Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
NATIONAL POWER TRANSMISSION CORPORATION
---------------------------------------------------------------
TRANSMISSION EFFICIENCY PROJECT (TEP)
ENVIRONMENTAL MANAGEMENT PLAN
DONG ANH 220KV SUBSTATION SUBPROJECT
(Final)
Prepared by
POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 1
March 2014
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
TEP - Dong Anh 220 kV Substation Environment Management Plan
1
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................................... 1
2. POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS ............................... 1
2.1. Government Regulations: ......................................................................................................................... 1
2.2. World Bank Safeguard Policies .................................................................................................................. 3
3. SUBPROJECT DESCRIPTION .................................................................................................... 4
3.1. Objectives of the Subproject ..................................................................................................................... 4
3.2. Scope of the Subproject ............................................................................................................................ 4
3.3. Location of Subproject .............................................................................................................................. 4
3.4. Subproject Main Work Volume ................................................................................................................. 9
3.5. Main Activities Before and During Construction ..................................................................................... 10
3.6. Subproject Implementation Schedule and Total Investment ................................................................... 11
4. BASELINE DATA ......................................................................................................................... 13
4.1. Geographical Location and Population .................................................................................................... 13
4.2. Topography and Geology ........................................................................................................................ 13
4.3. Hydro- Meteorological Characteristics .................................................................................................... 13
4.4. Land use .................................................................................................................................................. 14
4.5. Environmental baseline data .................................................................................................................. 15
4.6. Socio-economic status of the project area .............................................................................................. 15
4.7. Protected areas, natural reserves, sensitive areas, cultural property, historical monument, temple and pagoda in the project area. ............................................................................................................................ 16
5. POTENTIAL IMPACTS .............................................................................................................. 16
6. MITIGATION MEASURES ......................................................................................................... 23
7. EMP IMPLEMENTATION ARRANGEMENTS ...................................................................... 36
7.1. EMP Implementation Reporting Requirements ....................................................................................... 38
8. MONITORING PROGRAM ........................................................................................................ 39
TEP - Dong Anh 220 kV Substation Environment Management Plan
2
8.1. Objectives ............................................................................................................................................... 39
9. INSTITUTIONAL DEVELOPMENT ACTIVITIES.................................................................. 48
10. COST ESTIMATION FOR EMP IMPLEMENTATION ......................................................... 51
11. PUBLIC CONSULTATION ....................................................................................................... 51
11.1. Public consultation ................................................................................................................................ 51
Annex 1: Environmental Specifications for the Contractor ............................................................................. 51
LIST OF TABLES
Table 3.1. Main construction quantity of the subproject ....................................................................................... 9
Table 3.2. List of primary construction material .................................................................................................. 10
Table 5.1. Impact of the subproject ...................................................................................................................... 17
Table 6.1. Impact mitigation measures for environment ...................................................................................... 23
Table 7.1. Institutional Arrangement for Subproject’s EMP implementation ...................................................... 36
Table 8.1. Environmental Monitoring Plan .......................................................................................................... 40
Table 9.1. Cost estimation for capacity building in EMP implementation (*) ........................................................ 48
Table 11.1. Summary of cost estimation for implementation of EMP ................................................................... 51
ABBREVIATION
AMB : North Power Project Management Board
EVN : Vietnam Electricity
SIMC : Safeguard Independent Monitoring Consultant
EMP : Environmental Management Plan
WB : World Bank
NPT : National Power Transmission Corporation
PFF : Preventing and fighting fire
TEP - Dong Anh 220 kV Substation Environment Management Plan
3
PTC1 : Power Transmission Company No.1
PECC1 : Power Engineering Consulting Joint – stock Company No. 1
TEP : Transmission Efficiency Project
VND : Vietnam Dong
USD : U.S.Dollar
EMF : Electromagnetic Field
GOV : Government of Vietnam
HV : High voltage
LV : Low Voltage
MONRE : Ministry of Natural Resources and Environment
PCBs : Polychlorinated Biphenyls
PMU : Project Management Unit (under the AMB)
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 1
1. INTRODUCTION
The subproject: “Dong Anh 220kV Substation” is one of the subprojects that will be
implemented in Phase I of the Transmission Efficiency Project (TEP) funded by the World
Bank. The subproject will be implemented in Lien Ha and Thuy Lam communes of Dong
Anh district, Hanoi city. The implementation of the subproject is in line with the City Power
Development Master Plan (CPDMP) to meet the growing electricity demand load and power
system in the Northeast area of Hanoi city.
The activities of subproject include construction of a new 220kV substation and
construction of 1,453m of 22kV power line supplying auxiliary power for the substation.
These activities may cause negative impacts on the local environment and communities
during pre-construction, construction, and operation phases.
To ensure the potential negative impacts are identified and mitigated during the
subproject implementation and in compliance with the policy on environmental assessment of
the World Bank (OP/BP 4.01), an Environmental Management Plan (EMP) of the subproject
has been prepared in accordance with the guidelines provided in the Environmental and
Social Management Framework (ESMF) of the TEP project. The EMP includes the following
contents: an introduction, the main legal framework, the subproject description, the
environmental background, potential positive and negative impacts, proposed mitigation
measures, and implementation arrangements. It also includes an Environmental Codes of
Practice (ECOP) prepared for the subproject. The EMP will be incorporated into the bidding
documents and construction contracts, as well as a scope for environment quality monitoring.
A Resettlement Plan (RP) has also been prepared for the subproject and presented separately.
The Government’s regulation on EA requires submission of an Environmental Impact
Assessment (EIA) Report for the subproject. The EIA report has been prepared and submitted
to Hanoi Department of Natural Resources for appraisal and approval.
2. POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS
2.1. Government Regulations:
The following national laws and regulations are applied for subproject:
- Law on Protection of the Environment No. 52/2005/QH11 passed by the National
Assembly on November, 29th
, 2005 regulates the obligations of individuals,
organizations in protecting environment.
- Law on Water Resource No. 17/2012/QH13 enacted June 21, 2012.
- Land Law No. 13/2003/QH11 dated November 26, 2003, and the new Land Law No.
45\2013\QH13 dated November 29, 2013 which will take effect on July 1, 2014.
- Construction Law No. 16/2003/QH11 dated November 26, 2003.
- Labor law No. 35-L/CTN dated 23rd Jun 1994, with some amendment under
Document No. 84/2007/QH11 by the National Assembly.
- The Law of Cultural Heritage No. 28/2001/QH10 promulgated on June 29 2001, with
some amendment in 2009 by the National Assembly (No. 32/2009/QH12).
- Law on Fire Prevention and Fighting No. 27/2001/QH10 dated June 29, 2001.
- Law on electricity No. 28/2004/QH11 dated December 3, 2004.
- Decree of Government No. 80/2006/ND-CP dated 9 August 2006 on guidance for
implementation of Law on Protection of the Environment.
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 2
- Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic
environmental assessment, environmental impact assessment and environment
protection commitment.
- Decree No.106/2005/ND-CP dated August 17th, 2005 on implementation
guidelines for some items stipulated in the Electricity Law on protection of high
voltage electrical networks.
- Decree No. 81/2009/ND-CP dated October 12, 2009 on some corrections and
additions of Decree No.106/2005/ND-CP dated August 17th, 2005 on
implementation guidelines for some items stipulated in the Electricity Law on
protection of high voltage electrical networks.
- Decree No. 117/2009/ND-CP dated December 31, 2009 on sanction of violations in
the field of environmental protection.
- Decree No. 59/2007/ND-CP dated April 9, 2008 on solid waste management.
- Decree 174/2007/ND-CP dated November 29, 2007 of GOV on environmental
protection charges for solid wastes.
- Decree No. 98/2010/ND-CP of the Government dated 21 September 2010 on detailing
the implementation of some articles of the Law on Cultural Heritage and the Law
amending and supplementing some articles of Law on cultural heritage.
- Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some
Article of Decree No.106/2005/ND-CP dated 17 August, 2005.
- Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree
No.29/2011/ND-CP dated 18 April, 2011.
- Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to toxic waste
management.
- Circular No. 03/2010/TT-BCT dated January 1, 2010 on some rules on safe protection
of high voltage grids.
- Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on
management and pollution prevention and exposure to PCBs.
- The main applicable National Technical Regulations include: QCVN 05:
2009/BTNMT: National technical regulation on ambient air quality; QCVN
27:2010/BTNMT: National technical regulation on vibration; QCVN
26:2010/BTNMT: National technical regulation on maximum noise limit in public
and residential areas; QCVN 08: 2008/BTNMT - national technical regulation on
surface water quality; QCVN 09: 2008/BTNMT - national technical regulation on
ground water quality; QCVN 01: 2009/BYT- national technical regulation on drinking
water quality; QCVN 02: 2009/BYT- national technical regulation on domestic water
quality; QCVN 06: 2009/BTNMT – air quality –specified maximum allowable
concentrations of certain hazardous substances in ambient air; QCVN 14-
2008/BTNMT: National technical regulation on domestic wastewater; QCVN
40:2011/BTNMT: National technical regulations on industrial wastewater; QCVN
03:2008/BTNMT: National technical regulation on permissible limits of heavy metals
in soils; QCVN 07:2009/BTNMT – National Technical Regulation on Hazardous
Waste Thresholds; QCVN 01:2008/BCT – National technical regulation on safety
principles in working with transmission lines and electrical equipment.
- Other relevant sector technical regulation and standards.
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 3
2.2. World Bank Safeguard Policies
An environmental and social screening of the subproject was undertaken in line with
the OP 4.01 and it showed that the World Bank’s policies on Environmental Assessment
(OP/BP 4.01), and Involuntary Resettlement (OP/BP 4.12) will be triggered for the
subproject. The screening has also resulted in categorizing the subproject as a Category B
project. In addition, the Bank’s requirements on public consultation and information
disclosure will need to be followed.
Environmental Assessment (OP/BP 4.01):
Environmental Assessment (EA) is an umbrella policy for the Bank’s safeguard
policies. The overarching objective is to ensure that Bank-financed projects are
environmentally sound and sustainable, and that decision-making is improved through
appropriate analysis of actions and of their likely environmental impacts. The EA process is
intended to identify, avoid and mitigate potential impacts of Bank operations. EA takes into
account the natural environment (air, water, and land); human health and safety; social
aspects (involuntary resettlement, indigenous peoples, and physical cultural resources); and
transboundary and global environmental aspects. EA considers natural and social aspects in
an integrated way.
This subproject triggers OP 4.01 because it involves the construction and operation of
a high-voltage substation and connecting overhead transmission lines, requiring the
identification, mitigation and monitoring of potential adverse environmental and social
impacts. As required by OP 4.01, the subproject prepared an EIA and an EMP that meet the
Government’s and the World Bank’s safeguards requirements. By the TEP appraisal, the
subproject draft EIA and EMP were disclosed locally at the project site and the Bank’s
InfoShop in Washington DC on January 24, 2014 as required by OP 4.01 and the Bank’s
policy on access to information. The final EIA and EMP were disclosed locally at the
subproject sites, at the InforShop, and the Vietnam Development Information Center on April
18, 2014.
Involuntary Resettlement (OP/BP 4.12)
The Involuntary Resettlement policy seeks to prevent severe long-term hardship,
impoverishment, and environmental damage to the affected peoples during involuntary
resettlement. OP 4.12 applies whether or not affected persons must move to another location.
The Bank describes all these processes and outcomes as “involuntary resettlement,” or simply
resettlement, even when people are not forced to move. Resettlement is involuntary when the
government has the right to expropriate land or other assets and when affected people do not
have the option to retain the livelihood situation that they have.
This policy is triggered because the subproject it would have impacts involving the
temporary and permanent involuntary taking of land and the loss of structures and assets
associated with the land for the construction of the substation and the associated connecting
line. By appraisal, the subproject has prepared and disclose the raft RP locally at the project
site and the Bank’s InfoShop in Washington DC on January 24, 2014. The RP includes the
measures to ensure that displaced people are: (i) informed about the options regarding
resettlement; (ii) consulted and offered alternative resettlement choices; and (iii) provided
with effective compensation and livelihood restoration. The final RP was disclosed locally at
the subproject sites, at the InforShop, and the Vietnam Development Information Center on
April 18, 2014.
World Bank Group Environmental, Health, and Safety Guidelines
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 4
World Bank-financed projects should also take into account the World Bank Group
Environmental, Health, and Safety Guidelines1 (known as the "EHS Guidelines"). The EHS
Guidelines are technical reference documents with general and industry-specific examples of
Good International Industry Practice.
The EHS Guidelines contain the performance levels and measures that are normally
acceptable to the World Bank Group and are generally considered to be achievable in new
facilities at reasonable costs by existing technology. The environmental assessment process
may recommend alternative (higher or lower) levels or measures, which, if acceptable to the
World Bank, become project- or site-specific requirements.
This subproject should conform the Environmental, Health, and Safety Guidelines for
Electric Power Transmission and Distribution and the General EHS Guidelines.
3. SUBPROJECT DESCRIPTION
3.1. Objectives of the Subproject
The objectives of the proposed subproject are to: i) meet the load growing electricity
demand of Hanoi city power system especially load of the Northeast of Hanoi city; ii) create
power links between Northeast of Hanoi city and neighboring provinces, distributing power
capacity, avoiding overloading of the transformers at the station in the area, thereby ensuring
safety and reliable operation of power network in Hanoi city; iii) reduce power loss in entire
power network, enhancing effectiveness of electricity generation of EVN.
3.2. Scope of the Subproject
Dong Anh 220kV Substation shall be built with capacity of 2 x 250MVA and space
land for installation of additional transformer No.3 at the substation. In the first time, install
01 transformer AT1 -250MVA put into operation in 2014. The second transformer shall be
expected to be installed in the period of 2016-2020. The transformer of AT3 shall be installed
after 2030.
Dong Anh 220kV substation shall be built suitably with following period size and
taking into account the link with 500kV switchgear of the next stage. The entire area of the
220kV Dong Anh subproject is approximately 49,819.38m2.
The construction activities include: i) construction and installation for outdoor civil
work (transformer foundation, tower and conductor brace, cable trench system, supporting
pole and equipment foundation etc.; ii) function house service for management and operation
(bay housing and control housing 220kV and 110kV, pumping station for fire-fighting) 22kV
connectionline; and iii) construction of 30 m of access road to the substation.
3.3. Location of Subproject
The substation:
Dong Anh 220kV substation construction in this stage is proposed to be constructed and
in consideration with coupling with the 500kV switchyard in later stage. An area of Dong
Anh 220kV substation is 49,819.38 m2, (land occupied area of 500kV switchyard in later
stage is 29,762.32 m2) in paddy field, of Bieu Khe village, Thuy Lam commune and Ha
Phong village, Lien Ha commune, Dong Anh district, Hanoi city. The substation borders the
residential area of Huong Tram village – Thuy Lam commune to the North; the communal
road of Xuan Non - Thuy Lam communes to the East; the rice paddy to the South, further as
1 The EHS Guidelines can be consulted at www.ifc.org/ifcext/enviro.nsf/Content/EnvironmentalGuidelines.
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 5
residential area of Ha Phong village in Lien Ha commune, and the Dong Anh – Soc Son
existing 110kV connection line to the West.
The subproject site was approved by Hanoi city People’s Committee via Document No.
3431/UBND-CT dated 11/05/2011 and by Hanoi Architecture - Planning Department via
document No. 4130/QHKT-HTKT dated 14/12/2010.
Total acquired land for the substation is: 49,819.38 m2
Substation ground: Substation ground will be designed to ensure that ground level will
be higher than flood level.
Existing ground level is: 5.1m.
Maximum historic flood level in 2008 in substation area is: 5.54m
An average level of the ground after leveling is: 6.8m
Substation area near the irrigation channel system so drainage is very good.
The subproject location is illustrated in the map below:
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No.1 8
Figure 1: The Dong Anh 500/220kV subproject location
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 9
Number of project affected
households 112 households (440 people)
Total area land required Temporary = 0 m2 Permanent = 49,819.38 m
2
Agricultural land required Temporary = 0 m2 Permanent = 49,819.38m
2
Residential land required Temporary = 0 m2 Permanent = 0 m
2
Industrial land required Temporary = 0 m2 Permanent = 0 m
2
Other land required (Forestry
land and hill land)
Temporary = 0 m2 Permanent = 0 m
2
3.4. Subproject Main Work Volume
Table 3.1. Main construction quantity of the subproject
No. Project components Unit Qty Notes
I Civil works
1 Ground leveling
Vegetation soil excavation m3 15,942.1
Embanking sand to substation foundation m3 113,218.7
Embanking soil to substation foundation m3 8,079.8
2 Foundation excavation, embankment
- Soil excavation m3 24,755.4
- Soil embankment m3 14,574.4
3 Asphalted concrete road m2 7,062.6
4 Concrete work
- Local placed concrete m3 5,103.5
- Precast concrete m3 161.9
5 Steel works
- Steel for concrete ton 342.9
- Local galvanized steel ton 0.4
- Electric welded steel ton 31.2
6 Construction, paving
- Construct brick wall m3 921.6
- Coating wall, floor m2 14,036.9
- Paving m2 2,067,8
(Source: Adjusted FS of 220kV Dong Anh substation, PECC1, 12/2013)
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 10
Table 3.2. List of primary construction material
No. Project components Unit Qty Notes
1 Cement kg 1,819,669.7 Loss calculated
2 Coarse yellow sand m3 3,120.7 -
3 Aggregate -
Aggregate 1x2 m3 2,972.3 -
Aggregate 2x4 m3 1,783.8 -
4 Rounded steel < 18 kg 184,131.0 -
5 Shaped steel kg 17,721.5 -
6 Timber formwork m3 158.6 -
7 Brick piece 510,490.6 - Source: Adjusted FS of 220kV Dong Anh substation,12/2013
3.5. Main Activities Before and During Construction
3.5.1. Main Activities Before and During Construction
Activities before construction: - Acquiring land for tower foundation construction, conducting compensation and
allowances for land damages and assets on land for site clearance.
- Constructing auxiliary facilities (worker camps, stockpiles, material storage yards).
- Mobilization of workers.
- Temporary land acquisition partly along roadside for storing material and
equipment.
- Set-up of domestic water supply for the domestic and construction needs
Activities during construction:
- Construction of substation:
+ Foundation excavation.
+ Transportation of material and equipment to the site.
+ Set-up of pillars and substation equipment.
- Construction of transmission line:
+ Foundation excavation.
+ Transportation of material to the site.
+ Set-up of poles – installation of line components.
- Main materials and equipment to be used:
+ Cement, sand, stone, iron, pole, porcelain, mixing station, cranes, etc: bought
in the locality, transported to the subproject site by road.
3.5.2. Transportation
Material and equipment supply
Material and equipment supply will be determined in detail in later phase, depending on
the state budget disbursement and the subproject bidding method. Two sources are expected:
- Material and equipment supply by the subproject owner.
- Material and equipment supply by the contractor.
Long distance transportation
For material and equipment supplied by the project owner:
+ Long distance transportation of such material and equipment will be undertaken
using specialized trucks. Such trucks will be selected in accordance with the requirements
provided in the contract.
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 11
+ Long distance transportation from the subproject owner warehouse to the site will
be undertaken using 5-7.5 ton trucks and loading and unloading will be done using 5-ton
cranes.
For materials and equipment supplied by the contractor:
+ Electric poles will be transported using Kawaz trucks, using 5-ton cranes for
loading and unloading.
+ Supporting frames and accessories will be transported using 5-ton trucks with
manual loading and unloading.
+ Cement and steel will be transported using 5-12 ton trucks with manual loading and
unloading.
+ Stone and sand will be transported using 5-12 ton dump trucks.
Intermediate transportation
- Materials and equipment stored at the site such as cables, insulators, accessories,
breakers, capacitors, power meters, meter boxes and cement will be transported to the
construction sites using non-motorized vehicles and manual handling.
Manual handling
All materials and equipment will be transported to the construction site manually. The
distance will be determined case by case.
3.5.3. Emplyoment and Workers Camps
Temporary warehouse, camp used for construction works are planned to be built in an
unused of substation ground (reserved area, road etc.).
Area of temporary camps is taken according to number of worker working in
construction site. These temporary camps include: camp for accommodation, camp for
administration, camp for public activities…. The labor demand is determined by the volume
of work, construction method and the current labor norms. In the construction phase is
expected to be apporoximately 150 people participating in construction.
3.6. Subproject Implementation Schedule and Total Investment
3.6.1 Subproject Implementation Schedule
Based on the requirements of power supply and capacity of the subproject owner, the
subproject timeline is scheduled as follows:
No. Implementation schedule Time
1 Preparation of Technical Design and professional
reports Dec.2013
2 Preparation of Bidding Document 1st Quarter 2014
3 Preparation of Construction Drawing for part not related
to equipment 2nd Quarter 2014
4 Project commencement 3rd quarter 2014
5 Preparation of construction Drawing part related to
equipment 4th Quarter 2014
6 Connection, operation 2nd Quarter 2015
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 12
3.6.2. Total Investment
Total investment breakdown is indicated in the table below:
- Cost of civil work 141,939,873,000
Cost for equipment 143,416,798,000
- Cost for compensation, clearance& resettlement 36,369,507,000
Cost for project management 3,718,914,000
Cost for Engineering, Investment 14,186,706,000
Others 25,540,411,000
Ccontingencies 93,986,334,000
Total investment: 459,158,544,000
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 13
4. BASELINE DATA
4.1. Geographical Location and Population
The 220kV substation subproject will be located on the paddy rice land area
belonging to the communes of Thuy Lam and Lien Ha, Dong Anh district, Hanoi city. Dong
Anh district is the gateway to the west of Hanoi with a total natural land area of 18,230 ha,
divided into 23 administrative communes and 1 town including 156 villages and 62 wards,
and with a population of about 331,000 people.
Dong Anh district has favorable natural conditions for economic and social
development, and significant transportation advantages facilitating good and trade exchange
between Hanoi and the north eastern provinces. The district administratively borders Soc Son
district to the north; Bac Ninh province and Gia Lam district to the East; Hong River to the
south; and Vinh Phuc province on the west.
4.2. Topography and Geology
Topography
As mentioned above 220kV Dong Anh is proposed to be located on paddy field so
geomorphologic terrain on the region is rather flat, it belongs to accumulation plain terrain
type. Topographical grade: Topography of III grade.
Geology
Geology in the region comprises of soil layer: Clay, blended clay, originated from
quaternary formation.
Physo-geological phenomena
Earthquakes
According to earthquake zoning map in Vietnam created by the Geo-physics Institute
under National Technology and Natural Science in 1995, it is found that in the proposed site
for substation, the earthquake up to grade 7 may occur.
Substation is located on river/marine sedimentation terrain, engineering geological
condition is rather complicated. The phenomena can occur, such as sliding to foundation
wall, swampy in shallow field. Suitable solution shall be applied to foundation to ensure
long-term stability.
