13
UPGRADING OF WASTE-TO-ENERGY PLANT IN BRESCIA, ITALY Client: ASM Brescia Financed by: The client Start: 2004-04 End: Ongoing Contact: Managing Director A. Bonomo, Via Lamarmora 230, IT-25124 Brescia, Italy Tel.: +39 030-35531 Rambøll is assisting the waste-to-energy plant of ASM Brescia in installing a new waste crane and establishing crane automation. ASM Brescia S.P.A. is a large public utilities company established more than 100 years ago. The company is responsible for the production of power and district heating, gas supply, waste collection, treatment and disposal, and wastewa- ter treatment. Brescia was one of the first cities to have a well-established district heating net- work. Today, the waste-to-energy plant supplies heat to approx. 65 per cent of Brescia’s inhabi- tants. In addition, ASM Brescia runs an adjacent power plant, a composting plant for source- separated household and garden waste and a sanitary landfill. The management of the waste-to-energy plant became very interested in crane automation during one of Rambøll’s visits to the plant when Rambøll reported on the success of automated cranes at the two largest waste-to-energy plants in Denmark, I/S Amagerforbrænding and I/S Vestforbrænding. Rambøll’s experience from these two plants was a decisive factor when ASM Brescia requested our assistance. Rambøll has also assisted ASM Brescia in exam- ining the options for the management of bio- mass incinerated in a recently commissioned unit 3 dedicated specifically for that purpose.

UPGRADING OF WASTE-TO-ENERGY PLANT IN … OF WASTE-TO-ENERGY PLANT IN BRESCIA, ITALY Client: ASM Brescia Financed by: The client Start: 2004-04 End: Ongoing Contact: Managing Director

Embed Size (px)

Citation preview

UPGRADING OF WASTE-TO-ENERGY PLANT IN BRESCIA, ITALY

Client: ASM Brescia Financed by: The client Start: 2004-04 End: Ongoing Contact: Managing Director A. Bonomo, Via Lamarmora 230, IT-25124 Brescia, Italy Tel.: +39 030-35531

Rambøll is assisting the waste-to-energy plant of ASM Brescia in installing a new waste crane and establishing crane automation. ASM Brescia S.P.A. is a large public utilities company established more than 100 years ago. The company is responsible for the production of power and district heating, gas supply, waste collection, treatment and disposal, and wastewa-ter treatment. Brescia was one of the first cities to have a well-established district heating net-work. Today, the waste-to-energy plant supplies heat to approx. 65 per cent of Brescia’s inhabi-tants. In addition, ASM Brescia runs an adjacent power plant, a composting plant for source-separated household and garden waste and a sanitary landfill.

The management of the waste-to-energy plant became very interested in crane automation during one of Rambøll’s visits to the plant when Rambøll reported on the success of automated cranes at the two largest waste-to-energy plants in Denmark, I/S Amagerforbrænding and I/S Vestforbrænding. Rambøll’s experience from these two plants was a decisive factor when ASM Brescia requested our assistance. Rambøll has also assisted ASM Brescia in exam-ining the options for the management of bio-mass incinerated in a recently commissioned unit 3 dedicated specifically for that purpose.

NEW WASTE-TO-ENERGY UNIT IN AALBORG, DENMARK

Client: I/S Reno-Nord Financed by: The Client Start: 1999 End: Ongoing Referee: Dir. Henrik Skovhaug, I/S Reno-Nord, Troensevej 2, DK-9220 Aalborg Øst. Tel.: +45 98 15 65 66

Client’s Representative for I/S Reno-Nord during all stages of the planning and establishment of a new waste-to-energy plant with combined heat and power production (CHP) and a treatment capacity of about 160,000 tpa. RAMBØLL’s re-sponsibilities include, inter alia: • Application for planning approval • Conceptual design and layout of the plant • Detailed design of civil works • Preparation of tender documents for all M&E

plant and civil works

● Procurement management • Tender evaluation and contract negotiations • Project and contract management • Supervision during construction and com-

missioning In addition to the new furnace/boiler and tur-bine/generator units the new plant includes a wet flue gas cleaning system, which satisfies the new EU directive 2000/76/EC. The plant is scheduled for commercial operation in 2005.

