© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 1 of 151

C HAPTER 18

Introduction to Systems Development and Systems

Analysis

Page 2: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 2 of 151

INTRODUCTION

• Questions to be addressed in this chapter include:– What are the phases in the systems development

life cycle?– Who are the individuals involved in systems

development?– What techniques are used to plan the development

of a system?– How do you determine whether a particular system

is feasible?– How do people respond to systems changes, and

how can dysfunctional behavior be minimized?

Page 3: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 3 of 151

INTRODUCTION

• As the environment, technology, and competition change, an information system must continually undergo changes

• These changes range from minor adjustments to major overhauls.

• Occasionally the old system is scrapped and replaced.

Page 4: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 4 of 151

INTRODUCTION

• Companies change their systems for a variety of reasons:– To respond to changes in user needs or business needs– To take advantage of or respond to technology changes– To accommodate improvements in their business

process– To gain a competitive advantage and/or lower costs– To increase productivity– To accommodate growth– To accommodate downsizing or distribute decision

making– To replace a system that is aged and unstable

Page 5: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 5 of 151

INTRODUCTION

• Developing quality, error-free software is difficult, expensive, and time-consuming.

• Projects tend to deliver less than expected and consume more time and money.

• A KPMG survey found that 35% of all major information systems projects were classified as runaways—hopelessly incomplete and over budget.– Major cause of runaways: Skimping on systems development

processes.

• Omitting basic systems development steps becomes tempting but may lead to disaster as developers create well-structured systems that fail to meet user needs or solve business problems.

Page 6: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 6 of 151

INTRODUCTION

• This chapter discusses five topics:– Systems development life cycle– Planning activities during the systems

development life cycle– Feasibility analysis– Behavioral aspects of change– Systems analysis

Page 7: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 7 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• Whether systems changes are major or minor, most companies go through a systems development life cycle.

• In this section, we discuss the steps in the cycle and the people involved.

Page 8: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 8 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 9: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 9 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 10: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 10 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• As organizations grow and change, they may need more or better information.

• Systems analysis is the first step. It includes:– Initial investigation

Involves gathering the information needed to buy or develop a new system and determining whether it is a priority.

Page 11: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 11 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• As organizations grow and change, they may need more or better information.

• Systems analysis is the first step. It includes:– Initial investigation– Systems survey

If the system is a priority, survey the existing system to define the nature and scope of the project and identify the strengths and weaknesses of the system.

Page 12: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 12 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• As organizations grow and change, they may need more or better information.

• Systems analysis is the first step. It includes:– Initial investigation– Systems survey– Feasibility study

Involves an in-depth study of the proposed system to determine whether it’s feasible.

Page 13: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 13 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• As organizations grow and change, they may need more or better information.

• Systems analysis is the first step. It includes:– Initial investigation– Systems survey– Feasibility study– Determination of information needs and system

requirements Involves finding out and documenting what

users and management need. This is the most important aspect of

systems analysis.

Page 14: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 14 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• As organizations grow and change, they may need more or better information.

• Systems analysis is the first step. It includes:– Initial investigation– Systems survey– Feasibility study– Determination of information needs and system

requirements– Delivery of systems requirements

Involves preparation of a report summarizing the systems analysis work.

This report is submitted to the information systems steering committee.

Page 15: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 15 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 16: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 16 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• In the conceptual design phase, the company decides how to meet user needs.

• Tasks in this phase include:– Identify and evaluate design alternatives

Possibilities include: Buying software Developing in-house Outsourcing

Page 17: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 17 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• In the conceptual design phase, the company decides how to meet user needs.

• Tasks in this phase include:– Identify and evaluate design alternatives– Develop design specifications

Involves writing up details of what the system is to accomplish and how it is to be controlled and developed.

Page 18: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 18 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• In the conceptual design phase, the company decides how to meet user needs.

• Tasks in this phase include:– Identify and evaluate design alternatives– Develop design specifications– Deliver conceptual design requirements

These requirements will be forwarded to the information systems steering committee.

Page 19: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 19 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 20: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 20 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• In the physical design phase, the broad, user-oriented requirements of the conceptual design are translated into detailed specifications that can be used by programmers to code the programs.

• Tasks include:– Design outputs, database, and inputs– Develop programs– Develop procedures– Design controls– Deliver developed system

• Goes to information systems steering committee

Page 21: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 21 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 22: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 22 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• This is the capstone phase during which everything comes together.

• Tasks include:– Develop an implementation and conversion plan

• Needed because of the complexity and importance of this phase

– Install any new hardware and software– Train personnel

• New employees may need to be hired and trained or existing employees relocated.

