Upload
bqdianz
View
53
Download
1
Tags:
Embed Size (px)
DESCRIPTION
report
Citation preview
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
i
COMMENTS Table of contents List of tables List of figures List of photos Appendices Abbreviations
TABLE OF CONTENTS BRIEF DESCRIPTION OF THE PROJECT 1.0 INTRODUCTION.................................................................................................................................. 1
1.1 BRIEF DESCRIPTION OF THE PROJECT ................................................................................................. 1 1.2 PROJECT OBJECTIVES AND WATER DEMAND ........................................................................................ 1 1.3 RAW WATER DEMAND OF THE OYU TOLGOI PROJECT ........................................................................... 2 1.4 PROJECT DURATION ............................................................................................................................ 6
2.0 WATER SUPPLY PIPELINE SITE PLAN .......................................................................................... 7 2.1 GENERAL OF WATER SUPPLY SYSTEM ................................................................................................. 7
2.1.1 Bore pump stations ..................................................................................................................... 7 2.2 COLLECTOR AND BREAK TANK STATIONS ........................................................................................... 10 2.3 EMERGENCY STORAGE LAGOON ........................................................................................................ 13 2.4 WATER PIPELINE DESIGN ................................................................................................................... 14
2.4.1 Pipeline cleaning...................................................................................................................... 16 2.4.2 CTPS#1~CTPS#5 and BTPS#1 pipeline layout ......................................................................... 17 2.4.3 Layout of lagoon ...................................................................................................................... 17 2.4.4 Pipeline protection ................................................................................................................... 17 2.4.5 Pipeline excavation and backfill ............................................................................................... 18
2.5 INFRASTRUCTURE REQUIREMENTS .................................................................................................... 19 2.5.1 Fire safety ................................................................................................................................ 19 2.5.2 Heating, Ventilation and air conditioning system ...................................................................... 19 2.5.3 Power supply ........................................................................................................................... 20 2.5.4 Design of distributed control system ......................................................................................... 20 2.5.5 Design of security system.......................................................................................................... 21 2.5.6 Maintenance road .................................................................................................................... 21
2.6 WATER QUALITY ................................................................................................................................ 22 3.0 ENVIRONMENTAL IMPACTS ASSESSMENT OF THE PROJECT ............................................. 23
3.1 METHODOLOGY OF ASSESSMENT ...................................................................................................... 23 3.2 MAIN ASSESSMENT METHODS............................................................................................................ 25
4.0 CLIMATE ............................................................................................................................................ 25 4.1 CHARACTERISTICS OF CLIMATE ......................................................................................................... 25
4.1.1 Basic meteorological parameter ............................................................................................... 27 4.2 IMPACTS OF OYU TOLGOI WATER SUPPLY PIPELINE FOR CLIMATE .................................................... 28
4.2.1 Impacts of climate for Water Supply Pipeline project ................................................................ 29 4.3 MITIGATION MEASURES FOR THE NEGATIVE IMPACTS......................................................................... 29 4.4 IMPACTS ON AIR QUALITY AND ITS ASSESSMENT ................................................................................ 30
4.4.1 Main indicators of air quality ................................................................................................... 30 4.4.2 Impacts on air quality and its assessment .................................................................................. 31 4.4.3 Mitigation measures for the negative impacts on air quality ...................................................... 32
5.0 IMPACT ASSESSMENT ON SOIL SURFACE AND SUBSOIL, THEIR ASSESSMENT .............. 33 5.1 LOCATION OF OYU TOLGOI WATER SUPPLY PIPELINE PROJECT AND GENERAL INDICATORS ............... 33 5.2 IMPACT ASSESSMENT OF LANDSCAPE AND SUBSOIL ........................................................................... 34 5.3 MITIGATION MEASURES FOR THE NEGATIVE IMPACTS FROM THE WATER SUPPLY PIPELINE ................. 37
6.0 IMPACT ASSESSMENT ON SURFACE AND GROUNDWATER .................................................. 38 6.1 SURFACE AND GROUNDWATER AT PROPOSED AREA FOR WATER SUPPLY PIPELINE ............................ 38 6.2 GROUNDWATER ................................................................................................................................ 39 6.3 IMPACT ASSESSMENT ON SURFACE AND GROUNDWATER ................................................................... 41 6.4 MITIGATION MEASURES FORTHE NEGATIVE IMPACTS ......................................................................... 43
7.0 IMPACT ASSESSMENT ON SOIL .................................................................................................... 45
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
ii
7.1 SOIL DESCRIPTION OF THE AREA ....................................................................................................... 45 7.1.1 Grey brown soil of desert steppe ............................................................................................... 47 7.1.2 Light clayey brown soil of desert steppe .................................................................................... 47 7.1.3 Sandy brown soil of desert steppe ............................................................................................. 47 7.1.4 Aeolian sands ........................................................................................................................... 47 7.1.5 Meadow grey brown soil of desert steppe .................................................................................. 48 7.1.6 Saline grey brown soil of desert steppe ..................................................................................... 48
7.2 IMPACT ASSESSMENT ON SOIL COVER ............................................................................................... 48 7.2.1 Mitigation measures for the negative impacts ........................................................................... 50
8.0 IMPACT ASSESSMENT ON FLORA ................................................................................................ 51 8.1 CURRENT CONDITION OF VEGETATION COVER ................................................................................... 51
8.1.1 Vegetation of water supply pipeline project area ....................................................................... 55 8.1.2 Desert peneplain (Vegetation cover of low hills, plain valleys and ridges) ................................. 57 8.1.3 Desert steppe ........................................................................................................................... 57 8.1.4 Low hills .................................................................................................................................. 57 8.1.5 Ephemeral creeks and saline marshes ....................................................................................... 57 8.1.6 Vegetation on depositional sands (Saxsaul wood) .................................................................... 57
8.2 IMPACT ASSESSMENT ON VEGETATION COVER ................................................................................... 57 8.3 MITIGATION MEASURES FOR THE NEGATIVE IMPACTS......................................................................... 59
9.0 IMPACT ASSESSMENT ON FAUNA ................................................................................................ 60 9.1 FAUNA OF PROJECT AREA ................................................................................................................. 60 9.2 MITIGATION MEASURES FOR THE NEGATIVE IMPACTS ......................................................................... 61
10.0 PHYSICAL POLLUTION TO THE ENVIRONMENT IN TERMS OF WATER SUPPLY PIPELINE PROJECT .................................................................................................................................. 63
10.1 IMPACT ASSESSMENT OF NOISE AND VIBRATION CONDITION .............................................................. 63 10.1.1 Impact assessment .................................................................................................................... 63 10.1.2 Mitigation measures for the negative impacts ........................................................................... 64
11.0 IMPACT ASSESSMENT ON HISTORICAL AND CULTURAL HERITAGE ................................ 65 11.1.1 Mitigation measures for the negative impacts ........................................................................... 65
12.0 IMPACT ASSESSMENT ON SOCIO-ECONOMICS ........................................................................ 66 12.1 SOCIO-ECONOMIC CONDITION OF THE UMNUGOBI PROVINCE ............................................................. 66
12.1.1 Population, social condition ..................................................................................................... 66 12.1.2 Agriculture ............................................................................................................................... 69 12.1.3 Industry.................................................................................................................................... 70
12.2 BRIEF DESCRIPTION OF THE KHANBOGD SUM .................................................................................... 70 12.3 IMPACT ASSESSMENT OF SOCIO-ECONOMICS .................................................................................... 70
13.0 SUMMARY OF THE ENVIRONMENTAL IMPACT ASSESSMENT ............................................. 73 14.0 RISK ASSESSMENT........................................................................................................................... 74
14.1 NATURAL DISASTERS AND POTENTIAL RISKS RELATED TO EQUIPMENTS AND TECHNOLOGY ................ 74 14.1.1 Natural disasters and related risks: .......................................................................................... 74 14.1.2 Risk and danger caused by equipments and technology ............................................................. 76