REHABILITATION OF WASTE INCINERATION PLANT IN BUDAPEST, HUNGARY

Client: Municipality of Budapest Financed by: The Client Start: 2001 End: Ongoing Referee: Head of PIU Attila Pocs, Municipality of Budapest Tel. +36 1 317 63 10 Janos Banhidy, Municipal Public Services Tel. +36 1 307 6174

Rambøll is assisting the Municipality of Budapest in the upgrading and rehabilitation of the Buda-pest Waste-to-Energy Plant. Rambøll’s responsi-bilities include assistance in the tendering of a flue gas treatment system and rehabilitation of the existing four boilers as well as assistance in the tendering

of pre-treatment technology and facility for re-covery and disposal of solid flue gas treatment and incineration residues. After signature of the contract Rambøll provides expert assistance to the client in connection with commercial issues, check of scope of supply and review of technical solutions.

NEW WASTE-TO-ENERGY UNIT IN HALMSTAD, SWEDEN

Client: Halmstads Renhållnings AB Financed by: The Client Start: 1999-03 End: Ongoing Referee: Dir. Per-Olof Andersson, Halmstads Renhållnings AB, Box 8005, S-300 08 Halmstad, Sweden. Tel.: + 46 35 190 121

Rambøll is the Client’s Representative in connec-tion with machinery at the waste-to-energy plant in Halmstad, responsible for elaboration of decision-making basis for the extension by a new combined heat and power producing unit with a capacity of 15 t/h. In addition Rambøll is responsible for planning, conceptual design, elaboration of tender documents, tendering, tender evaluation and contracting of the entire machinery supply as well as co-ordination of the conceptual and detailed design of buildings and construction works. The new unit was commis-sioned at the beginning of 2003. In June 2000 the contract for the machinery supply was awarded to Babcock Borsig Power BBP (formerly Steinmüller) from Germany, while NCC in the autumn of 2000 was chosen as turn-key contractor for the entire building activities. The final layout was decided during the course of 2000, and all information necessary for the building activities was procured.

BBP has in co-operation with the Client selected all sub-suppliers, and the production has been going on all over Europe. The installation of ma-chinery started in mid-August 2001. In Septem-ber 2002 BBP went bankrupt and consequently could not complete the project. A contract was signed with FISIA Babcock Environment GmbH (FBE) for completion of the project. In April 2003 waste was incinerated in the new unit for the very first time, and in June 2003 power was supplied to the power network. Rambøll assisted the Client in connection with the bankruptcy of BBP. The plant is dimensioned in accordance with the latest EU environmental requirements. In some areas, including NOx, the guarantee require-ments at the new plant are stricter than future requirements. Rambøll is also assisting the Client in the up-grading of the two existing heat producing units to ensure compliance with future requirements.

UPGRADING OF WASTE-TO-ENERGY PLANT IN MALLORCA

Client: TIRME S.A. Financed by: The Client Start: 2004-09 End: 2004-12 Referee: Mr. Rafael Guinea, TIRME, S.A.Ctra. de Sóller, km 8,2, 07120 – Palma de Mallorca, Spain. Tel.: +34 971 43 50 50

The waste-to-energy plant at Son Reus (in Palma de Mallorca) reduces the volume of waste by 92% and allows for the production of electric-ity, which accounts for 4.7% of Mallorca’s and Minorca's consumption. The flue gas cleaning system and the continuous environmental con-trol ensure that contamination levels of emis-sions to the atmosphere are lower than the lim-its fixed by European and Spanish legislation. In 2004 TIRME decided to further upgrade the flue gas cleaning system by establishing SCR (Selective Catalytic Reduction) technology at the plant. Rambøll provided assistance in the evaluation of tenders for the implementation of such SCR technology.

Our services included a technical as well as an economic evaluation:

Technical evaluation − Robust solutions of high quality − Documented operation experience with

the suggested technical solutions − Design philosophy − Operation and maintenance needs − Energy consumption and recovery

Economic evaluation − The economic evaluation was based on

the received tender prices supplemented by an evaluation of the operating costs of the system during its technical life-time.

Furthermore, Rambøll prepared a detailed rec-ommendation, which included the following is-sues: The evaluation criteria applied Comparison of the individual tenders regard-

ing design, technical concept etc. Commercial conditions and economy (devia-

tions from demands in the tender docu-ments, comparison of time schedules, guar-anteed efficiencies, operating and mainte-nance costs etc.).

