METODE PELAKSANAAN
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 2/143
1. DATA PROYEK
2. KONDISI EXISTING SITE
4. STRUKTUR ORGANISASI
5. TEMPORARY FACILITIES
9. DAFTAR ALAT KERJA
3. SCHEDULE PROYEK
10. PERKEMBANGAN PROGRESS
11. ANIMASI SEQUENCE PEKERJAAN
GO
6. PEMBAGIAN ZONA KERJA
7. PEKERJAAN TANAH
8. METODE PEKERJAAN MASSFOND
12. PEKERJAAN FINISHING
13. QUALITY PLAN & SAFETY PLAN
GO
GO
GO
GO
GO
GO
GO
GO
GO
GO
GO
GO
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 3/143
BACK
NAMA PROYEK :
LOKASI PROYEK :
PEMBERI TUGAS :
KONSULTAN PERENCANA :
KONSULTAN STRUKTUR :
QUANTITY SURVEYOR :
WAKTU PELAKSANAAN :
LINGKUP PEKERJAAN :
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 4/143
BACK
LOKASI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 5/143
KONDISI EXISTING PROYEK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 6/143
KONDISI EXISTING SITE PROYEK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 7/143
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 8/143
SEQUENCE KEGI T N PEKERJ N KOORDIN SI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 9/143
BACK
Untuk Produksi dikoordinasikan oleh :
-1 Site Manager Struktur ( PPM Struktur )
-1 Site Manager Arsitek ( PPM Arsitek )
-1 Site Manager ME & DC ( PPM ME & Koor DC )
- Proyek ON GOING
STRUKTUR ORGANISASI
LA MAISON BARITO APARTMENT
JAKARTA SELATAN
Deputy PM
PEM PPM Struktur PPM Arsitektur PPM MEP PFM
Perenc S.Dwg Supervisor Supervisor Akuntansi
Quantity Surveyor Surveyor
Procurement Staff Mekanik
Cost Control Officer K3
Staff QC
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 10/143
BACK
15
11 9
8
6
5
16
12 14
13
3 1
3
7
10
14
Gardu
Existing
P1
P2
P3
Kantor
Owner
Keterangan :
Tower Crane TC
Type Static
Jib : 60 M
Jumlah : 1 Unit
Kap. Max : 3,6 – 12 Ton
- Barak Pekerja di luar lahan proyek
16
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 11/143
BACK
Pada pelaksanaan Proyek La Maison ini pembagian zona kerja dibagiberdasarkan luasan lantai yang akan dikerjakan. Pembagiannya meliputiarea basement, area podium dan area tower yang terdiri dari :
Area Basement 6 Zona Kerja, Pekerjaan Galian dan Struktur
- Pekerjaan Galian 6 Zona
- Pekerjaan Struktur 6 ZonaArea Podium 6 Zona Kerja, Pekerjaan Struktur
Area Tower 4 Zona Kerja, Pekerjaan Struktur
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 12/143
Total Luasan = 3596 m2/LT
START
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 13/143
START
Total Luasan = 2308 m2/LT
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 14/143
Total Luasan = 1355 m2
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 15/143
BACK
-Pekerjaan galian tanah yang dikerjakan dengan alat / excavator antara lain :
Galian Mass Pondasi dan Pail Cap.
-Pekerjan galian tanah yang dikerjakan dengan cara manual antara lain :Galian di sela – sela bor pile, Galian tertinggal / tidak terjangkau
excavator.
-Urugan tanah dilaksanakan untuk mengurug di sela-sela batako dan karena metode /
meratakan tanah
Pada saat galian tanah, Setelah lubang pondasi selesai digali, dasar dan
dindingnya disemprot dengan larutan Anti Rayap secara merata sebanyak 5 liter / m2 .Tanah galian atau urugan harus disemprot secara merata dengan larutan Anti Rayap.
Setelah pondasi dibangun, tanah atau urugan tersebut dimasukan kembali kedalam
lubang pondasi agar berfungsi sebagai penyangga serangan rayap.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 16/143
START
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 17/143
Catatan :
1. Tanah Miring
dilapisi dengan
Blue Sheet
2. Tanah dikasih
Cerucuk3. Kemiringan Tanah
1:2
4. Bak Kontrol 50x50
cm per 20 m
BKBKBK
BK
BK
BK
BKBK
BK
BK
BK
BK
BK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 18/143
BACK
Pengecoran Massfond
menggunakan 3 buah
concrete pump dan
dibantu dengan TC.
CP1
CP2
CP3
START
P3
P2
P1
CP-1 pada P-3
CP-2 pada P-2
CP-3 pada P-1
-Luas Area Massfond :
1008 m2
-Ketinggian Massfond :
2m
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 19/143
NO URAIAN SATUAN VOLUME KETERANGAN
1 Volume Beton m3 2150
2 Alat
- Concrete Pump Mobil Unit 3 Mass Pondasi
- Conventor Unit 4
- Vibrator Buah 9
- Concrete Pump Kodok Unit 1 Podium (Permanen)
3 Lama Penecoran Jam 364 Waktu Pengecoran
- Start : Sabtu Pukul 15.00 wib Sore Hari
-Finish : Senin Pukul 03.00 wib Dini Hari
5 Mobil Mixer Buah 10 di Lapangan
6 Tower Crane Unit 1
7 Tukang Cor Orang 21
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 20/143
Potongan Bekisting Mass Pondasi
Siklus Pengecoran :
-Tinggi Pengecoran dibagi menjadi 2 lapis di setiap lapis
setinggi 1 m
-Pengecoran Lapis Ke 1, Vol = 1150 m3
Siklus 1A 2A 1B 2B
Waktu Pelaksanaan ± 20 Jam = 15.00 – 11.00
-Pengecoran Lapis Ke 2, Vol = 1000 m3Siklus 1A 2A 1B 2B
Waktu Pelaksanaan ± 16 Jam = 11.00 – 03.00
Pengecoran dibagi 2 Lapis
1A
1A
2A
2A
Urugan Tanah
Potongan Bore Pile Mass Pondasi
1A2A
2B 1B
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 21/143
BACK
2
Keterangan :1. CP Untuk Cor Lt.Dasar-Lt.7
2. TC Jib 60m untuk cor Lt.8-Lt.31
3. PH 1
4. PH 2
1
3 4
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 22/143
Pada Proyek ini menggunakan 1 buah TC dengan panjang Jip 60 m.
Denah Pondasi TC
Potongan A
Posisi Peletakan Bracing TC Lt. Tower
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 23/143
SCHEDULE TOWER CRANE
NO URAIAN LANTAI ELEVASI SCHEDULE
A Pondasi + Erection TC
1 Cor Bore Pile / Tiang Pancang 12-Mar-12
2 Cor Pondasi TC -2.00 m 18-Mar-12
3 Erection TC 28-Mar-12
B Bracing TC
1 BR 1 8 + 30,00 m 30-Aug-122 BR 2 13 + 50,50 m 10-Okt-12
3 BR 3 19 + 74,00 m 15-Des-12
4 BR 4 25 + 98,00 m 15-Jan-13
C Jumlah Section Pcs 42 Pcs 2mx2mx3m
D Dismantling 15-Apr-13
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 24/143
Pada Proyek ini menggunakan 2 Area penempatan PH, yaitu PH 1 dan PH 2.
