SU.S.NRC United States Nuclear Regulatory Commission Protecting People and the Environment Information Briefing on Emergency Preparedness May 3, 2011

Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

SU.S.NRCUnited States Nuclear Regulatory Commission

Protecting People and the Environment

Information Briefing on

Emergency Preparedness

May 3, 2011

Page 2: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Evolution of NRC EmergencyPreparedness Regulations

" Emergency Planning Basis

" Pre-Three Mile Island

" Post-Three Mile Island

* State/Local Participation

* Post-September 11, 2001

2

Page 3: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EP Rulemaking Process

too

Draft PreliminaryRule and Technical

Basis Development

Proposed Rule and DraftGuidance Development

CommentResolution Final Rule to

Commission

Draft Preliminary Proposed Rule and Final RuleRule Language Draft Guidance Published and Guidance

Issued (Public Comments PublishedAccepted for 150 days)

3

Page 4: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EP Rulemaking Topics

1 Amended Emergency Plan Change Process

2 Evacuation Time Estimate Updating

3 Licensee Coordination with Offsite Response Organizations*

4 On-Shift Staffing Analysis*

5 Emergency Action Levels for Hostile Action*

6 Emergency Declaration Timeliness

7 Alert and Notification System Backup Means

8 Emergency Operations Facility - Performance-Based Approach

9 Emergency Response Organization Augmentation at Alternative Facility*

10 Challenging Drills and Exercises*

11 Protection for Onsite Personnel*

12 Removal of Completed One-Time Requirements

(*) Indicates Security-Related EP Topic

4

Page 5: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

NRC Guidance Documents

" NUREG/CR-7002

" Regulatory Guide 1.219

* NSIR/DPR-ISG-01

5

Page 6: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Public Comments

" Emergency Plan Change Process

" Evacuation Time EstimateUpdates

o Licensee Identification of OffsiteSupport

6

Page 7: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Public Comments (Continued)

" On-Shift Staffing Analysis

" Alert and Notification SystemBackup Means

" Exercise Cycles and Variations

7

Page 8: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Implementation Considerations

" Alignment with FEMA

" Cumulative Effects of Regulation

" Implementation Periods

" Implementation Workshops

" Follow-Up Inspection

8

Page 9: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

AcronymslAbbreviations*ACRS

*ANS

* CFR

*EP

* EPA

" EPZ

" ERO

" ETE

* FEMA

Advisory Committee onReactor Safeguards

alert and notification system

Code of Federal Regulations

emergency preparedness

Environmental ProtectionAgency

emergency planning zone

emergency responseorganization

evacuation time estimate

Federal EmergencyManagement Agency

• FOF force-on-force

*ISG Interim Staff Guidance

*NEI Nuclear Energy Institute

•NGO non-governmentalorganization

*NRC Nuclear RegulatoryCommission

*PNREP National RadiologicalEmergency Preparedness

oSRM staff requirementsmemorandum

OTMI Three Mile Island

9

Page 10: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Backup Slides

10

Page 11: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EP Rule Implementation DatesOROP6ftD MI iUL-E' rK~LE FiiAL#ý RULE4 U~bTE lREVISEDAFNAL RULE-`

#~ EPU RUET~,IPEE TOIPEENTATION STAKEHOLD~ER IMPLEMENTATION4____________ PERIOD (2009)ERLETOI M EMITAiN(09 PERIOD (2010) INPUT (2010) PERIOD L(2011)

, Amended 30 days after date of 30 days after date ofI Emergency Plan final rule publication in 12 months final rule publication in 90 days None

• Change Process Federal Register Federal Register

Within 365 days of the Within 365 days of the later

Evacuation Time 6 months after date of later of the availability of the availability of2 final rule publication in 12 months of decennial census 12 months•,'i Estimate Updating• decennial census data or

Federal Register data or effective date effective date of final rule

of final rule

Licensee 6 months after date of 365 days after date of

Coordination with final rule publication in 24 months final rule publication in Up to 36 months 30 of from e! Offsite Response date of final rule•'• rgniaton Federal Register Federal Register•!iOrganizations

365 days from effective dateof final rule to perform

O 6 months after date of 180 days after date of staffing analysis, then 304O Stalys n final rule publication in 36 months final rule publication in 36 months days to implement interim< Federal Register Federal Register comp. measures and 24

months to complete long-

term corrective actions

Emergency Action 6 months after date of 180 days after date of 180 days from effective date5 Levels for Hostile final rule publication in 36 months final rule publication in 36 months of final rule