4.3. Hydro- Meteorological Characteristics
Meteorology
Dong Anh 220kV Substation is located entirely in an area affected by climate and
hydrological regime of Hong and Ca Lo river basin, which basically belongs to the tropical
climate region with cold winter and hot humid summer heavy rain.
The average wind speed in the area is about 2.1m/s with the prevailing west,
southeast, and east directions from April to September and north and northwest directions
from October to March.
The yearly average temperature is 23.6oC. Maximum temperature is up to 42.8
oC, and
often occurs in May and lowest temperature is 2.7oC, and often occurs in January.
The yearly average humidity is about 82%, with the highest level of 100%, and the
lowest possible level of below 16%.
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 14
The annual average rainfall in the region is relatively high reaching 1611 mm. The
rainy season begins in May and ends in October. The average number of rainy days in a year
are about 152.1 days. The number of average thunderstorms per year at the substation site is
58.6 days.
In order to determine the lighting region partition in the area of the 22kV transmission
line supplying electricity to the station, using the lightning observation data of Lang station.
thunderstorms could occur any day, month in year but mostly in the summer especially in the
afternoon from 13h to evening, maximum thunderstorm month is from May to September
coincide with high rainfall; time occur thunderstorm is 1 – 2h, having thunder.
From November to March is period of monsoon activity, there is little thus
thunderstorm in the period, about 2 – 3 days per month.
Hydrology:
The flow regime of the Red River system is divided into two distinct seasons, dry
season and flood season. The dry season lasts from November to May next year. The total
volume of water in the dry season accounts for 20 – 30% of the annual flow. The driest time
occurs in January, February, and March with a total water volume of about 3.6 – 5.8% of the
annual flow. The flood season starts from June to October. The total water volume in flood
season accounts for 70 – 80%. August is the month with the largest flow accounting for 19 –
23% of the total annual flow.
The river and stream water levels seasonally affect the substation site, resulting in dry
rice fields during the dry season. In the flood season (rainy season), the infield rain and heavy
flood in the rivers cause flooding in the fields, especially in the July, August, and September.
A historical rain in August 1971 in the Red River area and a heavy rain happened in October
– November 2008 caused flooding in many parts in Ha Noi. However, Dong Anh 500kV
substation and the connecting line will be constructed on elevated land sites of Lien Ha and
Thuy Lam communes, thus would only affected by flooding by rain. The flooding level is
from 0.3 – 0.7m and lasts for a few days.
4.4. Land use
Dong Anh district has the natural land area of 18,230 ha, including agricultural land of
10,015 ha, making up 54.76%; the remainder is of specialized land, urban, unused and
forestry land.
Distribution of land use in the Dong Anh district
No. Land type Area (ha) Land rate (%)
1 Agricultural land 10,015 54.79
1.1 Annual crop land 9,366 0.51
1.2 Perennial crop land 153 0.027
1.3 Aquaculture land 496 9.7
2 Specialized land 3,744.15 20.72
3 Residential land 2,049 11.34
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 15
4 Unused land 2,417 13.15
5 Forestry land 5,17 0.00028
Total 18,230.32
(Source: Statistic Yearbook of Dong Anh district - http://www.donganh.hanoi.gov.vn/)
4.5. Environmental baseline data
Quality of air, noise and vibration
Air quality in the district is very different areas. However, the project is located in
arable agricultural land, population density and traffic are not high. Overall, air quality in the
project region have not contaminated, thus the health of people living the region is insured,
all of criterias (CO, SO2, CO, noise, and vibration) are in the allowable limit of National
Technical Standard.
Water quality
Surface water sources in the region is diversity on population level. Water quality is
quite good in the Red rivers but it is polluted in main river Nhue river, Kim Nguu river…
which is playing the role of the region sewerage. In general, water and underground quality in
the project is quite good, through evaluating the analysis result of water sample in and
adjacent the project and compared with the national standards found that most the criteria are
located in allowable limit, only Coliforms and Fe are higher than allowable standard.
Therefore, to meet domestic use purposes, underground water should be treated to reject
metal before using in domestic purposes.
Soil quality
Most of the heavy metals in soil at the survey area have lower value and within the
allowable limits. Soil in the project area is agricultural land to plant rice, this proved that soil
quality at the project is quite good, not polluted by heavy metal.
Location of the subproject is in an open area, air is very clean. There are no industrial,
handicraft activities in the area. There is no observed pollution in term of water, air and soil.
People are living in surrounding area of the subproject site. Main land use pattern in the
site is rice field. No forest is presented in the area. There are no wild animals in the
subproject area, except for such species as small frog, mouse, small snakes and intersects.
4.6. Socio-economic status of the project area
Dong Anh district has an advanced economic growth rate, which has 17.4% for many
years. Commercial and service activities are increasingly developing towards a modern
civilized society. Many new areas are formed such as Thang Long industrial and Nguyen Khe
industrial zones that have contributed to the creation of nearly 50.000 jobs for local labors.
The agricultural sector continues to be a strong investment area and interest of the
district, with high level of total investment. Restructuring plants and animals having high
economic value has been a focus. The poverty rate reduces by 2%.
The district focuses on the development of culture, especially social goals of
education. In recent years, the district maintains the right scale of education, quality of key
and comprehensive education of the district are maintained, striving to maintain universal
TEP - Dong Anh 220 kV Substation Environment Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 16
primary education, secondary and high schools (reached 90-95%), 100% of teachers at all
levels reached standards.
Public health, family population and children are of attention of the authority,
especially on building national standard communal health with 100% of communes having
medical doctors.
4.7. Protected areas, natural reserves, sensitive areas, cultural property, historical
monument, temple and pagoda in the project area.
The project is located in an area of agricultural land. There are no any natural reserve
area, sensitive area, cultural property, historical monument, temple and pagoda in the project
area. The district has no natural reserve areas, national parks. In the the Thuy Lam
commune, has “Sai” temple is 5km far from the subproject.
5. POTENTIAL IMPACTS
The subproject would contribute to meeting the demand load and power safety in Hanoi
city and thereby bring about significant socioeconomic benefit. Apart from such benefits, the
subproject may also result in environmental and socioeconomic impacts which are adverse to
the local conditions.
The environmental screening of the subproject indincates that it is eligible for financing
considering that the subproject would not involve possible high risk and would not create
potential adverse impacts on (a) critical natural habitats and/or protected area including
proposed protected areas; (b) loss or damage to cultural property, including sites having
archeological (prehistoric), paleontological, historical, religious, cultural and unique natural
values, graves and graveyards; (c) water regime, particularly water flow and water quality;
and (d) local traffic.
The implementation of the subproject would mainly cause land acquisition, increased
dust generation, air pollution, domestic waste, and health and safety issues due to
construction activites and electrical magnetic field. However, these impacts are not
significant, temporary, localized impacts with available mitigation measures. Only OP 4.01
and OP 4.12 are triggered for this subproject.
The potential negative impacts of the subproject are identified in table 5.1 and could be
minimized by applying the proposed mitigation measures developed for the subproject which
is described in Table 6.1 of Section 6.
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 17
Table 5.1. Impact of the subproject
Impact/issues Significance
of impact
Duration of
impact Impact description
- THE PRE-CONSTRUCTION AND CONSTRUCTION PHASES
Effect of land
acquisition
Medium Short-term
and
Long-term
- The substation and connection line would be located in the rice fields of 110 households
of Thuy Lam commune and Lien Ha commune, Dong Anh district, Hanoi city. Of these,
16 affected households belong to Thuy Lam commune. The number of affected household
in Lien Ha commune are expected about 94 households (according to the Resettlement
Plan report, PECC1, 2013), households would lose their land permanently.
- 47,953.71m2
of agricultural land would be permanently acquired. This land is located in
communes of Thuy Lam and Lien Ha.
- No household would need to be relocated because of the subprojects.
- Land acquisition would have adverse impacts on income and livelihood of the affected
households. Impacts of land acquisition are described in detail in the subproject
Resettlement Plan, PECC1, 2013).
- In addition, 120 m2 of inter-field concrete irrigation ditch, 1120 m
2 of inner-communal
concrete road and 625.67 m2 of inner-commune earth road land are also permanently
affected. This would pose some difficulties for agricultural activities at the rice field and
traffic in the area.
Temporary and
permanent
acquisition
Medium Short- term
Long-term
Total land acquisition of the subproject is as follows:
Land Unit Permanent
affected
Temporary
affected
1. Substation land
Paddy field m2 47,953.71 0
Inner –field irrigation ditch m2
120 0
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 18
Impact/issues Significance
of impact
Duration of
impact Impact description
land
Inner-field concrete road land m2 1120 0
Inner-commune earth road
land m
2 625.67 0
Total m2 49,819.38 0
Loss of vegetation
due to land
clearance for
Dong Anh
substation
Small Short tem
Long term
- Ground for substation and connection line is used to be rice fields. This area is rice
cultivate land of Bieu Khe and Ha Phong’s village households of Thuy Lam and Lien Ha
communes. Vegetation near the subproject comprises grass and shrubs at the time of
survey (June, 2013) this area has been harvesting.
Erosion or
sediment
generation caused
by earthworks
Medium Short-term - Project areas have flat, not through rivers and streams
- The earthworks of the project include:
+ Digging foundation holes: 15,942.06 m3
soil.
+ Backfilling foundation holes: 113,218.69 m3
sand and 10,262.78 m3 soil. (according
to adjusted FS of the 220kV Dong Anh substation)
- Activities of construction and excavation only happen in a short time at
foundation holes and are prioritized to be done in dry season.
- The project will apply successive construction method. Therefore, risk of soil erosion is at
low level, so there is no risk of erosion, landslides.
Air pollution and
dust generation
Medium Short – term - Exhaust gases such as SOx, NOx, CO from the operating transportation vehicles and
power generators would have potential impacts of degrading air quality in the subproject
area and the health of workers and local communities.
- Dust is generated from soil excavation and substation site leveling work, especially in dry
season. The affected people will be the workers and the inhabitants around the project
area.
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 19
Impact/issues Significance
of impact
Duration of
impact Impact description
- Dust is also generated by means of transport of materials and plants during the
construction of the subproject. The affected people will be road users and local
communities along the route of construction material transportation on the National road
No.3 especially entering road to substation (Lien Ha – Thuy Lam inter-commune road).
- Given the small number of vehicles mobilized for the subproject, short time of
construction, and far location of the Bieu Khe village residential area (about 200m), the
impact of air and dust pollution on workers and communities can be assessed as medium
and can be mitigated.
Noise and
vibration
Small Short-term - Operation of transportation vehicles, site grading and piling machines, and power
generators can cause noise and vibration affecting households along the national No.3
especially along Lien Ha – Thuy Lam inter-commune road and at subproject construction
sites. However, this impact is small because it the related activities would only occur
during the construction phase and can be easily mitigated.
Contamination of
water and soil by
hazardous waste
Medium Short-term - Oil spill from vehicles and construction machines can affect quality of soil and water,
especially in rainy season. This leakage oil can affect surrounding area by run off
rainwater.
- Transformer oil or oil having PCBs might also be leakage to the environment due to
accidents. However, oil having PCBs to be used at substation are prohibited by the
national regulation.
- The operation of the substation will use some chemicals available in such equipment as
battery, insulating oil, grease oil and etc., but in small quantities.
Effects on
environmental
quality by
discharging of
construction
waste and
Medium Short-term
to medium
term
- Discharging of construction waste and domestic waste can make adverse effects to
environment quality.
