1. DATA PROYEK

2. KONDISI EXISTING SITE

4. STRUKTUR ORGANISASI

5. TEMPORARY FACILITIES

9. DAFTAR ALAT KERJA

3. SCHEDULE PROYEK

10. PERKEMBANGAN PROGRESS

11. ANIMASI SEQUENCE PEKERJAAN

GO

6. PEMBAGIAN ZONA KERJA

7. PEKERJAAN TANAH

8. METODE PEKERJAAN MASSFOND

12. PEKERJAAN FINISHING

13. QUALITY PLAN & SAFETY PLAN

GO

GO

GO

GO

GO

GO

GO

GO

GO

GO

GO

GO

Page 3: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 3/143

BACK

NAMA PROYEK :

LOKASI PROYEK :

PEMBERI TUGAS :

KONSULTAN PERENCANA :

KONSULTAN STRUKTUR :

QUANTITY SURVEYOR :

WAKTU PELAKSANAAN :

LINGKUP PEKERJAAN :

Page 4: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 4/143

BACK

LOKASI

Page 5: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 5/143

KONDISI EXISTING PROYEK 

Page 6: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 6/143

KONDISI EXISTING SITE PROYEK 

Page 7: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 7/143

BACK

Page 8: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 8/143

SEQUENCE KEGI T N PEKERJ N KOORDIN SI

Page 9: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 9/143

BACK

Untuk Produksi dikoordinasikan oleh :

-1 Site Manager Struktur ( PPM Struktur )

-1 Site Manager Arsitek ( PPM Arsitek )

-1 Site Manager ME & DC ( PPM ME & Koor DC )

- Proyek ON GOING

STRUKTUR ORGANISASI

LA MAISON BARITO APARTMENT

 JAKARTA SELATAN

Deputy PM

PEM PPM Struktur PPM Arsitektur PPM MEP PFM

Perenc S.Dwg Supervisor Supervisor Akuntansi

Quantity Surveyor Surveyor

Procurement Staff Mekanik

Cost Control Officer K3

Staff QC

Page 10: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 10/143

BACK

15

11 9

8

6

5

16

12 14

13

3 1

3

7

10

14

Gardu

Existing

P1

P2

P3

Kantor

Owner 

Keterangan :

Tower Crane TC

Type Static

Jib : 60 M

Jumlah : 1 Unit

Kap. Max : 3,6 – 12 Ton

- Barak Pekerja di luar lahan proyek 

16

Page 11: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 11/143

BACK

Pada pelaksanaan Proyek La Maison ini pembagian zona kerja dibagiberdasarkan luasan lantai yang akan dikerjakan. Pembagiannya meliputiarea basement, area podium dan area tower yang terdiri dari :

Area Basement   6 Zona Kerja, Pekerjaan Galian dan Struktur

- Pekerjaan Galian 6 Zona

- Pekerjaan Struktur 6 ZonaArea Podium   6 Zona Kerja, Pekerjaan Struktur

Area Tower   4 Zona Kerja, Pekerjaan Struktur

Page 12: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 12/143

Total Luasan = 3596 m2/LT

START

Page 13: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 13/143

START

Total Luasan = 2308 m2/LT

Page 14: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 14/143

Total Luasan = 1355 m2

Page 15: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 15/143

BACK

-Pekerjaan galian tanah yang dikerjakan dengan alat / excavator antara lain :

Galian Mass Pondasi dan Pail Cap.

-Pekerjan galian tanah yang dikerjakan dengan cara manual antara lain :Galian di sela   –   sela bor pile, Galian tertinggal / tidak terjangkau

excavator.

-Urugan tanah dilaksanakan untuk mengurug di sela-sela batako dan karena metode /

meratakan tanah

Pada saat galian tanah, Setelah lubang pondasi selesai digali, dasar dan

dindingnya disemprot dengan larutan Anti Rayap secara merata sebanyak 5 liter / m2 .Tanah galian atau urugan harus disemprot secara merata dengan larutan Anti Rayap.

Setelah pondasi dibangun, tanah atau urugan tersebut dimasukan kembali kedalam

lubang pondasi agar berfungsi sebagai penyangga serangan rayap.

Page 16: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 16/143

START

Page 17: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 17/143

Catatan :

1. Tanah Miring

dilapisi dengan

Blue Sheet

2. Tanah dikasih

Cerucuk3. Kemiringan Tanah

1:2

4. Bak Kontrol 50x50

cm per 20 m

BKBKBK

BK

BK

BK

BKBK

BK

BK

BK

BK

BK

Page 18: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 18/143

BACK

Pengecoran Massfond

menggunakan 3 buah

concrete pump dan

dibantu dengan TC.

CP1

CP2

CP3

START

P3

P2

P1

CP-1 pada P-3

CP-2 pada P-2

CP-3 pada P-1

-Luas Area Massfond :

1008 m2

-Ketinggian Massfond :

2m

Page 19: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 19/143

NO URAIAN SATUAN VOLUME KETERANGAN

1 Volume Beton m3 2150

2 Alat

- Concrete Pump Mobil Unit 3 Mass Pondasi

- Conventor Unit 4

- Vibrator Buah 9

- Concrete Pump Kodok Unit 1 Podium (Permanen)

3 Lama Penecoran Jam 364 Waktu Pengecoran

- Start : Sabtu Pukul 15.00 wib Sore Hari

-Finish : Senin Pukul 03.00 wib Dini Hari

5 Mobil Mixer Buah 10 di Lapangan

6 Tower Crane Unit 1

7 Tukang Cor Orang 21

Page 20: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 20/143

Potongan Bekisting Mass Pondasi

Siklus Pengecoran :

-Tinggi Pengecoran dibagi menjadi 2 lapis di setiap lapis

setinggi 1 m

-Pengecoran Lapis Ke 1, Vol = 1150 m3

Siklus 1A 2A 1B 2B

Waktu Pelaksanaan ± 20 Jam = 15.00  – 11.00

-Pengecoran Lapis Ke 2, Vol = 1000 m3Siklus 1A 2A 1B 2B

Waktu Pelaksanaan ± 16 Jam = 11.00  – 03.00

Pengecoran dibagi 2 Lapis

1A

1A

2A

2A

Urugan Tanah

Potongan Bore Pile Mass Pondasi

1A2A

2B 1B

BACK

Page 21: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 21/143

BACK

2

Keterangan :1. CP Untuk Cor Lt.Dasar-Lt.7

2. TC Jib 60m untuk cor Lt.8-Lt.31

3. PH 1

4. PH 2

1

3 4

Page 22: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 22/143

Pada Proyek ini menggunakan 1 buah TC dengan panjang Jip 60 m.

Denah Pondasi TC

Potongan A

Posisi Peletakan Bracing TC Lt. Tower

Page 23: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 23/143

SCHEDULE TOWER CRANE

NO URAIAN LANTAI ELEVASI SCHEDULE

A   Pondasi + Erection TC

1 Cor Bore Pile / Tiang Pancang 12-Mar-12

2 Cor Pondasi TC -2.00 m 18-Mar-12

3 Erection TC 28-Mar-12

B Bracing TC

1 BR 1 8 + 30,00 m 30-Aug-122 BR 2 13 + 50,50 m 10-Okt-12

3 BR 3 19 + 74,00 m 15-Des-12

4 BR 4 25 + 98,00 m 15-Jan-13

C Jumlah Section Pcs 42 Pcs 2mx2mx3m

D Dismantling   15-Apr-13

Page 24: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 24/143

Pada Proyek ini menggunakan 2 Area penempatan PH, yaitu PH 1 dan PH 2.

PH2PH1

PH1   PH2

Posisi PH Pada Lantai Dasar

Page 25: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 25/143

Potongan Posisi Pipa Cor

Catatan :1. Concrete Pump digunakan untuk pengecoran

Lt. Dasar – Lt.7

2. Tower Crane digunakan untuk pengecoran Lt.

8 – Lt.31

Page 26: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 26/143

Page 27: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 27/143

Page 28: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 28/143

BAR CUTTER

BAR BENDER

Kebutuhan Volume :

Jumlah penyediaan Bar

Cutter dan Bar Bender

masing-masing 2 set

Page 29: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 29/143

WS1

WS2

Penempatan Washing Bay

Area :

WS – 1 pada P3

WS – 2 pada P1

Kendaraan proyek sebelum keluar lokasi, harus dibersihkan dahulu di

area washing bay . Air cucian kotor dibuang melalui saluran

temporary ke arah sungai

Page 30: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 30/143

Panel

Induk

Panel

Kerja

Panel

Kerja

Panel

Kerja

Panel

Kerja

Panel

Kerja

Basement-Lt.7

Lt.8 – Lt.17

Lt.18 – Lt.30

Pada panel kerja, kabel vertikal

melalui shaft elektrik dan dibagi

menjadi 3 zona, yaitu :

- Zona 1 Lt. Basement-Lt.7

- Zona 2 Lt.8-Lt.17

- Zona 3 Lt.18-Lt.30

Paneldistribusi

Panel

Induk

Panel

Distribusi

PanelKerja

Panel

Eksternal

Panel TC

Denah Peletakan Panel Listrik

Page 31: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 31/143

Volume lampu per Area :

-Area Podium 40 Titik

-Area Tower   20 Titik

-Area External 20 Titik

HBTHBT

HBT

HBT

Page 32: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 32/143

PLNPANEL

INDUK

NYYHY 4 X 95 mm

NYYHY 4 X 16 mm

PANEL

DISTRIBUSI

PANEL

KANTOR

Diagram Pembagian Arus Listrik

NYYHY 4 X 70 mm

NYYHY 4 X 35mm

NYYHY 4 X 25mm

PANEL

TC

PANEL

PH

PANEL

KERJA

NYYHY 4 X 35 mmPANEL

EKSTERNAL

Page 33: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 33/143

Tangki

10.000 L

Pompa

Transfer

Denah Pengeboran dan titik pompa

Pompa 2

Pompa 1

Pompa 2 = Pompa Deep well

-Untuk Pengisian torn 10.000 L

-Untuk distribusi air kerja ke setiap lantai

-Untuk curing Beton

Sistem air kerja dibagi :

