Upload
buinguyet
View
218
Download
0
Embed Size (px)
Citation preview
UPGRADING OF WASTE-TO-ENERGY PLANT IN BRESCIA, ITALY
Client: ASM Brescia Financed by: The client Start: 2004-04 End: Ongoing Contact: Managing Director A. Bonomo, Via Lamarmora 230, IT-25124 Brescia, Italy Tel.: +39 030-35531
Rambøll is assisting the waste-to-energy plant of ASM Brescia in installing a new waste crane and establishing crane automation. ASM Brescia S.P.A. is a large public utilities company established more than 100 years ago. The company is responsible for the production of power and district heating, gas supply, waste collection, treatment and disposal, and wastewa-ter treatment. Brescia was one of the first cities to have a well-established district heating net-work. Today, the waste-to-energy plant supplies heat to approx. 65 per cent of Brescia’s inhabi-tants. In addition, ASM Brescia runs an adjacent power plant, a composting plant for source-separated household and garden waste and a sanitary landfill.
The management of the waste-to-energy plant became very interested in crane automation during one of Rambøll’s visits to the plant when Rambøll reported on the success of automated cranes at the two largest waste-to-energy plants in Denmark, I/S Amagerforbrænding and I/S Vestforbrænding. Rambøll’s experience from these two plants was a decisive factor when ASM Brescia requested our assistance. Rambøll has also assisted ASM Brescia in exam-ining the options for the management of bio-mass incinerated in a recently commissioned unit 3 dedicated specifically for that purpose.
NEW WASTE-TO-ENERGY UNIT IN AALBORG, DENMARK
Client: I/S Reno-Nord Financed by: The Client Start: 1999 End: Ongoing Referee: Dir. Henrik Skovhaug, I/S Reno-Nord, Troensevej 2, DK-9220 Aalborg Øst. Tel.: +45 98 15 65 66
Client’s Representative for I/S Reno-Nord during all stages of the planning and establishment of a new waste-to-energy plant with combined heat and power production (CHP) and a treatment capacity of about 160,000 tpa. RAMBØLL’s re-sponsibilities include, inter alia: • Application for planning approval • Conceptual design and layout of the plant • Detailed design of civil works • Preparation of tender documents for all M&E
plant and civil works
● Procurement management • Tender evaluation and contract negotiations • Project and contract management • Supervision during construction and com-
missioning In addition to the new furnace/boiler and tur-bine/generator units the new plant includes a wet flue gas cleaning system, which satisfies the new EU directive 2000/76/EC. The plant is scheduled for commercial operation in 2005.
REHABILITATION OF WASTE INCINERATION PLANT IN BUDAPEST, HUNGARY
Client: Municipality of Budapest Financed by: The Client Start: 2001 End: Ongoing Referee: Head of PIU Attila Pocs, Municipality of Budapest Tel. +36 1 317 63 10 Janos Banhidy, Municipal Public Services Tel. +36 1 307 6174
Rambøll is assisting the Municipality of Budapest in the upgrading and rehabilitation of the Buda-pest Waste-to-Energy Plant. Rambøll’s responsi-bilities include assistance in the tendering of a flue gas treatment system and rehabilitation of the existing four boilers as well as assistance in the tendering
of pre-treatment technology and facility for re-covery and disposal of solid flue gas treatment and incineration residues. After signature of the contract Rambøll provides expert assistance to the client in connection with commercial issues, check of scope of supply and review of technical solutions.
NEW WASTE-TO-ENERGY UNIT IN HALMSTAD, SWEDEN
Client: Halmstads Renhållnings AB Financed by: The Client Start: 1999-03 End: Ongoing Referee: Dir. Per-Olof Andersson, Halmstads Renhållnings AB, Box 8005, S-300 08 Halmstad, Sweden. Tel.: + 46 35 190 121
Rambøll is the Client’s Representative in connec-tion with machinery at the waste-to-energy plant in Halmstad, responsible for elaboration of decision-making basis for the extension by a new combined heat and power producing unit with a capacity of 15 t/h. In addition Rambøll is responsible for planning, conceptual design, elaboration of tender documents, tendering, tender evaluation and contracting of the entire machinery supply as well as co-ordination of the conceptual and detailed design of buildings and construction works. The new unit was commis-sioned at the beginning of 2003. In June 2000 the contract for the machinery supply was awarded to Babcock Borsig Power BBP (formerly Steinmüller) from Germany, while NCC in the autumn of 2000 was chosen as turn-key contractor for the entire building activities. The final layout was decided during the course of 2000, and all information necessary for the building activities was procured.
