S.l. No. Description Work Program of 2nd June, 2011 Achievement of 1st May, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Culvert (road) Concrete pouring of 2nd wall Concrete pouring of 1st wall Executed
6 Open Deep Drain(CH 600-650) Concrete pouring of wall (2nd lift) Shuttering Executed
Open Deep Drain(CH 520-535) CC Casting Soling Executed
7 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Earth Excavation
8 RCC pipe Concrete pouring Concrete pouring in progress
9 Shore Pile Shutter making & Rebar fabrication
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,2nd June, 2011
8/13/2019 Daily Program June-2011
2/23
Project Manager
S.l. No. Description Work Program of 7th June, 2011 Achievement of 6th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Culvert (road) Shuttering of 2nd lift Rebar fabrication in 2nd lift
6 Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Shuttering Executed
7 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Earth Excavation Earth Excavation in progress
8 RCC pipe Concrete pouring Concrete pouring in progress
9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,7th June, 2011
8/13/2019 Daily Program June-2011
3/23
S.l. No. Description Work Program of 8th June, 2011 Achievement of 7th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Shuttering Executed
6 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Earth Excavation Earth Excavation in progress
7 RCC pipe Concrete pouring Concrete pouring in progress
8 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
9 Interlocking Block ILB plant shift ILB plant shift in progress
10 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,8th June, 2011
8/13/2019 Daily Program June-2011
4/23
S.l. No. Description Work Program of 11th June, 2011 Achievement of 10th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Shuttering Executed
6 Culvert (Roadl) Wall 2nd lift Concrete pouring of wall 2nd lift
7 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Earth Excavation Earth Excavation in progress
8 RCC pipe Concrete pouring Concrete pouring in progress
9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progres
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 11th June, 2011
8/13/2019 Daily Program June-2011
5/23
S.l. No. Description Work Program of 12th June, 2011 Achievement of 11th June, 2011 Remark
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Shuttering Executed
6 Culvert (Roadl) Wall 2nd lift Concrete pouring of wall 2nd lift
7 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Earth Excavation Earth Excavation in progress
8 RCC pipe Concrete pouring Concrete pouring in progress
9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 12th June, 2011
8/13/2019 Daily Program June-2011
6/23
S.l. No. Description Work Program of 13th June, 2011 Achievement of 12th June, 2011 Remarks
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) 300mm Sand Blanket filling finished 300mm Sand Blanket filling in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Open Deep Drain (CH 520-535) Shuttering of 2nd lift Concrete pouring of wall 1st lift
6 Culvert (Roadl) Top slab shuttering Concrete pouring of wall 2nd lift
7 Culvert (rail) Rebar fabrication Rebar fabrication in progress
Base C.C casting Earth Excavation finished
8 RCC pipe - Concrete pouring in progress
9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantl ing work at Segment 3 & 4 in progress
(Engr.Nityananda Nandi)
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 13th June, 2011
8/13/2019 Daily Program June-2011
7/23
S.l. No.Description Work Program of 16th June, 2011 Achievement of 15th June, 2011 Rem
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) PVD Driving 300mm Sand Blanket filling is finished
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress
7 Culvert (rail) Rebar binding of Base Rebar binding of Base in progress
9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 16th June, 2011
8/13/2019 Daily Program June-2011
8/23
S.l. No Description Work Program of 21th June, 2011 Achievement of 20th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) PVD Driving PVD Driving in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress
5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress
7 Culvert (rail) Shuttering & Rebar binding of Base Rebar binding of Base in progress
9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 21th June, 2011
8/13/2019 Daily Program June-2011
9/23
S.l. No Description Work Program of 22th June, 2011 Achievement of 21th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog
Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 2A (part) PVD Driving PVD Driving in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress
5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress
7 Culvert (rail) Shuttering & Rebar binding of Base Rebar binding of Base in progress
9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 22th June, 2011
8/13/2019 Daily Program June-2011
10/23
S.l. No Description Work Program of 23th June, 2011 Achievement of 22th June, 2011
1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog
Regular Settlement Record of Preloading Settlement Record in progress
3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress
5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
6 Culvert (Roadl) Concrete pouring of top slab Top slab shuttering & rebar binding finished
7 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed
9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress
10 Interlocking Block ILB plant shift ILB plant shift in progress
11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 23th June, 2011
8/13/2019 Daily Program June-2011
11/23
8/13/2019 Daily Program June-2011
12/23
S.l. No Description Work Program of 25th June, 2011 Achievement of 24th June, 2011
1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
3 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress
4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
5 Culvert (Roadl) Concrete pouring of slab executed
6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed
7 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress
8 Interlocking Block ILB plant shift ILB plant shift in progress
9 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 25th June, 2011
8/13/2019 Daily Program June-2011
13/23
8/13/2019 Daily Program June-2011
14/23
S.l. No Description Work Program of 26th June, 2011 Achievement of 25th June, 2011
1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
3 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress
4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
5 Culvert (Roadl) Concrete pouring of slab executed
6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed
7 Shore Pile Concrete Pouring Concrete Pouring in Progress
8 Inter locking Block ILB plant shift ILB plant shift in progress
9 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 26th June, 2011
8/13/2019 Daily Program June-2011
15/23
8/13/2019 Daily Program June-2011
16/23
S.l. No.Description Work Program of 28th June, 2011 Achievement of 27th June, 2011 Rem
1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
3 Segment 4 (part) Sub-Grade Preparation Levelling & Dressing in progress
4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
5 Culvert (Roadl) Concrete pouring of slab executed
6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed
7 Shore Pile Concrete Pouring Concrete Pouring in Progress
8 Interlocking Block ILB plant shift ILB plant shift in progress
9 Road Work Layout fixing of Road Type-1
10 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 28th June, 2011
8/13/2019 Daily Program June-2011
17/23
8/13/2019 Daily Program June-2011
18/23
8/13/2019 Daily Program June-2011
19/23
8/13/2019 Daily Program June-2011
20/23
S.l. No.Description Work Program of 29th June, 2011 Achievement of 28th June, 2011 Rem
1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress
2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.
3 Segment 4 (part) Sub-Grade Preparation Sub-Grade preparation in progress
4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished
5 Culvert (Roadl) Concrete pouring of slab executed
6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed
7 Shore Pile Concrete Pouring Concrete Pouring in Progress
8 Interlocking Block ILB plant shift ILB plant shift in progress
9 Road Work Layout fixing of Road Type-1
10 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress
Project Manager
NCT Back-up Project
Project Builders Ltd
NCT BACK-UP PROJECT, CHITTAGONG
Work Program, 29th June, 2011