DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17) 2)K.Murugan (05ME31) 3) R.Satheesh Kumar (06MEL65) 4)S.Sathish (06MEL66) INTERNAL GUIDE: Mr.S.Gopikannan M.E,MBA EXTERNAL GUIDE: Mr. P.Nithyakumar-Rane Engine Valve Ltd,.

DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

Embed Size (px)

Citation preview

Page 1: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN

HEADED FORGING PRESSBATCH NUMBER-15

BATCH MEMBERS:

1)S.Ganapathy Subramaniam (05ME17)

2)K.Murugan (05ME31)

3) R.Satheesh Kumar (06MEL65)

4)S.Sathish (06MEL66)

INTERNAL GUIDE:

Mr.S.Gopikannan M.E,MBA

EXTERNAL GUIDE:

Mr. P.Nithyakumar-Rane Engine Valve Ltd,.

Page 2: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

CONTENTS

• Company profile

• Definition of problem

• Reason Why We Chosen

• Objective and Scope

• Proposed Methodology

• Phase Schedule

Page 3: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

COMPANY PROFILERANE ENGINE VALVES Ltd,.

• Incepted in 1959 to manufacture valves and valve train components for various engine applications

• Latest manufacturing practices to keep abreast of technological advancements

• Caters to every section of the auto industry through four manufacturing plants

• Cutting edge technology• Market leaders in range of products-Engine valves,

Valve Guide and Tappets.• Clientele spread across Europe, North America and the

Far Eastern markets including the best known brands such as Volkswagen, Deutz and Yamaha

Page 4: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

MANUFACTURING

• 5 plants located in Chennai, Hyderabad & Trichy manufacture engine valves, valve guides and tappets.

• Plant 1 (Chennai) - Engine Valves

• Plant 2 (Hyderabad) - Engine Valves

• Plant 3 (Chennai) - Guides & Tappets

• Plant 4 (Hyderabad) - Engine Valves

• Plant 5 (Trichy) - Engine Valves

Page 5: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

DEFINITION OF PROBLEM

• The equipment for production of Engine Valves is not fully utilized due to practical difficulties over the material handling devices.

• Analysis for Automation feasibility is expensive or inexpensive.

Page 6: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

REASON WHY WE CHOSEN

• As we have to design a handling device for loading cum unloading the valves from die to increase the utilization of equipment efficiency and also production rate.

• we have chosen this project because its related to production area in which we are very much interested and also a challenging real time industrial project.

Page 7: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

OBJECTIVE AND SCOPE

• Objective: To increase the production rate of valves by introducing Twin Die Forging Concept with handling device.

• Scope: By implementing this concept nearly production rate can be doubled.

Page 8: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

PROPOSED METHODOLOGY

Analysis of component

Analyze the present Die manufacturing technique

Designing a loading cum unloading device

Analysis of pros and cons of the design

Fabrication Of HandlingDevice

Trial run

Production

Page 9: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)
Page 10: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)

PHASE SCHEDULE

Phase-1

(8thDec’08 to 31st Jan 09)

Phase-2

(Feb)

Phase-3

(Mar)

Analysis of component Pros and Cons Report Preparation

Analyzing the existing manufacturing technique

Fabrication process

Designing process Trial run

Production

Page 11: DESIGN AND FABRICATION OF ENGINE VALVES HANDLING DEVICE FOR TWIN HEADED FORGING PRESS BATCH NUMBER-15 BATCH MEMBERS: 1)S.Ganapathy Subramaniam (05ME17)