• Action Federal Register Federal Register

11

Page 12: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EP Rule Implementation DatesPROPOS,#D RULE 9W FIAL RULE' U AED REVISED FINAL -RULE

# EP RULE TOPIC; IMPLEMENTATION NPT O9 IMPLEMENTA'TION STKHLE MPEETTO

_________ PERIOD (2009) PERIOD (2010)~ INPUT ý(2O10) ~ PERIODp(2O114)~

Emergency 6 months after date of 180 days after date of6• 180 days from effective date•6) Declaration final rule publication in 12 months final rule publication in 12 months of final rule

• Timeliness Federal Register Federal Register

1) For a site with existingFEMA-approved ANS backupmeans in ANS design report,12 months from effective date

of final rule to implement ANSbackup means2) For a site at which anupdated ANS design report

1St biennial exercise would be submitted for FEMAAlert and 1st biennial exercise approval, 18 months from

more than 395 daysSNotification 36 months after date of final rule 36 months effective date of final rule to

System Backup effective date of final 3ublication in Federal submit the updated ANS

Means rule pubictio design report to FEMA for

Register adequacy review, then 365

days to install/implement theANS backup means following

FEMA approval, with totaltime period to implementFEMA-approved ANS backupmeans not to exceed 3 years

and 6months from effective____date of final rule

12

Page 13: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EP Rule Implementation Dates

EmergencyOperationsFacility -

Performance-Based Approach

6 months after date offinal rule publication inFederal Register

No input180 days after date offinal rule publicationin Federal Register

No input180 days from effective dateof final ,rule

Emergency 1) 180 days from effectivedate of final rule to have

Response 6 months after date of 180 days after date of staging area andOrganization final rule publication in 36 months final rule publication 36 months communications capabilityAugmentation at

Alternative Federal Register in Federal Register 2) 36 months from effectiveFacility date of final rule to have

Facility_ remaining capabilities

1st biennial exercise 1) Licensees to conduct

1st biennial exercise more thanhostile action exercise for1 exrcis tha 395dayseach of their sites by

more than 1 year after after date of final rule 3+ ya 12i31i15.Challenging Drills effective date of final 6 months publication in Federal 3+ years 12/31/15.and Exercises rule2) States to fully participate

in one hostile action exerciseaction exercise by 12/31/15.

Protection for 6 months after date of 180 days after date of 180 days from effective dateOnsite Personnel final rule publication in 90 days final rule publication .90 days of final rule

Federal Register in Federal Register

NOTE: Applicants whose COL or ESP applications are docketed as of the final rule effective date will beallowed to defer compliance until December 31, 2013.

13

Page 14: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Offsite Emergency Preparedness Activities

May 3, 2011 James R. KishDirector

,PR Technological Hazards Division

FEMA

Page 15: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Topics" Presidential Policy Directive 8 (PPD 8)

" DHS-FEMA Administrator's Charge

" Other Related Preparedness Initiatives

" On-going Preparedness Activities

" Proposed FEMA Guidance: Revision of FEMA RadiologicalEmergency Preparedness (REP) Program Manual

" Moving forward on REP Program Manual and Supplement 4(Supp 4) to NUREG-0654/FEMA-REP-1 Rev. 1

" Next Steps - Beyond RPM and Supp 4

EAR.

~Q1FEMA

2

Page 16: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Presidential Policy Directive-8Directs the development of the following:* A National Preparedness Goal that'is risk informed, regionally

oriented, measurable, define core capabilities and emphasize anintegrated, layered, all-of-nation preparedness approach

" A National Preparedness System that is an integrated set ofguidance, programs and processes that guide planning,organization, equipment, training and exercises to build andmaintain domestic capabilities

" A comprehensive campaign to build and sustain nationalpreparedness including public outreach and community-based,and private-sector programs

" A National Preparedness Report an annual report that definesstrengths and weaknesses which will be used to inform thepreparation of the Administrations budget

FEAARTA.

0FEMA1ND S'C

3

Page 17: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

FEMA Administrator's Chargem Assure that REP Program is fully integrated within FEMA.

n Maintain REP's compliance responsibilities, build on thecurrently strong system, while identifying FEMA capabilitiesthat should participate in preparedness activities.

m Align REP Program planning activities to be consistent withthe 'whole of community' planning effort.