14.2 MITIGATION MEASURES FOR THE POTENTIAL RISKS ........................................................................... 77 15.0 ENVIRONMENTAL PROTECTION PLAN ...................................................................................... 80 16.0 ENVIRONMENTAL MONITORING PLAN ..................................................................................... 88 17.0 RELEVANT LEGISLATION TO THE PROJECT ........................................................................... 93 18.0 SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT FINDINGS ................................ 100
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
iii
List of Tables Table 1.1 Plant Raw Water Demand Requirements of the Oyu Tolgoi, L/s .......................................... 4 Table 1.2 Water demand management options of the water supply pipeline ...................................... 6 Table 2.1 Location and area of the bores............................................................................................ 8 Table 2.2 Production Bores Flow Rate ............................................................................................... 9 Table 2.3 General parameters of bore pump system .......................................................................... 9 Table 2.4 Location and area of the CTPS ..........................................................................................11 Table 2.5 Technical parameters in Pump House CTPS#1~CTPS#5 and BTPS #1 .............................12 Table 2.6 Borehole to CTPS#1~ CTPS#5 Pipeline Parameters .........................................................15 Table 2.7 Main pipeline parameter ....................................................................................................16 Table 2.8 Excavation Depth for Pipe Trenches ..................................................................................18 Table 2.9 Trench slope versus soil types and depths .........................................................................18 Table 2.10 Heating, Ventilation, and Air Contioning Design Considerations for BPS, CTPS and BTPS .........................................................................................................................................................20 Table 4.1 Air temperature in Oyu Tolgoi and its surrounding area, by months ....................................26 Table 4.2 Soil temperature in Oyu Tolgoi and its surrounding area , by months .................................26 Table 4.3 Climate Impact Assessment...............................................................................................29 Table 4.4 Location of the monitoring ..................................................................................................29 Table 4.5 Emission Factors for Diesel Industrial Vehicle Exhaust Emissions (based on engine power) .........................................................................................................................................................31 Table 4.6 Air Quality Impact Assessment ..........................................................................................32 Table 5.1 - ..........................................35 Table 5.2 - , ............................36 Table 5.3 Impact assessment on landscape and subsoil....................................................................37 Table 6.1 Wells located along the water supply pipeline project implementing area ...........................40 Table 6.2 Pumping Test Groundwater Quality Gunii Hooloi Aquifer....................................................41 Table 6.3 Temporal runoff beds crossing water supply pipeline at Gunii Hooloi groundwater reserve .42 Table 6.4 Qualitative Assessment of Impacts on Surface and Groundwater .......................................43 Table 7.1 Soil field records and location of sample ............................................................................46 Table 7.2 Main agrochemical parameters of soil ................................................................................46 Table 7.3 Impact Assessment of Soil .................................................................................................50 Table 8.1 Detailed list of vegetation composition at Gunii Hooloi borefield and pipeline ......................52 Table 8.2 List of Endemic plants ........................................................................................................53 Table 8.3 List of plants included in list of rare plants of Mongolia .......................................................54 Table 8.4 List of Plants included in list of very rare plants of Monglolia...............................................54 Table 8.5 Vegetation Classification of Water Supply Pipeline Project .................................................56 Table 8.6 Impact Assessment of Fauna .............................................................................................58 Table 9.1 Impact Assessment of Fauna .............................................................................................61 Table 10.1 Impact Assessment of Noise and Vibration ......................................................................64 Table 11.1 List of archeological memorials ........................................................................................65 Table 12.1 Impact assessment of the water supply pipeline project ...................................................72 Table 13.1 Summary of EIA of the .....................................................................................................73 Table 14.1 Seismicity registered at Oyu Tolgoi project area ...............................................................74 Table 14.2 Risk Assessment .............................................................................................................77 Table 15.1 Environmental Protection Plan .........................................................................................81 Table 16.1 Environmental Monitoring Plan ........................................................................................89 Table 17.1 Mongolian laws on environment .......................................................................................93 Table 17.2 Mongolian National Standards and Codes .......................................................................96 Table 17.3 International Standards and Codes ..................................................................................96 Table 17.4 Existing Mongolian standards on Gunii Hooloi Borefield and water supply pipeline project of the Oyu Tolgoi ...............................................................................................................................98
List of Figures Figure 1.1 Site, Infrastructure and Plant Raw Water Demand, L/s ....................................................... 5 Figure 2.1 Maintenance road design .................................................................................................22 Figure 3.1 Expert assessment matrix.................................................................................................24 Figure 4.1 Wind Rose for the Oyu Tolgoi project area ........................................................................27 Figure 12.1 Birth, mortality and net growth of population of Umnugobi aimag (2004-2007).................67 Figure 12.2 Number of the infected people, especially infected by hepatitis, in Umnugobi aimag .......67 Figure 12.3 Educational level of the registered unemployed people of Umnugobi aimag ....................68
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
iv
Figure 12.4 Volume and structure of the livestock herds in Umnugobi aimag .....................................69 List of Photos Photo 1. General position of the lagoon .............................................................................................13 Photo 2. Proposed position of water supply pipeline ..........................................................................34 Photo 3. Ephemeral creek in the Khaliviin valley ................................................................................39 Photo 4. Khulans at the project area during the fauna field survey .....................................................60
Appendices
Appendix 1.1 Oyu Tolgoi project location Appendix 1.2 Raw water supply pipeline project location Appendix 2.1 Oyu Tolgoi water supply system schematic drawing Appendix 2.2 Bore pump location of the borefield Appendix 2.3 Bore pump station GH01_PB01site plan Appendix 2.4 Bore pump station GH01_PB01 elevation Appendix 2.5Collector tank pump station CTP#1 plan Appendix 2.6 Collector tank pump station CTP#1 elevation Appendix 2.7 General site plan of lagoon Appendix 2.8 Collector tank pump station, CTP1 pumping plan Appendix 2.9 Collector tank pump station CTP1 pipeline section Appendix2.10 Break tank pump station BTP1 pipeline plan sheet 2 of 1 Appendix 2.11 Break tank pump station BTP1 pipeline plan sheet 2 of 2 Appendix 2.12 Pipeline typical cross sections Appendix 4.1 Location of meteorological stations around the project location Appendix 5.1 Project location and administrative units Appendix 5.2 Project area landscape and its impact assessment Appendix 5.3 Main water supply pipeline longitudinal section Appendix 7.1 Soil cover of the project area Appendix 8.1 Vegetation of the project area Appendix 8.2 Rare and very rare plants location at the project area Appendix 11.1 Location of archeological sites around the project area Appendix 14.1 Seismicity zones in Mongolia and project location Appendix 14.2 Earthquake events in 100 years since 1900 and project location
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
v
Abbreviations
IMMI - Ivanhoe Mines Mongolia Inc
- Oyu Tolgoi
RWSP - Raw Water Supply Pipeline
DEIA - Detailed Environmental Impact Assessment
MNE - Ministry of Nature and Environment
BPS - Bore Pump Station
CTP - Collector Tank Pump
BTPS - Break Tank Pump Station
CTPS - Collector Tank Pump Station
L- Lagoon
HT - High Transmissvity
LT - Low Transmissivity
DICL - Ductile Iron Cement Lined
HDPP - High-Density Polyethylene Pipe
CS - Carbon Steel
FRP - Fiberglass-Reinforced Plastic
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
vi
EXECUTIVE SUMMARY OF THE SUPPLEMENTARY DETAI LED IMPACT ASSESSMENT
REPORT FOR THE GUNII HOOLOI BOREFIELD AND PIPELINE WATER SUPPLY OF
THE OYU TOLGOI PROJECT
October, 2008
In accordance with the order of Ivanhoe Mines Mongolia Inc (IMMI), the proponent of the
Oyu Tolgoi copper and gold mining project in Khanbogd sum of Umnugobi Aimag, Mongolia,
this Supplementary Detailed Environmental Impact Assessment (SDEIA) report for the Gunii
Hooloi Borefield and Pipeline water supply project has been prepared by the Eco Trade LLC,
Mongolia.
This SDEIA report is for the Gunii Hooloi Borefield and Pipeline project which originates at
the Gunii Hooloi groundwater resource area and extends to the storage lagoon of the Oyu
Tolgoi copper and gold processing plant. The SDEIA presents a detailed description of the
project, technology details, and potential impacts to the environment from the Gunii Hooloi
Borefield and Pipeline construction and its operation. The SDEIA includes mitigation
measures and an attached Environmental Protection Plan and Environmental Monitoring
Plan.
IMMI completed project water supply investigations from 2002 to 2004 which identified and
defined the Gunii Hooloi groundwater aquifer and has calculated the available groundwater
reserve of the water supply.