- Excavation is planned to do in dry season. Excess soil will be reused to fill in the poles’
foundation. Thus there will be no soil, sand left after the subproject implementation.
- During construction stage, construction waste will be collected, sold and discharge
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 20
Impact/issues Significance
of impact
Duration of
impact Impact description
domestic waste appropriately (backfilling). Domestic waste will be collected or treated in on-site
treatment system. However, it is necessary to implement a efficient management plan to
ensure all of wastes are colleted and treated obey the regulation.
Public health and
safety effects
from construction
camps, materials
storehouse and
ground
Medium Short-term
to medium
term
- There are some storehouses and grounds need to be built temporary in order to contain
materials and equipments. Construction camp will be built for workers.
- Construction camp and materials storehouses can affect the health and safety of local
inhabitants and workers by unsafe keeping of construction materials and equipments and
the conflict between workers and local inhabitants especially residents in Thuy Lam and
Lien Ha communes.
- Workers will be from the locality; the construction camp will include rest room and
arranged in substation area; all of construction equipments and materials will be placed in
appropriate places which are fenced around. Therefore, the conflict between workers and
local inhabitant’s and impacts on public health and safety are at low level.
Arising conflicts
between
construction
workers and local
residents.
Small Short-term - Focusing large number workers of construction activities (150 people in maximum) shall
cause a risk in conflict between the worker and the local residents. The subproject
implementation is expected to be completed in short period about 12 months. However,
the contractors will mainly use local workers for jobs suitable and worker will be chosen
from the skilled ones in the region so this impact is minor and be able to minimize.
Local road
degradation due
to construction
activities and
Medium Short-term - The subproject site is near Lien Ha – Thuy lam asphalte commune road route, National
Road No. 3; it is very advantageous in construction materials transportation.
- These roads are well-processed foundation and are covered by thick layer of bitumen. In
addition, level of transportation activities is not high, transporting oversize and overload
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 21
Impact/issues Significance
of impact
Duration of
impact Impact description
materials
transportation
equipments should be followed existing regulation and responsible authorities to ensure
safety for people and existing infrastructure system. Hence, the impact of the local road
degradation is at low level. existing regulation and responsible authorities to ensure safety
for people and existing infrastructure system. However, if not transportation weight is not
well managed, the impact of the local road degradation would be moderate.
OPERATION PHASE
Exposure to
electromagnetic
field (EMF) levels
exceeding the
standard.
Medium Long-term - If not properly designed and constructed the substation and the connection lines would
have adverse impact on worker and community health. Based on the calculation and
existing substation 220kV show that, the EMF level is under standard. The Dong Anh
220kV substation was designed to conform to safety standard. Safety regulation will also
be applied strictly by workers when operating substation.
Interference with
radio, TV or other
communications.
No impact No impact - The location of the project is far away from the radio communication works.
Effects on public
health and safety,
including voltage
hazard
Medium Long – term - In design stage, all safety measurements were considered. However, voltage hazard and
effects on safety of local inhabitants and operation workers can in case of no conform to
safety regulation.
Fire hazard due to
oil leakage
Medium Long – term - Fire hazard can be caused from cooling oil leakage or transformer problems. However,
this effect is minimized since the substation has oil-collected pit and fire safely
equipments.
TEP- Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 22
Impact/issues Significance
of impact
Duration of
impact Impact description
Pollution due to
leakage oil and
hazardous
materials
Medium Long – term - Leakage oil from transformers can affect adversely on environmental quality. In order to
prevent the impact on the environment quality due to leakage oil, oil-collected pit will be
installed. Oil collected pit has concreted cover and prevented from leaking, also be
equipped with an automatic water pump. Oil collected tank is arranged in locations
convenient for the collection of the transformer (V = 90m3) in capacity (equivalent 78tons
of oil) to ensure 100% volume of oil discharge from transformer will be obtained when
there is a problem.
- The project does not use cooling oil that contains PCBs and hazardous materials
Noise from
substation
operation
Small Long – term - The transformer will be manufactured according to regulations with noise level under
70dBA at 30m of distance. It will also be installed complying technical requirements to
reduce the noise to operation. Besides, the project locates in paddy field. Thus, impact of
the noise is insignificant.
Impact due to
waste water and
domestic solid
waste of operation
workers
Small Long – term - In the operation stage, the substation does not discharge any of hazardous wastes.
Domestic waste water from daily activities of operation workers will be treated by a
septic tank before discharging the environment. Domestic solid waste will be collected
and discharged through waste collected system of the local. Therefore, impact on the
environmental due to waste discharge is small.
Problems of grid,
accident at work
during operation
management.
Medium Long – term - In activities of management, operation, repair and maintenance of the subproject,
problems of grid and accident can occur in case workers do not conform to safety and
operation regulations.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 23
6. MITIGATION MEASURES
Table 6.1. Impact mitigation measures for environment
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
Engineering design phase
1.Engineeri
ng design
- Select an optimal alternative to minimize land acquisition, avoid
causing the existing vegetable covers and trees and structures.
- Strictly follow electrical and fire safety requirements of the related
regulations.
Relevant
technical
regulations and
standards
Employer:
EVNNPT
AMB
NPMB
By appraisal
authority
Pre-construction phase
1. Land
acquisition
- Careful site-survey, consultation with the affected local communities
and authorities to choose optimal solutions for the location substation
and auxiliary facilities to minimize land acquisition.
- Compensate for land acquisition and damages strictly in accordance
with the RPF of the TEP project and the Resettlement Plan of the
subproject.
At the land
acquisition
site of Bieu
Khe
village.
- Decree No.
69/2009/ND-
CP.
- Cicular
No.14/2009/TT-
BTNMT
EVNNPT
PMU
Local
authority
Local
authorities
and the
affected
people
- Construction phase
1. Dust
generation
- The Contractor is responsible for compliance with relevant
Vietnamese legislation with respect to ambient air quality.
- The Contractor shall implement dust suppression measures (e.g. water
spray vehicles, covering of material stockpiles, etc.) as required;
- Construction vehicles shall comply with speed limits and haul
distances shall be minimized.
- Material loads shall be suitably covered and secured during
At the
constructio
n site
Along Lien
Ha – Thuy
Lam
transportati
on road
QCVN
05:2009/BTNM
T: National
technical
regulation on
ambient air
quality
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 24
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
transportation to prevent the scattering of soil, sand, materials or dust.
- The Contractor shall be responsible for any clean-up resulting from
the failure by his employees or suppliers to property secure
transported materials.
- Exposed soil and material stockpiles shall be protected against wind
erosion and the location of stockpiles shall take into consideration the
prevailing wind directions and locations of sensitive receptors.
- Dust masks should be used where dust levels are excessive.
route
2. Air
pollution
- All vehicles must comply with Vietnamese regulations controlling
allowable emission limits of exhaust gases.
- Vehicles in Vietnam must undergo a regular emissions check and get
certified named: “Certificate of conformity from inspection of quality,
technical safety and environmental protection” following Decision
No. 35/2005/QD-BGTVT.
- There should be no burning of waste or construction materials or
cleared vegetation on site.
At the
constructio
n site.
Along Lien
Ha – Thuy
Lam
transportati
on road
route.
Nearest
residential
area.
TCVN 6438-
2005: Road
vehicles.
maximum
permitted
emission limits
of exhaust
gages.
QCVN
05:2009/BTNM
T. National
technical
regulation on
ambient air
quality.
Contractor
PMU
Compliance
reported by
CSC
3. Noise and
vibration
- The contractor is responsible for compliance with the relevant
Vietnamese legislation with respect to noise and vibration.
- All vehicles must have appropriate “Certificate of conformity from
inspection of quality, technical safety and environmental protection”
following Decision No. 35/2005/QD-BGTVT; to avoid exceeding
At the
constructio
n site.
Lien Ha –
Thuy Lam
- QCVN
26:2010/BTNM
T: National
technical
regulation on
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 25
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
noise emission from poorly maintained machines.
- Construction will be carried out during daylight hours. If it is
necessary to carry out some works at night or weekends, the affected
local community must be informed sufficiently in advance.
- Avoiding or minimizing transportation though or material processing
near community areas.
road route.
Residential
areas
surrounding
the
subproject
noise
- QCVN
27:2010/BTNM
T: National
technical
regulation on
vibration.
4. Water
pollution
- The Contractor must be responsible for compliance with the relevant
Vietnamese legislation relevant to wastewater discharges into
watercourses.
- Portable or constructed hygienic toilets must be provided on site for
construction workers. Wastewater from toilets as well as kitchens,
showers, sinks, etc. shall not be discharged directly to any water body.
- Wastewater over standards set by relevant Vietnam technical
standards/regulations must be collected in a conservancy tank and
removed from site by licensed waste collectors.
- Using techniques as berming or diversion during construction to limit
the exposure of disturbed sediments to moving water.
- Before construction, all necessary wastewater disposal
permits/licenses and/or wastewater disposal contract have been
obtained.
- At completion of construction works, wastewater collection tanks and
septic tanks shall be safely disposed or effectively sealed off
At the
foundation
constructio
n site.
At worker’s
camp
(location of
receiving
points for
wastewater
discharge).
- QCVN
09:2008/BTNM
T: National
Technical
Standard on
underground
water quality.
- QCVN
14:2008/BTNM
T: National
technical
regulation on
domestic
wastewater
- QCVN
24:2009/BTNM
T: National
technical
regulation on
industrial
wastewater.
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 26
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
5. Drainage
and
sedimentati
on control
- The Contractor shall follow the detailed drainage design included in
the construction plans, intended to prevent storm water from causing
local flooding or scouring slopes and areas of unprotected soil
resulting in heavy sediment loads affecting local watercourses.
- Ensure drainage system is always maintained cleared of mud and
other obstructions.
- Areas of the site not disturbed by construction activities shall be
maintained in their existing conditions.
- Earthworks, cuts, and fill slopes shall be properly maintained, in
accordance with the construction specifications, including measures
such as installation of drains, use of plant cover.
- To avoid sediment-laden runoff that could adversely impact
watercourses, install sediment control structures where needed to slow
or redirect runoff and trap sediment. Sediment control structures could
include windrows of logging slash, rock berms, sediment catchment
basins, straw bales, storm drain inlet protection systems, or brush
fences.
At
foundation
constructio
n site of
substation
and power
line.
At drainage
system site
serve for
the
subproject.
- TCVN
4447:1987:
Earth works-
Codes for
construction
- Decree No.
22/2010/TT-
BXD on
regulation of
construction
safety.
- QCVN
08:2008/BTNM
T: National
technical
regulation on
the quality of
surface water
Contractor
PMU
Compliance
reported by
CSC
6.Managem
ent of
stockpiles,
and
construction
ranges
- All locations to be used for disposal of construction excavation and
stockpiles must be previously identified in the approved construction
specifications. Sensitive sites such as scenic spots, areas of natural
habitat, areas near sensitive receptors, or areas near water should be
avoided.
- An open ditch shall be built around the stockpile site to intercept
wastewater.
- Stockpile topsoil when first opening of the substation and power
towers and use it later to restore the area to near natural conditions.
At disposal
site and
stockpiles
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 27
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
- If landowners are affected by use of their areas for stockpiles, they
must be included in the project resettlement plan.
- All stones and the needed filling materials must be bought at licensed
sources
7. Solid
waste
- Before construction, a solid waste control procedure (storage,
provision of bins, site clean-up schedule, bin clean-out schedule, etc.)
must be prepared by Contractors and it must be carefully followed
during construction activities.