– Test the system and make any needed modifications.– Complete the documentation.– Convert from the old to the new system.– Deliver operational system.

• Send the final report to the IS steering committee.

Page 23: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 23 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• The five stages in the systems development life cycle are:– Systems analysis– Conceptual Design– Physical Design– Implementation and Conversion– Operation and Maintenance

Page 24: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 24 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• Once the system is up and running, operations and monitoring continue.

• Tasks include:– Fine-tune and do post-implementation review.– Operate the system.– Periodically review and modify the system.– Do ongoing maintenance.– Deliver improved system.

Page 25: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 25 of 151

SYSTEMS DEVELOPMENT LIFE CYCLE

• Eventually a major modification or system replacement is necessary, and the systems development life cycle (SDLC) will start over.

• In addition to the preceding five phases, three activities are performed throughout the life cycle:– Planning– Managing behavioral reactions to change– Assessing ongoing feasibility

• These three activities will be discussed in this chapter.

Additionally, the first phase in the SDLC, systems analysis, will be discussed in more detail.

Page 26: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 26 of 151

THE PLAYERS

Many people are involved in developing and successfully implementing an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 27: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 27 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 28: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 28 of 151

THE PLAYERS

• Top management’s role in systems development is to:– Provide support and encouragement and a clear

signal that user involvement is important.– Help align the systems with corporate strategies.– Establish system goals and objectives.– Review IS department performance and leadership.– Establish policies for project selection and

organizational structure.– Participate in important systems decisions.

Page 29: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 29 of 151

THE PLAYERS

• User management needs to:– Determine information requirements for departmental

projects.– Assist systems analysts with project cost-benefit

estimates.– Assign key staff members to development projects.– Allocate funds.

Page 30: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 30 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 31: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 31 of 151

THE PLAYERS

• Accountants also play an important role in systems development:– As AIS users, they must determine their information needs

and systems requirements and communicate them to system developers.

– As members of project development teams or steering committees, they help management in the development process.

– They are also active in:• Designing system controls and monitoring and testing these

controls.• Ensuring the system is easy to audit.

– Controls and “auditability” need to be built in early to minimize costs and inefficiencies later.

Page 32: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 32 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 33: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 33 of 151

THE PLAYERS

• The information systems steering committee is an executive-level committee whose duty is to plan and oversee the IS function.– Consists of high level management, such as:

• Controller• IS Manager• User department managers

– Sets policies to govern the AIS and assure top-management participation, guidance, and control.

– Attempts to encourage goal congruence and reduce goal conflict.

Page 34: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 34 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 35: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 35 of 151

THE PLAYERS

• The project development team includes systems specialists, managers, accountants, auditors, and users whose responsibility is to guide development

• Their job:– Plan each project.– Monitor to ensure timely and cost-effective completion.– Ensure the human element is considered.– Communicate project status to top management and steering

committee.– Communicate and meet with users to:

• Consider ideas• Discuss progress• Eliminate surprises

– The team approach produces more effective results and better user acceptance.

Page 36: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 36 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 37: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 37 of 151

THE PLAYERS

• Systems analysts study existing systems, design new ones, and prepare specifications that are used by programmers.– They interact with technical personnel and

users to bridge the gap.– They are responsible for ensuring the system

meets user needs.

Page 38: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 38 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 39: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 39 of 151

THE PLAYERS

• Computer programmers write the computer programs, using the specs developed by the systems analysts.

• They also modify and maintaining existing programs.

Page 40: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 40 of 151

THE PLAYERS

Many people are involved in developing and successfully implement an AIS, including: Top management Accountants The information systems steering committee The project development team Systems analysts Computer programmers External players

Page 41: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 41 of 151

THE PLAYERS

• External players include:– Customers– Vendors– Auditors– Governmental entities

• Their needs must also be met in systems development.

Page 42: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 42 of 151

PLANNING SYSTEMS DEVELOPMENT

• Several activities must be performed at various times throughout the SDLC.

• One of these activities is planning.• The organization should have plans for:

– The long range– Each systems development project– Each phase of each systems development project

• We’ll discuss these plans and a number of techniques to develop them.

Page 43: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 43 of 151

PLANNING SYSTEMS DEVELOPMENT

• We’ve all experienced the disasters that occur when we fail to plan.

• Suppose you bought a personal computer on impulse without thinking about what you wanted to do with it.

• When you got it home, you realized it wasn’t compatible with your existing printer and scanner.

• Furthermore, it wasn’t equipped for broadband internet access and you had been hoping to switch to broadband.

• By the time you spend the money and buy the parts to equip the computer to do what you want it to do, you find that you could have bought a leading-edge computer for less money.