Water demand for the Oyu Tolgoi mine has been estimated with an average yearly demand
696 L/s based on peak year for 110,000 tonnes per day for the mine development, 64%
tailings density and 0% mine dewatering. A margin of 150 L/s for lagoon refilling of its
emergency use, the indicated design capacity requirement for the borefield / pipeline is 935
L/s. The water demand of the Oyu Tolgoi mine will be more in initial years than yearly
average water demand in other years until drainage water will be possible to reuse.
The proposed corridor for the pipeline and pumping stations for the Oyu Tolgoi project begins
at Gunii Hooloi located 25 km from the northeast of the Oyu Tolgoi license area and
continues 70 km to the Oyu Tolgoi project area.
The project water supply system facilities include 28 production and 5 standby bores, 5
collector pump stations, approximately 148.9 km of pipe, a raw water storage pond with a
capacity of 400000 m3 break pump station including 110 MW electricity transmission lines, a
maintenance road and other facilities. The water supply system facilities occupy an
estimated total area of 1030 ha.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
vii
Production bores are proposed to be developed in two distinct areas of the Gunii Hooloi
Borefield; 12 water bores in the southern portion of the southeast part of the borefleld which
are predicted to provide 30 L/s per bore in the low transmissivity (LT) and 21 water bores in
the higher transmissivity (HT) northeast part of the borefield which are estimated to provide
40 L/s per bore.
Powerlines linking the borefiled pumps with the Oyu Tolgoi site power supply will generally
follow the pipeline corridor. An access road for maintenance and inspection is planned in the
pipeline corridor.
A 400,000 m3 capacity, emergency raw water storage pond will be located on elevated
ground approximately 5 km north of the Oyu Tolgoi mining and processing site to provide an
emergency supply of water to the site in the event of a pipeline failure. Water supply from the
emergency storage lagoon to the site will be carried within two pipelines.
A Detailed EIA report on the potential impacts of groundwater use from the Gunii Hooloi
aquifer was prepared by Eco Trade LLC and approved by the MNE, April in 2005. The
approved EIA for the use of the aquifer did not include the details of the borefield
Infrastructure and pipeline as design of these facilities was not complete at the time. Field
observations, laboratory analysis, and identification of applicable Mongolian and International
legal requirements, standards, regulations and legislation during the construction and
operation phase were completed for the SDEIA of this project in July, 2007.
DEIA report is supplementary to "Environmental Impact Assessment report for Oyu Tolgoi
Project Groundwater Resource Use from the Gunii Hooloi and Galbyn Gobi Regional
Aquifers" completed by Eco Trade LLC and approved by MNE.
The identification of potential environmental impacts from the Gunii Hooloi Borefield and
Pipeline water supply was completing using a risk matrix which considers potential impacts
and severity. The SDEIA indicates that the impact on the environment from Gunii Hooloi
Borefield and Pipeline Water Supply is temporary and limited to the immediate area of the
infrastructure. These localized impacts can be minimized during construction through
implementation of technical procedures for removal of soil and vegetation, and excavation
and installation of pipe stations and other facilities.
Potential short term negative impacts may occur on air quality from dust emissions during
installation and the construction of pipeline facilities (pipeline, collector and break tank pump
stations , emergency lagoon, service road and electric line), soil stripping and stockpiling,
and gaseous emission from vehicles used during construction. There is not direct impact to
cultural heritage and climate. According to archeology research done there are not burial and
memorials alongside the pipeline site .
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
viii
The development and operation of the Gunii Hooloi Borefield and Pipeline project will be
undertaken to minimize impacts to the environment through application of the Environmental
Protection Plan and the Environmental Monitoring Plan.
Prepared by: Oyuntuya.S
Expert of Eco trade LLC, Environmental Assessment and Expertise Company.
"" m
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-1
1.0 INTRODUCTION
11..11 BBRRIIEEFF DDEESSCCRRIIPPTTIIOONN OOFF TTHHEE PPRROOJJEECCTT
Project name: OYU TOLGOI RAW WATER SUPPLY PIPELINE PROJECT Project proponent:
Ivanhoe Mines Mongolia Inc LLC (IMMI) is the development proponent of the Oyu Tolgoi raw
water supply pipeline project and is holded 6709A mining license at the Oyu Tolgoi
(Appendix 1.1 Oyu Tolgoi project location).
Project location: This project will be implemented in the Jargalant bag of the Khanbogd
sum in the Umnugobi province and that pipeline will be lied about 82.2 km from the Gunii
Hooloi aquifer areas to the Oyu Tolgoi project area. Total width of the pipe is between 60
and 70 km which will be approximately 40 km narrow around the south of the Khanbogd
mountain (Appendix 1.2 Raw water supply pipeline project location).
Project capacity: The peak design water demand rate of 745 L/s and the pipeline capacity
is 895 L/s of the water pipeline system. Pipeline system consist main 28 boreholes, 4
standby boreholess, a capacity of 400,000 m3 emergtency storage lagoon, collection and
break tank pumps, length of 148.9 km underground pipeline, capcacity of 110 kW powerline
and maintenance road covering 1030 hectares. The system will work during the operation.
DEIA executive: A Detailed Environmental Impact Assessment of Oyu Tolgoi
projectGroundwater Resource Use from the Gunii Hooloi and Galbyn Gobi Regional
Aquifers, Volume II report was submitted by MNE in June, 2005 and approved in
September, 2005. DEIA of the project was prepared by Eco Trade LLC, Environmental
Consultants, Mongolia.
11..22 PPRROOJJEECCTT OOBBJJEECCTTIIVVEESS AANNDD WWAATTEERR DDEEMMAANNDD
Oyu Tolgoi water supply pipeline project is one of the certain significant which will supply raw
water demand of the Oyu Tolgoi mine processing in Khanbogd sum of Umnugobi province.
The raw water supply project is included in Oyu Tolgoi mine processing plan in September
2005.
Following procedures requires to construc the Oyu Tolgoi water supply pipeline:
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-2
1. To supply continuously water demand for the Oyu Tolgoi mining and processing
during the its operation,
2. Water supply of dust suppression from the construction and operation period of Oyu
Tolgoi project,
3. Water supply of the air Oyu Tolgoi power plant,
4. Raw water that will be directed for domestic use will be fully treated in the Oyu Tolgoi
water treatment and bottling plant.
11..33 RRAAWW WWAATTEERR DDEEMMAANNDD OOFF TTHHEE OOYYUU TTOOLLGGOOII PPRROOJJEECCTT
Accordance with order of IMMI LLC, Fluor group studied water demand of Oyu Tolgoi project
based on water suply resource and water demand for the operation period prepared for IMMI
LLC. This report based on Oyu Tolgoi raw water supply pipleine detailed engineering design
report in August, 2008.
Water demands for the mine vary depending on the level of production within the mine
operations. Preliminary information from Technical Discussion Memorandum TDM201 Site
Water Balance and Design Criteria for GH Pipeline_Rev2 is that production within the mine
is proposed to commence with a production rate around 70,000 t/d possibly during years 1
to 3 of operation, increasing to a production rate of 85,000 t/d during years 4 to 8 of
operation and 170,000 t/d up to year 16.
The peak design demand rate for the 85,000 t/d, 64% tailings density and 0% mine
dewatering scenario is recommended to be carried forward for pipeline sizing purposes
(Table 1.1).
Plant design water demand:
The plant raw water demand ranges from 535 to 671.2 L/s, with an average yearly demand
of 627 L/s.
Infrastructure and Mining Raw Water Demand:
1. Domestic Water Supply 400 people living continuously on site at a consumption
rate of 0.27 m3 per person per day. 1900 people working but not living on site a
consumption rate of 0.135 m3 per person per day. For the this water consumtion is
4.2 L/s throughout year.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-3
2. Steam Boiler System Makeup Water It rates between 0.1-6.3 L/s and average rate
is 2.6 L/s. This water consumption is 0.1 L/s in summer to 6.3 L/s in winter.
3. Glycol Heating System Makeup Water According to estimation the water
consumption is 1.2 L/s from November to April in winter time and maximum water
demand is 2.8 L/s.
4. Ongoing Construction Activities (including Concrete Batch Plant) It is 0.3 L/s in
winter to 0.8 L/s in summer, average is 0.6 L/s.
5. Sewage Return and Primary Crusher water demand has been transferred to the plant
water balance.
