview

Page 1: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

mTCA use in Linac to replace CAMAC

Tom Himel

June 4, 2012

1

Page 2: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Outline

• General plan for replacing the linac CAMAC.

• Can it be done without disrupting the accelerator run schedule?

• Budget and schedule

2

Page 3: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

General plan (1 of 3)• As mentioned in my introductory talk:

– Had planned to replace CAMAC in sectors 10-20 during four 7 month long annual downtimes of FACET.

– This would save cost of doing the phase I upgrade for LCLS-II

– Would allow LCLS-II to start with new hardware.

– Very unlikely to happen on this time-scale as all available resources are needed for upgrades more essential for LCLS-II

3

Page 4: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

General plan (2 of 3)• Full CAMAC replacement is now far enough

in the future, have not made new detailed plans.

• Do want intermediate improvements to be compatible with future plans– E.g. LCLS-II linac needs BPMs with better

resolution and lower charge sensitivity than present CAMAC readout.

– Best if done with final architecture so infrastructure can be shared with other systems and have best most modern hardware

4

Page 5: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

General plan (3 of 3)• If lab decides to use sectors 1-10 for FACET-II followed

by LCLS-III, will propose to do those 10 sectors first during the long downtimes of FACET, then spread to rest of linac after we have all procedures down pat.

• Otherwise will start in LCLS I or II sectors during down days and the 2 month annual downtimes.

• Systems where we are happy with LCLS-I solution will mostly be duplicated. Systems with no or problematic LCLS-I solutions will be redone, typically in mTCA

• High channel count systems are the most important to develop early.

5

Page 6: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Plans by system• LLRF:

– LCLS-I still depends on CAMAC. PADs and PACs supplement the CAMAC on a few stations. All interlocks, timing and some analog readings are done with PIOP and MKSU

– Replace with mTCA and MKSU-II (interlock and diagnostic network attached device (NAD) developed as part of the LLRF AIP project)

• BPM:– Upgraded linac LCLS-I has VME + NAD which works well.

Cannot do 2 bunch, very kludgey.– Replace CAMAC with mTCA.– Present CAMAC system inadequate for low current running.

6

Page 7: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Plans by system• Quads/Bends:

– Upgraded linac LCLS uses NAD which works well– Duplicate– Present CAMAC + rack mounted controller solution has

regulation problems at low current.• Correctors

– Upgraded linac LCLS uses VME ADC and DAC and PLC to control 2 bulk supplies and 16 corrector channels. Works fine but expensive

– AIP developing new controller that goes in the crate with the 16 channels and replaces the VME and PLC functionality. Makes the power supply crate a NAD similar to that for the Quad power supply controller

– Will use the AIP solution7

Page 8: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Plans by system• Machine Protection

– Upgraded linac LCLS uses home-brew “link node” chassis that has plug in cards some of which are COTS, others are home-brew. Works well.

– Will probably duplicate as requirements are odd enough that COTS solution is unlikely

• Vacuum:– LCLS non-linac uses signal conditioning

chassis + COTS PLC’s – duplicate

8

Page 9: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Plans by system• Temperatures and other slow ADCs

– LCLS non-linac uses Beckoff I/O. Cheap, works well.

– Duplicate• Digital I/O

– LCLS non-linac uses IP cards on VME carrier board

– Will use same IP cards on mTCA carrier.

9

Page 10: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Plans by system• Small channel count diagnostics like

toroids, Faraday cups, profile monitors, wire scanners– LCLS solutions have various problems– Will improve for LCLS-II as allowed.– For toroid would build a new RTM for same

ADC used for LLRF– Linac upgrade will either duplicate the

improved versions or, if needed, develop improved versions probably in mTCA.

10

Page 11: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Installation without disruption• We have considerable experience at this.• Process:

– Test in lab– Test in part of linac not in use– Where possible (not too many cables), develop quick

switch over from old to new and back– Install and test on down days

• Phase I was done this way with virtually no disruption of accelerator program. See “Changing horses mid-stream” at http://www.esrf.eu/icalepcs2011/papers/tucaust04.pdf 11

Page 12: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Installation without disruption• Most RF stations can be taken offline,

worked on and put back online while the linac is running. Main exceptions are injector klystrons.

• The mTCA LLRF testing was done this way using cable adaptors to make the switching of cables quick.

• Some systems like vacuum and MPS will have to have their final connections made during the two month downtimes.

12

Page 13: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Cost comparision

• The two biggest (and hence most expensive) systems are LLRF and BPMs.

• They are also the only systems for which we have seriously looked at more than one solution.

• Dan and Qiao showed that the costs for the considered solutions were quite similar

• Expect the same to be true for other locations of the same types of hardware

13

Page 14: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Linac upgrade cost and schedule

• As I mentioned before, we have not updated the cost and schedule for upgrading the linac as the start date is distant and uncertain.

• I’ll show some of what we presented at the last review.

• Mention a few possible changes

14

Page 15: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Budget Cost Analysis

• Resource Cost Estimates– All tasks detailed – Resources identified – Discussed details w/ resources for estimates– Summed resources vs. draft schedule– Performed similar exercise for RF (already

approved AIP)– Totaled all manpower costs vs. time (24 mo.)

Page 16: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Hardware Cost Estimates• MTCA Infrastructure

– COTS based on actual quotes or vendor budgetary quotes

– Includes crate, power modules, Hub Controller, Processor IOC, Timing Module

– Timing module not yet a commercial item but base cost on similar commercial products

Page 17: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Hardware Costs 2• Applications Modules

– AMCs: ADC-DAC, 3-IP, PMC adapter• ADC-DAC: Vendor quotes, DESY target (Strück);

Vadatech quote pending• 3-IP: quote in hand (TEWS)• PMC: Quotes pending (Vadatech,TEWS)

– US 2nd sources:• Buying first articles to specification, compatible RTM

– Timing • Source is Stockholm U., working to develop vendors

Page 18: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Estimated 10-Sector Cost

T. Himel

systemoption probability

average NRE (k$)

LI11-20 basic

LI11-20 deluxe

LI21-30 basic

LI21-30 deluxe

MPS 0 200 200 0 0Timing 0 608 608 608 608RF 0 2240 2240 2240 2240network 0 820 820 50 50corrector incl PS 0 608 608 0 0LGPS control 0 432 432 0 0LGPS 0 0 864 0 0solid state subbooster 0 0 1440 0 1440BCS readout 0 50 50 50 50BCS full system 750 0 750 0 750profile monitors 150 320 320 0 320toroids 100 80 80 0 0wire scanners 0 0 0 0 0modulator PLC+ upgrade 0 0 5000 0 4000racks 0 1512 1512 1512 1512vacuum CAMAC replacement 0 150 150 150 150vacuum rack mounted chassis 100 0 432 0 144PPS 0 0 0 0 0long haul cables 2048 2048 0 0crates 1150 1150 1150 1150temperatures etc 300 300 300 300

total 5110 11670 20156 6060 12714

edi_factor 1.6nsector 10manmonth_cost 25indirect_rate_labor 52%indirect_rate_MandS 9.40%

Assume LI11-20 Column costs

Solid state sub-booster required

Modulator PLC not required

BCS & Power Supplies Included

RF Station Unit Cost = $28K

1440 1440

13110

Page 19: MTCA use in Linac to replace CAMAC Tom Himel June 4, 2012 1

Summary• The R&D for the major systems is well

advanced.• We still have a few implementation

decisions to make on the minor systems• We have a rough and somewhat out of

date cost estimate• We have experience doing upgrades

during short downtimes and while this one involves more cables, it is still doable

19