Upload
eli
View
40
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Status of mTCA Stripline BPM Development. June 4-5, 2012 Dan Van Winkle for BPM team: Sonya Hoobler, Tom Himel, Jeff Olsen, Steve Smith, Till Straumann, Ernest Williams, Chuck Yee, Andrew Young. Outline. Background Motivation System Description Physics Requirements Proposed new design - PowerPoint PPT Presentation
Citation preview
Status of mTCAStripline
BPM DevelopmentJune 4-5, 2012
Dan Van Winkle for BPM team:Sonya Hoobler, Tom Himel, Jeff Olsen, Steve Smith, Till Straumann, Ernest Williams, Chuck Yee, Andrew Young
2
Outline• Background
– Motivation• System Description
– Physics Requirements– Proposed new design– Cost comparisons– Technical Overview
• Current Status• Schedule• Risks
– mTCA– Pizza Box– VME/AFE
• Next Steps
mTCA BPM DevelopmentJune 4-5, 2012
3
Background
mTCA BPM DevelopmentJune 4-5, 2012
4
Background4 Flavors of BPMs
mTCA BPM DevelopmentJune 4-5, 2012
LCLS Pizza Box
FACET – LINAC CAMAC
FACET – Sector 20
XTA
5
Background
• Assumptions– LCLS II will use existing BPMs whenever possible
(CAMAC)– 91 new BPMs will be necessary for LCLS II. These will
be some type of “new” electronics.– The existing linac BPMs will eventually need to be
upgraded to something more sensitive (exactly like LCLS I).
– This development is targeted at both the new BPMs for LCLS II and the upgrading of the existing BPM electronics throughout the linac.
mTCA BPM DevelopmentJune 4-5, 2012
6
Why not just clone the LINAC (CAMAC) BPM electronics? (Motivation)
• CAMAC technology is obsolete and becoming more difficult to maintain– Obsolete Parts– PDR Specs can not be met (this was demonstrated in
LCLS I)– Technical expertise is disappearing– EPICS incompatibility
mTCA BPM DevelopmentJune 4-5, 2012
7
Why not just clone the LCLS-I stripline BPM electronics? (more Motivation)
• Pizza Box solution was a quickly thrown together solution used to replace a COTS solution that did not work out.
• It worked so well that it is now used throughout LCLS I.Unfortunately:• Coldfire CPU in pizza box is too wimpy to do full job of IOC. Hence
special private network link to a VME IOC to transfer data for processing.– Requires VME crate/CPU/EVR per 4 BPMs
• Takes multiple people each with special expertise to put in a new BPM or even to repair an existing one.
• Requires a lot of network equipment and cables.
mTCA BPM DevelopmentJune 4-5, 2012
8
System Description
mTCA BPM DevelopmentJune 4-5, 2012
9
Physics Requirements
mTCA BPM DevelopmentJune 4-5, 2012
2 Differences from LCLS I
• 10pC Charge• 2 Bunches
10
Design Proposal• A new designed based upon the emerging
technology of mTCA was proposed.– New design can be used for rest of LCLS-II (even the
injector if we get the design done in time)– New Design at 250 Msamp/sec (300 MHz center
frequency) means existing cable plant can be used (for existing LINAC BPMs. (~500k$ savings)
– Allows for mix and match of systems (LLRF/BPMs) in same shelf (theoretically sharing infrastructure costs)
mTCA BPM DevelopmentJune 4-5, 2012
11
Deliverables• Design build and install one crate of 3 BPMs in a sector (1st
20 sectors)– We expect to use new 250 Msamp/sec ADC or potential
undersample at 125 Msamp/sec using Struck Board– The analog front end electronics will be a new design,
same topology as pizza box front end (but higher in frequency)
– The necessary software will be done to integrate the BPMs into the EPICS control system
• Mass production for 10 sectors (LCLS II) will be a separate AIP funded outside LCLS II core project.