- Before construction, all necessary waste disposal permits or licenses
must be obtained.
- Measures shall be taken to reduce the potential for litter and negligent
behavior with regard to the disposal of all refuse. At all places of
work, the Contractor shall provide litter bins, containers and refuse
collection facilities.
- Solid waste may be temporarily stored on site in a designated area
approved by the Construction Supervision Consultant and relevant
local authorities prior to collection and disposal by a licensed waste
collector for disposal at government-approved sites.
- Waste storage containers shall be covered, tip-proof, weatherproof
and scavenger proof.
- No burning, on-site burying or dumping of solid waste shall occur.
- Recyclable materials such as wooden plates for trench works, steel,
scaffolding material, site holding, packaging material, etc shall be
collected and separated on-site from other waste sources for reuse, for
use as fill, or for sale to reprocessing to companies with legitimate
operating permits.
- If not removed off site, solid waste or construction debris shall be
At
constructio
n site.
- Decree No.
59/2007/ND-CP
on solid waste
management.
- Circular No.
12/2011/TT-
BTNMT on
hazardous waste
management.
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 28
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
disposed of only at sites identified and approved by the Construction
Supervision Consultant and included in the site specific measures.
Under no circumstances shall the contractor dispose of any material in
environmentally sensitive areas, such as in or close to watercourses.
8.Hazardou
s wastes
- Hazardous waste of any kind shall be disposed of at an approved
appropriate landfill site and in accordance with the national legislative
requirements. The Contractor shall obtain needed disposal certificates.
- The removal of asbestos-containing materials or other toxic
substances shall be performed and disposed of by specially trained
and certified workers.
- Used oil and grease shall be removed from site and sold to an
approved used oil recycling company.
- Used oil, lubricants, cleaning materials, etc. from the maintenance of
vehicles and machinery shall be collected in holding tanks and
removed from site by a specialized oil recycling company for disposal
at an approved hazardous waste site.
- Used oil or oil-contaminated materials that could potentially contain
PCBs shall follow procedures provided in the ESMF to avoid any
leakage or affecting workers. The local DONRE must be contacted for
further guidance.
- Relevant agencies shall be promptly informed of any accidental spill
or incident.
- Tender documents will prohibit procurement of equipment containing
PCBs.
At
constructio
n site.
- Decision No.
23/2006/QD-
TNMT with list
of hazardous
substance
- Circular No.
12/2011/TT-
BTNMT on
management of
hazardous
substance
Contractor
PMU
Compliance
reported by
CSC
9.Workforc
e, Camps
- The workforce shall be provided with safe, suitable and comfortable
accommodations and safe portable water. They have to be maintained
in clean and sanitary conditions.
At worker
camp site.
- Decree
No.12/2010/TT-
BXD concering
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 29
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
and Site
Managemen
t
- Site offices, worker camps, mixing stations, and workshops shall be
located NOT within 100m from any water courses, at least 500 meters
of existing residential area.
- Engineers and workers shall register their temporary residence with
the local authority.
- Allocate officer to be the Contractor‘s Workplace Safety and
Environment Officer responsible for environmental and safety issues
including training for workers.
- Septic tank toilets must be provided at all construction camp areas
where there will be concentration of labor.
- First aid boxes shall be provided in each construction camp site.
regulation on
construction
safety.
10.Disruptio
n of
vegetative
cover
- The Contractor shall prepare a Clearance, Vegetation and Restoration
Management Plan for prior approval by the Construction Engineer,
following relevant regulations. The Clearance Plan shall be approved
by Construction Supervision Consultant and followed strictly by
Contractor. Areas to be cleared should be minimized as much as
possible.
- The stripped topsoil shall be stockpiled in areas agreed with the
Construction Supervision Consultant for later use in re-vegetation and
shall be adequately protected.
- The application of chemicals for vegetation clearing is not permitted.
- Prohibit cutting of any tree unless explicitly authorized in the re-
vegetation clearing plan.
At the re-
vegetation
site
- Law on
Environmental
Protection
No.52/205/QH1
1.
Contractor
PMU
Compliance
reported by
CSC
11.Traffic
managemen
t
- Before construction, carry out consultations with local government
and community and with the traffic police.
- Significant increases in number of vehicle trips must be covered in a
construction plan previously approved. Routing, especially of heavy
At
constructio
n site
Along
- Law on traffic
and
transportation
No.23/2008/QH
Contractor
NPMB
Local
authorities
and
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 30
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
vehicles, needs to take into account sensitive sites such as schools,
hospitals, and markets.
- Installation of lighting at night must be done if this is necessary to
ensure safe traffic circulation.
- Place signs around the construction areas to facilitate traffic
movement, provide directions to various components of the works,
and provide safety advice and warning.
- Employing safe traffic control measures, including road signs and flag
persons to warn of dangerous conditions.
- Passageways for pedestrians and vehicles within and outside
construction areas should be segregated and provide for easy, safe,
and appropriate access.
connection
line route
12.
Law on
construction
No.16/2003/QH
11.
Decree No.
22/2010/TT-
BXD on
regulation of
construction
safety.
communities
12.Restorati
on of
affected
areas
- Disposal areas, site facilities, workers’ camps, stockpiles areas,
working platforms and any areas temporarily occupied during
construction of the project works shall be restored using landscaping,
adequate drainage and re-vegetation.
- Start re-vegetation at the earliest opportunity. Appropriate local native
species of vegetation shall be selected for the planting and restoration
of the natural landforms.
- Spoil heaps and excavated slopes shall be re-profiled to stable batters,
and grassed to prevent erosion.
- All affected areas shall be landscaped and any necessary remedial
works shall be undertaken without delay.
- Trees shall be planted at exposed land and on slopes to prevent or
reduce land collapse and keep stability of slopes.
- Soil contaminated with chemicals or hazardous substances shall be
removed and transported and buried in waste disposal areas.
At
temporary
occupied
site.
- Law on
Environment
protection
No.52/2005/QH
11.
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 31
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
- Restore all damaged inter-filed irrigation canals, inter-field roads, and
inter-communal roads caused by the subproject activities to their
original state (site specific measures) or better.
13. Worker
and public
Safety
- Contractor shall comply with all Vietnamese regulations regarding
worker safety.
- Prepare and implement action plan to cope with risk and emergency
and aid service at construction site.
- Training workers on occupational safety regulations.
- Ensure that ear pieces are provided to and used by workers who must
use noisy machines such as piling, mixing, etc., for noise control and
workers protection.
- Install fences, barriers, dangerous warning/prohibition site around the
construction area which showing potential danger to public people
(such as unfinished power pole foundation, high risk electrical shock
areas, etc.).
- The contractor shall provide safety measures as installation of fences,
barriers warning signs, lighting system against traffic accidents as
well as other risk to people and sensitive areas.
At the
constructio
n site
- Decree No.
22/2010/TT-
BXD
concerning
regulation on
construction
safety.
- Instruction
No.02/2008/CT-
BXD on safe
and sanitation
issues in
construction
agencies.
Contractor
PMU
Compliance
reported by
CSC
14.Commun
ication with
local
communitie
s
- Maintain open communications with the local government and
concerned communities; the contractor shall coordinate with local
authorities (leaders of local wards or communes, leader of villages)
for agreed schedules of construction activities at areas nearby
sensitive places or at sensitive times (e.g., religious festival days).
- Disseminate project information to affected parties (for example local
authority, enterprises and affected households, etc) through
community meetings before construction commencement.
- Provide a community relations contact from whom interested parties
At the
constructio
n site
- Decree No.
73/2010/ND-CP
on
administrative
penalization
security and
society issues
Contractor
PMU
Compliance
reported by
CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 32
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
can receive information on site activities, project status and project
implementation results.
- Monitor and address community concerns and information
requirements as the project progresses.
- Respond to telephone inquiries and written correspondence in a timely
and accurate manner.
- Inform local residents about construction and work schedules,
interruption of services, traffic detour routes and material
transportation routes, as appropriate.
- Notification boards shall be erected at all construction sites providing
information about the project, as well as contact information about the
site managers, environmental staff, health and safety staff, telephone
numbers and other contact information so that any affected people can
have the channel to voice their concerns and suggestions.
15.Chance
find
procedures
- If the Contractor discovers archeological sites, historical sites, remains
and objects, including graveyards and/or individual graves during
excavation or construction, the Contractor shall:
- Stop the construction activities in the area of the chance finds.
- Delineate the discovered site or area.
- Secure the site to prevent any damage or loss of removable objects. In
cases of removable antiquities or sensitive remains, a night guard shall
be arranged until the responsible local authorities or the Department
of Culture and Information takes over.
- Immediately notify the Construction Supervision Consultant and the
subproject owner who in turn will notify responsible local or national
authorities in charge of the Cultural Property of Viet Nam.
- Contact the relevant local or national authorities who would be in
At the
constructio
n site.
Along
connection
line
- Law on Cultural
Heritage (2002).
- Decree No
98/2010/ND-CP
dated
21/10/2010 on
guideline to
implement
Cultural
Heritage Law.
Contractor,
supervising
consultant
cooperates to
implement
Cultural
Information
Department
Contractor,
NPMB and
local
Relevant
local
authorities
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 33
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
charge of protecting and preserving the site before deciding on
subsequent appropriate procedures. This would require a preliminary
evaluation of the findings to be performed. The significance and
importance of the findings should be assessed according to the various
criteria relevant to cultural heritage; those include the aesthetic,
historic, scientific or research, social and economic values.
- Ensure decisions on how to handle the finding be taken by the
responsible authorities. This could include changes in the layout (such
as when finding an irremovable remain of cultural or archeological
importance) conservation, preservation, restoration and salvage.
- If the cultural sites and/or relics are of high value and site preservation
is recommended by the professionals and required by the cultural
relics authority, the subproject’s owner will need to make necessary
design changes to accommodate the request and preserve the site.
- Decisions concerning the management of the finding shall be
communicated in writing by relevant authorities.
- Construction works could resume only after permission is granted
from the responsible local authorities concerning safeguard of the
heritage.
- These procedures must be referred to as standard provisions in
construction contracts, when applicable.
Authority
- Operation phase
Exposure of
substation
worker to
EMF and
- Existing national law and technical regulations and standards should
be strictly followed by operation and maintenance staff to ensure safe
limits for EMF are not exceeded.
- Evaluate potential exposure to the public against the reference levels
developed by the International Commission on Non-Ionizing
At the
central
control
room.
At
- Decree No.
106/2005/ND-
CP, dated
August 17th,
2005 by the
Operation
and
Management
unit
NPMB
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 34
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
risk of
electrical
shock
Radiation Protection (ICNIRP) or the IEEE.
- If EMF levels are confirmed or expected to be above the
recommended exposure limits, application of engineering techniques
should be considered to reduce the EMF produced by power lines,
substations, or transformers. Examples of these techniques include: i)
Shielding with specific metal alloys; ii) Burying transmission lines;
and iii) Increasing height of transmission towers.
- Specifically Worker hours will be limited in accordance with WHO:
- EMF Intensity (kV/M) - Admissible exposure time (min)
- Up to 5 - - No limits
- - Up to 180
- - Up to 30
- - Up to 10
- >25 Prohibited
transformer
site.
GOV.
- Decree No.
81/2009/ND-CP
dated October
12th , 2009 by
the GOV.
- QCVN
01:2008/BTC:
National
technical
regulation on
Electric safety.
Fire hazard
due to
accident
- Comply with the national law and regulation on fire prevention and
fight extinguishing.