BBP has in co-operation with the Client selected all sub-suppliers, and the production has been going on all over Europe. The installation of ma-chinery started in mid-August 2001. In Septem-ber 2002 BBP went bankrupt and consequently could not complete the project. A contract was signed with FISIA Babcock Environment GmbH (FBE) for completion of the project. In April 2003 waste was incinerated in the new unit for the very first time, and in June 2003 power was supplied to the power network. Rambøll assisted the Client in connection with the bankruptcy of BBP. The plant is dimensioned in accordance with the latest EU environmental requirements. In some areas, including NOx, the guarantee require-ments at the new plant are stricter than future requirements. Rambøll is also assisting the Client in the up-grading of the two existing heat producing units to ensure compliance with future requirements.
UPGRADING OF WASTE-TO-ENERGY PLANT IN MALLORCA
Client: TIRME S.A. Financed by: The Client Start: 2004-09 End: 2004-12 Referee: Mr. Rafael Guinea, TIRME, S.A.Ctra. de Sóller, km 8,2, 07120 – Palma de Mallorca, Spain. Tel.: +34 971 43 50 50
The waste-to-energy plant at Son Reus (in Palma de Mallorca) reduces the volume of waste by 92% and allows for the production of electric-ity, which accounts for 4.7% of Mallorca’s and Minorca's consumption. The flue gas cleaning system and the continuous environmental con-trol ensure that contamination levels of emis-sions to the atmosphere are lower than the lim-its fixed by European and Spanish legislation. In 2004 TIRME decided to further upgrade the flue gas cleaning system by establishing SCR (Selective Catalytic Reduction) technology at the plant. Rambøll provided assistance in the evaluation of tenders for the implementation of such SCR technology.
Our services included a technical as well as an economic evaluation:
Technical evaluation − Robust solutions of high quality − Documented operation experience with
the suggested technical solutions − Design philosophy − Operation and maintenance needs − Energy consumption and recovery
Economic evaluation − The economic evaluation was based on
the received tender prices supplemented by an evaluation of the operating costs of the system during its technical life-time.
Furthermore, Rambøll prepared a detailed rec-ommendation, which included the following is-sues: The evaluation criteria applied Comparison of the individual tenders regard-
ing design, technical concept etc. Commercial conditions and economy (devia-
tions from demands in the tender docu-ments, comparison of time schedules, guar-anteed efficiencies, operating and mainte-nance costs etc.).
Economic comparison of tenders Recommendation for choice of contractor
NEW WASTE-TO-ENERGY UNIT IN MALMÖ, SWEDEN, SYSAV
Client: Sydvästra Skånes avfallsaktiebolag (SYSAV) Financed by: The Client Start: 1998-10 End: Ongoing Referee: Manager of SYSAV Energy Jonas Eek, SYSAV, Box 50344, 202 13 Malmö, Sweden. Tel.: +46 40-680 18 50
The waste-to-energy plant of SYSAV in Malmö has been extended by a new unit producing both heat and power on the basis of municipal solid waste and industrial waste from approx. ½ mil-lion inhabitants in the nine municipalities in Greater Malmö. The plant supplies heat and power to 30,000 households. The capacity of the plant is 250,000 tonnes of waste annually, and it produces 540,000 MWh heat and 135,000 MWh power. The plant is dimensioned in accordance with the latest EU requirements. In some areas, including NOx, the guarantee requirements are stricter than the future EU requirements. RAMBØLL is SYSAV’s representative, responsible for planning, design, tendering, contracting, pro-curement and construction supervision. In April 2000 the contract for the machinery was signed with MARTIN GmbH for the fur-nace/boiler, LAB SA for the flue gas treatment system and Alstom Power Sweden AB for the turbine/generator set. In the autumn of 2000
KCI Special Cranes AB was chosen as the over-head crane supplier. PEAB was in the spring of 2000chosen as the constructor of the concrete structures, while NCC in the autumn of 2001 was chosen as the constructor of the steel struc-tures. Rewiring and excavations for the waste pit and slag bunker were carried out in the summer and autumn of 2000 followed by pile foundation of the building with approx. 2200 piles. In September 2001 the concrete structures were finished to such an extent that the installation of machinery could begin. MARTIN, LAB and Alstom have in co-operation with SYSAV standardised the selection of com-ponents and sub-suppliers in order to ensure optimal maintenance conditions and a high de-gree of quality. The first firing with waste took place in December 2002. After this the produc-tion of heat and power started at the new plant.