Page 44: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 44 of 151

PLANNING SYSTEMS DEVELOPMENT

• Systems development planning is an important step for the following key reasons:– Consistency with the organization’s strategic plan.– Efficiency achieved through coordination of the

subsystems.– Cutting edge technology and techniques.– Lower costs due to lack of duplication, wasted effort,

time overruns, and cost overruns.– Adaptability for future changes.

Page 45: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 45 of 151

PLANNING SYSTEMS DEVELOPMENT

When a system is poorly planned, a company must often return to a prior phase and correct errors and design flaws.

These returns are costly and result in delays, frustration, and low morale.

Page 46: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 46 of 151

PLANNING SYSTEMS DEVELOPMENT

Two types of systems development plans are needed:- Individual project plans developed by the

project teams.- A master plan developed by the IS steering

committee.

Page 47: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 47 of 151

PLANNING SYSTEMS DEVELOPMENT

Two types of systems development plans are needed:- Individual project plans developed by the

project teams.- A master plan developed by the IS steering

committee.

Page 48: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 48 of 151

PLANNING SYSTEMS DEVELOPMENT

• Individual project plans contain:– A cost-benefit analysis.– Developmental and operational requirements,

including:• Human resources• Hardware• Software• Financial resources

– A schedule of activities to develop and operate the new application

Page 49: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 49 of 151

PLANNING SYSTEMS DEVELOPMENT

Two types of systems development plans are needed:- Individual project plans developed by the

project teams.- A master plan developed by the IS steering

committee.

Page 50: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 50 of 151

PLANNING SYSTEMS DEVELOPMENT

• A master plan specifies:– What the system will consist of– How it will be developed– Who will develop it– How needed resources will be acquired– Where the AIS is headed

• It also provides:– Status of projects in process– Prioritization of planned projects and criteria for

establishing priorities– Timetables for development

Page 51: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 51 of 151

PLANNING SYSTEMS DEVELOPMENT

• Projects with highest priority are first to be developed.– These decisions are made by top management.

• Planning horizon:– About a 3-year horizon– With updates at least 2-3 times/year—even more

frequently in some companies.

• The CIO should determine:– How soon technologies will be in wide use– Whether the company should adopt late or early– What business opportunities might arise from new

technologies

Page 52: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 52 of 151

PLANNING SYSTEMS DEVELOPMENT

• Planning Techniques– Two techniques for scheduling and

monitoring systems development activities are:• Program Evaluation and Review Technique

(PERT)• Gantt Charts

Page 53: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 53 of 151

PLANNING SYSTEMS DEVELOPMENT

• Planning Techniques– Two techniques for scheduling and

monitor systems development activities are:• Program Evaluation and Review

Technique (PERT)• Gantt Charts

Page 54: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 54 of 151

PLANNING SYSTEMS DEVELOPMENT

• A PERT diagram requires that all activities in a project be identified along with the activities that precede and follow them.

• These activities are used to draw a PERT diagram, which consists of a network of:– Arrows—representing activities that require

time and resources.– Nodes—representing completion and initiation

of activities.

Page 55: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 55 of 151

PLANNING SYSTEMS DEVELOPMENT

• The critical path in a PERT diagram is the path requiring the greatest amount of time.

• If an activity on the critical path is delayed, the whole project is delayed.

• Resources may be shifted to the critical path to reduce the delay.

Page 56: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 56 of 151

DesignBirdhouse

(2)(Bill)

Buy Wood& Nails

(1)(Bill)

BuyPaint

(1)(Sara)

BuildBase

(2)(Bill)

BuildRoof(1)

(Bill)

NailTogether

(2)(Bill)

Paint &Decorate

(3)(Sara)

Sell(2)

(Sara)

• SAMPLE PERT CHART– For building and selling a birdhouse.– Each block contains a task and a time estimate (may

include best time, worst time, and average time)– May indicate who will be responsible for the task.

Page 57: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 57 of 151

PLANNING SYSTEMS DEVELOPMENT

• Planning Techniques– Two techniques for scheduling and

monitor systems development activities are:• Program Evaluation and Review Technique

(PERT)• Gantt Charts

Page 58: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 58 of 151

PLANNING SYSTEMS DEVELOPMENT

• A Gantt chart is a bar chart with project activities on the left and time across the top.

• For each activity, a bar of expected time is drawn.

• As activities are completed, the bar is filled in.• The Gantt chart makes it easy to eyeball the

chart and understand the current status of a project.

• But the chart does not show the relationship between activities like the PERT chart does.