- Prepare an emergency preparedness plan for fire hazard control.
- Equip the substation with enough number of fire extinguishers.
- Frequently examine equipment to detect and repair fire hazard.
- Train operation staff on fire prevention and fire control.
At
substation
site.
- Law on Fire
Prevention and
Fighting No.
27/2001/QH10
dated June 29,
2001.
Operation
and
Management
unit
NPMB
Pollution
due to oil
spill and oil
leakage
from
- Build an appropriate emergency oil spill tank as required by the
regulation.
- Set up a maintenance program in order to timely detect any risk of oil
spill or oil leakages.
- Train the operation staff for dealing with oil spill and leakages,
At oil
storehouse
site
- Circular
No.12/2011/TT-
BTNMT on
hazardous waste
management.
Operation
and
Management
unit
NPMB
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 35
Environment
al and social
issues
Mitigation measures
Locations
for
mitigation
measures
Applicable
National
Regulations,
Standards
Responsible
party
Verification
required to
determine
effectiveness
of measures
substation especially in emergencies case.
Noise from
substation
operation
- Adopt low noise generating standard electrical equipment in the
bidding and contractual documents.
- Frequently check and maintain equipment, repair damages (If any)
that can increase noise generation.
- Install natural barrier (such as trees) to absorb and minimize noise.
At
transformer
site
- QCVN
26:2010/BTNM
T: National
technical
regulation on
noise
QCVN
27:2010/BTNM
T: National
Technical
regulation on
vibration.
Operation
and
Management
unit
NPMB
Domestic
waste water
and solid
waste
- Installed septic tanks to treat domestic waste water at all working
stations.
- Implement a 3Rs plan for reducing, recycling, and reusing solid
waste.
- Sign a contract with a local environment and sanitation licensed
company to collect solid waste generated at the substation.
At water
discharge
system of
the station.
- QCVN
14:2008/BTNM
T: National
technical
regulation on
domestic
wastewater
- Decree
No.59/2007/ND
-CP on the
management of
solid waste.
Operation
and
Management
unit
NPMB
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 36
7. EMP IMPLEMENTATION ARRANGEMENTS
Proper environmental management during construction requires the involvement of
several stakeholders and agencies, each with different roles and responsibilities including:
NPT, PMB, DONREs (Provincial Department of Natural Resources and Environment) of
Hanoi city, the Contractors, the Construction Supervision Consultant, and local communities.
To ensure effective implementation of the EMP, the following actions will be carried out
during the implementation of the subproject:
a) During the detailed design and tender documentation making
- During the detailed design of technical specifications and preparation of bidding
contract documents for each contract, the technical design consultant will incorporate
into these bidding and contractual documents the parts of the EMP specific to that
contract, as well as the specific measures identified in the EMP.
- In preparing the bidding and contract documents, make an effort to ensure that the
contractors are aware of the safeguard obligation and commit to comply. The
environmental specifications in Annex 1 needs to be included in the bidding and
contractual documents
b) During the course of preconstruction and construction
PMU will assign the Construction Supervising Consultant (CSC) and/or field
engineer to be responsible for supervision of safeguard performance of contractor on a daily
basis. A generic Terms of Reference (TOR) is provided in Appendix 2, CSC and/or field
engineers will carry out, but not limited to, the following tasks:
- Before the commencement of the construction, confirm that all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed.
- Review and approve Site Environmental Management Plan (SEMP) to be prepared by
contractor before the commencement of the construction.
- Closely supervise the implementation of the EMP throughout the construction period.
- Confirm the compliance with the agreed environmental plan and inspect any damages
incurred by the contractor. If necessary, prepare an order to compensate/restore the
construction sites as specified in the contracts. Contractor safeguard performance will
be included in the subproject progress report.
The role and responsibilities of relevant parties in the implementation of EMP are
described in the following table:
Table 7.1. Institutional Arrangement for Subproject’s EMP implementation
Community/
agencies
Responsibilities
Project
Implementing
Agency: NPT
- NPT will be responsible for overseeing the project implementation
including ESMF implementation and environmental performance of the
project.
- The NPMB will be responsible for monitoring the subproject
implementation, including environmental compliance of the project. PMB
will have the final responsibility for ESMF implementation and
environmental performance of the subproject during both the construction
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 37
Community/
agencies
Responsibilities
Project
Implementing
Agency: PMBs
and operational phases.
- The NPMB is responsible for fostering effective coordination and
cooperation between contractor, local authorities, and local communities
during construction phase. PMB will be assisted by the environmental staff,
and CSC/or field engineer.
- Specifically NPMB will: i) closely coordinate with local authorities in the
participation of the community during subproject preparation and
implementation; ii) monitor and supervise EMP implementation including
incorporation of EMP into the detailed technical designs and bidding and
contractual documents; iii) ensure that an environmental management
system is set up and functions properly; iv) be in charge of reporting on
EMP implementation to NPT and the World Bank.
- In order to be effective in the implementation process, PMBs will establish
an Environmental Unit with at least an environmental staff to help with the
environmental aspects of the project.
Environmental Unit
EU (EU) under
NPMB
- The EU is responsible for monitoring the implementation of WB’s
environmental safeguard policies in all stages and process of the subproject.
Specifically, this unit will be responsible for: i) reviewing the subproject
EIAs and EMPs prepared by consultants to ensure that they follow the
project ESMF and meet the government and the Bank requirements; ii)
helping NPMB incorporate EMPs into the detailed technical designs and
civil works bidding and contractual documents; iii) helping PMB
incorporate responsibilities for EMP monitoring and supervision into the
TORs, bidding and contractual documents for CSC; iv) providing relevant
inputs to the consultant selection process; v) reviewing reports submitted by
the CSC; vi) conducting periodic site checks; vii) advising PMB on
solutions to environmental issues of the project; and viii) preparing
environmental performance section on the progress and review reports to be
submitted to NPT, the Bank, and the local authorities if requested.
Construction
Supervision
Consultant (CSC)
and/or Field
Engineer
- The CSC will be responsible for routine supervising and monitoring all
construction activities and for ensuring that Contractors comply with the
requirements of the contracts and the EMP. The CSC shall engage sufficient
number of qualified staff (e.g. Environmental Engineers) with adequate
knowledge on environmental protection and construction project
management to perform the required duties and to supervise the
Contractor’s performance.
- The CSC also assists PMB in reporting and maintaining close coordination
with the local community.
Contractor
- Based on the approved EMP and environmental specifications/requirements
in the bidding and contractual documents, the Contractor is responsible for
establishing a site-specific EMP for each construction site area, submit the
plan to the NPMB and CSC for review and approval before commencement
of construction. In addition, it is required that the Contractor get all
permissions for construction (traffic control and diversion, excavation, labor
safety, etc. before civil works) following current regulations.
- The contractor is required to appoint a competent individual as the
contractor‘s on-site Safety and Environment Officer (SEO) who will be
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 38
Community/
agencies
Responsibilities
responsible for monitoring the contractor‘s compliance with the EMP
requirements and the environmental specifications.
- Take actions to mitigate all potential negative impacts in line with the
objective described in the EMP.
- Actively communicate with local residents and take actions to prevent
disturbance during construction.
- Ensure that all staff and workers understand the procedure and their tasks in
the environmental management program.
- Report to the NPMB on any difficulties and their solutions.
- Report to local authority and NPMB if environmental accidents occur and
coordinate with agencies and keys stakeholders to resolve these issues.
Local community
- Community: According to Vietnamese practice, the community has the right
and responsibility to routinely monitor environmental performance during
construction to ensure that their rights and safety are adequately protected
and that the mitigation measures are effectively implemented by contractors
and the NPMB. In case of unexpected problems, they will report to
CSC/PMB.
Mass organizations
- These organizations could play a role as a bridge between the PPC/DPC,
communities, contractors, and NPMB by assisting in community
monitoring.
- Mobilizing communities participation in the subproject, providing training
to communities.
- Participating in solving environmental problems if any.
Province and District
People’s
Committees
(PPCs/DPCs),
Provincial DONRE
- Oversee implementation of subprojects under recommendations of DONRE
and NPMB to ensure compliance of Government policy and regulations.
- DONRE is responsible for monitoring the compliance with the Government
environmental requirements.
7.1. EMP Implementation Reporting Requirements
The safeguard performance will be included in the subproject and Project progress reports.
NPMB with assistance from the CSC will include safeguard performance at subproject level
to NPMB periodically. At the project level, NPT will prepare safeguard performance report
twice per year for submission to the World Bank describing the Project progress and
compliance with the ESMF and other safeguard requirements.The reporting requirements are
described in Table 7.2 below.
Table 7.2. Reporting Procedures
Report Prepared by Submitted to Frequency of Reporting
1 Contractor to the Employer PMB Once before construction commences
and monthly thereafter
2 Construction Supervision NPMB Weekly and monthly
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 39
consultant (CSC)
4 Community Monitoring NPMB When the community has any
complaint about the subproject
safeguards implementation
5 PMBs NPT Six-monthly
6 NPT WB Six-monthly
NPMB reports on environmental performance/compliance of the subproject should be
included in the progress report submitted to the NPT before each project implementation
support mission and must include sufficient information on: i) preparation and disclosures of
environmental safeguards instruments for subprojects; ii) incorporation of new subproject
EMPs in the bidding and contractual documents; iii) monitoring and supervision of EMP
implementation by the contractor, the construction supervision engineer, and the NPMB; iv)
any challenges in safeguard implementation, solutions, and lessons learned.
8. Monitoring Program
8.1. Objectives
It is essential to design the monitoring program and monitoring frequency
appropriately to be able to demonstrate both the overall performance of the subproject works
as well as the short- term impact due to peak construction activities. More specifically, as the
integral and critical part of the EMP, the environment monitoring program should have the
following objectives:
Determine the actual extent of the impacts.
Control impacts which are generated from construction process and mentioned in the
EMP.
Check and supervise implementation of environmental protection solutions during
construction based on EMP.
Suggest mitigation measures in case of unexpected impacts.
Suggest to the related parties to coordinate with central and local environmental
organizations to solve any pending issues that might arise relating to environmental
protection under the scope of the subproject.
Assess the effect of mitigation measures in pre-construction, construction and operation
stages and recommend for improvement.
The environmental monitoring plan is described in Table 8.1 below.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 40
Table 8.1. Environmental Monitoring Plan
Impact Monitored parameter Monitored point Monitoring
method
Timing/
frequency of
monitoring
Responsibility Verification
Pre-construction and construction Phase
I. Vegetation cover
clearance or cutting
down trees
- Clearance technique
- Disposal of cut-down
trees.
- At substation site
- In a centralized place
for processing.
- Observation - From beginning to the
last moment.
-Contractor
-Construction
supervising consultant
Compliance
report by CSC
I I. Rural roads in
the project region,
especially along
Lien Ha – Thuy
Lam road
- All heavy tonnage
vehicles on the local
roads
- Road surface situation,
damage level and
density of vehicles and
people participating in
traveling activities.
- Along the traffic road
National No.3, and
especially in Lien Ha –
Thuy Lam inter-
commune road route.
- Observation and
consultation with
local residents.
- Weekly basis when
material is transported
to the region.
- During the
construction time.
- Contractor,
-Construction
supervising consultant
Compliance
report by CSC
III. Surface water
quality,
sedimentation and
erosion
- Not excavate while it
is raining
- Water drainage
system, and
construction and
domestic sewage
collection system at
jobsite and rented house
of worker.
- Level of flora
clearance and subproject
of slope stabilization
- Surface water near the
foundation
construction site of
substation and power
line.