1. Area Podium disiapkan : 2 kran + 2 drum2. Area Tower disiapkan : 1 kran + 1 drum

Pompa 1 = Pompa Jet Pump

-Untuk toilet kantor

-Untuk cuci mobl mixer

Page 34: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 34/143

AIR SUMUR

TANGKI

10.000 L

POMPA

TRANSFER

POMPA DEEP WELL

TANGKI

5.000 L

DRUM

PENAMPUNGAN

PIPA 1 ½ ‘’ PIPA 1 ‘’

AIR SUMUR

TANGKI

1.000 L

TOILET

KANTOR

JET PUMP

Diagram Pembagian Distribusi Air

Pompa 1 Pompa Deep well

Pompa 2 Jet Pump

Page 35: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 35/143

INSTALLATION

CORNER

COUPLE

R

TIANG RAILINGHANDRAIL

MID HANDRAIL

BESI BEHEL

D12

BASEPLA

TE

POLYNET

BESI BEHEL

D12

TIANG RAILING

POLYNET

Pemasangan Safety Net Pada setiap lantai

bangunan dan pemasangan safety Wing dua

lantai dibawah pekerjaan struktur

SAFETY NET

form work/pekerjaanstruktur

railing perimeter

safety net perimeter

2 lantai

safety wing net

temporary railing

polynet

Page 36: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 36/143

Detail

potongan

1

2

3

4

Page 37: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 37/143

SLING

Dia.10mm

MID BRACING

BEHEL D16

CROSS BRACING

BEHEL D13

KAWAT HARMONIKA

(LAYER 1) +POLYNET

(LAYER 1)

PIPE Dia. 1 ½”

PIPE Dia.1 ½”

D16

CLAMP

SLING

Dia.10mm

L50x50,

100mmPIPE Dia. 1 ½”,

750mmDYNABOLT M12

PIPE Dia. 1 ½”

PIPE Dia. 2”,

100mm

SAFETY WING

Page 38: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 38/143

OPENING > 2 M / VOID AREA

KAWAT AYAM + SAFETY NET

HANDRAIL

MID HANDRAIL

BESI BEHEL D12

OPENING 100 ~ 600 mm

OPENING 650~ 2000 mm

SAFETY RAILING VOID

Page 39: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 39/143

SAFETY NET DI LIFT SAFETY VOID

Page 40: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 40/143

RANGKA INSTALLATION

Page 41: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 41/143

TS 2TS 1

TS 1TS 2

TF 2 TF 1

A. Terminal Struktur disiapkan 4 Unit

-TS 1 = Terminal Barang Struktur Lantai Ganjil (2 Unit)

-TS 2 = Terminal Barang Struktur Lantai Genap (2 Unit)

B. Terminal Finishing disiapkan 2 Unit

-TF 1 = Terminal Barang Finishing Lantai Ganjil (1 Unit)-TF 2 = Terminal Barang Finishing Lantai Genap (1 Unit)

Denah Peletakan Terminal Barang

BACK

Page 42: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 42/143

PENEMPATAN TEMPORARY FACILITY

PENGECORAN MASS FOND DENGAN

BANTUAN ALAT CONCRETE PUMP

Periode bulan Maret 2012

Periode bulan Maret– 

 April 2012

PENGECORAN LANTAI BASEMENT

Page 43: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 43/143

PENGECORAN LANTAI BASEMENT

PENGECORAN LANTAI DASAR

PEMINDAHAN TEMPORARY SITE OFFICEKEDALAM BANGUNAN DI BASEMENT

Periode awal April-awal Juni 2012

Periode akhir april –  pertengahan Juni 2012

Periode pertengahan Mei 2012

PEMASANGAN SAFETY NET DI SEKELILING

Page 44: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 44/143

BANGUNAN PODIUM

-PEMASANGAN SAFETY WING DI LT.9

-SAFETY NET DI LT. 8 & 10

-PEKERJAAN STRUKTUR DI LT. 11

Periode pertengahan juli 2012

Siklus pemasangan 2 lantai dibawah

Pekerjaan struktur 

Page 45: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 45/143

-PEKERJAAN STRUKTUR DI LT.20

-PEKERJAAN FINISHING DI LT. 13

-PEKERJAAN FASAD DI AREA PODIUM

Periode sampai dengan akhir bulan Oktober 2012

-PEKERJAAN STRUKTUR DI LT.24

-PEKERJAAN FINISHING DI LT. 17-PEKERJAAN FASAD SAMPAI LT.11

Periode sampai dengan akhir bulan November 2012

Page 46: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 46/143

SEMUA PEKERJAAN STRUKTUR, FINISHING,

LANDSCAPE DAN FASAD SUDAH SELESAI

Periode Bulan

Maret 2013 Topping Off 

Periode Bulan Mei 2013

Periode Bulan Oktober 2013

BACK

Page 48: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 48/143

 ALAT YANG DIPERLUKAN :

1. TROWEL2. PALU KARET

3. WATER PASS

4. BESI SIKU

5. GERGAJI

6. RAMSET

7. GARUKAN PERATA

HAL – HAL YANG PERLU DIPERHATIKAN :

1. PEMASANGAN HABEL HARUS ZIG-ZAG DENGAN OVERLAP YANG DIIJINKAN MIN.10 CM

2. DERAH PERTEMUAN ANTARA HABEL DAN STRUKTUR HARUS DIBERIKAN ADUKAN

ELASTIS 1 PC : 6 PS

3. HASIL AKHIR PEMASANGAN HABEL YANG BENAR DITANDAI DENGAN TIDAK ADANYA

LUBANG-LUBANG SINAR YANG MUNCUL DARI DINDING PERMUKAAN PASANGAN

HEBEL

4. PENGGUNAAN BETON PRAKTIS MENGIKUTI ATURAN DARI PABRIK HABEL

5. PEMASANGAN HABEL YANG BAIK ADALAH DENGAN MENGGUNAKAN ALAT TROWEL

SELEBAR TEBAL HEBEL6. PM-100 YANG MENEMPEL PADA HEBEL YANG AKAN DIREKATKAN

SATU DENGAN YANG LAIN HARUS DALAM KONDISI BERALUR- ALUR AGAR PADA SAAT

DIREKATKAN DAN KEMUDIAN DIPUKUL-PUKUL DENGAN PALU KARET AKAN

MENGHASILKAN REKATANYA BENAR-BENAR RAPAT (TIDAK ADA CELAH)

Material Bata Ringan

LANGKAH 01

Siapkan sloof / balok dan periksa kerataan dan mutu pengecoran betonnya

Page 49: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 49/143

LANGKAH 02

LANGKAH 03

Siapkan sloof / balok dan periksa kerataan dan mutu pengecoran betonnya.

Tarik benang antara sudut-sudut dinding untuk menentukan posisi dan kerataan

dinding

Gunakan “Waterpass” untuk menyamakan ketinggian benang dan gunakan

“Theodolite” bila diperlukan.

Untuk lapisan dasar, gunakan Mortar atau setara. Tebarkan adukan tersebut secara

merata.

LANGKAH 04

Gunakan cethok untuk merapikan kelebihan adukan di sepanjang tepian.

Page 50: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 50/143

LANGKAH 05

LANGKAH 06

Letakkan blok yang sudah diberi Thin Bed mortar di ujung dinding tepat pada pertemuan benang.

Tekan hingga ketebalan adukan 10 mm. Periksa kembali level blok dengan menggunakan

“waterpass”. Lakukan langkah yang sama untuk setiap ujung dinding.

Untuk merekatkan bagian vertikal blok digunakan “Thin Bed Mortar”

LANGKAH 07

Setelah meletakkan blok pada masing-masing ujung dinding, letakkan blok lapis kedua dengan

“Thin Bed Mortar” Langkah ini penting untuk dudukan benang dan mencegah pergerakan blok di

Page 51: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 51/143

“Thin Bed Mortar”. Langkah ini penting untuk dudukan benang dan mencegah pergerakan blok di

ujung dinding pada saat meletakkan blok-blok lain pada lapis pertama.

Penting :

- Untuk pasangan blok Hebel harus menggunakan sistem Thin Bed Mortar, agar manfaat produk

beton ringan aerasi dapat diperoleh sepenuhnya.- Blok-blok dan panel Hebel di lokasi proyek harus dilindungi dari air dan hujan..

LANGKAH 08

Campur “Thin Bed Mortar” dengan air dalam sebuah ember. Penggunaaan “Mixer” akan menghasilkan

campuran adukan yang lebih baik Perbandingan “Thin bed mortar” dan air sesuai petunjuk pemakaian

Page 52: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 52/143

campuran adukan yang lebih baik. Perbandingan Thin bed mortar dan air sesuai petunjuk pemakaian

pada kemasan. Pada saat hari terasa amat panas, tambahkan sedikit lebih banyak air dari takaran

yang disarankan, untuk menhindari adukan cepat kering.

Bilamana campuran mulai mengering tambahkan air ke dalam bak dan aduk kembali. Sebelum mulai

campuran baru, bersihkan ember terlebih dahulu dengan air untuk mencegah adukan lamamempercepat waktu pengeringan campuran pasangan yang baru. Jangan menggunakan lagi adukan

sisa yang berjatuhan.

LANGKAH 09

Dengan menggunakan sikat halus, bersihkan permukaan blok setiap kali akan

memasang lapis baru..

Penting :

Bilamana suhu udara terasa sangat panas, celupkan sikat halus ke dalam air sebelum menyikat.

LANGKAH 10

Rentangkan benang dari ujung dinding ke ujung dinding yang lain Gunakan cethok

Page 53: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 53/143

Rentangkan benang dari ujung dinding ke ujung dinding yang lain. Gunakan cethok

khusus dengan lebar yang sesuai dengan lebar blok. Letakkan “Thin bed mortar” pada

arah vertikal terlebih dahulu, baru kemudian arah horisontal. Tebarkan adukan

secukupnya untuk satu blok saja. Pastikan pasangan “Thin bed Mortar” menutup

selebar permukaan blok.

LANGKAH 11

Pada saat meletakkan blok, angkat permukaan blok yang menghadap adukan vertikal

dan mulai letakkan sisi blok yang berlawanan terlebih dahulu..

LANGKAH 12

Page 54: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 54/143

Setelah blok diletakkan, rapatkan dengan palu karet secara merata. Langkah ini sangat penting

untuk mamastikan bahwa seluruh permukaan blok sudah tertutup dengan “Thin Bed Mortar”.

