STF EP facility at KEK. Presentation for ILC EC 4 September 2008 Takayuki SAEKI. Contents. EP Facilities for ILC R&D at KEK (Nomura and STF/KEK) Current status of EP facilities at STF/KEK EP facility update plan at STF/KEK for 2008 Current status of EP facilities at Nomura - PowerPoint PPT Presentation

Citation preview

Page 1: STF EP facility at KEK

STF EP facility at KEK

Presentation for ILC EC4 September 2008

Takayuki SAEKI

Page 2: STF EP facility at KEK

Contents

• EP Facilities for ILC R&D at KEK (Nomura and STF/KEK)

• Current status of EP facilities at STF/KEK• EP facility update plan at STF/KEK for 2008• Current status of EP facilities at Nomura• EP facility update plan at STF/KEK for 2009• EP schedule for 2008/2009 and STF2/S0• Summary

Page 3: STF EP facility at KEK

EP facilities for ILC R&D

EP beds/HPR/CR….= KEK properties.Building = Nomura properties.Operated by Nomura personnel.

Location is Kanuma: 70 km away from KEK. It takes 2 hours for transportation from Nomura to KEK.

Superconducting Test Facility (STF)Building/EP beds/HPR/CR …. = KEK properties.Operated by KEK personnel.

KEK

MoveNext year

Nomura Plating Co.

Page 4: STF EP facility at KEK

Current status of EP facilities at STF/KEK

2nd floor EP bed

HPR

Clean room

Drafter

Ultra-sonic cleaning

HPR

STF Building EP bed

Water buffer tank

Air compressor

ShutterEntrance

Just started the commissioning of EP facilities

Assembly area

Page 5: STF EP facility at KEK

Current status of EP facilities at STF/KEK

Reservoir tank for EP acid

“Close” when black-out

Inlet of rinse waterGas vent

Schematic of EP system

2nd floor

1st floor

Pump

Page 6: STF EP facility at KEK

Current status of EP facilities at STF/KEK

EP bed 9-cell cavityAutomaticOperation Console

2nd floor

1st floor

Reservoir tank

Page 7: STF EP facility at KEK

Current status of EP facilities at STF/KEK

EP bed Single-cell cavity

Single-cell cavity setup is also possible for fundamental R&D activities.

Page 8: STF EP facility at KEK

Current status of EP facilities at STF/KEK

Ultrasonic cleaning

Ultrasonic Oscillator9-cell cavity

Ultra-Pure Water (UPW)

Hot water bath

Page 9: STF EP facility at KEK

Current status of EP facilities at STF/KEK

CavityUp and down

High Pressure Rinse (HPR) HPR water jet nozzle

Page 10: STF EP facility at KEK

• Post-EP Rinse process is very important to eliminate FE. Now ethanol(DESY) and degreaser(Jlab) rinses are in the standard recipe in these Lab’s. KEK is interested in H2O2 rinse. Post-EP Rinse setup will be installed.

• Pre-EP removes dirty particles after tumbling. Fresh-EP has similar effect to post-EP rinse. Both processes cannot use EP acid in tank. We need additional fresh and waste acid tanks.

• After VT, cavity is disassembled and the indium sealing of flange should be removed completely by Chemical-Polish (CP) for next assembly. Flange-CP setup will be installed for this.

• Robot arm will be installed around EP-bed. One operator can handle 9-cell cavity + jigs easily by this robot arm.

• Cavity-CP (BCP) is necessary, even if it is not essential for KEK standard recipe. Full-automatic cavity-CP (BCP) system cannot be installed due to the lack of budget. Man-operated cavity-CP (BCP) setup is planned to be installed.

EP facility Update Plan at STF/KEK for 2008

Page 11: STF EP facility at KEK

Schematic of Rinse Setup(Ethanol, Degreaser, H2O2)

Cavity

Supply tank

Waste tank

Replacement tank

Pumps

Gas Scrubber

Scrubber ductTransparent Vinyl Tent

Rinse waterWaste tank

Waste tank

EP facility Update Plan at STF/KEK for 2008

Ultra-Pure Water

Page 12: STF EP facility at KEK

Rinse Setup (Ethanol, Degreaser, H2O2) Transparent Vinyl Tent is made.

EP facility Update Plan at STF/KEK for 2008

Page 13: STF EP facility at KEK

Schematic of Pre-EP, Fresh-EP setup

Cavity

Diaphragm pump

Rinse water

Tank for used EP acid

Tank for fresh EP acid

Reservoir tank for EP acid

2nd floor

1st floor

EP facility Update Plan at STF/KEK for 2008

EP-bed

Page 14: STF EP facility at KEK

Schematic of cavity-flange Chemical-Polish (CP) setup

Scrubber duct

Rinse waterWaste tank

Cavity

Waste tank

Gas Scrubber

Transparent Vinyl Tent

Anti-chemicalGlove for work

EP facility Update Plan at STF/KEK for 2008

Ultra-Pure Water

Page 15: STF EP facility at KEK

Robot arm (Easy-handler)

9-cell Cavity + jigs (< 60 kg) can be easily handled around EP bed.