- Water drainage are in
the worker’s camping
site, stockpiles..
(location of receiving
points for wastewater
discharge).
Observation -During and after heavy
rain
-Contractor,
-Construction
supervising consultant
Compliance
report by CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 41
Impact Monitored parameter Monitored point Monitoring
method
Timing/
frequency of
monitoring
Responsibility Verification
IV. Dust and air
pollution
- Checking the
efficiency of the
operation permission
and its deadline date of
construction
equipment and
machines.
- Checking the spraying
measure (reducing
dust) at the material
transportation roads
Cover for material
during transportation
process
- Checking woker’s
domestic waste
collection.
- Concentration of air
pollutants: total dust,
SO2, NOx, CO…
- Along transportation
road
- Material gathering
points for construction
of subproject
- Observation
- Survey equipment
- Before material
transportation trucks
start in hot, dry and
windy days
-Contractor,
-Construction
supervising consultant
Compliance
report by CSC
V. Noise - Noise by machinery
- Local resident
response to noise from
the construction
process
- Residental areas
surrounding the
subproject area.
- Consultation with
local residents
- Visual inspection
-During activities that
may result in high noise
level; Complaints by
local residents
-Contractor,
-Construction
supervising consultant
Compliance
report by CSC
VI. Sanitation
situation at the
construction site,
including the
hygiene of
workers’ camps
- Garbage, waste water
at the construction site
and workers’ tents
- If the tents have been
supplied clean water
and had sanitary
latrines.
- At the construction
location of tower
foundation.
- At worker’s camp
Observing - Every week, when
official acceptance of
work
-Contractors
-Construction
monitoring consultant
Compliance
report by CSC
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 42
Impact Monitored parameter Monitored point Monitoring
method
Timing/
frequency of
monitoring
Responsibility Verification
- Collection of solid
wastes at the
construction site and at
the worker’s tent areas.
- Disposal method
VII. Safety of
workers and local
presidents
- Minutes about training
in labors safety for
workers.
- Conditions for living
activities of worker.
- Labor protection
equipment, warning
signs and compliance
with regulation on
labor safety of
workers.
- At the construction
site.
- At the worker’s camp
- Inspection
- Checking the
construction diary
of the contractor
- Every month - Contractors
- Construction
monitoring
consultant
Compliance
report by CSC
Operation Phase
I. Electrical field
and magnetic field
- Electrical field and
magnetic field
- At the transformer
site, central control
room.
- At the local people’s
houses near to
substation.
Electrical field and
magnetic field
measuring
equipment.
- 1 time/6 month.
- When there are some
complaints of local
people
PTC1
III. Danger of
High-voltage
electricity to health
and electric safety
for workers and
- Frequency of TL
inspection and
maintenance.
- Labor safety
equipment providing
- The substation site
Observation 1 time/03 month
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No. 1 43
Impact Monitored parameter Monitored point Monitoring
method
Timing/
frequency of
monitoring
Responsibility Verification
local residents. for worker.
- Safe distance of
substation
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JS COMPANY No 1 48
9. INSTITUTIONAL DEVELOPMENT ACTIVITIES
+ EVN's training: Internal training course on how to monitor EMP and how to report
environmental results as part of quarterly and annual project reports.
+ Training of PTC1: The following training will be provided for the environmental staffs
and some people of local authority.
+ Safety training: Regular training on safety issues related to the distribution network
maintenance;
+Monitoring and reporting of environmental management plan for
stakeholders of the Project’s district or communes:
The training will give guidance to the local stakeholders about the participation of local
peoples during implementation of EMP. The training will also include the methodology
for site observation and monitoring check sheet filling.
Table 9.1. Cost estimation for capacity building in EMP implementation (*)
Type of training
Number
of
students
Duration
of
training
Starting
date/Ending
date (for
each student)
Venue of
training
(Domestic or
Abroad)
Institute or
organization
to provide
training
Cost estimate
(VND)
Environmental
Management
Training
Course of
EVN’s training
05
03 days
Before
subproject
implementation
Training
location is
chosen by
EVN
(in Hanoi
city)
EVN
combines
with
specialized
organization.
05 persons x 03
days x
1,000,000 VND
15,000,000
VND
Seminar of
environmental
management
(training of
PTC1)
05
03 days
Before
subproject
implementation,
after finish
Environmental
Management
Training Course
Training
location is
chosen by
PTC1
(in Hanoi
city or
others).
PTC1
combines
with
specialized
consultant
15,000,000
Training
Course for
Contractor
05 03 days Before
subproject
implementation
Location
will be
selected by
NPT or by
contractor.
Contractor
combines with
NPT and
consultant
15,000,000
Total
45,000,000
(*) Cost for environmental management training is held by EVN for TEP project. The cost
estimated above is used for the 220kV Dong Anh substation.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 51
10. COST ESTIMATION FOR EMP IMPLEMENTATION
Table 11.1. Summary of cost estimation for implementation of EMP
No. Items Implementation cost (VND)
Construction phase Operation phase
1 Mitigation
measures (*)
- The costs is covered in the
contract with construction
contractor.
- Cost in covered in the
operation cost of
Transmission Company No1.
(PTC1)
2 Environmental
monitoring during
construction stage
(conducted by the
CSC) (*)
1person/month x
8,000,000VND/person x 12
month = 96,000,000
3 Supervision cost
for environmental
supervisor of PMU
Included in management cost of
the project of AMB
The cost is covered in
running cost of subproject
operating unit
4 Capacity building
(training cost)
45,000,000
5 Total 141,000,000
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
11. PUBLIC CONSULTATION
11.1. Public consultation
Activity 1: During survey and consultation for agreement of the 220kV Dong Anh
station subproject, the subproject’s engineering consultancy notified local authorities at
levels regarding the subproject (scale, objectives and signification of the subproject).
Activity 2: Surveying, investigating field, establishing environmental impact
assessment and the EMP of the subproject were conducted.
After surveying and investigating, and having enough data on the subproject’s
impacts. The Consultant (on behalf of the Employer) held meeting dated from 15/10/2013
with local authorities of Thuy Lam commune of Dong Anh district, Hanoi city and
06/12/2013 with local authorities of Lien Ha commune of Dong Anh district. The
Consultant presented the following issues:
+ Subproject description: location of the project, and the necessary of the
subproject construction;
+ Potential impacts on environment caused by the subproject;
+ Mitigation measures against negative impacts.
Summarization of attendees’s opinions:
+ Agree with the project investment policy.
+ Agree with potential impact on environment caused by the project and
mitigation measures against negative impacts on the environment and society.
+ Recommendation: the remaining land area of Bieu Khe village field should be
recovered for the project.
(Minutes of the public consultation meeting are enclosed in appendix 2).
Information disclosure
The draft EMP was disclosed at the CPC office of commune of Thuy Lam commune
and Lien Ha commune, Dong Anh district, Hanoi city in Vietnamese version
The Vietnamese and English draft EMP was disclosed at the Vietnam Development
Information Center at No. 63, Ly Thai To St, Hanoi City and the WB’s Info Shop in
Washington DC on January 24, 2014.
The final EMP was disclosed locally at the subproject sites, at the InforShop, and the Vietnam
Development Information Center on April 18, 2014.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
Table 12.1: Summary on pubic environmental consultation meetings
N0. Subproject Location, date and
time consultation
meeting
No. of
Participant
Representative of attended
local authority and HHs
Summary of discussed
issues and concerns
How concerns were
taken into account
or why not
1 220KV Dong Anh
substation
- Office of CPC
Thuy Lam
commune – Dong
Anh district.
- Date October,
2013.
10 person 1. Representatives of CPC
Nguyen Huu Tuu -
Chairman of CPC.
Ngo Thi Bon - Chairman
of Fatherland Front.
2. Representatives of others
3. Representatives of
PECC1 (consultant)
Comment of attended
representatives
- Agree with the project
investment policy.
- Agree with potential
impact on environment
caused by the project and
mitigation measures
against negative impacts
on the environment and
society.
2 - Office of CPC
Lien Ha commune
– Dong Anh
district
- Date December,
2013
10 person 4. Representatives of CPC
Le Xuan Thuy – Deputy
Chairman of CPC.
5. Ngo Van Quyen -
Chairman of Fatherland
Front.
6. Representatives of others
7. Representatives of
PECC1 (consultant)
- Agree with the project
investment policy.
- Agree with potential
impact on environment
caused by the project and
mitigation measures
against negative impacts
on the environment and
society.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
Annex 1: Environmental Specifications for the Contractor
The environmental management requirements in construction of the subproject have been
established and presented clearly in the EMP (indicate the specific section of the EMP here). The
Contractor need to carefully read and fully understand all requirements included in the
contractor’s bid: (Insert the name of the Civil Works Package here) of the subproject.
I. Overview
In order to avoid negative effects into the environment and local community, as well as
minimizing damaging impacts to the environment during the construction and operation stages of
the resettlement sites, Contractor and workers are required to observe the mitigation measures as
mentioned below:
- “Environmental Management Plan for the Project…”.
- The technical specifications, procedures and the most popular practices are presented in
this annex.
II. Overall requirements of Contractor for environmental management
Contractor need, in in line with the requirements of the EMP, to include, but not limited the
following responsibilities:
- Be in compliance with the current national legal regulations on environmental
management.
- Work in scope of requirements in the contract and the conditions in the bidding documents.
- Assign the representative of the construction team to participate in the site inspection
operations by the PMB, CSC or the DONRE as well as implement all corrective actions to
overcome the environmental issues as guidance provided by the Construction Supervision
Consultant (CSC).
- Provide and update information for PMB about any activities, assignments that can
contribute or continue to cause the significant harmful impacts into the environment.
- In case of instruction by the CSC and PMB, the Contractor must stop the construction
activities that causes adverse impacts, also propose and conduct the environmental
remedial actions and implementation other construction methods (if required) to minimize
the negative environmental impacts.
- Establish and maintain an Environmental and Safety Unit, which consists of Construction
team leader or Vice- team leader and Safety and Environmental Officer (SEO) with the
purpose of receiving and dealing with the complaints, objections, argument and displeased
of the local community caused by the construction operation. SEO is responsible to record
all of complaints, resolve methods and results into the complained register. The register
need to keep at the construction office and available for review by the supervision engineer
and PMB.
III. Responsibilities of Contractor in EMP implementation:
The construction Contractor has responsibility in compliance with the technical specifications of
the EMP, (name of the subproject to be inserted here) and national environmental management
regulations, including but not limited the following items:
i) The mitigation measures presented in relevant section of the EMP(indicate the specific
section of the EMP here) and prepare budget for implementing the mitigation measures.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
ii) Based on EMP, Contractor developed a detail Site Environmental Management Plan for
addressing the construction related impacts. The SEMP includes the following
components:
- Management Plan for worker camps.
- Management Plan of the overall construction operation.
- Plan for management and storage of construction materials (including the dangerously
chemicals)
- Solid waste and waste water management plan (including construction and household
waste)
- Plan for management and mitigation of noise and dust.
- Plan for management and mitigation of impacts to vegetation and wild animals.
- Plan for environmental landscape restoration
- Healthy and safety ensuring plan at the construction.
- Erosion and soil aggrandizement controlling plan.
- Safety plan during the construction stage and training for workers about environmental
management and community relations.
- Rules and regulations about living activities of staffs and workers at the construction
sites.
- Emergency Problem Treatment Plan.
- Management and Monitoring Plan for Report Process.