Economic comparison of tenders Recommendation for choice of contractor

NEW WASTE-TO-ENERGY UNIT IN MALMÖ, SWEDEN, SYSAV

Client: Sydvästra Skånes avfallsaktiebolag (SYSAV) Financed by: The Client Start: 1998-10 End: Ongoing Referee: Manager of SYSAV Energy Jonas Eek, SYSAV, Box 50344, 202 13 Malmö, Sweden. Tel.: +46 40-680 18 50

The waste-to-energy plant of SYSAV in Malmö has been extended by a new unit producing both heat and power on the basis of municipal solid waste and industrial waste from approx. ½ mil-lion inhabitants in the nine municipalities in Greater Malmö. The plant supplies heat and power to 30,000 households. The capacity of the plant is 250,000 tonnes of waste annually, and it produces 540,000 MWh heat and 135,000 MWh power. The plant is dimensioned in accordance with the latest EU requirements. In some areas, including NOx, the guarantee requirements are stricter than the future EU requirements. RAMBØLL is SYSAV’s representative, responsible for planning, design, tendering, contracting, pro-curement and construction supervision. In April 2000 the contract for the machinery was signed with MARTIN GmbH for the fur-nace/boiler, LAB SA for the flue gas treatment system and Alstom Power Sweden AB for the turbine/generator set. In the autumn of 2000

KCI Special Cranes AB was chosen as the over-head crane supplier. PEAB was in the spring of 2000chosen as the constructor of the concrete structures, while NCC in the autumn of 2001 was chosen as the constructor of the steel struc-tures. Rewiring and excavations for the waste pit and slag bunker were carried out in the summer and autumn of 2000 followed by pile foundation of the building with approx. 2200 piles. In September 2001 the concrete structures were finished to such an extent that the installation of machinery could begin. MARTIN, LAB and Alstom have in co-operation with SYSAV standardised the selection of com-ponents and sub-suppliers in order to ensure optimal maintenance conditions and a high de-gree of quality. The first firing with waste took place in December 2002. After this the produc-tion of heat and power started at the new plant.

New Energy-from-Waste Plants Selected References

Page 1

Client/ location

Country Project Capacity tpa

Rambøll’s main responsibilities

Year

Norsk Varme/ Kristiansand

Norway Establishment of a complete new WtE unit (CHP)

48,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2005-ongoing

Government of Gibraltar

Gibraltar Establishment of a complete new WtE plant for the incineration of MSW and sludge and demolition of an existing WtE plant

up to 28,000 Planning, PPP assessment, project structuring, conceptual design, tendering, contracting, project/contract management, supervision, commissioning, initial operation. Civil engineering design.

2005-ongoing

Uddevalla Energi

Sweden Establishment of a complete new WtE plant (CHP)

up to 100,000

Planning, conceptual design, tendering, contracting.

2005-ongoing

European Bank for Reconstruc-tion and Development

Russia Establishment of a new fluidised bed sludge incineration plant in St. Petersburg

44,000 Lender’s Supervisor 2005-ongoing

European Commission

Russia Establishment of a new fluidised bed sludge incineration plant in St. Petersburg

2 x 16,000 (on dry basis)

Bid evaluation, contract management, supervision, commissioning and project management.

2004-ongoing

South East Region

Ireland Procurement of an integrated waste management system including WtE (25 years DBFO contract)

up to 300,000

Waste strategy review, PPP assessment, project structuring, tendering, contracting, project/contract management, supervision, and commissioning.

2004- ongoing

Trekantområ-dets Affalds-selskab I/S

Denmark Establishment of a complete new WtE unit (CHP)

80,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

2003- ongoing

Trondheim Energiverk

Norway Establishment of a complete new WtE unit (CHP)

120,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2003-ongoing

States of Guernsey, Board of administration

UK Establishment and operation of a green-field WtE facility (DBO contract).

72,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2001-ongoing (on hold pending political review)

I/S FASAN* Denmark Establishment and operation of a green-field WtE facility

65,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design

2001-ongoing

Vattenfall Värme Uppsala AB*

Sweden Establishment of a complete new WtE unit (CHP)

175,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2000-ongoing

I/S Reno-Nord*

Denmark Establishment of a complete new WtE unit (CHP)

160,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1999-ongoing

New Energy-from-Waste Plants Selected References

Page 2

Client/ location

Country Project Capacity tpa

Rambøll’s main responsibilities

Year

Halmstads Renhållnings AB*

Sweden Establishment of a complete new WtE unit (CHP)

120,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

1999 –ongoing

SYSAV*

Sweden Establishment of a complete new WtE unit (CHP)

210,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1998 –ongoing

Department of Local Government and Environment, Isle of Man

UK Establishment and operation of a green-field WtE facility, including a facility to incinerate special waste (20 year DBO contract).

65,000 + 5,000

Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

1997 –ongoing

States of Alderney

UK Establishment of a waste gasification system

2,000 Procurement of a waste gasification system on a lease basis.

2002-2004

DANIDA / Cairo University Hospital

Egypt Introduction of a new clinical waste system. Establishment of a state-of-the art clinical waste incineration plant.