New Energy-from-Waste Plants Selected References
Page 1
Client/ location
Country Project Capacity tpa
Rambøll’s main responsibilities
Year
Norsk Varme/ Kristiansand
Norway Establishment of a complete new WtE unit (CHP)
48,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2005-ongoing
Government of Gibraltar
Gibraltar Establishment of a complete new WtE plant for the incineration of MSW and sludge and demolition of an existing WtE plant
up to 28,000 Planning, PPP assessment, project structuring, conceptual design, tendering, contracting, project/contract management, supervision, commissioning, initial operation. Civil engineering design.
2005-ongoing
Uddevalla Energi
Sweden Establishment of a complete new WtE plant (CHP)
up to 100,000
Planning, conceptual design, tendering, contracting.
2005-ongoing
European Bank for Reconstruc-tion and Development
Russia Establishment of a new fluidised bed sludge incineration plant in St. Petersburg
44,000 Lender’s Supervisor 2005-ongoing
European Commission
Russia Establishment of a new fluidised bed sludge incineration plant in St. Petersburg
2 x 16,000 (on dry basis)
Bid evaluation, contract management, supervision, commissioning and project management.
2004-ongoing
South East Region
Ireland Procurement of an integrated waste management system including WtE (25 years DBFO contract)
up to 300,000
Waste strategy review, PPP assessment, project structuring, tendering, contracting, project/contract management, supervision, and commissioning.
2004- ongoing
Trekantområ-dets Affalds-selskab I/S
Denmark Establishment of a complete new WtE unit (CHP)
80,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
2003- ongoing
Trondheim Energiverk
Norway Establishment of a complete new WtE unit (CHP)
120,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2003-ongoing
States of Guernsey, Board of administration
UK Establishment and operation of a green-field WtE facility (DBO contract).
72,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2001-ongoing (on hold pending political review)
I/S FASAN* Denmark Establishment and operation of a green-field WtE facility
65,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design
2001-ongoing
Vattenfall Värme Uppsala AB*
Sweden Establishment of a complete new WtE unit (CHP)
175,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2000-ongoing
I/S Reno-Nord*
Denmark Establishment of a complete new WtE unit (CHP)
160,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1999-ongoing
New Energy-from-Waste Plants Selected References
Page 2
Client/ location
Country Project Capacity tpa
Rambøll’s main responsibilities
Year
Halmstads Renhållnings AB*
Sweden Establishment of a complete new WtE unit (CHP)
120,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
1999 –ongoing
SYSAV*
Sweden Establishment of a complete new WtE unit (CHP)
210,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1998 –ongoing
Department of Local Government and Environment, Isle of Man
UK Establishment and operation of a green-field WtE facility, including a facility to incinerate special waste (20 year DBO contract).
65,000 + 5,000
Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
1997 –ongoing
States of Alderney
UK Establishment of a waste gasification system
2,000 Procurement of a waste gasification system on a lease basis.
2002-2004
DANIDA / Cairo University Hospital
Egypt Introduction of a new clinical waste system. Establishment of a state-of-the art clinical waste incineration plant.
Batch 2 x 3.6 tpd
Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2000 – 2002
EPA Hong Kong
Hong Kong Animal carcass incineration plant
30 tpd Feasibility study and preparation of tender documents.
2001
Avedøre Waste Water Treatment Plant (serves a large part of Copenhagen)
Denmark Establishment of a complete new sludge incineration plant based on fluidised bed technology
16,000 (on dry basis)
Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning. Civil engineering design.