6. Truck Wash - Each month truck wash will be done and 1.7 L/s throughout the year.
7. Power Plant 7.6 L/s in winter to 9.5 L/s in summer, average demand is 8.5 L/s.
8. Infrastructure Dust Suppression It will be depends on seasons and 11.5 L/s in June
July. There is no water use for the dust suppression activity in winter time. Average
water demand is 3.3 L/s.
9. Open Pit Mine Dust Suppression The water demand ranges from 0 and 57.5 L/s
throughout the year with average yearly demand of 16.6 L/s.
10. Underground Mine 30 L/s throughout the year.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-4
Table 1.1 Plant Raw Water Demand Requirements of the Oyu Tolgoi, L/s
A
Plant Raw Water Demand (L/s)
Mine dewatering scenario
Plant capacity 6 7 8 9 10 11 12 1 2 3 4 5 Average Maximum
0% Dewatering Design (110.000 t/day)
670.1 671.2 625.1 640.3 607.3 548.7 638.7 635.9 639.8 534.8 657.8 650.6 627.5 671.2
Water Demand User Infrastructure/Mining Raw Water Demand (L/s)
6 7 8 9 10 11 12 1 2 3 4 5 Average Maximum
1 Domestic Water Supply 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2
2 Sewage return
3 Steam boiler System Makeup water 0.1 0.1 0.1 0.1 0.1 2.8 6.3 6.3 6.3 6.3 2.8 0.1 2.6 6.3
4 Glycol Heating System Makeup Water
0 0 0 0 0 1.4 2.8 2.8 2.8 2.8 1.4 0 1.2 2.8
5 Ongoing Construction Activities (inc. Concrete Batch Plant)
0.8 0.8 0.8 0.8 0.8 0.8 0.3 0.3 0.3 0.3 0.8 0.8 0.6 0.8
6 Primary crusher
7 Truck wash 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7
8 Power Plant 9.5 9.5 9.5 9.5 9.5 7.6 7.6 7.6 7.6 7.6 7.6 9.5 8.5 9.5
9 Infrastructure Dust Suppression 11.5 10 7.2 3 0 0 0 0 0 0 2.4 5.7 3.3 11.5
10 Open Pit Mine Dust Suppression 57.5 50 36 15 0 0 0 0 0 0 12 28.5 16.6 57.5
11 Underground Mine 30 30 30 30 30 30 30 30 30 30 30 30 30 30
B Total Infrastructure/Mining Demand 115.3 106.3 89.5 64.5 46.3 48.5 52.8 52.8 52.8 52.8 62.9 80.5 68.8 115.3
A+B total Design (110.000 t/day)
785.4 777.6 714.6 704.6 653.6 597.2 691.5 688.7 692.6 587.6 720.7 741.1 696.3 785.4
Source: Raw Water Supply Pipeline Detailed Engineering Report, Fluor group, Aug, 2008.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-5
Total water demand of plant raw water demand and infrastructure / mining water demand is
110,000 tonn per day with 64% availability factor and 0% mine dewatering. Site design water
demand ranges from 588 L/s to 785 L/s, with an average yearly demand of 696 L/s (Figure 1.1).
0
100
200
300
400
500
600
700
800
900
1 2 3 4 5 6 7 8 9 10 11 12
Month
De
ma
nd
Flo
w R
ate
L/s Plant Design Demand (L/s)
Site Design Demand (L/s)
Infrastructure Demand
(L/s)
Figure 1.1 Site, Infrastructure and Plant Raw Water Demand, L/s
It is probable that water supply will be decreased from water supply pipeline in winter period, and
water supply will be increased in high evaporation period.
Three options for the improvements of the raw water supply sysytem have been examined.
According to the scenario the peak design water demand rate of 785 L/s and it is recommended
that a lower margin of 115 L/s is adopted for lagoon refilling (Table 1.2 Raw water demand
management options). The below table shown the pipeline / borefield design capacity is estimated
of 900 L/s.
A 400,000 m3 emergency / buffer storage lagoon is recommended that wil provide approximately
one weeks emergency supply to the site in the event of a major borefield / pipeline failure.
Inclusive of a margin of 150 L/s for lagoon refilling within one month of its emergency use, the
indicated design capacity requirements for the borefield / pipeline is 935 L/s.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-6
Table 1.2 Water demand management options of the water supply pipeline
Options Option 1. Increased Emergency Storage
(m3)
Op
tio
n 2
. Y
earl
y R
aw
W
ate
r D
em
an
d
Bala
ncin
g (
m3)
Option 3. Yearly Raw Water Demand Balancing plus increased Emergency Storage
(m3)
Min
e
Dew
ate
ring
options
Pla
nt
capcaic
ty
2 hours
12 hours
1 day
2 days
1 week
2 weeks
2 hours
12 hours
1 hour
2 days
1 week
2 weeks
Min
e D
ew
ate
ring 0
%
Desig
n w
ate
r dem
and
(110.0
00 t
/d)
5013 30079 60158 120316 421107 842214 984564 989577 1014643 1044722 1104880 1405671 1826778
Borefield and pipeline design
parameters
Mine water demand: 785 L/s + Borefield and pipeline:115 L/s = 900 L/s
Average water demand - 696 L/s
Source: Raw water supply pipeline detailed engimeering design report, Flour group, Aug, 2008.
11..44 PPRROOJJEECCTT DDUURRAATTIIOONN
The water supply pipeline project is one of the significant infrastructure of the Oyu Tolgoi project.
The project is proposed to supply water demand of Oyu Tolgoi project from the Gunii Hooloi
borefield in whole project duration. According to the preliminary estimation, Oyu Tolgoi mining and
processing operation will be for 60 years. The water supply pipeline system designed during the
operation continuously.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-7
2.0 WATER SUPPLY PIPELINE SITE PLAN
22..11 GGEENNEERRAALL OOFF WWAATTEERR SSUUPPPPLLYY SSYYSSTTEEMM
The detailed engineering design of the water supply pipeline and borefield at the Oyu Tolgoi covers
the following aspects:
Access and borefield road;
Piping and fittings;
Pump stations and water collector tank;
Lagoon;
Electrical, fire protection instrumentation, guard fence and communication systems.
According to the profile diagram of pipeline of 33 bore pump system, two groups can be divided.
The whole system consists of 5 collector tank pump station (CTPS#1~ CTPS#5) which collect
pressure flow from the Borehole pump station (BTPS#1), and boosted again to lagoon far away,
from which gravity flow runs to the site (Appendix 2.1 Oyu Tolgoi water supply system schematic
drawing ).
2.1.1 Bore pump stations
The OT water supply system obtains water from the bore fields of the High Transmissivity (HT)
area and the Low Transmissivity (LT) area, respectively including 21 bores with design flow rate of
40 L/s each and 12 bores with 30 L/s (Appendix 2.2 Bore pumps locaton of the borefield).
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-8
Table 2.1 Location and area of the bores
No. Of bores Latitude (m) Longitude (m) Area (m) Aquifer area
GH01_PB01 697500 4814000 625
HT zone
GH01_PB02 697370 4812090 625
GH01_PB03 699500 4812000 625
GH01_PB04 699500 4810000 625
GH01_PB05 695500 4812000 625
GH01_PB06 696007 4813515 625
GH01_PB07 700750 4810709 625
GH02_PB01 691391 4810202 625
GH02_PB02 693658 4811345 625
GH02_PB03 693474 4808009 625
GH02_PB05 695500 4808000 625
GH02_PB06 697500 4810000 625
GH02_PB07 697424 4808524 625
GH03_PB01 689500 4806000 625
GH03_PB02 691500 4808000 625
GH03_PB04 689500 4804000 625
GH03_PB05 692368 4805110 625
GH03_PB06 693500 4806300 625
GH03_PB07 689500 4808000 625
GH04_PB01 681400 4801010 625
LT zone
GH04_PB02 682500 4804000 625
GH04_PB03 681347 4802834 625
GH04_PB04 682387 4798517 625
GH04_PB05 684500 4802000 625
GH04_PB06 685000 4804500 625
GH05_PB01 673500 4797000 625
GH05_PB02 676419 4798866 625
GH05_PB04 675500 4795000 625
GH05_PB05 678161 4797735 625
GH05_PB06 679000 4800000 625
Source: Fluor group, 2MW-6100-10C-200
The production bores will achieve a combined flow rate of 900 L/s. Production bores flow rate are
shown in Table 2.2.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-9
Table 2.2 Production Bores Flow Rate
LT area HT area
Total flow (L/s) No. of
bores
Flow per bore (L/s)
Total flow (L/s)
No. of bores
Flow per bore (L/s)
Total flow (L/s)
10 30 300 18 40 720 1020
2* 30 60 3
* 40 120 180
Source: Raw water supply pipeline detailed engineering design for bore location updated design report , Flour group, Aug 2008.