PH2PH1
PH1 PH2
Posisi PH Pada Lantai Dasar
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 25/143
Potongan Posisi Pipa Cor
Catatan :1. Concrete Pump digunakan untuk pengecoran
Lt. Dasar – Lt.7
2. Tower Crane digunakan untuk pengecoran Lt.
8 – Lt.31
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 26/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 27/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 28/143
BAR CUTTER
BAR BENDER
Kebutuhan Volume :
Jumlah penyediaan Bar
Cutter dan Bar Bender
masing-masing 2 set
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 29/143
WS1
WS2
Penempatan Washing Bay
Area :
WS – 1 pada P3
WS – 2 pada P1
Kendaraan proyek sebelum keluar lokasi, harus dibersihkan dahulu di
area washing bay . Air cucian kotor dibuang melalui saluran
temporary ke arah sungai
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 30/143
Panel
Induk
Panel
Kerja
Panel
Kerja
Panel
Kerja
Panel
Kerja
Panel
Kerja
Basement-Lt.7
Lt.8 – Lt.17
Lt.18 – Lt.30
Pada panel kerja, kabel vertikal
melalui shaft elektrik dan dibagi
menjadi 3 zona, yaitu :
- Zona 1 Lt. Basement-Lt.7
- Zona 2 Lt.8-Lt.17
- Zona 3 Lt.18-Lt.30
Paneldistribusi
Panel
Induk
Panel
Distribusi
PanelKerja
Panel
Eksternal
Panel TC
Denah Peletakan Panel Listrik
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 31/143
Volume lampu per Area :
-Area Podium 40 Titik
-Area Tower 20 Titik
-Area External 20 Titik
HBTHBT
HBT
HBT
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 32/143
PLNPANEL
INDUK
NYYHY 4 X 95 mm
NYYHY 4 X 16 mm
PANEL
DISTRIBUSI
PANEL
KANTOR
Diagram Pembagian Arus Listrik
NYYHY 4 X 70 mm
NYYHY 4 X 35mm
NYYHY 4 X 25mm
PANEL
TC
PANEL
PH
PANEL
KERJA
NYYHY 4 X 35 mmPANEL
EKSTERNAL
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 33/143
Tangki
10.000 L
Pompa
Transfer
Denah Pengeboran dan titik pompa
Pompa 2
Pompa 1
Pompa 2 = Pompa Deep well
-Untuk Pengisian torn 10.000 L
-Untuk distribusi air kerja ke setiap lantai
-Untuk curing Beton
Sistem air kerja dibagi :
1. Area Podium disiapkan : 2 kran + 2 drum2. Area Tower disiapkan : 1 kran + 1 drum
Pompa 1 = Pompa Jet Pump
-Untuk toilet kantor
-Untuk cuci mobl mixer
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 34/143
AIR SUMUR
TANGKI
10.000 L
POMPA
TRANSFER
POMPA DEEP WELL
TANGKI
5.000 L
DRUM
PENAMPUNGAN
PIPA 1 ½ ‘’ PIPA 1 ‘’
AIR SUMUR
TANGKI
1.000 L
TOILET
KANTOR
JET PUMP
Diagram Pembagian Distribusi Air
Pompa 1 Pompa Deep well
Pompa 2 Jet Pump
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 35/143
INSTALLATION
CORNER
COUPLE
R
TIANG RAILINGHANDRAIL
MID HANDRAIL
BESI BEHEL
D12
BASEPLA
TE
POLYNET
BESI BEHEL
D12
TIANG RAILING
POLYNET
Pemasangan Safety Net Pada setiap lantai
bangunan dan pemasangan safety Wing dua
lantai dibawah pekerjaan struktur
SAFETY NET
form work/pekerjaanstruktur
railing perimeter
safety net perimeter
2 lantai
safety wing net
temporary railing
polynet
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 36/143
Detail
potongan
1
2
3
4
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 37/143
SLING
Dia.10mm
MID BRACING
BEHEL D16
CROSS BRACING
BEHEL D13
KAWAT HARMONIKA
(LAYER 1) +POLYNET
(LAYER 1)
PIPE Dia. 1 ½”
PIPE Dia.1 ½”
D16
CLAMP
SLING
Dia.10mm
L50x50,
100mmPIPE Dia. 1 ½”,
750mmDYNABOLT M12
PIPE Dia. 1 ½”
PIPE Dia. 2”,
100mm
SAFETY WING
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 38/143
OPENING > 2 M / VOID AREA
KAWAT AYAM + SAFETY NET
HANDRAIL
MID HANDRAIL
BESI BEHEL D12
OPENING 100 ~ 600 mm
OPENING 650~ 2000 mm
SAFETY RAILING VOID
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 39/143
SAFETY NET DI LIFT SAFETY VOID
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 40/143
RANGKA INSTALLATION
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 41/143
TS 2TS 1
TS 1TS 2
TF 2 TF 1
A. Terminal Struktur disiapkan 4 Unit
-TS 1 = Terminal Barang Struktur Lantai Ganjil (2 Unit)
-TS 2 = Terminal Barang Struktur Lantai Genap (2 Unit)
B. Terminal Finishing disiapkan 2 Unit
-TF 1 = Terminal Barang Finishing Lantai Ganjil (1 Unit)-TF 2 = Terminal Barang Finishing Lantai Genap (1 Unit)
Denah Peletakan Terminal Barang
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 42/143
PENEMPATAN TEMPORARY FACILITY
PENGECORAN MASS FOND DENGAN
BANTUAN ALAT CONCRETE PUMP
Periode bulan Maret 2012
Periode bulan Maret–
April 2012
PENGECORAN LANTAI BASEMENT
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 43/143
PENGECORAN LANTAI BASEMENT
PENGECORAN LANTAI DASAR
PEMINDAHAN TEMPORARY SITE OFFICEKEDALAM BANGUNAN DI BASEMENT
Periode awal April-awal Juni 2012
Periode akhir april – pertengahan Juni 2012
Periode pertengahan Mei 2012
PEMASANGAN SAFETY NET DI SEKELILING
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 44/143
BANGUNAN PODIUM
-PEMASANGAN SAFETY WING DI LT.9
-SAFETY NET DI LT. 8 & 10
-PEKERJAAN STRUKTUR DI LT. 11
Periode pertengahan juli 2012
Siklus pemasangan 2 lantai dibawah
Pekerjaan struktur
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 45/143
-PEKERJAAN STRUKTUR DI LT.20
-PEKERJAAN FINISHING DI LT. 13
-PEKERJAAN FASAD DI AREA PODIUM
Periode sampai dengan akhir bulan Oktober 2012
-PEKERJAAN STRUKTUR DI LT.24
-PEKERJAAN FINISHING DI LT. 17-PEKERJAAN FASAD SAMPAI LT.11
Periode sampai dengan akhir bulan November 2012
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 46/143
SEMUA PEKERJAAN STRUKTUR, FINISHING,
LANDSCAPE DAN FASAD SUDAH SELESAI
Periode Bulan
Maret 2013 Topping Off
Periode Bulan Mei 2013
Periode Bulan Oktober 2013
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 47/143
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 48/143
ALAT YANG DIPERLUKAN :
1. TROWEL2. PALU KARET
3. WATER PASS
4. BESI SIKU
5. GERGAJI
6. RAMSET
7. GARUKAN PERATA
HAL – HAL YANG PERLU DIPERHATIKAN :
1. PEMASANGAN HABEL HARUS ZIG-ZAG DENGAN OVERLAP YANG DIIJINKAN MIN.10 CM
2. DERAH PERTEMUAN ANTARA HABEL DAN STRUKTUR HARUS DIBERIKAN ADUKAN
ELASTIS 1 PC : 6 PS
3. HASIL AKHIR PEMASANGAN HABEL YANG BENAR DITANDAI DENGAN TIDAK ADANYA
LUBANG-LUBANG SINAR YANG MUNCUL DARI DINDING PERMUKAAN PASANGAN
HEBEL
4. PENGGUNAAN BETON PRAKTIS MENGIKUTI ATURAN DARI PABRIK HABEL
5. PEMASANGAN HABEL YANG BAIK ADALAH DENGAN MENGGUNAKAN ALAT TROWEL
SELEBAR TEBAL HEBEL6. PM-100 YANG MENEMPEL PADA HEBEL YANG AKAN DIREKATKAN
SATU DENGAN YANG LAIN HARUS DALAM KONDISI BERALUR- ALUR AGAR PADA SAAT
DIREKATKAN DAN KEMUDIAN DIPUKUL-PUKUL DENGAN PALU KARET AKAN
MENGHASILKAN REKATANYA BENAR-BENAR RAPAT (TIDAK ADA CELAH)
Material Bata Ringan
LANGKAH 01
Siapkan sloof / balok dan periksa kerataan dan mutu pengecoran betonnya
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 49/143
LANGKAH 02
LANGKAH 03
Siapkan sloof / balok dan periksa kerataan dan mutu pengecoran betonnya.
Tarik benang antara sudut-sudut dinding untuk menentukan posisi dan kerataan
dinding
Gunakan “Waterpass” untuk menyamakan ketinggian benang dan gunakan
“Theodolite” bila diperlukan.
Untuk lapisan dasar, gunakan Mortar atau setara. Tebarkan adukan tersebut secara
merata.
LANGKAH 04
Gunakan cethok untuk merapikan kelebihan adukan di sepanjang tepian.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 50/143
LANGKAH 05
LANGKAH 06
Letakkan blok yang sudah diberi Thin Bed mortar di ujung dinding tepat pada pertemuan benang.
Tekan hingga ketebalan adukan 10 mm. Periksa kembali level blok dengan menggunakan
“waterpass”. Lakukan langkah yang sama untuk setiap ujung dinding.
Untuk merekatkan bagian vertikal blok digunakan “Thin Bed Mortar”
LANGKAH 07
Setelah meletakkan blok pada masing-masing ujung dinding, letakkan blok lapis kedua dengan
“Thin Bed Mortar” Langkah ini penting untuk dudukan benang dan mencegah pergerakan blok di
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 51/143
“Thin Bed Mortar”. Langkah ini penting untuk dudukan benang dan mencegah pergerakan blok di
ujung dinding pada saat meletakkan blok-blok lain pada lapis pertama.
Penting :
- Untuk pasangan blok Hebel harus menggunakan sistem Thin Bed Mortar, agar manfaat produk
beton ringan aerasi dapat diperoleh sepenuhnya.- Blok-blok dan panel Hebel di lokasi proyek harus dilindungi dari air dan hujan..
LANGKAH 08
Campur “Thin Bed Mortar” dengan air dalam sebuah ember. Penggunaaan “Mixer” akan menghasilkan
campuran adukan yang lebih baik Perbandingan “Thin bed mortar” dan air sesuai petunjuk pemakaian
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 52/143
campuran adukan yang lebih baik. Perbandingan Thin bed mortar dan air sesuai petunjuk pemakaian
pada kemasan. Pada saat hari terasa amat panas, tambahkan sedikit lebih banyak air dari takaran
yang disarankan, untuk menhindari adukan cepat kering.
Bilamana campuran mulai mengering tambahkan air ke dalam bak dan aduk kembali. Sebelum mulai
campuran baru, bersihkan ember terlebih dahulu dengan air untuk mencegah adukan lamamempercepat waktu pengeringan campuran pasangan yang baru. Jangan menggunakan lagi adukan
sisa yang berjatuhan.
LANGKAH 09
Dengan menggunakan sikat halus, bersihkan permukaan blok setiap kali akan
memasang lapis baru..
Penting :
Bilamana suhu udara terasa sangat panas, celupkan sikat halus ke dalam air sebelum menyikat.
LANGKAH 10
Rentangkan benang dari ujung dinding ke ujung dinding yang lain Gunakan cethok
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 53/143
Rentangkan benang dari ujung dinding ke ujung dinding yang lain. Gunakan cethok
khusus dengan lebar yang sesuai dengan lebar blok. Letakkan “Thin bed mortar” pada
arah vertikal terlebih dahulu, baru kemudian arah horisontal. Tebarkan adukan
secukupnya untuk satu blok saja. Pastikan pasangan “Thin bed Mortar” menutup
selebar permukaan blok.
LANGKAH 11
Pada saat meletakkan blok, angkat permukaan blok yang menghadap adukan vertikal
dan mulai letakkan sisi blok yang berlawanan terlebih dahulu..
LANGKAH 12
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 54/143
Setelah blok diletakkan, rapatkan dengan palu karet secara merata. Langkah ini sangat penting
untuk mamastikan bahwa seluruh permukaan blok sudah tertutup dengan “Thin Bed Mortar”.
Pastikan palu jangan terlalu keras supaya “Thin Bed mortar tidak keluar. Jaga ketebalannya ( 1-2
mm setelah blok direkatkan).
Penting :
Bila hujan turun, lindungi permukaan atas blok dengan plastik
Kelebihan thin bed mortar pada permukaan dinding,
dibersihkan dengan menggunakan cethok biasa.
LANGKAH 13
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 55/143
Bilamana ada penonjolan blok pada permukaan dinding, dapat diratakan dengan menggunakan
garukan perata (gambar a)
Pecahan blok dapat dimanfaatkan untuk meratakan kelebihan adukan (gambar b). Kalau
permukaan dinding akan ditutup dengan “Plasterboard”, maka yang diperlukan agar rata adalah
dengan menggunakan garukan perata/”leveling scraper”. Amplas tidak diperlukan.
Untuk menghaluskan permukaan yang luas, dapat menggunakan papan amplas (gambar C)
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 56/143
Periksalah kelengkapan berikut :
Pelajarilah denah keseluruhan lokasi pemasangan kolom praktis beserta pelengkap (jika diperlukan), dalam skala 1:200, 1:50
dan 1:20 yang menggambarkan :
PEMBESIAN KOLOM PRAKTIS
PERSIAPAN
KEPERLUAN ALAT
MEMPELAJARI GAMBAR KERJA
Meteran
Kawat bendratGegep/kakatua
Palu & tang
Bor beton
Helm pengaman
Bar cutter
Bar bender Gunting besi manual
Profil kayu kaso
Kunci besi
Sabuk pengaman
1. Posisi kolom praktis dan dimensinya
2. Letak pasangan batu bata
3. Detail Pembesian beserta diameter, ukuran dan jumlah besi.
4. Jarak kolom praktis As ke As.
1. Bersihkan area dimana akan dilakukan pemasangan kolom praktis dan sekitarnya.
2. Rangkailah besi tulangan kolom praktis dengan jarak yang sesuai dengan shop drawing,
ikatlah dengan sistem ikat satu arah dengan kuat, antara tulangan utama dan sengkang/beugeldengan menggunakan kawat bendrat. Jarak setiap sengkangnya dibuat seragam.
3. Persiapkan potongan besi d 10 sebanyak 8 buah, 4 buah untuk sisi atas pelat dan 4 buah
untuk sisi bawah pelat.
PELAKSANAAN PEMBESIAN KOLOM
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 57/143
1. Buatlah marking posisi 8 stek penguat, 4 stek
pada pelat atas dan 4 stek pada bawah.
Bor pelat lantai atas dan bawah sampai
kedalaman 5cm pada sudutnya, kemudian
bersihkan lubang tersebut dan pasanglah stek
menggunakan epoxy, pastikan stek tidakgoyang.
2. Ikatlah antara besi kolom praktis dengan stek
penguat atas dan bawah menggunakan kawat
bendrat dan posisikan sehingga besi kolom
praktis berdiri tegak.
Stek Kolom Praktis
Kolom Praktis
Disambung dan Diikat Kuat
dengan Kawat Besi
Pasangan Dinding
Mempelajari Gambar
Kerja
Pelajarilah denah keseluruhan lokasi pemasangan kolom praktis beserta denah pelengkap (jika diperlukan),
BEKISTING DAN PENGECORAN KOLOM PRAKTIS
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 58/143
dalam skala 1:200, 1:100 dan 1:50 yang menggambarkan :
1. Bersihkan area dimana akan dilakukan bekisting dan pengecoran kolom praktis
2. Bekisting dibuat dari papan kayu plywood dengan ukuran yang sesuai dan jika menggunakan
plywood bekas, maka harus dibersihkan terlebih dahulu
Periksalah kelengkapan peralatan berikut :
PERSIAPAN
PELAKSANAAN BEKISTING DAN PENGECORAN KOLOM PRAKTIS
1. Letak dan tinggi pasangan batu bata
2. Dimensi dan ukuran kolom praktis
KEPERLUAN ALAT
Steger/tangga kerja
Dolak/alat takar
Meteran
Kawat bendrat
Gergaji
Sendok semen&roskam
Palu kayu&paku
Gegep
Helm pengaman
Gerobak
Adukan beton(molen kecil)&sekop
Unting-unting(lot)
Kayu kaso
Ember
Alat penampung adonan yang jatuh
Papan kayu plywood
Kotak kayu untuk tempat adukan sabuk pengaman
Sabuk pengaman
1. Bekisting 1 dipasang sesuai ketinggian pasangan bata dan bekisting 2 dipasang lebih rendah
dari pasangan bata. Kedua bekisting dilebihkan jarak 5cm pada sisi kanan dan kiri untuk
menutupi pasangan bata.
2. Tambahkan jendela dari papan kayu pada
bekisting 2 dengan kemiringan yang cukup
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 59/143
bekisting 2 dengan kemiringan yang cukup,
kemudianlah ikatlah antara kedua sisi
bekisting dengan kawat bendrat pada atas,
tengah dan bawah bekisting. Pastikan kawat
bendrat terikat dengan baik.
3. Ukurlah dan cek vertikalitas bekisting kolom
praktis tersebut dengan dilot.
Campurlah adonan beton sesuai
spesifikasinya sampai adonannya rata dan
homogen.
Pasanglah alas untuk menampung adonan
yang jatuh, kemudian cor kolom praktis
dengan menuangkan adonan kedalamlubang bekisting, pada saat pengecoran ke
dua sisi bekisting dipukul-pukul dengan
palu agar beton nantinya tidak keropos.
6. Bekisting kolom praktis dapat dibuka setelah 8 jam.
7. Lanjutkan kembali pemasangan batu bata dengan
ketinggian max. 1,5 m (ulangi methode kerja pasangan
celcon) kemudian bekisting kolom praktis (langkah 1
sampai 5) dan ulangi kembali pengecoran (langkah 6)sampai kolom praktis selesai.
Mempelajari Gambar
Kerja
P l j il h d h l h l k i di di k di l t b t d h l k (jik di l k )
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 60/143
Pelajarilah denah eseluruhan lokasi dinding yang akan diplester beserta denah pelengkap (jika diperlukan),
dalam skala 1:200, 1:100 dan 1:50 yang telah menggambarkan :
• Steger / tangga kerja
• Molen kecil• Meteran
• Siku besi
• Ember
• Palu & paku
• Waterpass
• Kawat ayam
• Benang
• Helm pengaman
Gerobak
Dolak/alat takar Unting-unting/lot
Kotak tempat adukan
Drum air
Sendok semen&roskam
Alat penampung adonan yang
jatuh
Selang plastik
Jidar alumunium
Sabuk pengaman
Alat Kerja
Periksalah kelengkapan peralatan berikut :
1.Posisi dan jarak pasangan dinding
2.Tebal plesteran dan detail material finishing padadinding
3.Letak kusen pintu dan jendela
PERSIAPAN
1. Umur pasangan batu bata minimal 1 hari (24jam) dan
dinding beton minimal 14 hari.
2 Bersihkan area plesteran dan permukaan dindingnya
5. Berilah marking bidang yang akan diplester dengan
memaku keempat sudutnya dan jika tidak
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 61/143
2. Bersihkan area plesteran dan permukaan dindingnya
dari kotoran dengan sapu lidi.
3. Pada dinding beton, permukaannya terlebih dahulu
diciping atau dapat juga dikamprot dengan bahan tile
additive, lalu dibiarkan selama 24 jam sampai kering.
4. Apabila terdapat pertemuan antara dinding beton
dengan pasangan batu bata dan tidak ditentukan
dalam spesifikasi serta tidak ada tali air, maka
sepanjang pertemuannya dipasang kawat ayam
dengan cara dipaku.
ditentukan di spek, pakukan sudut atas 25m lebih
tinggi dari elevasi plafondnya.
Kemudian tariklah benang horisontal dan vertikal
dari paku satu ke yang lain. Jarak antara benang
dan permukaan dinding merupakan ketebalanplesteran nantinya.
6. Pasanglah alas kayu untuk menampung adonan
yang jatuh.
A
C
B
D
7.Periksalah vertikalitas benang dengan dilot.
8. Tariklah benang berikutnya pada keempat sisi
bidang plesteran dengan jarak 5cm dan benang
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 62/143
9. Persiapkan adukan plesteran sesuai
spesifikasi di dalam kotak kayu tempat adukan
atau menggukan molen kecil dan adonanharuslah rata, homogen dan tidak menggumpal.
Jika adonan terlalu kental, boleh ditambahi air
sedikit selama umur adonan belum melebihi ½
jam sejak awal pengadukan. Umur adonan dan
tidak boleh lebih dari 2jam, karena daya
rekatnya ,emjadi berkurang, oleh sebab itu,
buatlah adonan secukupnya.
g p g j g
horisontal dan vertikal selanjutnya ditarik dengan
jarak antar benang 1,5m.
Kemudian siramlah dinding yang akan diplester
dengan air bersih.
BENANG LOT
LOTAN
METERAN
PAKU BESAR
1. Buatlah caplakan pada setiap persilangan benang
Pelaksanaan Plesteran Dinding
2. Setelah membuat caplakan lepaskan benang
dengan paku hati-hati. Kemudian antara caplakan
tersebut buatlah klabangan horisontal atas dan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 63/143
dan ratakan permukaan adukan dengan sendok
semen sampai mencapai ketebalan yang
diinginkan (jarak antara benang dan permukaan
dinding)
1 mCAPLAKAN
tersebut buatlah klabangan horisontal atas dan
bawah saja serta kelabangan vertikal.
Permukaan adukan diratakan dengan jidar
alumunium dan roskam.
3. Pada pertemuan 2 dinding di sisi dalam,
buatlah salah satu klabangan mepet dengan
4. Sebelum melaksanakan plesteran, cek
kelembaban pada dinding yang akan diplester
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 64/143
buatlah salah satu klabangan mepet dengan
siku dalam pada dinding, dan berkaitan jarak
5cm untuk klabangan dinding berikutnya.
p g y g p
dan jika diperlukan siram lagi dinding dengan air
bersih. Lakukan plesteran dengan mengguinakan
sendok semn atau roskam, ratakan serta
padatkan permukaan dengan jidar aluminium.