1995 – 2001
I/S REFA*
Denmark Establishment of a complete new WtE unit (CHP)
72,000 Planning, environmental approval, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1997 – 2000
I/S Nordforbræn-ding*
Denmark Establishment of a complete new WtE unit (CHP)
80,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1994-2000
I/S KARA*
Denmark Establishment of a complete new WtE unit (CHP)
160,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1994-2000
AVV I/S* Denmark Establishment of a complete new WtE unit (CHP)
50,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
1993-2000
Svendborg Incineration Plant I/S*
Denmark Establishment of a complete new WtE unit (CHP)
48,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1994-1999
New Energy-from-Waste Plants Selected References
Page 3
Client/ location
Country Project Capacity tpa
Rambøll’s main responsibilities
Year
I/S Vestforbræn-ding*
Denmark Establishment of a complete new WtE (CHP) unit.
210,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1994-1999
Environmental Protection Agency
Taiwan Establishment and operation of a green-field WtE facility
300,000 Expert support to tender preparation, bid evaluation, evaluation of specifications, supervision and commissioning.
1993-1999
BIR* Norway Establishment of a complete new WtE (CHP) unit.
112,000 Planning, conceptual design, tendering, contracting of the electro-mechanical equipment.
1996
Sønderborg CHP plant*
Denmark Establishment of a complete new WtE unit (CHP)
66,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.
1993 – 1996
LIPOR (Oporto)
Portugal Establishment and operation of a green-field WtE facility
400,000 Expert assistance in the tender evaluation.
1993
Notes *a regional local authority waste disposal company
Upgrading of Energy-from-Waste Plants Selected References
Page 4
Client/ location
Country Project Capacity tpa
Rambøll’s main responsibilities
Year
ASM Brescia Italy Upgrading of existing WtE facility, including crane automation and establishment of a new crane
3x184,000 Feasibility study, planning, conceptual design, tendering, contracting.
2004-ongoing
Trondheim Energiverk
Norway Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
96,000 Feasibility study, planning, conceptual design, tendering, contracting.
2004 – ongoing
Torshavn Municipality
Faroe Islands
Upgrading of flue gas cleaning system
22,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2004 – ongoing
IRF, Leirvik Faroe Islands
Upgrading of flue gas cleaning system and furnace/boiler
22,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2004 – ongoing
AVV I/S* Denmark Upgrading of the flue gas cleaning system to comply with EU directive 2000/76/EC
50,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2003- ongoing
Lynette-fællesskabet I/S
Denmark Upgrading of the flue gas cleaning system on the sludge incineration plant to comply with EU directive 2000/76/EC
- Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2003 – ongoing
Århus Kommunale Værker
Denmark Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
2 x 50,000 Feasibility study, planning, conceptual design, tendering, contracting.
2003 – ongoing
SYSAV Sweden Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
2 x 90,000 Feasibility study, planning, conceptual design, tendering, contracting.
2003 – ongoing
Sønderborg CHP plant*
Denmark Upgrading of the flue gas cleaning system to comply with EU directive 2000/76/EC
66,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2002-ongoing
KAVO I/S*
Denmark Upgrading of an existing WtE facility including the flue gas cleaning system comply with EU directive 2000/76/EC
32,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2002-ongoing
I/S FASAN*
Denmark Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
2 x 36,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.
2001-ongoing
Upgrading of Energy-from-Waste Plants Selected References
Page 5
Client/ location
Country Project Capacity tpa
Rambøll’s main responsibilities
Year
Renhållnings Bolaget*
Sweden Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
2 x 40,000 Feasibility study, planning, conceptual design, tendering, contracting,.
2001-ongoing
TIRME, S.A., Mallorca
Spain Upgrading of existing WtE facility, including the flue gas cleaning system.
2x150,000 Assistance in evaluation of tenders for the establishment of a system for selective catalytic reduction of NOx (SCR)
2004-2005
I/S Nordforbræn-ding*
Denmark Upgrading of the existing WtE facility (three lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC
3 x 24,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.
2001-2003
City of Budapest
Hungary Upgrading of an existing WtE facility including the flue gas cleaning system to comply with EU directive 2000/76/EC. Introduction of facilities for pre-treatment of waste and treatment and disposal of residues
4 x 120,000 Analysis, planning, conceptual design, tendering and contracting of the upgrading of the WtE facility and the new units for the pre-treatment of waste and management of residues.