Pastikan palu jangan terlalu keras supaya “Thin Bed mortar tidak keluar. Jaga ketebalannya ( 1-2

mm setelah blok direkatkan).

Penting :

Bila hujan turun, lindungi permukaan atas blok dengan plastik

Kelebihan thin bed mortar pada permukaan dinding,

dibersihkan dengan menggunakan cethok biasa.

LANGKAH 13

Page 55: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 55/143

Bilamana ada penonjolan blok pada permukaan dinding, dapat diratakan dengan menggunakan

garukan perata (gambar a)

Pecahan blok dapat dimanfaatkan untuk meratakan kelebihan adukan (gambar b). Kalau

permukaan dinding akan ditutup dengan “Plasterboard”, maka yang diperlukan agar rata adalah

dengan menggunakan garukan perata/”leveling scraper”. Amplas tidak diperlukan.

Untuk menghaluskan permukaan yang luas, dapat menggunakan papan amplas (gambar C)

Page 56: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 56/143

Periksalah kelengkapan berikut :

Pelajarilah denah keseluruhan lokasi pemasangan kolom praktis beserta pelengkap (jika diperlukan), dalam skala 1:200, 1:50

dan 1:20 yang menggambarkan :

PEMBESIAN KOLOM PRAKTIS

PERSIAPAN

KEPERLUAN ALAT

MEMPELAJARI GAMBAR KERJA

Meteran

Kawat bendratGegep/kakatua

Palu & tang

Bor beton

Helm pengaman

Bar cutter 

Bar bender Gunting besi manual

Profil kayu kaso

Kunci besi

Sabuk pengaman

1. Posisi kolom praktis dan dimensinya

2. Letak pasangan batu bata

3. Detail Pembesian beserta diameter, ukuran dan jumlah besi.

4. Jarak kolom praktis As ke As.

1. Bersihkan area dimana akan dilakukan pemasangan kolom praktis dan sekitarnya.

2. Rangkailah besi tulangan kolom praktis dengan jarak yang sesuai dengan shop drawing,

ikatlah dengan sistem ikat satu arah dengan kuat, antara tulangan utama dan sengkang/beugeldengan menggunakan kawat bendrat. Jarak setiap sengkangnya dibuat seragam.

3. Persiapkan potongan besi d 10 sebanyak 8 buah, 4 buah untuk sisi atas pelat dan 4 buah

untuk sisi bawah pelat.

PELAKSANAAN PEMBESIAN KOLOM

Page 57: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 57/143

1. Buatlah marking posisi 8 stek penguat, 4 stek

pada pelat atas dan 4 stek pada bawah.

Bor pelat lantai atas dan bawah sampai

kedalaman 5cm pada sudutnya, kemudian

bersihkan lubang tersebut dan pasanglah stek

menggunakan epoxy, pastikan stek tidakgoyang.

2. Ikatlah antara besi kolom praktis dengan stek

penguat atas dan bawah menggunakan kawat

bendrat dan posisikan sehingga besi kolom

praktis berdiri tegak.

Stek Kolom Praktis

Kolom Praktis

Disambung dan Diikat Kuat

dengan Kawat Besi

Pasangan Dinding

Mempelajari Gambar 

Kerja

Pelajarilah denah keseluruhan lokasi pemasangan kolom praktis beserta denah pelengkap (jika diperlukan),

BEKISTING DAN PENGECORAN KOLOM PRAKTIS

Page 58: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 58/143

dalam skala 1:200, 1:100 dan 1:50 yang menggambarkan :

1. Bersihkan area dimana akan dilakukan bekisting dan pengecoran kolom praktis

2. Bekisting dibuat dari papan kayu plywood dengan ukuran yang sesuai dan jika menggunakan

plywood bekas, maka harus dibersihkan terlebih dahulu

Periksalah kelengkapan peralatan berikut :

PERSIAPAN

PELAKSANAAN BEKISTING DAN PENGECORAN KOLOM PRAKTIS

1. Letak dan tinggi pasangan batu bata

2. Dimensi dan ukuran kolom praktis

KEPERLUAN ALAT

Steger/tangga kerja

Dolak/alat takar

Meteran

Kawat bendrat

Gergaji

Sendok semen&roskam

Palu kayu&paku

Gegep

Helm pengaman

Gerobak

 Adukan beton(molen kecil)&sekop

Unting-unting(lot)

Kayu kaso

Ember

 Alat penampung adonan yang jatuh

Papan kayu plywood

Kotak kayu untuk tempat adukan sabuk pengaman

Sabuk pengaman

1. Bekisting 1 dipasang sesuai ketinggian pasangan bata dan bekisting 2 dipasang lebih rendah

dari pasangan bata. Kedua bekisting dilebihkan jarak 5cm pada sisi kanan dan kiri untuk

menutupi pasangan bata.

2. Tambahkan jendela dari papan kayu pada

bekisting 2 dengan kemiringan yang cukup

Page 59: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 59/143

bekisting 2 dengan kemiringan yang cukup,

kemudianlah ikatlah antara kedua sisi

bekisting dengan kawat bendrat pada atas,

tengah dan bawah bekisting. Pastikan kawat

bendrat terikat dengan baik.

3. Ukurlah dan cek vertikalitas bekisting kolom

praktis tersebut dengan dilot.

Campurlah adonan beton sesuai

spesifikasinya sampai adonannya rata dan

homogen.

Pasanglah alas untuk menampung adonan

yang jatuh, kemudian cor kolom praktis

dengan menuangkan adonan kedalamlubang bekisting, pada saat pengecoran ke

dua sisi bekisting dipukul-pukul dengan

palu agar beton nantinya tidak keropos.

6. Bekisting kolom praktis dapat dibuka setelah 8 jam.

7. Lanjutkan kembali pemasangan batu bata dengan

ketinggian max. 1,5 m (ulangi methode kerja pasangan

celcon) kemudian bekisting kolom praktis (langkah 1

sampai 5) dan ulangi kembali pengecoran (langkah 6)sampai kolom praktis selesai.

Mempelajari Gambar 

Kerja

P l j il h d h l h l k i di di k di l t b t d h l k (jik di l k )

Page 60: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 60/143

Pelajarilah denah eseluruhan lokasi dinding yang akan diplester beserta denah pelengkap (jika diperlukan),

dalam skala 1:200, 1:100 dan 1:50 yang telah menggambarkan :

• Steger / tangga kerja

• Molen kecil• Meteran

• Siku besi

• Ember 

• Palu & paku

• Waterpass

• Kawat ayam

• Benang

• Helm pengaman

Gerobak

Dolak/alat takar Unting-unting/lot

Kotak tempat adukan

Drum air 

Sendok semen&roskam

 Alat penampung adonan yang

 jatuh

Selang plastik

Jidar alumunium

Sabuk pengaman

 Alat Kerja

Periksalah kelengkapan peralatan berikut :

1.Posisi dan jarak pasangan dinding

2.Tebal plesteran dan detail material finishing padadinding

3.Letak kusen pintu dan jendela

PERSIAPAN

1. Umur pasangan batu bata minimal 1 hari (24jam) dan

dinding beton minimal 14 hari.

2 Bersihkan area plesteran dan permukaan dindingnya

5. Berilah marking bidang yang akan diplester dengan

memaku keempat sudutnya dan jika tidak

Page 61: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 61/143

2. Bersihkan area plesteran dan permukaan dindingnya

dari kotoran dengan sapu lidi.

3. Pada dinding beton, permukaannya terlebih dahulu

diciping atau dapat juga dikamprot dengan bahan tile

additive, lalu dibiarkan selama 24 jam sampai kering.

4. Apabila terdapat pertemuan antara dinding beton

dengan pasangan batu bata dan tidak ditentukan

dalam spesifikasi serta tidak ada tali air, maka

sepanjang pertemuannya dipasang kawat ayam

dengan cara dipaku.

ditentukan di spek, pakukan sudut atas 25m lebih

tinggi dari elevasi plafondnya.

Kemudian tariklah benang horisontal dan vertikal

dari paku satu ke yang lain. Jarak antara benang

dan permukaan dinding merupakan ketebalanplesteran nantinya.

6. Pasanglah alas kayu untuk menampung adonan

yang jatuh.

 A

C

B

D

7.Periksalah vertikalitas benang dengan dilot.

8. Tariklah benang berikutnya pada keempat sisi

bidang plesteran dengan jarak 5cm dan benang

Page 62: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 62/143

9. Persiapkan adukan plesteran sesuai

spesifikasi di dalam kotak kayu tempat adukan

atau menggukan molen kecil dan adonanharuslah rata, homogen dan tidak menggumpal.

Jika adonan terlalu kental, boleh ditambahi air 

sedikit selama umur adonan belum melebihi ½

 jam sejak awal pengadukan. Umur adonan dan

tidak boleh lebih dari 2jam, karena daya

rekatnya ,emjadi berkurang, oleh sebab itu,

buatlah adonan secukupnya.

g p g j g

horisontal dan vertikal selanjutnya ditarik dengan

 jarak antar benang 1,5m.

Kemudian siramlah dinding yang akan diplester 

dengan air bersih.

BENANG LOT

LOTAN

METERAN

PAKU BESAR

1. Buatlah caplakan pada setiap persilangan benang

Pelaksanaan Plesteran Dinding

2. Setelah membuat caplakan lepaskan benang

dengan paku hati-hati. Kemudian antara caplakan

tersebut buatlah klabangan horisontal atas dan

Page 63: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 63/143

dan ratakan permukaan adukan dengan sendok

semen sampai mencapai ketebalan yang

diinginkan (jarak antara benang dan permukaan

dinding)

1 mCAPLAKAN

tersebut buatlah klabangan horisontal atas dan

bawah saja serta kelabangan vertikal.

Permukaan adukan diratakan dengan jidar

alumunium dan roskam.

3. Pada pertemuan 2 dinding di sisi dalam,

buatlah salah satu klabangan mepet dengan

4. Sebelum melaksanakan plesteran, cek

kelembaban pada dinding yang akan diplester 

Page 64: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 64/143

buatlah salah satu klabangan mepet dengan

siku dalam pada dinding, dan berkaitan jarak

5cm untuk klabangan dinding berikutnya.

p g y g p

dan jika diperlukan siram lagi dinding dengan air 

bersih. Lakukan plesteran dengan mengguinakan

sendok semn atau roskam, ratakan serta

padatkan permukaan dengan jidar aluminium.