mTCA BPM DevelopmentJune 4-5, 2012
12
Cost Comparisons
mTCA BPM DevelopmentJune 4-5, 2012
Cost Comparisons Between Systems
Micro TCA LCLS - I XTA Hardware Labor Estimate 960 Hardware Labor Estimate 2880 Hardware Labor Estimate 1920
Digitizer 4250 Pizza Box 3598 Digitizer 2200 RTM (AFE) 1500 AFE 2100
Total 6710 Total 6478 Total 6220
Crate 9 BPMs 1BPM 9 BPMs 1BPM
Shelf 5300 Crate (21 SLOT) 8495 Crate (21 SLOT) 8495 Crate (4-slot) 3885 3885
MCH 2300 CPU 4125 CPU 4125 CPU 2125 EVR 2700 EVR 2700
Power Module 1000 EVR Fanout 550 EVR Fanout 550 EVR 3300 Network Switch (x2) 360 Network Switch(x2) 360
Power Switch 600 Power Switch 600
Total 14025 Total 16830 12220 Total 16830 12220
Max Number of BPM/Shelf 9 9 9 Max Cost per BPM (1BPM) $20,735.00 $18,698.00 $18,440.00
Min Cost per BPM (9 BPM) $8,268.33 $8,348.00 $8,090.00
13
Requirements
• Similar Analog Front end at new frequency (300 MHz) (next slide)
• Expect slightly better dynamic range to accommodate new 10 pC charge limit for LCLS II
• Initial operation will use internal clock.• For multi-bunch operation, phase synchronous
ADC clock will be required to extract bunch phase information (238 MHz).
mTCA BPM DevelopmentJune 4-5, 2012
14
300 MHz vs. 140 MHz
mTCA BPM DevelopmentJune 4-5, 2012
0 50 100 150 200 250 300-20.00
-18.00
-16.00
-14.00
-12.00
-10.00
-8.00
-6.00
-4.00
-2.00
0.00
BPM Response
BPM Response
Frequency (MHz)
Am
plitu
de (d
B)
• By using 300 MHz instead of 140 MHz gain 4.6 dB of signal level• This allows us to potentially save large sums of cabling costs when we
eventually upgrade the LINAC BPMs. (New LCLS II BPMs will not see this cost advantage due to pulling of new cables anyway.
15
System Description
mTCA BPM DevelopmentJune 4-5, 2012
BPM
Crate
Analog Front End and Calibrator ADC IOC
(CPU)EVR
(Timing)
Channel Access Network
Calibrator Trigger
ADC Trigger
Timing Network
Crate Controller
(MCH)
ADC Clock
Utility Network (crate management)
Fast Feedback (coming later; to be connected to MCH or CPU or network
card)
Up to 9 BPM processors per crate
16
RTM Signal Flow Block Diagram
mTCA BPM DevelopmentJune 4-5, 2012
R=50 Ohm
R=50 Ohm
R=50 Ohm Freq=300 MHz
T=1.00 T=1.00
T=1.00 T=1.00
T=1.00 T=1.00
T=1.00T=1.00
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
BWpass=30 MHzFcenter=300 MHz
R3
R2
R1
SWITCH5
SWITCH4
SWITCH3 16dB_9 VAR_ATTEN9 SRC1
CLin4TF8 TF7
CLin3TF6 TF5
CLin2
TF4 TF3
CLin1TF2TF1
VAR_ATTEN8 VAR_ATTEN716dB_8 16dB_7 BPF8BPF7
VAR_ATTEN6 VAR_ATTEN516dB_6 16dB_5 BPF6BPF5
SWITCH2
VAR_ATTEN4 VAR_ATTEN316dB_4 16dB_3 BPF4BPF3
SWITCH1 BPF2VAR_ATTEN2VAR_ATTEN1 16dB_216dB_1BPF1
R
R
R
SPDT_Static
SPDT_Static
SPDT_Static Amplifier2 Attenuator VtSine
PCLIN2TF TF
PCLIN2TF TF
PCLIN2TF TF
PCLIN2
TFTF
Attenuator AttenuatorAmplifier2 Amplifier2 BPF_ButterworthBPF_Butterworth
Attenuator AttenuatorAmplifier2 Amplifier2 BPF_ButterworthBPF_Butterworth
SPDT_Static
Attenuator AttenuatorAmplifier2 Amplifier2 BPF_ButterworthBPF_Butterworth
SPDT_Static BPF_ButterworthAttenuatorAttenuator Amplifier2Amplifier2BPF_Butterworth
Calibrator
4 Channels of Analog Processing
17
Current Status
mTCA BPM DevelopmentJune 4-5, 2012
18
• 3 RTM Boards Loaded– Initial RF testing complete– Initial Data acquisition complete
• RTM CPLD Programmed and verified• FPGA on AMC card started
– Code for driving and control of CPLD• 250 Msamp digitizer spec started (90%
complete).