Pada pertemuan anatra sudut, plesteran dibuatdengan lurus.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 65/143
1
- Check kondisi real kondisi, di lapangan dan buat
shop drawing- Tentukan posisi start point dalam shop drawing dan
mintalah persetujuan dari pengawas/MK
- Terapkan posisinya start point yang sudah disetujui
dilapangan sebagai contoh lihat gambar dibawah ini.
1.Palu karet2.Zidar / water pass
3.Besi siku4.Benang nylon5.Ember dan gayung6.Skrap7.Sapu8.Spon basah / kain basah
ALAT YANG DIPERLUKAN :
JIDAR / WATERPASS3BENANG NYLON
2
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 66/143
- Pemasangan berikutnya dilaksanakan dengan cara mengeser benang
nylon sejajar dengan salah satu sumbu kepalaan
1.Check terhadap elevasi lantai pada saatmembuat
kepalaan awal
2.Pasir yang digunakan harus diayak agarmendapatkangradasi material yang seragam
3.Air yang digunakan memenuhi syarat sebagai air minum
4.Sebelum dipasang keramik harus direndam dalam air
dahulu sampai jenuh
5.Pada saat pemasangan keramik harus dipastikan bahwa
spesi yang terletak dibawah keramik benar-benar padat
tidak berongga
dengan cara dipukul – pukul dengan palu karet
6.Pemasangan keramik dapat juga dengan cara
menggunakan lem (tergantung permintaan spek)7.Check kerataan pasangan keramik dengan jidar
atau pun dengan water pass
HAL – HAL YANG PERLU DIPERHATIKAN :- Pasang keramik menurut salah arah sumbu kepalaan
BENANG NYLON
DI GESER
BENANG NYLON
CONTOH DENAH
BENANG NYLON
DI GESER
1
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 67/143
- Pasang keramik dengan posisi as
keramik sama dengan CL
- Buat kepalaan dari keramik secara
horizontal dan vertikal
- Selanjutnya pelaksanaan
pemasangan keramik mengikuti alur
kepalaan
- Pemasangan lapis berikutnya selalu
dimulai dari tengah dinding kearah kiri
dan kekanan
A
B
d1 d2
CL
ARAH PEKERJAAN
- Cari CL (center line) dari dinding a1 =
d1=d2
- Buat titik A dan B dimana elevasi titik
A=elevasi titik B setinggi ukuran keramik
yang akan dipasang
- Hubungkan titik A-B dengan benang
nylon
1
2
ARAH PEKERJAAN - Diharapkan pada posisi-posisi sudut tembok merupakan daerah
buangan keramik yang simetris
- Lebar sisa buangan A = lebar buangan B
3
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 68/143
1.Sebelum dipasang keramik harus direndam dalam air sampai jenuh
2.Pemasangan keramik harus urut mengikuti kepalaan vertikal yang sudah dibuat sebelumnya.
3.Pastikan tidak ada celah / rongga pada spasi antara keramik dantembok dengan cara memukul-mukul keramik sampai denganBunyi yang seragam dan padat pada semua bagian
4.Pemasangan dinding keramik dapat jugadilaksanakan dengan menggunakan lem keramik (tergantungpermintaan spek)
5.Pasir yang digunakan harus diayak dahulu untuk mendapatkangradasi material yang seragam
6.Gunakan water pass / jidar untuk mengontrol kerataanpermukaan keramik yang terpasang
7.Air yang digunakan tidak boleh mengandung asam (bebas daripengaruh asam).
KAPASITAS PRODUKSI :- 1 TUKANG- 2 KENEK
HAL –HAL YANG PERLU DIPERHATIKAN :
12 m² / Hari
SISA BUANGAN SAMA BESAR
Lebar sisa buangan A lebar buangan B
Catatan : Untuk kondisi buangan yang terlalu kecil, pemasangan
keramik dapat di mulai dari sisi tepi.
1. Pemasangan kepalaan mulai dari sisi tepi bidang.
2. Pemasangan selanjutnya mengikuti arah ke sisi lain
bidang (ke arah kanan)3. Didapat sisa buangan yang cukup besar (lebih dari ¼
lebar keramik).
Untuk lebih pasti shop drawing harus terlebih dahulu
disetujui oleh konsultan.
P ik l t / d h l it P ik khi l t i t t d l t i tid k l l
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 69/143
1
2
3
4
5
6
8
9
10
11
712
Periksa lay-out / denah, pola granit
/marmer, detail-detail khusus, bentuk
pinggulan serta area mana saja yg ada
finishing granit/marmer dan gambar telah
dikoordinasikan dengan M/E.
Periksa area yg di syaratkan anti-slip
granit/marmer atau tipe khusus pada area
tertentu
Periksa warna, ukuran,pattern(urat), bentuk dan tipe
granit/marmer, sortir seperti yang disetujui. dan kelompokkan
material yang seragam/uniform harus mencukupi hiasan bidang-
bidang yang akan dipasang.
Periksa tipe grout dan warna seperti yang disetujui.
Periksa pembuatan mockup
Periksa granit/marmer dinding dipasang sebelum granit/marmer
lantai.
Periksa waterproofing telah dipasang sesuai persyaratan.
Periksa pengakhiran lantai terutama pada lantai yang tidak selevel
atau ada perbedaan material ,memakai threshold vinyl, metal strip
atau sejenisnya.
Periksa kemiringan screed/lantai kearah pembuangan pada tempat
yang lebih rendah.
Periksa tipe dan lokasi expansion joint
sesuai persyaratan.
Pada sistem acian/adhesive, landasan screed
yang dipasang harus padat, tidak keropos dan
tidak retak.
Periksa pemasangan granit/marmer bahan perekatnya dapat
menggunakan latex cement atau epoxy atau acian (tanpa gypsum) sesuai
persyaratan. Granit/ marmer dipukul agar lebih melekat dan bahan
perekat yg menempel segera dibersihkan sebelum setting/keras.
1.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 70/143
2.
3.
4.
5.
6.
8.
9.
Tentukan elevasi plafond dan buat garis
sipatan pada dinding & as sumbu ruangan.Pasang rangka hollow tepi tepat pada sipatan.
Tentukan jarak penempatan hollow
pengantung
Pasang rangka utama
Pasang panel gypsum
1
2
3
4
5
6
7
8
Pasang benang untuk pedoman penentuan
titik paku penggantung untuk menjamin
kelurusan.
Pasang rangka pembagi.
9 Tutup sambungan antara panel gypsumdengan paper tape dan compound lalu
diampelas dan finish dengan cat
Cek kerapihan dan kerataan bidang plafond.
7.
PERTEMUAN ANTAR PANEL GYPSUM
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 71/143
METHODE PEMASANGAN COMPOUND PADA
GYPSUM BOARDLakukan pelapisan pada petemuan bidang panel dengan compound
Dilanjutkan dengan penempelan paper tape pada lapisan
compound.
Lapiskan kembali compound menimpa paper tape4 Tunggu sampai kering lalu haluskan permukaan dengan hand sander
dan grit paper 150/120
3
1
2
1. POTONG UJUNG LIST PROFIL PLAFONDB G G P
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 72/143
SISTEM SAMBUNGAN LIST PROFIL
MIRING 45 DERAJAT
SAMBUNGAN
UNTUK SAMBUNGAN, GUNAKAN MAL PO-
TONG DENGAN SUDUT KEMIRINGAN 45DERAJAT.
KEPALA PAKU PIPIH
PERMUKAANLIST YANGMENEMPEL
PADA PLAFOND
UJUNG PAKURATA
2. SEBELUM LIST PROFIL PLAFOND DIPASANG,PAKU LIST PROFIL PLAFOND DENGAN PAKU
YANG KEPALANYA TELAH DIPIPIHKAN HING-GA UJUNG PAKU RATA DENGAN PERMUKA-AN LIST PROFIL YANG MENEMPEL PADA
PLAFOND.
PEMASANGAN PAKU SEBELUM
LIST DIPASANG
3. PASANG BENANG UNTUK PEDOMAN PEMA -
SANGAN LIST PROFIL PLAFOND TARIKAN
4. PASANG / TEMPELKAN LIST PROFIL PLAFOND PADA POSISINYADENGAN ACUAN BENANG AWAL PEMASANGAN DIMULAI DARI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 73/143
SANGAN LIST PROFIL PLAFOND, TARIKAN
BENANG MAKSIMUM 7 M UNTUK MENGHIN-
DARI LENDUTAN.
LIST
PROFIL
BENANG
DENGAN ACUAN BENANG, AWAL PEMASANGAN DIMULAI DARI
SALAH-SATU UJUNG. ( SAMBUNGAN HARUS RAPAT & RATA ).
DETAIL PEMASANGAN LIST
PROFIL PLAFOND
RANGKA PLAFOND
LISTPROFIL
DINDING
5. MASUKKAN/PUKUL KEPALA PAKU DENGAN DRIP AGAR KEPALA PAKU
MASUK ( TIDAK KELIHATAN ).
6. DEMPUL LUBANG-LUBANG BEKAS PAKU DAN SAMBUNGAN.
7. DEMPUL LUBANG-LUBANG BEKAS PAKU DAN SAMBUNGAN.
8. SELESAI
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 74/143
QUALITY
ASSURANCE
Semua aktifitas terencana dan sistematis yang di implementasikan
dalam suatu sistem mutu untuk memberikan keyakinan bahwa
proyek akan memenuhi standard mutu yang relevan
QUALITY CONCEPT
ZERO DEFECT : Tidak ada toleransi atas kesalahan didalam sistem. Tujuan dari semua proses adalahmenghindari cacat pada produk atau jasa.
Pelanggan adalah seseorang dekat anda berikutnya dalam
suatu proses. Do the Right Thing Right the First Time
Adalah lebih mudah dan lebih murah mengerjakan
pekerjaan yang tepat pada saat awal dari pada
melakukannya untuk kedua kalinya.
