Detail discussion of S1 Global at STF H. Hayano (KEK) GDE meeting@Sendai Mar 3-6, 2008

Detail discussion of S1 Global at STF H. Hayano (KEK) GDE meeting@Sendai Mar 3-6, 2008

Embed Size (px)

Citation preview

Detail discussion of S1 Global at STF

H. Hayano (KEK)

GDE meeting@Sendai Mar 3-6, 2008

Need to be solved for S1 global

1. Cavity package collaboration from FNAL and DESY.

need to start negotiation.

2. Cavity package installation into Cryostat.

installation consideration started.

3. Schedule conflict with STF phase 2 and phase 3. tunnel access construction will conflict. -> postpone it.

4. Cryogenics cooling power is enough? need to check. (upgrade of 2k heat exchanger and collecting

compressor?)5. RF power, distribution, LLRF, cables enough? need to check. Maybe OK.

6. KEK Budget and man power support is enough? need to check. Maybe OK.

108

109

1010

1011

0.01

0.1

1

10

100

1000

104

105

0 5 10 15 20 25 30 35

#1 Cavity 4th Qo#2 Cavity 5th Qo#3 Cavity 2nd Qo#4 Cavity 3rd Qo

#1 Cavity 4th x- ray#2 Cavity 5th x- ray#3 Cavity 2nd x- ray#4 Cavity 3rd x- ray

Qo

x-ray [mSv/h]

Eacc [MV/m]

#1 Cav.

#3 Cav.#2 Cav.

#4 Cav.

TESLA style : Final Performance in Vertical Tests

high Qo > 1010

Eacc,max #1 20.8 MV/m#2 29.4 MV/m#3 20.5 MV/m#4 20.2 MV/m

#2 and #4 Cav.additional EP (20 µm)H2O2 Rinse (1h)Hot Rinse (1h)HPR (16h)

2 TESLA-style cavities (MHI) #5 and #6 are under fabrication with improved EBW, may deliver in April 2008.

9-cell Test ResultsMostly Jlab and Some Cornell

US

Those go to CM2; candidates will be from new production.

TESLA-style #3 #4 #2 #120MV/m 20MV/m 29MV/m 21MV/m

TESLA-style(DESY or US) #2 #5 #6>32MV/m 29MV/m ??MV/m ??MV/m

STF12008.4-10

TESLA DESY1 DESY2 FNAL1 FNAL2 >32MV/m >32MV/m >32MV/m >32MV/m

S1 Global : cavity installation

S1 Global

( or TESLA-style#7?) ( or LL #7? #8?)

Module A Module B

Not yet decided for nextIf we go S1 global for next

1337mm

Make this construction 1 year postpone.We can use tunnel until 2010.3, and little more.

CY2008 2009 2010

STF

FNAL

S1 Global (connected module)

Possible Schedule plans

Y1, Y2 (Y3) tuner, jacket, coupler

DESY X1, X2 (X3) tuner, jacket, coupler

Module A

Module B

#5,#6 process, VT, jacket

(LL #7,#8 process, VT, jacket)

operation

assembly

assembly

connection

STF1 (4 cavity test)

LL #1 test

disassemble

disassemble

6 month operation exp.

(#7, process, VT, jacket)

?

TESLA-style Cavity

LL type Cavity

Cavity Installation into Cryomodule

Module A

Module B

Module A(for TESLA-style)

Module B(for LL cavity)S1 Global

No coupler assey holder

DESY Cavities in STF cryomodule for S1• The design length between input couplers in the STF

cryomodule=1337mm Design lengths of the STF cavities = 1258.6 mm for BL cavity, 1272 mm for LL cavity

Lengths of connection bellows and flanges: 78.4 mm for BL cavity, 65.0 mm for LL cavity

Design length of the DESY cavity = 1293 mm Lengths of three DESY cavities which have been delivered to KEK: 1290, 1290, 1286 Length of connection bellows and flanges in STF cryomodule: 43 mm

• The connection flanges and bellows was designed for installing the DESY cavities into the STF cryostat.

Designed Connection Flanges and Bellows

Two flanges with bellows are tapped.The screwed holes do not penetrate the flanges.

Designed bellow length: 29.1 mmNumber of waves: 6Changeability of length: 2mm

Input coupler flange

Designed for 1290 mm cavity

Expected contribution: cavity package

cavity package: Cavity, Jacket, Tuner, coupler, Mag. Shield, HOM pickups, monitor pickup, coupler installation assembly, motor driver, piezo driver, associated instruments.Assembly participation, operation participation.*Sending them back after experiment.

If it is special motor, piezo.