The detail measure of plan need to satisfy the following requirements: to implement the
particular mitigation measures: who implement (people, team, etc), how to implement (labours,
machines, equipment, etc.) and the cost. This plan shall be completed and submitted to the CSC
for review and approval before start of the construction. The Contractor will:
a) ensure that at least one supervisor is available in compliance with EMP before and during
the construction time.
b) ensure that all of the construction activities will be approved in document of the relevant
authorities.
c) ensure that all of staff and workers understand through their process and duties.
d) be in compliance with requirements about the environmental management monitoring
and reporting in EMP and inform to PMB about the difficulties and solutions.
e) Inform to the local authority and PMB in case of environmental problems and co-ordinate
with the relevant institutions and stakeholders for resolving.
IV. Safety and Environmental Officer of Contractor:
Each contractor will nominate a Safety and Environmental Officer (SEO) to work full-time at the
construction site. Requirements for a SEO include an undergraduate degree in Environmental
Major, at least 3 years of working experience in environmental management, training and
monitoring at the infrastructure construction project. Additionally, SEO should have a good
knowledge about Vietnamese Environmental Legal Regulations and has participated to the labor
safety and sanitation training class that organized by Department of Labour- Invalids and Social
Affairs and have the labor safety and sanitation certificate.
SEO have the responsibilities for implementing and managing EMP of Contractor. Tasks of SEO
will include, but not limit the following activities:
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
i) Training and developing environmental awareness for workers of Contractor within 2
weeks after the contractor is mobilized. The training is repeating every six months. The
additional trainings will be implemented under the guidance of Environmental
Supervision Engineer.
ii) Conduct the internal environmental monitoring at the site to check the construction
activity implementation of contractors, equipment and implementation methods to
manage the environmental pollution and evaluate the efficiency of the mitigation
measures into the environmental impacts.
iii) Internal monitoring the implementation of environmental mitigation measures and in
compliance of contractors with the environmental protection measures to prevent and
control pollution; the committed requirements in the contract; guidelines of the
contractor(s) on environmental improvement, environmental awareness and also
proactive measures to prevent pollution.
iv) Conduct an investigation and propose the mitigation measures for the contractor(s) in
case of incompliance/ infringe the EMP; monitoring and implementing the
environmental mitigation measures.
v) Evaluate the success of the EMP implementation to estimate effectively the cost and
adequacy of the implemented mitigation measures.
vi) Survey after receiving the complaint, thence evaluate and select the corrective actions.
vii) Conduct the additional monitoring activities, based on the concrete guidelines of the
monitoring engineer and/ or PMB; and
viii) Contact and implement all activities under the co-ordination or guidance of the
Contractor Leader, Environmental Supervision Engineer, Supervision Engineer, PMB,
representatives of the provincial environmental management offices, local authority
about all of environmental problems if necessary.
ix) Establish the regularly reports for the environmental implementation of the civil works
package.
x) All of the internal monitoring as well as other activities of SEO should be documented
and updated frequently in the environmental implementation monitoring diary of
Contractor. This diary is used for normally checking by the CSC to evaluate the
effectiveness of mitigation and the work of SEO.
V. Monitoring the environmental implementation of Contractor:
The PMB will sign a contract with the Consultant to carry out the task of CSC. The CSC will
apply the environmental and monitoring activities of the package as indicated in Appendix 2.
The environmental monitoring engineer of construction/execution monitoring Consultant is
responsible to monitor daily the implementation of measures, in order to minimize
environmental impact and safety of the Contractor. The construction monitoring Consultant will
carry out the following main tasks:
Before the construction stage, make sure that all of the compensation process for
land, works on land and relocation and/ or recovery/ donation of land as well as the
clearance of landmines and UXO have been completed.
Review and approve the SEMP for implementing the EMP by Contractor before
the construction operation.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
During the construction process, monitoring closely the compliance with
implementing of the environmental and safety mitigation measures.
Confirm the compliance with the EMP of Contractor and check any negative effect
or damage caused by the contractor. If necessary, establish a request statement for
contractor to compensate/ restore the construction site, as provided in the contract.
The implementation of environmental management issues of the Contractor shall
be mentioned in the progress report of the sub-projects.
VI. Compliance Framework:
a) The contractors are not allowed to implement the construction activities, including
preparation of construction within the project scope in advance the detail SEMP for
implementation of the EMP are reviewed and approved by the construction supervision
consultant and environmental official of the Client.
b) The PMB is mandatory to ensure that the Contractor in compliance with the contract
provision including compliance with EMP and the detail implementation plan of EMP. In
case of incompliance with EMP, Client will require the Contractor to bring out the
suitable measures.
c) In order to ensure in compliance with the environmental standards of the sub- project,
PMB is allowed to hire the third party to solve the problems in case the Contractor could
not implement the remedies on time, leading to the negative effects into the environment,
as follow:
- For small infringements (such as minor impact/ damage, temporary and repairable),
PMB or the representative of PMB (the CSC) will notify the Contractor to correct the
problems as required in the EMP within 48 hours after receiving the official report. If
the mistakes are satisfactorily repaired during that time, no more action should be
undertaken. Supervision consultants have the right to extend more 24 hours in the
limited time for recovery, under the conditions that the Contractor has implemented
activities but not completed the prescribed time, due to irresistible conditions that
mentioned in the contract.
- For major violations, it is required about 72 hours for repairing, the PMB through the
CSC will announce the violation and require the Contractor to rectify the problems
within the prescribed time by their budget. If the Contractor fails to complete
corrective work according to the specified time, they will be punished by financial
punishment (cost punishment is calculated by the cost of remedying damage)
- According to the evaluation of the CSC, if the Contractor fails to resolve the
problems in environmental management or the contractor conduct reparing
unsatisfactorily within the specified period of time (48 hours or 72 hours), the
investors have the capacity to arrange for another contractor (third-party) to
implement the suitable measures and deduct money for this task from the contract
with the contractor in the next payment.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
APPENDIX 2
TOR FOR CONSTRUCTION SUPERVISION CONSULTANT
Overview
The Construction Supervision Consultant will be the provider of engineering services
(“Services”) to ensure the effective implementation of the Sub-project EMP.
Scope of Services:
General services as provided by the Construction Supervision Consultant are checking and
inspecting construction activities to ensure that the mitigation measures set forth in the Sub-
project EMP shall be accurately taken and adverse impacts on the environment shall be
mitigated.
On behalf of PMU, the Construction Supervision Consultant shall fulfill the following tasks:
- Execute site inspection on a regular basis;
- Consider the implementation situation of environmental protection measures stated in the
EMP and Contract Documents;
- Consider efficiency of environmental mitigation measures and environmental
implementation of the Project;
- If necessary, take account of acceptability in terms of environmental aspect of construction
method (for temporary and permanent works), relevant design plannings and submittals.
When necessary, the Construction Supervision Consultant shall look for and recommend the
least impact plan on the environment in consultation with the designer, the Contractor and
PMU;
- Appraise the survey results about any nonconformity to the environmental quality and
efficiency of remedial measures; and
- Provide regular feedback audit results to the contractor’s Chief Engineer according to the
ECOP and site-specific mitigation measures;
- Instruct the Contractor to execute the remedial actions within the prescribed schedule and
carry out additional supervision if necessary, in accordance with requirements and sequence
of the Contract in case there are any nonconformities and complaints;
- Instruct the Contractor to implement actions to mitigate impacts and comply with the EMP
procedures as requested in case the nonconformity/inconsistency is identified;
- Instruct the Contractor to stop the actions which cause adverse impacts and/or the
Contractor’s failure to implement requirements of the EMP / carry out remedial actions.
- For the contracts, it will be required to set forth EMP on site (SEMP), the Construction
Supervision Consultant shall consider the last time and make a recommendation via all the
environmental plans at site which are likely to affect the environment. This task includes but
not limits to: dredging areas, borrowed pits and dumping site areas, camping area of workers.
The Construction Supervision Consultant shall consider and approve SEMP as submitted by
the Contractor. If finding that these plans do not comply with the EMP, EIA or RAP, the
Construction Supervision Consultant shall co-ordinate with PMU and the Contractor to
propose a reasonable measures or remediation.
- Settlement of complaints: The complaints about environmental violation such as noise,
dust, traffic safety and etc. from the local people will be received by the Contractor’s site
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
staff. The site superintendent or his deputy of the Contractor and the Construction
Supervision Consultant shall have to settle and achieve the solution for such complaints. The
Construction Supervision Consultant shall be provided with a copy of such complaints and
certify that these complaints are settled by the Contractor in a proper manner, which is
similar to the related matter as identified in the site inspection.
- Certification of monthly payment: The Construction Supervision Consultant shall certify
monthly payments for the related activities on the environment performed by the Contractor.
- Report: The Construction Supervision Consultant shall prepare the following written
reports:
o Report on nonconformities every two weeks
o Report on monthly summaries including issues and main findings from review
and construction activities
o To the end of the Project, the Construction Supervision Consultant shall prepare a
final report which summarizes main findings in its work, a number of violations,
solution and etc. as well as provide consultations and guidance’s on the
implementation form of such tasks in future.
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
Appendix 3.1: Example of report template for monitoring of EMP implementation
(Used for reports by contractor)
Project name:
Project location:
Contractor name:
Initial or monthly report:
Date of report:
No. Impact Mitigation
measure taken Comment
Construction phase
1 Surface water pollution
2 Noise and vibration level
3 Soil erosion
4 Air pollution
5 Impacts on agriculture land due to
temporary land acquisition
6 Local traffic interruptions
7 Existing road damage
8 Solid waste from excavation
9 Remained soil management
10 Environmental impacts by workers
11 Conflict between workers and local
residents
12 Disease spreading between workers
and local residents
13 Health and safety
14 …..
Reported by :
Title :
Address :
Telephone :
TEP-Dong Anh 220kV Substation Environmental Management Plan
POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52
Appendix 3.2: Example of environmental performance monitoring report
(Applying for monthly report of the Construction Supervision Consultancy submitting to the
Subproject Management Board of AMB/PTC1 and SIMC)
Project name:
Project location: Province: District: Commune:
Monthly report (Yes/No): Quarterly Report to EVN
(Yes/No): Quarterly Report to the WB (Yes/No): SIMC report (Yes/No):
Date of report:
No. Parameter
Assessment of
Consultant/
community
complaints
Comments/
Recommendations
During Construction
1 Amount of cut down vegetation in the
subproject site.
2 Noise level around construction sites
and adjacent residential areas.
3
Dust, exhausts released from machines,
machines, and construction activities on
material transportation roads and the
subproject site.
4 Tree cutting and access roads
management and control.
5 Solid waste and site cleaning up after
the construction.
6 Workers' sanitation facilities and
safety management.
7 Increased levels of traffic.
8 Status of application of safety measures.
9 Construction material management.
10 Operational status of the treatment system
and waste collection.
During operation
1 The safety of the electrical system, signs
and accident frequency from the power.
2 Equipment fire fighting and rescue
capabilities.
3 Ability from leak from the oil sumps into
the environment.
4 Noise levels to operation transformers.
5 The operation of the collection system
and the treatment of domestic waste.
Report prepared by: Position:
Position:
TEP-Dong Anh 220kV Substation Environmental Management Plan
APPENDIX 4: DRAWING OF THE PROJECT LOCATION
TEP-Dong Anh 220kV Substation Environmental Management Plan
APPENDIX 5: STATUS IMAGE OF THE PROJECT AREA
The proposed substation and connection line site
Lien Ha – Thuy lam inter-commune road
Vegetation image in the subproject