2001-2002
Kommune-kemi Ltd
Denmark Complete retrofit of a hazardous waste incineration plant.
- Supervisor of the retrofit of the combustion chamber and the boiler.
2001
Moscow City Russia Rehabilitation of an existing WtE plant
4 x 84,000 Detailed study of the feasibility of rehabilitating plant no. 3 in Moscow.
1993-2001
Notes *a regional local authority waste disposal company
Studies etc. on Energy-from-Waste Plants Selected References
Page 6
Client/ location
Country Project Rambøll’s main responsibilities
Year
South East Region
Ireland Waste Management Strategy for the South East region of Ireland
Preparation of strategy together with a local Irish partner company
2004-ongoing
NEFCO via ERM
Russia Waste incineration plant in Murmansk
Study of possibility of improving existing waste incineration plant in Murmansk.
2002
States of Alderney
UK Review of waste strategy Review of Alderney’s preliminary waste strategy including an analysis of an on-island disposal option of MSW through thermal treatment.
2001
South East Region
Ireland Preparation of Waste Management Plan for the region
As a sub-consultant to a local Irish Consultant Ramboll prepared the review and assessment of the thermal treatment options outlined in a previous strategy study.
2000
Danish EPA Denmark Study on waste as a resource for energy production
Studies to assess the need for incineration over the next decade for each region and for Denmark as a whole.
2000
Municipality of Torshavn
Faroe Islands
Studies regarding the establishment of a complete new WtE unit (CHP)
Study to assess the feasibility of a new plant. 2000
I/S FASAN*
Denmark Studies regarding the establishment of a new WtE unit and the purchase of a gas fired power plant
Technical, operational and financial analysis to assess the feasibility of a new plant and the purchase of a gas fired power plant.
1999 - 2000
World Bank (IBRD)
Regional Preparation of the World Bank publication “the Decision Makers Guide to Municipal Solid Waste Incineration”
Preparation of the guide and a supporting World Bank Technical Paper “Municipal Solid Waste Incineration – Requirements for a Successful Project”
1998
I/S Vestforbræn-ding*
Denmark Environmental Impact Assessment. Application for environmental permit
Preparation of EIA and application for environmental/operational permit for I/S Vestforbræmding – the largest WtE facility in Scandinavia.
1998
Municipality of Køge
Denmark Privatisation of sludge incineration plant
Support to the seller of the plant (the municipality) with analysis and during negotiations.
1998
The European Bank / Moscow City
Russia Review of PPP options for waste treatment in Moscow.
Review of PPP options for the revamping, financing and operation of incineration plants in Moscow city.
1997
Private Client UK Refurbishment and refinancing of WtE facility
Technical and financial analysis to assess the feasibility of a refurbishment and refinancing of an existing WtE facility on a BOT basis.
1997
Danish EPA Denmark Study on waste as a resource for energy production
Studies to assess the need for incineration over the next decade for each region and for Denmark as a whole.
1996
I/S Fælles Forbrænding*
Denmark Studies regarding the establishment of a new green-field WtE facility.
Studies to assess the feasibility of a new facility.
1996
Oslo Renholdsver-ket*
Norway Studies regarding the extension of the WtE facility.
Studies to assess the feasibility of a new facility. 1996
DANIDA Philip-pines
Pre-appraisal of WtE facility. Review of project feasibility. 1995-1996
Studies etc. on Energy-from-Waste Plants Selected References
Page 7
Client/ location
Country Project Rambøll’s main responsibilities
Year
IPE-EGF Portugal Review of alternative thermal treatment technologies
Preparation and review of different thermal treatment technologies. Presentation of plant concepts, environmental performance, costs and manufactures.
1994
DANIDA China Pre-appraisal of WtE facility. Review of project to assess feasibility for soft credit financing.
1994
Municipality of Skagen
Denmark Studies on the establishment of a CC plant for incineration of waste, biomass and natural gas
Studies to assess the feasibility of a new facility. Preparation of preliminary design.
1993
I/S KARA* Denmark Studies regarding the establishment of a new WtE plant with a capacity of 160,000 tpa.
Studies to assess the feasibility of a new facility. 1993
Notes *a regional local authority waste disposal company