Wind Energy in Poland – Potential, Prospects and Pitfalls
A presentation for the joint seminar by demosEuropa and the Danish Embassy in Warsaw by Kenneth Kolvits, Head of Vestas Poland
19 November 2008
2 | Presentation title, April 19, 2023
Agenda
1. Wind Potential in Poland
2. Installations, Share of Wind in Electricity Mix and Comparisons
3. What Hampers Poland in Exploiting its Potential?
3 | Presentation title, April 19, 2023
Wind Atlas Poland
Source: GreenMax, 2008
4 | Presentation title, April 19, 2023
Wind Potential/Prospects in Poland
• EER: 5-6 GW by 2020 (EER Country Analysis)
• PWEA: 13,5 GW by 2020 (PWEA Assessment of Wind Energy Development Opportunities)
• BTM: 3,4 GW by 2012 (World Market Update 2007)
”Due to excellent wind conditions (…), Poland is one of the most promising wind energy markets in Europe. The country possesses plenty of potentially profitable locations and great development possibilities”
(European Bank for Reconstruction and Development in 2004)
5 | Presentation title, April 19, 2023
Installed Wind Power Capacity in the EU (total end 2007 in MW)
Germany 22,247 MW
Spain 15,145 MW
Denmark 3,125 MW
Italy 2,726 MW
France 2,454 MW
UK 2,389 MW
Portugal 2,150 MW
Netherlands 1,746 MW
Austria 982 MW
Greece 871 MW
Ireland 805 MW
Sweden 788 MW
Norway 333 MW
Belgium 287 MW
Poland 276 MW
Source: GWEC, 2008
6 | Presentation title, April 19, 2023
Wind penetration per capita in 2007: Poland one of the lowest figures in the EU
7 | Presentation title, April 19, 2023
Share of Wind in Electricity Generation
8 | Presentation title, April 19, 2023
Despite Great Resources and International Requirements, Poland is Lagging Behind
• Indicative RES-E target: 7,5 % of electricity shall be met by renewable energy sources by 2010 (Directive 2001/77EC)
• Proposed mandatory RES-target of Draft European Directive of January 2008: 15 % of gross final energy consumption shall come from renewable energy
”Progress towards the RES-E target in Poland is low.”
(European Commission, DG Energy and Transport 2008)
9 | Presentation title, April 19, 2023
What Hampers Poland? 2 Main Barriers for Polish Wind Energy Development
1. Grid Infrastructure and Connection
A) Insufficient grid infrastructure in Northern Poland, where best resource is
According to PSE: 1,120 km of new HV lines and 5 new substations needed by 2020
B) Obtaining grid connection
- SOs have 3- to 5-year infrastructure development plans, but investment priorities often change (i.e. Need to repair existing line before building new one)
- Lack of coordination between different DSOs and TSO
- Connection conditions (CCs) are sometimes hard to meet, i.e. very high transmission fees
- In theory, CCs lapse after 2 years; in practice, not the case → capacity reserved on grid for projects that might not get built (many not viable projects hold CCs) blocking other projects: Thus, new projects stuck in connection queue
Source: EER, 2008; Green Max, 2008 and PSE, 2008
10 | Presentation title, April 19, 2023
What Hampers Poland? 2 Main Barriers for the Wind Energy Development
2. Complex process of development procedures
Time consuming and relative complex set of procedures for the projects to obtain zoning plan
Time consuming and complex procedure for environmental analysis in order to obtain the approval for wind energy
Few and/or insufficient resources and knowledge to ease the process
11 | Presentation title, April 19, 2023
To sum up:
• Poland has a huge resource and its overall regulatory framework makes it an attractive market
• However, barriers hamper wind energy development in Poland and should be removed as soon as possible
• When barriers removed, Poland expected to be able to exploit full potential and comply with international obligations
Vestas believes in the Polish market and remains strongly committed
vestas.com
Thank you for your attentionKenneth F. Kolvits, Head of Vestas Poland
Copyright NoticeThe documents are created by Vestas Wind Systems A/S and contain copyrighted material, trademarks, and other proprietary information. All rights reserved. No part of the documents may be reproduced or copied in any form or by any means—such as graphic, electronic, or mechanical, including photocopying, taping, or information storage and retrieval systems without the prior written permission of Vestas Wind Systems A/S. The use of these documents by you, or anyone else authorized by you, is prohibited unless specifically permitted by Vestas Wind Systems A/S. You may not alter or remove any trademark, copyright or other notice from the documents. The documents are provided “as is” and Vestas Wind Systems A/S shall not have any responsibility or liability whatsoever for the results of use of the documents by you.