Pada pertemuan anatra sudut, plesteran dibuatdengan lurus.

Page 65: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 65/143

1

- Check kondisi real kondisi, di lapangan dan buat

shop drawing- Tentukan posisi start point dalam shop drawing dan

mintalah persetujuan dari pengawas/MK

- Terapkan posisinya start point yang sudah disetujui

dilapangan sebagai contoh lihat gambar dibawah ini.

1.Palu karet2.Zidar / water pass

3.Besi siku4.Benang nylon5.Ember dan gayung6.Skrap7.Sapu8.Spon basah / kain basah

 ALAT YANG DIPERLUKAN :

JIDAR / WATERPASS3BENANG NYLON

2

Page 66: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 66/143

- Pemasangan berikutnya dilaksanakan dengan cara mengeser benang

nylon sejajar dengan salah satu sumbu kepalaan

1.Check terhadap elevasi lantai pada saatmembuat

kepalaan awal

2.Pasir yang digunakan harus diayak agarmendapatkangradasi material yang seragam

3.Air yang digunakan memenuhi syarat sebagai air minum

4.Sebelum dipasang keramik harus direndam dalam air 

dahulu sampai jenuh

5.Pada saat pemasangan keramik harus dipastikan bahwa

spesi yang terletak dibawah keramik benar-benar padat

tidak berongga

dengan cara dipukul – pukul dengan palu karet

6.Pemasangan keramik dapat juga dengan cara

menggunakan lem (tergantung permintaan spek)7.Check kerataan pasangan keramik dengan jidar 

atau pun dengan water pass

HAL – HAL YANG PERLU DIPERHATIKAN :- Pasang keramik menurut salah arah sumbu kepalaan

 BENANG NYLON 

 DI GESER

 BENANG NYLON 

CONTOH DENAH

 BENANG NYLON 

 DI GESER

1

Page 67: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 67/143

- Pasang keramik dengan posisi as

keramik sama dengan CL

- Buat kepalaan dari keramik secara

horizontal dan vertikal

- Selanjutnya pelaksanaan

pemasangan keramik mengikuti alur 

kepalaan

- Pemasangan lapis berikutnya selalu

dimulai dari tengah dinding kearah kiri

dan kekanan

 A

B

d1 d2

CL

 ARAH PEKERJAAN

- Cari CL (center line) dari dinding a1 =

d1=d2

- Buat titik A dan B dimana elevasi titik

 A=elevasi titik B setinggi ukuran keramik

yang akan dipasang

- Hubungkan titik A-B dengan benang

nylon

1

2

 ARAH PEKERJAAN - Diharapkan pada posisi-posisi sudut tembok merupakan daerah

buangan keramik yang simetris

- Lebar sisa buangan A = lebar buangan B

3

Page 68: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 68/143

1.Sebelum dipasang keramik harus direndam dalam air sampai jenuh

2.Pemasangan keramik harus urut mengikuti kepalaan vertikal yang sudah dibuat sebelumnya.

3.Pastikan tidak ada celah / rongga pada spasi antara keramik dantembok dengan cara memukul-mukul keramik sampai denganBunyi yang seragam dan padat pada semua bagian

4.Pemasangan dinding keramik dapat jugadilaksanakan dengan menggunakan lem keramik (tergantungpermintaan spek)

5.Pasir yang digunakan harus diayak dahulu untuk mendapatkangradasi material yang seragam

6.Gunakan water pass / jidar untuk mengontrol kerataanpermukaan keramik yang terpasang

7.Air yang digunakan tidak boleh mengandung asam (bebas daripengaruh asam).

KAPASITAS PRODUKSI :- 1 TUKANG- 2 KENEK 

HAL –HAL YANG PERLU DIPERHATIKAN :

12 m² / Hari

SISA BUANGAN SAMA BESAR

Lebar sisa buangan A lebar buangan B

Catatan : Untuk kondisi buangan yang terlalu kecil, pemasangan

keramik dapat di mulai dari sisi tepi.

1. Pemasangan kepalaan mulai dari sisi tepi bidang.

2. Pemasangan selanjutnya mengikuti arah ke sisi lain

bidang (ke arah kanan)3. Didapat sisa buangan yang cukup besar (lebih dari ¼

lebar keramik).

Untuk lebih pasti shop drawing harus terlebih dahulu

disetujui oleh konsultan.

P ik l t / d h l it P ik khi l t i t t d l t i tid k l l

Page 69: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 69/143

1

2

3

4

5

6

8

9

10

11

712

Periksa lay-out / denah, pola granit

/marmer, detail-detail khusus, bentuk

pinggulan serta area mana saja yg ada

finishing granit/marmer dan gambar telah

dikoordinasikan dengan M/E.

Periksa area yg di syaratkan anti-slip

granit/marmer atau tipe khusus pada area

tertentu

Periksa warna, ukuran,pattern(urat), bentuk dan tipe

granit/marmer, sortir seperti yang disetujui. dan kelompokkan

material yang seragam/uniform harus mencukupi hiasan bidang-

bidang yang akan dipasang.

Periksa tipe grout dan warna seperti yang disetujui.

Periksa pembuatan mockup

Periksa granit/marmer dinding dipasang sebelum granit/marmer

lantai.

Periksa waterproofing telah dipasang sesuai persyaratan.

Periksa pengakhiran lantai terutama pada lantai yang tidak selevel

atau ada perbedaan material ,memakai threshold vinyl, metal strip

atau sejenisnya.

Periksa kemiringan screed/lantai kearah pembuangan pada tempat

yang lebih rendah.

Periksa tipe dan lokasi expansion joint

sesuai persyaratan.

Pada sistem acian/adhesive, landasan screed

yang dipasang harus padat, tidak keropos dan

tidak retak.

Periksa pemasangan granit/marmer bahan perekatnya dapat

menggunakan latex cement atau epoxy atau acian (tanpa gypsum) sesuai

persyaratan. Granit/ marmer dipukul agar lebih melekat dan bahan

perekat yg menempel segera dibersihkan sebelum setting/keras.

1.

Page 70: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 70/143

2.

3.

4.

5.

6.

8.

9.

Tentukan elevasi plafond dan buat garis

sipatan pada dinding & as sumbu ruangan.Pasang rangka hollow tepi tepat pada sipatan.

Tentukan jarak penempatan hollow

pengantung

Pasang rangka utama

Pasang panel gypsum

1

2

3

4

5

6

7

8

Pasang benang untuk pedoman penentuan

titik paku penggantung untuk menjamin

kelurusan.

Pasang rangka pembagi.

9 Tutup sambungan antara panel gypsumdengan paper tape dan compound lalu

diampelas dan finish dengan cat

Cek kerapihan dan kerataan bidang plafond.

7.

PERTEMUAN ANTAR PANEL GYPSUM

Page 71: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 71/143

METHODE PEMASANGAN COMPOUND PADA

GYPSUM BOARDLakukan pelapisan pada petemuan bidang panel dengan compound

Dilanjutkan dengan penempelan paper tape pada lapisan

compound.

Lapiskan kembali compound menimpa paper tape4 Tunggu sampai kering lalu haluskan permukaan dengan hand sander 

dan grit paper 150/120

3

1

2

1. POTONG UJUNG LIST PROFIL PLAFONDB G G P

Page 72: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 72/143

SISTEM SAMBUNGAN LIST PROFIL

MIRING 45 DERAJAT 

SAMBUNGAN

UNTUK SAMBUNGAN, GUNAKAN MAL PO-

TONG DENGAN SUDUT KEMIRINGAN 45DERAJAT.

KEPALA PAKU PIPIH

PERMUKAANLIST YANGMENEMPEL

PADA PLAFOND

UJUNG PAKURATA

2. SEBELUM LIST PROFIL PLAFOND DIPASANG,PAKU LIST PROFIL PLAFOND DENGAN PAKU

YANG KEPALANYA TELAH DIPIPIHKAN HING-GA UJUNG PAKU RATA DENGAN PERMUKA-AN LIST PROFIL YANG MENEMPEL PADA

PLAFOND.

PEMASANGAN PAKU SEBELUM

LIST DIPASANG

3. PASANG BENANG UNTUK PEDOMAN PEMA -

SANGAN LIST PROFIL PLAFOND TARIKAN

4. PASANG / TEMPELKAN LIST PROFIL PLAFOND PADA POSISINYADENGAN ACUAN BENANG AWAL PEMASANGAN DIMULAI DARI

Page 73: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 73/143

SANGAN LIST PROFIL PLAFOND, TARIKAN

BENANG MAKSIMUM 7 M UNTUK MENGHIN-

DARI LENDUTAN.

LIST 

PROFIL

BENANG

DENGAN ACUAN BENANG, AWAL PEMASANGAN DIMULAI DARI

SALAH-SATU UJUNG. ( SAMBUNGAN HARUS RAPAT & RATA ).

DETAIL PEMASANGAN LIST

PROFIL PLAFOND

RANGKA PLAFOND

LISTPROFIL

DINDING

5. MASUKKAN/PUKUL KEPALA PAKU DENGAN DRIP AGAR KEPALA PAKU

MASUK ( TIDAK KELIHATAN ).

6. DEMPUL LUBANG-LUBANG BEKAS PAKU DAN SAMBUNGAN.

7. DEMPUL LUBANG-LUBANG BEKAS PAKU DAN SAMBUNGAN.

8. SELESAI

BACK

Page 74: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 74/143

QUALITY

 ASSURANCE

Semua aktifitas terencana dan sistematis yang di implementasikan

dalam suatu sistem mutu untuk memberikan keyakinan bahwa

proyek akan memenuhi standard mutu yang relevan

QUALITY CONCEPT

ZERO DEFECT : Tidak ada toleransi atas kesalahan didalam sistem. Tujuan dari semua proses adalahmenghindari cacat pada produk atau jasa.

Pelanggan adalah seseorang dekat anda berikutnya dalam

suatu proses. Do the Right Thing Right the First Time

 Adalah lebih mudah dan lebih murah mengerjakan

pekerjaan yang tepat pada saat awal dari pada

melakukannya untuk kedua kalinya.

Continuous Improvement Process (CIP)

Mengakui bahwa dunia selalu berubah secara konstan dan

setiap proses yang hari ini telah memuaskan mungkin tidak

akan memuaskan lagi pada esok hari.