* Enhance FEMA's Planning, Training and Exerciseparticipation related to radiological emergencypreparedness.

o FEMA4

Page 18: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Other Related Preparedness Initiatives" National Incident Management System (NIMS)

" National Response Framework (NRF)

" National Recovery Framework

" Comprehensive Preparedness Guide (CPG 101)

" Post-Katrina Emergency Management Reform Act

" Integration of Federal Radiological Preparedness PolicyCommittee (FRPCC) with IND and RDD hazards

" Outreach through National Advisory Council and NationalEmergency Management Association

qFEMA5

Page 19: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Proposed FEMA Guidance" REP Program Manual

" Supplement 4 to NUREG-0654/FEMA-REP-1, Rev.1 "Criteriafor Preparation and Evaluation of Radiological EmergencyResponse Plans and Preparedness in Support of NuclearPower Plants"

QXFEMA6

Page 20: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

New REP Program Manual" Consolidated Implementation Guidance: Provide

comprehensive FEMA policy and interpretation of regulationsand guidance based on 44 CFR 350 and NUREG-0654/FEMA-REP-1, Rev. 1

" Alignment with National Preparedness Initiatives:. NationalIncident Management System (NIMS); National ResponseFramework (NRF); Homeland Security Exercise EvaluationProgram (HSEEP); National Preparedness Guidelines;National Preparedness Goal; Comprehensive PreparednessGuide (CPG 101); Post-Katrina Emergency ManagementReform Act

FEARVAR

r~FEMA7

Page 21: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

New REP Program Manual (cont.)" Enhance REP Exercise Activities: Ensure more challenging

drills and exercises to enhance exercise activities

" Alignment with NRC's Regulations: Align FEMA guidancewith NRC regulations in 10 CFR Part 50 and NRC's proposedrulemaking activities

)FE.MA8

Page 22: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Proposed Supplement 4 Impacts" Hostile Action Based Events: Preparing for and

responding to hostile action-based (HAB) events at nuclearpower plants

" National Preparedness Initiatives: Aligning with NIMS;NRF; HSEEP; National Preparedness Guidelines; NationalPreparedness Goal; CPG 101; Post-Katrina EmergencyManagement Reform Act

m Enhanced Exercise Activities: Enhancing scenariorealism, ensuring challenging exercises, and reducingnegative training

" Alert & Notification: Ensuring backup means for Alert &Notification Systems

0 FEMA9

Page 23: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

REP Program Manual & Supplement 4:Moving Forward

* Publication & Issuance:

" Public comment adjudication (FEMA and Joint FEMA-NRC)

" Pre-decisional status, release pending

* Implementation Strategy:

n Regional meetings to allow for questions and discussion

m Site specific workshops to assist local/state jurisdictionsincorporate updates and coordinate necessary updates toexisting schedules.

;FEMA10

Page 24: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Next Steps (Beyond RPM/Supp 4)Review of NUREG 0654/FEMA REP 1, Rev 1:

" Comprehensive look to include contemporary law,policy, and regulations

" Include findings from NRC Task Force, PPD 8implementation, and related preparedness initiatives

" Transparent process - stakeholder inclusive

iFEMA11

Page 25: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after
Page 26: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Minnesota Department ofPublic Safety

Division of Homeland Securityand Emergency Management

a

I

Kevin C Leuer, DirectorPreparedness Branch

May 3, 2011-/ ••-

~HSA

Page 27: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

I Comment Overview HSEMr

*Implementation of NUREG0654 Supplement 3.

- Hostile Action Based (HAB)planning and response.

*New regulation impacts.

* Implementation of newrequirements.

Page 28: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

NUREG 0654 Supplement 34 I*SEMR•~a Se~•.cr7d EiiwgIlcyMnamgnwimt

* Site specific implementation of stagedevacuation requirements.

* One size does not fit all. o blooo .0

= Predetermined PARs.

* Coordination between on

and off-site for PARs.

Page 29: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

HAB Planning andResponse

* Synchronization of securityresponse and off-site radiologicalresponse plans is needed for aneffective hostile action basedresponse.

- Plant security response plansmust be integrated with the restof the response.

HSE rt

Page 30: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

HAB PlanningAssumptions

* Prepare for designbasis events orbeyond design basisevents?

* With a radioactiverelease or without?