Batch 2 x 3.6 tpd

Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2000 – 2002

EPA Hong Kong

Hong Kong Animal carcass incineration plant

30 tpd Feasibility study and preparation of tender documents.

2001

Avedøre Waste Water Treatment Plant (serves a large part of Copenhagen)

Denmark Establishment of a complete new sludge incineration plant based on fluidised bed technology

16,000 (on dry basis)

Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning. Civil engineering design.

1995 – 2001

I/S REFA*

Denmark Establishment of a complete new WtE unit (CHP)

72,000 Planning, environmental approval, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1997 – 2000

I/S Nordforbræn-ding*

Denmark Establishment of a complete new WtE unit (CHP)

80,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1994-2000

I/S KARA*

Denmark Establishment of a complete new WtE unit (CHP)

160,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1994-2000

AVV I/S* Denmark Establishment of a complete new WtE unit (CHP)

50,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

1993-2000

Svendborg Incineration Plant I/S*

Denmark Establishment of a complete new WtE unit (CHP)

48,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1994-1999

New Energy-from-Waste Plants Selected References

Page 3

Client/ location

Country Project Capacity tpa

Rambøll’s main responsibilities

Year

I/S Vestforbræn-ding*

Denmark Establishment of a complete new WtE (CHP) unit.

210,000 Planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1994-1999

Environmental Protection Agency

Taiwan Establishment and operation of a green-field WtE facility

300,000 Expert support to tender preparation, bid evaluation, evaluation of specifications, supervision and commissioning.

1993-1999

BIR* Norway Establishment of a complete new WtE (CHP) unit.

112,000 Planning, conceptual design, tendering, contracting of the electro-mechanical equipment.

1996

Sønderborg CHP plant*

Denmark Establishment of a complete new WtE unit (CHP)

66,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning. Civil engineering design.

1993 – 1996

LIPOR (Oporto)

Portugal Establishment and operation of a green-field WtE facility

400,000 Expert assistance in the tender evaluation.

1993

Notes *a regional local authority waste disposal company

Upgrading of Energy-from-Waste Plants Selected References

Page 4

Client/ location

Country Project Capacity tpa

Rambøll’s main responsibilities

Year

ASM Brescia Italy Upgrading of existing WtE facility, including crane automation and establishment of a new crane

3x184,000 Feasibility study, planning, conceptual design, tendering, contracting.

2004-ongoing

Trondheim Energiverk

Norway Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

96,000 Feasibility study, planning, conceptual design, tendering, contracting.

2004 – ongoing

Torshavn Municipality

Faroe Islands

Upgrading of flue gas cleaning system

22,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2004 – ongoing

IRF, Leirvik Faroe Islands

Upgrading of flue gas cleaning system and furnace/boiler

22,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2004 – ongoing

AVV I/S* Denmark Upgrading of the flue gas cleaning system to comply with EU directive 2000/76/EC

50,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2003- ongoing

Lynette-fællesskabet I/S

Denmark Upgrading of the flue gas cleaning system on the sludge incineration plant to comply with EU directive 2000/76/EC

- Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2003 – ongoing

Århus Kommunale Værker

Denmark Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

2 x 50,000 Feasibility study, planning, conceptual design, tendering, contracting.

2003 – ongoing

SYSAV Sweden Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

2 x 90,000 Feasibility study, planning, conceptual design, tendering, contracting.

2003 – ongoing

Sønderborg CHP plant*

Denmark Upgrading of the flue gas cleaning system to comply with EU directive 2000/76/EC

66,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2002-ongoing

KAVO I/S*

Denmark Upgrading of an existing WtE facility including the flue gas cleaning system comply with EU directive 2000/76/EC

32,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2002-ongoing

I/S FASAN*

Denmark Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

2 x 36,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, commissioning.

2001-ongoing

Upgrading of Energy-from-Waste Plants Selected References

Page 5

Client/ location

Country Project Capacity tpa

Rambøll’s main responsibilities

Year

Renhållnings Bolaget*

Sweden Upgrading of the existing WtE facility (two lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

2 x 40,000 Feasibility study, planning, conceptual design, tendering, contracting,.

2001-ongoing

TIRME, S.A., Mallorca

Spain Upgrading of existing WtE facility, including the flue gas cleaning system.

2x150,000 Assistance in evaluation of tenders for the establishment of a system for selective catalytic reduction of NOx (SCR)

2004-2005

I/S Nordforbræn-ding*

Denmark Upgrading of the existing WtE facility (three lines) including the flue gas cleaning system to comply with EU directive 2000/76/EC

3 x 24,000 Analysis, planning, conceptual design, tendering, contracting, project/contract management, supervision, commissioning.