9-cell cavity

EP facility Update Plan at STF/KEK for 2008

Page 16: STF EP facility at KEK

Cavity Chemical-Polish (CP)

Large walk-in type draft-chamber will be used. Man-operated (non-automatic) CP setup is planned, simply due to the lack of budget. CP acid and waste tanks + pump are needed. Still discussing the design.

9-cell cavity

EP facility Update Plan at STF/KEK for 2008

Page 17: STF EP facility at KEK

EP facility Update Plan at STF/KEK for 2008Year 2008        Month Septemb

er October November December

         Rinse hut        Alcohol, Degreaser, H2O2

                Pre-EP, Fresh-EP                 Flange-CP                 Robot arm                 Cavity CP        

Page 18: STF EP facility at KEK

Current status of EP facilities at Nomura

EP bed 9-cell cavity

EP acid reservoir tank: 500 L

Page 19: STF EP facility at KEK

Current status of EP facilities at Nomura

Ultrasonic cleaning High Pressure Rinse (HPR)

Hot water bath

Page 20: STF EP facility at KEK

Move Nomura facilities to STF/KEK

STF Building Existing EP bed (ILC/ERL)

Move Nomura facilities to this area

Existing HPR

Existing Clean RoomNomura EP bed(KEKB/ILC/ERL)

New HPR

Nomura UPW system

Two EP beds are available for ILC R&D activities

EP facility Update Plan for Year 2009

Page 21: STF EP facility at KEK

EP facility Update Plan at STF/KEK for Year 2009

Year 2009                        Month Jan. Feb. MarchApril May June July Aug Sept. Oct. Nov. Dec.                         2nd floor extension                    at STF building   Floor   Ext.                                          Disassembly                at Nomura Plating Co.                                               Installation                    at STF building               Pipin

g Elec.                               Machine tuning                  at STF building                   Tunin

g                             Stop EP process                  at STF building                 Stop      

Move Nomura facilities to STF/KEK

Page 22: STF EP facility at KEK

EP schedule for Year 2008/2009

Year 2008      200

9                     Month Sep

t Oct NovDecJan.Feb.

Mar.

April

May

June JulyAu

gSept.

Oct.

Nov.

Dec.                                 

Base-line 9-cell cavities                EP at STF/KEK         1 2 2 2 2 2 2 1 1 2 2 2                                 FNAL/DESY 9-cell                              EP at STF/KEK 1                                                              ICHIRO 9-cell            EP at STF/KEK                           2 2 2EP at Nomura   2 2 2 2 2 2 2 2 2                                            1-cell and other cavities                                EP at STF/KEK     1  1  1  1  1  1  1  1  1        2  2  2EP at Nomura     1  1  1  1  1  1  1  1  1                                              Stop EP process                              at STF/KEK                            at Nomura                              

Termination

Stop

Not yet scheduled

S1-Global + S0

Page 23: STF EP facility at KEK

• Two EP beds cannot be used in parallel due to safety reason, but during one EP bed is used for EP, the other can be used for the next EP setup. This will raise the efficiency.

• We are assuming the capacity of STF/KEK EP facility = twice EP processes per week utilizing two EP beds.

• The schedule of EP processes for STF2 cavities depends on the fabrication schedule of cavities. We roughly estimate that the EP processes for STF2 cavities might start from the beginning of 2010.

• Rough estimation of STF2 EP schedule: 28 cavities for 2 years and 4 months (28 months), assuming 1 cavity with 3 EP’s and 2 VT’s, utilizing Kyoto-camera checks. This occupies only 38% (3/8) of the capacity of STF/KEK EP facility.

• The rest of the EP capacity at STF/KEK can be used for S0 and fundamental R&D activities for ILC, and other project: KEKB and ERL.

EP schedule for STF2 production and S0

Page 24: STF EP facility at KEK

Summary• EP facilities for ILC R&D at KEK are currently located at STF/KEK and

Nomura Plating Co.• EP bed, Ultrasonic cleaning, HPR have been already installed at

STF/KEK.• Alcohol/degreaser/H2O2 rinse, Pre-EP, Fresh-EP, flange-CP, Robot-

arm, cavity-CP facilities will be installed within 3 months.• EP facility will start regular EP processing from January 2009. • EP facilities at Nomura will be moved to STF building at KEK in the

middle of Year 2009. Then Nomura EP facility will be terminated.• The EP process of 9-cell cavity can be performed twice per week

regularly utilizing two EP beds at STF/KEK. This capacity is enough for STF2 production, S0, and fundamental R&D activities for ILC.