Note: * represents the installed standby capacity
Pump station is set for every production bore. Bore pump station hoist water from the raw water
storage pond and deliver to the collection tank pump. Each bore pump station will comprise a
modular structure containing the water bore, bore pump equipment, headworks, electrical
distribution panels and pipeline connection (Appendix 2.3 Bore pump station GH01_PB01site
plan).
With reference to the layout of mechanical and electrical equipment, the borehole pump house has
a design plan size of 4.8x8.0 m and height of 4.445 m and double-sloped roof. For maintaining the
suction pipe, the manhole in 1000 mm diameter is set at the roof. For installing equipment, the
pump house gate is sized 1500x2400 mm.
For cold climate protection, windows have double-layered glass, and the exterior gate is of
insulation-type steel.
With reference to operating conditions, the bore pump house adopts lightweight steel structure for
portal rigid frame, wall grider, gable column and purlin, and color coated steel sandwiched with
PVC benzene board for insulation. According to structural calculation, walls and roofs adopt 150
mm-thick boards sandwiched within steel plates of 0.8 mm thick; wall griders, gable columns and
purlins are of C-type lightweight steel, portal rigid frame is of H-type high frequency welded
variable-section lightweight steel structure.
Foundation is of the independent type below columns and connected with bracing beams in
adepth of over 2.2 m. The reinforced concrete foundation uses C35 concrete. This report attached
general architecture and design of the bore pump station. (Appendix 2.4 Bore pump station
GH01_PB01 elevation).
Gunii Hooloi borefield and water supply pipeline system consists total area of 2.0625 (for 33 bores)
hectares and bore pump station construction with its outside protection fence for each bore. Table
2.3 shown general parameters of the bore pump system.
Table 2.3 General parameters of bore pump system
No Types Size Area
1 Protection fence 25 m 25 m 625 m2
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-10
2 Protection fence (for 33 bore pumps) (25 m 25 m)x33 625*33=20625 m2 or 2.0625 ha
3 Bore pump station 8 m x 4.8 m 38.4 m2
4 Bore pump station (for 33 bore pumps ) (8 m 4.8 m) x 33 38.4*33=1267.2 m2
Source: Bore Pump Station General layout (A2MW-6110-10C-025),Gunii Hooloi borefield and Pipeline project
22..22 CCOOLLLLEECCTTOORR AANNDD BBRREEAAKK TTAANNKK SSTTAATTIIOONNSS
Water is delivered from the water bores to collection tanks via low pressure high density
polyethylene pipelines. Collection tank will serve groups of bores for the collection and onward
pumping of raw water to the emergency storage lagoon and Oyu Tolgoi site. CTPS#1-CTPS#5 will
be constructed depends on bore pump parameters and flow rate of the borefield and location and
area of the CTPS shown in Table 2.4.
Each collector tank will have approximately 1 hour storage and will include a series of horizontal
split case centrifugal pums including variable speed drive, magnetic flowmeter and rainage pumps.
(Appendix 2.5 Collector tank pump station CTP1 pipeline plan).
One operational and one standby pump will be provided for each of the two collection tanks in the
low transmissivity south-west part of the borefield and two operational and one standby pump will
be provided for each of the three collection tanks in the high transmissivity north-east part of the
borefield (Table 2.4).
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-11
Table 2.4 Location and area of the CTPS
No. of pump station Latitude (m) Longitude (m) Area () Borefield
aquifer area
CTPS#1 697295.02 4811780.88 5688
HT zone CTPS#2 694820.69 4809230.18 5688
CTPS #3 690844.73 4805587.32 5688
CTPS#4 681699.5 4800947.2 5688 LT zone
CTPS#5 675227.91 4796579.97 5688
#1 672505 4793168 6216
Source: Fluor group, 2MW-6100-10C-200
As requirement by pump layout, equipment room of CTPS#~CTPS#5 and BTPS#1 pump house is
of semi-underground type. Equipment room, based on installation and lifting requirement, has a
building height of 6.4 m, and electrical room of 4.3 m. Pump houses have double roofs with slope
of 1:12. For requirements of equipment installation and maintenance and ramp of 4.2 m wide is
arranged at extreme end in equipment room for convenience of transport and installation.
Windows sized as 3600 x 1500 mm are set in the front wall. For cold climate protection, windows
have double-layered glass, and the exterior gate is of insulation-type steel.
CTPS#1~CTPS#5 and BTPS #1 pump houses adopt lightweight portal steel structure, and walls,
and roofs use insulation type sandwiched board. According to electro-mechanical calculation, walls
and roofs adopt 150 mm thick boards sandwiched within steel plates of 0.8 mm thick; wall griders,
gable columns and purlins are of C-type lightweight steel, portal rigid frame is of H-type high-
frequency welded variable section lightweight steel structure (Appendix 2.6 General layout of
CTPS#1). In the detail design based on water regulation, the collector tank and break tank have
three types of storage capacity respectively 300 m3, 400 m3 and 600m3, CTP#1~CTP#3 have
design capacity of 2 x 400 m3, CTP#4~CTP#5 of 2 x 300 m3, BTPS#1 of 2x600 m3. Structural
calculation are based on cast-in-place concrete. Structural calculations have been made for tank
wall, top and base slabs using respectively substition framework method and no beam cover
structure.
Below Table 2.5 shown technical parameters of the CTPS#1~CTPS#5 and BTPS#1.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-12
Table 2.5 Technical parameters in Pump House CTPS#1~CTPS#5 and BTPS #1
Layout of pump house
CTPS#1 CTPS#2 CTPS#3 CTPS#4 CTPS#5 BTPS#1
Plan size 45.87512.0m 45.87512.0m 51.87512.0m 38.37512.0m 38.37512.0m 69.87518.0m
Building height 6.404 m 6.404 m 6.404 m 6.404 m 6.404 m 6.404 m
Electrical room 4.3 m 4.3 m 4.3 m 4.3 m 4.3 m 4.3 m
Equipment installation and maintenance
4.2m, 12 slope
4.2m, 12
slope 4.2m, 12
slope 4.2m, 12
slope 4.2m, 12
slope 4.2m, 12
slope
Water capacity 2300 m3 2300 m
3 2300 m
3 2300 m
3 2300 m
3 2600 m
3
Pump parameters
2 duty, 1 standby, Q=432m
3/h,
H=188m and N=315 kW
2 duty, 1 standby, Q=432m
3/h,
H=156m and N=250kW
2 duty, 1standby, Q=432 m
3/h,
H=105m and N=315kW
1 duty, 1 standby, Q=540m
3/h
H=38m and N=90kW
1 duty, 1 standby, Q=540m
3/h
H=31b and N=75kW
3 duty, 1 standby, Q=1080m
3/h,
H=237m and N=1000kW
Maintanence of Equipment and Valve (gantry crane features)
5t weight, 9.0m lifting height, 11.0m span, 7.5kW electric hoist, 0.8kW small trolley and and 20.8 kW big trolley
5t weight, 9.0m lifting height, 11.0m span, 7.5kW electric hoist, 0.8kW small trolley and and 20.8 kW big trolley
3t weight, 9.0m lifting height, 11.0m span, 4.5kW electric hoist, 0.4 kW small trolley and 20.8 kW big trolley
2t weight, 9.0m lifting height, 11.0m span, 3kW electric hoist, 0.4 kW small trolley and 20.8 kW big trolley
2t weight, 9.0 m lifting height, 11.0m span, 3kW electric hoist, 0.4 kW small trolley and 20.8 kW big trolley
10t weight, 9.0m lifting height, 16.5m span, 13kW electric hoist, 0.8 2kW small and 20.8 kW big trolley
Air (water) surge tank
Diameter of 2.0m, height 4.0 m
Diameter 3.8m , 6.0m height
Diameter of 3.8 m, 6.0m height
Leakage and Maintenance Drainage
To drain water from seepage, maintenance and rain on ramp from pump house, a sump of 2.0m (H)1.5m (W)1.8m(D)is set at left side of pump house with two movable submersible drainage pumps(1 duty and 1 standby) in. Pump outlet pipes separately extend out of house wall 0.3m
above ground and 1.0m away to an anti-scour apron.