2001-2003

City of Budapest

Hungary Upgrading of an existing WtE facility including the flue gas cleaning system to comply with EU directive 2000/76/EC. Introduction of facilities for pre-treatment of waste and treatment and disposal of residues

4 x 120,000 Analysis, planning, conceptual design, tendering and contracting of the upgrading of the WtE facility and the new units for the pre-treatment of waste and management of residues.

2001-2002

Kommune-kemi Ltd

Denmark Complete retrofit of a hazardous waste incineration plant.

- Supervisor of the retrofit of the combustion chamber and the boiler.

2001

Moscow City Russia Rehabilitation of an existing WtE plant

4 x 84,000 Detailed study of the feasibility of rehabilitating plant no. 3 in Moscow.

1993-2001

Notes *a regional local authority waste disposal company

Studies etc. on Energy-from-Waste Plants Selected References

Page 6

Client/ location

Country Project Rambøll’s main responsibilities

Year

South East Region

Ireland Waste Management Strategy for the South East region of Ireland

Preparation of strategy together with a local Irish partner company

2004-ongoing

NEFCO via ERM

Russia Waste incineration plant in Murmansk

Study of possibility of improving existing waste incineration plant in Murmansk.

2002

States of Alderney

UK Review of waste strategy Review of Alderney’s preliminary waste strategy including an analysis of an on-island disposal option of MSW through thermal treatment.

2001

South East Region

Ireland Preparation of Waste Management Plan for the region

As a sub-consultant to a local Irish Consultant Ramboll prepared the review and assessment of the thermal treatment options outlined in a previous strategy study.

2000

Danish EPA Denmark Study on waste as a resource for energy production

Studies to assess the need for incineration over the next decade for each region and for Denmark as a whole.

2000

Municipality of Torshavn

Faroe Islands

Studies regarding the establishment of a complete new WtE unit (CHP)

Study to assess the feasibility of a new plant. 2000

I/S FASAN*

Denmark Studies regarding the establishment of a new WtE unit and the purchase of a gas fired power plant

Technical, operational and financial analysis to assess the feasibility of a new plant and the purchase of a gas fired power plant.

1999 - 2000

World Bank (IBRD)

Regional Preparation of the World Bank publication “the Decision Makers Guide to Municipal Solid Waste Incineration”

Preparation of the guide and a supporting World Bank Technical Paper “Municipal Solid Waste Incineration – Requirements for a Successful Project”

1998

I/S Vestforbræn-ding*

Denmark Environmental Impact Assessment. Application for environmental permit

Preparation of EIA and application for environmental/operational permit for I/S Vestforbræmding – the largest WtE facility in Scandinavia.

1998

Municipality of Køge

Denmark Privatisation of sludge incineration plant

Support to the seller of the plant (the municipality) with analysis and during negotiations.

1998

The European Bank / Moscow City

Russia Review of PPP options for waste treatment in Moscow.

Review of PPP options for the revamping, financing and operation of incineration plants in Moscow city.

1997

Private Client UK Refurbishment and refinancing of WtE facility

Technical and financial analysis to assess the feasibility of a refurbishment and refinancing of an existing WtE facility on a BOT basis.

1997

Danish EPA Denmark Study on waste as a resource for energy production

Studies to assess the need for incineration over the next decade for each region and for Denmark as a whole.

1996

I/S Fælles Forbrænding*

Denmark Studies regarding the establishment of a new green-field WtE facility.

Studies to assess the feasibility of a new facility.

1996

Oslo Renholdsver-ket*

Norway Studies regarding the extension of the WtE facility.

Studies to assess the feasibility of a new facility. 1996

DANIDA Philip-pines

Pre-appraisal of WtE facility. Review of project feasibility. 1995-1996

Studies etc. on Energy-from-Waste Plants Selected References

Page 7

Client/ location

Country Project Rambøll’s main responsibilities

Year

IPE-EGF Portugal Review of alternative thermal treatment technologies

Preparation and review of different thermal treatment technologies. Presentation of plant concepts, environmental performance, costs and manufactures.

1994

DANIDA China Pre-appraisal of WtE facility. Review of project to assess feasibility for soft credit financing.

1994

Municipality of Skagen

Denmark Studies on the establishment of a CC plant for incineration of waste, biomass and natural gas

Studies to assess the feasibility of a new facility. Preparation of preliminary design.

1993

I/S KARA* Denmark Studies regarding the establishment of a new WtE plant with a capacity of 160,000 tpa.

Studies to assess the feasibility of a new facility. 1993

Notes *a regional local authority waste disposal company