Project Quality Management

Page 75: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 75/143

1.Quality Planning

2.Quality Assurance

3.Quality Control

PROCESS PLANNING PROCESS EXECUTING PROCESS CONTROLLING

Perencanaan mutu proyek,sesuai spesifikasi & sistempengujian/test, tertuangdalam PQP

Pelaksanaan Sistem Mutu,baik secara sistem maupunteknis mutu pelaksanaan

Pemantauan Sistem Mutu, padaproses pelaksanaan, in coming , in

 process, final process. Untukmemastikan tercapainya mutu

pelaksanaan

Audit Mutu InternalPelaksanaan Audit Mutu Internal

Page 76: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 76/143

Proses : 

PROSES

KONTROL

OUTPUT

SUMBER DAYA

INPUT

• Material

• Informasi

• Prosedur • Spesifikasi

• Training/kualifikasi

• Sasaran/target

• Peralatan

• Orang

• Sasaran

• Kualitas produk

ISO 9001 : 2000Sections 1 - 4 covers scope, exclusions and general quality management system requirements.

Seksi 1 4 mencakup ruang lingkup pengecualian dan persyaratan umum sistem manajemen

Quality Management System Requirements

Page 77: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 77/143

INPUT PROCESSESINPUT OUTPUT

5. Management ResponsibilityTanggung jawab Manajemen

6. Resource ManagementManajemen Sumber Daya

7. Product Realization

Realisasi Produk 

8. Measurement, Analysisand Improvement

Pengukuran, Analisis danPenyempurnaan

Seksi 1 - 4 mencakup ruang lingkup, pengecualian dan persyaratan umum sistem manajemen

mutu.

Management Responsibility

Resource Management

Product Realization

Measurement, Analysis and Improvement

Continual Improvement of theQuality Management System

Page 78: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 78/143

ManajemenSumber Daya

 Input 

Tanggung JawabManajemen

PerwujudanProduk 

Produk 

Output 

Pengukuran, Analisa danPeningkatan

Kegiatan Pertambahan Nilai

 Aliran Informasi

PLAN

DO

 ACTION

CHECK 

Tahapan “Quality Control”untuk mencegah ketidaksesuaian pada setiap tahapan, maka perlu dilakukan pengendalian pada setiap kondisi

Page 79: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 79/143

Incoming Control

Pengendalian Pada setiap

Permulaan Kerja dan

Kedatangan bahan

In process Control

Pengendalian Pada setiap

Proses Pekerjaan

Final Control

Pengendalian Pada Akhir 

Proses Pekerjaan

Initial Control

Pengendalian Parameter 

Quality (Spesifikasi, Job

Mix, Test Material, Dsb)

KESESUAIAN PRODUK

1

2

3

4

1. Initial Control

Pengendalian ‘quality’ paling awal dari semua tahapan konstruksi yang ada.

Page 80: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 80/143

Initial Inspection lebih dominan sebagai Engineering Process

 – Pemahaman design (Posisi, Dimensi, Quantity dan BentukRencana)

 – Pemahaman Spesifikasi (Karakter Material Rencana)

 – Persetujuan Material ( Test Sample Material, Brosur-brosur,

Mock Up,)

 – Pembuatan Job Mix Formula (Beton,Mortar)

 – Proposal Justifikasi Teknis (Design Usulan/Alternatif &Hitungan Teknis Jika Ada)

 – Persetujuan Shop Drawing/Gambar Kerja lapangan

 – Persetujuan RENCANA MUTU KONTRAK

PIC Quality – Initial Control

Engineering (Design, Justek, Shop Drawing), Procurement

(Persetujuan Material), Laborat (Test Sample Material, Job Mix

Formula)

2. Incoming ControlPengendalian Pada saat Permulaan Kerja dan Kedatangan Bahan

Page 81: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 81/143

• Permulaan Kerja

 – Uitzet Posisi, Bentuk, Dimensi Pekerjaan, dibandingkan terhadap rencana

• Kedatangan Material

 – Pemeriksaan Material datang, dibandingkan dengan Material Contoh

(Visualisasi/Bentu k/Warna, Dimen si/Ukuran, Merk, Type, Serial dsb) 

 – Pemeriksaan Proses Produksi Material, dibandingkan dengan Job Mix

(Beton Ready Mix, Factory Visit untuk material Pabrikan ds b) 

 – Test Berkala terhadap material datang (cara acak/sampling)

(Slump Test, Test Baja tulangan ds b) • PIC Quality

Procurement (Pemeriksaan Material), Laborat (Proses Produksi & Test Berkala)

Superviser (Uitzet Posisi, Bentuk dan Dimensi)

• Dimungkinkan penggunaan alat penguji, sample pembanding

3. Inprocess Control

Pengendalian Pada setiap Proses Pekerjaan

Page 82: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 82/143

• Checking Kesesuaian dengan Shop Drawing

• Checking Kesesuaian dengan Mock Up

• Checking Kesesuaian hasil penghamparan Aspal• Dilakukan secara Kontinu -  Checking

• PIC Quality

Superviser dan Quality Officer 

4. Final Control

Pengendalian Pada Akhir Pekerjaan

• Checking Hasil Akhir Mutu Beton

• Checking Ketebalan Aspal (Core drill)

• Checking Kadar Aspal (Extrac)

• PIC Quality

Superviser dan Quality Officer 

Page 83: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 83/143

Quality Control sebagai Tujuan

Inspeksi dan Test sebagai Alat/Parameter Pencapaian

FLOW CHART PEMERIKSAAN BESI BALOK LAPANGAN

MULAI

Page 84: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 84/143

JUMLAH BESI

CHECK BESI BALOK 

SELESAI

TAMBAH BESI

GANTI SESUAI SHOP DRAWING

TIDAK SESUAI

OK 

OK 

TIDAK SESUAICHECK DIAMETER 

BESI

CHECK JARAK 

JARAK ANTAR BESI

CHECK POSISI

TULANGAN

DI PERBAIKIOK 

DI PERBAIKI OK 

TIDAK SESUAI

TIDAK SESUAI

FLOW CHART PENGECHECKAN BESI KOLOM

MULAI

Page 85: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 85/143

CHECK BESI KOLOM

SELESAI

DITAMBAH

DIGANTI

TIDAK SESUAI

SESUAI

TIDAK SESUAI

CHECK JUMLAH

CHECK DIAMETER 

CHECK TERHADAP

POSISI

DI PERBAIKI

SESUAI

SESUAI

TIDAK SESUAI

FLOW CHART CHECK PEMBESIAN BESI PLAT

MULAI

Page 86: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 86/143

CHECK BESI PLAT

SELESAI

DI PERBAIKI

DIGANTI

TIDAK SESUAI

SESUAI

TIDAK SESUAI

CHECK JARAK 

CHECK DIAMETER 

CHECK TERHADAP

OVERLAP

DI PERBAIKI

SESUAI

TIDAK SESUAI

FLOW CHART PEMERIKSAAN BEKISTING

MULAI

Page 87: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 87/143

BEKISTING BALOK,KOLOM,

PLAT

SELESAI

DI PERBAIKI

PERBAIKI

TIDAK SESUAI

SESUAI

TIDAK SESUAI

CHECK TERHADAP

POSISI

CHECK DIMENSI

CHECK TERHADAP

ELEVASI

DI PERBAIKI

SESUAI

TIDAK SESUAI

SESUAI

FLOW CHART PENGENDALIAN MUTU BESI

MULAI

Page 88: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 88/143

CHECK MILL SHEET

BESI SAMPAIDI SITE

DIPRODUKSI

SELESAI

TEST BESI

GUDANG

TOLAK 

TOLAK DIKEMBALIKANKE PABRIK 

TIDAK MASUK 

MASUK 

MASUK 

TIDAK MASUK 

FLOW CHART PEMELIHARAAN BETON

MULAIMULAI

Page 89: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 89/143

BUAT TANGGULKELILING TEPI PLAT

BETON PLATHASIL COR 

RENDAM DENGAN

 AIR PBI. 14 HARI

SELESAI

BUNGKUS KOLOMDENGAN KARUNG

BETON KOLOMHASIL COR 

SIRAM KOLOM DENGAN

 AIR MIN 3X SEHARI

SELESAI

FLOW CHART PENGENDALIAN MUTU BETON

MULAI

Page 90: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 90/143

CHECK SLUMP BETON

BETON READY MIXDI SITE

COR BETON

SELESAI

BENDA UJI

TOLAK 

RENDAM

TIDAK MASUK 

MASUK 

TEST SESUAI

UMUR 

Periode Check List  Periode

Serah Terima I

Periode

Serah Terima II

Page 91: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 91/143

YES

START

PERSIAPAN

PEMBERITAHUAN CHECK LIST I

REPAIR DC

YES

NO

1

2

3

CHECK LIST I

4

5

CHECK LIST II8

BERITA ACARACLOSE REPAIR DC

6

REPAIR AK7

NO

SERAH TERIMA I

RECORD I

Serah Terima I

MAINTENANCE PERIOD

SERAH TERIMA II

RECORD II

Serah Terima II

11

12

13

9

10

Manajemen Pengendalian Gambar Konstruksi

DETAIL RENCANA KONSULTAN PEMILIK KONTRAKTOR  

a. Persetujuan GambarPelaksanaan ( Shop Drawing )

Page 92: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 92/143

RENCANAPELAKSANAANINSTRUKSI UNTUK

MEMBUAT GAMBARPELKSANAAN

MEMBUATGAMBARPELAKSANAAN

EVALUASI

BUTUHEVALUASIRENCANA 

PEMERIKSAANEVALUASIOLEH PIHAK YANGBERSANGKUTAN

TIDAK 

PERSETUJUAN A / B / C / D

R E K O M E N D A S IOLEH PIHAK YANGBERSANGKUTAN

 YA 

COPY 

DISTRIBUSIOLEH PIHAK YANGBERSANGKUTAN

DISTRIBUSI KE PROSESPELAKSANAAN

 YA 

DISTRIBUSI

PERSETUJUAN A / B / C / D

TIDAK 

TIDAK 

 A 

KETERANGAN :

= DISETUJUI

= DISETUJUI DENGAN CATATAN–TDK PERLU PENGAJUAN LAGIB

= PENGAJUAN LAGI SETELAH DI REVISI

= TIDAK DISETUJUI

C

D

DETAIL RENCANA KONSULTAN PEMILIK KONTRAKTOR  

KOORDINASIPEKERJAANSELESAI 100%

 b. Persetujuan As Built Drawing

Page 93: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 93/143

DIPERIKSA 

1 COPY 

 AS BUILTDRAWING

1. INSPEKSI2. DISTRIBUSI

2 COPY + ASLI 1 COPY 

Max.7 Hr

REVISI

PERSETUUANCETAKBIRU

RENCANA DETAIL KONSULTAN PEMILIK KONTRAKTOR  

INSTRUKSI RENCANA

Manajemen Pengendalian Pengadaan Material

Page 94: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 94/143

INSTRUKSI

CONTOHMATERIAL

EVALUASI

MATERIALDENGANPERSETUJUAN

PELAKSANAAN

PERSETUJUAN

RENCANAKERJA 

TIDAK 

 YA 

PERSETUJUAN

Page 95: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 95/143

Page 96: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 96/143

Page 97: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 97/143

BACK

Page 98: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 98/143

form work/pekerjaan struktur

railing perimeter

safety net perimeter

2 lantai

safety wing net

temporary railing

polynet

TUJUAN UTAMA K3L

1. Menghilangkan atau mengurang bahaya kerja, kecelakaan kerja dan atau mencegah

 jatuhnya korban serta penyakait akibat kerja.