Water Supply As required by Client, a toilet is set nearby control room, getting water through pipes after relieved by three-stage valves from pump outlet pipe
Sewage system Domestic sewage and waste water meet and drain through DN150 DICL pipe into
outdoor septic tank.
Source: Raw water supply pipeline detailed engiinering design report, Fluor group, Aug, 2008.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-13
22..33 EEMMEERRGGEENNCCYY SSTTOORRAAGGEE LLAAGGOOOONN
Two 200,000 m3 capacity emergency storage lagoons will be constructed on elevated ground (N
650824.56, E 4772533.64) approximately 5 km to the north of the Oyu Tolgoi site. As required,
the Lagoon storage is 400,000m3, including a 2-cell arrangement and each with a base width of 90
m and base length of 120 m.
The emergency storage lagoons will provide over a weeks water supply to the site in the event of
a major borefield / pipeline failure. This will allow sufficient time for any necessary repairs to be
made and the borefield/pipeline returned to full functionality. The emergency storage lagoons will
be constructed with earth embankments and will be completely lined with high density polyethylene
liner system in order to minimize leakage and water loss. The emergency storage lagoons will also
be completely covered by a floating cover liner in order to minimize evaporative water loss and to
prevent the undesirable accumulation of dust. The embankment design is to fully utilize the local
material. The excavation area is 55300 m2 and 5.53 ha, and if not fully utilized, disposal will be
large and the project cost will be increased. The design therefore will take measures to make the
material satisfactory to embankment and minimize disposal and soil replacement. On the basis of
safety, cost will be minimized. The embankment seepage and stability calculation has been carried
out on the basis of shear strength of rocks available in geological data, indicating the exterior slope
of 1:2.5 and interior slope of 1:3 are feasible ( 2.7
).
Photo 1. General position of the lagoon
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-14
22..44 WWAATTEERR PPIIPPEELLIINNEE DDEESSIIGGNN
The main line of water supply pipeline totals 148.814 km, which is included delivered pipeline from
collection tank pump of 67.162 km length and pipeline of borehole connected from collection tank
pump 81.652 km length.
Under the control of the design principle, the suitable types of pipe include Ductile Iron Cement
Lined (DICL) pipe, High-Density Polyethylene (HDPE) pipe, carbon steel (CS) pipe and Fiberglass-
Reinforced Plastics (FRP) pipe.
Main pipeline diameter is different which is depends on flow rate capacity of tank pupms and the
main pipeline characteristic parameters are shown in Table 2.6 and Table 2.7.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-15
Table 2.6 Borehole to CTPS#1~ CTPS#5 Pipeline Parameters
Pip
e
sta
rtin
g
Pip
e e
nd
Desig
n f
low
L
/s
Calc
ula
tio
n
pre
ssu
re
b
ar
Pip
e
dia
mete
r (
)
Pip
e
mate
rial
Pip
elin
e
len
gth
m
Bo
refi
eld
are
a
GH01_PB01 C
TP
S#1
40 2.04 10 HDPE 2185
HT
zo
ne
GH01_P02 40 0.60 10 HDPE 278
GH01_PB03 40 2.76 10 HDPE 2558
GH01_PB04 40 2.16 10 HDPE 2948
GH01_PB05 40 1.32 10 HDPE 1791
GH01_PB06 40 1.56 10 HDPE 2107
GH01_PB07 40 3.24 10 HDPE 3696
GH02_PB01
CT
PS
#2
40 2.64 10 HDPE 3596
GH02_PB02 40 3.96 10 HDPE 2407
GH02_PB03 40 1.32 10 HDPE 1861
GH02_PB04 40 3.36 10 HDPE 1049
GH02_PB05 40 1.80 10 HDPE 1441
GH02_PB06 40 3.24 10 HDPE 2786
GH02_PB07 40 3.60 10 HDPE 2700
GH03_PB01
CT
PS
#3
40 1.20 10 HDPE 1393
GH03_PB02 40 4.92 10 HDPE 2503
GH03_PB03 40 2.04 10 HDPE 793
GH03_PB04 40 1.80 10 HDPE 2090
GH03_PB05 40 2.16 10 HDPE 1593
GH03_PB06 40 6.36 10 HDPE 4205
GH03_PB07 40 3.12 10 HDPE 2756
GH04_PB01
CT
PS
#4
30 1.08 10 HDPE 2429
LT
zo
ne
GH04_PB02 30 1.32 10 HDPE 3157
GH04_PB03 30 0.84 10 HDPE 1943
GH04_PB04 30 2.04 10 HDPE 2565
GH04_PB05 30 1.56 10 HDPE 2984
GH04_PB06 30 2.04 10 HDPE 4845
GH05_PB01
CT
PS
#5
30 1.32 DN200 DICL 1767
GH05_PB02 30 2.04 DN200 DICL 2577
GH05_PB03 30 1.56 DN200 DICL 1198
GH05_PB04 30 2.28 DN200 DICL 1647
GH05_PB05 30 4.32 DN200 DICL 3560
GH05_PB06 30 3.72 DN200 DICL 5086
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-16
Table 2.7 Main pipeline parameter
Pipe starting
Pipe end
Design flow
m3/h
Design pressure
bar
Diameter of the
pipeline (mm)
Pipeline material
Length of the
pipeline
m
CTPS#1 BTPS#1 432/864/1296/1836/2376
22.8/19.2/13.2/4.32/24
DN500/DN700/DN800/DN900
DICL
31309
CTPS#2 Main pipeline 432 19.20 DN500 DICL
82
CTPS3 Main pipeline 432 13.20 DN500 DICL
111
CTPS#4 Main pipeline 540 4.32 DN400 DICL 111
CTPS#5 Main pipeline 540 24.00 DN400 DICL
111
CTPS#1 Lagoon 2376 28.20 DN900 DICL
31218
Lagoon Mine site 2376 2.00 DN900 DICL
24268
Source: Detailed design report of the industrial water supply pipeline, Flour Group, Aug, 2008.
The parameters of the these CTPS and BTPS attached in (Appendix 2.8 Collector tank pump
station CTP1 piping plan, Appendix 2.9 Collector tank pump station CTPS1 pipeline section,
Appendix 2.10 Break tank pump station BTP1 pipeline plan (Sheet 1 of 2), Appendix 2.11 Break
tank pump station BTP1 pipeline plan (Sheet 2 of 2)).
2.4.1 Pipeline cleaning
The cleaning devices (Pigging) are arranged at the main pipeline, 7 sets of pigging will be
designed for the main pipeline system.
HDPE pipe has excellent performance of stable chemical property, inherent resistance against
corrosion and scaling, strong abrasiveness, resistance against acid and alkali and low roughness.
So pipeline pigging system is not considered for the HDPE pipe.
Noted that gravity pipeline has excessive capacity to the site even with scaling and that build up
of scale doesnt impact any pumping efficiencies (as the gravity line is not pumped). As such,
pigging system is not considered to be necessary.
Pigging No.1 is installed in the DN500 pipe section near the connection with
CTPS#1 discharge pipe.
Pigging No.2 is installed in the DN700 pipe section near the connection with
CTPS#2 discharge pipe.
Pigging No.3 is installed in the DN800 pipe section near the connection with
CTPS#3 discharge pipe.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-17
Pigging No.4 is installed in the DN900 pipe section near the connection with
CTPS#4 discharge pipe.
Pigging No.5 is installed in the DN900 pipe section near the main pipe inlet to break
tank.
Pigging No.6 is installed in the DN900 pipe section near the connection with
BTPS#1 discharge pipe.
2.4.2 CTPS#1~CTPS#5 and BTPS#1 pipeline layout
CTPS#1~CTPS#5 & BTPS#1 mainly consist of inlet flow meter pit, collector tank and pump
house. The pipeline consists of inlet pipe, overflow pip, vent pipe and outlet pipe for collector tank,
suction pipe, inlet pipe and outlet pipe for pumps, bypass (CTPS#5), compressed air pipe, diesel
oil pipe and instrument pipe.