HSEMIWNoSmwtyndfomitwifm rmyMam-gw-wfl

Page 31: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

I

Regulation Impacts QH$S* Hostile Action Response

" Many new players becoming involved.* Need federal agency participation in planning

and response.

p'Mft

* REP Program Manum New exercise cycle

Changesbut unknown exercise

criterion frequency demonstration requirements." Unknown HAB demonstration requirements." HSEEP implementation requirements. 6

Page 32: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Regulation Impacts HSE~t

*Response ImpactResponse to a crisis at the sitewhile responding to theradiological emergency.

* Jurisdiction Impacts" New law enforcement agency

impacts. .* New fire and EMS agency impacts." Tribal jurisdiction impacts.

/

Page 33: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Rule Implementation HSE&r

" Site specific implementation plan.

" Priority on hostile action

response implementation. ACAT RISK OF

- Consideration for states withmultiple sites.

" Consideration of budget cycles.°

" CY 2015 completion date.

8

Page 34: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Thank Youfor the opportunity to present today

0

I

Kevin C Leuer, DirectorPreparedness Branch

[email protected]

Page 35: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

State Perspective onEP Rule

Patrick Mulligan, ManagerState of New Jersey

Department of Environmental ProtectionBureau of Nuclear Engineering

NRC Briefing on Emergency PreparednessMay 3, 2011

Page 36: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Positive Feedback on Process

m NRC was responsive to requests for an extendedcomment period

m Numerous Opportunities for stakeholderinvolvement

m Regional outreach and public meetings

m Comprehensive document summarizing publiccomments

m Stakeholder comments impacted Final Rule

Page 37: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

State Concerns

* Dual Impact of both NRC and FEMArulemaking and guidance on state resources

* Events in Japan will require a comprehensiveanalysis of plant safety and design, emergencyresponse plans and the application of lessonslearned stretching limited resources

" Draft/Final FEMA guidance has not beenreleased for review

Page 38: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Federal Guidance Consistency

* Acceptance criteria for ANS systems is notcurrently available in any FEMA guidance

* NRC considering changes to NUREG-0654Supplement 3

" FEMA proposed changes to NUREG-0654Supplement 4

* NUREG-0654 initially issued as a jointdocument; need consistency

Page 39: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Backup Alert and Notification

System

" ISG-O1 recommends that no PI credit should begive for the backup ANS system

* No metrics to measure its contribution to theANS reliability PI.

" No Time requirement

m Question: If it has no effect on health and safetyand no design criteria, why is it regulated? Is achange to the current system necessary?

Page 40: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Exercise Schedule

" All offsite exercise objectives required by FEMAcannot be met during some of the suggested exercisescenarios.

* Off line and out-of-sequence exercises demand moretime, resources and funding.

" Added burden on state, county and local responseorganizations.

* FEMA must be consistent and flexible in allowingstates to meet these objectives with minimal impacts tostaffs and funding.

Page 41: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Future Rulemaking

" Supplement 3

" NUREG-0654

* Minimize impact/changes to recently adoptedrules and guidance

* Recognize the resources and time required toimplement current rule changes

* Continue to engage stakeholders early in thereview process.

Page 42: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EMERGENCYPREPAREDNESSWHAT'S WRONG?

May 3, 2011

Mary Lampert

Pilgrim Watch, Director

Page 43: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

FUKUSHIMA'S LESSONS

Wake up Call or Snooze Alarm?

Page 44: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

WHAT'S FUNDAMENTALLYWRONG?

#1

Rules Lack Specificity

Requirements

Page 45: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

RULES PROVIDE FLEXIBILITYLACK ACCOUNTABILITY

Capability Based Rules -

* Licensee given flexibility* Licensee saves money* Licensee no real accountability

Performance Based Rules =

• EnforceablelAccountability

* Public Safety First

'4

Page 46: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

WHAT'S FUNDA MEN TA L LYWRONG?

#2What Rules Do Not Address

Until the basic issues are faced-

no "reasonable assurance"

Page 47: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EMERGENCY PLANNING ZONE20125 MILES

NRC advised U.S. citizens inJapan within 50 miles to evacuate

* NRC says advice was an ..."ABUNDANCE OF CAUTION"

• Why not the same "ABUNDANCEOF CAUTION" for citizens here?

Page 48: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

DOSE PROJECTIONSWhat's Wrong?

Likely Amount & Impact Radiation

Released Minimized

* PAGs not based on BEIR VII

" Large accidents ignored, e.g.

•spent fuel pool fire

) hydrogen explosions

~core or containment breach

more than 1% fuel failure

Page 49: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

PLUME MODELINGWhat's Wrong?