Page 99: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 99/143

j y p y j

2. Melindungi aset dan lingkungan terhadap kerusakan yang diakibatkan oleh adanya

aktifitas pekerjaan.3. Menjamin tidak terjadinya kerusakan pada lingkungan ditempat kerja dan kerusakan

lingkungan akibat pelaksanaan proyek.

4. Memastikan penerapan SMK3L sesuai persaratan Permenaker RI PER05/MEN/1996

dan OHSAS 18001:1999 serta ISO 14001:1996.

PERENCANAAN K3L

PENERAPAN DAN

OPERASI

PENGUKURAN

KINERJA AUDIT PERENCANAAN

POLICY

Sistem Manajemen K3L

• Merupakan suatu rangkaian proses kegiatan K3 yang memiliki siklus dimulai dari

kegiatan PERENCANAAN IMPLEMENTASI PEMANTAUAN dan PENINJAUAN

Page 100: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 100/143

kegiatan PERENCANAAN , IMPLEMENTASI, PEMANTAUAN dan PENINJAUAN

KEMBALI .

• Prinsip dasar manajemen perbaikan melalui siklus Plan – Do – Check -Action.

• Rangkaian merupakan rangkaian tertutup yang mengandung spirit PERBAIKAN

BERKESINAMBUNGAN …..

TARGET K3L PROYEK

ZERO ACCIDENT

WAJIB HELM & APD

MATERIAL TERTATA RAPI

PROYEK BERSIH DAN SEHA

SAFETY PROGRAMME

Page 101: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 101/143

GOALS SAFETY

INDUCTION

SAFETY

INSPECTIONEQUIPMENT

INDUCTION

TOOL BOX

MEETING

SAFETY

PATROL &

MEETING

FOGGING

 AND

GENERAL

CLEANING

TRAINING

SAFETY

MONTHLY

REPORT

Zero

 Accident All Staff &

Employee /

Worker 

Daily by Safety

Officer Bi - Weekly Weekly

Morning

Time

Monthly Bi - Weekly Basic Safety

Fire Fighting

First Aid

Rigging

Welding

Recorded

by

Division

Office

* TARGET

 Target untuk kecelakaan yang ingin di capai oleh PT. ADHIKARYA (Persero ) Tbk adalah tidak ada fatality dalam setiapkegiatan proyeknya. ( Target Zero Accident)

* SAFETY INDUCTION

Page 102: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 102/143

* SAFETY INDUCTION

Pemberian Pengenalan peraturan safety proyek kepada setiap

karyawan dan sub kontraktor serta mandor yang terlibat dalamperoyek ini untuk partisipasi dan tanggung jawab terhadapkeselamatan kerja oleh semua pihak.

* TOOL BOX MEETING.

Memberikan penjelasan mengenai pentingnya keselamatankerja dalam bekerja pada bidang konstruksi bangunan danmemberikan informasi   –   informasi lapangan kepada pekerja

mengenai daerah bahaya, penanggulangan dan hal lainnya yang berkaitan yang akan diadakan setiap kamis pagi sebelumbekerja.

* SAFETY MONTHLY MEETING

Mempersentasikan hasil yang telah dicapai setiap bulannyakepada top management perusahaan dan subkont dan untuk menarik dukungan terhadap keselamatan kerja dari semua top

management setiap 1 kali sebulan tiap hari kamis.

BRIEFING LAPANGAN

RAPAT MINGGUAN

 APEL PAGI

* SAFETY INSPECTION

Melakukan inspeksi pada setiap kegiatan, lingkungan dan peralatanyang memungkinkan untuk terjadinya kecelakaan dan melakukantindakan pencegahannya secara langsung serta membuat sistempelaporan.

* SAFETY PATROL

Page 103: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 103/143

*   SAFETY PATROL.

Melakukan patrol tiap senin siang bersama semua topmanagement ke lapangan untuk mengetahui permasalahankeselamatan kerja di lapangan.

*   FOGGING

Penyemprotan nyamuk di lapangan untuk mencegah penyakit yang dapat ditimbulkan oleh serangga dan sejenisnya sebagai salah satukepedulian kami terhadap kesehatan pekerja

tiap hari sabtu sore.

*   GENERAL CLEANING AND HOUSE KEPPING.

Melakukan pembersihan secara masal yang melibatkan seluruhpekerja dan seluruh subkontraktor di lapangan untuk menciptakanlapangan kerja yang selalu bersih dan rapih setiap sabtu siang.

SAFETY PATROL

FOGGING

GENERAL CLEANING

PROGRAMME JOB DESCRIPTION PIC

Page 104: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 104/143

1. DAILY

ACTIVITY

1. Introducing Health & Safety Work ti all Staff & Warkers Safety Manager 

Safety Staff & Daily Worker 

2. Briefing on daily programme Safety Manager  

Safety Officer 

3. Safety Patrol Safety Manager  

Safety Officer 

Security

4. Safety ( K3 ) Daily Report Safety Officer  

5. Cleaning Inspection Safety Officer  

6. Monitoring Site & Surrounding Security Safety Manager  

Safety Officer 

Security

7. First Aid Safety Staff  

PROGRAMME JOB DESCRIPTION PIC

1. Tool Box Meeting Safety Staff

Page 105: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 105/143

2. WEEKLY

ACTIVITY

Evaluating Last Week Programme All Site Staff

Next Week Work Programme All Workers

2. Safety Inspection Safety Manager  

Safety Officer 

Security

Supervisor 

Sub Contractor 

3. General Cleaning All Workers

4. Management Review Meeting ( Every Wednesday ) Safety Supervisor 

5. Fogging depend on Site Conditions ( if necessary ) Safety Supervisor 

6. Coordination with Surrounding Hospital, Depnaker and Safety Officer 

Insurance Company ( Temporary ) Each Sub Contractor  

7. Coordination with Project Stakeholders Safety Manager  ( Owner/Employer, Engineer, NSC )

Page 106: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 106/143

PROGRAMME JOB DESCRIPTION PIC  

3. MONTHLY

1. Safety Report Safety Manager  

ACTIVITY

2. General Safety Inspection Safety Manager  

Safety Officer 

Other Manager 

3. Varius Job Safety Staff  

RAMBU

Pemasangan rambu dalam proyek yang berisikan pesan berupa larangan, perhatian, ataupun anjuran

yang bertujuan untuk menertibkan setiap orang yang berada di dalam areal proyek, baik itu pekerja

ataupun tamu yang datang agar tertib dalam K3L.

IMPLEMENTASI K3L DI PROYEK

Page 107: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 107/143

PINTU MASUK JALAN UTAMA PINTU MASUK

PROYEKSPANDUK

Pemasangan spanduk dalam proyek yang berisikan informasi berupa informasi tertentu ataupun tata tertib

bertujuan untuk menertibkan setiap orang yang berada di dalam areal proyek agar tertib dalam K3L.

GERBANG JALAN KERJA TATA TERTIB PROYEK ANJURAN ATURAN

SAFETY SIGN( Rambu-rambu K3L)

Page 108: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 108/143

Page 109: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 109/143

Wujud kasih sayang kita kepada keluarga adalah bekerja

sesuai dengan petunjuk kerja aman dan tidak ceroboh

Pelajari, pahami Buku Panduan K3 ini.

Camkan mana yang terkait dengan pekerjaan yang akan

Page 110: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 110/143

sesuai dengan petunjuk kerja, aman dan tidak ceroboh.

Kita adalah tumpuan harapan keluarga.

Camkan mana yang terkait dengan pekerjaan yang akan

dilakukan dan laksanakan sesuai petunjuk kerja.

Kecelakaan kerja lebih sering terjadi di bidang industri

konstruksi dibandingkan bidang lain dan karena itulah

Tidak adanya kekompakan di antara rekan sekerja lapangan

seringkali menjadi penyebab terjadinya kecelakaan. Setiap

k h i t b h

Page 111: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 111/143

konstruksi dibandingkan bidang lain, dan karena itulah

perusahaan menyediakan sarana keselamatan untuk

mencegah terjadinya kecelakaan pada diri anda. Tetapi

yang paling dibutuhkan adalah kerjasama anda. Anda

harus sungguh-sungguh mematuhi semua peringatan

yang tertera dalam Buku Panduan ini agar tempat kerja

anda aman dan menyenangkan!

karyawan harus ingat bahwa :

Kita semua adalah bagian dari kelompok

Kita harus sealu saling membantu

Kita harus selalu mengalah pada rekan satu kelompok kerja

Kita harus selalu saling memberi salam saat masuk kerja pada pagi

hari dan saat kita pulang

Patuhi dengan sungguh-sungguh peraturan keselamatan

kerja yang ada di lokasi (berbagai peringatan dan aturan

rutin). Undang-undang nasional menyebutkan bahwa “Pekerja

harus mematuhi peraturan yang dibuat untuk mencegah

terjadinya kecelakaan kerja dan harus bekerjasama dalam

Dengarkan baik-baik penjelasan yang disampaikan oleh

mandor anda, atau atasan anda lainnya, mengenai kondis

tempat kerja anda saat ini dan pahami semua yang

Page 112: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 112/143

mengambil langkah-langkah pencegahan kecelakaan kerja

yang ditetapkan oleh perusahaan dan pihak-pihak lain yangberkepentingan.”

