5
Better BART … Better El Cerrito C u t t i n g B l v d . P l a z a M i d B l o c k C r o s s i n g H i l l S t . P l a z a B A R T P l a z a T B D M i d B l o c k C r o s s i n g B A R T G a r a g e B A R T S t a t i o n B u s L a n e I m p r o v e d G r e e n w a y BART is advancing the second round of the Station Modernization Program, which will invest resources into the existing core stations and surrounding areas to enable transit ridership and enhance the quality of life around the stations. As part of our Station Modernization effort BART is currently developing design and construction estimates for the El Cerrito del Norte Station. The goal of the project is to develop potential station improvements to upgrade and modernize the station’s function, safety, capacity, sustainability, appearance, and improve the customer experience. The Station is estimated to be under construction beginning in the summer of 2016 and ending in late 2017. El Cerrito del Norte Station Modernization BART is a partnering with the City and helping fund the improvements along the Ohlone Greenway at both El Cerrito BART stations and the adjacent intersections. The goal is to improve access, safety and improve the vibrancy of these areas. Ohlone Greenway Station Improvements in partnership with the City of El Cerrito

El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

Better BART … Better El Cerrito

Del Norte BART Concept Plan.

Cutting Blvd .Plaza

Mid‐Block Crossing

Hill St. PlazaBART Plaza TBD

Mid‐Block Crossing

BART Garage

BART Station

Bus Lane

Improved Greenway

BART is advancing the second round of the Station Modernization Program, which will invest resources into the existing core stations and surrounding areas to enable transit ridership and enhance the quality of life around the stations.

As part of our Station Modernization effort BART is currently developing design and construction estimates for the El Cerrito del Norte Station. The goal of the project is to develop potential station improvements to upgrade and modernize the station’s function, safety, capacity, sustainability, appearance, and improve the customer experience.

The Station is estimated to be under construction beginning in the summer of 2016 and ending in late 2017.

El Cerrito del Norte Station Modernization

BART is a partnering with the City and helping fund the improvements along the Ohlone Greenway at both El Cerrito BART stations and the adjacent intersections. The goal is to improve access, safety and improve the vibrancy of these areas.

Ohlone Greenway Station Improvements in partnership with the City of El Cerrito

Page 2: El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

Better BART … Better El Cerrito

Liberty Street

Hill

Stre

et

San Pablo Boulevard

Cutting B

oulevard

Key Boulevard

Expanded paid area Enhanced Ohlone Greenway Connection - in coordination with City of El Cerrito

Relocated passenger drop-off

Reconfigured pedestrian space, including new seating and windscreens

Replant trees to shield parking garage

Relocate and reconfigure bike racks

Raised crosswalks

Reconfigured bus drop off

1

2

3

4

1

2

3

4

5

5

6

6

7

7

8

8

8

Site Circulation

5

Relocating the passenger drop-off to the western parking lot allows the current Ohlone Greenway to be expanded and develop a larger pedestrian promenade. The plan also includes improvements to

increase the safety and accessibility of the station.

Glass facade - material example

Bus Stop - proposed

Exterior floor materials Interior floor materials

Site furnishings - proposed

Page 3: El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

Better BART … Better El Cerrito

Expanding the paid area provides more room for vertical circulation, provides more room for queuing,

accommodates the redesign of restrooms and staff rooms, and helps de-clutter the station.

Expanded paid area

New faregates

New station agent booth

New daily use stairs

New elevators in paid area

Refurbish flooring in paid area

New art

LED lighting, including new fixtures and metal ceiling soffits

Upgraded public restrooms

New staff breakroom/bathrooms

9

9

10

10

11

12

13

14

15

16

17

18

11

12 13

14

15

16

17

18

Paid Area Improvements

Public Restroom Redesign

West Elevation - New Glass Encased Stairs

Page 4: El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

Better BART … Better El Cerrito

Lighting ConceptThe entire station lighting will be re-lamped to energy efficient LED fixtures with

smart controllers

SustainabilityIncorporate sustainable materials and technologies into the station to increase the life-cycle value of

the station’s infrastructure and to conserve natural resources and protect the public investment

Landscape and StormwaterThe plants are drought tolerant and low maintenance, and

are placed allow visibility and to help to cleanse stormwater

runoff. The irrigation system is water efficient and will be used

to establish the plants for the first few years and then will be

turned off. BART is committed to doing its part to save water

during this serious drought.

Page 5: El Cerrito del Norte Station Modernization · palette (blues & greens). BART El Cerrito del Norte Station Improvements Area Available for Art April 28, 2015 Permanent New Art At El

Better BART … Better El Cerrito

EXPANDED PAIDAREA

(E) PAID AREA

N

8'-7

"8'

-1"

4'-3

"4'

-4"

42'-9 1/2"

4'-11 3/4"

SPACE AVAILABLE FOR ART

1/8" = 1'-0"2 INTERIOR WEST VIEW

42'-9 1/2"

4'-4

"4'

-3"

8'-1

"8'

-7"

4'-11 3/4"

SPACE AVAILABLE FOR ART

1/8" = 1'-0"1 INTERIOR EAST VIEW

WM

ConcreteBeam

Ceiling Ceiling

View 2

View 1

Plan View of Paid Area Photos of existing mosaic artNew art installation should be mosaic tile medium and employ a similar cool color palette (blues & greens).

BART El Cerrito del Norte Station ImprovementsArea Available for Art April 28, 2015

Art InspirationWhat would you want to see as potential inspiration or themes to be incorporated into new art at the El Cerrito del Norte Station? Answer below

Tree Planting SelectionBART will remove the existing trees planted along the edge of the parking garage.

Please provide your input on the proposed tree options identified below.

Brisbane Box• 23-35’ tall

• 25’ wide

• Rounded form

• Evergreen

• Drought tolerant

• Tolerant of urban

environment

• Fast growth

EXPANDED PAIDAREA

(E) PAID AREA

N

8'-7

"8'

-1"

4'-3

"4'

-4"

42'-9 1/2"

4'-11 3/4"

SPACE AVAILABLE FOR ART

1/8" = 1'-0"2 INTERIOR WEST VIEW

42'-9 1/2"

4'-4

"4'

-3"

8'-1

"8'

-7"

4'-11 3/4"

SPACE AVAILABLE FOR ART

1/8" = 1'-0"1 INTERIOR EAST VIEW

WM

ConcreteBeam

Ceiling Ceiling

View 2

View 1

Plan View of Paid Area Photos of existing mosaic artNew art installation should be mosaic tile medium and employ a similar cool color palette (blues & greens).

BART El Cerrito del Norte Station ImprovementsArea Available for Art April 28, 2015

Permanent New Art At El Cerrito del Norte the public art opportunity will be two permanent wall mounted art pieces related to the station’s existing art scheme and representative of the surrounding community.

California Incense Cedar• 75’ tall

• 10-15’ wide

• Pyramidal form

• Evergreen

• Drought tolerant

• Native to California

• Moderate growth

Southern Magnolia• 50’ tall

• 23-30’ wide

• Pyramidal form

• Evergreen

• Tolerant of the

urban environment

• Moderate growth

BART will be issuing a competitive Call for Artists for all three stations undergoing modernization (El Cerrito del Norte, 19th St/Oakland, Powell St). For more information visit www.bart.gov/art.

Future Call for Artists