2.4.3 Layout of lagoon
Lagoon mainly consists of inlet flow meter pit, inlet valve pit, storage pond, outlet valve pit, outlet
flow meter pit, intake and outlet. The pipeline consists of inlet pipe, outlet pipe, bypass and
instrument pipe.
2.4.4 Pipeline protection
High density polyethylene (HDPE) and ductile iron cement lied (DICL) pipes have been selcted for
use due to having high internal and external corrosion resistance. In extreme cases, (for example
at river crossing), additional corrosion protection will be applied to DICL pipes. Engineering
geological investigation analysis shows the amount of mineral substances in the gravel, sand and
clay soils is extremely high. However because of the generally low moisture barrier is sufficient
protection for most of the pipelines.
Common practice in Mongolia for basic corrosion protection for steel pipe involves outside coating
with a layer of bitumen of 3 mm thick and wrapping by one layer of synthetic film or brizol (ruberoid
film coated with bitumen). The strenghtened protection involves coating by two layers of bitumen
and two layers of wrapping by ruberoid containing brizol or bitumen. There are other wrapping
products used outside Mongolian that may be more effective and these should be compared with
the local methods for cost-effectiveness.
It is also important to route high-voltage power lines away from the steel pipelines to avoid inducing
currents that will promote corrosion.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-18
2.4.5 Pipeline excavation and backfill
Trench digging and backfilling should be done in accordance with Mongolian standards. The
standard state that potable water pipelibes without insulation shall be installed at a minimum depth
of 0.5 m below freezing level which, based on the stated freezing depth of 1.5 m to 2.2 m, would
require that the top of the pipe be placed at a minimum depth of 2.2 m to 2.7 m depth beneath
natural surface. With pipe diameters up to 900 mm diameter plus bedding material, trench depth
can easily reach 4.0 m. Freezing depth for different soils in accordance with Mongolian norms are
presented in the Table below (Appendix 2.12 Pipeline typical cross sections).
Table 2.8 Excavation Depth for Pipe Trenches
Nominal diameter
Trench width (m ) Records
10 2.75 Pipeline between bore pump and
CTPS#1CTPS#5
DN400 2.65 Main pipe
DN500 2.60 Main pipe
DN700 2.6 Main pipe
DN800 1.95 Main pipe
DN900 1.85 Main pipe
The finally adopted trench slope shall be determined based on type of soil and depth of trench and
will be finalised in the detailed design phase. The current proposed trench slopes are illustrated in
the Table below.
Table 2.9 Trench slope versus soil types and depths
Soil type Trench depths, m
0,0 3,0 3,0 6,0
Sand and gravel 1:1.25 1:1.25
Sandy clay 1:0.67 1:1
Clay 1:0.5 1:0.67
Note: Slopes shown are to read as Ver : Hor
The minimum width at the base of the trench shall be at least the outside diameter of the pipe plus
a minimum of 0.5 m. Where the pipe diameter exceeds DN700 mm, the trench width should be a
minimum of 1.5 times the diameter of pipe (i.e. 1.5 DN) as illustrated below. However, in
estimating the extent of the trench excavation and costs, it has been assumed that an excavator
with a 1.25 m wide bucket will be used to excavate the trench, and for practical proposes this is
has been taken as the minimum bottom width of the trench.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-19
2.4.6 Pipeline thrust block
Hydraulic thrust forces occur at changes in direction, reductions in diameter (bends, tees and
tapers) and at the ends of pipelines carrying water under pressures. They can be high and must be
counterbalanced by appropriate self-anchored joint systems or by anchor blocks. According to the
arrangement design of main pipeline, the following typical pipe section should be protected by
thrust block.
1. Unburied pipe at the turn in the pump house.
2. Ductile iron pipe with socket and spigot connection at the vertical bend, horizontal bend, T-
shaped pipe and pipe block.
3. Fiberglass-Reinforced Plastic (FBR) pipe with socket and spigot connection at the vertical
bend.
When the hydraulic thrust forces in the pipe is beyond the force endured by the pipe itself, the
thrust block should be considered.
22..55 IINNFFRRAASSTTRRUUCCTTUURREE RREEQQUUIIRREEMMEENNTTSS
2.5.1 Fire safety
With reference to geographic location and project features, fire safety approaches are selected
based on functions of different rooms in CTPS#1~CTPS#5 and BTPS#1. At present, both propane
heptafluoride gas no-pipe devices (propane devices) and portable fire extinguishers are used in
control room, electrical room, diesel generator room and oil tank room of CTPS#1 to CTPS#5,
BTPS#1 and control room of Lagoon, and only portable fire extinguishers are used in bore pump
houses and operators room at Lagoon.
2.5.2 Heating, Ventilation and air conditioning system
Water pipeline and water pump are arranged in CTP, CTP#1~CTP#5 and BTPS#1, Indoor
temperature shall be maintained within the range specified in codes while water pump working or
water pump in shutdown in winter. A set of air conditioner is installed at the electric room with
different cooling capacity for use in summer. Air conditioner is started once temperature is higher
than 38C, and stop once lower than 28C. Heating, Ventilation, and Air Contioning Design
Considerations for BPS, CTPS and BTPS are listed in Table 2.10.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-20
Table 2.10 Heating, Ventilation, and Air Contioning Design Considerations for BPS, CTPS and BTPS
Parameters Bore Pump
Station CTPS#1 BTPS#1
Hot-
pla
tes
Indoor temperature +5C +5C +5C
Started once temperature
lower than +5C lower than +5C lower than +5C
Stop once temperature higher than +15C higher than +8C higher than +8C
Far infrared hot-plates eight 2000 W far infrared hot-plates
three 2000 W far infrared hot-plates
three 2000 W far infrared hot-plates
Air c
onditio
ner
at
the e
lectr
ical
room
Heat generation of electrical equipment
4 kW 4 kW 4 kW
Cooling capacity 6000 kW 14000 kW 100000 kW
Started once temperature
higher than +38C higher than +38C higher than +38C
Stop once temperature lower than +28C lower than +28C lower than +28C
Air c
onditio
ner
at
the e
lectr
ical
room
Cooling capacity 7000 kW 7000 kW
Started once temperature
higher than +38C higher than +38C
Stop once temperature lower than +28C lower than +28C
Water pipe 6 cm of exceed thin glass cotton
6 cm of exceed thin glass cotton
6 cm of exceed thin glass cotton
2.5.3 Power supply
The 35kV power supply which comes from the mine through the overhead line serves every BPS,
CTPS#1, CTPS#2, CTPS#3, CTPS#4, CTPS#5, BTPS#1, and Lagoon. A 35KV substation is set at
the pump station to step down the voltage to 6KV and connects every BPS, CTPS#1-CTPS#5,
BTPS#1 and Lagoon through cables.
The 6KV overhead line connects the nearby CTPS#1-CTPS#5 to each Bore Pump Station (all 33),
and a 6KV outdoor transformer stepping down to 0.4KV is set at each Bore Pump Station.
2.5.4 Design of distributed control system
The DCS is arranged for the whole OT water supply system, which consists of the remote control
layer within the WCC, the control layer of pump station, local control station and network
equipment, installed respectively in each CTPS#1~CTPS#5, BTPS#1 and Lagoon under VFD
(Variable Frequency Drives) to regulate flow rate. The VFD communicates with the DCS through
Profibus DP to realize automatic control of the pipeline system. The DCS takes signal
measurement of flow, pressure, temperature, leakage, etc. at key positions of the pipeline, and
enables local display and remote transmission.
The DCS for the pump station is open and distribution system with flexible configuration and
convenient functional pattern. The local control station, as the LCU (Local Control Unit) of the
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-21
motor, is distributed in each pump house, and collects the status signal of the motor, enables auto-
control of the pump and remote signal transmission.
The connection between every control layer of pump station is carried out through Ethernet in
exchange at a speed of 100Mbps in conformity with TCP/IP. The communication means of either
wireless (e.g. microwave) or optical cable are to be determined by PMT.
2.5.5 Design of security system
Security system is composed of three sub-systems:
Fire alarm,
CCTV system,
Security and access control.
