Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
11
Underground
Operations
Crew ManagementCrew ManagementNewlands Northern UndergroundNewlands Northern Underground
Welcome Welcome
Glen DonnellanGlen Donnellan Development Superintendent Development Superintendent
Newlands Northern UndergroundNewlands Northern Underground
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
22
Underground
Operations TodayToday
Movie on Glenden/Northern Movie on Glenden/Northern UndergroundUnderground
History on the Northern History on the Northern UndergroundUnderground
Crew Management during high turn Crew Management during high turn overover
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
33
Underground
Operations Newlands Northern UndergroundNewlands Northern Underground
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
44
Underground
Operations Xstrata QLDXstrata QLD
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
55
Underground
Operations Newlands Underground MinesNewlands Underground Mines
The Northern Mine is The Northern Mine is located in the same seam located in the same seam (UNS) as the Southern (UNS) as the Southern mine. There is only 2,000 mine. There is only 2,000 metres between the metres between the workings of each mine.workings of each mine.
The Northern Mine has 6 The Northern Mine has 6 Longwall blocks accessed Longwall blocks accessed directly from the open cut directly from the open cut between ramps 4 & 6.between ramps 4 & 6.
29 million tonnes29 million tonnes
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
66
Underground
Operations Newlands Northern UndergroundNewlands Northern Underground
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
77
Underground
Operations The Portal AreaThe Portal Area
Newlands SeamUpper
Portal
80m High wallReverse Fault
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
88
Underground
Operations The StartThe Start
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
99
Underground
Operations Taking BottomsTaking Bottoms
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1010
Underground
Operations The First PortalThe First Portal
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1111
Underground
Operations
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1212
Underground
Operations After Floor Brushing After Floor Brushing
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1313
Underground
Operations
History of Newlands Northern History of Newlands Northern UndergroundUnderground
Northern started in 2003 with Walters Northern started in 2003 with Walters developing the mains until the developing the mains until the Development drivage at the Southern Development drivage at the Southern underground was complete in April underground was complete in April 20042004
Contractors finished up at the end of Contractors finished up at the end of April 2004 April 2004
January to the end of April 2004 January to the end of April 2004 2487.8 mts were driven by Walters at 2487.8 mts were driven by Walters at an average of 621.9 metres per an average of 621.9 metres per month month
Development crews started at the Development crews started at the Northern Underground in May 2004Northern Underground in May 2004
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1414
Underground
Operations One unit onlyOne unit only The unitThe unit
1 x 12cm12(Joy) with 1 x 12cm12(Joy) with 5.8 metre head5.8 metre head
Road way dimensions Road way dimensions are 5.8 mts wide and are 5.8 mts wide and 4 metres high 4 metres high
1 x shuttle car (Joy 1 x shuttle car (Joy 15sc32)15sc32)
1 x stamler breaker 1 x stamler breaker feederfeeder
1 x aux fan(23)1 x aux fan(23)
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1515
Underground
Operations Development Crews Development Crews Cutting crews work 7 on 7 offCutting crews work 7 on 7 off
The 4 coal cutting crews are made up ofThe 4 coal cutting crews are made up of 1 x Deputy1 x Deputy 6 x Miners 6 x Miners 2 x Fitters 2 x Fitters
1 x Electrician 1 x Electrician
The maintenance crew work 5 on 2 off The maintenance crew work 5 on 2 off 1x Deputy 1x Deputy 3 x Miners3 x Miners 3 x Fitters3 x Fitters
2 x Electricians 2 x Electricians
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1616
Underground
Operations 20042004
In first year of the In first year of the permanent permanent workforce arriving workforce arriving at the Northern at the Northern Underground Underground 10,789 mts were 10,789 mts were driven from May to driven from May to December 2004December 2004
At an average of At an average of 1348.6 metres per 1348.6 metres per month month
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1717
Underground
Operations 20052005
13,877.3 metres 13,877.3 metres were driven were driven
At an average of At an average of 1,156.4 metres 1,156.4 metres per monthper month
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1818
Underground
Operations 20062006
10,713 metres 10,713 metres were cut in 2006were cut in 2006
At an average of At an average of 892.7 metres per 892.7 metres per monthmonth
This was down This was down 263.7 metres per 263.7 metres per month down from month down from the previous year the previous year
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
1919
Underground
Operations Movement of PeopleMovement of People
In June 2006 we lost 18 people to In June 2006 we lost 18 people to another pitanother pit
13x Miners (12 were miner drivers )13x Miners (12 were miner drivers ) 4 x Deputies4 x Deputies 1 x Mining Co-ordinator1 x Mining Co-ordinator This reduced the development This reduced the development
department to just 2 full coal cutting department to just 2 full coal cutting crewscrews
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2020
Underground
Operations Pit Average Pit Average
The impacted it had on the companyThe impacted it had on the company
Monthly average metres per month Monthly average metres per month dropped from 1193.6 to 724.6 dropped from 1193.6 to 724.6 metresmetres