Page 59: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 59 of 151

SAMPLE GANTT CHART

1 2 3 4 5 6 7 8 9 10Design birdhouseBuy wood & nailsBuy paintBuild roofBuild baseNail togetherPaint & decorateSell

Period

Complete

Testing

In Development

Milestone

Page 60: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 60 of 151

FEASIBILITY ANALYSIS

• During the systems analysis phase, a feasibility study (aka, a business case) is prepared and is updated during the remaining steps in the SDLC.

• The extent of the feasibility study depends on the size and nature of the system.

• Feasibility team should include:– Management– Accountants skilled in controls and auditing– Systems personnel– Users

Page 61: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 61 of 151

FEASIBILITY ANALYSIS

• The feasibility study and its updates are used by the steering committee as the project proceeds to decide whether to:– Terminate the project– Proceed– Proceed if specific problems are resolved

Page 62: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 62 of 151

FEASIBILITY ANALYSIS

• Five aspects need to be considered during a feasibility study:– Technical feasibility

• Is the technology there to do it?

– Operational feasibility• Do we have people who can do it, and will it get used?

– Legal feasibility• Does it comply with legal, regulatory, and contractual

obligations?

– Scheduling feasibility• Can it be done in time?

– Economic feasibility• Will the benefits exceed the costs?

Page 63: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 63 of 151

FEASIBILITY ANALYSIS

• Calculating Economic Feasibility Costs and Benefits– Economic feasibility is probably the most important

and frequently analyzed aspect.– This examination requires a careful investigation of

costs and benefits.– It typically uses a capital budgeting model that

considers:• Cost savings and other benefits• Initial outlay costs• Operating costs• Other costs

Page 64: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 64 of 151

FEASIBILITY ANALYSIS

• When possible, benefits and costs should be estimated and included even if they are not easily quantifiable.

• If some costs and benefits cannot be accurately estimated, they should at least be listed, along with the likelihood of their occurrence and their expected impact.

Page 65: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 65 of 151

FEASIBILITY ANALYSIS

• Benefits might include:– Cost savings.– Improved customer service, productivity,

decision making, or data processing.– Better management control.– Increased job satisfaction and employee

morale.

Page 66: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 66 of 151

FEASIBILITY ANALYSIS

• Costs might include:– Equipment costs

• Initial outlay plus ongoing operating costs

– Software costs• Costs of acquiring, maintaining, supporting, and operating

– Human resource costs• Salaries, as well as costs of hiring, training, and relocating staff

– Site preparation costs– Installation and conversion costs– Supplies– Overhead– Financial charges

• The primary operating cost is maintaining the system.• Makes up 65-75% of the organization’s system efforts

Page 67: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 67 of 151

FEASIBILITY ANALYSIS

• Capital Budgeting– Most organizations use a capital budgeting

return on investment technique to evaluate the economic merits of different system alternatives.

– There are three commonly used techniques• Payback period

• Calculates the number of years before the new savings from the project equal the initial cost of the investment.

• Select projects with shorter payback periods.

Page 68: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 68 of 151

FEASIBILITY ANALYSIS

• Capital Budgeting– Most organizations use a capital budgeting

return on investment technique to evaluate the economic merits of different system alternatives.

– There are three commonly used techniques• Payback period• Net present value (NPV)

• Calculates and sums the discounted future cash flows of the costs and benefits.

• Select projects with higher positive NPV.

Page 69: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 69 of 151

FEASIBILITY ANALYSIS

• Capital Budgeting– Most organizations use a capital budgeting

return on investment technique to evaluate the economic merits of different system alternatives.

– There are three commonly used techniques• Payback period• Net present value (NPV)• Internal rate of return (IRR)

• Calculates the effective interest rate that would result in a net present value of zero for the project.

• Select projects with higher IRRs.

Page 70: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 70 of 151

BEHAVIORAL ASPECTS OF CHANGE

• The best system will fail without the support of the people it serves.

• So the behavioral aspects of change are crucial.

• You need to be aware of and sensitive to the types of behavioral problems that can result from change.

Page 71: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 71 of 151

BEHAVIORAL ASPECTS OF CHANGE

• Why Behavioral Problems Occur– Employees will tend to view change as good if

they believe it will affect them positively and vice versa.

Page 72: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 72 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background

• Employees are more likely to accept change if they are:– Young;

– Highly educated; or

– Comfortable with technology.

Page 73: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 73 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced

• The rationale used to sell the system may need to vary with the job responsibilities of the employees involved.

Page 74: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 74 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes

• Fool me once, shame on me . . .• Let’s see if I even give you a

second chance.

Page 75: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 75 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes– Top management support

Page 76: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 76 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes– Top management support– Communication

Page 77: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 77 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes– Top management support– Communication– Biases and natural resistance to change

• Employees may be too emotionally attached to their duties, i.e., “sacred cows.”