Fire alarm: With reference to the building layout in the basic design and specifications, an
area fire alarm control is set in each of BPS, CTPS#1~CTPS#5, BTPS#1, and Lagoon,
totally 40 of such controls, which connects with the communication device of the pump
station supplied by others through the Ethernet interface. The dot-type smoke detector and
dot-type temperature detector is placed on the roof of the each BPS.
CCTV system: A set-up of this system is isatalled each construction. Two cameras are set
at each of the bore pump stations, totally 66. Four CCTV cameras are set in each of
CTPS#1~CTPS#5, totally 20 cameras. CCTV cameras are set at BTPS#1, totally five
cameras. The totally five cameras are set at Lagoon.
Security and access control: All rooms of the above buildings are set with passive
infrared detector, and the access switch is set at the entrance of pump and main room. The
active infrared detector is set at the walls around the building. All detection signals are
received by the main security control in the pump station and then interface with the
communication device supplied by others.
2.5.6 Maintenance road
The main line of maintenance roads totals 67.105 km, and the line of totally 30 branch roads is
75.596 km long. The design of maintenance roads considers the low frequency of traffic and small
load. According to the geotechnical data along the pipeline, the plane curve, vertical curve and
turning radius all follow the requirements of Mongolian design codes. The pavement structural
design is based on truck-20t load, including the road surface width of 4.5 m, shoulder width of 1m
at both cut and fill sections, and the road surface is of graded gravel pavement. Roads across the
river are specially designed with concrete pavement. Fill sections will borrow materials from the
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-22
nearby area, and for pure sand sections, materials will be cut and transported from the specialized
borrow area.
The design of maintenance roads includes minimum horizontal curvature radius of 100m, minimum
vertical curve of 1000m and maximum slope of 5.7%. The alignment has been modified to ensue
that there are minimal crossing of watercourses and where these occur, there will be requirements
for culvert / floodway type crossing at these points.
All road construction material will be won from local sources along the route with the best quality
material being used for the wearing course and the lower quality material utilized as base course.
Figure 2.1 Maintenance road design
22..66 WWAATTEERR QQUUAALLIITTYY
The raw water quality of the Gunii Hooloi borefield may be characterized as:
1. Relatively high salinity;
2. A high degree of hardness;
3. Relatively high pH and alkalinity;
4. Relatively low in iron; and
5. Does not present any significant bacteriological contamination.
It is anticipated that the water will fall in temperature from the approximately insitu temperature of
15C in the aquifer to a temperature of 2C at the delivery point at the end of the main pipeline
during winter. It is highly undesirable to treat the water in dispersed bore field. At most, chemical
dosing is sometimes used to control scaling or corrosivity in the collector main pipelines.
Section Groundwater will be included about it more comprehensive.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-23
3.0 ENVIRONMENTAL IMPACTS ASSESSMENT OF THE PROJECT
This assessment was conducted in accordance with law on Environmental Impacts Assessment
and in coordination with methodological instruction on conducting detailed environmental impact
assessment indicated in attachment three of order N 119 issued by Minister of Environment in April
27, 2006. They include establishment of water supply pipelines from Oyu Tolgoi and Gunii Hooloi
phreatic water resources; main environmental impacts on nature when water supply is closed;
movements of vehicles and equipments used for constructing and utilizing the water supply; noise
caused by engines used in facilities, and; damage and soil degredation and vegetation.
Detailed environmental baseline research of areas where the project is planned to implement
including Oyu Tolgoi deposit, Galbyn Gobi and Gunii Hooloi has been conducted by environmental
impact assessment experts of Eco Trade Company since 2002. Therefore detailed report on
assessment was developed and some information and data from the report are used in the present
report.
Please refer to following documents for more detailed information: Detailed Environmental Impact
Assessment of Oyu Tolgoi project- Volume III: Mining and Processing, Detailed Environmental
Impact Assessment of Oyu Tolgoi project Groundwater Resource Use from Gunii Hooloi and
Galbyn Gobi Regional Aquifers-Volume II, Environmental baseline report, 2003 , Environmental
Baseline Report of Oyu Tolgoi project, 2003 prepared by Eco Trade LLC.
33..11 MMEETTHHOODDOOLLOOGGYY OOFF AASSSSEESSSSMMEENNTT
When we assessed environmental impacts of Oyu Tolgoi water supply pipeline project we used
matrix method with 5 stages and then we consolidated how much was the impact of water supply
pipeline project for the area. Finally we combined all impacts for each certain area to make one
general conclusion. We have assessed the extent of impacts to the environment and their
probability using the expert matrix method with 5 stages and 25 categories. A summary
considering the main results of impacts regarding each object affected negatively is as follows:
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-24
Figure 3.1 Expert assessment matrix
Impacts
Magnitude and extent of impact
Insignificant Low Moderate High Extreme
Probability
High :
given or certain
or currently
occurring
Moderate Moderate High High High
Probable or
likely:
re-occurrence
interval of less 1
month
Low Moderate Moderate High High
Possible:
re-occurrence
interval of 1
month to 2
years
No impact Low Moderate High High
Unusual or
unlikely:
re-occurrence
interval of 2 to
10 years
No impact No impact Low Moderate High
Rare:
re-occurrence
interval of >10
years
No impact No impact Low Moderate Moderate
Assessing certain risk in coordination with intensity, extent and probability of negative
environmental impact corresponded with reality more and it was helpful to design and work out the
environmental protection plan and environmental analysis and monitoring program. For instance, in
the occurrence of certain risk, if negative impact is medium and extent is little while probability is
high, this risk or negative impact is included in the high risk category which requires us to pay more
attention on risk preventive measures.
We analyzed intensity and probability of each environmental impact by the following methods:
collecting data, analyzing the collected data and simulating the impact through mathematical
modeling.
Oyu Tolgoi project DEIA of Water Supply Pipeline
Prepared by ECO-TRADE LLC., Environmental Consultants, Mongolia. Client: Ivanhoe Mines Mongolia Inc LLC
Page-25
33..22 MMAAIINN AASSSSEESSSSMMEENNTT MMEETTHHOODDSS
Fundamental environmental research Current condition of environment (it includes: climate, air
quality, geography, landscape, geology, surface and internal water, soil and subsoil, flora and
fauna) and cultural heritage research were conducted based on field research material, data and
monitoring data done in June 2007. Additionally we used data from the following reports: Detailed
Environmental Impact Assessment of the Oyu Tolgoi Project Mining and Processing - Volume III
and Detailed Environmental Impact Assessment of the Oyu Tolgoi Project Groundwater Resource
Use from Gunii Hooloi and Galbyn Gobi Groundwater Regional Aquifer-Volume II.
The assessment on impact to the quality of the environment involved analysis of data and
compiling summaries based on fundamental research on the current condition of environment
using the method of matrix according to assessment requirements.
Probable negative impacts to environment were estimated based on modeling, standard analysis
and estimation. Management and mitigation measures are presented in this report to address the
predicted negative impacts.
4.0 CLIMATE
44..11 CCHHAARRAACCTTEERRIISSTTIICCSS OOFF CCLLIIMMAATTEE
Internal water resource area of Gunii Hooloi is located 40-60 km away north east of Oyu Tolgoi
deposit. It borders with mountain Khanbogd the east and with Galbyn Gobi on the northeast which
creates very large valley. As for climate, it is same as climate of areas of Khanbogd and Oyu
Tolgoi. Location of the meteorological stations around the project area is included in Appendix 4.1.
Eco Trade Company developed main climate indicators of Oyu Tolgoi and surrounding areas
based on long term data collected at meteorological stations of Khanbogd and Bayan-Ovoo sums
and data collected at meteorological station established at Oyu Tolgoi project area in 2002. The
collected information was included in report Detailed Environmental Impact Assessment of Oyu
Tolgoi project Mining and Processing - Section III by Eco Trade LLC completed in 2006.
To examine the climate characteristics:
Generally there is high temperature fluctuation at Oyu Tolgoi and surrounding areas depending on
day, night and season. Therefore the extreme temperature varies between -350 and +380 which
has severe continental climate characteristics. The number of warm days which temperature is
over +300 reaches 120-140 days per year, and number of warm days per year which temperature
is over 00 ranges between 210 and 232 days.
Average annual temperature is 6.9C, and annual temperature difference is 50.6C in average.
Highest average temperature of many years reaches 30.9C (average of July), average minimum
temperature reaches -19.7C (average of January). Daily average temperature fluctuation is
Oyu Tolgoi project