Continuous Improvement Process (CIP)
Mengakui bahwa dunia selalu berubah secara konstan dan
setiap proses yang hari ini telah memuaskan mungkin tidak
akan memuaskan lagi pada esok hari.
Project Quality Management
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 75/143
1.Quality Planning
2.Quality Assurance
3.Quality Control
PROCESS PLANNING PROCESS EXECUTING PROCESS CONTROLLING
Perencanaan mutu proyek,sesuai spesifikasi & sistempengujian/test, tertuangdalam PQP
Pelaksanaan Sistem Mutu,baik secara sistem maupunteknis mutu pelaksanaan
Pemantauan Sistem Mutu, padaproses pelaksanaan, in coming , in
process, final process. Untukmemastikan tercapainya mutu
pelaksanaan
Audit Mutu InternalPelaksanaan Audit Mutu Internal
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 76/143
Proses :
PROSES
KONTROL
OUTPUT
SUMBER DAYA
INPUT
• Material
• Informasi
• Prosedur • Spesifikasi
• Training/kualifikasi
• Sasaran/target
• Peralatan
• Orang
• Sasaran
• Kualitas produk
ISO 9001 : 2000Sections 1 - 4 covers scope, exclusions and general quality management system requirements.
Seksi 1 4 mencakup ruang lingkup pengecualian dan persyaratan umum sistem manajemen
Quality Management System Requirements
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 77/143
INPUT PROCESSESINPUT OUTPUT
5. Management ResponsibilityTanggung jawab Manajemen
6. Resource ManagementManajemen Sumber Daya
7. Product Realization
Realisasi Produk
8. Measurement, Analysisand Improvement
Pengukuran, Analisis danPenyempurnaan
Seksi 1 - 4 mencakup ruang lingkup, pengecualian dan persyaratan umum sistem manajemen
mutu.
Management Responsibility
Resource Management
Product Realization
Measurement, Analysis and Improvement
Continual Improvement of theQuality Management System
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 78/143
ManajemenSumber Daya
Input
Tanggung JawabManajemen
PerwujudanProduk
Produk
Output
Pengukuran, Analisa danPeningkatan
Kegiatan Pertambahan Nilai
Aliran Informasi
PLAN
DO
ACTION
CHECK
Tahapan “Quality Control”untuk mencegah ketidaksesuaian pada setiap tahapan, maka perlu dilakukan pengendalian pada setiap kondisi
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 79/143
Incoming Control
Pengendalian Pada setiap
Permulaan Kerja dan
Kedatangan bahan
In process Control
Pengendalian Pada setiap
Proses Pekerjaan
Final Control
Pengendalian Pada Akhir
Proses Pekerjaan
Initial Control
Pengendalian Parameter
Quality (Spesifikasi, Job
Mix, Test Material, Dsb)
KESESUAIAN PRODUK
1
2
3
4
1. Initial Control
Pengendalian ‘quality’ paling awal dari semua tahapan konstruksi yang ada.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 80/143
Initial Inspection lebih dominan sebagai Engineering Process
– Pemahaman design (Posisi, Dimensi, Quantity dan BentukRencana)
– Pemahaman Spesifikasi (Karakter Material Rencana)
– Persetujuan Material ( Test Sample Material, Brosur-brosur,
Mock Up,)
– Pembuatan Job Mix Formula (Beton,Mortar)
– Proposal Justifikasi Teknis (Design Usulan/Alternatif &Hitungan Teknis Jika Ada)
– Persetujuan Shop Drawing/Gambar Kerja lapangan
– Persetujuan RENCANA MUTU KONTRAK
PIC Quality – Initial Control
Engineering (Design, Justek, Shop Drawing), Procurement
(Persetujuan Material), Laborat (Test Sample Material, Job Mix
Formula)
2. Incoming ControlPengendalian Pada saat Permulaan Kerja dan Kedatangan Bahan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 81/143
• Permulaan Kerja
– Uitzet Posisi, Bentuk, Dimensi Pekerjaan, dibandingkan terhadap rencana
• Kedatangan Material
– Pemeriksaan Material datang, dibandingkan dengan Material Contoh
(Visualisasi/Bentu k/Warna, Dimen si/Ukuran, Merk, Type, Serial dsb)
– Pemeriksaan Proses Produksi Material, dibandingkan dengan Job Mix
(Beton Ready Mix, Factory Visit untuk material Pabrikan ds b)
– Test Berkala terhadap material datang (cara acak/sampling)
(Slump Test, Test Baja tulangan ds b) • PIC Quality
Procurement (Pemeriksaan Material), Laborat (Proses Produksi & Test Berkala)
Superviser (Uitzet Posisi, Bentuk dan Dimensi)
• Dimungkinkan penggunaan alat penguji, sample pembanding
3. Inprocess Control
Pengendalian Pada setiap Proses Pekerjaan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 82/143
• Checking Kesesuaian dengan Shop Drawing
• Checking Kesesuaian dengan Mock Up
• Checking Kesesuaian hasil penghamparan Aspal• Dilakukan secara Kontinu - Checking
• PIC Quality
Superviser dan Quality Officer
4. Final Control
Pengendalian Pada Akhir Pekerjaan
• Checking Hasil Akhir Mutu Beton
• Checking Ketebalan Aspal (Core drill)
• Checking Kadar Aspal (Extrac)
• PIC Quality
Superviser dan Quality Officer
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 83/143
Quality Control sebagai Tujuan
Inspeksi dan Test sebagai Alat/Parameter Pencapaian
FLOW CHART PEMERIKSAAN BESI BALOK LAPANGAN
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 84/143
JUMLAH BESI
CHECK BESI BALOK
SELESAI
TAMBAH BESI
GANTI SESUAI SHOP DRAWING
TIDAK SESUAI
OK
OK
TIDAK SESUAICHECK DIAMETER
BESI
CHECK JARAK
JARAK ANTAR BESI
CHECK POSISI
TULANGAN
DI PERBAIKIOK
DI PERBAIKI OK
TIDAK SESUAI
TIDAK SESUAI
FLOW CHART PENGECHECKAN BESI KOLOM
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 85/143
CHECK BESI KOLOM
SELESAI
DITAMBAH
DIGANTI
TIDAK SESUAI
SESUAI
TIDAK SESUAI
CHECK JUMLAH
CHECK DIAMETER
CHECK TERHADAP
POSISI
DI PERBAIKI
SESUAI
SESUAI
TIDAK SESUAI
FLOW CHART CHECK PEMBESIAN BESI PLAT
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 86/143
CHECK BESI PLAT
SELESAI
DI PERBAIKI
DIGANTI
TIDAK SESUAI
SESUAI
TIDAK SESUAI
CHECK JARAK
CHECK DIAMETER
CHECK TERHADAP
OVERLAP
DI PERBAIKI
SESUAI
TIDAK SESUAI
FLOW CHART PEMERIKSAAN BEKISTING
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 87/143
BEKISTING BALOK,KOLOM,
PLAT
SELESAI
DI PERBAIKI
PERBAIKI
TIDAK SESUAI
SESUAI
TIDAK SESUAI
CHECK TERHADAP
POSISI
CHECK DIMENSI
CHECK TERHADAP
ELEVASI
DI PERBAIKI
SESUAI
TIDAK SESUAI
SESUAI
FLOW CHART PENGENDALIAN MUTU BESI
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 88/143
CHECK MILL SHEET
BESI SAMPAIDI SITE
DIPRODUKSI
SELESAI
TEST BESI
GUDANG
TOLAK
TOLAK DIKEMBALIKANKE PABRIK
TIDAK MASUK
MASUK
MASUK
TIDAK MASUK
FLOW CHART PEMELIHARAAN BETON
MULAIMULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 89/143
BUAT TANGGULKELILING TEPI PLAT
BETON PLATHASIL COR
RENDAM DENGAN
AIR PBI. 14 HARI
SELESAI
BUNGKUS KOLOMDENGAN KARUNG
BETON KOLOMHASIL COR
SIRAM KOLOM DENGAN
AIR MIN 3X SEHARI
SELESAI
FLOW CHART PENGENDALIAN MUTU BETON
MULAI
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 90/143
CHECK SLUMP BETON
BETON READY MIXDI SITE
COR BETON
SELESAI
BENDA UJI
TOLAK
RENDAM
TIDAK MASUK
MASUK
TEST SESUAI
UMUR
Periode Check List Periode
Serah Terima I
Periode
Serah Terima II
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 91/143
YES
START
PERSIAPAN
PEMBERITAHUAN CHECK LIST I
REPAIR DC
YES
NO
1
2
3
CHECK LIST I
4
5
CHECK LIST II8
BERITA ACARACLOSE REPAIR DC
6
REPAIR AK7
NO
SERAH TERIMA I
RECORD I
Serah Terima I
MAINTENANCE PERIOD
SERAH TERIMA II
RECORD II
Serah Terima II
11
12
13
9
10
Manajemen Pengendalian Gambar Konstruksi
DETAIL RENCANA KONSULTAN PEMILIK KONTRAKTOR
a. Persetujuan GambarPelaksanaan ( Shop Drawing )
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 92/143
RENCANAPELAKSANAANINSTRUKSI UNTUK
MEMBUAT GAMBARPELKSANAAN
MEMBUATGAMBARPELAKSANAAN
EVALUASI
BUTUHEVALUASIRENCANA
PEMERIKSAANEVALUASIOLEH PIHAK YANGBERSANGKUTAN
TIDAK
PERSETUJUAN A / B / C / D
R E K O M E N D A S IOLEH PIHAK YANGBERSANGKUTAN
YA
COPY
DISTRIBUSIOLEH PIHAK YANGBERSANGKUTAN
DISTRIBUSI KE PROSESPELAKSANAAN
YA
DISTRIBUSI
PERSETUJUAN A / B / C / D
TIDAK
TIDAK
A
KETERANGAN :
= DISETUJUI
= DISETUJUI DENGAN CATATAN–TDK PERLU PENGAJUAN LAGIB
= PENGAJUAN LAGI SETELAH DI REVISI
= TIDAK DISETUJUI
C
D
DETAIL RENCANA KONSULTAN PEMILIK KONTRAKTOR
KOORDINASIPEKERJAANSELESAI 100%
b. Persetujuan As Built Drawing
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 93/143
DIPERIKSA
1 COPY
AS BUILTDRAWING
1. INSPEKSI2. DISTRIBUSI
2 COPY + ASLI 1 COPY
Max.7 Hr
REVISI
PERSETUUANCETAKBIRU
RENCANA DETAIL KONSULTAN PEMILIK KONTRAKTOR
INSTRUKSI RENCANA
Manajemen Pengendalian Pengadaan Material
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 94/143
INSTRUKSI
CONTOHMATERIAL
EVALUASI
MATERIALDENGANPERSETUJUAN
PELAKSANAAN
PERSETUJUAN
RENCANAKERJA
TIDAK
YA
PERSETUJUAN
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 95/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 96/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 97/143
BACK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 98/143
form work/pekerjaan struktur
railing perimeter
safety net perimeter
2 lantai
safety wing net
temporary railing
polynet
TUJUAN UTAMA K3L
1. Menghilangkan atau mengurang bahaya kerja, kecelakaan kerja dan atau mencegah
jatuhnya korban serta penyakait akibat kerja.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 99/143
j y p y j
2. Melindungi aset dan lingkungan terhadap kerusakan yang diakibatkan oleh adanya
aktifitas pekerjaan.3. Menjamin tidak terjadinya kerusakan pada lingkungan ditempat kerja dan kerusakan
lingkungan akibat pelaksanaan proyek.