Page 78: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 78 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes– Top management support– Communication– Biases and natural resistance to change– Disruptive nature of the change process

• Disturbances often create negative feelings.

Page 79: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 79 of 151

BEHAVIORAL ASPECTS OF CHANGE

• To minimize adverse behavioral reactions, it helps to understand why resistance occurs:– Personal characteristics and background– Manner in which change is introduced– Experience with prior changes– Top management support– Communication– Biases and natural resistance to change– Disruptive nature of the change process– Fear

• May include fear of:– The unknown– Failure– Technology– Losing respect or status– Losing their jobs

Page 80: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 80 of 151

BEHAVIORAL ASPECTS OF CHANGE

• How People Resist AIS Changes– Resistance to change often takes one of

three forms:• Aggression

• Behavior intended to destroy, cripple, or weaken the system’s effectiveness.

• Examples: Increased error rates, disruptions, or deliberate sabotage.

Page 81: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 81 of 151

BEHAVIORAL ASPECTS OF CHANGE

• How People Resist AIS Changes– Resistance to change often takes one of

three forms:• Aggression• Projection• Blaming the new system for any and every unpleasant

occurrence, i.e., the system becomes a scapegoat.• To preserve the integrity of the system, these

criticisms must be controlled or answered.

Page 82: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 82 of 151

BEHAVIORAL ASPECTS OF CHANGE

• How People Resist AIS Changes– Resistance to change often takes one of

three forms:• Aggression• Projection• Avoidance

• “If I don’t use this thing, maybe it will go away!”

Page 83: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 83 of 151

FEASIBILITY ANALYSIS

• Reactions to change can be improved by observing the following guidelines:– Meet user’s needs with respect to the form,

content, and volume of system output.– Keep communication lines open. Managers

and users should be fully informed about:• What changes are being made• Why• How it will benefit them• Who to contact with questions

Page 84: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 84 of 151

FEASIBILITY ANALYSIS

– Maintain a safe and open atmosphere.• If employees become hostile, it’s an uphill battle

you probably won’t win.

– Obtain management support.– Allay fears.

• To the extent possible, reassure employees that no major job losses or responsibility shifts will occur.

• If employees are terminated, severance pay and outplacement services should be provided.

Page 85: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 85 of 151

FEASIBILITY ANALYSIS

– Solicit user participation.• It is ego enhancing, challenging, and intrinsically

satisfying.• Users who participate will be more committed to

using the system.

– Provide honest feedback.• Explain which suggestions are and are not being

used and why.

– Make sure users understand the system.• Don’t underestimate training needs.

Page 86: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 86 of 151

FEASIBILITY ANALYSIS

– Humanize the system.• Employees shouldn’t feel the computer is

controlling them or has usurped their positions.

– Describe new challenges and opportunities.• The system can provide greater job satisfaction

and increased opportunities.

– Reexamine performance evaluation.• Are performance standards and criteria realistic in

light of the change?

– Test the system’s integrity.• It’ important to minimize bad impressions

Page 87: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 87 of 151

FEASIBILITY ANALYSIS

– Avoid emotionalism.• Emotional issues should be allowed to cool, handled in

a non-confrontational manner, or sidestepped.

– Present the system in the proper context.• Address the concerns of the people to whom you’re

speaking, not the concerns of management or developers.

– Control the user’s expectations• Don’t oversell, and be realistic.

– Keep the system simple• Avoid complex systems that cause radical changes.

Page 88: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 88 of 151

FEASIBILITY ANALYSIS

Ignoring the preceding steps can leave to behavior issues that are difficult or impossible to reverse.

Page 89: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 89 of 151

SYSTEMS ANALYSIS

• When a new or improved system is needed, a written request for systems development is prepared. That request describes:– The current system’s problems– The reasons for the proposed changes– The goals and objectives of a proposed

system– The anticipated benefits and costs

Page 90: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 90 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps:– Initial investigation– Systems survey– Feasibility study– Information needs and systems requirements– Systems analysis report

Page 91: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 91 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps– Initial investigation– Systems survey– Feasibility study– Information needs and systems requirements– Systems analysis report

Page 92: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 92 of 151

SYSTEMS ANALYSIS

• The initial investigation is conducted to:– Gain a clear picture of the problem or

need.• Sometimes what is thought to be the cause of the

problem is not the real source.

Page 93: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 93 of 151

SYSTEMS ANALYSIS

• The initial investigation is conducted to:– Gain a clear picture of the problem or need.– Determine the viability of the project and

expected costs and payoffs.

Page 94: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 94 of 151

SYSTEMS ANALYSIS

• The initial investigation is conducted to:– Gain a clear picture of the problem or need.– Determine the viability of the project and

expected costs and payoffs.– Evaluate the scope and nature of the new

AIS.