mTCA BPM DevelopmentJune 4-5, 2012
19
Prototype Board Complete (in test)
BPM AIP ReviewApril 11, 2012
Analog Front End RTM Struck 125 MHz digitizer
20
Modifications of 125 MS/s Board
mTCA BPM DevelopmentJune 4-5, 2012
0 50 100 150 200 250 300 350-14
-12
-10
-8
-6
-4
-2
0
2
Original
no AMC filter
No Filters
No Filters and New tranformer
Frequency (MHz)
dBc
(5 M
Hz
Valu
e)
Maximum Bandwidth achieved with SIS8300 is approximately 130 MHz.
21
Initial Results
mTCA BPM DevelopmentJune 4-5, 2012
1.8307 1.8308 1.8309 1.8311.5
2
2.5
3
3.5
4
4.5
5
5.5x 10
4
time (ms)
AD
C C
ount
s
Measured BPM signal (125 MSamp/sec) - simulated signal
Ch1Ch2Ch3Ch4
1.8307 1.8308 1.8309 1.8311.5
2
2.5
3
3.5
4
4.5
5
5.5x 10
4
time (ms)
AD
C C
ount
s
Measured BPM signal (125 MSamp/sec) - simulated signal
Ch1Ch2Ch3Ch4Oscope - Ch4
Measured Results from mTCA system on “simulated” Beam Signal
22
Schedule
mTCA BPM DevelopmentJune 4-5, 2012
23
Current Schedule
BPM AIP ReviewApril 11, 2012
24
Schedule Comments
• Tight Schedule to make LCLS II Injector• FDR’s for Injector occurring in July/August
time frame. • Hardware installed in racks not required till
late 2013.• There is some belief that we can still get the
design into the LCLS II injector.
mTCA BPM DevelopmentJune 4-5, 2012
25
Risks
mTCA BPM DevelopmentJune 4-5, 2012
26
Risks (mTCA)• mTCA Infrastructure
– New standard - interoperability is a potential issue – we are diligently working on this
• Digitizer– Counting on vendor which is currently struggling with 10
channel design. However vendor seems solid and recent vendor visit put most fears to rest.
– Potential delays due to vendor• Manpower availability/Priority Setting• Backup Plan for injector is VME digitizer with AFE in
small pizza box.
mTCA BPM DevelopmentJune 4-5, 2012
27
Risks (Pizza box)• Obsolete Parts• Unsupportable PADs with “wimpy” coldfire CPU’s• Redesign necessary on PAD for continued use• Custom electronics which must be supported for the
indefinite future.
mTCA BPM DevelopmentJune 4-5, 2012
28
Risks (VME Digitizer/AFE) (Backup Plan)
• Custom Boards (ADC and AFE) (not COTS)• Could be obsolete parts on digitizer• Custom electronics which must be supported for the
indefinite future.• May not be able to do multi-bunch operation
mTCA BPM DevelopmentJune 4-5, 2012
29
Next Steps
• Calibrator needs to be tested• Finish FPGA code in Struck 10ch digitizer• Order new digitizer (250 Msamp/sec version)• System software and integration
mTCA BPM DevelopmentJune 4-5, 2012