4. Memastikan penerapan SMK3L sesuai persaratan Permenaker RI PER05/MEN/1996
dan OHSAS 18001:1999 serta ISO 14001:1996.
PERENCANAAN K3L
PENERAPAN DAN
OPERASI
PENGUKURAN
KINERJA AUDIT PERENCANAAN
POLICY
Sistem Manajemen K3L
• Merupakan suatu rangkaian proses kegiatan K3 yang memiliki siklus dimulai dari
kegiatan PERENCANAAN IMPLEMENTASI PEMANTAUAN dan PENINJAUAN
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 100/143
kegiatan PERENCANAAN , IMPLEMENTASI, PEMANTAUAN dan PENINJAUAN
KEMBALI .
• Prinsip dasar manajemen perbaikan melalui siklus Plan – Do – Check -Action.
• Rangkaian merupakan rangkaian tertutup yang mengandung spirit PERBAIKAN
BERKESINAMBUNGAN …..
TARGET K3L PROYEK
ZERO ACCIDENT
WAJIB HELM & APD
MATERIAL TERTATA RAPI
PROYEK BERSIH DAN SEHA
SAFETY PROGRAMME
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 101/143
GOALS SAFETY
INDUCTION
SAFETY
INSPECTIONEQUIPMENT
INDUCTION
TOOL BOX
MEETING
SAFETY
PATROL &
MEETING
FOGGING
AND
GENERAL
CLEANING
TRAINING
SAFETY
MONTHLY
REPORT
Zero
Accident All Staff &
Employee /
Worker
Daily by Safety
Officer Bi - Weekly Weekly
Morning
Time
Monthly Bi - Weekly Basic Safety
Fire Fighting
First Aid
Rigging
Welding
Recorded
by
Division
Office
* TARGET
Target untuk kecelakaan yang ingin di capai oleh PT. ADHIKARYA (Persero ) Tbk adalah tidak ada fatality dalam setiapkegiatan proyeknya. ( Target Zero Accident)
* SAFETY INDUCTION
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 102/143
* SAFETY INDUCTION
Pemberian Pengenalan peraturan safety proyek kepada setiap
karyawan dan sub kontraktor serta mandor yang terlibat dalamperoyek ini untuk partisipasi dan tanggung jawab terhadapkeselamatan kerja oleh semua pihak.
* TOOL BOX MEETING.
Memberikan penjelasan mengenai pentingnya keselamatankerja dalam bekerja pada bidang konstruksi bangunan danmemberikan informasi – informasi lapangan kepada pekerja
mengenai daerah bahaya, penanggulangan dan hal lainnya yang berkaitan yang akan diadakan setiap kamis pagi sebelumbekerja.
* SAFETY MONTHLY MEETING
Mempersentasikan hasil yang telah dicapai setiap bulannyakepada top management perusahaan dan subkont dan untuk menarik dukungan terhadap keselamatan kerja dari semua top
management setiap 1 kali sebulan tiap hari kamis.
BRIEFING LAPANGAN
RAPAT MINGGUAN
APEL PAGI
* SAFETY INSPECTION
Melakukan inspeksi pada setiap kegiatan, lingkungan dan peralatanyang memungkinkan untuk terjadinya kecelakaan dan melakukantindakan pencegahannya secara langsung serta membuat sistempelaporan.
* SAFETY PATROL
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 103/143
* SAFETY PATROL.
Melakukan patrol tiap senin siang bersama semua topmanagement ke lapangan untuk mengetahui permasalahankeselamatan kerja di lapangan.
* FOGGING
Penyemprotan nyamuk di lapangan untuk mencegah penyakit yang dapat ditimbulkan oleh serangga dan sejenisnya sebagai salah satukepedulian kami terhadap kesehatan pekerja
tiap hari sabtu sore.
* GENERAL CLEANING AND HOUSE KEPPING.
Melakukan pembersihan secara masal yang melibatkan seluruhpekerja dan seluruh subkontraktor di lapangan untuk menciptakanlapangan kerja yang selalu bersih dan rapih setiap sabtu siang.
SAFETY PATROL
FOGGING
GENERAL CLEANING
PROGRAMME JOB DESCRIPTION PIC
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 104/143
1. DAILY
ACTIVITY
1. Introducing Health & Safety Work ti all Staff & Warkers Safety Manager
Safety Staff & Daily Worker
2. Briefing on daily programme Safety Manager
Safety Officer
3. Safety Patrol Safety Manager
Safety Officer
Security
4. Safety ( K3 ) Daily Report Safety Officer
5. Cleaning Inspection Safety Officer
6. Monitoring Site & Surrounding Security Safety Manager
Safety Officer
Security
7. First Aid Safety Staff
PROGRAMME JOB DESCRIPTION PIC
1. Tool Box Meeting Safety Staff
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 105/143
2. WEEKLY
ACTIVITY
Evaluating Last Week Programme All Site Staff
Next Week Work Programme All Workers
2. Safety Inspection Safety Manager
Safety Officer
Security
Supervisor
Sub Contractor
3. General Cleaning All Workers
4. Management Review Meeting ( Every Wednesday ) Safety Supervisor
5. Fogging depend on Site Conditions ( if necessary ) Safety Supervisor
6. Coordination with Surrounding Hospital, Depnaker and Safety Officer
Insurance Company ( Temporary ) Each Sub Contractor
7. Coordination with Project Stakeholders Safety Manager ( Owner/Employer, Engineer, NSC )
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 106/143
PROGRAMME JOB DESCRIPTION PIC
3. MONTHLY
1. Safety Report Safety Manager
ACTIVITY
2. General Safety Inspection Safety Manager
Safety Officer
Other Manager
3. Varius Job Safety Staff
RAMBU
Pemasangan rambu dalam proyek yang berisikan pesan berupa larangan, perhatian, ataupun anjuran
yang bertujuan untuk menertibkan setiap orang yang berada di dalam areal proyek, baik itu pekerja
ataupun tamu yang datang agar tertib dalam K3L.
IMPLEMENTASI K3L DI PROYEK
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 107/143
PINTU MASUK JALAN UTAMA PINTU MASUK
PROYEKSPANDUK
Pemasangan spanduk dalam proyek yang berisikan informasi berupa informasi tertentu ataupun tata tertib
bertujuan untuk menertibkan setiap orang yang berada di dalam areal proyek agar tertib dalam K3L.
GERBANG JALAN KERJA TATA TERTIB PROYEK ANJURAN ATURAN
SAFETY SIGN( Rambu-rambu K3L)
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 108/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 109/143
Wujud kasih sayang kita kepada keluarga adalah bekerja
sesuai dengan petunjuk kerja aman dan tidak ceroboh
Pelajari, pahami Buku Panduan K3 ini.
Camkan mana yang terkait dengan pekerjaan yang akan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 110/143
sesuai dengan petunjuk kerja, aman dan tidak ceroboh.
Kita adalah tumpuan harapan keluarga.
Camkan mana yang terkait dengan pekerjaan yang akan
dilakukan dan laksanakan sesuai petunjuk kerja.
Kecelakaan kerja lebih sering terjadi di bidang industri
konstruksi dibandingkan bidang lain dan karena itulah
Tidak adanya kekompakan di antara rekan sekerja lapangan
seringkali menjadi penyebab terjadinya kecelakaan. Setiap
k h i t b h
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 111/143
konstruksi dibandingkan bidang lain, dan karena itulah
perusahaan menyediakan sarana keselamatan untuk
mencegah terjadinya kecelakaan pada diri anda. Tetapi
yang paling dibutuhkan adalah kerjasama anda. Anda
harus sungguh-sungguh mematuhi semua peringatan
yang tertera dalam Buku Panduan ini agar tempat kerja
anda aman dan menyenangkan!
karyawan harus ingat bahwa :
Kita semua adalah bagian dari kelompok
Kita harus sealu saling membantu
Kita harus selalu mengalah pada rekan satu kelompok kerja
Kita harus selalu saling memberi salam saat masuk kerja pada pagi
hari dan saat kita pulang
Patuhi dengan sungguh-sungguh peraturan keselamatan
kerja yang ada di lokasi (berbagai peringatan dan aturan
rutin). Undang-undang nasional menyebutkan bahwa “Pekerja
harus mematuhi peraturan yang dibuat untuk mencegah
terjadinya kecelakaan kerja dan harus bekerjasama dalam
Dengarkan baik-baik penjelasan yang disampaikan oleh
mandor anda, atau atasan anda lainnya, mengenai kondis
tempat kerja anda saat ini dan pahami semua yang
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 112/143
mengambil langkah-langkah pencegahan kecelakaan kerja
yang ditetapkan oleh perusahaan dan pihak-pihak lain yangberkepentingan.”