• A new AIS is useful when problems are a result of:– Lack of information

– Inaccessibility of data

– Inefficient data processing

• A new AIS will not answer problems such as:– A manager who has too many subordinates

– A manager who lacks organizational skills

– Failure to enforce existing problems

Page 95: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 95 of 151

SYSTEMS ANALYSIS

• The initial investigation is conducted to:– Gain a clear picture of the problem or need.– Determine the viability of the project and

expected costs and payoffs.– Evaluate the scope and nature of the new

AIS.– Recommend whether to proceed.

• Either:– Initiate the project as proposed.

– Modify it.

– Abandon it.

Page 96: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 96 of 151

SYSTEMS ANALYSIS

• If the project is approved:– A proposal to conduct systems analysis is

prepared.– The project is assigned a priority and added

to the master plan.– The development team begins a survey of the

existing AIS.– The proposal will be modified as more

information becomes available.

Page 97: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 97 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps– Initial investigation– Systems survey– Feasibility study– Information needs and systems requirements– Systems analysis report

Page 98: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 98 of 151

SYSTEMS ANALYSIS

• A systems survey involves an extensive study of the current AIS which could take weeks or months. Objectives are:– Gain a thorough understanding of:

• Company operations, policies, and procedures• Data and information flow• AIS strengths and weaknesses• Available hardware, software, and personnel

– Make preliminary assessments of current and future processing needs, and determine extent and nature of needed changes.

– Develop working relationships with users and build support.– Collect data that identify user needs, conduct a feasibility

analysis, and make recommendations to management.

Page 99: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 99 of 151

SYSTEMS ANALYSIS

• Data can be gathered from:– Employees.– Documentation such as organization charts

and procedure manuals.– External sources such as:

• Consultants• Customers• Suppliers• Industry associations• Government agencies

Page 100: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 100 of 151

SYSTEMS ANALYSIS

• Four common methods of gathering data are:– Interviews– Questionnaires– Observation– System Documentation

Page 101: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 101 of 151

SYSTEMS ANALYSIS

• Four common methods of gathering data are:– Interviews– Questionnaires– Observation– System Documentation

Page 102: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 102 of 151

SYSTEMS ANALYSIS

• Advantages of interviews:– Can answer “why” questions– Can allow for follow-up and clarification– Provides opportunity to build positive relationships

with interviewees and support for new system

• Disadvantages of interviews:– Time-consuming– Expensive– Personal biases or self-interest may produce

inaccurate information

Page 103: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 103 of 151

SYSTEMS ANALYSIS

• When you do interviews:– Make an appointment.– Explain the purpose ahead of time.– Indicate the amount of time needed.– Be on time.– Be familiar with the interviewee’s responsibilities.– Make notes on points to cover.– Put the interviewee at ease and let him/her do the

talking.– Pay attention to nonverbal cues.– Take notes and augment them with impressions after

the interview.– Request permission to tape critical interviews.

Page 104: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 104 of 151

SYSTEMS ANALYSIS

• Four common methods of gathering data are:– Interviews– Questionnaires– Observation– System Documentation

Page 105: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 105 of 151

SYSTEMS ANALYSIS

• Questionnaires can be used when:– The amount of information to be gathered is

small and well defined.– The information is to be obtained from many

people or from those who are remotely located.

– The information is intended to verify data from other sources.

Page 106: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 106 of 151

SYSTEMS ANALYSIS

• Advantages of questionnaires:– Can be anonymous.– Not time-consuming to complete.– Inexpensive.– Allows the subject time to think about responses.

• Disadvantages of questionnaires:– Does not allow in-depth questions or answers.– Does not allow follow-up or clarification.– Does not build relationships.– Difficult to develop.– May be ignored or completed superficially.

Page 107: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 107 of 151

SYSTEMS ANALYSIS

• Four common methods of gathering data are:– Interviews– Questionnaires– Observation– System Documentation

Page 108: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 108 of 151

SYSTEMS ANALYSIS

• Advantages of observations:– Can verify how the system actually works

rather than how it should work.– Results in greater understanding of systems.

• Disadvantages of observations:– Time-consuming.– Expensive.– Difficult to interpret.– People may alter behavior while being

observed.

Page 109: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 109 of 151

SYSTEMS ANALYSIS

• When you do observations:– Identify what is to be observed and estimate

the time required.– Obtain permission.– Explain what will be done and why.– Don’t make value judgments.– Take notes and document impressions ASAP.

