PRESENTED BY:- RAHUL SINGH (RP14068)
NICMAR, Pune
SUMMER INTERNSHIP AT DMRC CC-18
Project name : Delhi Metro Rail Transport Service, Phase-3.Client: DMRCContractor: FEMC PRATIBHA JVContract Package: Design and construction of tunnel by Shield TBM
from Motibagh to Lajpatnagar.Length of tunnel: 4.687 Km + 4.687 Km = 9.374 Km
Project details:
Company FEMC PRATIBHA JVCLIENT DMRC
LOCATION CC-18, BCP, NEW DELHI
DURATION 02/05/2015 to 01/07/2015
MY ASSIGNMENT 1. Understanding the methodology used for tunneling by using Tunnel Boring Machine (TBM)
2. Time delay analysis for the Down line tunnel.
Assignment 1 Target date : No target date, only for self learning process.
Activities: TBM methodology, Ring building process.
Assignment 2 Target date: 25/06/2015Status : Achieved on timeActivities: Analyzing production reports of last 6 months.
Overview of Internship:
Assignment 1: Construction methodology.
Tunnel Construction: By using Tunnel Boring Machine (TBM) with cut and cover approach. Outer dia = 6.6 mInner dia = 5.8 mLength = 90 m (TBM + Backup )
Front shield: Cutting wheelsMiddle shield: Screw conveyor Tail skin shield : Ring building
Phases in tunneling by TBM:1. Tunneling phase.2. Ring Building phase.
Downline tunnel
Upline tunnel
Cutting wheels rotates and pressed against the tunnel phase with a pressure.
Under this high pressure disc cutters and cutting knives loosen the material on tunnel phase.
Conditioning of soil.Excavated soil is then transported from invert area to a belt
conveyor by a screw conveyer.Tunneling phase is completed.
Tunneling phase:
Complete tunnel ring consist of several segments called lining segments.
Segment info :Inner dia = 5.8 mLength = 1.4 mThickness = 275 mmRing arrangement = 5+1
Ring building phase:
Transported into the tunnel by locomotives.In first section of backup segment lifted individually by transfer
crane.Then segment are picked up and positioned by erector using
remote control.Key segment is installed last.
Ring building process:
The remaining gap between outer side of the segment and the soil is continuously filled with grout.
It is done to provide bed for the tunnel tube and to stabilize it.
Grouting:
Daily ring Production summary:
Objective:1. Make a production summary report for the month of May 2015
of down line tunnel.
2. Perform time delay analysis on the production summary report.
3. Find out the reason and solution for the delay in the project.
Assignment 2: Time delay and production summary reports
Production report daily basis (24 hours a day) :
Weekly analysis of all activities and time taken by them:
Delays summary:
MAJOR ACTIVITY WEEKLY TIME TAKEN
Excavation 33.4%Ring building 19.2 %
Delays 38.1 %
Weekly Summary :MAJOR ACTIVITY WEEKLY TIME
TAKENExcavation 4.1 %
Ring building 13.9 %
Delays 16.5 %
Machine B/D 64 %
MAJOR ACTIVITY WEEKLY TIME TAKEN
Excavation 22.3 %
Ring Building 11.1 %
Delays 28 %
Machine B/D 21.6 %
MAJOR ACTIVITY WEEKLY TIME TAKEN
Excavation 29.1 %
Ring building 14.4 %
Delays 30.3 %
Machine B/D 21.5 %
Delay reason: Major delay is due to supply delays. And waiting for skip activity is the major reason for delays.
Solution: Tunnel team should try to increase the rate of skips, so that saved time could be used for the major activity like excavation and ring building.
Advantage: This model will help the organization to identify that which activity is taking how much time and according to that they can manage them.
Conclusion of assignment 2: