Hope all of you had a good weekend
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
A new part time student , Patrick Brejza has joined the Tridium team – CVA/CCI please ensure he joins our Linkedin group
Drinks after work!!! Next scheduled for 27/1/17- keep the afternoon free and may as many of you join this social event
Welcome back to all from their Holidays and welcome back to the
Fenech’s who will be back tomorrow 9/1/2017
Some Points Before Starting
Unfortunately I have to advise that Shawn Agius will be resigning and is
presently on notice... We wish Shawn luck in his next job and thank him for
the 5 years of service given to ESI
Projects and Deadlines
16_051_Baxter_AHU
We have nearly put this project to sleep!
We have performed well and I feel overall it was a success
Some snags pending – the remote access of the system and installation and commissioning of the valve actuator
16_041_RSM_Security
We need to complete all works by End of January 2017- All materials have been ordered and we have started Panel building.
Installation on site need to be commenced
Next would be programming , Testing and commissioning
16_025_DeLaRue_OFX
Design will be ready this week , materials have been delivered and training by overseas specialists will be on 18 and 19/1/17
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy
Q021_TF4- Panel is on site and installed- still issues to be resolved with regards to the FOC terminations
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
By the Jan 2017 we should do the change over for the roof panels with the programmed logic and some basic graphics only
Projects and Deadlines
16_023_GGY
we have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... This week we should have more light shed on a completion date
16_015_RSM_Lighting
this lighting control project is to be completed soon
As soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program
15_023_FM panels
We have a new 2 panels for FM environmental (D5M-110) ... The delivery date is not know – design is completed
16_058_Methode
Another fast tack project Jace Based AHU control system here – we will kick it off in this week – Target is to finish it by end of February 2017- we have started ordering the long lead items here – the plan is to start Panel design ASAP and start panel build on 3 or 4th week of Jan 2017.
Projects and Deadlines
12_043_LSP
We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here .. We will be going through the snags this week and listing them with a completion date
12_027- Parliament
We are finalizing the documentation and eventually need to integrate ProWatch.
15_038_new_HA_Ovt and 15_026_Apap
Residence
are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others- After 16/1
HMI will be installed next week
we also have to deliver the pool panel
Projects and Deadlines
14_081_Siggiewi School-
there are some snags pending here due to louvres
12_025
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
13_070- SCM Lagoona Plant room
We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
01 02 03 04
DesignFor the Past week we have been working on the following
Methode SMT – Started & Completed Points List, P&IDs, submitted P&IDsStarted Panel Design sketching
De la Rue – Completed 1st Typical Panel Drawing for CFH (we’ll split into different Drawings according to his site feedback)
RSM Security – met Stefan re: Intruder Panel
Design
Design
01 02 03 04
DesignAnd next week… we will work on
Methode SMT – Continue Panel Design sketching, start draughting.get quote for ancillaries after Panel Design sketching
Meridien – Site Visit with DSH re: Mech & Elec Additions Installations requiredchase Gas Line details from client
RSM Security – gather Intruder & DAC Panel Design from Stefan, draught accordingly
Design
This is what the Installation team have been working on last week
Installed DAC and BMS panels at Graham on levels 1, 2 and 3.
PPM (bolt tightening) at Sterling.
Dismantling at RSM
Installation on changing room at Baxter
Paint work on one panel at Lifesciences.
Installation
….. And this is what is planned for next week
Continue with works at Mosta workshop
RSM install security field devices
Intercontinental , fitting of new HMI
OVT install field devices
This is a sample text. Insert your desired text here.
Installation
• RSM security panels (DAC/Intruder)• 16_058_Methode- 3rd or 4th week of Jan 2017
Panel Build
Panel Build
Week 48
Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1
Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders
OthersParticipating in weekly fire drillsTackling software work orders New Angiography ProjectTraining of new team memberIntegration of Samoc into Master
Mater Dei Maintenance
Sterling Chemicals Line 2 PLC system
S5 PLC upgrade for Kordin Grain terminals
lighting control systems in Qatar.
And…. We may still have a chance to win a VERY large
BMS job
These are the quotes the business development
team have been working on
Business Development
\
LOADS OF BIRTHDAYS TO CELEBRATE
KAROLINAJURCZENIA TODAY 8TH JANPATRICK BREZJA 13TH JANDENNIS SMITH 15TH JAN
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
Some Last Thoughts
I remind you all .... I would like you take the opportunity and spend 15-30 minutes reflecting on 2016 and listing what went good for you on your job and what went bad... List your achievements and disappointments and set your major objectives for 2017!! I have done my exercise and published it .... Anyone wishing to share this exercise .. Please do so!!