Page 110: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 110 of 151

SYSTEMS ANALYSIS

• Four common methods of gathering data are:– Interviews– Questionnaires– Observation– System Documentation

Page 111: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 111 of 151

SYSTEMS ANALYSIS

• Advantages of systems documentation:– Describes how the system should work.– Written form facilitates review and analysis.

• Disadvantages of systems documentation:– Time consuming.– May be elusive.

• When you examine systems documentation:– Keep in mind that the system doesn’t always work as

it should per the documentation.– If documentation is unavailable, it may be worthwhile

to develop it.

Page 112: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 112 of 151

SYSTEMS ANALYSIS

• Once the data is gathered, document findings and model the existing system.– Documentation consists of:

• Questionnaire copies• Interview notes• Memos

Page 113: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 113 of 151

SYSTEMS ANALYSIS

• Another form of documentation is a system model:– Physical models illustrate how a system

functions by describing:• Flow of documents.• Computer processes performed and the people

doing them.• Equipment used.• Any other physical elements.

– Logical models illustrate what is being done regardless of how the flow is accomplished.

Page 114: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 114 of 151

SYSTEMS ANALYSIS

• When documentation is complete, analyze the existing system:– Evaluate the AIS’s strengths and weaknesses

to develop ideas for designing and structuring the new AIS.

• Try to retain strengths.• Correct weaknesses.

– Sometimes, you need revolutionary, rather than evolutionary change.

• Called re-engineering.

Page 115: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 115 of 151

SYSTEMS ANALYSIS

• At the end of this phase, prepare systems survey report:– Outlines and documents the data gathered.– Provides recommendations that result from

the systems survey.

Page 116: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 116 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps– Initial investigation– Systems survey– Feasibility study– Information needs and systems requirements– Systems analysis report

Page 117: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 117 of 151

SYSTEMS ANALYSIS

• After the systems survey, a more thorough feasibility analysis is conducted.

• This analysis is updated regularly as the project proceeds and costs and benefits become clearer.

Page 118: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 118 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps– Initial investigation– Systems survey– Feasibility study– Information needs and systems

requirements– Systems analysis report

Page 119: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 119 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes

• Describes what is to be done and by whom.

Page 120: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 120 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements

• Describes name, size, format, source, and significance of necessary data elements.

Page 121: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 121 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure • A preliminary structure showing

how the data elements will be organized into logical records.

Page 122: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 122 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure- Outputs • Layouts of system outputs and

a description of their purpose, frequency, and distribution.

Page 123: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 123 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure- Outputs- Inputs • A copy of system inputs and a

description of their contents, source, and who is responsible for them.

Page 124: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 124 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure- Outputs- Inputs- Constraints

• A description of deadlines, schedules, security requirements, staffing limitations, and legal requirements.

Page 125: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 125 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure- Outputs- Inputs- Constraints- Controls • Controls that are needed to

ensure accuracy and reliability.

Page 126: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 126 of 151

SYSTEMS ANALYSIS

Once a project clears the feasibility hurdle, the company identifies the information needs of AIS users and documents systems processes, including:- Processes- Data elements- Data structure- Outputs- Inputs- Documentation constraints- Controls- Reorganizations

• Changes in staffing, job functions, etc., that would be necessary.

Page 127: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 127 of 151

SYSTEMS ANALYSIS

• Issues:– There is much to be specified, even for a

simple AIS.– It may be difficult to get employees to

accurately articulate their needs.– Errors are best caught early, as the cost to

correct them increases significantly the farther you are into the project.

Page 128: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 128 of 151

SYSTEMS ANALYSIS

• Systems Objectives and Constraints– Many entities take a systems approach to

determining information needs and systems requirements.

– Problems and alternatives are viewed from the standpoint of the entire organization—as opposed to a single department.

Page 129: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 129 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness

• Able to help users make decisions.

Page 130: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 130 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy

• Benefits exceed costs.

Page 131: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 131 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability

• Data is processed accurately and reliably.

Page 132: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 132 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability

• You can access it when you need it.

Page 133: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 133 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness

• More critical information is provided first.

Page 134: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 134 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

• Efficient and courteous.

Page 135: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 135 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity• Can handle peak periods.

Page 136: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 136 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity- Ease of use

Page 137: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 137 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity- Ease of use- Flexibility

• Can accommodate changes.

Page 138: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 138 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity- Ease of use- Flexibility- Tractability

• Easily understood.• Facilitates problem solving and

future development.

Page 139: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 139 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity- Ease of use- Flexibility- Tractability- Auditability

Page 140: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 140 of 151

SYSTEMS ANALYSIS

• Systems objectives must be identified, so analysts and users can focus on those elements most vital to success of the AIS. These may include:- Usefulness- Economy- Reliability- Availability- Timeliness- Customer service

- Capacity- Ease of use- Flexibility- Tractability- Auditability- Security • Available only to

authorized users.

Page 141: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 141 of 151

SYSTEMS ANALYSIS

• There are often trade-offs between objectives.• Organizational constraints make it impossible to

develop all parts of an AIS simultaneously.– You divide it into modules that are analyzed,

developed, and installed independently.– When changes are made, only the affected modules

need to be changed.– The modules should be properly integrated into a

workable system.

Page 142: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 142 of 151

SYSTEMS ANALYSIS

• Success often depends on the project team’s ability to cope with organizational constraints, including:– Requirements of governmental agencies.– Managerial policies and guidelines.– Lack of sufficient, qualified staff.– Capabilities and attitudes of users.– Available technology.– Limited financial resources.

Page 143: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 143 of 151

SYSTEMS ANALYSIS

• Strategies for Determining Requirements:– One or more of the following four strategies

are used to determine AIS requirements:• Ask users what they need

• This is the simplest and fastest strategy.• But many people don’t realize or understand their true

needs.• It’s sometimes better to ask them what decisions they

make and what processes they are involved in.• Users also need to think beyond their current

information needs.

Page 144: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 144 of 151

SYSTEMS ANALYSIS

• Strategies for Determining Requirements:– One or more of the following four strategies

are used to determine AIS requirements:• Ask users what they need• Analyze existing systems

Internal and external systems should be analyzed to avoid reinventing the wheel.

Page 145: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 145 of 151

SYSTEMS ANALYSIS

• Strategies for Determining Requirements:– One or more of the following four strategies

are used to determine AIS requirements:• Ask users what they need• Analyze existing systems• Examine existing system use

• Certain modules:– May not be used as intended

– May be augmented by manual tasks

– May be avoided altogether

• Helps determine whether the system really needs to be simply modified rather than replaced.

Page 146: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 146 of 151

SYSTEMS ANALYSIS

• Strategies for Determining Requirements:– One or more of the following four strategies

are used to determine AIS requirements:• Ask users what they need• Analyze existing systems• Examine existing system use• Create a prototype

• Entails roughing out a system for users to critique.• When they see something on a screen, it’s easier to

identify what they like and don’t like.• Goes through iterations of improving and reviewing

with users until users agree on their needs.

Page 147: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 147 of 151

SYSTEMS ANALYSIS

• Documentation and Approval of User Requirements:– Detailed requirements for the new AIS should

be created and documented.• How to produce the required features is

determined during the design phases of the SDLC.• The requirements list should be supported by

sample input and output forms and charts that make it easier to conceptualize.

• A nontechnical summary is often prepared for management.

Page 148: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 148 of 151

SYSTEMS ANALYSIS

• Once user requirements have been determined and documented, the project team:– Meets with users.– Explains the requirements.– Obtains their agreement and approval.

• When an agreement is reached, user management should sign off on the requirements.

Page 149: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 149 of 151

SYSTEMS ANALYSIS

• The project development team will conduct the systems analysis in five steps– Initial investigation– Systems survey– Feasibility study– Information needs and systems requirements– Systems analysis report

Page 150: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 150 of 151

SYSTEMS ANALYSIS

• The last step in systems analysis is the systems analysis report.– Summarizes and documents the activities.– Serves as a repository of data from which designers

can draw.– Outlines:

• Goals and objectives of the new system.• Scope of the project.• How the new system fits into the company’s master plan.• User processing requirements and information needs.• Feasibility analysis.• Recommendations for the new system.

Page 151: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 151 of 151

SYSTEMS ANALYSIS

• A go-no-go decision is usually made three times during systems analysis:– During the initial investigation to determine

whether to go ahead with a systems survey.– At the end of the feasibility study to determine

whether to proceed with the information requirements step.

– At the completion of the analysis phase to decide whether to proceed to the next phase (conceptual design).

Page 152: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 152 of 151

SYSTEMS ANALYSIS

• When systems analysis is completed, the project can move on to:– Conceptual design phase– Physical design phase– Implementation and conversion– Operation and maintenance

Page 153: Ais Romney 2006 Slides 18 Introduction To Systems Development

© 2006 Prentice Hall Business Publishing Accounting Information Systems, 10/e Romney/Steinbart 153 of 151

SUMMARY

• You’ve learned about the five phases in the systems development life cycle, with a particular emphasis on systems analysis.

• You’ve learned who the players are in the systems development process.

• You’ve learned about various techniques that are used to plan the development of a system.

• You’ve reviewed some techniques for determining system feasibility.

• You’ve learned about behavioral responses to systems changes and how dysfunctional behavior can be minimized.