Down 469 metres per monthDown 469 metres per month
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2121
Underground
Operations 20062006
Before people leftBefore people left January to June a total of 6368 January to June a total of 6368
metres were driven at an average of metres were driven at an average of 1061 metres per month1061 metres per month
After people leftAfter people left June to December a total of 4345 June to December a total of 4345
metres were driven at an average of metres were driven at an average of 724 metres per month 724 metres per month
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2222
Underground
Operations SSeniorenior M Managementanagement TTeameam
Business goalsBusiness goals The company visionThe company vision Getting the right people to fill Getting the right people to fill
permanent roles within the companypermanent roles within the company Give our front line supervisors Give our front line supervisors
(Deputies) the correct tools to do (Deputies) the correct tools to do manage their crews to meet the manage their crews to meet the companies goals companies goals
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2323
Underground
Operations The PlanThe Plan Step 1Step 1 Move people around within the crews to keep the Move people around within the crews to keep the
development ticking over until the crews were manned up development ticking over until the crews were manned up fullyfully
Step 2Step 2 Employ the right team leaders (Deputies) Employ the right team leaders (Deputies) Step 3Step 3 Employ the right crew members Employ the right crew members Step 4Step 4 Train our team leaders up to understand the people in their Train our team leaders up to understand the people in their
crews crews Step 5Step 5 Train the crews up to the Newlands standards and procedures Train the crews up to the Newlands standards and procedures
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2424
Underground
Operations Team leaders tools Team leaders tools
MBTI MBTI (Myer Briggs type indicator)(Myer Briggs type indicator) Help them in Help them in understanding the people within their understanding the people within their crew bettercrew better
Active leadership training ( Give them Active leadership training ( Give them the tools to lead and get the best out the tools to lead and get the best out of their people )of their people )
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2525
Underground
Operations
Why is Newlands Northern Why is Newlands Northern Underground using MBTIUnderground using MBTI
To build a common framework for discussingTo build a common framework for discussing effective effective communications, team work and communications, team work and
Through greater understanding and better relationships achieve Through greater understanding and better relationships achieve alignment to Newlands Underground’s values and future vision.alignment to Newlands Underground’s values and future vision.
Helping people to understandHelping people to understand Their comfort levels (preferences) at work and at homeTheir comfort levels (preferences) at work and at home Their source of discomfort (out-of preference) at work and at Their source of discomfort (out-of preference) at work and at
home home The impact of their preferences on self and othersThe impact of their preferences on self and others Differences in theirs and others preferences and the impact on Differences in theirs and others preferences and the impact on
relationshipsrelationships
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2626
Underground
Operations
Where do you prefer to focus your attention?Where do you prefer to focus your attention?Where do you get energy?Where do you get energy?EE xtraversionxtraversion andand II ntroversionntroversion
Outgoing, expressive Energised by interactionInitiate conversationAct before reflectingSociable – easy to get to knowHave many interestsNeed regular interactionInterested more in external eventsCommunicate more easily by talkingLearn best by doing or interacting
Reflective, quietEnergised by being aloneWait to be invitedReflect before actingReserved – take time to get to knowFocused on a few things in depth Need privacy for concentrationInterested more in internal reactionsCommunicate more easily by writingLearn best by reading and reflecting
MBTIMBTI
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2727
Underground
Operations 20072007 YTD 5324 YTD 5324
metres have metres have been drivenbeen driven
2410 metres 2410 metres have been have been driven in the driven in the high wall dips high wall dips area with no area with no belts using belts using shuttle cars shuttle cars piggy backing piggy backing to the surfaceto the surface
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2828
Underground
Operations Back in the gate roads Back in the gate roads
The crews in the last two months in the The crews in the last two months in the gate roads are cutting at an average of gate roads are cutting at an average of 1187.5 metres per month1187.5 metres per month
The same crews six months ago were The same crews six months ago were cutting at 724.6 metres per monthcutting at 724.6 metres per month
This is up 462.9 metres per monthThis is up 462.9 metres per month Cut rate has jumped from 2.6 mts/hr to Cut rate has jumped from 2.6 mts/hr to
4mts/hr 4mts/hr
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
2929
Underground
Operations Breaking new groundBreaking new ground
CM02 has cut 27 km without an over haul
Joy 12CM12
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
3030
Underground
Operations The last 2 monthsThe last 2 months
Averaged 311.5 mts per week
79.5 up time hrs per week
Cut 2491.6 mts
Safe Production through TeamworkSafe Production through Teamwork Standards and Urgency Standards and Urgency
3131
Underground
Operations Thank youThank you
Any QuestionsAny Questions