Undang-Undang tersebut juga menharuskan karyawan
mematuhi ketentuan tentang pemakaian helm proyek, sabuk
pengaman dan masker pernapasan. (Pasal 26, Undang-
Undang Kesehatan dan Keselamatan Kerja).
tempat kerja anda saat ini dan pahami semua yang
dikatakannya.
Kenali tempat-tempat yang membahayakan, jalur yang aman
tempat mengamankan diri.
Caritahu lokasi alat pemadam api dan peralatan P3K
Selalu hadiri pertemuan harian di lokasi kerja yang membahas
masalah keselamatan saat upacara pagi dan pertemuan pada
akhir jam kerja.
<Siklus Mingguan>
P b ih k j b
Setiap hari sebelum mulai bekerja, patuhi ketentuan mewaspadai
bahaya, dan :
Semua orang bersama-sama memikirkan cara mewaspadai bahaya.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 113/143
Pembersihan tempat kerja bersama-sama
<Siklus Bulanan>Inspeksi bulanan, dll.
Diskusikan langkah-langkah yang harus ditempuh.
Tetapkan prosedur kerja paling aman yang akan dipakai.
Setiap karyawan harus berpakaian dengan rapih.
Selalu kenakan baju kerja yang bersih.
Jahit bagian baju yang robek dan lepas jahitannya, dll.
Helm pengaman harus selalu ada pakai. Luka di kepala bisa
membahayakan diri anda!
Tali pengikat helm pengaman harus selalu terpasang dengan baik
dan kencang
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 114/143
Ujung kemeja dan celana harus selalu terkancing dengan baik.
Pakai selalu sepatu yang aman sesuai jenis pekerjaan anda atau
pakai sepatu cats yang mempunya sol anti selip.
Helm harus dipakai dengan posisi yang benar dan jangan dipakai dibelakang kepala.
Selalu kenakan sarung tangan pengaman sebagaimana
diwajibkan ketika mengangkut barang berat di lokasi kerja.
Pilih sarung tangan yang sesuai dengan jenis pekerjaan anda.
(Gunakan sarung tangan tahan getar untu pekerjaan vibrasi).
Selalu gunakan sabuk pengaman jika anda bekerja di tempat tinggi yang
tidak berlantai atau berbagar, atau ketika anda bekerja di tempat yang
mewajibkan pengunaan sabuk pengaman.
Sabuk pengaman harus dikaitkan ke kabel yang sudah terpasang baik
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 115/143
(Gunakan sarung tangan tahan getar untu pekerjaan vibrasi).
Jangan kenakan sarung tangan jika mengoperasikan bor listrik.Sabuk pengaman harus dikaitkan ke kabel yang sudah terpasang baik.
Jika anda bekerja sambil berpindah-pindah, pastikan bahwa kabel dalam
keadaan tegang sebelum sabuk pengaman anda pasangkan
Sabuk pengait tunggal hanya boleh digunakan dengan cara yang sudah
ditetapkan perusahaan.
Di tempat kerja banyak terpasang rambu-rambu untuk
keselamatan anda. Pelajari apa arti masing-masing rambu
dan bekerjalah dengan hati-hati!
Selalu kenakan peralatan pelindung yang sesuai dengan jenis
pekerjaan anda saat berada di lokasi.
Selalu kenakan kacamata las jika bekerja dengan alat las listrik
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 116/143
Jangan merusak rambu atau memindahkannya ke tempat
lain.
atau gas atau alat pemotong.
Kenakan masker anti debu dan kacamata pelindung debu saatmelakukan pekerjaan yang menghasilkan debu.
Jika pekerjaan yang anda lakukan menimbulkan suara yang
keras, kenakan penutup telinga.
Di tempat kerja, telah ditetapkan berbagai sinyal/tanda-
tanda untuk digunakan. Pelajari apa arti masing-masing
sinyal/tanda-tanda dan patuhi sinyal/tanda-tanda yang
diberikan oleh siapapun yang ada di lokasi.
<Untuk jenis jenis pekerjaan dibawah ini telah ditetapkan
Selalu gunakan jalur orang yang telah ditetapkan
meskipun anda sedang terburu-buru!
Jalur orang yang tinggi letaknya, balok penyangga dan
tangga harus selalu dalam keadaan aman untuk
di k i
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 117/143
<Untuk jenis-jenis pekerjaan dibawah ini telah ditetapkan
sinyal/tanda-tanda tertentu>
Mengangkut barang dengan
tali baja.
Saat menjalankan kendaraan
konstruksi dan memindahkan
crane, dsb.
Saat mengoperasikan lift dan
katrol.
Pekerjaan dengan
menggunakan tekanan tinggi
Pekerjaan peledakan batu
dipakai
Jangan biarkan ada barang-barang yang menghambat
gerak di jalur yang dilalui orang.
Pindahkan semua hambatan yang ditemui.
Pastikan bahwa barang-barang ditumpuk dengan baik agar
tidak berjatuhan.
Jangan menumpuk barang terlalu tinggi
Barang-barang yang ukurannya panjang tidak boleh diletakan
Semua barang yang mudah menggelinding harus diberi
penahan atau diikat agar tidak bergerak dari posisinya.
Setiap kali menumpuk barang, selalu gunakan palet atau
penyangga.
Jangan menumpuk barang yang berbeda-beda bentuk,
panjang dan ukurannya dalam satu tumpukan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 118/143
dalam posisi berdiri. Letakkan barang-barang tersebut dalam
posisi rebah dan teratur.Barang tidak boleh menghalangi jalan, dan jangan meletakkan
barang di atas balok atau pondasi, dll.
Jangan meletakkan barang-barang di pinggir tempat kerja atau
dekat pintu.
panjang dan ukurannya dalam satu tumpukan.
Sejak awal, pisahkan barang-barang yang sedang dipakaidan yang tidak dipakai.
Ketika menumpuk barang, tumpuklah dari yang terberat
sampai yang teringan, dan dari yang terbesar sampai
yang terkecil.
Tabung oksigen dan barang-barang berat yang mudah
terjatuh harus diikat dengan baik agar tidak jatuh.
Agar pekerjaan bisa diselesaikan dengan aman dan
cepat, patuhi urut-urutan kerja yang baik dan benar yang
anda pelajari dalam pertemuan (harian)
Lakukan pekerjaan dengan urut-urutan seperti yang telah
Periksa semua perkakas sebelum digunakan
Segera ganti perkakas yang rusak
Perkakas yang digunakan untuk pekerjaan di tempat yang
tinggi harus dilengkapi tali pengikat untuk mencegahnya agar
id k j h
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 119/143
Lakukan pekerjaan dengan urut urutan seperti yang telah
ditetapkan oleh pimpinan di lokasi kerja (mandor).Jangan melakukan sendiri; jangan mencoba melakukan
sesuatu yang belum pernah dikerjakan sebelumnya.
tidak jatuh.
Jangan pernah biarkan perkakas tidak dibersihkan. Selalubersihkan perkakas setiap kali selesai digunakan.
Setelah digunakan selalu simpan kembali perkakas di tempat
yang disediakan.
Jangan melakukan pekerjaan dengan posisi tubuh
menjulur dari tangga.
Pasang tangga ditempat datar, dan jangan lupa untuk
memasang penguncinya
Ketika menggunakan tangga, selalu jaga agar tangga tersebut tidak jatuh
atau terbalik.
Jangan menaiki tangga hanya dengan satu tangan yang bebas sementara
tangan lain mengangkat sesuatu.
Jangan ada lebih dari satu orang yang naik atau turun tangga pada saat
yang bersamaan.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 120/143
memasang penguncinya.
Hanya boleh ada satu orang diatas tangga.Tangga dan kuda-kuda adalah dua peralatan yang
berbeda. Setiap kali menggnakan tangga, pilih yang
pijakannya datar.
Ketika menggunakan diatas kuda-kuda atau tanggga,
selalu pastikan papannya terpasang dengan baik.
Ketika menggunakan tangga untuk bekerja di ketinggian
lebih dari 2 meter, selalu gunakan sabuk pengaman.
yang bersamaan.
Jangan melakukan apapun ketika berdiri diatas anak tangga.Posisi tubuh harus selalu menghadap tangga saat menaiki atau menuruni
tangga.
Sebaiknya anda tidak menggunakan tangga jika menggunakan sepatu bot
atau sandal.
Gunakan tangga dengan kaki atau penahan anti selip dan pasang tangga
tersebut dengan baik.
U jung atas tangga harus menjulur 60cm dari bagian atas bangunan dan
membentuk sudut sekitar 75 derajat.
Scaffolding/Steger beroda bisa terbalik, karena itu berhati-hatikah
saat menggunakannya.
Pasang rem pada rodanya.
Turun atau naik harus melalui bagian steger yang disediakan
khusus untuk itu.
Selalu berhati-hatilah jika bekerja di atas steger
karena bahaya jatuh selalu ada!
Saat menaiki atau menuruni steger, selalu gunakan
jalur atau tangga yang tersedia.
Jangan membuka sendiri pegangan tangan atau
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 121/143
Jangan gunakan steger pada bidang yang miringJangan pindahkan steger jika ada orang di atasnya.
Jangan naik atau turun dari steger sambil memegang sesuatu.
Jangan cabut pegangan tangan pada steger
Jangan menjulurkan tubuh saat bekerja menggunakan steger.
Jangan membuka sendiri pegangan tangan atau
pengikat.Jangan memindahkan sendiri papan lantai.
Setiap kali melakukan pekerjaan di atas atap genteng
atau atap asbes, jaga jangan sampai anda jatuh karena
atap pecah.
Ketika berjalan melintasi atap genteng atau asbes, selalu
alasi atap dengan papan selebar minimal 30 cm
Saat melakukan pekerjaan di atas atau di bawah gedung,
selalu waspadai benda-benda yang jatuh.
Jika di atas sedang dilakukan pekerjaan, jangan bekerja di
bawah tempat tersebut.