Undang-Undang tersebut juga menharuskan karyawan

mematuhi ketentuan tentang pemakaian helm proyek, sabuk

pengaman dan masker pernapasan. (Pasal 26, Undang-

Undang Kesehatan dan Keselamatan Kerja).

tempat kerja anda saat ini dan pahami semua yang

dikatakannya.

Kenali tempat-tempat yang membahayakan, jalur yang aman

tempat mengamankan diri.

Caritahu lokasi alat pemadam api dan peralatan P3K

Selalu hadiri pertemuan harian di lokasi kerja yang membahas

masalah keselamatan saat upacara pagi dan pertemuan pada

akhir jam kerja.

<Siklus Mingguan>

P b ih k j b

Setiap hari sebelum mulai bekerja, patuhi ketentuan mewaspadai

bahaya, dan :

Semua orang bersama-sama memikirkan cara mewaspadai bahaya.

Page 113: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 113/143

Pembersihan tempat kerja bersama-sama

<Siklus Bulanan>Inspeksi bulanan, dll.

Diskusikan langkah-langkah yang harus ditempuh.

Tetapkan prosedur kerja paling aman yang akan dipakai.

Setiap karyawan harus berpakaian dengan rapih.

Selalu kenakan baju kerja yang bersih.

Jahit bagian baju yang robek dan lepas jahitannya, dll.

Helm pengaman harus selalu ada pakai. Luka di kepala bisa

membahayakan diri anda!

Tali pengikat helm pengaman harus selalu terpasang dengan baik

dan kencang

Page 114: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 114/143

Ujung kemeja dan celana harus selalu terkancing dengan baik.

Pakai selalu sepatu yang aman sesuai jenis pekerjaan anda atau

pakai sepatu cats yang mempunya sol anti selip.

Helm harus dipakai dengan posisi yang benar dan jangan dipakai dibelakang kepala.

Selalu kenakan sarung tangan pengaman sebagaimana

diwajibkan ketika mengangkut barang berat di lokasi kerja.

Pilih sarung tangan yang sesuai dengan jenis pekerjaan anda.

(Gunakan sarung tangan tahan getar untu pekerjaan vibrasi).

Selalu gunakan sabuk pengaman jika anda bekerja di tempat tinggi yang

tidak berlantai atau berbagar, atau ketika anda bekerja di tempat yang

mewajibkan pengunaan sabuk pengaman.

Sabuk pengaman harus dikaitkan ke kabel yang sudah terpasang baik

Page 115: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 115/143

(Gunakan sarung tangan tahan getar untu pekerjaan vibrasi).

Jangan kenakan sarung tangan jika mengoperasikan bor listrik.Sabuk pengaman harus dikaitkan ke kabel yang sudah terpasang baik.

Jika anda bekerja sambil berpindah-pindah, pastikan bahwa kabel dalam

keadaan tegang sebelum sabuk pengaman anda pasangkan

Sabuk pengait tunggal hanya boleh digunakan dengan cara yang sudah

ditetapkan perusahaan.

Di tempat kerja banyak terpasang rambu-rambu untuk

keselamatan anda. Pelajari apa arti masing-masing rambu

dan bekerjalah dengan hati-hati!

Selalu kenakan peralatan pelindung yang sesuai dengan jenis

pekerjaan anda saat berada di lokasi.

Selalu kenakan kacamata las jika bekerja dengan alat las listrik

Page 116: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 116/143

Jangan merusak rambu atau memindahkannya ke tempat

lain.

atau gas atau alat pemotong.

Kenakan masker anti debu dan kacamata pelindung debu saatmelakukan pekerjaan yang menghasilkan debu.

Jika pekerjaan yang anda lakukan menimbulkan suara yang

keras, kenakan penutup telinga.

Di tempat kerja, telah ditetapkan berbagai sinyal/tanda-

tanda untuk digunakan. Pelajari apa arti masing-masing

sinyal/tanda-tanda dan patuhi sinyal/tanda-tanda yang

diberikan oleh siapapun yang ada di lokasi.

<Untuk jenis jenis pekerjaan dibawah ini telah ditetapkan

Selalu gunakan jalur orang yang telah ditetapkan

meskipun anda sedang terburu-buru!

Jalur orang yang tinggi letaknya, balok penyangga dan

tangga harus selalu dalam keadaan aman untuk

di k i

Page 117: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 117/143

<Untuk jenis-jenis pekerjaan dibawah ini telah ditetapkan

sinyal/tanda-tanda tertentu>

Mengangkut barang dengan

tali baja.

Saat menjalankan kendaraan

konstruksi dan memindahkan

crane, dsb.

Saat mengoperasikan lift dan

katrol.

Pekerjaan dengan

menggunakan tekanan tinggi

Pekerjaan peledakan batu

dipakai

Jangan biarkan ada barang-barang yang menghambat

gerak di jalur yang dilalui orang.

Pindahkan semua hambatan yang ditemui.

Pastikan bahwa barang-barang ditumpuk dengan baik agar

tidak berjatuhan.

Jangan menumpuk barang terlalu tinggi

Barang-barang yang ukurannya panjang tidak boleh diletakan

Semua barang yang mudah menggelinding harus diberi

penahan atau diikat agar tidak bergerak dari posisinya.

Setiap kali menumpuk barang, selalu gunakan palet atau

penyangga.

Jangan menumpuk barang yang berbeda-beda bentuk,

panjang dan ukurannya dalam satu tumpukan

Page 118: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 118/143

dalam posisi berdiri. Letakkan barang-barang tersebut dalam

posisi rebah dan teratur.Barang tidak boleh menghalangi jalan, dan jangan meletakkan

barang di atas balok atau pondasi, dll.

Jangan meletakkan barang-barang di pinggir tempat kerja atau

dekat pintu.

panjang dan ukurannya dalam satu tumpukan.

Sejak awal, pisahkan barang-barang yang sedang dipakaidan yang tidak dipakai.

Ketika menumpuk barang, tumpuklah dari yang terberat

sampai yang teringan, dan dari yang terbesar sampai

yang terkecil.

Tabung oksigen dan barang-barang berat yang mudah

terjatuh harus diikat dengan baik agar tidak jatuh.

Agar pekerjaan bisa diselesaikan dengan aman dan

cepat, patuhi urut-urutan kerja yang baik dan benar yang

anda pelajari dalam pertemuan (harian)

Lakukan pekerjaan dengan urut-urutan seperti yang telah

Periksa semua perkakas sebelum digunakan

Segera ganti perkakas yang rusak

Perkakas yang digunakan untuk pekerjaan di tempat yang

tinggi harus dilengkapi tali pengikat untuk mencegahnya agar

id k j h

Page 119: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 119/143

Lakukan pekerjaan dengan urut urutan seperti yang telah

ditetapkan oleh pimpinan di lokasi kerja (mandor).Jangan melakukan sendiri; jangan mencoba melakukan

sesuatu yang belum pernah dikerjakan sebelumnya.

tidak jatuh.

Jangan pernah biarkan perkakas tidak dibersihkan. Selalubersihkan perkakas setiap kali selesai digunakan.

Setelah digunakan selalu simpan kembali perkakas di tempat

yang disediakan.

Jangan melakukan pekerjaan dengan posisi tubuh

menjulur dari tangga.

Pasang tangga ditempat datar, dan jangan lupa untuk

memasang penguncinya

Ketika menggunakan tangga, selalu jaga agar tangga tersebut tidak jatuh

atau terbalik.

Jangan menaiki tangga hanya dengan satu tangan yang bebas sementara

tangan lain mengangkat sesuatu.

Jangan ada lebih dari satu orang yang naik atau turun tangga pada saat

yang bersamaan.

Page 120: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 120/143

memasang penguncinya.

Hanya boleh ada satu orang diatas tangga.Tangga dan kuda-kuda adalah dua peralatan yang

berbeda. Setiap kali menggnakan tangga, pilih yang

pijakannya datar.

Ketika menggunakan diatas kuda-kuda atau tanggga,

selalu pastikan papannya terpasang dengan baik.

Ketika menggunakan tangga untuk bekerja di ketinggian

lebih dari 2 meter, selalu gunakan sabuk pengaman.

yang bersamaan.

Jangan melakukan apapun ketika berdiri diatas anak tangga.Posisi tubuh harus selalu menghadap tangga saat menaiki atau menuruni

tangga.

Sebaiknya anda tidak menggunakan tangga jika menggunakan sepatu bot

atau sandal.

Gunakan tangga dengan kaki atau penahan anti selip dan pasang tangga

tersebut dengan baik.

U jung atas tangga harus menjulur 60cm dari bagian atas bangunan dan

membentuk sudut sekitar 75 derajat.

Scaffolding/Steger beroda bisa terbalik, karena itu berhati-hatikah

saat menggunakannya.

Pasang rem pada rodanya.

Turun atau naik harus melalui bagian steger yang disediakan

khusus untuk itu.

Selalu berhati-hatilah jika bekerja di atas steger

karena bahaya jatuh selalu ada!

Saat menaiki atau menuruni steger, selalu gunakan

 jalur atau tangga yang tersedia.

Jangan membuka sendiri pegangan tangan atau

Page 121: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 121/143

Jangan gunakan steger pada bidang yang miringJangan pindahkan steger jika ada orang di atasnya.

Jangan naik atau turun dari steger sambil memegang sesuatu.

Jangan cabut pegangan tangan pada steger

Jangan menjulurkan tubuh saat bekerja menggunakan steger.

Jangan membuka sendiri pegangan tangan atau

pengikat.Jangan memindahkan sendiri papan lantai.

Setiap kali melakukan pekerjaan di atas atap genteng

atau atap asbes, jaga jangan sampai anda jatuh karena

atap pecah.

Ketika berjalan melintasi atap genteng atau asbes, selalu

alasi atap dengan papan selebar minimal 30 cm

Saat melakukan pekerjaan di atas atau di bawah gedung,

selalu waspadai benda-benda yang jatuh.

Jika di atas sedang dilakukan pekerjaan, jangan bekerja di

bawah tempat tersebut.