Key Hole

Is

Page 50: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

PLUME MODELING

What's Wrong?* Plume modeling based simplistic

straight-line, Gaussian plume; notsuited for complex sites (non-temporal, non-spatial)

What's Needed?• Advanced variable models and

multiple meteorological towersfor both pre-planning & response

9

Page 51: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

NOTIFICATIONWhat's Wr?

Require Multiple RedundantSystems & Backup

• Sirens- outdoor alert

• Reverse 911- indoor alert

• Electronic Reader Boards

l Emergency Alert System

10

Page 52: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

PROTECTIVE ACTIONSEVACUATION

What's Wrong?* Reception Centers equipped for

only 20% population.

Where will 80% get monitored,decontaminated, serviced?

* "Shadow Evacuation" ignored

* ETEs based "best case" scenario

I I

Page 53: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

RADIOLOGICAL PROTECTION

POTASSIUM IODIDE (KI):- support stockpiling to 20 miles

(bioterrorism act, 2002)- require both tablets & liquid KI for

young children

3-M TYPE MASKS:-require stockpiling both adult &

children's sizes in schoolsishelters

12

Page 54: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

EMERGENCY WORKERS

What's Wrong?* Communications: Require

in teroperability* Protective Gear: Require

protective clothinglmasks &training for its use

* REWMDs: RadiologicalEmergency Worker MonitoringDecontamination Centers- =requiremultiple centers per EPZ, located> 20 miles from reactor

Page 55: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

RETURN & RECOVERY

What's Wrong?

" No Agreed Clean-Up Standard* No Federal Agency In Charge* No Money- Price Anderson pays

damages, not clean-upi MACCS2 (MELCOR Accident

Consequence Code System) isused but outdated - code severelyunderestimates offsite costs

14

Page 56: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

4k

Emergency Planningfor the Possible

May 3, 2011Deborah Brancato

Staff Attorney, Riverkeeper, Inc.

RIVERKEEPER.NY's clean water advocate

Page 57: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Fundamental ProblemsOverlooked

The proposed final rule fails torequire consideration of andpreparation for all possible

emergency situations or instituteperformance based standards withwhich to ensure the effectivenessof nuclear power plant emergency

plans under all such situations

2

Page 58: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Licensees Must Prepare for"The Worst"

" 50-mile evacuation zone

* Accurate plume transport model

* Realistic ETE development

" Beyond design basis threats

* Adequate back-up Alert andNotification System

• Rapid escalation to GeneralEmergency

i Credible range of drill scenarios3

Page 59: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

NRC Should ImplementPerformance-Based Standards

" ETEs

" Licensee coordination with OffsiteResponse Organizations

" Emergency declaration timeliness

" Drills

4

Page 60: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Other Recommendations

* Fully consider the lessons ofFukushima prior to finalizingNRC Staff's proposed final rule

" Incorporate emergencypreparedness into plant licenserenewal reviews

5

Page 61: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Indian Point

" Uniquely situated

* Existing Emergency Plan:

Completely Unworkable

Notable lack of confidence ineffectiveness of plan

" And yet, consistent NRC andFEMA approval

6

Page 62: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

:6.

Industry Perspective onEP Rule

Tom JoycePresident and Chief Nuclear Officer

PSEG Nuclear

NRC Briefing on Emergency Preparedness

May 3, 2011

Page 63: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Positive Aspects of the Process

* Draft rule guidance provided for comment

well in advance of implementation

" Public meetings conducted to gather

stakeholder input

" Incorporation of review comments and

input improved the guidance

" New rule will improve several elements of

EP programs

Page 64: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Areas of Concern

* Changes that are not adequately justified ordo not have benefits commensurate withresources required to implement

- Drills and exercises, backup alert andnotification system, evacuation time

estimates, and emergency plan changeprocess

* Some elements of each lack a sound technical

basis or are inconsistent with Principles of

Good Regulation

Page 65: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Areas of Concern

* Guidance continues to evolve

On-shift collateral duty analysis

Task analyses should be required only for

positions not already analyzed by otherprograms or processes

-No additional formal comment period

C

Page 66: Information Briefing on - NRC: Home Page · 2012. 12. 4. · Information Briefing on Emergency Preparedness May 3, 2011. Evolution of NRC ... PERIOD L(2011), Amended 30 days after

Going Forward

" Finalize and issue staff guidancedocuments

" Timely staff review or endorsement ofindustry guidance documents

" Planned NRC/FEMA Workshops

" Implementation will be challenging forlicensees and State/local agencies