Jika melakukan pekerjaan di bagian atas dan bawah pada
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 122/143
alasi atap dengan papan selebar minimal 30 cm.
Selalu gunakan penyangga dan kenakan sabukpengaman.
p j g p
saat bersamaan, usahakan untuk selalu bekerjabersamaan.
Dilarang melempar benda apapun.
Pekerjaan pengecoran lapisan beton selalu dilakukan bersama pekerja
lain, jadi semua pekerja yang terlibat harus sama-sama waspada.
Selang pemompa bahan coran dari mesin pemompa bisa tiba-tiba
bergerak tak terkendali, jadi berhati-hatilah.
Sebelum mulai menuangkan bahan coran yang bertekanan tinggi,
patikan bahwa semua sambungan sudah rapat.
Berhati-hatilah ketika bekerja di area terbuka yang tidak
terlindung.
Jangan sembarangan membuka pegangan tangan atau
penutup tanpa alasan.
Setiap kali diperintahkan untuk membuka pegangan tangan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 123/143
patikan bahwa semua sambungan sudah rapat.
Berhati-hatilah jangan sampai jari atau tangan anda terjepit saatmenyetel talang pada molen.
Jangan cabut talang sebelum bahan coran berhenti mengalir.
Ketika melakukan pekerjaan di pinggir work platform, selalu kenakan
sabuk pengaman.
kembalikan lagi begitu pekerjaan selesai dilakukan.Setiap kali membawa barang melintasi area yang terbuka,
kenakan sabuk pengaman.
Jangan sampai menjatuhkan barang dari area terbuka.
Jaga agar tempat kerja selalu bersih, teratur dan rapih,
dan pekerja harus saling memberi informasi.
Amankan jalur orang (pathway)
Jaga agar bahan pencetak tidak rusak.
Perhatikan urut-urutan kerja yang akan dilakukan sebelum dimulai.
Periksa semua perkakas yang akan digunakan hari itu sebelum
mulai bekerja.
Sebelum mengangkut besi seton, periksa jalur transportasi dan
tempat penyimpanan agar tidak timbul kecelakaan
Di tempat kerja dengan ketinggian lebih dari 2m dan tanpa
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 124/143
Saat menggunakan tangga, jangan melakukan pekerjaanapapun saat berdiri di atasnya.
Bersihkan selalu perkakas listrik anda.
Saat memasang cetakan beton, ikuti petunjuk pengawas
lokasi
Di tempat kerja dengan ketinggian lebih dari 2m dan tanpa
pengangan, kenakan selalu sabuk pengaman.Saat mengikat besi beton dengan menggunakan tangga, jangan
melakukannya sambil berdiri diatas tangga.
Saat mengikat besi beton berdua dengan rekan kerja anda, lakukan
pekerjaan itu bersamaan
Operator mesin harus selalu melakukan inspeksi
sebelum mulai bekerja.
Operator mesin harus selalu mematuhi arahan
petugas pengatur lokasi.
Selalu bekerja dengan hati-hati agar tidak bertubrukan atau
terjepit diantara mesin.
Jangan berjalan di bawah barang yang sedang diangkat
dengan derek.
Saat bekerja dekat mesin pengeruk tanah buldoser dll Selalu
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 125/143
Saat meninggalkan mesin derek, bagian mesin
yang bergerak harus dalam posisi di atas tanah,
rem dipasang, dan kunci selalu dicabut.
Saat bekerja dekat mesin pengeruk tanah, buldoser, dll. Selalu
ikuti perintah pengatur lalu lintas.
Jangan masuk ke area kerja mesin derek atau crane.
Semua karyawan harus melakukan pekerjaannya dengan hati-
hati agar bahaya kebakaran bisa dihindari.
Dilarang merokok atau menyalakan api di lokasi kecuali di
daerah-daerah yang telah ditetapkan.
Setiap kali menyalakan api, selalu sediakan ember berisi air di
Saat bekerja ditempat bertekanan tinggi seperti sumuran
dan terowongan anda bisa terkena gangguan kesehatan
akibat tekanan yang tinggi; karena itu tindakan
pencegahan harus dilakukan.
Pekerjaan hanya boleh dilakukan setelah anda
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 126/143
Setiap kali menyalakan api, selalu sediakan ember berisi air di
dekat anda.Selalu ketahui lokasi alat pemadam api dan cara
menggunakannya.
Saat melakukan pengelasan, selalu gunakan kain pelindung
untuk menghidari percikan api
mendapatkan pelatihan khususAnda harus bekerja di bawah perintah langsung
pengawas.
Anda harus mematuhi dengan sungguh-sungguh waktu
kerja yang ditentukan untuk masing-masing jenis
pekerjaan bertekanan tinggi.
Patuhi dengan sungguh-sungguh waktu yang ditetapkan
untuk proses kompresi dan dekompresi.
Lakukan pemeriksaan kesehatan khusus secara teratur.
Kita harus selalu waspada akan bahaya saat bekerja dengan
listrik.
Sengatan listrik yang besarnya hanya 100 volt pun bisa
menyebabkan orang meninggal dunia.
Saat memindahkan pipa berukuran panjang jaga agar pipa
Pelajari dengan seksama dan pahami Buku
Panduan penggunaan perkakas listrik, serta
gunakan perkakas tersebut dengan cara yang
aman.
Periksa perkakas listrik anda sebelum digunakan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 127/143
Saat memindahkan pipa berukuran panjang, jaga agar pipa
tidak bersentuhan dengan kabel listrik.
Setelah sekering dimatikan untuk memutus aliran listrik,
segera beritahu pengawas anda.
Jangan sentuh saklar di panel pembagi jika anda hanya
sendirian.
Setiap kali melakukan pekerjaan yang berisiko terkena
sengatan listrik, gunakan sarung tangan karet dan sepatu bot
karet.
setiap hari.Pastikan bahwa perkakas anda sudah diberi
arde.
Pastikan bahwa fasilitas pengaman difungsikan
Setiap berjalan sambil membawa perkakas listrik
pastikan bahwa perkakas tersebut sudah
DIMATIKAN.
Setiap kali pekerjaan selesai, bersihkan perkakas
anda dengn baik.
Setiap kali bekerja di dalam gedung dengan menggunakan
cat atau perekat selalu ada bahaya keracunan bahan pelarut
organik; karena itu diperlukan tindakan pencegahan.
Pekerjaan hanya bisa dilakukan setelah anda mendapatkan
pelatihan untuk menangani bahan pelarut organik.
Saat melakukan pengeboram dan pemecahan batu yang
menimbulkan suara bising, ada kemungkinan terjadina
kerusakan organ tubuh akibat getaran dan kerusakan
pendengaran; oleh karena itu kita harus melakukan tindakan
pencegahan yang diperlukan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 128/143
pelatihan untuk menangani bahan pelarut organik.
Lakukan pekerjaan sesuai perintah pengawas anda.Ventilasi yang baik harus selalu tersedia selama pekerjaan
dilaksanakan.
Selama bekerja, kenakan masker ventilasi atau masker gas.
Lakukan pemeriksaan kesehatan khusus secara teratur.
Pekerjaan hanya boleh dilakukan setelah anda mendapatkanpelatihan tentang pengaruh getaran pada kesehatan tubuh.
Penggunaan perkakas getar hanya diizinkan untuk waktu 2
jam saja per hari.
Pekerjaan hanya boleh dilakukan dengan menggunakan
sarung tangan anti-getar dan penutu telinga.
Anda harus melakukan gerak badan sebelum dan sesudah
bekerja untuk melemaskan otot-otot anda.
Lakukan pemeriksaan kesehatan khusus secara teratur
Perhatikan dan jaga kesehatan anda sendiri.
Periksakan kesehatan anda secara teratur
Sering-seringlah mencuci tangan anda dan berkumur.
Jangan makan dan minum terlalu banyak.
Jangan bergadang dan tidurlah yang cukup.
Nikmatilah kehidupan di mess/asrama.
Jangan merokok di tempat tidur.
Jangan membuat gaduh setelah lampu asrama dimatikan.
Simpan dengan rapih barang-barang pribadi anda dan jaga
jangan sampai rusak; jaga agar kamar anda selalu bersih.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 129/143
Patuhi dengan sungguh-sungguh aturan yang berlaku di asrama.
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 130/143
COUPLER
TIANG RAILINGHANDRAIL
HANDRAIL
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 131/143
INSTALLATION
CORNER
MID HANDRAIL
BESI BEHEL D12
BASEPLATE
POLYNET
BESI BEHEL D12
TIANG RAILING
POLYNET INSTALLATIONS VERTICAL (STAIR CASE)
DETAIL SIKU
SIKU
MID
HANDRAIL
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 132/143
HANDRAIL
MID HANDRAIL
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 133/143
OPENING > 2 M / VOID AREA
KAWAT AYAM + SAFETY NET
BESI BEHEL D12
OPENING 100 ~ 600 mm
OPENING 650~ 2000 mm
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 134/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 135/143
SIKU
KASO / BESI
MID HANDRAIL
HANDRAIL
SWIVE
L
CLAMP
ANAK TANGGA
OVERLAP
Min.500mm
KAWAT HARMONIKA
(LAYER 1) +POLYNET
(LAYER 1)
PIPE Dia. 1 ½”
D16
CLAMP
SLING
Dia.10mm
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 136/143
SLINGDia.10mm
MID BRACING
BEHEL D16
CROSS BRACING
BEHEL D13
PIPE Dia.1 ½”
L50x50,
100mmPIPE Dia. 1 ½”,
750mmDYNABOLT M12
PIPE Dia. 1 ½”
PIPE Dia. 2”,
100mm
Safety Wing
setiap 2 Lantai
dari pelaksanaan
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 137/143
RANGKA INSTALLATION
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 138/143
BAR CUTTER
BAR BENDER
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 139/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 140/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 141/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 142/143
7/17/2019 Metode Pelaksanaan Gedung (1)
http://slidepdf.com/reader/full/metode-pelaksanaan-gedung-1 143/143