Jika melakukan pekerjaan di bagian atas dan bawah pada

Page 122: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 122/143

alasi atap dengan papan selebar minimal 30 cm.

Selalu gunakan penyangga dan kenakan sabukpengaman.

p j g p

saat bersamaan, usahakan untuk selalu bekerjabersamaan.

Dilarang melempar benda apapun.

Pekerjaan pengecoran lapisan beton selalu dilakukan bersama pekerja

lain, jadi semua pekerja yang terlibat harus sama-sama waspada.

Selang pemompa bahan coran dari mesin pemompa bisa tiba-tiba

bergerak tak terkendali, jadi berhati-hatilah.

Sebelum mulai menuangkan bahan coran yang bertekanan tinggi,

patikan bahwa semua sambungan sudah rapat.

Berhati-hatilah ketika bekerja di area terbuka yang tidak

terlindung.

Jangan sembarangan membuka pegangan tangan atau

penutup tanpa alasan.

Setiap kali diperintahkan untuk membuka pegangan tangan

Page 123: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 123/143

patikan bahwa semua sambungan sudah rapat.

Berhati-hatilah jangan sampai jari atau tangan anda terjepit saatmenyetel talang pada molen.

Jangan cabut talang sebelum bahan coran berhenti mengalir.

Ketika melakukan pekerjaan di pinggir work platform, selalu kenakan

sabuk pengaman.

kembalikan lagi begitu pekerjaan selesai dilakukan.Setiap kali membawa barang melintasi area yang terbuka,

kenakan sabuk pengaman.

Jangan sampai menjatuhkan barang dari area terbuka.

Jaga agar tempat kerja selalu bersih, teratur dan rapih,

dan pekerja harus saling memberi informasi.

Amankan jalur orang (pathway)

Jaga agar bahan pencetak tidak rusak.

Perhatikan urut-urutan kerja yang akan dilakukan sebelum dimulai.

Periksa semua perkakas yang akan digunakan hari itu sebelum

mulai bekerja.

Sebelum mengangkut besi seton, periksa jalur transportasi dan

tempat penyimpanan agar tidak timbul kecelakaan

Di tempat kerja dengan ketinggian lebih dari 2m dan tanpa

Page 124: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 124/143

Saat menggunakan tangga, jangan melakukan pekerjaanapapun saat berdiri di atasnya.

Bersihkan selalu perkakas listrik anda.

Saat memasang cetakan beton, ikuti petunjuk pengawas

lokasi

Di tempat kerja dengan ketinggian lebih dari 2m dan tanpa

pengangan, kenakan selalu sabuk pengaman.Saat mengikat besi beton dengan menggunakan tangga, jangan

melakukannya sambil berdiri diatas tangga.

Saat mengikat besi beton berdua dengan rekan kerja anda, lakukan

pekerjaan itu bersamaan

Operator mesin harus selalu melakukan inspeksi

sebelum mulai bekerja.

Operator mesin harus selalu mematuhi arahan

petugas pengatur lokasi.

Selalu bekerja dengan hati-hati agar tidak bertubrukan atau

terjepit diantara mesin.

Jangan berjalan di bawah barang yang sedang diangkat

dengan derek.

Saat bekerja dekat mesin pengeruk tanah buldoser dll Selalu

Page 125: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 125/143

Saat meninggalkan mesin derek, bagian mesin

yang bergerak harus dalam posisi di atas tanah,

rem dipasang, dan kunci selalu dicabut.

Saat bekerja dekat mesin pengeruk tanah, buldoser, dll. Selalu

ikuti perintah pengatur lalu lintas.

Jangan masuk ke area kerja mesin derek atau crane.

Semua karyawan harus melakukan pekerjaannya dengan hati-

hati agar bahaya kebakaran bisa dihindari.

Dilarang merokok atau menyalakan api di lokasi kecuali di

daerah-daerah yang telah ditetapkan.

Setiap kali menyalakan api, selalu sediakan ember berisi air di

Saat bekerja ditempat bertekanan tinggi seperti sumuran

dan terowongan anda bisa terkena gangguan kesehatan

akibat tekanan yang tinggi; karena itu tindakan

pencegahan harus dilakukan.

Pekerjaan hanya boleh dilakukan setelah anda

Page 126: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 126/143

Setiap kali menyalakan api, selalu sediakan ember berisi air di

dekat anda.Selalu ketahui lokasi alat pemadam api dan cara

menggunakannya.

Saat melakukan pengelasan, selalu gunakan kain pelindung

untuk menghidari percikan api

mendapatkan pelatihan khususAnda harus bekerja di bawah perintah langsung

pengawas.

Anda harus mematuhi dengan sungguh-sungguh waktu

kerja yang ditentukan untuk masing-masing jenis

pekerjaan bertekanan tinggi.

Patuhi dengan sungguh-sungguh waktu yang ditetapkan

untuk proses kompresi dan dekompresi.

Lakukan pemeriksaan kesehatan khusus secara teratur.

Kita harus selalu waspada akan bahaya saat bekerja dengan

listrik.

Sengatan listrik yang besarnya hanya 100 volt pun bisa

menyebabkan orang meninggal dunia.

Saat memindahkan pipa berukuran panjang jaga agar pipa

Pelajari dengan seksama dan pahami Buku

Panduan penggunaan perkakas listrik, serta

gunakan perkakas tersebut dengan cara yang

aman.

Periksa perkakas listrik anda sebelum digunakan

Page 127: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 127/143

Saat memindahkan pipa berukuran panjang, jaga agar pipa

tidak bersentuhan dengan kabel listrik.

Setelah sekering dimatikan untuk memutus aliran listrik,

segera beritahu pengawas anda.

Jangan sentuh saklar di panel pembagi jika anda hanya

sendirian.

Setiap kali melakukan pekerjaan yang berisiko terkena

sengatan listrik, gunakan sarung tangan karet dan sepatu bot

karet.

setiap hari.Pastikan bahwa perkakas anda sudah diberi

arde.

Pastikan bahwa fasilitas pengaman difungsikan

Setiap berjalan sambil membawa perkakas listrik

pastikan bahwa perkakas tersebut sudah

DIMATIKAN.

Setiap kali pekerjaan selesai, bersihkan perkakas

anda dengn baik.

Setiap kali bekerja di dalam gedung dengan menggunakan

cat atau perekat selalu ada bahaya keracunan bahan pelarut

organik; karena itu diperlukan tindakan pencegahan.

Pekerjaan hanya bisa dilakukan setelah anda mendapatkan

pelatihan untuk menangani bahan pelarut organik.

Saat melakukan pengeboram dan pemecahan batu yang

menimbulkan suara bising, ada kemungkinan terjadina

kerusakan organ tubuh akibat getaran dan kerusakan

pendengaran; oleh karena itu kita harus melakukan tindakan

pencegahan yang diperlukan

Page 128: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 128/143

pelatihan untuk menangani bahan pelarut organik.

Lakukan pekerjaan sesuai perintah pengawas anda.Ventilasi yang baik harus selalu tersedia selama pekerjaan

dilaksanakan.

Selama bekerja, kenakan masker ventilasi atau masker gas.

Lakukan pemeriksaan kesehatan khusus secara teratur.

Pekerjaan hanya boleh dilakukan setelah anda mendapatkanpelatihan tentang pengaruh getaran pada kesehatan tubuh.

Penggunaan perkakas getar hanya diizinkan untuk waktu 2

 jam saja per hari.

Pekerjaan hanya boleh dilakukan dengan menggunakan

sarung tangan anti-getar dan penutu telinga.

Anda harus melakukan gerak badan sebelum dan sesudah

bekerja untuk melemaskan otot-otot anda.

Lakukan pemeriksaan kesehatan khusus secara teratur

Perhatikan dan jaga kesehatan anda sendiri.

Periksakan kesehatan anda secara teratur

Sering-seringlah mencuci tangan anda dan berkumur.

Jangan makan dan minum terlalu banyak.

Jangan bergadang dan tidurlah yang cukup.

Nikmatilah kehidupan di mess/asrama.

Jangan merokok di tempat tidur.

Jangan membuat gaduh setelah lampu asrama dimatikan.

Simpan dengan rapih barang-barang pribadi anda dan jaga

 jangan sampai rusak; jaga agar kamar anda selalu bersih.

Page 129: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 129/143

Patuhi dengan sungguh-sungguh aturan yang berlaku di asrama.

Page 130: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 130/143

COUPLER

TIANG RAILINGHANDRAIL

HANDRAIL

Page 131: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 131/143

INSTALLATION

CORNER

MID HANDRAIL

BESI BEHEL D12

BASEPLATE

POLYNET

BESI BEHEL D12

TIANG RAILING

POLYNET INSTALLATIONS VERTICAL (STAIR CASE)

DETAIL SIKU

SIKU

MID

HANDRAIL

Page 132: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 132/143

HANDRAIL

MID HANDRAIL

Page 133: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 133/143

OPENING > 2 M / VOID AREA

KAWAT AYAM + SAFETY NET

BESI BEHEL D12

OPENING 100 ~ 600 mm

OPENING 650~ 2000 mm

Page 134: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 134/143

Page 135: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 135/143

SIKU

KASO / BESI

MID HANDRAIL

HANDRAIL

SWIVE

L

CLAMP

 ANAK TANGGA

OVERLAP

Min.500mm

KAWAT HARMONIKA

(LAYER 1) +POLYNET

(LAYER 1)

PIPE Dia. 1 ½”

D16

CLAMP

SLING

Dia.10mm

Page 136: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 136/143

SLINGDia.10mm

MID BRACING

BEHEL D16

CROSS BRACING

BEHEL D13

PIPE Dia.1 ½”

L50x50,

100mmPIPE Dia. 1 ½”,

750mmDYNABOLT M12

PIPE Dia. 1 ½”

PIPE Dia. 2”,

100mm

Safety Wing

setiap 2 Lantai

dari pelaksanaan

Page 137: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 137/143

RANGKA INSTALLATION

Page 138: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 138/143

BAR CUTTER

BAR BENDER

Page 139: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 139/143

Page 140: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 140/143

Page 141: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 141/143

Page 142: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 142/143

Page 143: Metode Pelaksanaan Gedung (1)

7/17/2019 Metode Pelaksanaan Gedung (1)

http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 143/143