    S.l. No. Description Work Program of 2nd June, 2011 Achievement of 1st May, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Culvert (road) Concrete pouring of 2nd wall Concrete pouring of 1st wall Executed

    6 Open Deep Drain(CH 600-650) Concrete pouring of wall (2nd lift) Shuttering Executed

    Open Deep Drain(CH 520-535) CC Casting Soling Executed

    7 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Earth Excavation

    8 RCC pipe Concrete pouring Concrete pouring in progress

    9 Shore Pile Shutter making & Rebar fabrication

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,2nd June, 2011

  • 8/13/2019 Daily Program June-2011

    2/23

    Project Manager

    S.l. No. Description Work Program of 7th June, 2011 Achievement of 6th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Culvert (road) Shuttering of 2nd lift Rebar fabrication in 2nd lift

    6 Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Shuttering Executed

    7 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Earth Excavation Earth Excavation in progress

    8 RCC pipe Concrete pouring Concrete pouring in progress

    9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,7th June, 2011

  • 8/13/2019 Daily Program June-2011

    3/23

    S.l. No. Description Work Program of 8th June, 2011 Achievement of 7th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Shuttering Executed

    6 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Earth Excavation Earth Excavation in progress

    7 RCC pipe Concrete pouring Concrete pouring in progress

    8 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    9 Interlocking Block ILB plant shift ILB plant shift in progress

    10 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program,8th June, 2011

  • 8/13/2019 Daily Program June-2011

    4/23

    S.l. No. Description Work Program of 11th June, 2011 Achievement of 10th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Shuttering Executed

    6 Culvert (Roadl) Wall 2nd lift Concrete pouring of wall 2nd lift

    7 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Earth Excavation Earth Excavation in progress

    8 RCC pipe Concrete pouring Concrete pouring in progress

    9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progres

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 11th June, 2011

  • 8/13/2019 Daily Program June-2011

    5/23

    S.l. No. Description Work Program of 12th June, 2011 Achievement of 11th June, 2011 Remark

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) 300mm Sand Blanket filling 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Shuttering Executed

    6 Culvert (Roadl) Wall 2nd lift Concrete pouring of wall 2nd lift

    7 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Earth Excavation Earth Excavation in progress

    8 RCC pipe Concrete pouring Concrete pouring in progress

    9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 12th June, 2011

  • 8/13/2019 Daily Program June-2011

    6/23

    S.l. No. Description Work Program of 13th June, 2011 Achievement of 12th June, 2011 Remarks

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) 300mm Sand Blanket filling finished 300mm Sand Blanket filling in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Open Deep Drain (CH 520-535) Shuttering of 2nd lift Concrete pouring of wall 1st lift

    6 Culvert (Roadl) Top slab shuttering Concrete pouring of wall 2nd lift

    7 Culvert (rail) Rebar fabrication Rebar fabrication in progress

    Base C.C casting Earth Excavation finished

    8 RCC pipe - Concrete pouring in progress

    9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantl ing work at Segment 3 & 4 in progress

    (Engr.Nityananda Nandi)

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 13th June, 2011

  • 8/13/2019 Daily Program June-2011

    7/23

    S.l. No.Description Work Program of 16th June, 2011 Achievement of 15th June, 2011 Rem

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) PVD Driving 300mm Sand Blanket filling is finished

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress

    7 Culvert (rail) Rebar binding of Base Rebar binding of Base in progress

    9 Shore Pile Shutter making & Rebar fabrication Shutter making & Rebar fabrication in progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 & 4 CC/RCC Dismantling work at Segment 3 & 4 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 16th June, 2011

  • 8/13/2019 Daily Program June-2011

    8/23

    S.l. No Description Work Program of 21th June, 2011 Achievement of 20th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) PVD Driving PVD Driving in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress

    5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress

    7 Culvert (rail) Shuttering & Rebar binding of Base Rebar binding of Base in progress

    9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 21th June, 2011

  • 8/13/2019 Daily Program June-2011

    9/23

    S.l. No Description Work Program of 22th June, 2011 Achievement of 21th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog

    Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 2A (part) PVD Driving PVD Driving in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress

    5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    6 Culvert (Roadl) Top slab shuttering & rebar binding Top slab shuttering & rebar binding in progress

    7 Culvert (rail) Shuttering & Rebar binding of Base Rebar binding of Base in progress

    9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 22th June, 2011

  • 8/13/2019 Daily Program June-2011

    10/23

    S.l. No Description Work Program of 23th June, 2011 Achievement of 22th June, 2011

    1 Segment 1A Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in prog

    Regular Settlement Record of Preloading Settlement Record in progress

    3 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    4 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress

    5 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    6 Culvert (Roadl) Concrete pouring of top slab Top slab shuttering & rebar binding finished

    7 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed

    9 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress

    10 Interlocking Block ILB plant shift ILB plant shift in progress

    11 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 23th June, 2011

  • 8/13/2019 Daily Program June-2011

    11/23

  • 8/13/2019 Daily Program June-2011

    12/23

    S.l. No Description Work Program of 25th June, 2011 Achievement of 24th June, 2011

    1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    3 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress

    4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    5 Culvert (Roadl) Concrete pouring of slab executed

    6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed

    7 Shore Pile Shuttering & Rebar fabrication Concrete Pouring in Progress

    8 Interlocking Block ILB plant shift ILB plant shift in progress

    9 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 25th June, 2011

  • 8/13/2019 Daily Program June-2011

    13/23

  • 8/13/2019 Daily Program June-2011

    14/23

    S.l. No Description Work Program of 26th June, 2011 Achievement of 25th June, 2011

    1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    3 Segment 4 (part) Levelling & Dressing Levelling & Dressing in progress

    4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    5 Culvert (Roadl) Concrete pouring of slab executed

    6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed

    7 Shore Pile Concrete Pouring Concrete Pouring in Progress

    8 Inter locking Block ILB plant shift ILB plant shift in progress

    9 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 26th June, 2011

  • 8/13/2019 Daily Program June-2011

    15/23

  • 8/13/2019 Daily Program June-2011

    16/23

    S.l. No.Description Work Program of 28th June, 2011 Achievement of 27th June, 2011 Rem

    1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    3 Segment 4 (part) Sub-Grade Preparation Levelling & Dressing in progress

    4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    5 Culvert (Roadl) Concrete pouring of slab executed

    6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed

    7 Shore Pile Concrete Pouring Concrete Pouring in Progress

    8 Interlocking Block ILB plant shift ILB plant shift in progress

    9 Road Work Layout fixing of Road Type-1

    10 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 28th June, 2011

  • 8/13/2019 Daily Program June-2011

    17/23

  • 8/13/2019 Daily Program June-2011

    18/23

  • 8/13/2019 Daily Program June-2011

    19/23

  • 8/13/2019 Daily Program June-2011

    20/23

    S.l. No.Description Work Program of 29th June, 2011 Achievement of 28th June, 2011 Rem

    1 Segment 1A Regular Settlement Record of Preloading Settlement Record in progress

    2 Segment 1 (part) Clearing & Grubbing. Clearing & Grubbing in progress.

    3 Segment 4 (part) Sub-Grade Preparation Sub-Grade preparation in progress

    4 Open Deep Drain (CH 520-535) Soling & CC work Earth Excavation is finished

    5 Culvert (Roadl) Concrete pouring of slab executed

    6 Culvert (rail) Shuttering & Rebar binding of wall Concrete Pouring of Base executed

    7 Shore Pile Concrete Pouring Concrete Pouring in Progress

    8 Interlocking Block ILB plant shift ILB plant shift in progress

    9 Road Work Layout fixing of Road Type-1

    10 Dismantling work CC/RCC Dismantling work at Segment 3 CC/RCC Dismantling work at Segment 3 in progress

    Project Manager

    NCT Back-up Project

    Project Builders Ltd

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program, 29th June, 2011